16
AUSTRALIA BUSINESS UNIT EAST AUSTRALIA PACIFIC LNG FACILITY Safety Case Summary Operated by Australia Pacific LNG Facility, Curtis Island, Queensland

safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

AustrAliA business unit eAst

AUSTRALIA PACIFIC LNG FACILITY

safety Case summary

Operated by

Australia Pacific lnG Facility, Curtis island, Queensland

Page 2: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

2

AUSTRALIA PACIFIC LNG Safety Case Summary

Table of ContentsMessage from the Australia Pacific lnG Facility Operations Manager

Glossary

Australia Pacific lnG

introduction

Australia Pacific lnG Facility

schedule 15 Chemicals and Other Hazardous Materials

safety Assessment

Control Measures

Health, safety and environmental Management system

emergency response

Further information

6

5

4

3

7

9

10

11

12

14

15

Page 3: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

3

AUSTRALIA PACIFIC LNG Safety Case Summary

Message from the Australia Pacific LNG Facility Operations Manager

in keeping with our corporate values and those of our joint venture shareholders, ConocoPhillips Australia considers safety as our number one priority and we are committed to protecting the health and safety of all our employees and visitors as well as everyone in the communities in which we operate. We believe accidents are preventable and, as such, all operations occurring at the Australia Pacific lnG Facility on Curtis island as well as our mainland facilities in Gladstone are undertaken in a manner that ensures all practicable and reasonable steps are taken to reduce risks to health and safety.

Historically, the lnG industry has enjoyed an enviable safety record since its inception around 70 years ago with very few fatal incidents having occurred globally. Along with ConocoPhillips Australia’s considerable industry experience, the lessons learned from these prior incidents within the industry have been recognised and applied to the Australia Pacific lnG Facility, such as the use of materials designed for the low temperatures involved in lnG production, storage and export.

As required under Queensland work health and safety regulation, ConocoPhillips Australia conducted a comprehensive safety assessment prior to the start of operations at the Australia Pacific lnG Facility. the assessment was focussed on identifying hazards and potential adverse incidents and assessing the risk they pose to our employees and visitors and members of the community. Control measures based on the design and operating experience of ConocoPhillips Australia and the Australia Pacific lnG joint venture shareholders and the knowledge captured in modern lnG design standards and codes have been identified, assessed and implemented.

As part of our continuous improvement processes, we constantly monitor and review our health, safety and environmental performance and strive for excellence across all areas of our business and operations.

ConocoPhillips Australia values the communities within which we operate and we are committed to engagement that extends beyond compliance with applicable regulations. this document, the Australia Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG Facility and its operations and the measures ConocoPhillips Australia have implemented as operator of the facility to ensure our goal of zero accidents is achieved.

Charles McWattie

Australia Pacific lnG Facility Operations Manager

Page 4: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

4

AUSTRALIA PACIFIC LNG Safety Case Summary

Australia Pacific LNG

incorporated joint venture between Origin (37.5%), ConocoPhillips Australia (37.5%) and sinOPeC (25%).

Australia Pacific LNG Facility

liquefied natural gas production and export facility located on Curtis island, Queensland. the facility receives coal seam gas from Australia Pacific lnG ’s gas fields and liquefies the gas through

refrigeration for export.

Australia Pacific LNG Project

integrated coal seam gas to liquefied natural gas project involving the development of gas fields and construction of a gas transmission pipeline and lnG production and export facility.

Coal Seam Gas (CSG)

Coal seam gas is a naturally occurring gas (primarily methane) found in coal deposits. both the coal and the coal seam gas are formed from plant matter under pressure for millions of years. the coal seam gas collects in underground coal seams by bonding to the surface of coal particles. the coal seams are generally filled with water which exerts pressure keeping the coal seam gas as a

thin film on the surface of the coal.

ConocoPhillips Australia

Operator of the Australia Pacific lnG Facility on behalf of the Australia Pacific

lnG joint venture shareholders.

Consequence

the outcome of an incident expressed either quantitatively or qualitatively, as

loss, injury, disadvantage or gain.

Control Measure

Measures implemented at the Australia Pacific lnG Facility for prevention or mitigation of incidents. these measures reduce the likelihood of incidents occurring and/or the magnitude of the

consequences should an incident occur.

Health, Safety and Environmental Management System (HSEMS)

the documented, integrated system used within ConocoPhillips Australia to manage all facets of risks to health and the safety of people and the environment from activities at the

Australia Pacific lnG Facility.

Hazardous Industry and Chemicals Branch (HICB)

the regulator of major hazard facilities in Queensland. HiCb is part of the Queensland Government’s Department of Justice and Attorney General.

Likelihood

A description of the probability and frequency of an event occurring.

Community

the area surrounding the Australia Pacific lnG Facility on Curtis island in which the health and safety of people could be adversely affected by a major incident.

Loss of Containment

the unintended release of a material such as lnG to the environment.

Major Hazard Facility (MHF)

A facility at which materials listed in schedule 15 of the Work Health and Safety Regulation 2011 are present or likely to be present in quantities above

defined threshold levels.

Major Incident

An uncontrolled occurrence at the Australia Pacific lnG Facility, including an escape, spillage or leakage or implosion, explosion or fire that:

• involves a chemical listed under schedule 15 of the Work Health and Safety Regulation 2011;

• exposes a person to a serious health and safety risk emanating from an immediate or imminent exposure to

the occurrence.

Major Incident Hazard

Any potential physical or chemical process, procedure or circumstance which could result in a potential major

incident occurring.

Risk

the product of the likelihood of a potential major incident occurring and the severity of the associated consequences to people at and surrounding the Australia Pacific lnG Facility.

Safety Assessment

A comprehensive and systematic process involving the identification of major incident hazards and potential major incidents, an assessment of the associated risks, identification and analysis of suitable control measures and assessment that risks have been reduced

‘so far as is reasonably practicable’.

Safety Case

A document required under the Queensland Work Health and Safety Regulation 2011 that demonstrates that the potential hazards and major incidents that could occur at an MHF have been identified, assessed and understood and appropriate control measures implemented to reduce the risks of a major incident so far as

reasonably practicable.

Schedule 15 Chemical

A material listed under schedule 15 (table 15.1, 15.2 and 15.3) of the Work Health and Safety Regulation 2011. in general, schedule 15 chemicals are considered hazardous due to their properties such as flammability, combustibility and toxicity. At the Australia Pacific lnG Facility, three materials listed under schedule 15 are present (propane, ethylene and

methane).

‘So far as is reasonably practicable’ (SFARP)

the measure of risk after implementation of control measures that eliminate or reduce risks ‘so far as is reasonably practicable’. ConocoPhillips Australia continues actions to eliminate or reduce risks until the effort expended is grossly disproportionate to the benefit that is gained.

Work Health and Safety Regulation 2011 (WHS Regulation)

Primary legislative instrument governing workplace health and safety in Queensland, including at major hazard facilities such as the Australia Pacific lnG Facility.

Glossary

Page 5: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

AUSTRALIA PACIFIC LNG Safety Case Summary

5

Australia Pacific lnG is Australia’s leading producer of CsG, supplying the gas to power stations for generation of low emissions electricity as well as industrial, commercial and residential customers throughout southeast Queensland. As part of the Australia Pacific lnG Project which was undertaken to deliver a cleaner, greener sustainable energy source, Australia Pacific lnG further developed gas fields located in the surat and bowen basins in southwest and central Queensland and constructed an lnG production and export facility on Curtis island (the Australia Pacific lnG Facility) as well as a 362 kilometre gas transmission pipeline connecting the gas fields to the lnG plant.

Origin is responsible for operation of the gas fields and gas transmission pipeline (upstream assets) on behalf of Australia Pacific lnG while a subsidiary of ConocoPhillips, ConocoPhillips Australia, is responsible for operating the Australia Pacific lnG Facility and its associated infrastructure (downstream assets). the CsG transported to

the Australia Pacific lnG Facility via the pipeline is cooled at the facility to -161°C and becomes a liquid (lnG). the Australia Pacific lnG Facility has an initial capacity of up to 9 million tonnes per annum (Mtpa) of lnG which will be produced by two identical production ‘trains’ and exported to customers via purpose-built lnG carriers.

Major customers of the lnG produced at the Australia Pacific lnG Facility include sinOPeC who entered a 7.6 Mtpa lnG off-take agreement with Australia Pacific lnG for 20 years and Kansai electric Power Company who entered a 1 mtpa lnG off-take agreement, also for 20 years.

As operator of the Australia Pacific lnG Facility, ConocoPhillips Australia is committed to ensuring all operations at the facility are conducted in a safe, healthy and environmentally responsible manner. As part of this commitment, ConocoPhillips Australia addresses hazards and associated risks at the facility until risks are reduced so far as is reasonably practicable.

Australia Pacific LNG is a coal seam gas (CSG) to liquefied natural gas (LNG) incorporated joint venture between three industry leaders: Origin (37.5%), ConocoPhillips (37.5%) and Sinopec (25%).

Origin is Australia’s largest integrated energy company with activities spanning gas exploration and production to power generation and energy retailing and has been operating in the Australian CSG industry for 15 years.

ConocoPhillips is one of the world’s largest CSG operators with over 25 years’ experience in CSG development and more than 40 years in LNG production, including at the Darwin LNG Facility from 2006.

The third Australia Pacific LNG joint venture partner, China Petrochemical Corporation (Sinopec), is one of China’s largest crude oil and natural gas producers and suppliers of petroleum products and its activities include exploration, production, storage, transportation and distribution of petrochemical products.

Australia Pacific LNG

25%

Integrated energy and chemical company. One of China’s largest petroleum

products suppliers and crude oil and natural gas producers.

37.5%

Energy company with global operations. One of

the world’s largest CSG operators with over 25

years’ experience.

Domestic contracts

37.5%

Australia’s largest integrated energy company. Listed in

S&P/ASX 20 index.

UpstreamOperated by Origin. Long history of

CSG production in Australia, complemented by ConocoPhillips’ 25

years of CSG experience.

DownstreamOperated by ConocoPhillips. 40 years’ LNG experience. Owner of Optimised Cascade® Process LNG technology. Using ConocoPhillips technology license, Bechtel has

delivered eight LNG trains globally.

Developer of CSG to LNG project based on Australia’s

largest CSG 2P Reserves base.

7.6 mtpa LNG off-take agreement for 20 years.

1 mtpa LNG off-take agreement for 20 years.

Page 6: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

6

AUSTRALIA PACIFIC LNG Safety Case Summary

under the Queensland Work Health and Safety Regulation 2011, facilities that handle, process or store certain hazardous chemicals in quantities above defined threshold amounts are deemed as MHFs and subject to specific regulation and requirements. three such hazardous chemicals (known as schedule 15 chemicals as they are listed along with threshold quantities in schedule 15 of the Work Health and Safety Regulation 2011) are present at the Australia Pacific lnG Facility in excess of threshold quantities.

typically, schedule 15 chemicals are considered hazardous due to their physical and chemical characteristics such as flammability, combustibility or toxicity, low or high temperatures or pressures and their potential to cause a major incident. under the Work Health and Safety Regulation 2011, a major incident is defined as an uncontrolled occurrence, including an escape, spillage or leakage or implosion, explosion or fire that involves a schedule 15 chemical and exposes a person to a serious health and safety risk emanating from exposure to the uncontrolled exposure.

the Queensland MHF regulator, the Hazardous industries and Chemicals branch (HiCb) of the Queensland Department of Justice and Attorney-General, has determined the Australia Pacific lnG Facility as an MHF. there are a number of other MHFs in the Gladstone region including other lnG facilities also located on Curtis island (Queensland Curtis lnG and Gladstone lnG) and the Orica Australia chemical plant and Origin energy liquefied petroleum gas terminal on the mainland near Gladstone.

Introduction

The Australia Pacific LNG Facility uses three hazardous materials regulated under the Queensland Work Health and Safety Regulation 2011 in amounts above legislated threshold quantities. Accordingly, the facility has been determined as a major hazard facility (MHF) by the Queensland MHF regulator and subject to the relevant requirements of the Work Health and Safety Regulation 2011. Examples of MHFs include oil and gas processing facilities, refineries, chemical manufacturing sites and some warehouses and transport depots. This document, the Australia Pacific LNG Safety Case Summary, is intended to provide the community with information on the Australia Pacific LNG Facility and its operations, the hazards present and major incidents that could occur as well as a summary of the Australia Pacific LNG Facility Safety Case submitted to the MHF regulator.

As the ‘operator’ of a determined MHF, ConocoPhillips Australia is required to submit a facility ‘safety Case’ to the MHF regulator as part of the licensing process and approval to operate. the safety Case is a written document that provides a comprehensive overview of the way in which ConocoPhillips Australia manages the risks associated with operation of the Australia Pacific lnG Facility. the safety Case documents the facility and its systems and equipment, the safety management systems and control measures that are in place and the safety assessment that was undertaken to ensure that all risks at the facility are identified, assessed and reduced so far as is reasonably practicable prior to and continuously throughout operations.

the safety Case has been developed in consultation with community residents, community organisations, local, state and federal government departments, local industry and business representatives, emergency services and medical providers and ConocoPhillips Australia employees. similarly, consultation has taken place with relevant parties during development of the facility’s emergency response and security management plans. Competent and experienced ConocoPhillips Australia employees and contractors are actively involved in the development of operating and maintenance procedures as well risk assessments, inspections and audits.

this document, the Australia Pacific lnG Facility safety Case summary, is intended to provide the community surrounding the Australia Pacific lnG Facility with information as detailed in the safety Case including the major hazards present at the facility, the credible major incidents that could occur, the control measures in place to prevent or mitigate major incidents and the actions that would be taken by ConocoPhillips Australia should such an event occur. Although the facility is located remotely, away from residential dwellings, and any credible incident is extremely unlikely to impact any offsite persons, information on what actions should be taken by the community in the event of an incident occurring is included.

As part of ConocoPhillips Australia’s continuous improvement processes, the safety Case and the safety assessment are reviewed and updated as required. Any changes to the safety Case and safety assessment will be considered for inclusion in subsequent revisions of this summary document to ensure it continues to provide an accurate reflection of ConocoPhillips Australia and the Australia Pacific lnG Facility.

Page 7: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

7

AUSTRALIA PACIFIC LNG Safety Case Summary

the Australia Pacific lnG Facility is located on Curtis island at laird Point, approximately 11 kilometres northeast of the City of Gladstone. the facility is located on an approximately 243 hectare lot situated within the Curtis island industry Precinct which is an area reserved by the Queensland Government for the establishment of lnG facilities and associated infrastructure. there are no residential dwellings in close proximity to the Australia Pacific lnG Facility; the nearest is approximately 7 kilometres away on the mainland. the facility is neighboured by other CsG to lnG production and export plants: both the Queensland Curtis lnG and Gladstone lnG facilities are situated to the south.

Australia Pacific LNG Facility

The Australia Pacific LNG Facility is a two train LNG production and export facility that utilises ConocoPhillips Optimised Cascade® LNG Process to liquefy CSG to LNG. The facility design utilises ConocoPhillips’ previous experience and knowledge in design of LNG plants and is operated by a workforce competent in discharging their duties in a healthy, safe and environmentally sustainable manner.

the Australia Pacific lnG Facility has a capacity of 9 million tonnes of lnG per year which is produced by two identical, independent production trains and stored temporarily onsite before being loaded onto lnG carriers. the facility includes the necessary utility infrastructure required to support its operations including power generation and distribution, refrigerant storage, water and effluent treatment systems, material offloading and passenger facilities and administration, central control, medical, security and workshop buildings.

the Australia Pacific lnG Facility utilises ConocoPhillips’ Optimised Cascade® lnG technology to liquefy the CsG transported to the facility via the gas transmission pipeline. the ConocoPhillips process, which is in use in a number of lnG plants around the world, uses three refrigerants (propane, ethylene and methane) to chill the CsG to -161°C.

Process trains

lnG storage

Page 8: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

8

AUSTRALIA PACIFIC LNG Safety Case Summary

Australia Pacific LNG Facilityupon arrival at the facility, impurities such as water and carbon dioxide are removed from the CsG before the treated gas is passed through the three successive stages of refrigeration. the lnG product is stored in two 160,000 cubic metre full containment tanks designed to safely and reliably contain the product and loaded onto lnG carriers every two to three days (when both production trains are operating) for export to Australia Pacific lnG ’s customers.

After arriving at its destination, lnG is warmed to return it to its gaseous state and delivered to customers to be used in heating and cooking as well as electricity generation and other industrial/commercial uses. lnG can also be used as an alternative transportation fuel as a liquid.

the Australia Pacific lnG Facility is designed to operate 24 hours per day, 365 days of the year although parts of, or the whole facility, will be periodically shut down to allow maintenance and inspection activities to occur as needed.

the total number of employees present at the facility during normal operations is approximately 195 and is typically a mix of operations, maintenance, management, administration, support and contractor personnel and visitors. Most employees work a day shift of 12-hour duration, although a number of process operators work a 12-hour day/night shift pattern to ensure 24-hour operations and site coverage.

The CSG to LNG Process

Page 9: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

9

AUSTRALIA PACIFIC LNG Safety Case Summary

Schedule 15 Chemicals and Other Hazardous Materials

(present at the facility as CsG and liquid methane (refrigerant and lnG

product); contained in process equipment, piping and lnG storage tanks).

Methane (CH4; un number 1972) is the primary constituent of the CsG supplied to the Australia Pacific lnG Facility. Methane is a colourless, odourless and non-toxic gas which in high concentrations can present a health hazard as it is an asphyxiant which displaces oxygen in the breathable atmosphere. Methane is lighter than air at ambient temperatures and the gas rises and diffuses rapidly in an open space. Methane vapour is flammable and can be ignited where the concentration is within the range of 5 to 15% methane in air.

lnG (liquid methane) is the end product of the facility’s process and is a clear, colourless, odourless and non-toxic liquid. lnG is characterised as a cryogen, which is a liquefied gas kept in its liquid state at very low temperatures (temperature of -161°C). Contact with lnG can cause cold burns or frostbite to exposed tissues, including the lungs if cold vapours are inhaled. When lnG is inadvertently released to the environment (known as a loss of containment), it forms a pool and as it comes in contact with the warmer air and ground, it boils off becoming a visible vapour cloud. As it continues to warm, the vapour cloud (methane in gaseous form) becomes lighter than air and rises. there are approximately 154,000 tonnes of lnG at the facility when considering both lnG storage tank capacities, both production trains and lnG loading lines.

(present at the facility as a liquid refrigerant; contained within process equipment and piping and three refrigerant storage vessels).

Propane (C3H8; un number 1978) is employed in the facility’s process as a refrigerant used to lower the temperature of the CsG. liquid propane is a colourless, cryogenic liquid (temperature of -42°C) which can cause cold burns or frostbite to exposed tissues, including the lungs if cold vapours are inhaled. When released to the environment, propane rapidly boils off into the gas phase, which can present a health hazard in high concentrations

(present at the facility as a liquid refrigerant; contained within process

equipment and piping and three refrigerant storage vessels).

ethylene (C2H4; un number 1962) is also employed in the facility’s process as a refrigerant to lower the temperature of the CsG. liquid ethylene is a colourless, cryogenic liquid (temperature of -103°C) with a slightly sweet odour that can cause cold burns or frostbite to exposed tissues, including the lungs if cold vapours are inhaled. When released to the environment, ethylene rapidly boils off into the gas phase, which can present a health hazard in high concentrations as it is an asphyxiant and displaces oxygen in the breathable atmosphere.

Gaseous ethylene is flammable in the concentration range of 3 to 35% gas in air, is neutrally buoyant and may spread long distances. there are approximately 890 tonnes of ethylene at the facility contained in the refrigeration storage vessels and the ethylene refrigeration circuits for both production trains.

(present in various, minor amounts at the facility).

A number of other materials that are not listed in schedule 15 yet are considered hazardous are used and stored at the facility in minor amounts. these materials include reagents and chemicals used in laboratory analysis such as sulphuric acid, diesel fuel and lubricant oils and certain materials used in the process such as absorbents/adsorbents. Materials considered hazardous are handled, stored, used and disposed of in accordance with the relevant safety Data sheet, manufacturer/supplier recommendations and/or industry good practice.

The Australia Pacific LNG Facility handles and stores a number of substances that are classified as hazardous chemicals under the Work Health and Safety Regulation 2011 (Schedule 15 chemicals) and as flammable or combustible under AS 1940 2004 (The storage and handling of flammable and combustible liquids). Hazard identification and safety assessment studies considered all Schedule 15 and other hazardous materials to ensure that their risks were understood and managed. The following sections summarise the nature of the Schedule 15 chemicals (methane, propane and ethylene) and other hazardous materials handled in support of or during operation of the facility.

Methane

Propane

Ethylene

Other Hazardous Materials

as it acts as an asphyxiant. the gas is heavier than air and may spread long distances. Gaseous propane is flammable in the concentration range of 2 to 10% gas in air. there are approximately 2,600 tonnes of propane at the facility contained in the refrigeration storage vessels and propane refrigeration circuits for both production trains.

Page 10: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

10

AUSTRALIA PACIFIC LNG Safety Case Summary

ConocoPhillips Australia’s safety assessment process involves a range of studies examining aspects of health and safety such as qualitative and quantitative risk assessments, facility layout and building assessments, operability and maintainability reviews and fire and explosion risk analyses. the initial safety assessment process which is documented in the Australia Pacific lnG Facility safety Case identified the hazards present at the facility that could result in a major incident; all of these hazards related to a loss of containment of a schedule 15 chemical followed by ignition.

the major incidents that could occur were also identified (as jet fires, pool fires, flash fires and vapour cloud explosions) and evaluated as remotely possible (occurring less than once every million years) in line with industry codes, standards and good practice as well as the requirements of Queensland’s state Development Assessment Provisions and project approval conditions placed on the facility by the Queensland Coordinator-General.

ConocoPhillips Australia captures and documents safety assessment outputs in hazard and risk registers as well as pictorial hazard-consequence-control diagrams (such as bow-tie diagrams) that provide facility personnel with easy to comprehend graphical hazard, incident and control information and the safety Case. ConocoPhillips Australia ensures all employees and contractors are made aware of, trained in and provided with these hazard/risk control and awareness tools.

Safety Assessment

Prior to commencement of facility operations, ConocoPhillips Australia conducted a comprehensive and systematic assessment of the Australia Pacific LNG Facility which is periodically revised during operations. This assessment, which forms a key component of the Safety Case, focuses on identifying and evaluating major hazards and credible major incidents that could occur at the facility, recommending and assessing risk control measures and evaluating whether risk is reduced so far as is reasonably practicable. The outcome of the safety assessment indicates that the facility’s design and layout and safety features result in risk levels that meet the requirements imposed upon the Australia Pacific LNG Facility by the Queensland Coordinator-General and required under the Queensland State Development Assessment Provisions as well as ConocoPhillips Australia’s corporate requirements.

the location of the Australia Pacific lnG Facility on Curtis island in an area reserved for lnG industrial development and remote from residential populations is such that no credible major incidents were identified during the safety assessment that could impact the community or people outside the facility’s boundaries.

the impact of any major incident involving a release of a schedule 15 chemical and subsequent ignition is likely to be contained within the specific plant area in which it occurs although there is a potential for smoke impact on neighbouring facilities or marine/recreational areas on Curtis island.

the impact of a release of flammable gas from the facility is likely to be localised and contained within the facility’s boundary, dependent upon wind strength and speed and the material released. escalation of an incident from one section of the plant to another is unlikely also due to the separation between the process and utility/storage systems, occupied buildings and the facility boundary and the diversity of control measures such as fire and gas detection and protection and depressurising systems.

Given the intervening terrain and distance between the Australia Pacific lnG Facility and neighbouring lnG facilities and the characteristics of the schedule 15 chemicals, it is unlikely that flammable concentrations of gas would reach or impact upon neighbouring properties. similarly, given the remoteness of the Australia Pacific lnG Facility considering residential populations or public areas, it is also unlikely that a flammable gas or liquid release, even with subsequent ignition would impact the community.

the safety assessment process included a ‘so far as is reasonably practicable’ evaluation in which hazards and control measures were assessed to determine if any additional measures would be practicable to implement, considering the benefit gained and the effort in cost, time and resources. the study concluded that the risks posed by the identified hazards and possible major incidents were reduced to a level considered to meet both ConocoPhillips Australia’s and the Work Health and Safety Regulation 2011 definitions of ‘so far as is reasonably practicable’.

Page 11: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

11

AUSTRALIA PACIFIC LNG Safety Case Summary

Historically, incidents at lnG facilities such as a loss of containment and ignition of a flammable gas or liquid hydrocarbon have occurred for a number of reasons such as inadequate or unsuitable maintenance; failure of components fabricated from materials unfit for their intended purpose; inadequate or absent safety systems of work such as health, safety and environmental management systems and permit to work systems; unnoticed/unanticipated process conditions exceeding design specifications of equipment and materials; and dropped/swinging loads or vehicles/mobile plant colliding with process equipment.

All hazardous materials at the facility, including the schedule 15 chemicals, are processed and stored in equipment and piping specifically designed for the temperatures and pressures involved. the facility utilises integrated process control systems to ensure the process is monitored and maintained within the design operating conditions of the equipment and facility operators are aware of the status of critical plant and equipment.

the facility is equipped with a diverse range of control measures designed to prevent and minimise the consequence of major incidents and limit escalation. Control measures are consistent with industry good practice and ConocoPhillips Australia’s operating experience. Control measures in place at the facility to prevent major incidents occurring include the Health, safety and environmental Management system,

Control Measures

The Australia Pacific LNG Facility has a range of measures in place to prevent the occurrence of or minimise the consequences of major incidents. ConocoPhillips Australia implements control measures based on a hierarchy of controls in which the strongest or most effective control measure such as elimination of the hazard is utilised wherever feasible. ConocoPhillips Australia continues to treat risks until they are reduced so far as is reasonably practicable using a diversity of controls including hardware, software, procedural and administrative controls. Emergency shutdown, isolation and relief systems have been strategically installed throughout the facility to limit the effects of incidents and prevent escalation. Wherever Schedule 15 chemicals are handled, processed or stored, there are extensive fire and gas detection and alarm systems and firefighting equipment such as fire hydrants, fire hoses, sprinklers, hand-held extinguishers and gaseous extinguishing systems.

equipment inspection strategies and schedules, change approval processes, computerised trip and alarm systems, standard operating and maintenance procedures, permit to work systems and employee training and competency processes.

the facility also has a range of controls in place to ensure that if a major incident occurs, it is detected and controlled quickly to minimise its severity and prevent escalation to other sections of the facility. such controls include fire and gas detection systems, safety equipment, site alarms, fixed firefighting systems and devices and emergency shutdown and depressurisation systems. the last two function to allow the whole facility or sections of the facility to be brought to a safe and steady state from which it can be safely restarted and operations resumed. this is supplemented by the facility’s emergency response plans and emergency resources which are designed to quickly and safely manage and resolve emergency situations and facilitate return of the facility to a safe operating state.

Facility personnel are trained and assessed as competent to discharge their duties safely and contractor personnel are held to the same standards.

As the Australia Pacific lnG Facility is a significant asset, it is protected from security threats by a network of security features managed under a security management plan. the marine facilities (materials offloading facility) are similarly equipped with security provisions as required under commonwealth maritime acts and regulations.

Fire and Gas Detection System

this system comprises fire and gas detectors and manual alarm call points located strategically throughout the facility and buildings (and particularly where schedule 15 chemicals are processed or stored) that report to a computerised system, capable of executive actions dependent on the extent of detection. these actions include the automatic shutdown of equipment and production facilities and the initiation of visual and audible alarms to alarm personnel and fire suppression systems. All fire and gas system information including alarms are displayed within the facility’s Central Control room where plant operators are fully aware of plant status to allow appropriate actions to be taken.

Page 12: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

12

AUSTRALIA PACIFIC LNG Safety Case Summary

Health, Safety and Environmental Management System

ConocoPhillips Australia has developed and implemented an integrated Health, Safety and Environmental Management System (HSEMS) to manage health and safety performance and continuous improvement at the Australia Pacific LNG Facility.

The HSEMS, which is based upon widely recognised, international health and safety management system standards, draws upon the operational experience gained by ConocoPhillips at similar LNG facilities over many years and ensures that the Australia Pacific LNG Facility is operated and maintained in a safe and environmentally sound manner and in compliance with ConocoPhillips standards and applicable laws and regulations.

ConocoPhillips Australia’s HseMs is a structured and documented framework under which health, safety and environmental risks are identified and managed. the HseMs, which is a major control measure at the facility, is consistent with international management standards As/nZs isO 4804:2001 (Occupational health and safety management systems – General guidelines on principles, systems and supporting techniques) and As/nZs isO 14001:2004 (Environmental management systems – Specification with guidance for use). similar to these standards, the HseMs has adopted continuous improvement as a fundamental principle which is achieved by following a Plan, Do, Assess and Adjust (PDAA) methodology.

ConocoPhillips Australia plans the activities required to meet desired levels of health and safety performance and implements the necessary activities and resources to do the activities. throughout this process, an assessment is undertaken to monitor and confirm conformance with ConocoPhillips Australia’s required standards of performance and to identify any areas of non-compliance or potential improvement. these findings facilitate the adjustments necessary to continuously improve performance and feedback actions to the next planning phase.

ConocoPhillips Australia has organised the underlying components of the HseMs into discrete elements, each aligned with a phase of the PDAA methodology and designed to manage aspects of health and safety performance and reduce risks as far as practicable.

the HseMs includes policies and standards defining ConocoPhillips Australia’s approach to managing health and safety within the company and at the Australia Pacific lnG Facility, identifies responsibilities and accountabilities and establishes processes and procedures for the assessment and management of hazards and associated risks. the HseMs incorporates targets and objectives by which Hse performance is monitored and assessed and provides feedback mechanisms that ensure appropriate corrective actions are identified and implemented.

the HseMs also includes proven and contemporary safe systems of work including operating and maintenance procedures, permit to work systems, management of change and asset and operational integrity processes, employee awareness, training and competency processes and emergency response.

ConocoPhillips Australia investigates and reports incidents and near misses to ensure appropriate lessons can be learned and corrective actions identified and implemented to prevent recurrence.

the HseMs is subject to ongoing audit, both internally and externally, as part of ConocoPhillips Australia’s commitment to continuous improvement in Hse performance and to ensure it continues to adequately control and monitor risks at the Australia Pacific lnG Facility.

Page 13: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

13

AUSTRALIA PACIFIC LNG Safety Case Summary

The HSEMS has adopted continuous improvement as a fundamental principle

which is achieved by following a Plan, Do, Assess and Adjust (PDAA) methodology.

Page 14: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

14

AUSTRALIA PACIFIC LNG Safety Case Summary

to manage adverse and unwanted incidents at the Australia Pacific lnG Facility, ConocoPhillips Australia utilises a comprehensive emergency response and preparedness plan supported by adequate emergency response resources and personnel. the emergency plans have been developed in consultation with local emergency services such as the Queensland Fire and rescue service and medical service providers such as local and regional hospitals. ConocoPhillips updates its emergency response plans where applicable in response to incidents and learnings, industry contemporary practices and changes to the facility, emergency response resources or the regulatory environment.

in the event of an emergency situation occurring at the Australia Pacific lnG Facility, the appropriate emergency response is activated by ConocoPhillips Australia as determined by the nature of the incident, its severity and the resources required for its safe and effective management and resolution. ConocoPhillips Australia regularly conducts emergency response and evacuation drills to test emergency plans and ensure a timely, efficient and effective response can be mounted by emergency response teams at the facility should it ever be needed.

On-site emergency response resources include a highly trained emergency response team and fire fighting and emergency response equipment with a number of site-based employees trained in first aid and firefighting. in the event of an incident, the facility’s emergency response team provides an initial rapid response which is supported by external emergency services as

Emergency Response

ConocoPhillips Australia has a comprehensive emergency response plan developed for the Australia Pacific LNG Facility in consultation with local authorities, local emergency services, Queensland Health, neighbouring LNG facilities and the major hazard facility regulator. The emergency response plan has been developed to effectively respond to any emergency situation that adversely impacts on the health and safety of people, the environment and property. This plan ensures that this adverse impact is minimised and the facility is returned to normal, safe operations as quickly as possible.

required by the situation. resources are available from neighbouring lnG facilities on a mutual aid basis.

A facility-wide emergency alarm system comprising audible and visual alarms at strategic points facilitates early warning of a major incident or potential incident and evacuation of potentially hazardous areas. During facility operation the warning systems are tested regularly and where required.

if an incident occurs at the facility, an alarm will sound to alert everyone within the facility and surrounding areas that there is an emergency event occurring. if the alarm is heard, there are no actions to be taken by the community as there is no credible off-site potential for harm to the public. As people may be undertaking activities nearing the waterfront or in the conservation areas on Curtis island and to ensure the community is informed, the public will also be notified of an emergency event via the local emergency services and radio and television stations.

in the extremely unlikely event the community needs to take action during a major incident or be made aware of any potential disruptions such as marine restrictions, the local Disaster Management Group consisting of representatives from the Gladstone Council, Queensland Police, Fire, Ambulance and ses will broadcast information and advice via electronic means such as social media, radio and sMs alerts. the community will also be informed when the event is over.

Page 15: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG

AUSTRALIA PACIFIC LNG Safety Case Summary

15

Further InformationCopies of the Australia Pacific LNG Facility Safety Case Summary have been distributed to the Gladstone Regional Libraries, the Gladstone Regional Council as well as the major hazard facility regulator. It is also available on the Australia Pacific LNG and ConocoPhillips Australia websites and at the Australia Pacific LNG Community Centre in Gladstone. Other opportunities to review the Australia Pacific LNG Facility include information sessions/public presentations held by ConocoPhillips Australia.

MORE ABOUT AUSTRALIA PACIFIC LNG, THE AUSTRALIA PACIFIC LNG PROJECT AND THE AUSTRALIA PACIFIC LNG FACILITY

MORE ABOUT THE MAJOR HAZARD FACILITY REGULATOR AND THE WHS REGULATION

MORE ABOUT CSG AND LNG

Visit our website at

www.conocophillips.com.au

Visit Australia Pacific LNG’s website at

www.aplng.com.au

Contact us on 1300 776 205

Write to us at

[email protected]

Ask us a question about Australia Pacific LNG or the Australia Pacific LNG Project at

[email protected]

Visit the Australia Pacific LNG Community Centre at

84 Goondoon St, Gladstone

Queensland Workplace Health and Safety

www.deir.qld.gov.au/workplace/index.htm

Queensland Work Health and Safety Regulation 2011

www.legislation.qld.gov.au

Major Hazard Facilities in Queensland

www.deir.qld.gov.au/workplace/ major-hazard-facilities/index

Major Hazard Facilities in Queensland

www.worksafe.qld.gov.au/injury-prevention-safety/workplace-hazards/major-hazard-facilities-mhf

Safety Case Guides

www.safeworkaustralia.gov.au/sites/swa/whs-information/mhf/pages/mhf

Coal Seam Gas

www.aplng.com.au/about-project/about-csgf

Liquefied Natural Gas

www.aplng.com.au/about-project/about-liquefied-natural-gas

Robert Gibb, Community relations Manager

Australia Pacific LNG Downstream Project, ConocoPhillips Australia Pty Ltd (07) 4836 7610 | [email protected]

In case of an emergency call 000

Page 16: safety Case summary - Index | Australia Pacific LNG · Pacific lnG Facility safety Case summary, is intended to provide the community with information on the Australia Pacific lnG