SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
Depressurization & Disposal of Hydrotest Water SAIC-A-2017 1-Dec-06 MECH.
EQPT CODE SYSTEM ID.
LAYOUT DRAWING NUMBER
PLANT NO.EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION
QUANTITY INSP.SCHEDULED INSPECTION DATE & TIME
ITEM
No.ACCEPTANCE CRITERIA PASS FAIL N/A
ACTUAL INSPECTION DATE & TIME
SAUDI ARAMCO USE ONLYWORK PERMIT REQUIR
CONTRACTOR INSPECTION LEVEL
RE-INSP DA
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER
EC / PMCC / MCC NO.REV. NO. PURCHASE ORDER NUMBER
MH's SPENT TRAVEL TIME
A General Requirements
SAUDI ARAMCO INSPECTION LEVEL
REFERENCE
GI-002.102,
Section 5.20
A1
Depressurization is done slowly and safely after completion of test or on
discovery of leaks. Bleed off the system slowly to an approved safe
discharge area and monitor discharge.
GI-002.102,
Section 5.17
B Specific Disposal Requirements
B1New pipelines, and pipelines in gas service do not require oil/water
separation prior to wastewater discharge/disposal
SAEP-327,
Section 3
A2
Inspection ensures written procedures approved prior to testing are
followed upon disposal of any test medium containing chemical additives
for control of corrosion and bacteria.
Dispos al methods follo w SAEP-327, Sect ion 3 requirements .
SAEP-327,
Section 3
B3
As far as possible locate the disposal site within the existing pipeline
corridor while ensuring adequate pipeline access and without causing
damage to the existing roadways, pipelines, private entities or other
structures
SAEP-327,
Section 3
B2
Do not discharge wastewater to local wadi environments. Discharge
separated wastewater to non-sabkhah areas into approved pits or to
lined evaporation ponds constructed.
B4Do not dispose wastewater within or adjacent to wetland or sensitive
environments, including specified conservation areas
SAEP-327,
Section 3
Disposal to Industrial Wastewater Treatment Plant
Discharge wastewater directly to the local industrial wastewater
treatment plant if disposal does not affect the normal operations of the
plant. Obtain concurrence from the operators of the treatment plant prior
to selection of this disposal option.
SAEP-327,
Section 3
B5
Disposal to Sabkhah
Discharge separated wastewater directly to the sabkhah for evaporation
provided that the wastewater remains on land, and does not flow directly
to the marine environment. An oil/water Separator Pond is required
before wastewater is discharged to sabkhah to ensure retention of
residual hydrocarbon for subsequent collection and proper handling.
Separator pond site is downwind to minimize exposure risk to nearby
facilities personnel.
SAEP-327,
Section 3
B6
Disposal to an Evaporation Pond
Oil/water separator ponds are required upstream of evaporation ponds to
collect residual hydrocarbon and improve evaporation in the evaporation
ponds.
SAEP-327,
Section 3
B8
Disposal to Injection Well
Dispose wastewater into injection wells if it does not affect the well
operation. Obtain concurrence from the operators of the well prior to
selection of this disposal option. Injection well operators will provide
water quality criteria for any wastewater that will be introduced to theirsystem for disposal
SAEP-327,
Section 3
B7
Page 1 of 3
7/29/2019 SAIC-A-2017 Rev 2
2/3
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FA
QC Supervisor Proponent and Others
Name, Sign and Date:
Quality Record Approved:Name, Organization,
Initials and Date:
T&I W itnessed QC Record Reviewed W ork Verified
QC Inspector PID Representative
Name, Initials and Date:
Performed Inspection Work / Rework May Proceed
Name, Initials and Date:
T&I W itnessed QC Record Reviewed W ork Verified
Name, Initials and Date:
Work is Complete and Ready for Inspection:
Name, Initials and Date:
T&I W itnessed QC Record Reviewed W ork Verified
2. SAEP-327, Disposal of Wastewater from Cleaning, Flushing, and Dewatering Pipelines and Vessels (31 May, 2003)
3. SA General Instruction Manual GI-002.102 (July 22, 2001) Pressure Testing Safely
Contractor / Third-Party Saudi AramcoConstruction Representative* PMT Representative
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-A-007, Hydrostatic Testing Fluids and Lay-Up Procedures, (5 October 2005)
B16
For pipelines, dewatering is performed by scraping. If sea water was
used for testing a pipeline, remove salt deposits by scraping with slugs
of water containing less than 4500 mg/L total dissolved solids until the
water soluble sulfates and chlorides on the steel surface at the drain or
outlet end are reduced to
7/29/2019 SAIC-A-2017 Rev 2
3/3
QC Supervisor
Y = YES N = NO F = FA*Person Responsible for Completion of Quality Work / Test
Name, Sign and Date:
Quality Record Approved: Work VerifiedName, Organization,
Initials and Date:
T&I Witnessed QC Record Reviewed
31-Dec-05
REMARKS:
Work is Complete and Ready for Inspection:
SAUDI ARAMCO INSPECTION CHECKLIST
REFERENCE DOCUMENTS:
Saudi Aramco
Name, Initials and Date:
QC Record Reviewed Work Veri fiedT&I Witnessed
Name, Initials and Date:
Construction Representative*
Name, Initials and Date: Name, Initials and Date:
Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2
Proponent and Others
PMT Representative
3. SA General Instruction Manual GI-002.102 (July 22, 2001) Pressure Testing Safely
Contractor / Third-Party
Work Verified
QC Inspector PID Representative
DATE APPROVED QR NUMBERSAIC NUMBER
Depressurization & Disposal of Hydrotest Water SAIC-A-2017 1-Dec-06 MECH.
REFERENCE
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
B9
Disposal OffshoreDispose wastewater offshore to the Arabian Gulf or Red Sea perSAEP-
327 Table 1 (See Excel Sh # 2 Att'd).Adequate dispersal of wastewater
in marine environment by diffuser or similar method or transfer
wastewater onshore for treatment/disposal.
SAEP-327,
Section 3
PASS FAIL N/A RE-INSP DAITEM
No.ACCEPTANCE CRITERIA
B10
Biocides other than Troskil-1 (Polyhexamethylene biguanide
hydrochloride or PHMB) require evaluation & approval by EPD/EED prior
to disposal to the Arabian Gulf or the Red Sea.
Water Disposal Ap proval Form h as been subm it ted
SAEP-327,
Section 3
B11
Dispose wastewater with Rhodamine B and TROS (fluorescent) dyes
into deep water, shallow water and embayment systems perSAEP-327
Table 1 (See Excel Sh # 2 Attached). For other dyes provide toxicity
data, submit Water Disposal Approval Form. Notify Frontier Force of
any discharges of dyes to sea to prevent alarm.
SAEP-327,
Section 3
B12Use a spray nozzle to allow maximum oxygenation of discharge of
waters containing oxygen scavenger added
SAEP-327,
Section 3
B13
Submit Water Disposal Approval Form and obtain approval from
EPD/EED before discharge of any wastewater to embayments and/or
conservation areas in the Arabian Gulf
SAEP-327,
Section 3
B14
Discharge of contaminated wastewaters follows SAES-A-103.
A) Discharge locations are where water columns are deepest.
B) Discharge there is as close to the water surface as practicable.
C) If only oxygen scavenger is used, discharge is into the air and
discharge rate is less than five cubic meters per minute
D) Alternatively, SAES-A-104 allows injection of wastewater into any
petroleum reservoir producing hydrocarbons.
SAEP-327,
Section 3
B15Submit Water Disposal Approval Form and obtain approval from
EPD/EED before disposal of wastewater to the Red Sea
SAEP-327,
Section 3
B16
For pipelines, dewatering is performed by scraping. If sea water was
used for testing a pipeline, remove salt deposits by scraping with slugs
of water containing less than 4500 mg/L total dissolved solids until the
water soluble sulfates and chlorides on the steel surface at the drain or
outlet end are reduced to