ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
1 1 <Project - Startup / Initiation> 7,232.28
hrs
233.52 days? Fri
4/1/11
W ed
2/22/12
100%
2
3 1.1 1.0 Initiatation 710 hrs 44.63 days? Fri
4/1/11
Thu
6/2/11
100%
4 1.1.1 1.1 Project Start Up and Administration 29 hrs 5 days? Fri
4/1/11
Thu
4/7/11
100%
5 1.1.1.1 Project Administration 6 hrs 5 days Fri
4/1/11
Thu
4/7/11
100%
6 1.1.1.1.1 Manpower Estimations - PM Efforts 4 hrs 5 days Fri
4/1/11
Thu
4/7/11
100%
7 1.1.1.1.1.1 Weekly Coordination Efforts xxwks (5 hr wk x
project duration)
1 hr 1 wk Fri
4/1/11
Thu
4/7/11
100%
8 1.1.1.1.1.2 Weekly Project Meetings xxwks (1 hr wk x
project duration)
1 hr 1 wk Fri
4/1/11
Thu
4/7/11
100% Resources Identified Periodic Status Meeting Invite Distribut PM[3%]
9 1.1.1.1.1.3 Weekly Status Reporting xx wks (1 hr wk x
project duration)
1 hr 1 wk Fri
4/1/11
Thu
4/7/11
100% Copy of Weekly Template in Sharepoint
as of Day 1
PM[3%]
10 1.1.1.1.1.4 Plan / Issues Log / Risk Log Updates (1 hr wk
x project duration)
1 hr 1 wk Fri
4/1/11
Thu
4/7/11
100% Copy of Log Templates in Sharepoint PM[3%]
11 1.1.1.1.2 Manpower Estimations - All other Resources 2 hrs 5 days Fri
4/1/11
Thu
4/7/11
100%
12 1.1.1.1.2.1 Weekly Project Efforts xxwks (25-50% hr week
x segment duration)
2 hrs 1 wk Fri
4/1/11
Thu
4/7/11
100% Est. Resources necessary, Est. segment
durations
Est. work effort across all GOI Teams
working project
PM[5%]
13 1.1.1.2 W ork in-take 10 hrs 1.88 days Fri
4/1/11
Mon
4/4/11
100%
14 1.1.1.2.1 Prepare TCO(0) if not budgeted 4 hrs 0.5 days Fri
4/1/11
Fri
4/1/11
100% High Level Requirements - Project
Brief?
Budget Posted in Sharepoint PM
15 1.1.1.2.2 Assign Project Priority and submit to PMO 1 hr 0.13 days Fri
4/1/11
Fri
4/1/11
14 100% Project Added to Project Register CAE
16 1.1.1.2.3 Complete Project Leveling Matrix and submit to
PMO
1 hr 0.13 days Fri
4/1/11
Fri
4/1/11
15 100% Leveling Matrix Posted in Sharepoint CAE
17 1.1.1.2.4 Request PM Assignment 1 hr 0.13 days Fri
4/1/11
Fri
4/1/11
16 100% PM Assigned in Project Register CAE[96%]
18 1.1.1.2.5 Prepare Project Brief 2 hrs 0.5 days Fri
4/1/11
Mon
4/4/11
17 100% Project Brief Posted in Sharepoint CAE[50%]
19 1.1.1.2.6 Engage Lead Architect 1 hr 0.5 days Mon
4/4/11
Mon
4/4/11
18 100% Lead Architect Assigned in Project
Register
PM[25%]
20 1.1.1.2.7 TCO(0) Approval 0 hrs 0 days Mon
4/4/11
Mon
4/4/11
19 100% Project Brief Completed Customer Signoff/E-mail posted in
Sharepoint
Customer
21 1.1.1.2.8 Project Brief 0 hrs 0 days Mon
4/4/11
Mon
4/4/11
20 100% Project Brief Completed Project Brief associated with Customer
Signoff posted in Sharepoint
CAE
22 1.1.1.3 Project Start-Up 13 hrs 3.51 days? Fri
4/1/11
W ed
4/6/11
100%
PM[3%]
PM[3%]
PM[3%]
PM[5%]
PM
CAE
CAE
CAE[96%]
CAE[50%]
PM[25%]
4/4
4/4
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 1
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
23 1.1.1.3.1 Setup Project Sharepoint 1 hr 0.13 days Mon
4/4/11
Tue
4/5/11
21 100% PM Assignment Sharepoint Site Initialized PM
24 1.1.1.3.2 Draft Weekly and Monthly Status Report 4 hrs 0.5 days Tue
4/5/11
Tue
4/5/11
23 100% Copy of Weekly and Monthly Templates
in Sharepoint as of Day 1
PM
25 1.1.1.3.3 Produce project team organization and contact
list
2 hrs 0.25 days Tue
4/5/11
Tue
4/5/11
24 100% Identification of Segments to be Impacted Segment Line Mgr Assignments
posted in Project Register and used in
S&A Doc
PM
26 1.1.1.3.4 Produce Initial Risk Register 1 hr 0.13 days Tue
4/5/11
Tue
4/5/11
25 100% Copy of Register Template in
Sharepoint
PM
27 1.1.1.3.5 Produce Initial Issues Log 1 hr 0.13 days Tue
4/5/11
Wed
4/6/11
26 100% Copy of Log Template in Sharepoint PM
28 1.1.1.3.6 Produce Project Scope Management Change
Plan
1 hr 0.13 days Wed
4/6/11
Wed
4/6/11
27 100% PM
29 1.1.1.3.7 Produce Project Communication Plan 1 hr 0.13 days Wed
4/6/11
Wed
4/6/11
28 100% Communications Section 6 of the S&A
Document
PM
30 1.1.1.3.8 Prepare Project Assignment 2 hrs 0.25 days Wed
4/6/11
Wed
4/6/11
29 100% Resource Segments Identified, Brief
Completed/Approved
Minutes of Meeting Posted in
Sharepoint
PM
31 1.1.1.3.9 Project Assignment Handoff / Team Assembled 0 hrs 0 days Wed
4/6/11
Wed
4/6/11
30 100% Project Handoff to Project Manager
from PMO
32 1.1.1.3.10 0 hrs 1 day? Fri
4/1/11
Fri
4/1/11
31 100%
33 1.1.2 1.2 - Scope & Assess / TCO(1) 681 hrs 44.63 days? Fri
4/1/11
Thu
6/2/11
100%
34 1.1.2.1 Preparation 17 hrs 2.13 days W ed
4/6/11
Fri
4/8/11
100%
35 1.1.2.1.1 Prepare High-Level function (business)
requirements
2 hrs 0.25 days Wed
4/6/11
Wed
4/6/11
32 100% Project Brief Completed Sections 1 and 4.1 of the
Scope and Assessment Document
PM
36 1.1.2.1.2 Define/assign other resources required to
complete Scope & Assess
2 hrs 0.25 days Wed
4/6/11
Thu
4/7/11
35 100% Identification of Segments to be Involved Completed Sections 2 and 5 of the
Scope and Assessment Document
PM
37 1.1.2.1.3 Prepare High-Level Technical requirements 4 hrs 0.5 days Thu
4/7/11
Thu
4/7/11
36 100% Completed Section 4 of the Scope and
Assessment Document
PM
38 1.1.2.1.4 Prepare Scope & Assess document 8 hrs 1 day Thu
4/7/11
Fri
4/8/11
37 100% Completed Section 3 of the Scope and
Assessment Document
PM
39 1.1.2.1.5 Define Solution Complexity for SDP 1 hr 1 hr Fri
4/8/11
Fri
4/8/11
38 100% Scope & Assessment Document Solution Level Identified (HML) Lead Architect
40 1.1.2.2 Prepare SDP(1) - Conceptual Design 576 hrs 28 days? Fri
4/8/11
W ed
5/18/11
39 100%
41 1.1.2.2.1 Gather Technical Requirements 80 hrs 1 day? Fri
4/8/11
Mon
4/11/11
20,38 100% Project Brief, Scope and Assessment Customer signoff on Tech
Requirements
42 1.1.2.2.2 Customer Signoff on Tech Requirements 0 hrs 0 days Mon
4/11/11
Mon
4/11/11
41 100%
43 1.1.2.2.3 SDP(1) - High Complexity 184 hrs 23 days Fri
4/8/11
W ed
5/11/11
100% This Template is determined by the
defined Solution Complexity/Level
Remove if Not High Complexity
44 1.1.2.2.3.1 Prepare SDP(1) High Complexity 160 hrs 20 days Fri
4/8/11
Fri
5/6/11
100% Bill of Materials Lead Architect
PM
PM
PM
PM
PM
PM
PM
PM
4/6
PM
PM
PM
PM
Lead Architect
4/11
Lead Architect
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 2
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
45 1.1.2.2.3.2 Solution Design Quality Review Lead time 24 hrs 3 days Fri
5/6/11
Wed
5/11/11
44 100% Completed SDP(1) SDP(1) Quality Review Meeting
Scheduled
46 1.1.2.2.4 SDP(1) - Med Complexity 112 hrs 14 days Fri
4/8/11
Thu
4/28/11
100% This Template is determined by the
defined Solution Complexity/Level
Remove if Not Medium Complexity
47 1.1.2.2.4.1 Prepare SDP(1) Med Complexity 96 hrs 12 days Fri
4/8/11
Tue
4/26/11
39 100% Bill of Materials Lead Architect
48 1.1.2.2.4.2 Solution Design Quality Review Lead time 16 hrs 2 days Tue
4/26/11
Thu
4/28/11
47 100% Completed SDP(1) SDP(1) Quality Review Meeting
Scheduled
49 1.1.2.2.5 SDP(1) - Low Complexity 80 hrs 10 days Fri
4/8/11
Fri
4/22/11
100% This Template is determined by the
defined Solution Complexity/Level
Remove if Not Low Complexity
50 1.1.2.2.5.1 Prepare SDP(1) Low Complexity 64 hrs 8 days Fri
4/8/11
Wed
4/20/11
39 100% Bill of Materials Lead Architect
51 1.1.2.2.5.2 Solution Design Quality Review Lead time 16 hrs 2 days Wed
4/20/11
Fri
4/22/11
50 100% Completed SDP(1) SDP(1) Quality Review Meeting
Scheduled
52 1.1.2.2.6 SDP - Lite 96 hrs 12 days Fri
4/8/11
Tue
4/26/11
100% This Template is determined by the
defined Solution Complexity/Level
Remove if Not Low Complexity
53 1.1.2.2.6.1 Prepare SDP Lite 80 hrs 10 days Fri
4/8/11
Fri
4/22/11
100% Lead Architect
54 1.1.2.2.6.2 Solution Design Quality Review Lead time 16 hrs 2 days Fri
4/22/11
Tue
4/26/11
53 100% Completed SDP SDP Quality Review Meeting
Scheduled
55 1.1.2.2.7 SDP(1) Quality Review Signoff 0 hrs 0 days Wed
5/11/11
Wed
5/11/11
45,48,51100% Quality Review Meeting Held Meeting Minutes posted in Sharepoint
56 1.1.2.2.8 Define on-going support costs 8 hrs 1 day Wed
5/11/11
Thu
5/12/11
55 100% Quality Review Meeting Bill of Materials Lead Architect
57 1.1.2.2.9 Finalize Scope and Assess Document with
SDP(1) inputs
4 hrs 1 day Thu
5/12/11
Fri
5/13/11
38,56 100% Quality Review Meeting Scope and Assessment Document
posted in Sharepoint
PM[50%]
58 1.1.2.2.10 Complete detailed project plan (V1.0) 8 hrs 2 days Fri
5/13/11
Tue
5/17/11
57 100% Quality Review Meeting This Document Posted in SharePoint PM[50%]
59 1.1.2.2.11 Prepare TCO(1) 4 hrs 1 day Tue
5/17/11
Wed
5/18/11
58 100% Ongoing support Costs TCO(1) Posted in Sharepoint PM[50%]
60 1.1.2.3 S&A TCO(1) Review Approval 88 hrs 44.63 days? Fri
4/1/11
Thu
6/2/11
100%
61 1.1.2.3.1 Review/obtain approval from customer for S&A
and TCO(1)
16 hrs 2 days Wed
5/18/11
Fri
5/20/11
59 100% Quality Review Meeting Held Meeting Minutes posted in Sharepoint PM
62 1.1.10 Scope & Assess & TCO(1) Approval 16 hrs 2 days Fri
5/20/11
Tue
5/24/11
61 100% Quality Review Meeting Customer
63 1.1.11 Review and assign resources for requirements
phase
8 hrs 1 day Tue
5/24/11
Wed
5/25/11
62 100% Quality Review Meeting Scope and Assessment Document
posted in Sharepoint
PMO
64 1.1.2.3.4 Prepare Project Kick-off Meeting 40 hrs 5 days Wed
5/25/11
Wed
6/1/11
63 100% Resources Assigned, Brief
Completed/Approved
PM Assignment Posted in Sharepoint
(Project Register)
PM
65 1.1.2.3.5 Project Kickoff Meeting / Team Members
Identified
0 hrs 0 days Wed
6/1/11
Wed
6/1/11
64 100% Project Kickoff Meeting Held with all
the identified Team Participants
66 1.1.2.3.6 Early Notification to GO&I Service Providers 8 hrs 1 day Wed
6/1/11
Thu
6/2/11
65 100% Kickoff Meeting This Document Posted in SharePoint PM
Lead Architect
Lead Architect
Lead Architect
5/11
Lead Architect
PM[50%]
PM[50%]
PM[50%]
PM
Customer
PMO
PM
6/1
PM
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 3
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
67 1.1.2.3.7 PMO Gate Review (Initiate Phase) 0 hrs 0 days Thu
6/2/11
Thu
6/2/11
66 100% Scope & Assess, SDP(1), BOM,
TCO(1)
TCO(1) Posted in Sharepoint PM
68 1.1.2.3.8 0 hrs 1 day? Fri
4/1/11
Fri
4/1/11
100%
6/213 20 27 3 10 17 24
Mar '11 Apr '11
Page 4
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
69 1.2 2.0 Requirements 24 hrs 7.76 days? Fri
4/1/11
Tue
4/12/11
100%
70 1.2.1 2.1 Functional, Technical Requirements 24 hrs 7.76 days? Fri
4/1/11
Tue
4/12/11
100%
71 1.2.1.1 Detailed Requirements 24 hrs 4 days W ed
4/6/11
Tue
4/12/11
100%
72 1.2.1.1.1 Prepare detailed functional (Business)
requirements
4 hrs 0.5 days Wed
4/6/11
Thu
4/7/11
35 100% Detail Requirements based on Project
Brief
Functional Requirements from which
Technical Requirement can be drawn
PM
73 1.2.2 Prepare detailed (Technical) requirements 4 hrs 0.5 days Thu
4/7/11
Thu
4/7/11
72 100% All Business functions identified Technical Requirements to meet all
identified business requirments
Solutions Architect
74 1.2.1.1.3 Prepare detailed Traceability Matrix & project
plan
8 hrs 1 day Thu
4/7/11
Fri
4/8/11
73 100% Map of Business requirements to
Technical Requirements
PM
75 1.2.1.1.4 Review Traceability Matrix (requirements) w/
customer
4 hrs 1 day Fri
4/8/11
Mon
4/11/11
74 100% Scheduled Review meeting to finalize
requirements
PM[50%]
76 1.2.1.1.5 Requirements sign-off 0 hrs 0 days Mon
4/11/11
Mon
4/11/11
75 100% Customer approval of functional,
technical and Traceability documents
Customer
77 1.2.1.1.6 Update detailed project plan 4 hrs 1 day Mon
4/11/11
Tue
4/12/11
76 100% Verification with each segment as to HL
duration of effort based on Requirements
Revised project schedule based on
identified efforts
PM[50%]
78 1.2.1.2 PMO Gate Review (Requirements Phase) 0 hrs 0 days Tue
4/12/11
Tue
4/12/11
77 100% PM
79 1.2.1.3 0 hrs 1 day? Fri
4/1/11
Fri
4/1/11
100%
PM
Solutions Architect
PM
PM[50%]
4/11
PM[50%]
4/12
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 5
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
80 1.3 3.0 Design 1,448.03
hrs
218.52 days? Fri
4/1/11
W ed
2/1/12
78 100%
81 1.3.1 3.1 Design Stages SDP(2) - Physical Design 1,448.03
hrs
218.52 days? Fri
4/1/11
W ed
2/1/12
100%
82 1.3.1.1 Design SDP(2) High Complexity 529 hrs 66.25 days Tue
4/12/11
Thu
7/14/11
100% This Template is determined by the
defined Solution Complexity/Level
Remove if Not High Complexity
83 1.3.1.1.1 Prepare SDP(2) High Complexity 480 hrs 12 wks Tue
4/12/11
Tue
7/5/11
76 100% Functional Signoff Solutions
Architech
84 1.3.1.1.2 Update project level & priority 1 hr 0.25 days Tue
7/5/11
Wed
7/6/11
83 100% PM[50%]
85 1.3.1.1.3 Review Design for Supportability 8 hrs 1 day Wed
7/6/11
Thu
7/7/11
84 100% Lead
Architect[50%],Solutions
Architect[50%]86 1.3.1.1.4 Solution Design Quality Review Lead time 40 hrs 5 days Thu
7/7/11
Thu
7/14/11
85 100% Completed SDP(2) SDP(2) Quality Review Meeting
Scheduled
87 1.3.1.2 Design SDP(2) Med Complexity 273 hrs 39.25 days Tue
4/12/11
Tue
6/7/11
100% This Template is determined by the
defined Solution Complexity/Level
Remove if Not Medium Complexity
88 1.3.1.2.1 Prepare SDP(2) Med Complexity 240 hrs 7 wks Tue
4/12/11
Tue
5/31/11
76 100% Functional Signoff Solutions
Architech[86%]
89 1.3.1.2.2 Update project level & priority 1 hr 0.25 days Tue
5/31/11
Wed
6/1/11
88 100% PM[50%]
90 1.3.1.2.3 Review Design for Supportability 8 hrs 1 day Wed
6/1/11
Thu
6/2/11
89 100% Lead
Architect[50%],Solutions
Architect[50%]91 1.3.1.2.4 Solution Design Quality Review Lead time 24 hrs 3 days Thu
6/2/11
Tue
6/7/11
90 100% Completed SDP(2) SDP(2) Quality Review Meeting
Scheduled
92 1.3.1.3 Design SDP(2) Low Complexity 185 hrs 23.25 days Tue
4/12/11
Mon
5/16/11
100% This Template is determined by the
defined Solution Complexity/Level
Remove if Not Low Complexity
93 1.3.1.3.1 Prepare SDP(2) Low Complexity 160 hrs 4 wks Tue
4/12/11
Tue
5/10/11
76 100% Functional Signoff Solutions
Architech
94 1.3.1.3.2 Update project level & priority 1 hr 0.25 days Tue
5/10/11
Wed
5/11/11
93 100% PM[50%]
95 1.3.1.3.3 Review Design for Supportability 8 hrs 1 day Wed
5/11/11
Thu
5/12/11
94 100% Lead
Architect[50%],Solutions
Architect[50%]96 1.3.1.3.4 Solution Design Quality Review Lead time 16 hrs 2 days Thu
5/12/11
Mon
5/16/11
95 100% Completed SDP(2) SDP(2) Quality Review Meeting
Scheduled
97 1.3.1.4 Review and Approval SDP(2) 19.03 hrs 3.13 days Thu
7/14/11
Tue
7/19/11
100%
98 1.3.1.4.1 Quality Review Signoff 0 hrs 0 days Thu
7/14/11
Thu
7/14/11
86,91,96100% Meeting Minutes posted in Sharepoint
99 1.3.1.4.2 Prepare TCO(2) 8 hrs 1 day Thu
7/14/11
Fri
7/15/11
98 100% PM
100 1.3.1.4.3 Review/obtain approval from customer for
TCO(2)
1.03 hrs 0.13 days Fri
7/15/11
Fri
7/15/11
99 100% PM
101 1.3.1.4.4 TCO(2) Approval 0 hrs 0 days Fri
7/15/11
Fri
7/15/11
100 100% Customer[25%]
Solutions Architech
Solutions Architech[86%]
PM[50%]
Lead Architect[50%],Solutions Architect[50%]
Solutions Architech
PM[50%]
Lead Architect[50%],Solutions Architect[50%]
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 6
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
102 1.3.1.4.5 EAEC Review 4 hrs 0.5 days Fri
7/15/11
Fri
7/15/11
101 100% 2nd week of month Lead Architect
103 1.3.1.4.6 TechOps / OCIO Review 4 hrs 0.5 days Fri
7/15/11
Mon
7/18/11
102 100% 4 week of month Lead Architect
104 1.3.1.4.7 Request and assign resources for design part
SDP(3) and TCO(3)
2 hrs 1 day Mon
7/18/11
Tue
7/19/11
103 100% Customer[25%]
105 1.3.1.5 Design SDP(3) - Configuration & Test Design 424 hrs 141.14 days? Fri
7/15/11
Mon
1/30/12
100% Testing and Operational
Specifications
106 1.3.1.5.1 Identify long lead time deliverables 216 hrs 115.14 days? Fri
7/15/11
Fri
12/23/11
101 100% PM
107 1.3.1.5.2 Execute procurement for long lead time 8 hrs 1 day? Fri
12/23/11
Mon
12/26/11
106 100% PM
108 1.3.1.5.3 Create configuration and test design 8 hrs 1 day? Mon
12/26/11
Tue
12/27/11
107 100% Solutions Architect
109 1.3.1.5.4 Develop SLA 8 hrs 1 day? Tue
12/27/11
Wed
12/28/11
108 100% Solutions Architect
110 1.3.1.5.5 Prepare SDP(3) (Varable Timeline) 80 hrs 10 days Wed
12/28/11
Wed
1/11/12
109 100% Solutions Architect
111 1.3.1.5.6 Prepare Detailed Design & Project Plan 80 hrs 10 days Wed
1/11/12
Wed
1/25/12
110 100% PM
112 1.3.1.5.7 Prepare TCO(3) 24 hrs 3 days Wed
1/25/12
Mon
1/30/12
111 100% PM
113 1.3.1.6 Review and Approval SDP(3) 18 hrs 218.52 days? Fri
4/1/11
W ed
2/1/12
100%
114 1.3.1.6.1 Review / Obtain Approval on design and TCO(3) 2 hrs 0.25 days Mon
1/30/12
Mon
1/30/12
112 100%
115 1.3.1.6.2 EAEC Review 4 hrs 0.5 days Mon
1/30/12
Tue
1/31/12
114 100% Lead Architect
116 1.3.1.6.3 TechOps / OCIO Review 4 hrs 0.5 days Tue
1/31/12
Tue
1/31/12
115 100% Lead Architect
117 1.3.1.6.4 PMO Gate Review (Design Phase) 0 hrs 0 days Tue
1/31/12
Tue
1/31/12
116 100% PM
118 1.3.1.6.5 Request and Assign Resources for Build and
Deploy
8 hrs 1 day? Tue
1/31/12
Wed
2/1/12
117 100% PM
119 1.3.1.6.6 0 hrs 1 day? Fri
4/1/11
Fri
4/1/11
100%
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 7
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
120 1.4 4.0 Build 3,322.23
hrs
159.52 days? Thu
7/14/11
W ed
2/22/12
100% Activity being Fast-Tracked Dep on
45// Normally dependent on SDP(2)
121 1.4.1 4.1 Physical HW & SW Procurement Process 2,866.23
hrs
159.52 days? Thu
7/14/11
W ed
2/22/12
100%
122 1.4.1.1 Ordering Process 34 hrs 4 days? Thu
7/14/11
W ed
7/20/11
100%
129 1.4.1.2 P2P Approval Process 56 hrs 7 days Tue
7/19/11
Thu
7/28/11
100% Entered Orders / Requests Electronic P.O. Cut to Vendor
133 1.4.1.3 Vendor Delivery Process 2,333.63
hrs
142.52 days? Thu
7/28/11
Mon
2/13/12
100% Release
Manager[200%]
141 1.4.1.4 VMW are (Servers) 160 hrs 20 days W ed
7/20/11
W ed
8/17/11
100%
144 1.4.1.5 Equipment Received and Acknowledged 0 hrs 0 days Mon
2/13/12
Mon
2/13/12
140 100% Delivery of equipment to Data Center Signed delivery (Courier) confirmation Data Center
Operations
145 1.4.1.6 Update DCFM Request 248.6 hrs 34 days? Fri
8/19/11
Thu
10/6/11
137,143100% W W N Assignments and SDP(2)
166 1.4.1.7 Initial Server Build & Validation 34 hrs 7 days Mon
2/13/12
W ed
2/22/12
100% Dependent on SDP(2) when being
Fast Tracked
174 1.4.2 4.2 Data Center Change Task Install Process 456 hrs 21 days? Thu
8/25/11
Fri
9/23/11
151 100%
198 1.5 0 hrs 1 day? Fri
4/1/11
Fri
4/1/11
100%
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 8
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
199 1.6 5.0 Deployment 1,728 hrs 39 days? Mon
9/12/11
Fri
11/4/11
100%
200 1.6.1 Operational Readiness 1,728 hrs 39 days? Mon
9/12/11
Fri
11/4/11
100%
201 1.6.1.1 Infrastructure Verification 0 hrs 1 day? Mon
9/12/11
Tue
9/13/11
197 100%
202 1.6.1.1.1 Document tests to be performed to verify the
infrastructure build
0 hrs 1 day? Mon
9/12/11
Tue
9/13/11
100%
203 1.6.1.1.2 Execute the infrastructure tests (HA, Monitoring,
Backup, etc.)
0 hrs 1 day? Mon
9/12/11
Tue
9/13/11
100%
204 1.6.1.2 Dev Deployment Cycle 672 hrs 20 days? Tue
9/13/11
Tue
10/11/11
203 100%
205 1.6.1.2.1 Negotiate Dev Warranty Period and Deployment
Cycles with Business/Build Teams
24 hrs 1 day? Tue
9/13/11
Wed
9/14/11
100% Warranty period set for the Dev
environment
PM,Build
Team,Customer
206 1.6.1.2.2 Unit Test Dev Environment (Connectivity, OS,
Storage) no applications
8 hrs 1 day? Wed
9/14/11
Thu
9/15/11
205 100% Hardware / Environment passed to Build
team
Connectivity tests, OS and SAN
validations
Build Team
207 1.6.1.2.3 Deploy Infrastructure and DB Software
(Webserve, Appache, Oracle, etc.)
16 hrs 1 day? Thu
9/15/11
Fri
9/16/11
206 100% DB Instances - detail All software (less applications) loaded
in the environment
Build Team,DB
Team
208 1.6.1.2.4 Deploy and Configure Mark Logic 80 hrs 5 days? Thu
9/15/11
Thu
9/22/11
206 100% ML Licenses, Configuration
Specifications, Veritas Clusters
Verified working ML Application DBA -
MarkLogic,Marklogic
Support209 1.6.1.2.4.1 Installation of ML on each of 4 nodes 0 hrs 1 day? Thu
9/15/11
Fri
9/16/11
100%
210 1.6.1.2.4.2 Create Search Forests across all nodes 0 hrs 2 days? Fri
9/16/11
Tue
9/20/11
209 100%
211 1.6.1.2.4.3 High Availability Fail-Over/Fail-Back Testing 0 hrs 2 days? Tue
9/20/11
Thu
9/22/11
210 100%
212 1.6.1.2.5 System Test Dev Environments (High Availability,
redundancy, etc.)
8 hrs 1 day? Thu
9/22/11
Fri
9/23/11
208 100% Connectivity, High Availability,
redundancy testing
Build Team
213 1.6.1.2.6 Deploy Application Software per Documented
Procedures (Business/Build Team)
8 hrs 0.5 days? Fri
9/23/11
Fri
9/23/11
212 100% Application Software loaded in all tiers Build
Team,Business
214 1.6.1.2.7 Deploy Data (Load/Migrate) per Documented
Procedures
16 hrs 1 day? Fri
9/23/11
Mon
9/26/11
213 100% Database(s) initialized with data for use
by application
Business,Build
Team
215 1.6.1.2.8 Perform Application Testing 8 hrs 1 day? Mon
9/26/11
Tue
9/27/11
214 100% Business
216 1.6.1.2.9 (re-)Configure environment based on Testing
Outcomes
24 hrs 1 day? Tue
9/27/11
Wed
9/28/11
215 100% PM,Business,Build
Team
217 1.6.1.2.10 Perform nn Deployment Cycles (over 2 week
period)
240 hrs 10 days Tue
9/13/11
Tue
9/27/11
100% PM,Business,Build
Team
218 1.6.1.2.11 Handoff Dev Environment to Run Team 0 hrs 0 days Tue
9/27/11
Tue
9/27/11
217 100% Run Book from the Build Team Acceptance of Run Book and all
Followups
Build Team,Run
Team
219 1.6.1.2.12 Dev Warrantee Period 240 hrs 10 days Tue
9/27/11
Tue
10/11/11
218 100% PM,Business,Build
Team
220 1.6.1.3 QA Deployment Cycle 672 hrs 20 days? Tue
9/13/11
Tue
10/11/11
203 100%
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 9
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
221 1.6.1.3.1 Negotiate QA Warranty Period and Deployment
Cycles with Business/Build Teams
24 hrs 1 day? Tue
9/13/11
Wed
9/14/11
100% Warranty period set for the QA
environment
PM,Build
Team,Customer
222 1.6.1.3.2 Unit Test QA Environment (Connectivity, OS,
Storage) no applications
8 hrs 1 day? Wed
9/14/11
Thu
9/15/11
221 100% Hardware / Environment passed to Build
team
Connectivity tests, OS and SAN
validations
Build Team
223 1.6.1.3.3 Deploy Infrastructure and DB Software
(Webserve, Appache, Oracle, etc.)
16 hrs 1 day? Thu
9/15/11
Fri
9/16/11
222 100% DB Instances - detail All software (less applications) loaded
in the environment
Build Team,DB
Team
224 1.6.1.3.4 Deploy and Configure Mark Logic 80 hrs 5 days? Thu
9/15/11
Thu
9/22/11
222 100% ML Licenses, Configuration
Specifications, Veritas Clusters
Verified working ML Application DBA -
MarkLogic,Marklogic
Support225 1.6.1.3.4.1 Installation of ML on each of 4 nodes 0 hrs 1 day? Thu
9/15/11
Fri
9/16/11
100%
226 1.6.1.3.4.2 Create Search Forests across all nodes 0 hrs 2 days? Fri
9/16/11
Tue
9/20/11
225 100%
227 1.6.1.3.4.3 High Availability Fail-Over/Fail-Back Testing 0 hrs 2 days? Tue
9/20/11
Thu
9/22/11
226 100%
228 1.6.1.3.5 System Test QA Environments (High Availability,
redundancy, etc.)
8 hrs 1 day? Thu
9/22/11
Fri
9/23/11
224 100% Connectivity, High Availability,
redundancy testing
Build Team
229 1.6.1.3.6 Deploy Application Software per Documented
Procedures (Business/Build Team)
8 hrs 0.5 days? Fri
9/23/11
Fri
9/23/11
228 100% Application Software loaded in all tiers Build
Team,Business
230 1.6.1.3.7 Deploy Data (Load/Migrate) per Documented
Procedures
16 hrs 1 day? Fri
9/23/11
Mon
9/26/11
229 100% Database(s) initialized with data for use
by application
Business,Build
Team
231 1.6.1.3.8 Perform Application Testing 8 hrs 1 day? Mon
9/26/11
Tue
9/27/11
230 100% Business
232 1.6.1.3.9 (re-)Configure environment based on Testing
Outcomes
24 hrs 1 day? Tue
9/27/11
Wed
9/28/11
231 100% PM,Business,Build
Team
233 1.6.1.3.10 Perform nn Deployment Cycles (over 2 week
period)
240 hrs 10 days Tue
9/13/11
Tue
9/27/11
100% PM,Business,Build
Team
234 1.6.1.3.11 Handoff QA Environment to Run Team 0 hrs 0 days Tue
9/27/11
Tue
9/27/11
233 100% Run Book from the Build Team Acceptance of Run Book and all
Followups
Build Team,Run
Team
235 1.6.1.3.12 QA Warrantee Period 240 hrs 10 days Tue
9/27/11
Tue
10/11/11
234 100% PM,Business,Build
Team
236 1.6.1.4 Prod Deployment Cycle 192 hrs 11.5 days? Tue
9/13/11
W ed
9/28/11
203 100%
237 1.6.1.4.1 Negotiate Prod Warranty Period and Deployment
Cycles with Business/Build Teams
24 hrs 1 day? Tue
9/13/11
Wed
9/14/11
100% Warranty period set for the QA
environment
PM,Build
Team,Customer
238 1.6.1.4.2 Unit Test Prod Environment (Connectivity, OS,
Storage) no applications
8 hrs 1 day? Wed
9/14/11
Thu
9/15/11
237 100% Hardware / Environment passed to Build
team
Connectivity tests, OS and SAN
validations
Build Team
239 1.6.1.4.3 Deploy Infrastructure and DB Software
(Webserve, Appache, Oracle, etc.)
16 hrs 1 day? Thu
9/15/11
Fri
9/16/11
238 100% DB Instances - detail All software (less applications) loaded
in the environment
Build Team,DB
Team
240 1.6.1.4.4 Deploy and Configure Mark Logic 80 hrs 5 days? Thu
9/15/11
Thu
9/22/11
238 100% ML Licenses, Configuration
Specifications, Veritas Clusters
Verified working ML Application DBA -
MarkLogic,Marklogic
Support241 1.6.1.4.4.1 Installation of ML on each of 4 nodes 0 hrs 1 day? Thu
9/15/11
Fri
9/16/11
100%
242 1.6.1.4.4.2 Create Search Forests across all nodes 0 hrs 2 days? Fri
9/16/11
Tue
9/20/11
241 100%
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 10
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
243 1.6.1.4.4.3 High Availability Fail-Over/Fail-Back Testing 0 hrs 2 days? Tue
9/20/11
Thu
9/22/11
242 100%
244 1.6.1.4.5 System Test Prod Environments (High
Availability, redundancy, etc.)
8 hrs 1 day? Thu
9/22/11
Fri
9/23/11
240 100% Connectivity, High Availability,
redundancy testing
Build Team
245 1.6.1.4.6 Deploy Application Software per Documented
Procedures (Business/Build Team)
8 hrs 0.5 days? Fri
9/23/11
Fri
9/23/11
244 100% Application Software loaded in all tiers Build
Team,Business
246 1.6.1.4.7 Deploy Data (Load/Migrate) per Documented
Procedures
16 hrs 1 day? Fri
9/23/11
Mon
9/26/11
245 100% Database(s) initialized with data for use
by application
Business,Build
Team
247 1.6.1.4.8 Perform Application Testing 8 hrs 1 day? Mon
9/26/11
Tue
9/27/11
246 100% Business
248 1.6.1.4.9 (re-)Configure environment based on Testing
Outcomes
24 hrs 1 day? Tue
9/27/11
Wed
9/28/11
247 100% PM,Business,Build
Team
249 1.6.1.5 DR Deployment Cycle 192 hrs 11.5 days? W ed
9/28/11
Fri
10/14/11
236 100%
250 1.6.1.5.1 Negotiate DR Warranty Period and Deployment
Cycles with Business/Build Teams
24 hrs 1 day? Wed
9/28/11
Thu
9/29/11
100% Warranty period set for the QA
environment
PM,Build
Team,Customer
251 1.6.1.5.2 Unit Test DR Environment (Connectivity, OS,
Storage) no applications
8 hrs 1 day? Thu
9/29/11
Fri
9/30/11
250 100% Hardware / Environment passed to Build
team
Connectivity tests, OS and SAN
validations
Build Team
252 1.6.1.5.3 Deploy Infrastructure and DB Software
(Webserve, Appache, Oracle, etc.)
16 hrs 1 day? Fri
9/30/11
Mon
10/3/11
251 100% DB Instances - detail All software (less applications) loaded
in the environment
Build Team,DB
Team
253 1.6.1.5.4 Deploy and Configure Mark Logic 80 hrs 5 days? Fri
9/30/11
Fri
10/7/11
251 100% ML Licenses, Configuration
Specifications, Veritas Clusters
Verified working ML Application DBA -
MarkLogic,Marklogic
Support254 1.6.1.5.4.1 Installation of ML on each of 4 nodes 0 hrs 1 day? Fri
9/30/11
Mon
10/3/11
100%
255 1.6.1.5.4.2 Create Search Forests across all nodes 0 hrs 2 days? Mon
10/3/11
Wed
10/5/11
254 100%
256 1.6.1.5.4.3 High Availability Fail-Over/Fail-Back Testing 0 hrs 2 days? Wed
10/5/11
Fri
10/7/11
255 100%
257 1.6.1.5.5 System Test DR Environments (High Availability,
redundancy, etc.)
8 hrs 1 day? Fri
10/7/11
Mon
10/10/11
253 100% Connectivity, High Availability,
redundancy testing
Build Team
258 1.6.1.5.6 Deploy Application Software per Documented
Procedures (Business/Build Team)
8 hrs 0.5 days? Mon
10/10/11
Tue
10/11/11
257 100% Application Software loaded in all tiers Build
Team,Business
259 1.6.1.5.7 Deploy Data (Load/Migrate) per Documented
Procedures
16 hrs 1 day? Tue
10/11/11
Wed
10/12/11
258 100% Database(s) initialized with data for use
by application
Business,Build
Team
260 1.6.1.5.8 Perform Application Testing 8 hrs 1 day? Wed
10/12/11
Thu
10/13/11
259 100% Business
261 1.6.1.5.9 (re-)Configure environment based on Testing
Outcomes
24 hrs 1 day? Thu
10/13/11
Fri
10/14/11
260 100% PM,Business,Build
Team
262 1.6.1.6 Prod/DR Testing Cycle 0 hrs 5 days? Fri
10/14/11
Fri
10/21/11
100%
263 1.6.1.6.1 Define DR Test Scenario 0 hrs 2 days Fri
10/14/11
Tue
10/18/11
248,261100%
264 1.6.1.6.2 Schedule DR Test Period 0 hrs 1 day? Tue
10/18/11
Wed
10/19/11
263 100%
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 11
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
265 1.6.1.6.3 Execute DR Fail-over 0 hrs 1 day? Wed
10/19/11
Thu
10/20/11
264 100%
266 1.6.1.6.4 Execute DR Fail-Back 0 hrs 1 day? Thu
10/20/11
Fri
10/21/11
265 100%
267 1.6.1.6.5 DR Testing Successful 0 hrs 0 days Fri
10/21/11
Fri
10/21/11
266 100%
268 1.6.1.7 Go Live Plan 0 hrs 10 days? Fri
10/21/11
Fri
11/4/11
262 100%
269 1.6.1.7.1 Warantee Support in Place 0 hrs 1 day? Fri
10/21/11
Mon
10/24/11
100%
270 1.6.1.7.2 Review Production Results 0 hrs 1 day? Fri
10/21/11
Mon
10/24/11
100%
271 1.6.1.7.3 Go/No-Go Decision 0 hrs 1 day? Fri
10/21/11
Mon
10/24/11
100%
272 1.6.1.7.4 Implement Live in Production Environment 0 hrs 1 day? Fri
10/21/11
Mon
10/24/11
100%
273 1.6.1.7.5 Prod/DR Warrantee Period 0 hrs 10 days Fri
10/21/11
Fri
11/4/11
100%
274 1.6.1.7.6 Handoff to Run Team 0 hrs 0 days Fri
11/4/11
Fri
11/4/11
273 100%
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 12
ID WBS RAG Task Name Work Duration Start Finish Predecessors%
Complete
Trigger / Dependent Tasks Deliverable(s) Resource Names
275 1.7 6.0 Project Closure 0 hrs 1 day? Fri
11/4/11
Mon
11/7/11
274 100%
276 1.7.1 Project Closure Documentation and Signoff 0 hrs 1 day? Fri
11/4/11
Mon
11/7/11
100%
277 1.7.1.1 Lessons Learn Review 0 hrs 1 day? Fri
11/4/11
Mon
11/7/11
100%
278 1.7.1.2 Project Survey Request 0 hrs 1 day? Fri
11/4/11
Mon
11/7/11
100%
279 1.7.1.3 Project Closure Customer Signoff 0 hrs 1 day? Fri
11/4/11
Mon
11/7/11
100%
280 1.7.1.4 Project Team Closure Acknowledgements and Party 0 hrs 1 day? Fri
11/4/11
Mon
11/7/11
100%
13 20 27 3 10 17 24
Mar '11 Apr '11
Page 13
ID WBS
1 1
2
3 1.1
4 1.1.1
5 1.1.1.1
6 1.1.1.1.1
7 1.1.1.1.1.1
8 1.1.1.1.1.2
9 1.1.1.1.1.3
10 1.1.1.1.1.4
11 1.1.1.1.2
12 1.1.1.1.2.1
13 1.1.1.2
14 1.1.1.2.1
15 1.1.1.2.2
16 1.1.1.2.3
17 1.1.1.2.4
18 1.1.1.2.5
19 1.1.1.2.6
20 1.1.1.2.7
21 1.1.1.2.8
22 1.1.1.3
PM[3%]
PM[3%]
PM[3%]
PM[5%]
PM
CAE
CAE
CAE[96%]
CAE[50%]
PM[25%]
4/4
4/4
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 14
ID WBS
23 1.1.1.3.1
24 1.1.1.3.2
25 1.1.1.3.3
26 1.1.1.3.4
27 1.1.1.3.5
28 1.1.1.3.6
29 1.1.1.3.7
30 1.1.1.3.8
31 1.1.1.3.9
32 1.1.1.3.10
33 1.1.2
34 1.1.2.1
35 1.1.2.1.1
36 1.1.2.1.2
37 1.1.2.1.3
38 1.1.2.1.4
39 1.1.2.1.5
40 1.1.2.2
41 1.1.2.2.1
42 1.1.2.2.2
43 1.1.2.2.3
44 1.1.2.2.3.1
PM
PM
PM
PM
PM
PM
PM
PM
4/6
PM
PM
PM
PM
Lead Architect
4/11
Lead Architect
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 15
ID WBS
45 1.1.2.2.3.2
46 1.1.2.2.4
47 1.1.2.2.4.1
48 1.1.2.2.4.2
49 1.1.2.2.5
50 1.1.2.2.5.1
51 1.1.2.2.5.2
52 1.1.2.2.6
53 1.1.2.2.6.1
54 1.1.2.2.6.2
55 1.1.2.2.7
56 1.1.2.2.8
57 1.1.2.2.9
58 1.1.2.2.10
59 1.1.2.2.11
60 1.1.2.3
61 1.1.2.3.1
62 1.1.10
63 1.1.11
64 1.1.2.3.4
65 1.1.2.3.5
66 1.1.2.3.6
Lead Architect
Lead Architect
Lead Architect
5/11
Lead Architect
PM[50%]
PM[50%]
PM[50%]
PM
Customer
PMO
PM
6/1
PM
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 16
ID WBS
67 1.1.2.3.7
68 1.1.2.3.8
6/224 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 17
ID WBS
69 1.2
70 1.2.1
71 1.2.1.1
72 1.2.1.1.1
73 1.2.2
74 1.2.1.1.3
75 1.2.1.1.4
76 1.2.1.1.5
77 1.2.1.1.6
78 1.2.1.2
79 1.2.1.3
PM
Solutions Architect
PM
PM[50%]
4/11
PM[50%]
4/12
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 18
ID WBS
80 1.3
81 1.3.1
82 1.3.1.1
83 1.3.1.1.1
84 1.3.1.1.2
85 1.3.1.1.3
86 1.3.1.1.4
87 1.3.1.2
88 1.3.1.2.1
89 1.3.1.2.2
90 1.3.1.2.3
91 1.3.1.2.4
92 1.3.1.3
93 1.3.1.3.1
94 1.3.1.3.2
95 1.3.1.3.3
96 1.3.1.3.4
97 1.3.1.4
98 1.3.1.4.1
99 1.3.1.4.2
100 1.3.1.4.3
101 1.3.1.4.4
Solutions Architech
PM[50%]
Lead Architect[50%],Solutions Architect[50%]
Solutions Architech[86%]
PM[50%]
Lead Architect[50%],Solutions Architect[50%]
Solutions Architech
PM[50%]
Lead Architect[50%],Solutions Architect[50%]
7/14
PM
PM
7/15
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 19
ID WBS
102 1.3.1.4.5
103 1.3.1.4.6
104 1.3.1.4.7
105 1.3.1.5
106 1.3.1.5.1
107 1.3.1.5.2
108 1.3.1.5.3
109 1.3.1.5.4
110 1.3.1.5.5
111 1.3.1.5.6
112 1.3.1.5.7
113 1.3.1.6
114 1.3.1.6.1
115 1.3.1.6.2
116 1.3.1.6.3
117 1.3.1.6.4
118 1.3.1.6.5
119 1.3.1.6.6
Lead Architect
Lead Architect
Customer[25%]
PM
PM
Solutions Architect
Solutions Architect
Solutions Architect
PM
PM
Lead Architect
Lead Architect
1/31
PM
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 20
ID WBS
120 1.4
121 1.4.1
122 1.4.1.1
129 1.4.1.2
133 1.4.1.3
141 1.4.1.4
144 1.4.1.5
145 1.4.1.6
166 1.4.1.7
174 1.4.2
198 1.5
2/13
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 21
ID WBS
199 1.6
200 1.6.1
201 1.6.1.1
202 1.6.1.1.1
203 1.6.1.1.2
204 1.6.1.2
205 1.6.1.2.1
206 1.6.1.2.2
207 1.6.1.2.3
208 1.6.1.2.4
209 1.6.1.2.4.1
210 1.6.1.2.4.2
211 1.6.1.2.4.3
212 1.6.1.2.5
213 1.6.1.2.6
214 1.6.1.2.7
215 1.6.1.2.8
216 1.6.1.2.9
217 1.6.1.2.10
218 1.6.1.2.11
219 1.6.1.2.12
220 1.6.1.3
PM,Build Team,Customer
Build Team
Build Team,DB Team
Build Team
Build Team,Business
Business,Build Team
Business
PM,Business,Build Team
PM,Business,Build Team
9/27
PM,Business,Build Team
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 22
ID WBS
221 1.6.1.3.1
222 1.6.1.3.2
223 1.6.1.3.3
224 1.6.1.3.4
225 1.6.1.3.4.1
226 1.6.1.3.4.2
227 1.6.1.3.4.3
228 1.6.1.3.5
229 1.6.1.3.6
230 1.6.1.3.7
231 1.6.1.3.8
232 1.6.1.3.9
233 1.6.1.3.10
234 1.6.1.3.11
235 1.6.1.3.12
236 1.6.1.4
237 1.6.1.4.1
238 1.6.1.4.2
239 1.6.1.4.3
240 1.6.1.4.4
241 1.6.1.4.4.1
242 1.6.1.4.4.2
PM,Build Team,Customer
Build Team
Build Team,DB Team
Build Team
Build Team,Business
Business,Build Team
Business
PM,Business,Build Team
PM,Business,Build Team
9/27
PM,Business,Build Team
PM,Build Team,Customer
Build Team
Build Team,DB Team
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 23
ID WBS
243 1.6.1.4.4.3
244 1.6.1.4.5
245 1.6.1.4.6
246 1.6.1.4.7
247 1.6.1.4.8
248 1.6.1.4.9
249 1.6.1.5
250 1.6.1.5.1
251 1.6.1.5.2
252 1.6.1.5.3
253 1.6.1.5.4
254 1.6.1.5.4.1
255 1.6.1.5.4.2
256 1.6.1.5.4.3
257 1.6.1.5.5
258 1.6.1.5.6
259 1.6.1.5.7
260 1.6.1.5.8
261 1.6.1.5.9
262 1.6.1.6
263 1.6.1.6.1
264 1.6.1.6.2
Build Team
Build Team,Business
Business,Build Team
Business
PM,Business,Build Team
PM,Build Team,Customer
Build Team
Build Team,DB Team
Build Team
Build Team,Business
Business,Build Team
Business
PM,Business,Build Team
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 24
ID WBS
265 1.6.1.6.3
266 1.6.1.6.4
267 1.6.1.6.5
268 1.6.1.7
269 1.6.1.7.1
270 1.6.1.7.2
271 1.6.1.7.3
272 1.6.1.7.4
273 1.6.1.7.5
274 1.6.1.7.6
10/21
11/4
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 25
ID WBS
275 1.7
276 1.7.1
277 1.7.1.1
278 1.7.1.2
279 1.7.1.3
280 1.7.1.4
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4
Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
Page 26
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Page 27
Project: Project Template - 6.0 - Infrastruc
Date: Sun 3/15/15