Saffron Avenue, London, E14 2AX

Demolition manual for internal soft strip of structure.

TABLE OF CONTENTS

Contents

Information _____________________________________________________________________________________________ 1

Introduction _____________________________________________________________________________________________ 2

Scope of Works _________________________________________________________________________________________________ 2

Plant and equipment _____________________________________________________________________________________________ 2

Internal Soft Strip of the structure ______________________________________________________________________ 3

Task Method ____________________________________________________________________________________________________ 3

Personal Protective Equipment ________________________________________________________________________ 14

Legislation and standards _______________________________________________________________________________ 15

Legislation _____________________________________________________________________________________________________ 15

Regulations ____________________________________________________________________________________________________ 15

British Standards ______________________________________________________________________________________________ 15

National Federation of Demolition Contractors Guidance ____________________________________________________ 15

Institution of Civil Engineers Guidance _______________________________________________________________________ 16

Other: _________________________________________________________________________________________________________ 16

Declaration _____________________________________________________________________________________________ 17

Contractor Completion Sign of Sheet __________________________________________________________________ 18

INFORMATION

P a g e | 1

Information

DOCUMENT INFORMATION

VERSION 4 DATE: 27th August, 2018

AUTHORED BY: Stephen McCann POSITION: Demolition Engineer

SIGNATURE DATE: 27th August, 2018

APPROVED BY: Gary Robinson POSITION: Demolition Director

SIGNATURE: DATE:

CHECKED BY: Lynda Robinson POSITION: Safety Director

SIGNATURE: DATE:

SAFETY COMPLIANCE: Mateusz Szablan POSITION: Safety Advisor

SIGNATURE: DATE: 27th August, 2018

DISCLAIMER: This risk assessed method statement has been produced by Perses Limited as part of

Complete Demolition Ltd. safe systems of work and is prepared in accordance with the requirements of section 5.2.3 of British Standard 6187 Code of practice for full and partial demolition, and Regulation 20 of the Construction (Design and Management) Regulation 2015 and is intended to be used as a guide for the safe execution of this contract.

Please be advised that as a competent and professional company Perses Ltd hold documental licence under the Management Regulations 1999 on the supply of site specific, hazard elimination risk assessments and method statements et cetera.

PROJECT INFORMATION

PROJECT: Global Switch, Sudlows Office, Saffron Avenue, London, E14 2AX

START DATE: DURATION:

CLIENT: CONTACT:

CONTRACT MANGER: PHONE:

SITE SUPERVISOR: PHONE:

QUANTITY SURVEYOR: PHONE:

HSQE MANAGER: PHONE:

FIRST AID:

DRAWING REFERENCE:

REPORT REFERENCE:

INTRODUCTION

P a g e | 2

Introduction

SCOPE OF WORKS

Location: Global Switch, Sudlows Office, Saffron Avenue, London, E14 2AX

No. of operatives involved: 1-site manager, 1-site supervisor, 2-operatives

Start Date: 28th of August, 2018

Duration: 1-week

PLANT AND EQUIPMENT

Plant and Equipment to be used Pictorial representation

Electric hand tools and:

110V Reciprocating Saw Ø300mm petrol cut-off saw (with metal cutting blade) Electric Tech guns

Hand tools: Sledge Hammer, Roughneck wrecking bar

Aluminium Scaffold Tower

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 3

Internal Soft Strip of the structure

TASK METHOD

SAFETY HOLD POINT

Only authorised personnel will be permitted to carry out these works.

The supervisor will ensure that an exclusion zone is established as per Section-13 of BS 6187:2011 Code of Practice for Full and Partial Demolition and DRG 110: National Federation of Demolition Contractors (NFDC) guidance not for exclusion zones is in place to maintain safe working zone around all working areas before works are permitted to progress.

SITE SUPERVISOR/MANAGER SIGNATURE DATE

• Operatives will approach the walls showing extreme care.

• Operatives working from the return end will insert the strong boy props under the timber door jamb. The operatives

will introduce the prop below the door frame/ stud section, gently tightening the prop to transfer the load to the

ground. (The strong boy props will take a load of 340kgs. Plasterboard weight is 16kg per m2 for double skinned

12.5 mm board.)

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 4

• Operatives will work towards the cut end installing the strong boys at each of the cut c-stud ends taking care to

ensure the load remains linear with straight load path.

• Access to height will be gained by a PASMA tower built by competent person with an up to date certification of

competence, floors will be boarded out where required.

SAFETY HOLD POINT

Only access to height required will be gained through the use of a temporary alloy scaffold tower which will be constructed by a P.A.S.M.A. trained operative.

SITE SUPERVISOR/MANAGER SIGNATURE DATE

• Operatives will approach the working area showing extreme care.

• Operatives will be working from the fixed end using battery operated/electrical screw guns drill *8x4 (Or equivalent)

25mm boarding onto the plaster board wall at 300mm from the floor level to above the cut line to re-secure the c-

studs.

SAFETY HOLD POINT

Ensure all props are in place prior to works progressing.

SITE SUPERVISOR/MANAGER SIGNATURE DATE

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 5

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 6

SAFETY HOLD POINT

Ensure all sections are secured before the works advance.

SITE SUPERVISOR/MANAGER SIGNATURE DATE

• If required further screws will be fixed at closer intervals.

• Operatives using hand tools (Electric reciprocating saws) will, working from the PASMA towers cut into small

sections at the supporting clips and remove the cable trays to provide access to the walls.

2

3

1

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 7

• Operatives, starting from the cut end using electrical reciprocating saws cut the plaster boards sheets at the point

between the c-studs to reduce the weight of the sections dropping the plaster to the floor.

• Once the plaster has been removed the c-stud sections will be cut and dropped to the ground. Once the sections has

been removed the ceiling channel will be cut and dropped before moving onto the next section.

• Operatives will follow on the method detailed in phase 2.

1

2

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 8

3

4

5

6

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 9

SAFETY HOLD POINT

Check wall for movement before works commence.

SITE SUPERVISOR/MANAGER SIGNATURE DATE

SAFETY HOLD POINT

Only access to height required will be gained using a temporary alloy scaffold tower which will be constructed by a P.A.S.M.A. trained operative.

SITE SUPERVISOR/MANAGER SIGNATURE DATE

• Operatives will remove the plaster board sections across the wall line moving from the free end to the fixed end to

ensure structural stability. The plaster will only be removed down to timber sheeting.

• Once the upper plaster is removed the operatives will cut the lower sections including the timber sheets before

removing the c-stud.

7

8

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 10

1

2

3

4

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 11

5

6

7

8

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 12

• Operatives will follow the method set out in the previous phase.

9

10

11

12

INTERNAL SOFT STRIP OF THE STRUCTURE

P a g e | 13

• As the plaster work is supported by the galvanised ducting no further support work is required.

• Operatives will gain access via PASMA tower.

• Operatives, using electrical reciprocating saws, will cut the plaster board from the end still infilled with plaster

working towards the open end systematically reducing the weight as the frame and c-studs are exposed.

• Once the c-studs are exposed the steel frame work will be cut out and dropped to the floor.

• Operatives will cut out any further unsupported sections following the same method until the site if returned to a

safe condition.

PERSONAL PROTECTIVE EQUIPMENT

P a g e | 14

Personal Protective Equipment

SYMBOL TYPE STANDARD WHEN IT SHOULD BE WORN

Hard hat BS EN 397 BS EN 812

397: At all times while on site 812: Bump caps for vehicles drivers and fitters

Safety footwear BS EN 20345

At all times while on site

Hi Vis clothing BS EN 20471 Class-2 required at all times while on site. Class-3 will be required for working near or on a dual-carriageway with a speed of 50MPH or above, motorways, airports, and railways.

Safety glasses BS EN166 A BS EN166 B BS EN166 4

At all times while on site. Impact goggle to a category A standard will be required when using an abrasive wheel cutting saw. 166 4: For general protection from dust.

Gloves BS EN 420 BS EN 388 BS EN 407 BS EN 511

388: 2.1.2.1 For light duties handling materials 388: 3.3.3.3 For hand demolition works 388: 4.5.4.4 For puncture and cut protection 407 For thermal hazards such as hot works. 511 For cold weather conditions

Ear defenders EN 352 When working adjacent to abrasive wheels or breakers, or sources of significant noise output based on the task specific risk assessment

Harness BS EN 363 Fall arrest lanyard at all times when working at height Fall restraint during the hand works from the cherry picker.

Overalls EN 340 EN 381 EN ISO 11612

340: For general working 381: When working with chainsaws 11612: When carrying out hot works

Half mask EN 140 EN 143

FPP3 Filter when working with Cat-B asbestos

Disposable mask EN 149 FPP2 filter disposable mask for light duties.

LEGISLATION AND STANDARDS

P a g e | 15

Legislation and standards All works will be carried out in full compliance, where reasonably practicable with the following articles:

LEGISLATION

✓ The Health and Safety at Work Act 1974,

✓ The Road Traffic Acts, 1972 and 1974,

✓ The Control of Pollution Act, 1974, and

✓ Environmental Protection Act 1990 (amended Scotland 2001).

REGULATIONS

✓ The Health & Safety (First Aid) Regulations 1981,

✓ The Road Vehicles (Construction and Use) Regulations 1986,

✓ The Electricity at Work Regulations 1989,

✓ The Personal Protective Equipment Regulations 1992,

✓ Workplace Health & Safety Welfare Regulations 1992,

✓ The Manual Handling Operations Regulations 1992 (MHR) (As amended 2002),

✓ The Building Standards (Scotland) Regulation 1994,

✓ The Health & Safety (Consultation with Employees) Regulations 1996,

✓ The Safety Signs and Safety Signals Regulations 1996,

✓ Construction (Health, Safety and Welfare) Regulations 1996,

✓ Confined Space Regulations 1997,

✓ The Waste Management (Licensing) Regulations 1998,

✓ The Provision and Use of Work Equipment Regulations (PUWER) 1998,

✓ The Lifting Operations and Lifting Equipment Regulations (LOLER) 1998,

✓ The Management of Health and Safety at Work Regulations (MHSWR) 1999,

✓ The Control of Lead at Work Regulations 2002,

✓ The Special Waste Amendment (Scotland) Regulations 2004 (& Special Waste Regulations 1996),

✓ The Regulatory Reform (Fire Safety) Order 2005,

✓ The Control of Vibration at Work Regulations 2005,

✓ The Control of Noise at Work Regulation 2005,

✓ Working at Height Regulations 2005 (As amended 2007),

✓ The Control of Asbestos Regulations 2012,

✓ Control of Substances Hazardous to Health (CoSHH) 2002 (As amended 2013),

✓ The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations (RIDDOR) 1995 (As amended 2013), and

✓ The Construction (Design and Management) Regulations (CDM) 2015.

BRITISH STANDARDS

✓ BS 5228-1:2009+A1:2014 Code of practice for noise control on construction and open sites,

✓ BS 5228-2:2009+A1:2014 Code of practice for vibration control on construction and open sites,

✓ BS 5607:1998 Code of practice for safe use of explosives in the construction industry,

✓ BS 5975:2008+A1:2011 Code of practice for temporary works, and

✓ BS 6187:2011 Code of practice for full and partial demolition.

NATIONAL FEDERATION OF DEMOLITION CONTRACTORS GUIDANCE

✓ DRG 012 - NFDC guidance note for Construction (Design and Management) Regulations (CDM) 2015,

✓ DRG 100 - NFDC guidance note for safe use of mobile crushers in demolition,

✓ DRG 101 - NFDC guidance note for high reach demolition rig guidance notes,

✓ DRG 102 - NFDC guidance note for guidance for deconstruction of tower blocks,

✓ DRG 103 - NFDC guidance note for work with non-licensed asbestos containing materials,

✓ DRG 104 - NFDC guidance note for demolition attachments,

✓ DRG 105 - NFDC guidance note for temporary works overview,

✓ DRG 106 - NFDC guidance note for scaffolding for demolition and structural refurbishment,

LEGISLATION AND STANDARDS

P a g e | 16

✓ DRG 107 - NFDC guidance note for termination of services,

✓ DRG 108 - NFDC guidance note for waste and permitting,

✓ DRG 109 - NFDC guidance note for DRIDS, and

✓ DRG 110 - NFDC guidance note for exclusion zones.

INSTITUTION OF CIVIL ENGINEERS GUIDANCE

✓ The Institute of Civil Engineers Manual of Health and Safety in Construction 2010,

✓ The Institute of Civil Engineers Manual of Health and Safety in Construction 2015 (second edition), and

✓ The Institute of Civil Engineers Temporary Works: Principals of Design and Construction.

OTHER:

✓ HSG 189/1 - Controlling Asbestos Stripping Works,

✓ HSG 189/2 - Working with Asbestos Cement.

Which are withdrawn but may be used as a reference.

DECLARATION

P a g e | 17

Declaration

I HEREBY DECLARE THAT I HAVE READ, FULLY UNDERSTOOD AND AGREE TO COMPLY WITH THIS METHOD STATEMENT.

Name: Signature: Date:

ALTERATIONS TO METHOD STATEMENT:

Name: Signature: Date: Alterations made/page number:

I HEREBY DECLARE THAT I HAVE READ, FULLY UNDERSTOOD AND AGREE TO COMPLY WITH THIS REVISED METHOD

STATEMENT.

Name: Signature: Date:

CONTRACTOR COMPLETION SIGN OF SHEET

P a g e | 18

Contractor Completion Sign of Sheet

Completion date:

Client: Sudlows Ltd

Project: Global Switch, Sudlows Office, Saffron Avenue, London, E14 2AX

Please mark one of the following:

I AM HAPPY WITH THE COMPLETION OF THIS PROJECT.

or

I HAVE REVIEWED THE PROJECT AND WOULD TO MAKE THE FOLLOWING CHANGES.

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

FOR AND ON BEHALF OF SUDLOWS LTD.

SIGNATURE

DATE

AGENT’S NAME

FOR AND ON BEHALF OF COMPLETE DEMOLITION LTD:

SIGNATURE

DATE