Upload
earl-smallwood
View
214
Download
0
Embed Size (px)
Citation preview
Risk Management & Real Options
IX. The Value of Phasing
Stefan ScholtesJudge Institute of Management
University of Cambridge
MPhil Course 2004-05
2 September 2004 © Scholtes 2004 Page 2
Course content
I. IntroductionII. The forecast is always wrong
I. The industry valuation standard: Net Present Value
II. Sensitivity analysisIII. The system value is a shape
I. Value profiles and value-at-risk charts
II. SKILL: Using a shape calculatorIII. CASE: Overbooking at EasyBeds
IV. Developing valuation modelsI. Easybeds revisited
V. Designing a system means sculpting its value shapeI. CASE: Designing a Parking Garage
III. The flaw of averages: Effects of
system constraintsVI. Coping with uncertainty I:
DiversificationI. The central limit theoremII. The effect of statistical
dependenceIII. Optimising a portfolio
VII. Coping with uncertainty II: The value of information
I. SKILL: Decision Tree Analysis
II. CASE: Market Research at E-Phone
VIII. Coping with uncertainty III: The value of flexibility
I. Investors vs. CEOs
II. CASE: Designing a Parking Garage II
III. The value of phasing
IV. SKILL: Lattice valuation
V. Case: Valuing a drug development projects
2 September 2004 © Scholtes 2004 Page 3
Key messages
Traditional valuation techniques have severe limitations when applied to the valuation of multi-stage projects
• Need to take downstream flexibility into account• Will present scenario tree approach as an alternative to Monte Carlo
simulation
Effect is magnified in contract valuation• Need to take account of your own as well as your contract partner’s
flexibility• Need to understand incentives provided by contract terms• Will present how scenario tree approach can be used
Will illustrate these points, using project valuation in the pharmaceutical industry as an example
2 September 2004 © Scholtes 2004 Page 4
Pharmaceutical R&D
0
5
10
15
20
25
30
35
0
20
40
60
80
100
120
140
160
180
200No. of new drugs R&D expense in $billion
Source: Tufts Centre for the study of drug development
2 September 2004 © Scholtes 2004 Page 5
Challenges for Big Pharma
R&D is high risk• 1:10,000 synthesized components make it to the market• Long and increasing time to market (12-15 years) • Many marketed drugs do not return development costs
Pharma relies on blockbuster drugs (sales > $ 1,000 M)• Increasingly difficult to discover• 80% of current blockbuster patents will expire by 2007
Emerging new technologies• Move from chemistry to biology/genetics biotech industry• Hope for new blockbuster potentials
Strategic interests in co-development with smaller biotech companies
• Early access to drugs with blockbuster potential• Access to and learning about new technologies
2 September 2004 © Scholtes 2004 Page 6
Challenges for Biotech
Cash refuelling is difficult in today’s market• Necessary to drive drugs through development process• Very few biotechs have drugs in the market
Biotech focus on upstream activity, based on protected technology platform
• Is this a sustainable business model?
Strategic aim of many biotechs: Move downstream• Move from a mere technology provider to a fully integrated
biopharmaceutical company (FIBCO) with products in the market
Strategic interests in partnership with big pharma companies• Access to capital to finance projects further downstream• Learning about downstream business, in particular building
competence in marketing and sales• Development of a suitable sales force to enable effective
participation in the market (e.g. selling non-blockbuster drugs effectively)
2 September 2004 © Scholtes 2004 Page 7
Industry with similar risk issues: Oil & Gas
High risk
Long time-lines to revenues
Exploit portfolio effect to cope with risk• Identify promising new therapeutic areas / plays
Reliance on big discoveries• Blockbusters / Elephants
High but staged investments
Reliance on new technologies
2 September 2004 © Scholtes 2004 Page 8
Agenda
Explain how a drug is typically valued• Applies generically to staged projects
Explain how contracts are valued in practice
Illustrate limitations of traditional valuation with regard to • Risk sharing• Downstream control
Suggest alternative valuation technique
2 September 2004 © Scholtes 2004 Page 9
What’s the value of a staged investment?
Phase 1 Phase 2 SalesPhase 3
-$10 M -$80 M -$120 M -$500 M
$0 $0 $0 $1,000 M
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
2 September 2004 © Scholtes 2004 Page 10
What’s the value of a staged investment?
Phase 1 Phase 2 SalesPhase 3
-$10 M -$80 M -$120 M -$500 M
$0 $0 $0 $1,000 M
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
Traditional valuation - risk-adjusted NPV (R-NPV or ENPV)
Sum of discounted cash flows weighted with probability of occurrence
2 September 2004 © Scholtes 2004 Page 11
What’s the value of a staged investment?
Phase 1 Phase 2 SalesPhase 3
-$10 M -$80 M -$120 M -$500 M
$0 $0 $0 $1,000 M
Traditional valuation - risk-adjusted NPV (R-NPV or ENPV)
Sum of discounted cash flows weighted with probability of occurrence
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
-$10 -80% * $80 -80%*70% * $120 +80%*70%*50% * $(1000-500) = -$1.2
2 September 2004 © Scholtes 2004 Page 12
What’s the value of a staged investment?
Phase 1 Phase 2 SalesPhase 3
-$10 M -$80 M -$120 M -$500 M
$0 $0 $0 $1,000 M
What if sales / cost projections changeduring development?
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
2 September 2004 © Scholtes 2004 Page 13
What’s the value of a staged investment?
Phase 1 Phase 2 SalesPhase 3
-$10 M -$80 M -$120 M -$500 M
$0 $0 $0 Projected Sales
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
$1,400
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,200$1,00
0
50/50 chance ofup or down
2 September 2004 © Scholtes 2004 Page 14
What’s the value of a staged investment?
Phase 1 Phase 2 SalesPhase 3
-$10 M -$80 M -$120 M -$500 M
$0 $0 $0
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
$1,400
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,200$1,00
0
50/50 chance ofup or down
Projected Sales
1/8
3/8
3/8
1/8
Average= $1,000
2 September 2004 © Scholtes 2004 Page 15
What’s the value of a staged investment?
$1,400
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,200$1,00
0
50/50 chance ofup or down
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
-$10 M -$80 M -$120 M -$500 M
How does the project value change with changing sales projections?
Want to take account of future continuation decisions
2 September 2004 © Scholtes 2004 Page 16
What’s the value of a staged investment?
-$10 M -$80 M -$120 M -$500 M
$1,400
50/50 chance of up or down
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,200$1,00
0
$?
$?
$?
$?
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
Key idea: Begin in the future and evaluate backwards
2 September 2004 © Scholtes 2004 Page 17
What’s the value of a staged investment?
-$10 M -$80 M -$120 M -$500 M
$1,400
50/50 chance ofup or down
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,200$1,00
0
$1,100$700
$300
$0
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
100,1500600,1 :NPV
700500200,1 :NPV
300500800 :NPV
launcht Don' 100500400 :NPV
2 September 2004 © Scholtes 2004 Page 18
What’s the value of a staged investment?
-$10 M -$80 M -$120 M -$500 M
$1,400
50/50 chance ofup or down
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,200$1,00
0
$1,100$700
$300
$0$?
$?
$?
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
2 September 2004 © Scholtes 2004 Page 19
What’s the value of a staged investment?
$1,200
-$10 M -$80 M -$120 M -$500 M
$1,400
50/50 chance ofup or down
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,000
$1,100$700
$300
$0$0
$130
$330
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
330120-700)50%1,100(50%50% :NPV-R
130120-300)50%700(50%50% :NPV-R
proceedt Don'45120-300)(50%50% :NPV-R
2 September 2004 © Scholtes 2004 Page 20
What’s the value of a staged investment?
50/50 chance ofup or down
-$10 M -$80 M -$120 M -$500 M
$1,400
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,200$1,00
0
$1,100$700
$300
$0$0
$130
$330
$0
$81
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
2 September 2004 © Scholtes 2004 Page 21
What’s the value of a staged investment?
$1,200
-$10 M -$80 M -$120 M -$500 M
$1,400
50/50 chance ofup or down
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,000
$1,100$700
$300
$0$0
$130
$330
$0
$81$22.4
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
2 September 2004 © Scholtes 2004 Page 22
What’s the value of a staged investment?
$1,200
-$10 M -$80 M -$120 M -$500 M
$1,400
50/50 chance ofup or down
$1,600
$400
$800
$1,200$1,00
0
$600$800
$1,000
$1,100$700
$300
$0$0
$130
$330
$0
$81$22.4
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
Read off optimal future decisions:Abandon after phase 1 if the downside scenario occurs, else continue whenevera phase is successful
2 September 2004 © Scholtes 2004 Page 23
What’s the value of a staged investment?
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
-400 -300 -200 -100 0 100 200 300 400 500 600 700 800 900 1000
Target Value ($M)
Pro
bab
ilit
y th
at t
arg
et v
alu
e is
no
t ac
hie
ved
With Decisions Without Decisions
Let’s not forget: The value of a project is a shape!
Project abandonmentwas right in hindsight
Project abandonment was wrong in hindsight
2 September 2004 © Scholtes 2004 Page 24
Spreadsheet analysis
Model of phase-to-phase change of revenue estimatesHere: 50/50 chance of 200 up or 200 down (you may want to use a different type of model, e.g. percentage deviations,three or more change scenarios, etc.)
2 September 2004 © Scholtes 2004 Page 25
Walk away if NPV is negative.
In this case value = 0
Spreadsheet analysis
=MAX(E2-$E$8,0)
NPV for high revenue scenario= PV of sales - investment
2 September 2004 © Scholtes 2004 Page 26
Spreadsheet analysis
2 September 2004 © Scholtes 2004 Page 27
Spreadsheet analysis
R-NPV=Expected PV of future sales - investment
Success probability of phase III
Expectedrevenue if phaseIII is successful
Cost to proceed to phase III
=MAX($D$7*(50%*E10+50%*E11)-$D$8,0)
2 September 2004 © Scholtes 2004 Page 28
Spreadsheet analysis
2 September 2004 © Scholtes 2004 Page 29
Calculate R-NPV backwards as for Phase III
Spreadsheet analysis
2 September 2004 © Scholtes 2004 Page 30
Value of the project with downstream decisions taken into account
Spreadsheet analysis
2 September 2004 © Scholtes 2004 Page 31
What’s the value of a staged investment?
Value as a function of uncertainty
-5
0
5
10
15
20
25
30
35
0 50 100 150 200 250
Phase-to-phase scenario deviations from projected sales
Val
ue
($
Mio
)
Value with downstream decisions Value w/o downstream decisions
R-NPV is correct if uncertainty is low or if there are no downstream decisionsOption value comes from interplay between uncertainty and flexibility
R-NPV=-$1.2M
2 September 2004 © Scholtes 2004 Page 32
What’s the value of a staged investment?
Value as a function of uncertainty
-5
0
5
10
15
20
25
30
35
0 50 100 150 200 250
Phase-to-phase scenario deviations from projected sales
Val
ue
($
Mio
)
Value with downstream decisions Value w/o downstream decisions
R-NPV is correct if uncertainty is low or if there are no downstream decisionsOption value comes from interplay between uncertainty and flexibility
R-NPV=-$1.2M
Key for communication: Clear connection between DCF value and Real Options value
2 September 2004 © Scholtes 2004 Page 33
A quick word about discount rates
Recall
Discount rate reflects• Reward for taking general macro-economic risk (government bond
rate)• Reward for taking debt risk: Default (corporate spread = corporate
bond rate – government bond rate)• Reward for taking equity risk: Volatile returns (CAPM)
Practice: Company hurdle rate, reflecting WACC• Generally higher than government bond rates (“risk-free” rate,
time-value of money)• Reflecting intrinsic risk of company / industry
2 September 2004 © Scholtes 2004 Page 34
Discount rates
Distinguish between “Options phase” and “Asset phase” of a project
• Investments during options phase are considered as payment for “option to make a (typically larger) future investment”
• Asset phase begins when the final “big investment” is madeU̵ Launch of new productU̵ IPO for VC
Options phase is riskier, capital is more expensive• Apply higher discount rate during options phase and lower rate
during asset phase
2 September 2004 © Scholtes 2004 Page 35
Discounting in staged projects
NPV-type analysis: Time for calculation of project value is time of investment
• Discounting to today
Real Options: Time of calculation of project value should be the time when the investment turns into a standard asset (i.e. no more investment in option)
Discount forward to beginning of asset phase using high rate during “Options” phase
Discount backwards to beginning of asset phase using standard discount rate
2 September 2004 © Scholtes 2004 Page 36
Year 0 3 5 8 9 10 11Success Probability 20% 40% 70% 100%Capital cost 30% 30% 30% 10% 10% 10% 10%Cash flow -1 -5 -20 -320 225 270 90Options discounting:Year -8 -5 -3 0 1 2 3DCF -8.15731 -18.5647 -43.94 -320 204.5455 223.1405 67.61833Expected DCF -8.15731 -3.71293 -3.5152 -17.92 11.45455 12.49587 3.786627Value in year 0: -5.5684NPV discounting:Year 0 3 5 8 9 10 11DCF -1 -2.27583 -5.38658 -149.282 95.42196 104.0967 31.54445Expected DCF -1 -0.45517 -0.43093 -8.35981 5.34363 5.829415 1.766489Value in year 0: 2.693629
Options Phase Asset Phase
Example
2 September 2004 © Scholtes 2004 Page 37
What’s the value of a staged investment?
Phase 1 Phase 2 SalesPhase 3
-$10 M -$80 M -$120 M -$500 M
$0 $0 $0 $1,000 M
Now Year 7Year 4 Year 9
80% 50%70%Success?
Time
Discounted forward to year 9at “options discount rate”
Discounted backwards to year 9 at WACC
2 September 2004 © Scholtes 2004 Page 38
Summary of scenario tree approach
What triggers downstream decisions?• “underlying uncertainty”• Here: Revenue estimate
Model evolution of the underlying uncertainty• Scenario tree
Model evolution of the FUTURE project value for all scenarios, taking account of future decisions
• Begin in the future and evaluate backwards in time• Surprisingly simple in spreadsheets
2 September 2004 © Scholtes 2004 Page 39
Summary of key concepts
A staged project cannot be properly evaluated without taking downstream decisions into account
• Another manifestation of the FLAW OF AVERAGES• Value of the project on the basis of average sales = -$1.2 M• Average value of the project = $22.4 M
Downstream decisions increase project value• Flexibility: Flaw works for you• Constraints: Flaw works against you (e.g. capacity case)
2 September 2004 © Scholtes 2004 Page 40
A bit more about the mechanics…
2 September 2004 © Scholtes 2004 Page 41
Modelling the underlying
Underlying is often an “expected value” in the sense that it is our best estimate (or the market price) associated with an uncertain future value
• Model: stock price• Example: Revenue expectations for drug
Simple models: • Binomial lattice • Trinomial lattice
Possible models, given value S today, • Additive: Upward Scenario = S+U, Downward Scenario = S-D• Multiplicative: Upward Scenario = u*S, Downward Scenario = d*S
Multiplicative model preferred because• Value cannot go negative if u,d>0• Value increment proportional to current value (state dependence)
2 September 2004 © Scholtes 2004 Page 42
Modelling the underlying
Convergence of additive model to normal distribution• Central limit theorem
Convergence of multiplicative model to log-normal distributionLet Xt be the rate of change of value during t-th period
Sn =S0 *X1 *….* Xn
ln(Sn/S0 )= ln(X1)+….+ln(Xn)
Central limit theorem: ln(Sn/S0 ) is close to normal if Xt’s are independent r.v.’s
Multiplicative binomial lattice is the prevalent model for stock prices
• Corresponding valuation of financial option with the stock price as underlying is the same as Black-Scholes formula
2 September 2004 © Scholtes 2004 Page 43
Martingale property
Current value of the underlying = our expectation of its future value given that we are in the current state
St=E(St+1|St)
In lattice model need to make sure that this is the case for each “atom” of the lattice
S
p1
p2
pn
u1*S
u2*S
un*S
.
.
.
2 September 2004 © Scholtes 2004 Page 44
Martingale property
Multiplicative binomial lattice upwards at factor u and probability p, downwards with factor d and probability 1-p
Binomial lattice with expected growth at rate (1+r)
Martingale property: Value today will be expected value in the next period discounted at growth rate
du
dppdup
1
1)1(
du
drprpdup
1
1)1(
2 September 2004 © Scholtes 2004 Page 45
Martingale property
Multiplicative trinomial lattice with upwards scenario growth factor u>1 and probability p, downwards scenario growth factor d=1/u <1 and probability q, and growth of expected rate (1+r) with probability 1-p-q
Martingale property (assuming expectation grows at rate r)
Can use u and p as free parameters, provided the calculated q as well as 1-p-q are non-negative
• If r=0 then this amounts to 0<=p<=1/(u+1)
ru
uupqrqp
u
qpu
111
2 September 2004 © Scholtes 2004 Page 46
First Part of Biotech Case(No Contract Valuation, yet)
You will need BiotechCase.xls