Road Works

Embed Size (px)

Citation preview

  • 7/29/2019 Road Works...

    1/23

    1

    Welcome to the lecture!

    Roadworks

  • 7/29/2019 Road Works...

    2/23

    2

    Objectives of the lecture

    To introduce the methods and techniques of road

    construction

  • 7/29/2019 Road Works...

    3/23

    3

    Learning outcomesBy the end of the lecture, the student willunderstand:

    The methods and techniques of road construction The key considerations in the design and

    construction of roads

  • 7/29/2019 Road Works...

    4/23

    4

    Roadworks - Outline

    Earthworks

    Construction of pavement

    Equipment and plant Road geometry

    Conclusions

  • 7/29/2019 Road Works...

    5/23

    5

    History of Highway Construction

    Stem from invention of the wheel - Samaria 3000 BC. Earliest UK road - log raft over the Somerset peat bogs to

    Glastonbury 2500 BC.

    Romans- built 50,000 miles of road throughout Europe- straight from hill top to hill top, less chance of ambush, wagons could

    not easily turn.

    - constructed above ground level (defence) - HIGHWAY.

    - 3 types depending on usage levelled earth, gravel and paved.

    Post Roman-

    Britons had no need to travel, roads deteriorated,

    used for building material.

    1765- John Metcalf road design included surface drainage and a goodfoundation of large stones (sub base) supporting finer material.

    1820- Macadam developed cheaper road with camber.

  • 7/29/2019 Road Works...

    6/23

    6

    Earthworks

    Preparation of the soil to obtain the right: level

    gradient

    profile

    strength

    Cut and fill

    Concerns

    balance of cut & fill quantitiesside slopes

    treatment of compressible soil

  • 7/29/2019 Road Works...

    7/237

    Earthworks

    Side slopes

    Non-cohesive soils

    Natural angle of repose

    Cohesive soils

    Height of bank

  • 7/29/2019 Road Works...

    8/238

    EarthworksTreatment of compressible soil

    Removal

    Blasting

    Overloading

    Jetting

    Stabilisation

    Involves mixing the sub-grade with agents (cement,

    lime, bitumen, liquid chemicals) The objective is to increase the strength of the sub-

    grade

  • 7/29/2019 Road Works...

    9/239

    Construction of pavements

    Flexible pavements Elastic

    Three main layersSurfacing

    Wearing course

    Base course

    Road base

    Sub base

    Supported by Sub-grade

  • 7/29/2019 Road Works...

    10/2310

    Pavement Sub-grade

    Strength of sub-grade determines thickness of

    pavement needed

    Usually measured by the Californian BearingRatio (CBR) test

    If CBR of sub-grade is too low then ground

    improvements necessary

  • 7/29/2019 Road Works...

    11/2311

    Californian Bearing Ratio (CBR)CBR (%)

    Depth of water table from formationlevel

    Type of soil PlasticityIndex(%)

    More than 600mm 600 mm or less

    Heavy clay 70605040

    22

    2.53

    11.522

    Silty clay 30 5 3Sandy clay 20

    10 67 45Silt

    2

    1

    Sand (poorlygraded) Non-plastic 20 10Sand (well graded) Non-plastic 40 15Well graded sandgravel Non-plastic 60 20

  • 7/29/2019 Road Works...

    12/2312

    Construction of pavements

    Rigid pavements

    Rigidity does not deform under stress

    Concrete air entrained increases resistance to

    frost damage and de-icing salt corrosion Reinforcement may be bars or mesh. Continuous

    rigid pavements have heavy reinforcement

    Joints used in non-continuous pavements toallow for thermal movement. Includes a filler andsurface sealant

  • 7/29/2019 Road Works...

    13/23

    13

    Construction of pavements

    Rigid pavements laid as single layer byconcrete paver

  • 7/29/2019 Road Works...

    14/23

    14

    Construction of pavements

    Surface water drainage Water causes damage and reduced skid resistance and

    should be removed as soon as possible

    Need an adequate surface drainage system

    Key issues:Intensity of rainfall;

    Size of catchment area;

    Duration of storm or time of concentration; and

    Permeability factor of the surfaces.

  • 7/29/2019 Road Works...

    15/23

    15

    Urban single carriageway

    Rural single carriageway

  • 7/29/2019 Road Works...

    16/23

    16

    Road geometry

    Standard size of

    traffic lane = 3.65m

  • 7/29/2019 Road Works...

    17/23

    17

    Equipment and plant

    Excavate onlyRipper, Grader

    Excavate and loadBack hoe / Back actor;Face shovel/ Forward loader; Dragline;Bucket

    wheel excavator

    Haul and depositLorries; Dump trucks; Conveyors

    Excavate, load, haul and depositBulldozer; Scraper; Elevated scraper

    Compact

    Smooth wheeled roller; Pneumatic roller; Vibratory roller

  • 7/29/2019 Road Works...

    18/23

    18

    Equipment and plant

    Bulldozer Planer

  • 7/29/2019 Road Works...

    19/23

    19

    Equipment and plant

    Wheel loaderExcavator

  • 7/29/2019 Road Works...

    20/23

    20

    Equipment and plant

    Dump truck

    Grader

  • 7/29/2019 Road Works...

    21/23

    21

    Equipment and plant

    Paving machine Chip spreader

  • 7/29/2019 Road Works...

    22/23

    22

    Equipment and plant

    Vibratory rollerDead weight roller

    7 Wheel pneumatic roller

  • 7/29/2019 Road Works...

    23/23

    23

    Conclusions

    Good roadworks ensure;

    Strong subgrade;

    Strong pavement layers;

    Adequate surface water drainage; and

    Appropriate road geometry.