Route 364 (Page Ave. Extension)

The Missouri Department of Transportation

Route 364 history• Project started in 1997, opened

in 2003

• Phase 1 from Route 270 to Jung Station Road, St. Charles – Completed

• Phase 2 from Jung Station Road to Mid Rivers Mall Drive – In progress

• Phase 3 from Mid Rivers Mall Drive to Route 40 (near Route N) – Planned

• Regional Priority for East-West Gateway Council of Governments, St. Charles County

What’s going on now?• Constructing Phase 2 between

Jung Station Road and east of Jungermann Road: $19.7 million

• Crews have built new north and south outer roads (one-way)

• Built two-way bypass to construct Harvester Road bridge

• Bridge completed later this fall

• Originally scheduled to open winter-spring 2010

What’s going on now?

Green = current construction

What’s on the horizon?

• Economic stimulus project completes Route 364 from Jungermann to west of Central School Road: about $44 million

• Work starts in October – completed by 2012

• Crews will construct outer roads, then Route 364

• Traffic flow may postpone reopening of Route 364 by Harvester Road

What’s on the horizon?

Yellow = under contract

What’s in the future?

• MoDOT and St. Charles County are working on an agreement to finish Phase 2 between Central School Road and Mid Rivers Mall Drive.

• MoDOT is expecting to start preliminary bridge or outer road work near Mid Rivers Mall Drive in 2010

• Currently, it will cost about $40 million to complete the rest of Phase 2.

What’s in the future?

Light Green = proposed Red = Phase 3

Overall view of Phase 2 of Rte 364

What about Phase 3?• Phase 3 runs between Mid Rivers Mall

Drive and Route 40/Route N

• No money is available for Phase 3 yet

• Estimated costs to complete Phase 3: $140 million

• Legislature has authorized MoDOT to use design-build on Route 364 project – if used, must start design-build by 2013

• May consider construction in two financially manageable segments – Mid Rivers to K, K to Route 40

What’s in the future?

Route 364(Page Avenue Extension)

The Missouri Department of Transportation