Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
ROAD RESEARCH LABORATORY
Ministry of Transport
RRL REPORT LR 247
CREEP OF CONCRETE PIPES UNDER LOAD
by
J.. W.. Grainger
Road Research Laboratory Crowthorne, Berksh ire
1969
Ownership of the Transport Research Laboratory was transferred from the Department of Transport to a subsidiary of the Transport Research Foundation on ! st April 1996.
This report has been reproduced by permission of the Controller of HMSO. Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.
CONTENTS
Abstract
1. Introduction
2. Results obtained in the pilot experiment at Christchurch
3. Tests on pipe rings
4. Results
5. Conclusions
• P a g e
1
" 2
• 2
3
•
5
6. Discussion of results 6
7. Acknowledgements
8. References 6
" ~ . , ~ i ~ • ~ . " . . ~ ' .
CROWN COPYRIGHT 1969 Extracts from the text may be reproduced
provided the source is acknowledged
CREEP OF CONCRETE PIPES UNDER LOAD
ABSTRACT
When 36-in (914-mm) diameter Class I concrete pipes were buried
4 ft. (1.22 m) below the surface of a representat ive road consisting
of 4 in (102 mm) of bitumen macadam on 9 in (230 ram) of hardcore
on 3 in (76 ram) of clinker, the circumferential tensi le strains
measured in the pipes on completion of the road were 33 and 35
microstrains at the top and bottom respect ively. These strains
increased by about 40 microstrains at the top of the pipe and by
30 microstrains at the bottom during the next seven weeks during
which the road was not open to traffic.
During the seven weeks, no change occurred in the strains
recorded in 12-in (305-mm) glazed vitreous clay pipes or in 36-in
(914-mm) cast iron pipes buried to the same depth below the road.
Although it seemed certain that creep of the concrete pipes under
the backfill loading could account for some increase in the circum-
ferential strain, it was thought that the large increases recorded
threw doubt on the readings. An experiment has now been made
to determine the magnitude of the creep occurring in a concrete
pipe under prolonged loading and to see whether it is affected by
the age of the concrete when the pipe is loaded.
In these tests, two 36-in (91~mm) concrete pipe rings were
loaded when the concrete was a month old and two rings were
loaded when the material was seven months old. Loads of 600 Ib
(272 kg)were applied to each ring and held constant for six months.
With the rings loaded when the concrete was a month old, the creep
strain resulting from six months of loading was 56 microstrains and
thus was 9..8 times the elastic strain of 20 microstrains resulting
from initial application of load. With the rings loaded when the
concrete was seven months old, the creep strain resulting from six
months of loading was 15 microstrains and thus approximately equal
to the initial elastic strain of 16 microstrains. The initial elastic
strains were, therefore, smaller than those measured in the pipes
under the road, but the creep strains in the rings loaded when the
concrete was a month old were larger than those recorded in the
road. The results of the tests on the pipe rings thus support those
obtained in the earlier road experiments. They emphasise that
concrete pipes should not be used for instrumental purposes when
studying the increase of backfill pressure under a road. Such tests
are best done with metal pipes which do not exhibit creep under
load.
I. INTRODUCTION
The Ministry of Housing and Local Government's Working Party on the Design and Construction of
Underground Pipe Sewers organised a pilot experiment at the Military Engineering Experimental
Establishment, Christchurch, Hants 1. The objective was to investigate the repetitive loads which,
when applied to the surface of a typical road, cause failure of representative underground sewer
pipes. The Road Research Laboratory was responsible for much of the instrumentation.
After the pipes had been laid in their trenches, and the backfilling and road construction were
completed, seven weeks elapsed before the loading tests began. Ouring this time a 12-in (305-mm)
diameter glazed vitreous clay pipe and 12-in (305-ram) and 36-in (914-mm) diameter east iron pipes
showed only a negligible increase in the circumferential strains measured at the top and bottom of
the pipe, but the strains measured in two 36-in (914-mm) diameter concrete pipes increased consider-
ably. The changes of strain recorded in the concrete pipes tended to throw doubt on the measure-
ments of strain. However, there was the possibility that the increase of strain was due to creep of
the concrete under the loading provided by the backfilling and the road construction. An examination
of the literature on creep in concrete indicated that creep might be more severe in new concrete
pipes than in those which have been stored for some time before use. To obtain ,information on these
points, an experiment has been made at the Road Research Laboratory to determine the magnitude of
the creep likely in a concrete pipe and to see whether it is affected by the age of the pipe when the
load is first applied.
2. RESULTS OBTAINED IN THE PILOT EXPERIHENT AT CHRISTCHURCH
Strain-measuring equipment was attached to two 36-in (914-mm) diameter concrete pipes which were
between four and five months old when tested. Electrical resistance strain gauges of the foil type,
2 in (51 mm) long and of 120 ohms resistance were cemented along the top (the crown) and bottom
(the base) of each pipe to measure the circumferential strains in the inner surface at right angles
to the pipe axis. There were five gauges along the crown and five along the base of each pipe.
Along each line of gauges one gauge was attached close to each end of the pipe and the remaining
three gauges were equally spaced along the pipe. All of these gauges recorded tensile circum-
ferential strains. To compensate for temperature effects, each of the " l ive" gauges attached to the
pipe was electrically connected with a matching "dummy" gauge attached to a block of similar
material placed within the pipe. Full details of the instruments were given in the report describing
the pilot experiments 1.
2
The resul ts of the measurements of tensile strain mad~ when the road construction was
finished and after an interval of seven weeks are summarised in Table 1. This table shows that the
creep at the crown of the pipe was 40-42 microstrains (average of the three readings taken on the
central gauges) while that at the base was 27-30 microstrains. There was variation in the initial
values of the tensile strain, but the average value for the central portion of the pipe was 33 micro-
strains along the crown and 35 microstrains along the base. In calculating this latter average, the
very large value of 102 microstrains was omitted.
3. TESTS ON PIPE RINGS
In the tes ts described in the present report, strain and deflection measurements were made on four
concrete pipe rings each 36 in (914 ram) diameter, and 24 in (610 mm) long. The rings were made at
the same works as the pipes used in the pilot experiments. They were considered to be of standard
Class I quality and did not contain steel reinforcement. The average wall thickness was 2.40 in
(61 ram). The pipes were made under controlled conditions to ensure uniformity of the concrete mix
and of the manufacturing technique, and to make them comparable in quality with the pipes used
in the pilot experiments. The rings were allowed to cure for a fortnight in the maker's stockyard and
were then Iransported to the Laboratory and stored on their sides in a temperature- and humidity-
controlled building. The loading tests were made in this building but the control was not so good
as anticipated owing to severa l mechanical failures of the newly installed air-conditloning plant
during the prolonged loading tes ts .
One month after manufacture, two of the rings were set in position as shown in Fig. 1 and dial
gauges reading to 0.001 mm were installed to measure changes of the vert ical diameter under load.
Electrical res is tance strain gauges of the foil type (2 in (51 ram) long and 120 ohms resis tance) were
attached to the inner surface of the pipe ring to measure the internal circumferential strains at the
crown, base and the two sides of each ring. As in the pilot experiments, each strain gauge was
connected electr ical ly with a "dummy" gauge cemented to a piece of concrete placed within the pipe
ring to provide temperature compensation. All of the strain gauges were covered with a layer of
cotton wool to minimise temperature flectuations. After the rings were instrumented, they were
left for two days to minimise the effects of any strains result ing from the weight of the pipe material.
It was estimated that a load of 600 lb (272 kg) applied to the top of each pipe would produce
a circumferential strain of the order of 20 microstrains. The load was applied to each r ing by hand-
loading with 56-1b (25.4-kg) weights - see Fig. 1. This was, in fact, the greatest load which could
be applied to the top of the pipe without difficulty and without constructing special loading apparatus.
Measurements on the resis tance strain gauges showed that tensile strains of about 20 microstrains
were developed at the crown and base of each of the two rings loaded one month after the date of
manufacture, and compressive strains of similar magnitude were recorded at the sides. These
values of strain compare reasonably well with the average values of 33 and 35 microstrains obtained
respectively at the crown and base of the concrete pipes in the pilot experiments at the completion
of the road construction.
3
Although the resistance strain gauges were satisfactory for recording the strain resulting from
the first application of the load of 600 lb in the tests on the pipe rings, they were found unsuitable
[or watching the progress of creep over long periods of time. They gave erratic readings due, it is
thought, to air currents which caused local temperature fluctuations around them. Because of this,
the long term behaviour of each pipe ring was determined by measuring the changes of the vertical
diameter by means of the dial gan.ge. Where strains were required for comparison with those
developed in the pilot experiment, they were deduced from the initial measurements of strain and the
diametral changes of the pipe rings.
The deflection gauges were read at intervals over a period of six months from the time of
applying the 600-1b (272 kg) load to each pipe ring. At the end of this loading period, each ring was
unloaded and the readings of deflection were continued for a further two months in order to watch any
recovery which might occur. When the loads were removed from the first two rings, the other two
rings were subjected to similar loading and the series of measurements was repeated. The results
obtained are shown in Fig. 2 and summarised in Table 2.
4. RESULTS
The Fig. 2 shows that all of the rings gave similar curves relating diametral change with time.
There was an elastic deflection when the load was applied, a gradual reduction of the ring diameter
during the six months under load, elastic recovery when the load was removed, a very small
additional recovery during the two months following load removal, and a permanent set. The elastic
deflection resulting from application of the load was approximately equal to the recovery accompany-
ing its removal, and this occurred even with the two rings which were tested a month after manu-
facture and at a time where their' strer~gth and elastic modulus would be increasing with age to a
significant extent.
Because the elastic modulus of concrete increases with age during the first few months of its
life, the elastic deflections resulting from applying the 600-1b load to the rings which were seven
months old were smaller than those of the rings loaded a month after manufacture, the difference
being about 25 per cent.
The diameter of the rings loaded a month after manufacture diminished on the average by
208prn during the six months under load. This creep was nearly four times that which occurred
with the rings which were seven months old when tested (56/zm). In the pilot experiments, creep
was recorded over a period of seven weeks, so, for reasons of comparison, deflections at a cor-
responding time after application of load have been read off the curves given in Fig. 2. During the
seven weeks of loading, the rings loaded a month after manufacture crept by 77 per cent of the
amount recorded during the six months under load, whereas those loaded seven months after manu-
• facture crept by only 52 per cent of the six months' loading value.
The circumferential strains in the rings would be expected to vary in proportion to the change
in vertical diameter. Measurements on the first pair of pipes showed that a reduction in pipe
4
diameter of 75#m accompanied circumferential tensile strains at the top and bottom of the pipe of
20 mierostrains. The ratio between hoop strain and diametral change has been used to convert the
remaining diametral changes to approximate strains in order to compare the results with those
obtained in the pilot experiment. Strains estimated in this way are given in Table 3 below:-
TABLE 3
Estimated strains developed in 36-in diameter concrete pipe rings loaded by 600 lb.
Elastic strain resulting from application
of load
Creep strain resulting from maintenance of
load for six months
Total strain at end of six months under
load (= elastic strain + creep)
Elastic recovery when load was removed
Residual strain immediately after removal
of load
Additional recovery during interval of
two months after load removal
Creep strain resulting from maintenance of
load for seven weeks
Total strain after seven weeks under load
Circumferential tensile strain (in micro-
strains) at the crown or base of pipe rings
loaded by 600 lb at an age of
1 month
20
56
76
21
55
1.6
43
63
7 months
16
15
31
17
14
X,3
8
24
In the pilot experiment at Christchurch, the initial strain within the concrete pipes was about
36 microstrains and increased to 65 microstrains at the base of the pipe and to 75 mierostrains at the
crown during the seven weeks which elapsed between completion of the road and the start of the
loading tests. These initial strains were somewhat greater than those recorded with the pipe rings,
but the creep produced by seven weeks of loading was comparable with that produced in the pipe
rings loaded a month after manufacture.
S. CONCLUSIONS
(1) Concrete pipes exhibit creep under load even when the initial elastic strains are fairly small.
(2) Less creep occurs with pipes which are some months old when loaded than with pipes which
are loaded soon after manufacture.
(3) The creep strains recorded in the tests on the pipe rings were comparable with those recorded
in the pilot experiment and there is, therefore, no reason to doubt the results obtained at
Christchurch.
(4) The results indicate that it would be unwise to employ concrete pipes in field-scale experi-
ments designed to study the increase of backfill pressure and resultant strain under prolonged
trafficking of a road. Such tests are best done with metallic pipes which neither creep under
load nor shrink and swell under moisture changes.
6. DISCUSSION OF RESULTS
The results show that greater amounts of creep under load occur with new concrete pipes than with
those which are of reasonable age when loaded. However, storage for as long as six or seven months
prior to loading does not eliminate the risk of creep altogether. The storage period is likely to be a
complicating factor in any field-scale experiments on concrete pipes and also in the application of
the resultant data to practice. It is certainly unlikely that pipe manufacturers will wish to store a
considerable number of concrete pipes for long periods in order to minimise the effects of creep.
Because of the loading arrangement employed, it was not possible to add greater loads than
600 lb (272 kg) to each pipe ring and thus determine the load causing failure or examine the
relationship between creep and applied load. Such an investigation appears desirable and should
be included in the research programme being prepared by the Working Party.
7. ACKNOWLEDGEMENTS
This work was carried out in the Structural Properties Section under the direction of Dr. A. C.
Whiffin and the author was assisted by Mr. J. N. Neal.
8. REFERENCES
. HAINSWORTH, I. H., E. P. POTOCKI, J. J.. TROTT and O. C. YOUNG 'Pilot experiments to
determine the loads causing failure of sewer pipes under roads'. Institutions of Civil and
Municipal Engineers, Joint Meeting on 23rd January, 1967.
Printed at the Road Research Laboratory, Crowthorne, Berkshire, England
m
_1
0
I o
0
= a :
= . ~
°..~ .,..4 11~
e o
~ ' ~ ~
o .~
0 0
e ' ~ . ~
° ~
0
o ~ ~
° ~
0
0
C ~ k ~ ~ ~
• 0
Q; ~ 0
-.~ ,-~
° ....i O
N
~)
¢)
¢)
¢)
° ~
0 .,.~
0
o
0
0
t ' - -
~)
.o 0
v ~)
0
CO L ~ - ~ , ( ~ ~ u'~
¢)
~;~ ° ~
o 0
~) ~ D
~ )
0
¢1
f.)
¢Y') C~1
c~
~ )
0 ~ ¢1 0
¢)
¢.) v
0
C'-1 ~f~ c q
OC ~ CO
&
bJO
v
0
0
7
TABLE 2
Results of creep tes ts on 36-in diameter concrete pipe rings
Ref.
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
Reduction of vert ical diameter of
ring due to application of load
Rings 7 months old
when loaded by
600 lb
Rings 1 month
old when loaded
by 6OO lb
Mean Ring Ring Ring Ring
A B A i B 1 1 2 2
Mean
68 81 75 57 61 59
Total reduction of diameter after 236 240 238 85 91 88
7 weeks under load
= (h) - (a) = Reduction of diameter 168 159 163 28 30 29
due to creep under 7 weeks of
loading
Total reduction of diameter at 9.91 275 283 108 121 115
end of 6 months under load
= (d) - (a) = Reduction of diameter 223 194 208 51 60 56
due to creep under 6 months of
loading
Total reduction of diameter 203 200 202 47 52 50
remaining after removal of load
= (d) - (f) = Increase of diameter
due to removal of load
Total reduction of diameter
remaining 2 months after removal
of load
88 75 81 61 69 65
197 194 196 42 47 45
6 6 5 5 = (f) - (h) Recovery 2 months
after load removal
Elast ic deflection on applying load
Creep during 6 months under load
Elast ic recovery when load removed
Additional recovery during 2 months after
load removal
Percentage of creep which occurred during
first 7 weeks after loading = 100 x (c)./(e)
75
208
81
77
59
56
65
52
8 All diametral changes are in pm
Static toad composed of standard 56tb. wts.
Crown of pipe Rubber pads
",~ Dial gauge
Tubu|ar support cemented to .pipe
))
Base of pipe
-4----12 in. channet iron
Fig. 1. HETHOD OF LOADING PIPE RIHGS AND RECORDING DEFLECTION
I I I
~ o ~ e
u II II |1
g
L.
¢- . - - " 0 0 0
0 u
° w
0
o I 1__
¢..
c 0 =
0
E E
"O
- 0
0 Q . .
a -
I 0 0
0
E
0
"ID 0
"D
0 0
e-
tn
c o
E
0
0
0 0
g C
I I 0 0 0 0 0 O 0 ~ 0 ~ 0
(uJ,,, LO0.O x ) u0!|~e1~ep 10~!),JeA
eO
r ~
(O
X I=.-
.~ .-.,
E * ' -
u =)
-4" " 0 o
"=~
13,.
t.~=.
c :3 w
..,.J l=i=. I L l
- - r e . _ j
i ' --"
L . J
. n
0 0
ABSTRACT
Creep of concrete pipes under load: J. W. GRAINGER': Mini- stry of Transport, RRL Report LR 247: Crowthome, 1969 (Road Research Laboratory). When 36-in (914-mm) diameter Class I concrete pipes were buried 4 ft. (1.22 m) below the surface of a representative road consis t ing of 4 in (102 ram) of bitumen macadam on 9 in (230 ram) of hardcore on 3 in (76 ram) of clinker, the circumferential tensi le strains measured
in the pipes on completion of the road were 33 and 35 micro- strains at the top and bottom respectively. These strains in- creased by about 40 microstrains at the top of the pipe and by 30 microstrains at the bottom during the next seven weeks during which the road was not open to traffic.
During the seven weeks, no change occurred in the strains recorded in 12-in (305-ram) glazed vitreous clay pipes or in 36-in (914-ram) cast iron pipes buried to the same depth below the road. Although it seemed certain that creep of the concrete pipes under the backfill loading could account for some increase in the circumferential strain, it was thought that the large increases recorded threw doubt on the readings. An experiment has now been made to detenlline the magnitude of the creep occurring in a concrete pipe under prolonged load- ing and to see whether it is affected by the age of the con- crete when the pipe is loaded.
In these tests , two 36-in (914-mm) concrete pipe rings were loaded when the concrete was a month old and two rings were loaded when the material was seven months old. Loads of 600 lb (272 kg) were applied to each ring and held constant for six months. With the rings loaded when the concrete was a month old, the creep strain resulting from six months of load- ing was 56 microstrains and thus was 2.8 times the elast ic strain of 20 microstrains resulting from initial application of load. With the rings loaded when the concrete was seven mon- ths old, the creep strain resulting from six months of loading was 15 microstrains and thus approximately equal to the in- itial elastic strain of 16 microstrains. The initial e last ic
strains were, therefore, smaller than those measured in the pipes under the road, but the creep strains in the rings loaded
when the concrete was a month old were larger than those re- corded in the road. The results of the tes ts on the pipe rings
thus support those obtained in the earlier road experiments.
T h e y emphasise that concrete pipes should not be used for
instrumental purposes when studying the increase of back- fill pressure under a road. Such tests are best done with metal pipes which do not exhibit creep under load.