2013 DOTD Engineering
Conference
Effort to Address Consultant Services
Workloadand Expedite Requests
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
2/46
Amount Contracted Last Three Years
Data from Lotus Notes
FY 2010/2011 - $90.2 million FY 2011/2012 - $155 million
FY 2012- present - $81 million
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
3/46
CCS Titles 48 Current Personnel
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
4/46
Additional Personnel to be Added
Contract Worker to add in the development of contracts, taskorders and supplements.
An over hire was approved due to an existing worker on FMLA
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
5/46
Effort to Reduce Number of Requests
Time Extension
Time extension with justification will be granted by
the Project Manager (except for retainer contracts
extensions are allowed for Task Orders)
Written notification from the PM shall be sent to theconsultant and two copies shall be provided to CCS.
By granting time extensions, the PM will impact the
contracts provision listed under the PROSECUTION
OF WORK.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
6/46
Negotiation of Contracts
Negotiation of the contract is part of the PMsduties. Initial negotiation shall now beperformed by PM using State Wide Averages, ifwithin 10%, submitted to CCS for action.
Negotiation shall continue until both parties arewithin 10% or the Negotiation time as establishedin the advertisement has exceeded.
If negotiations fail or cannot be completed within
this time period, the PM shall request CCS tosubmit another shortlist to the Secretary for theAward of the contract.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
7/46
Multiphase Contracts of Less Than
$1,000,000
The total contract will be advertised for all
known phases. This is an effort to reduce the number of Supplemental Agreements.
After each phase/task is completed, the PM shall give approval by writtennotification to the consultant (copy CCS) to advance to the next phase or task.
If at any time a change in scope or compensation will impact the Original
Contract, the PM shall request a Supplemental Agreement.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
8/46
Multiphase Contracts of Over
$1,000,000
The total contract will be advertised for all knownphases.
This is an effort to reduce the number of SupplementalAgreements.
After the each phase/task is completed, the PM shallgive approval to advance by a Detailed Scope &Compensation letter (all work must be within theoriginal scope and fee established in the contract).
If at any time a change in scope or compensation willimpact the Original Contract, the PM shall request aSupplemental Agreement.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
9/46
Notice To Proceed
Notice to proceed will no longer be delayed due
to budget issues
The PM shall inform CCS as to the recommended
NTP date.
The PM is responsible for the projects budget
including contract actions.
The PM shall ensure that budget is in place andsufficient to pay the invoice before submitting the
invoice to CCS.
CCS will return invoices if budget is not adequate.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
10/46
Invoice CCS Web Site
INVOICE SUBMITTAL INFORMATION FOR
PROJECT MANAGERS Last Updated: 02/06/2013
http://notes1/ContWEB.nsf/b88769326453be
f886256fe00047183a/dca7a93559830ece862
57b0a00793883?OpenDocument
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
11/46
Advance Notice to Proceed
Not recommended unless absolutely necessary
Division Heads may consider for state funded
projects and for delegated projects (benefitting
projects must have FHWA authorization).
Consultants should be made aware that invoices
will not be processed until the contract is
executed, budget is in place, and Purchase Orderis available.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
12/46
Purchase Order
Section 80 is the buyer for most of HQsections
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
13/46
Purchase Order
The PM or other member of their section willbe the Requisitioner.
The Requisitioner is the business line expert.
The business line expert is responsible for allaccounting codes required for the ShoppingCart or Purchase Order.
The Requisitioner is responsible for providingaccounting coding and other data needed forshopping carts or purchase orders.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
14/46
2013 DOTD Engineering
Conference
Past Rating System
(RTNG old2012 CPPR new)
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
15/46
RTNG System
Old System end used in 2011
Based on a 0-4 scale rating
Limited grading questions Only grader enters data into system
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
16/46
CPPR System
New System started in 2012
Based on a 1-5 scale rating
Rating questions proposed by each section The data entered by grader is approved by a
supervisor
E-mail notification to consultant of the ratings
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
17/46
Ranking of 24-102 forms
How are the two different ratings used to determine theconsultants past ratings score for the short list for the Secretary?
Since both scales have the same number of intervals between the
low score and the high score, the Department currently reduces the
CPPR score by one and performs a weighted average of the scores.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
18/46
Example Firm XYZ has
3 old RTNG scores for the category stated in theadvertisement
(2.5, 2.8 and 3.4 average 2.9)
2 new CPPR for the category stated in the advertisement
(3.3 and 4.1 average 3.7)
RTNG Average*# of RTNG Scores + (CPPR Average-1)*# of CPPR Scores
# of RTNG Scores+ # of CPPR Scores
(2.9*3)+((3.7-1)*2) Equal 8.7+5.4 Equal 2.82 Use 2.8(3+2) 5
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
19/46
2013 DOTD Engineering
Conference
Direct Expenses
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
20/46
DIRECT EXPENSES
Direct Expenses should be reasonable and
what a prudent person would pay for the
service or material.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
21/46
Travel Expenses
As per Departmental consultant contracts:
All travel expenses shall be in accordancewith the State Travel Regulations.
The Louisiana Travel Guide can be found at thefollowing web link:
http://www.doa.louisiana.gov/osp/travel/travelpolicy/travelguide.pdf
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
22/46
Extended Stays
For travel assignments approved by the
Commissioner of Administration involving duty
for extended periods (31 or more consecutive
days) at a fixed location, the reimbursement ratesindicated should be adjusted downward
whenever possible.
Prior approval must be given by Division Heads May approve per diem rate (lodging and meals)
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
23/46
Mileage
Recent change by DOA effective date 2-1-2013
Mileage for first 99 miles of any trip will bereimbursed at a rate of $0.51 per mile.
Mileage beyond the first 99 miles will be
reimbursed at a rate of $0.40 per mile.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
24/46
Office of the Commissioner
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
25/46
Special Rates for Vehicle, Equipment or
Materials
The direct expenses will be disallowed if subsequent audits reveal that the
Consultant has not maintained adequate bookkeeping.
Special vehicle/equipment rental rates will require prior approval from the
DOTD Project Manager. These rates shall be established in the contract.
If the PM lacks knowledge on rental rates for the special vehicle / equipment /
materials, the PM should request at least 3 quotes from the consultant todetermine if the rental rate is reasonable.
Direct expense shall not include a profit to a consultant nor be impacted by
the consultants overhead rate.
If PM needs help in determining a rate, the PM should contact the Audit
Section.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
26/46
2013 DOTD Engineering
ConferenceConsultant Services
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
27/46
Consultant Contract Services
As the name implies, we are here to serve the
other sections of the Department in acquiring
consultant contracts.
These engineering contracts are under Title 48
of the Louisiana Revised Statues.
Information requesting services must be in
accordance with the requirements of theselaws.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
28/46
Authorization Letter
Minimum Manpower Requirements
Weighting factors for RFP Complexity Factors
Shortlist
Notice to Proceed
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
29/46
Request for Consultant Services
RS:48:286 (1) The magnitude of the work involved in a project is
determined to be so taxing to the department's availablemanpower that it will be necessary to defer other essentialwork if the work is performed by the department staff.
(2) The work required by a project is determined to be ofsuch a specialized nature that the department will berequired to go outside its own staff for experts in theappropriate fields to accomplish the work.
(3) The time frame within which the work must becompleted is determined to be such that the departmentcannot undertake the work and maintain its program onschedule.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
30/46
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
31/46
Request for Advertisement
Standard contract templet for engineering
http://notes1/ContWEB.nsf/b88769326453be
f886256fe00047183a/f56d1a5493085cd08625
75d00002e369?OpenDocument
Scope of services DBE Goal
Items to be provided Reference Material
Compensation Contract time
QC/QA requirements Minimum Personnel Reqd
Evaluation Criteria Other items as needed
http://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/f56d1a5493085cd0862575d00002e369?OpenDocumenthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/f56d1a5493085cd0862575d00002e369?OpenDocumenthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/f56d1a5493085cd0862575d00002e369?OpenDocumenthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/f56d1a5493085cd0862575d00002e369?OpenDocumenthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/f56d1a5493085cd0862575d00002e369?OpenDocumenthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/f56d1a5493085cd0862575d00002e369?OpenDocument7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
32/46
Contract time
Contract time for the actions to be performed
Entire contract time shall be noted on
transmittal letter, used in determining
compatibility of firm in rating program.
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
33/46
Scope of Services
All services to be provided:
Original contract
All supplements
May limit the activity of future supplements
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
34/46
DBE Goals
DBE goals will be reviewed for all contract greaterthan $250,000 total (all phases)
DBE is considered when any activity with the contractcan be performed by a DBE firm located near theproject
DBE can be established with a No Goal to 10% normalmaximum.
If goals cannot be satisfied, documentation is neededin accordance with a Good Faith Efforthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/22a8505cdc115fc38625734800681e7e?OpenDocument
http://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/22a8505cdc115fc38625734800681e7e?OpenDocumenthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/22a8505cdc115fc38625734800681e7e?OpenDocumenthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/22a8505cdc115fc38625734800681e7e?OpenDocumenthttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/22a8505cdc115fc38625734800681e7e?OpenDocument7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
35/46
Reference Material
Standard reference material web link:http://webmail.dotd.louisiana.gov/ContWEB.nsf/b88769326453bef88625
6fe00047183a/18fc2860512aba5886257a62006133b8?OpenDocument
If additional reference material is needed, textis to be included in the advertisement along
with additional web links
http://webmail.dotd.louisiana.gov/ContWEB.nsf/b88769326453bef886256fe00047183a/18fc2860512aba5886257a62006133b8?OpenDocumenthttp://webmail.dotd.louisiana.gov/ContWEB.nsf/b88769326453bef886256fe00047183a/18fc2860512aba5886257a62006133b8?OpenDocumenthttp://webmail.dotd.louisiana.gov/ContWEB.nsf/b88769326453bef886256fe00047183a/18fc2860512aba5886257a62006133b8?OpenDocumenthttp://webmail.dotd.louisiana.gov/ContWEB.nsf/b88769326453bef886256fe00047183a/18fc2860512aba5886257a62006133b8?OpenDocument7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
36/46
Compensation
List the entire amount for the contract and the
amount to be paid for by the current contract
action
Direct Expenses may be shown separately
with a different maximum
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
37/46
QC/QA requirements
Standard QC/QA provisions should be stated in
majority of advertisements.
New QC/QA provisions are required for contracts
associated with bridge design elements. Bridgeteam member will grade these provisions. The
grading of these provisions will be included with
the short list to the Secretary. Link:http://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/81b8aac81583c4c586257a6700502e85/$FILE/Quality%20Control%20-
%20Quality%20Assurance%20for%20Bridge%20Projects.pdf
http://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/81b8aac81583c4c586257a6700502e85/$FILE/Quality%20Control%20-%20Quality%20Assurance%20for%20Bridge%20Projects.pdfhttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/81b8aac81583c4c586257a6700502e85/$FILE/Quality%20Control%20-%20Quality%20Assurance%20for%20Bridge%20Projects.pdfhttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/81b8aac81583c4c586257a6700502e85/$FILE/Quality%20Control%20-%20Quality%20Assurance%20for%20Bridge%20Projects.pdfhttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/81b8aac81583c4c586257a6700502e85/$FILE/Quality%20Control%20-%20Quality%20Assurance%20for%20Bridge%20Projects.pdfhttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/81b8aac81583c4c586257a6700502e85/$FILE/Quality%20Control%20-%20Quality%20Assurance%20for%20Bridge%20Projects.pdfhttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/81b8aac81583c4c586257a6700502e85/$FILE/Quality%20Control%20-%20Quality%20Assurance%20for%20Bridge%20Projects.pdfhttp://notes1/ContWEB.nsf/b88769326453bef886256fe00047183a/81b8aac81583c4c586257a6700502e85/$FILE/Quality%20Control%20-%20Quality%20Assurance%20for%20Bridge%20Projects.pdf7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
38/46
Minimum Personnel Reqd
Minimum personnel requirements should be
definable and verifiable by Evaluation Team.
Normally years of experiences are shown to
be 3, 5 or 10 years of experiences
Must list any required documentation of
profession licenses or certification(s).
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
39/46
Evaluation Criteria
The six standard weight factors will be usedunless approval is given by the Chief Engineer forspecialty projects.
Complexity up to moderate can be requested by
the Project Manager. For complex rating for anadvertisement, recommendation of the SectionHead, Chief Engineer and approval by theSecretary is required.
The Project Manager is to list the members of theEvaluation Team.
continue
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
40/46
Evaluation Criteria
Six Factors (weighting factor) Firm Experience as determined by Evaluation Team (3)
Staff Experience as determined by Evaluation Team (4)
Past Performance as per ratings given by previous Project Managers
(6)
Current Work Load as per CCS records and Consultants 24-102
submittal (5)
Compatibility (Firm Size) as determined by CCS rating program (3)
Location as reported on 24-102 and verified by CCS (location of themajority of the staff meeting the requirements of the minimum
personnel requirements) (4 with the exception of 6 for Urban System
Projects).
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
41/46
Evaluation Criteria
Past Performance Highest Rated Factor
Based on similar DOTD projects
The categories to be considered and their percentage
are determined by the Project Manager. CCS request that the categories to be considered to be
limited to at most three difference categories.
Past ratings from Project Managers are needed in
order for this factor to be fully utilized.
Past Ratings are considered for only three years. continue
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
42/46
Evaluation Criteria
Modifications or additional factors can be
added in accordance with RS 48: 293
the weighting factors may be varied based on the
specific project requirements
special evaluation criteria specified in the
advertisement required to meet particular project
needs
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
43/46
Shortlist Evaluation
Section Input
Firm and Staff Experience, Evaluation Team inputaccounts for approximately 28% of evaluation
Past Performance accounts for approximately 24% ofevaluation This is the best reason to rate all of the consultants work under
your supervision
Firms without scores will be assigned a rating as per theadvertisement. Either equal to the average of all of the otherrespondents for the project or the statewide average.
Total percentage of the input by the teams andsections is approximately 52% of evaluation
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
44/46
Shortlist Evaluation Additional Criteria
Work Load
Current Work Load the outstanding work
excluding retainage without active task orders
and work officially on hold for more than 6
months.
The maximum workload per person is
currently estimated as $125,000 per year.
This factor is approximately 20% of evaluation
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
45/46
Shortlist Evaluation Additional Criteria
Firm Size
Firm Size as know as Compatibility
Based on the percentage of the work to beperformed, the estimated amount of the
contract, length of the contract, currently$3000/person/month and the number ofemployees of the firm
Will be impacted by a moderate or complex
rating factor (large firms will receive a value notless than a 2).
This factor is approximately 12% of evaluation
h l l dd l
7/29/2019 S54_Consultants Rating and Proposal Advertisements_LTC2013
46/46
Shortlist Evaluation Additional Criteria
Location
Location is normally as stated in the firms 24-
102
CCS verifies and may change located based on
a review of the location of the majority of the
key staff listed to satisfy the minimum
personnel requirements.
This factor is approximately 16% of evaluation