RPS HYDRO ELECTRIC POWER
PLANT
8/11/2019 RPS power Plant
4/14
THE RPS DAM ( HEPS) IS PART OF CHAMBAL PROJECT .
THIS PLANT WAS OFFICIALLY DECLARED OPEN ON 9FEBRUARY 1970 BY INDRA GANDHI.
THIS DAM IS USED FOR BOTH IRRIGATION ANDGENERATION OF ELECTRICITY. THE TOTAL DAM LENGTHIS ABOUT 1 KM AND 25 FEET WIDE.
RPS HYDRO POWER PLANT CONSIST OF FOUR UNITSOF EACH 43 MW.
THE GENERATED VOLTAGE IS 11 KV ANDTRANSMISSION VOLTAGE IS 132 KV .
8/11/2019 RPS power Plant
5/14
GENERAL DESCRIPTION OF RPS HEPS
AT RPS HEPS 4 UNITS OF FRANCIS TURBINE AREINSTALLED & EACH TURBINE ROTATE AT 125 RPM.
GENERATOR IS DIRECTLY COUPLED WITH TURBINE,GIVING OUTPUT OF 43MW AT 11KV & 50HZFREQUENCY.
THE OUTPUT VOLTAGE IS STEP UP TO 132KV BYTRANSFORMER.
THE PLANT OPERATED AND CONTROLLED FROMCENTRALIZED ROOM WHICH IS HAVING ALL THEINFORMATION RAGARDING DIFFERENT SYSTEMS OFPLANT.
8/11/2019 RPS power Plant
6/14
PARTICULARS R.P.S UNITS
1. CATCHMENT AREA2. SUBMERGED AREA3. FULL RESERVOIR LEVEL4. MX. WATER LEVEL5. MIN. DRAWM DOWN LEVEL6. NO. & SIZE OF CREST
GATES7. NO. & SIZE OF SULICE
GATES8. INSTALLED CAPACITY9. NO. OF PENSTOCK& DIA.10. MAX. HEAD
11. MIN. HEAD
1. 96200 MILESQUARE
2. 76.55 MILESQUARE
3. 1157.50 FEET4. 1162.00 FEET5. 1125.00 FEET
6. 17,60*28 FEET SQUARE
7. 4, 9*11 FEETSQUARE
8. 4*43 MW9. 4*20 FEET10. 189 FEET11. 152 FEET
8/11/2019 RPS power Plant
7/14
STORAGE RESERVOIR
DAM
PENSTOCK
TAIL RACE
DRAFT TUBE
HYDRAULIC TURBINE
GENERATOR
8/11/2019 RPS power Plant
8/14
8/11/2019 RPS power Plant
9/14
HYDRAULIC TURBINE
THE RPS HEPS IS LOW HEAD POWER PLANT SO FRANCIS TURBINEIS USED.
IT IS A REACTION TURBINE.
THIS TURBINE DEVELOPS POWER PARTIALY DUE TO VELOCITYOF WATER & PARTIALY DUE TO DIFF. IN PRESSURE.
IT CONSIST GUIDE APPARATUS WITH AN OUTER RING OF
STATIONRY BLADES & INNER RINGS CONSISTING OF ROTATINGBLADES FORMING A RUNNER .
THE EFFICIENCY OF TURBINE VARIES IN 80% TO 85%.
8/11/2019 RPS power Plant
10/14
SPECIFICATION OF FRANCIS TURBINE
KW - 52000
NET HEAD - 49.7 M
NO. OF BLADES - 16
RPM - 125
8/11/2019 RPS power Plant
11/14
SPECIFICATION OF GENERATOR
MODEL
TYPE
KW
SPEED
VOLTS ON LOAD
AMP
WOUND
POLES
101213
EVF-8
250125 RPM
250
1000
SHUNT
8
8/11/2019 RPS power Plant
12/14
FUNCTION OF RPS HEPS
THIS PLANT SERVES ELECTRICITY TO KOTA , BHILWARA
AND GANDHI SAGAR.
WHEN THE GRID FAILS THIS POWER STATION PROVIDE S
START UP POWER FOR RESTORING THE NORTHEN GRID.
IT PROVIDES STABILITY TO MACHINES OF RAWATBHATA
ATOMIC POWER PLANT CONTRIBUTING TO THE STABILITY
OF THE GRID.