1
ROY HILL PORT MATERIALS HANDLING ESTIMATE ‘experience makes a difference’ Suite 901, 140 Bourke Street, Melbourne Victoria 3000 Level 6, 87 Wickham Terrace, Spring Hill Queensland 4000 Tel: 03 9663 6661 Fax: 03 9663 6330 Email: [email protected] The Client AGC AusGroup are a construction company active in mechanical scaffolding and insulation in remote sites. The Project The Roy Hill iron ore project included extensive materials handling and ship loading infrastructure at the port facility. AGC were tendering the train unloading, stockyard area and storage facility at the port. The Challenge Ø To perform first principles estimate for tender - for conveyors and construction of stackers, reclaimers and rail wagon tippler Ø To develop construction methods, and conceive construction schedule The Outcome Ø Estimate prepared from Flagstaff’s extensive database of resource costs, production rates and Flagstaff’s understanding of the basics of construction contracting

ROY HILL PORT MATERIALS HANDLING ESTIMATE · The Roy Hill iron ore project included extensive materials handling and ship loading infrastructure at the port facility. AGC were tendering

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ROY HILL PORT MATERIALS HANDLING ESTIMATE · The Roy Hill iron ore project included extensive materials handling and ship loading infrastructure at the port facility. AGC were tendering

ROYHILLPORTMATERIALSHANDLINGESTIMATE

‘experiencemakesadifference’Suite901,140BourkeStreet,MelbourneVictoria3000

Level6,87WickhamTerrace,SpringHillQueensland4000Tel:0396636661Fax:0396636330

Email:[email protected]

TheClient

AGCAusGroupareaconstructioncompanyactiveinmechanicalscaffoldingandinsulationinremotesites.

TheProject

TheRoyHillironoreprojectincludedextensivematerialshandlingandshiploadinginfrastructureattheportfacility.AGCweretenderingthetrainunloading,stockyardareaandstoragefacilityattheport.

TheChallenge

Ø Toperformfirstprinciplesestimatefortender-forconveyorsandconstructionofstackers,reclaimersandrailwagontippler

Ø Todevelopconstructionmethods,andconceiveconstructionschedule

TheOutcome

Ø EstimatepreparedfromFlagstaff’sextensivedatabaseofresourcecosts,productionratesandFlagstaff’sunderstandingofthebasicsofconstructioncontracting