Sacramento City College Sacramento City College Facilities Master Plan Facilities Master Plan Update Update Options, opportunities and considerations for Capital Projects • Projects funded with State and Local (Measure A & M) Bond Funds and other campus generated funds (e.g. Foundation) • Scope and Schedule of planned projects

Sacramento City College Facilities Master Plan Update

Embed Size (px)

DESCRIPTION

Sacramento City College Facilities Master Plan Update. Options, opportunities and considerations for Capital Projects Projects funded with State and Local (Measure A & M) Bond Funds and other campus generated funds (e.g. Foundation) Scope and Schedule of planned projects. - PowerPoint PPT Presentation

Citation preview

Sacramento City CollegeSacramento City CollegeFacilities Master Plan UpdateFacilities Master Plan Update

• Options, opportunities and considerations for Capital Projects• Projects funded with State and Local (Measure A & M) Bond Funds and other campus generated funds (e.g. Foundation)• Scope and Schedule of planned projects

Facility ProjectsFacility ProjectsReference: Facility Resource PlanReference: Facility Resource Plan

• Emergency / routine maintenance and repair and improvement—same year funding

• Facility projects—unit/program plan, ‘next’ year funding through budget planning process

• Modernization / New Construction – Capital Outlay or Bond Projects

• Both state and local bond funding +++

– Future Year Planning—Facilities Road Map

• Other Remodel / Backfill Construction– Unit or Program Plans may cover– College funding needed– May result from Capital / Bond projects as backfill

Facilities Master PlanFacilities Master PlanBackgroundBackground

• Original plan worked in 2003-04 after Measure A was passed (Nov 2002; LRCCD $265M)– Briefed to BOT for Approval in June 2004

• Updates to Citizen’s Bond Oversight Committee on a quarterly basis—excellent LRCCD track record

• Measure M driving this update (Nov 2008; LRCCD $475M)– Initial project proposals formulated as part of bond game plan– Multiple iterations of project proposals starting June ‘06

• SKW Architects retained for this update– Integrate state AND local bond funding and ‘other’ where

applicable– Architect for original master plan– Utilizing/updating original plan considerations– Structural limitations, building age/competitiveness, bond funding

ROE • Proposed Master Plan now ready for campus review—

interesting puzzle with several open issues

‘‘Eligible’ Assignable Square Feet (ASF)Eligible’ Assignable Square Feet (ASF)

• Annual update by FM of College Capacity-Load Ratios (Five-Year Construction Plan)– Capacity: ASF; Load: Projected Enrollment– Formula and analysis to compute, but still a moving target

• Key factor in State Bond funded projects– Lecture, lab, office, library (state)– AVTV, Parking, Café/bookstore (LRCCD)– Age, building condition, and funding also considered

• Long range plan developed for Measure M– 2007 Cap-Loads derived funding plan– 108K of eligible new space (25K on campus / 78K at centers)

• RoughRough planning factors for this MP Update– New Instructional (Lecture/Lab) Space: 15,000 ASF– Office Space (Student Services): 4,000 ASF– General lab, service, support: 3,000 ASF– Cafe, Bookstore: 3,000 ASF– + Temporary 3 Replacement: 2,500 ASF

Sample Campus Cap/Load Ratios

0%

100%

2000

Lecture

Lab

Office

Library

AVTV

PE

Book/Café

Parking

Sample Campus Cap/Load Ratios

0%

100%

2015

Lecture

Lab

Office

Library

AVTV

PE

Book/Café

Parking

Program Considerations

PossiblePossible Program Program Locations & Locations & ConsiderationsConsiderations

Issues / Spaces to ResolveIssues / Spaces to ResolveShort Term—2010-2014Short Term—2010-2014

• Layout & Space Allocations in new Student Services Building– Design begins January 2011; Select Architect November 2010 – Journalism layout– Photo Layout

• Anthropology Space—West Sac or Main• Administration of Justice Space—West Sac or Main• Electronics game plan

– LAC 11 is target– Motorcycle program

• Auditorium A—1-4 Spaces– DSPS/DRC space adjustments– AVPS to PAC or new Student Services Building

• Rodda Hall North, 3rd Floor Utilization once cleared– Modernization project due to size/scope potential

• TAP Projects….major portion of first FMP

T.A.P T.A.P ConsiderationsConsiderations

Student Parking

New Student Services BuildingNew Student Services BuildingProposed Space Allocations for ArchitectsProposed Space Allocations for Architects

• 16,000 ASF (AJ + SS = 8005 ASF)• Space Allocation:

– Student Services: 9,076 (current + 4,000)– Photo: 3,300 (from RHN)– Journalism: 2,400 (from Temp 3-

demo)– Anthropology: 1,000(from A-J)– AVPS: 224 (vs. A-1 in PAC)

• Administration of Justice relocated to RHN? Or retain at WSC?

Related Projects—Short TermRelated Projects—Short Term• Rodda Hall North, 3rd Floor: 9286 ASF

– Math Division Office: 1,054– Math Classrooms (vs LAC) 1,192– Administration of Justice: 1,818– Other Space to design: 5,222

• Lusk Modernization Project – Electronics: 5413 ASF– Lusk 11: 4509 ASF– Motorcycle Game Plan: McClellan Park

• Auditorium A-1thru 4: 2462 ASF– Already under construction as part of PAC– DSPS/DRC: 1958– AVPS: 504

• West Sacramento Center, 3rd Floor: 7000 ASF– Bond project remodel; type II funds retained

Issues / Spaces to Resolve & DiscussIssues / Spaces to Resolve & DiscussLong Term 2014-2020Long Term 2014-2020

• Mohr Hall & Lillard Hall Complex– State bond projects from Measure A--SLIP– Mohr Hall II Building Measure M (17,880 ASF)– Program Changes and relocations– Dental Clinic, Engineering, POD, others?

• Bookstore & Café Spaces– Integrated with Lillard & Mohr projects– Modest changes to Lusk Center spaces

• Other program locations or changes• Other Backfill Projects• Education Centers, Phases II & III

– ASF counts to overall cap-load picture

New Mohr Hall Bldg—Mohr IINew Mohr Hall Bldg—Mohr II Proposed Space Allocations for ArchitectsProposed Space Allocations for Architects

• Planned Building at 17,880 ASF• Planned allocation of space

– New Instructional Space 13,712– Temporary 11 1,345– New Lab/Support (engineering) 1,323– New Café 1,500

• Other program adjustments or relocations– Dental Clinic– POD

Education CentersSeptember 2010 Update

PROJECTPROJECT CONSTRUCTION TIMINGCONSTRUCTION TIMING

West Sacramento, Phase INew construction 10,500 ASF

+ Third Floor

June 08 - January 2010Opened Spring 2010

Davis Center, Phase IWest Village Site/ 14,000 ASF

June 2010 – November 2011Under ConstructionOpen--Spring 2012

West Sacramento Center- Phase II- Phase III

Occupy 2018

Occupy 2020

Davis Center- Phase II- Phase III

Occupy 2017

Occupy 2019

Construction ScheduleConstruction ScheduleBuilding Modernization / Replacement / NewBuilding Modernization / Replacement / New

BuildingStart

Construction Occupy Semester Start FPP or First Funding

Davis Center Phase I 6/10 11/11 Spring 2012 N/A Local Bond

Performing Arts Center 6/10 1/12 Spring 2012 2008 FF:08-09

Hughes Stadium 3/11 8/12 Fall 2012 N/A Local Bond

Student Services Bldg 8/12 12/13 Spring 2014 N/A Local Bond

Lusk Center Phase I 6/13 12/13 Spring 2014 N/A Local Bond

Rodda Hall North / 3rd Floor 2/14 7/14 Fall 2014 N/A Local Bond

Mohr Hall 6/14 12/15 Spring 2016 Complete. FF:12-13

Lillard Hall 6/16 12/17 Spring 2018 2011. FF:13-14

Mohr Hall II, New Bldg 6/18 12/19 Spring 2020 2012. FF: 14-15

Construction ScheduleConstruction ScheduleTAP and Education CentersTAP and Education Centers

BuildingStart

Construction OccupySemester

StartFPP or First

Funding

TAP: B,C, G&H Lots, Drop Offs, PAC/J-Lot 5/12 7/12 Fall 2012 N/A Local Bond

Davis Center Phase II / III 6/15 

20172019

 

 State and Local Bond Funding

West Sac Ctr, Phase II / III 6/16 

20182020   

State and Local Bond Funding 

Building Modernization ScheduleBuilding Modernization ScheduleAs of October 2010

Summary & ConclusionSummary & Conclusion

• State budget outlook troubling– Has impacted modernization projects’ schedule– Enrollment changes may effect timing and scope

• Modernization program continues– Shifts in timing/funding of projects inevitable

• Facilities Master Plan update– Tool for managing changes, charting a course– Capture Measure A & M projects and plan backfill

projects and program location changes– Account for budget and enrollment changes