ADB Loan 8271-CAM (SCF) / 3007-CAM (SF) ADB Grant 0350-CAM (SCF)
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM
QUARTERLY PROGRESS REPORT Q2 2016
MEF/PMO 9/15/2016
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
i
TABLE OF CONTENTS
A. INTRODUCTION ............................................................................................................................... 1
B. BASIC DATA ..................................................................................................................................... 2
C. PROGRAM PURPOSE AND IMPACT ................................................................................................. 4
D. SUMMARY OF PROJECT STATUS ..................................................................................................... 6
E. UTILIZATION OF FUNDS .................................................................................................................. 7
F. SUMMARY OF PHYSICAL IMPLEMENTATION PROGRESS ................................................................ 8
G. PROGRESS AND ACHIEVEMENTS DURING Q2 2016 ........................................................................ 9
H. GENDER ACTION PLAN .................................................................................................................. 12
I. ENVIRONMENT AND CLIMATE CHANGE ....................................................................................... 12
J. RESETTLEMENT ............................................................................................................................. 13
K. ASSESSMENTS OF RISKS, ASSUMPTIONS AND COMPLAINCE WITH CONVENANTS ...................... 13
L. PROGRAM ISSUES AND REMEDIAL ACTION .................................................................................. 15
Annex 1 Monitoring Frameworks
Annex 2 Financial Summaries
Annex 3 Policy Complaince Matrix
Annex 4 Summary of Physical Progress 2 – 6
Annex 5 GAFSP Progress Report
Annex 6 Gender Action Plan
Annex 7 PIC Activities
Annex 8 Status of Procurement of Contract Packages
Annex 9 Agreed Action Plan
Annex 10 Summary of Priority Sub-projects
Annex 11 Risk Management Matrix
Annex 12 Compliance with Loan and Grant Covenants
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
ii
ACRONYMS AND ABBREVIATIONS
ADB Asian Development Bank
AEA Agro-ecosystems Analysis
AFD Agence Française de Développement
AFD-SCCRP AFD Support to the Commercialization of Cambodian Rice Program
BER Bid Evaluation Report
CARDI Cambodian Agricultural Research and Development Institute
CARM ADB Cambodian Resident Mission
CCCA Cambodia Climate Change Alliance
CEFP Committee for Economic and Financial Policies
CISIS Cambodia Information System on Irrigation Schemes
CLUP Commune Land-use Planning
CS Construction Supervision
DAE Department of Agricultural Extension
DAEng Department of Agricultural Engineering
DD Detailed Design
DMF Design and Monitoring Framework
EARF Environmental Assessment Review Framework
EIA Environmental Impact Assessment
EMP Environment Management Plan
EoI Expression of Interest
FAO Food and Agriculture Organization (of the United Nations)
FS Feasibility Study
FWUCs Farmer Water User Community
GAFSP Global Agriculture and Food Security Program
GAP Gender Action Plan
GDA General Directorate of Agriculture (of MAFF)
GIS Geographic Information System
IEE Impact Environment Examination
ISS Implementation Support Specialist
LLL Laser Land Levelling
LUP Land Use Planning
M&E Monitoring and Evaluation
MAFF Ministry of Agriculture, Forestry and Fisheries
MEF Ministry of Economy and Finance
MIH Ministry of Industry and Handicrafts (formerly under MIME)
MLMUPC Ministry of Land Management, Urban Planning and Construction
MOWRAM Ministry of Water Resources and Meteorology
NIO National Implementation Office
O&M Operation and Maintenance
PDA Provincial Department of Agriculture
PDWRAM Provincial Department of Water and Resources and Meteorology
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
iii
PIC Project Implementation Consultants
PIO Provincial Implementation Offices
PMO Project Management Office
PPCR Pilot Program for Climate Resilience
PPMS Program Performance Monitoring System
PPP Public-Private Partnership
PPTA Preparatory Project Technical Assistance
QPR Quarterly Progress Report
RGC Royal Government of Cambodia
RSPG Rice Seed Producer Group
SCF Strategic Climate Fund
SDP Sector Development Program
SIP Sub-project Identification Proposal
SNEC Supreme National Economic Council
SPCR Strategic Program for Climate Resilience
TA Technical Assistance
ToT Training of Trainers
TOR Terms of Reference
UNFCC United Nations Framework Convention on Climate Change
WICI Weather-indexed Crop Insurance
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
1
A. INTRODUCTION
1. The Climate Resilient Rice Commercialisation Sector Development Program (Rice-
SDP), which commenced in November 2013, supports the implementation of the ‘Policy on
the Promotion of Paddy production and Rice Export’ of the Royal Government of Cambodia
(RGC). It is designed to help transform the predominantly subsistence rice sector into a
commercially oriented one by improving household and national food security and expand rice
export through (i) removing the legal and regulatory constraints inhibiting rice
commercialization; (ii) improving productivity of paddy crops and consistency in quality of
milled rice; (iii) enhancing rice value chain support services; and (iv) addressing risks of
climate change through mitigation and adaptation.
2. The Quarterly Progress Report (QPR) for Quarter 1 of 2016 provides a description of
the progress that has been achieved during that period. The PPMS that has been developed
by the PIC team is being integrated into the QPRs commencing in this quarter, in order to
allow more time for training of the PIO and NIO teams in the collection of the data for each
indicator and the establishment of the database for each office. The QPR also includes as
summary of the financial progress although the rates of disbursement are still very low due to
the long delays in the commencement of many activities. It is anticipated that commencing in
Q2 the rates of disbursement will improve.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
2
B. BASIC DATA
ADB Loan/Grant Numbers
ADF Loan 3006 - CAM; ADF Loan 3007 - CAM; SCF Loan 8271 - CAM; Grant SCF 0350 - CAM; GAFSP Grant 0349 - CAM.
Program Title Climate Resilient Rice Commercialization Sector Development Program (Rice SDP)
Borrower Royal Government of Cambodia
Executing Agency Ministry of Economics and Finance (MEF)
Implementing Agencies
Ministry of Agriculture, Forestry and Fisheries (MAFF) Ministry of Water Resources and Meteorology (MOWRAM) Ministry of Land Management, Urban Planning and Construction (MLMUPC) Provincial Governments (Battambang, Kampong Thom and Prey Veng)
Program Steering Committee
Committee for Economic and Financial Policies (CEFP)
Total Project Cost (USD million)
87.41 (excluding taxes and duties of USD 5 million)
Program Financing (USD million)
ADB Loans
ADF 3006 - CAM: 24.00 ADF 3007 - CAM: 31.00 SCF 8271 - CAM: 5.00 ADB Grants
SCF 0350 - CAM: 4.50 GAFSP 0349 - CAM: 14.60
Date of Loan/Grant Approval by ADB
27th June 2013 for all Loans and Grants
Date of Signing of Loan/Grant Agreements
26th August 2013 for all Loans and Grants
Date of Effectiveness of ADB Loan/Grant
13th November 2013 for all Loans and Grants
Closing Date of ADB Loan/Grant
30th June 2017 for ADB Loan 3006 - CAM 31st March 2020 for other ADB Loan and Grants and GAFSP Grant
Dates of Last ADB Review Mission
21 Apr - 10 May 2016
Program Impact Increased net incomes of stakeholders along the rice value chain.
Program Outcome Enhanced production of quality rice in Cambodia while preserving the natural resource base.
Components
1. Conducive legal framework and regulatory environment established to facilitate climate-resilient commercialization:
- Promoting production and distribution of improved quality seed. - Strengthening agricultural land management. - Strengthening farmer’s organisations and promoting contract farming; - Facilitating the domestic trading and export of milled rice.
2. Agricultural land-use zoning improved:
- Establishing land-use zones. - Updating rice ecosystems and soil classification maps for identification of higher
yielding rice growing areas. - Incorporating agro-ecosystems analysis into commune land-use planning; - Developing the capacity of MLMUPC at national and sub-national levels to
undertake joint work in relation to agricultural land-use planning. 3. Climate resilient rice value chain infrastructure developed
- Rehabilitation and climate proofing of irrigation systems.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
3
- Construction of paddy drying and storage facilities. - Construction of seed cleaning, drying, grading and storage facilities.
4. Rice value chain support services enhanced to improve quality of Cambodian rice
- Improving the availability and quality of commercial rice seed; - Upgrading technical extension materials to guide production in the four main
rice crops. - Capacity building (technical and financial) of mill managers and operators; - Facilitating access to credit by farmers, traders and millers.
5. Weather Indexed Crop Insurance (WICI) piloted
- Undertaking a detailed Feasibility Study (FS) to determine the appropriateness of a WICI scheme.
- Designing the operational parameters, product penetration plan and institutional arrangement.
- Piloting the scheme in selected areas in three target provinces. 6. Efficient program management and implementation
- Effective project management; - Capacity building of the Project Management Officer (PMO) and each national
Implementation Offices (NIOs) and the Provincial Implementation Offices (PIOs).
- Coordination between policy development and investment activities.
Program Area
The Project covers three provinces: Battambang (BTB), Kampong Thom (KPT) and Prey Veng (PRV). A number of sub-projects will be carried out in each target province for (i) rehabilitation of existing irrigation, drainage and flood control systems; (ii) paddy drying and storage facilities to be operated by private sector under Public Private Partnerships (PPPs); and (iii) rice seed drying and storage facilities to be operated by private sector under PPP arrangements.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
4
C. PROGRAM PURPOSE AND IMPACT
4. The Climate Resilient Rice Commercialization Sector Development Program (Rice-
SDP) comprises a policy-based program loan together with other loans and grants from ADB
sources. The Rice=SDP impact will be increased net incomes of stakeholders along the rice
value chain. The outcome is enhanced production of quality rice in Cambodia while preserving
the natural resource base.
5. The Rice-SDP will address key high priority and strategic measures stated in the Rice
Policy to improve national food security and expand rice export through (i) removing legal and
regulatory constraints inhibiting rice commercialization; (ii) improving productivity of paddy
crops and consistency in quality of milled rice; (iii) enhancing rice value chain support services;
and (iv) addressing risks of climate change through mitigation and adaptation. The Rice-SDP
has the following six outputs:
Output 1 - A Conducive Legal and Regulatory Environment established to facilitate
Climate-Resilient Rice Commercialization
This output focuses on legal and regulatory reforms that (i) promote production and
distribution of improved quality seed; (ii) strengthen agricultural land management; (iii)
strengthen farmers’ organizations and promote contract farming; and (iv) facilitate the
domestic trading and export of milled rice.
Output 2 - Agricultural Land-use Zoning improved
This output comprises: (i) establishing land-use zones; (ii) updating rice ecosystems
and soil classification maps for identification of higher yielding rice growing areas; (iii)
incorporating Commune Agro-Ecosystem Analyses into commune land-use planning;
and (iv) developing the capacity of Ministry of Agriculture, Forestry and Fisheries
(MAFF) and Ministry of Land Management, Urban Planning and Construction
(MLMUPC) at the national and sub-national levels to undertake joint work in relation to
agricultural land-use planning.
Output 3 - Climate Resilient Rice Value Chain Infrastructure developed
This output comprises high priority investments in three major rice-producing provinces
– Battambang (BTB), Kampong Thom (KPT), and Prey Veng (PVG). The investments
include: (i) rehabilitation and climate proofing of irrigation systems; (ii) construction of
paddy drying and storage facilities; and (iii) construction of seed cleaning, drying,
grading and storage facilities. The investments have been identified and prioritized
based on provincial development priorities.
Output 4 - Rice Value Chain Support Services Enhanced to Improve Quality of
Cambodian Rice
This output comprises: (i) improving the availability and quality of commercial rice
seed; (ii) upgrading technical extension material to guide production in the four main
rice crops; (iii) capacity building (technical and financial) of mill managers and
operators; and (iv) facilitating access to credit by farmers, traders, and millers.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
5
Output 5 - Weather-indexed Crop Insurance (WICI) Piloted
This output comprises: (i) undertaking a detailed feasibility study to determine the
appropriateness of a weather-indexed crop insurance scheme; (ii) designing the
operational parameters, product penetration plan, and institutional arrangements; and
(iii) piloting the scheme in selected areas in three program provinces.
Output 6 - Efficient Program Management and Implementation
This output comprises: (i) effective program management; (ii) capacity building of the
Program Management Office (PMO) and each National Implementation Office (NIO)
and Provincial Implementation Office (PIO); and (iii) coordination between policy
development and investment activities.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
6
D. SUMMARY OF PROJECT STATUS
Status of project scope/implementation arrangements compared with those in the report and RRP, and whether major changes have occurred or will need to be made:
The Program has made slow progress so far due to a number of factors concerning the Project Implementation Consultant (PIC) team and also the limited capacity of the IAs and
their relative unfamiliarity with ADB project procedures. The scope and implementation arrangements remain in line with those of the RRP to date.
Assessment of the likelihood that the Project purpose will be met in part or in full, and whether remedial measures are required based on the current project scope and
implementation arrangements:
It is too early to make any definitive judgement on this. The Program has made very limited progress during the first year but the achievement of the compliance conditions for the
Program loan fund release are reasonably well on track. With the restructuring of the PIC team and the mobilisation of key team members there can now be much more consistent
and skilled technical support provided to the IAs. The production of the PPMS and the AWPB for 2016 these will provide a guide for the implementation during 2016 and a better
means of tracking performance.
An assessment of changes to the key assumptions and risks that affect attainment of the development objectives:
Of the risks identified in the RRP the most challenging issue concerns “the inherently complex nature of sector development program modality and limited technical skills and resources
to implement legal and regulatory reforms”. PIC Agricultural Policy Specialists are assisting the government in implementing legal and regulatory reforms for compliance with the
release of the Second Tranche in Q2 2016. The current situation is summarised in Annex 3.
Other program developments, including monitoring and reporting on environmental and social requirements that might adversely affect the pro's viability or
accomplishment of immediate objectives:
At this early stage, no significant factors have emerged which might adversely affect the project’s long-term viability. The accomplishment of immediate objectives is partly
constrained by the issues that are described in Section J.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 QPR 2016
7
E. UTILIZATION OF FUNDS
6. The Climate Resilient Rice Commercialization Sector Development Program (Rice-
SDP) is funded through loans/grants from ADB with a total amount of USD 63.3 million,
together with a Program loan amounting to USD 24 million. The breakdown is as follows:
ADB Program Loan No. 3006 - CAM USD 24.0 million
ADB Loan No. 3007 - CAM USD 31.0 million
Global Agriculture & Food Security program (GAFSP) Grant No. - 0349 USD 14.6 million
Strategic Climate Fund (SCF) Loan No. 8271 - CAM USD 5.0 million
SCF Grant No. 0350 - CAM USD 4.5 million
Royal Government of Cambodia USD 8.3 million
7. The cumulative disbursement (for investment and recurrent costs) for each funding
source is as follows:
Table 1
Summary of Cumulative Disbursement by EA/IAs and Funding Source (to 30 June 2016)
(USD)
8. The overall cumulative disbursement, for investment and recurrent (implementation
and supervision costs), at the end of Q2 2016 was USD 1,703,369 (70 percent) and 728,971
(30 percent) respectively and the overall disbursement rate was 6.8 percent.1 The cumulative
disbursement during 2016 amounted to USD 992,198 which represented a disbursement rate
of 15 percent against the AWPB for 2016.
1 Annex 2 contains Summary Tables of Expenditure and Disbursement Progress.
Agency/
Category
Overall
Budget
Cumulative
Disbursement to
date
Budget
Balance
%
Disbursement
rate
MEF/PMO 11,424,300 1,590,779 9,833,521 14%
MAFF/NIO 23,751,900 221,212 23,530,688 1%
MOWRAM/NIO 17,957,200 241,209 17,715,991 1%
MLMUPC/NIO 2,917,500 103,353 2,814,147 4%
BTB/PIO 2,144,800 91,490 2,053,310 4%
KPT/PIO 2,144,800 99,391 2,045,409 5%
PVG/PIO 2,144,800 84,905 2,059,895 4%
ADB Loan No. 3007 - CAM 30,073,600 1,278,023 28,795,577 4%
GAFSP Grant No. 0349 14,601,400 260,631 14,340,769 2%
SCF Grant No. 0350 - CAM 4,997,600 0 4,997,600 0%
SCF Loan No. 8271 - CAM 4,501,200 313,823 4,187,377 7%
RGC 8,311,500 579,863 7,731,637 7%
Total Budget 62,485,300 2,432,340 60,052,960 4%
EA/IA
Source of Funds
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
8
F. SUMMARY OF PHYSICAL IMPLEMENTATION PROGRESS
9. Early in the quarter the Annual Work Plan and Budget (AWPB) for 2016 received an
endorsement from the ADB/CARM and a launching workshop was conducted on 10th June
with the participation of all NIOs and PIOs.
10. Some further progress on agricultural policy in relation to seed which have reached
the 2nd draft stage meaning that full compliance for these conditions can be achieved within
the October 31 timeframe. However, in the case of land and plant protection there has been
slower progress and additional time may be required in order to achieve full compliance.
11. Under Output 2 the ToT for the conduct of the Commune Agro-Ecosystems Analysis
(CAEA) has commenced in BTB province with the support of the PIC team. The ToT for the
Commune Land Use Planning (CLUP) service contract has been drafted and the training
materials for the Training of Trainers (ToT) for CLUP are being prepared. A training on soil
surveying and soil classification techniques was conducted by MAFF/NIO in KPT province for
provincial and district extension staff.
12. For Output 3 the Feasibility Study, Detailed Design and Construction Supervision
(FS/DD/CS) consultants recruited by MOWRAM/NIO were mobilised and commenced work
on the Detailed Designs for two core irrigation sub-projects in BTB and KPT provinces. The
ToR for the FS/DD/CS for paddy drying and storage was revised and split into two phases to
cover the initial assessment/feasibility study of selected facilities and then the preparation of
detailed designs and construction supervision respectively. A further round of meetings
occurred to discuss the implementation approach for the Laser Land Levelling (LLL), field level
consultations took place with farmers in some irrigation sub-projects sites and a consultative
workshop was conducted in KPT with local contractors to discuss further contractual
arrangements.
13. Under Output 4 the MAFF/GDA has allocated working space for the establishment of
the seed testing laboratory, and the bids for the supply of the seed testing equipment are being
evaluated. The MAFF/NIO team commenced the ToT for rice seed production with extension
staff from all three provinces.
14. For Output 5 the ToR for the WICI has been revised and split into two phases to cover
the initial feasibility study and then the conduct of the pilot testing respectively.
15. There was a total of eight international consultants and ten national consultants
working during the quarter. The new international and national Business Finance and Credit
Specialists were both mobilised.
16. ADB conducted a Review Mission from 21st April to 10th May which was led by the
Project Officer from ADB/Cambodia Resident Mission (CARM). The Aide Memoire included
an agreed action plan and the current status of the action plan in shown in Annex 9.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
9
G. PROGRESS AND ACHIEVEMENTS DURING Q2 2016
17. The main accomplishments during Q2 can be summarised as follows:2
G.1 Output 1: Conducive Legal and Regulatory Environment
18. The current status of the progress of the compliance with the covenants is summarised
as follows:
Promoting local seed production and distribution: No regulations related to seed
(policy conditions 1 to 5) have yet been issued. The 1st drafts have been submitted to
MEF and the Technical Working Group (TWG) is organising meetings and/or
consultations as needed to prepared the 2nd drafts. It is expected that the 2nd drafts will
be submitted to MAFF early in July 2016. This 2nd drafts will be reviewed by MAFF as
a part of the weekly committee meeting in charge of policy review. In the event that
additional revisions may be requested by MAFF to the TWG 3rd drafts will be prepared
which will constitute the final draft that is issued/approved by MAFF. The finalisation of
this process will take four months meaning that the compliance can be fully satisfied
by October 2016.
Strengthening agricultural land management: The documents related to the Policy
Conditions on Land (conditions 7 to 9) still require more work, particularly related to
the role of women. Consultations at national and regional level are also yet to be
undertaken.
Improvement phytosanitary restrictions: A 1st draft has been submitted to MEF by
the TWG with a copy to MAFF but there has not yet been any consultation on this draft.
It will require further work to clarify its content and incorporate stakeholders (particularly
private sector) comments. MAFF will also need to conduct inter-ministerial
consultations and submit the draft law to the Council of Ministers.
G.2 Output 2: Agricultural Land-Use Zoning Improved
G.2.1 Output 2.1: Undertake Commune Agro-Ecological Analysis
19. The ToT for CAEA was completed in BTB province and during reflection and review
by the MAFF/NIO team assisted by the PIC team there were a number of lessons identified
and necessary changes will be made to the methodology. The ToT for CAEA in KPT
commenced on 27 June and will be completed in mid-July. The PIC team are participating in
this ToT also so support the MAFF/NIO and PDA staff.
G.2.2 Output 2.2: Incorporation of the CAEAs into the Commune Land Use Plans
20. The guidelines for the CLUP have been revised with the support of the PIC team
members and the ToR for the CLUP contract services have been drafted and are currently
being reviewed by the MLMUPC/NIO team. It is intended that the Training of Trainers (ToT)
on CLUP for provincial and district team members will be conducted in Q3 and the preparation
of the training materials has commenced.
2 See Annex 3 for more detailed status report on agricultural policy work (Output 1) and Annex 4 for description of
the progress for Outputs 2 to 6.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
10
G.2.3 Output 2.3: Rice ecosystem Mapping
21. The MAFF/NIO team have conducted a training on soil surveying techniques for the
PDA and DOA staff in KPT province. The training included both classroom sessions and also
field practice on the procedures for collection of soil samples. Further training will be required
to enable the staff to gain a better understanding of the principles of soil science and rice soil
classification.
G.3 Output 3: Climate Resilient Rice Value Chain Infrastructure developed
G.3.1 Output 3.1: Recruitment of national consultants for irrigation sub-project
feasibility studies
22. There are 19 irrigation sub-projects that have been prioritized by the Ministry of Water
Resources and Meteorology (MOWRAM). During the quarter the FS/DD/CS consultant team
(KCC) recruited by MOWRAM were mobilised and they commenced work on the two irrigation
sub-projects that were studied during the PPTA, namely Prey Sangha in BTB and Chuck
Ckhsach in KPT. In both cases they have commenced the preparation of the detailed designs
and also updated the Initial Environment Examination done during the PPTA.
G.3.2 Output 3.2: Recruitment of national consultants for seed/paddy drying and
storage facilities
23. In the case of the FS/DD/CS for rice seed/paddy drying and storage facilities there are
11 sub-projects identified by the MAFF/NIO. Following further discussions with ADB/CARM
during the Review Mission it was decided to revise the ToR for the consultants and to separate
the task into two phases. Phase 1 would comprise an initial examination of the proposed sites
and the conduct of feasibility studies after land issues have been resolved. Phase 2 will then
consist of the detailed designs for those facilities which are found to be viable and the
supervision of construction after the civil works contracts have been awarded.
G.3.3 Output 3.3: Works contract procurement for rehabilitation of identified irrigation
schemes
24. The award of the first civil works contracts for the two irrigation sub=-projects currently
under study is expected in Q3.
G.3.4 Output 3.4: Works contract procurement for paddy drying and storage facilities
25. There has been no progress yet. It is envisaged that the works contract procurement
for the first facilities will not commence until Q2 2017.
G.3.5 Output 3.5: Works contract procurement for rice seed drying and storage
facilities
26. There has been no progress yet. It is envisaged that the works contract procurement
for the first facilities will not commence until Q2 2017.
G.3.6 Output 3.6: Contract services for implementation of sub-project associated
initiatives
27. A Concept Paper on Laser Land Levelling (LLL) was prepared by the PIC Team Leader
after consultations with local contractors mainly in BTB province to determine the costs of the
field operations. The Concept Paper included a proposal for the use of a PPP arrangement
for the conduct of the LLL through local contractors. After further discussions with the
MAFF/NIO team it was decided to assess the level of interest of farmers within some of the
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
11
irrigation sub-project site areas and to determine the extent to which they would pay for
service. T further regional workshop was conducted in KPT with the participation of local
contractors to discuss the mechanism for implementing the LLL but there remained a lack of
agreement on the most effective approach.
28. No activities have commenced for strengthening of agricultural extension services,
capacity building of the FWUC/FWUGs, market facilitation support or contract farming for rice
seed production all of which will be implemented by the PIOs.
G.3.7 Output 3.7: Procuring Public-Private Partnerships (PPPs) to operate paddy
drying and storage facilities
29. The PIC team have conducted field visits to each province to meet with rice millers and
other stakeholders in the rice sector and as a result have prepared an outline Concept Paper
that identifies three potential models (Options) for the PPP support to paddy drying and
storage. It is planned to conduct a PPP forum in July with private and public sector
participation.
G.4 Output 4: Enhanced rice value chain support services
G.4.1 Output 4.1: Increased availability of quality rice seed
30. Office space within the MAFF/GDA compound has been identified for the
establishment of the seed testing laboratory but no plans have been yet prepared for the
conversion work required. The bidding for the supply of the seed testing equipment has been
completed and the Bid Evaluation Report (BER) has been submitted to ADB/ARM for no
objection.
31. Work has commenced on the preparation of a Rice Seed Action Plan by the PIC team
that includes operational guidelines for a national seed certification scheme. There have been
further discussions with the MAFF/NIO team regarding the mechanisms for involving the
existing MAFF agriculture stations in each province in the production of registered seed of
selected rice varieties. The PIC TL conducted a field visit to Porlos agriculture station in PVG
to collect information on the rice seed production program at that station.
32. The ToT for rice seed production with the participation of 10 staff from the PDAs and
DOAs in each province commenced at Prey Phdao agriculture station in Kampong Speu
province.
G.4.2 Output 4.2: Expand and develop technical extension services
33. No progress has yet been made. This is an activity which is under the responsibility of
the PIOs. There is a need for further discussion between the MAFF/NIO and the PDAs to
identify the scope of these extension activities that will be implemented.
G.4.3 Output 4.3: Enhance business management capacities
34. No progress has been made yet. However, the PIC team mobilised the international
Business Finance and Credit Specialist to conduct an initial study on the management
capacity within the rice milling sector and the availability of financing to rice millers.
G.4.4 Output 4.4: Improved Access to and Reduced Cost of Financing
35. No progress has been made yet. This activity will commence in 2017.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
12
G.5 Output 5: Feasibility Study, Design and Pilot Testing of Weather Indexed Crop
Insurance
36. During the Review Mission there were further discussions with the MAFF/NIO team
and ADB/CARM and it was decided to split the original ToR into two Phases. Phase 1 would
comprise the conduct of the Feasibility Study to determine the viability of the scheme and the
opportunities for its application in Cambodia for rice production. Subject to a satisfactory
outcome of Phase 1 there would follow a Pilot Test of WICI which wold be implemented
through one or more local insurance companies.
G.6 Output 6: Efficient Program management and Implementation
37. The PMO and MAFF/NIO commenced the procurement of the motorcycles for the
PIOs. The PMO commenced the procurement of two additional vehicles. The PMO completed
the procurement of the office furniture and office equipment for the three PIOs. The MAFF/NIO
recruited a Procurement Adviser and the MLMUPC/NIO recruited a Finance Adviser.
38. The PIC team continued to provide technical support to the NIOs and PIOs during the
quarter and mobilised the international Business Finance and Credit Specialist for his first
input. The PIC team have continued to work within the respective line agencies that they are
supporting which has helped to build better working relationships.
39. The PIC team have prepared the first draft of the Project Performance Monitoring
System (PPMS) and delivered the first round of training for the NIO M&E staff and the PIO
teams in each province.
H. GENDER ACTION PLAN
40. Gender considerations are cross-cutting throughout the Rice-SDP and the Program
will enhance access by women at all levels to decision making, resources and services.
Gender issues have also been incorporated into appropriate covenants of the Program Loans
and Grants. A comprehensive Gender Action Plan has been prepared and will be regularly
updated on a quarterly basis.3
41. The PIC team includes two gender experts, one international and one national, who
will be mobilised in early Q3 2016 to support the gender mainstreaming training program and
the assist in the incorporation of guidelines for gender consideration into al manuals that are
developed.
I. ENVIRONMENT AND CLIMATE CHANGE
42. Through the preliminary capacity needs assessment conducted in 2015, it was
identified that the staff of the PMO, NOIs and POIs have a limited knowledge of climate
change. This is in terms of technical, economic, social, political and policy issues and actions
needed on climate change vulnerability and adaptation. It includes the prediction of climate
change impacts and incorporating climate resilience engineering designs for the rehabilitation
of irrigation systems as well as Climate Smart Agriculture (CSA) technologies into rice seed
production programs and agricultural extension programs.
43. During Q2 there were trainings conducted for initial awareness raising on
environmental issues for delivery to all NIO and PIO teams. The climate vulnerability
3 Annex 6 provides the current Gender Action Plan.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
13
assessments for irrigation system and crop insurance produce that are weather-indexed will
be conducted though collecting historical data on climate information over the last ten years
and consultations with key stakeholders in the area of each sub-project in the three provinces.
Climate risk assessments will be conducted to identify the climate change adaptation options
applicable for the sub-project civil works to ensure that they incorporate proofing for climate
change
J. RESETTLEMENT
44. The FS/DD/CS consultant teams that have been recruited by MOWRAM have
commenced a reassessment of the resettlement requirements for the two irrigation sub-
projects in BTB (Prey Sangha) and KPT (Chuck Khsak).
K. ASSESSMENTS OF RISKS, ASSUMPTIONS AND COMPLAINCE WITH
CONVENANTS
K.1 Assessment of Risks and Assumptions
45. A comprehensive assessment of risks and assumptions was undertaken from the
onset on project implementation. This was updated in Q1 2016 to ensure that risk and
assumptions are in line with the current status of implementation. A copy of the updated risk
matrix for the Rice-SDP project can be found in Annex 12.
K.2 Compliance with Covenants
46. The relevant loan agreements covering the Rice-SDP are as follows:
Loan Type Date
Loan Agreement (Special Operations) for Climate Resilient Rice Commercialization Sector Development Program (Loan 3006)
Agreements, Loan Agreement (Special Operations)
August 2013
Loan Agreement (Special Operations) for Climate Resilient Rice Commercialization Sector Development project (Loan 3007)
Agreements, Loan Agreement (Special Operations)
August 2013
Grant Agreement (GAFSP) for Climate Resilient Rice Commercialization Sector Development Project
Agreements, Grant Agreement August 2013
Loan Agreement (ADB Strategic Climate Fund) for Climate Resilient Rice Commercialization Sector Development Project
Agreements, Loan Agreement (Special Operations)
August 2013
Grant Agreement (ADB Strategic Climate Fund) for Climate Resilient Rice Commercialization Sector Development Project
Agreements, Grant Agreement August 2013
K.3 Compliance conditions for ADB Program Loan - 3006 (CAM)
47. The Program Loan Covenants are established in the loan and grant agreements with
further reference to the Development Policy Letter (April 2013) and Appendix 4 Policy Matrix
of the RRP (June 2013).
48. The Loan Agreement for the Commercial Sector Development Program, ADF 3006
(August 2013) includes a specific agreement under Schedule 3 on the withdrawal of funds:
“4. No withdrawal shall be made from the Loan Account for the First Tranche unless
ADB is satisfied that the Borrower has met the policy actions for the release of the
tranche specified in Attachment 2 to this Schedule.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
14
5. Notwithstanding any other provisions of this Loan Agreement and except as ADB
may otherwise agree, no withdrawals shall be made from the Loan Account for the
Second Tranche unless ADB is satisfied, after consultation with the Borrower, that (a)
sufficient progress has been achieved by the Borrower in the carrying out of the
Program; (b) the policy actions that were met for the release of the First Tranche
continue to be complied with by the Borrower; and (c) the Borrower has met the policy
actions for the release of the Second Tranche specified in Attachment 3 to this
Schedule.”
49. The PIC team have continued to provide support to the MAFF/NIO and the TWGs to
enable the achievement of the compliance conditions for the release of the 2nd tranche, which
also require continued compliance by the Borrower for the actions under this 1st tranche. Most
are currently not yet compliant, although for most of these items the Government (MAFF) is in
the process of drafting the necessary legislation or establishing Technical Working Groups to
consider these issues. An update on the progress towards achieving compliance is shown in
Annex 3.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 QPR 2016
15
L. PROGRAM ISSUES AND REMEDIAL ACTION
50. A series of issues were identified during Q1 2016 which are summarised below, together with where appropriate remedial action which is
being applied or is required.
Issue/Problem Proposed Remedial Action(s)
Output 1: Conducive Legal and Regulatory Environment established
Issues and Constraints in Policy Development
There has been some further progress towards achieving compliance with the conditions 1 to 5 relating to seed. However, in the case of the conditions relating to land and plant protection there
remains further progress to be made. In view of the resignation of the PIC national Agricultural Policy Adviser there is an urgent need for a replacement to be recruited, and in order to ensure skilled
support the position will be split and two advisers will be recruited with skills in land and plant protection respectively. In the case of the policy documents on land there is an urgent need for
expertise in gender aspects to examine the drafts that have been prepared. This necessitates the immediate mobilisation of the PIC Social and Gender Experts.
Output 2: Agricultural Land Use Zoning Improved
The award of the contract for CLUP consulting services has been delayed.
The preparation of the ToR for the CLUP service contract has taken an extended period and the draft
has been revised a number of times. There appears to be an acceptance of the fact that a contract
award may not be feasible until Q1 2017 and this will require a rescheduling of the work to ensure
that it can be completed within the Rice SDP timeframe. There are also concerns that the resources
that will be provided to the consultants may not be adequate. In order for the CLUP to be done it is
necessary for the CAEA to be completed and tis process has also been delayed by the absence of
an effective mechanism for funding the district field staff involved in the CAEA field work. MAFF/NIO
should expedite the arrangements for the conduct of the CAEA so that field work can commence
without further delay.
The training on soil surveying and soil classification revealed the very low level of
understanding by the provincial and district extension staff.
Further training and follow up will be needed for the extension staff in each province if there is to be
an improvement in their knowledge. This will need to be given consideration in the AWPB for 2017.
Output 3: Climate Resilient Rice Value Chain Infrastructure developed
There are insufficient funds available to support all of the prioritised irrigation subprojects.
In view of the cost escalations that have occurred since the PPTA was conducted there will need to
be some prioritisation of the irrigation sub-projects. The decision on which sub-projects to complete
should be made in consultation with the PIOs and PDWRAM.
Local contractors have a lack of experience and expertise on land levelling.
There are very few local contractors that have had past experience with LLL. It will be necessary for
the MAFF/NIO to organise training for the contractors who show interest in being contracted for LLL
services. Also farmers need to be made aware of the benefits of LLL and this can only be achieved
by the organisation of demonstrations within some of the irrigation sub-project site areas. The
availability of the equipment for LLL needs to be researched and information shared with local
contractors so that they are aware of potential suppliers of the equipment. The possibility of using a
PPP approach for LLL should be further explored.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q2 2016 QPR
16
Issue/Problem Proposed Remedial Action(s)
The proposed PPP modality in the PAM may not result in interest from the private sector.
The establishment of paddy drying and storage facilities as standalone facilities needs further
consideration to verify that they would be viable and would attract private sector investment. The
proposed management arrangements whereby they remain the property of the provincial
governments also need to be re-evaluated. In the case of the seed drying and storage facilities these
would be best targeted at existing Rice Seed Producer Groups (RSPGs) that have sufficient capacity.
There has been very slow progress on formulating the activities under the Associated
Interventions within the irrigation sub-project site areas.
MOWRAM/NIO and MAFF/NIO will both need to provide additional support to the PIOs to assist them
in the identification of activities to support the formation of FWUC/FWUGs, strengthening of
agricultural cooperatives, enhancing extension services, etc.,
Output 4: Enhanced Rice Value Chain Support Services
A large proportion of the extension staff that are attending the ToT on rice seed production
are not project assigned staff.
This will present a difficulty when the season long FFS are conducted in each province since these
staff will not be eligible to receive the benefits in terms of salary supplements and motorcycles. Given
that there are insufficient district staff deployed under the Rice SDP to support the season long FFS
that will be conducted it will be necessary to propose a different financing mechanism though a LoA
with the PDAs for the payment of DSAs to non-Rice SDP staff and also possible the procurement of
additional motorcycles.
Output 5: Feasibility Study, Design and Pilot Testing of WICI
The structure of the ToR is inappropriate in that the consultants who conduct the
Feasibility Study would also be responsible for the Pilot Study.
The ToR should be revised to split the responsibilities into two phases. The 1st phase is concerned
solely with the Feasibility Study. If the outcome is satisfactory and it is felt to be a viable opportunity
to subject to a Pilot Study then the 2nd phase can proceed.
Output 6: Efficient Project Management and Implementation
Lack of financial capacity within the PIO teams. Long delays have been experienced in
the submission of the financial reports by the PIOs.
The PIOs are all taking steps to recruit a Financial Assistant and once this has been completed the
PMO will be required to organise regular hands-on training for them to ensure they have a sound
understanding of the financial reporting mechanisms.
Lack of office space within the MAFF/NIO
The PIC team members who are supporting the MAFF/NIO have been relocated to their office but
there is a shortage of office space to accommodate them. Some additional office furniture has been
procured but there remains a lack of working space.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
17
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Design Summary
Performance Targets and Indicators with Baselines
Data Sources and
Reporting
Mechanisms
Assumptions and Risks
IMPACT:
Increased net
incomes of
stakeholders along
the rice value chain
Average farming household incomes increased from
$400 in 2010 to $700 by 2020
Revenue of rice exporters increased from
$100 million in 2012 to $600 million in 2020
Net profit of rice exporters increased from
$30 million in 2012 to $180 million by 2020
National Institute of Statistics’ Yearbook
Ministry of Commerce annual trade statistics
Assumption Medium-term macro-economic
Stability.
Risks
Lack of political commitment in Rice-SDP
implementation.
Climate change impacts may undo the intended gains and reduce anticipated benefits.
OUTCOME:
Enhanced production
of quality rice in
Cambodia while
preserving the natural
resource base
Paddy production increased from 8.0 million tons in
2012 to 9.5 million tons by 2018
Milled rice exports increased from 200,000 tons in
2011 to 1.2 million tons in 2017
Wet paddy exports to Viet Nam and Thailand reduced to 0.2 million tons by 2018 (2011 baseline: 2.2 million tons per annum) a.
MAFF annual crop
production
statistics
Ministry of Commerce annual trade statistics
Risks
Institutional and implementation risks from lack of
technical skills and resources.
Improper natural resources management may exacerbate the impacts of climate change.
OUTPUTS:
1. Conducive legal
and regulatory
environment
established to facilitate climate- resilient rice commercialization
By 2015, (i) policy and regulatory framework for local seed production are in place, (ii) guidelines for establishing agricultural land use zones are completed, (iii) legislation on sustainable management and use of agricultural land are operational, (iv) regulatory systems for farmers’ organizations and contract farming are functional, and (v) milled rice standards and trade facilitation measures in place
Tranche compliance reports prepared by the executing agency
Assumption Political parties and beneficiaries are
cooperative in the reform process.
Risk
Policy coordination and enforcement
are not strong.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
18
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Design Summary
Performance Targets and Indicators with Baselines
Data Sources and
Reporting
Mechanisms
Assumptions and Risks
2. Agricultural land-use zoning improved
90 rice growing communes in target provinces
complete AEAs and incorporate into CLUPs by
2017.
90 groups of farmers consulted (with at least
40% female representation) during the
preparation of CLUPs by 2015.
Progress reports produced quarterly by the executing agency
Assumption MLMUPC can accommodate AEAs
as an input to CLUPs.
3. Climate- resilient
rice value chain
infrastructure
developed
23,000 hectares (ha) of command area served
by climate-resilient rehabilitated irrigation
structures by 2017 (40% unskilled laborers
employed in the rehabilitation are women; 50%
of construction subcommittee members are
women; two FWUCs established in each
irrigation scheme, with women occupying 30%
of the management positions).
Four seed drying and storage facilities constructed by 2017 with a combined storage capacity of 8,000 tons (30% unskilled laborers and 50% administrative staff are women).
Capacity for drying paddy in target provinces extended
by 2,000 tons per day and capacity for paddy storage in
target provinces extended by 40,000 tons by 2018.
Progress reports
produced quarterly
by the executing agency
Assumptions
Climate-resilient infrastructure is economically viable
and politically acceptable.
Efficient operation of control structures to deliver water to canals.
Private entities are interested and capable of managing facilities.
Risk
River basin studies do not take climate change impact into
Account.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
19
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Design Summary
Performance Targets and Indicators with Baselines
Data Sources and
Reporting
Mechanisms
Assumptions and Risks
4. Rice value
chain support services enhanced to improve quality of Cambodian rice
2,400 tons of fragrant rice seed produced per
annum in target provinces by 2018
70% of farmers (disaggregated by sex) in target provinces using commercial seed every 2 years by 2018 (2012 baseline: 10%)
30% of farmers (disaggregated by sex) have leveled their paddy fields by 2018 (2012 baseline: 5%); 50% of farmers in target provinces (disaggregated by sex) obtain technical advice through trained input suppliers by 2016 (2012 baseline: 10%)
10 rice millers in target provinces use independent financial management advisory services by 2016 (2012 baseline: 0)
Progress reports produced quarterly by the executing agency
Progress reports produced quarterly by the executing agency
Assumptions
Growers accept the higher price needed
to purchase quality
seed
Farmers have resources to part finance the land leveling
Risk
Drying and storage facilities are not
operated at full
capacity
5. WICI piloted
100,000 ha of rice producing areas covered by
WICI by 2017 (50% of the policy holders
are women, of which 10% are from
households headed by women)
(2012 baseline: 0)
15 local input suppliers, 3 local financial institutions, and 3 local marketing agencies participating in the pilot tests in three provinces by 2015 (2012 baseline: 0)
Feasibility study
report
Design of WICI and evaluation report
Quarterly reports by the insurance firm
Assumption
Feasibility study recommends design and piloting
Risk
Piloting WICI shows no feasibility in
Cambodia
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
20
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Design Summary
Performance Targets and Indicators with Baselines
Data Sources and
Reporting
Mechanisms
Assumptions and Risks
6. Efficient program management and implementation
Rice-SDP performance monitoring system,
disaggregated by sex, designed and operational within 6 months of effectiveness. Baseline surveys completed within 12 months of loans and grants effectiveness and end-line impact evaluation undertaken 6 months
before Rice-SDP completion date
For PMO and PIOs, 30% of administrative
and technical positions are filled by women by
Q3 2013; progress of gender actions included as part of Rice-SDP progress reports. For PMO and PIOs, 30% of administrative
and technical positions are filled by women by
Q3 2013; progress of gender actions included as part of Rice-SDP progress reports
Progress reports produced quarterly by the executing agency. Base-line and end-line impact evaluation by the executing agency
Progress reports produced quarterly by the executing agency
Assumption
Qualified staff are appointed for
Implementation
Risks
Provincial capacity is insufficient
The availability of qualified staff is limited
ADB - Asian Development Bank; ADF -Asian Development Fund; AEA - Agro-Ecosystems Analysis; CLUP - Commune Land-use Plan; FWUC - Farmer Water User Community; GAFSP - Global Agriculture and Food Security Program; MAFF - Ministry of Agriculture Forestry and Fisheries; MLMUPC - Ministry of Land Management Urban Planning and Construction; NIO - National Implementation Office; PIC - Program Implementation Consultant; PIO - Provincial Implementation Office; PMO - Program Management Office; Rice-SDP - Climate Resilient Rice Commercialization Sector Development Program; SCF - Strategic Climate Fund; WICI - weather-indexed crop insurance.
a A separate survey on baseline and target indicator will be conducted during the second year of the program to validate information of informal paddy
trade across the border with Thailand and Viet Nam.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
21
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Activities with Milestones Inputs
1. Improvement of legal and regulatory environment
1.1. Establish policy working groups by Q4 2013
1.2. Produce compliance report for second tranche by Q2 2016 2. Improvement of agricultural land-use zoning
2.1. Undertake commune AEAs by Q4 2017
2.2. Incorporate the AEAs into CLUPs by Q4 2017
2.3. Develop three provincial rice ecosystem maps by Q4 2017 3. Development of rice value chain infrastructure
3.1. Recruit national consultants for subproject feasibility studies by Q3 2014
3.2. Rehabilitate identified irrigation schemes by Q4 2018
3.3. Establish paddy drying and storage facilities by Q4 2018
3.4. Establish seed drying and storage facilities by Q4 2018 3.5. Implement subproject-associated initiatives by Q4 2018 4. Enhancement of rice value chain support services
4.1. Increase availability of quality rice seed
4.1.1. Develop a national seed certification scheme by Q4 2015
4.1.2. Produce foundation and certified seed by Q4 2017
4.2. Expand and develop technical extension services
4.2.1. Revise six “technology information procedures” on rice production by Q4 2015
4.2.2. Develop extension services material by Q4 2015
4.3. Enhance business management capacities
4.3.1. Study the adoption of bulk handling by Q2 2015
4.3.2. Provide technical assistance to rice mill by Q4 2018 4.3.3. Organize study tours and training for millers by Q4 2016
4.4. Improve access to and reduce cost of finance
4.4.1. Develop capacities of financial institutions by Q4 2016 5. Feasibility study, design and pilot testing of WICI
5.1. Engage consultants for feasibility study by Q1 2014
5.2. Determine feasibility of WICI in Cambodia by Q2 2014
5.3. Upgrade automatic weather stations by Q4 2014
5.4. Pilot WICI in selected areas by Q2 2015 6. Project management and implementation
6.1. Appoint and mobilize PICs by Q1 2014
6.2. Design and operate Rice-SDP’s gender disaggregated program performance monitoring system by Q2 2014
1. ADF Policy Loan: $24.00 million
2. ADF Loan: $31.00 million
Item Amount
Civil Works 17.60 Associated Initiatives 0.53
Vehicles & Equipment 0.65
Consulting Services 3.75
Implementation Support 7.54
Interest Charges 0.93 3. GAFSP Grant: $14.60 million
Item Amount Civil Works 0.62 Equipment 7.17
Contract Services 3.28
Office Equipment 0.10 Consulting Services 1.11
Training and Studies 1.81
Implementation Support 0.51 4. ADB SCF Loan: $5.00 million
Item Amount
Civil Works 3.31
Associated Initiatives 1.10
Contract Services 0.59 5. ADB SCF Grant: $4.50 million
Item Amount
Civil Works 0.42
Crop Insurance 2.00
Consulting Services 2.08
6. Government: $8.33 million Item Amount
Staff Costs 1.46
Resettlement Costs 0.43
Land Purchase 0.88
Taxes and Duties 5.54
SCF Loan Service Charge 0.02
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
22
MONITORING FRAMEWORK FOR GAFSP
GAFSP Results Area
Indicators in Cambodia’s GAFSP Rice-SDP Indicators
(with reference to the GAFSP M&E Plan)
1. Raising Agricultural Productivity
An increasingly productive and diversified agricultural system that is capable of assuring food security.
40,000 beneficiary farmers (20,000 are women farmers) and 400
farmer organizations are benefited by extension, technology transfer,
improved production trainings and sets of low-input and improved
technical packages.
- Six technical information procedures for lowland rice production
upgraded by 2017.
- 20,000 days of training to raise agricultural productivity provided to
extension agents, agro-dealers, farmers, community members etc.
(disaggregated by gender).
- 30 subproject contracts providing extension services executed between
Rice-SDP and participating provincial department of agriculture (PDAs)
by 2018, covering an estimated 30,000 households.
- An increment of 30,000 hectares of paddy land on which modern
production technology has been adopted by 2018.
- At least 30,000 households will adopt water saving technology by land
levelling promoted by Rice-SDP by 2018.
Pro-poor and pro-women
community groups, particularly of food-insecure households, who are empowered to actively develop their potentials, opportunities and minimize risks and represent their own interests in political and administrative environment.
Community projects are implemented using participatory
planning techniques.
- Paddy area with improved/rehabilitated irrigation and drainage services
will be 23,000 ha by 2018
- Number of water users provided with new/improved/rehabilitated
irrigation and drainage services (disaggregated by gender) estimated to
be 23,000 by 2018
- Number of operational water user associations estimated to be 23 by
2018 within the subproject areas.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
23
MONITORING FRAMEWORK FOR GAFSP
GAFSP Results Area
Indicators in Cambodia’s GAFSP Rice-SDP Indicators
(with reference to the GAFSP M&E Plan)
Farmers have secure tenure to their land.
Land titles for rural land use are provided to project beneficiaries, including indigenous communities.
- 90 communes will have completed commune land use plans (CLUPs)
based on the agro- ecosystem analyses performed in these communes
by 2017.b/
2. Linking Farmers to Markets
Reduce transfer and transaction costs.
Traditional value chain partnerships strengthened for four commodities in 10 provinces over 3 years.
- 30,000 farming households become members of production association
and water user community members (30% are women) by 2017
Other value addition. Distribution of post-harvest storage systems to project villages by end
of year 4.
- Volume of paddy under improved post-harvest management increased
by 30,000 tons (in terms of storage capacity) by 2018
- Paddy drying capacity increased by 2,000 tons per day by 2018 in
participating provinces
- Six public-private seed processing facilities (grading, dying and storage)
installed by 2018
- 50,000 client days of training on better post-harvest procedures
provided (50% of participants being women)
3. Reducing Risk and Vulnerability
Community self-reliance for food security and nutrition and health.
40,000 households (20,000 women-headed households) are trained in home gardening techniques by year 4.
- A weather-indexed crop insurance scheme introduced to improve
weather-related risks by 2017 (co-financed by PPCR)
- 100,000 ha of rice producing areas covered by a WICI scheme
directed towards vulnerable groups (co-financed by PPCR)
4. Improved Non-farm rural livelihoods
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
24
MONITORING FRAMEWORK FOR GAFSP
GAFSP Results Area
Indicators in Cambodia’s GAFSP Rice-SDP Indicators
(with reference to the GAFSP M&E Plan)
Promoting non-farm rural
entrepreneurship. 4,000 self-help groups organized and functioning by end year 4. Basic administration training conducted within 6-months of self- help group formation. 1,000 micro-businesses (women headed) & 1,000 small-scale agro-processing developed and functioning at basic level by year 3 Community micro-projects are implemented by year 4. Set of vocational training packages are developed by end year 2. 4,000 (2,000 are women) are trained in new and/or additional vocational skills by year 4.
- Number of people trained:
- 10 rice millers trained through advisory services by 2016;
- 100,000 FWUC members trained in group management and irrigation
scheme operations and maintenance by 2018; 100 staff of financial
institutions in participating provinces receive training on the needs of
farmers wishing to diversify their livelihood sources by
- 2018: 1,000 farmers trained in requirements of financial institutions to
assist in gaining access to credit by 2018 (with 30% women participants)
Component 5: Technical assistance, institution building, capacity development
Policies, Plans and regulatory
framework of MAFF are fully established, maintained and coordinated.
MAFF have implemented and enforced
policies, plans, regulations for which they are responsible under this program.
- Five legal and regulatory frameworks will be in place by 2016 to promote
rice commercialization
- 300 participants in M&E workshops, training events, seminars,
conferences etc. (disaggregated by gender and affiliation)
Gender is mainstreamed in MAFF.
The gender unit in MAFF is functioning and fully funded to continue implementation of gender mainstreaming policies.
- Gender targets are mainstreamed into each of the component
outputs under Rice-SDP
Policies and information on aspects of food security related to agriculture and water management.
Food security concepts are integrated
into development programs and policy.
- Food security aspects of the Rice Policy are fully accommodated
under Rice-SDP by 2018
b/
Rice-SDP is not involved in land titling due to its political complexity. However, CLUPs established with assistance from Rice-SDP will facilitate the Government’s work in land titling.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
25
MONITORING FRAMEWORK FOR SCF PPCR
Results Indicators (consistent with PPCR Core Indicators)
Increased resilience of households, communities, businesses, sectors and society to climate change and climate variability through investments in irrigation subprojects being rehabilitated and climate proofed.
Numbers of people supported by the PPCR-supported Project to cope with effects of climate change as demonstrated by:
- 50,000 farmers will benefit from climate resilient irrigation structures by 2018
(2012 baseline: 0)
- Enhanced gender mainstreaming - 30% unskilled laborers employed in the rehabilitation are women by
o 2018; 30% of construction sub-committee members are women; 2 farmer water user committees
o established in each irrigation scheme, with women occupying 30% of the management positions.
(2012 baseline: 0)
- At least five local engineering firms will practice commercial design and construction of irrigation system that incorporated climate resilience options by 2019 (2012 baseline: 0).
- 100,000 ha of rice producing areas covered by WICI within the three participating provinces by 2017 (50% of the policy-holders is women, of which 10% is from female headed household) (2012 baseline: 0)
- 15 local input suppliers, 3 local financial institutions, and 3 local marketing agencies participating into the pilot
tests in three provinces (2012 baseline: 0).
- Four seed drying and storage facilities constructed by 2017 with a combined storage capacity of 8,000 tons
(30% unskilled laborers and 50% administrative staff are women)
- Capacity for drying paddy in target provinces extended by 2,000 tons per day by 2018
- Capacity for paddy storage in target provinces extended by 40,000 tons by 2018.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
26
MONITORING FRAMEWORK FOR SCF PPCR
Results Indicators (consistent with PPCR Core Indicators)
Climate responsive investment approaches implemented through land leveling as adaptation demonstrations being conducted in each irrigation subproject.
- Quality of and extent to which climate responsive instruments/investment models are developed and tested, as
reflected by
- 30% of farmers (disaggregated by sex) have leveled their paddy fields in target provinces by 2018 (2012
baseline: 0)
- At least nine private contractors in three project provinces engaged and trained to offer land leveling services by
2016 (2012 baseline: 0).
- Twenty private contractors, including 5 led by female entrepreneurs, replicated offering land leveling services at
their own initiatives in three participating provinces by 2018 (2012 baseline: 0).
- Strengthened capacity of provincial departments in Project provinces in improving efficiency of irrigation water
use through land leveling - baseline: 0% paddy land area leveled, target: 15% paddy land area leveled by 2018
Strengthened climate responsive
development planning
Degree of integration of climate change in national, including sector planning, as reflected by:
- Strengthened capacity of provincial departments in Project provinces in improving efficiency of irrigation
water use through land leveling - baseline: 0% paddy land area leveled, target: 15% paddy land area
leveled by 2018.
- A joint working group including female representatives established by the government to develop
agricultural land-use zoning as a climate adaptation strategy; developed and issued a framework providing
procedures for establishing agricultural land-use zones, incorporating measures and targets for involving
women in planning and decision making.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
27
MONITORING FRAMEWORK FOR SCF PPCR
Results Indicators (consistent with PPCR Core Indicators)
Strengthened adaptive capacity through
mill management training initiatives that
integrate climate change concerns.
- Extent to which vulnerable households, communities’ businesses and public sector services use improved
PPCR supported tools, instruments, strategies, activities to respond to CV&CC, as reflected by:
- 30% of rice mills in three project provinces equipped with knowledge to address change in paddy supply
patterns induced by climate change by 2018 (2012 baseline: 0).
- Post-harvest losses reduced from 15% of crop yield in 2012 to 10% of crop yield by 2017.
- Enhanced quality and participation of the private sector in providing advisory services to rice millers to address
climate change impacts, as reflected by: 10 local firms participating in providing advisory services to rice millers
by 2018. (2012 baseline: 0)
- Increased leverage factor of PPCR funding, reflected by an estimated $5 million from private sector mills by
2018 to address change in paddy supply patterns induced by climate change (2012 baseline: 0).
Strengthened adaptive capacity through developing and piloting weather-indexed crop insurance scheme.
Quality of and extent to which climate responsive instruments/ investment models are developed and tested, reflected by:
- 100,000 ha of paddy areas in three Project provinces covered by WICI by 2017 (2012 baseline: 0).
- 50% of insured rice farmers (i.e., policy-holders) is women.
- Enhanced capacities and participation of the private sector in paddy crop risk mitigation, reflected by: 15 local
input suppliers, three local financial institutions, and three local marketing agencies participating in crop
insurance services by 2017 (2012 baseline: 0).
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
28
MONITORING FRAMEWORK FOR SCF PPCR
Results Indicators (consistent with PPCR Core Indicators)
Improved institutional framework in place through the adoption of sector development program approach encompassing policy and institutional reform and appropriately coordinated climate resilient investments.
Evidence of strengthened government capacity and coordination mechanisms that demonstrate integration of climate vulnerability in national, including sector planning to mainstream climate resilience, reflected by
- Three important legal documents (a law, a policy and an action program) will be in place by 2016 to address
climate change risks and/or adjusted to incorporate climate change risks, including (i) Law on Management and
Use of Agricultural Land (ii) Framework providing procedures for establishing agricultural land-use zones; and
(iii) National action program to combat land degradation in Cambodia.
- Under the guidance of the Committee for Economic and Financial Policies (CEFP), a cross-sectoral mechanism
taking into account of climate variability and climate change will be established by 2016 as part of the review
and adjustment of the Policy on the Promotion of Paddy Production and Rice Export.
Annex 2
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
29
Rice SDP - Climate Resilient Rice Commecialisation Sector Development Program
ADB Loans 3006 & 3007 - CAM; GAFSP Grant 0349; SCF Loan 8271 & Grant 0350
Statement of Expenditure
Cumulative since Effectiveness Date
Reporting for the Quarter End 30 June 2016
PMR 1: Project Monitoring Report: Uses of Funds By Category for the Quarter Ending 30-Jun-16
(Note: Q = Quarter, YTD = Year to date, CTD = Cummulative to date) (Quaterly Report. In USD)
Overall 2015 2016 Unliquidated Q2 YTD Q2 CTD Q2 2016 Budget
Budget budget Budget Obligations 2016 2016 2016 Balance
(1) (2) (3) (4) (5) (6) (7)=(2)-(3)-(5) (8)=(5)/(2) (9)=(6)/(1)
I- INVESTMENT COSTS MEF/PMO 8,821,200.0 1,254,292.2 2,680,410.0 389,429 488,021.71 1,306,499.5 1,373,910.5 18.21% 14.81%
MAFF/NIO 22,521,100.0 124,356.0 1,528,904.0 11,070.6 -16,164.40 92,331.6 1,436,572.4 -1.06% 0.41%
MOWRAM/NIO 16,701,400.0 100,110.0 885,000.0 43,625.0 43,625.00 134,737.8 750,262.2 4.93% 0.81%
MLMUPC/NIO 1,808,600.0 86,890.0 252,483.7 0.0 43,000.00 43,000.0 209,483.7 17.03% 2.38%
BTB/PIO 690,100.0 68,375.0 45,930.0 0.0 0.00 41,900.0 4,030.0 0.00% 6.07%
KPT/NIO 690,100.0 68,375.0 45,930.0 0.0 43,000.00 43,000.0 2,930.0 93.62% 6.23%
PVG/NIO 690,100.0 68,375.0 45,930.0 14,665.0 41,900.00 41,900.0 4,030.0 91.23% 6.07%
Sub Total (I): Investment Costs 51,922,600.0 1,770,773.2 5,484,587.7 0.0 458,789.3 643,382.31 1,703,369.0 3,781,218.8 11.73% 3.28%
II. IMPLEMENTATION AND SUPERVISION COSTS MEF/PMO 2,603,100.0 287,924.8 268,220.0 39,476.0 137,427.59 284,279.9 -16,059.9 51.24% 10.92%
MAFF/NIO 1,230,800.0 133,910.0 189,990.0 31,631.6 49,293.83 128,880.7 61,109.3 25.95% 10.47%
MOWRAM/NIO 1,255,800.0 125,126.0 98,040.0 20,000.0 31,056.0 47,886.95 106,471.3 -8,431.3 48.84% 8.48%
MLMUPC/NIO 1,108,900.0 97,720.0 177,840.0 10,246.0 21,793.00 60,352.9 117,487.1 12.25% 5.44%
BTB/PIO 1,454,700.0 77,372.7 145,940.0 14,697.31 47,445.18 49,589.9 96,350.1 32.51% 3.41%
KPT/NIO 1,454,700.0 85,642.0 149,360.0 16,366.6 27,375.08 56,391.2 92,968.8 18.33% 3.88%
PVG/NIO 1,454,700.0 73,670.7 147,080.0 9,873.9 17,593.84 43,004.8 104,075.2 11.96% 2.96%
Sub Total (ii): Implementation
and
Supervision Costs 10,562,700.0 881,366.1 1,176,470.0 20,000.0 153,347.4 348,815.47 728,970.67 447,499.3 29.65% 6.90%
GRAND TOTAL (I)+(II) 62,485,300.0 2,652,139.3 6,661,057.7 20,000.0 612,136.7 992,197.78 2,432,339.63 4,228,718.1 14.90% 6.8%
Category
Disbursem
ent Rate
% Overall
Actual Expenditure
Disburse
ment
Rate %
2016
Annex 2
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
30
Rice SDP - Climate Resilient Rice Commecialisation Sector Development Program
ADB Loans 3006 & 3007 - CAM; GAFSP Grant 0349; SCF Loan 8271 & Grant 0350
Disbursement Accounts by Financiers (USD)
Cumulative since Effectiveness Date
Reporting for the Quarter Ending: 30 June 2016
Cat.
Ref.EAs/IAs Total Allocation (1)
Unliquidated
Obligations (2)
Cumulative
Expenditure (3)
Budget Balance
(4) = (1)-(2)-(3)
I. LOAN 3006 - CAM (SF)
MEF/PMO 24,000,000
MAFF/NIO
Sub-Total 24,000,000 0 - 0
I. LOAN 3007 - CAM (SF)
MEF/PMO 6,183,000 910,741.7 5,272,258
MAFF/NIO 7,850,400 83,250.07 7,767,150
MOWRAM/NIO 11,476,300 138,209.9 11,338,090
MLMUPC/NIO 840,600 31,372.7 809,227
BTB/PIO 1,241,100 38,499.5 1,202,601
KPT/PIO 1,241,100 38,436.5 1,202,664
PVG/PIO 1,241,100 37,512.8 1,203,587
Sub-Total 30,073,600 0 1,278,023.1 25,186,725.66
II. GAFSP GRANT
MEF/PMO 1,230,700 192,761.8 1,037,938
MAFF/NIO 10,929,400 52,662.08 10,876,738
MOWRAM/NIO 782,800 15,206.8 767,593
MLMUPC/NIO 1,609,900 1,609,900
BTB/PIO 16,200 16,200
KPT/PIO 16,200 16,200
PVG/PIO 16,200 16,200
Sub-Total 14,601,400 0 260,630.6 14,292,169.40
III. SCF LOAN
MEF/PMO -
MAFF/NIO 588,500 588,500
MOWRAM/NIO 3,306,600 3,306,600
BTB/PIO 367,500 367,500
KPT/PIO 367,500 367,500
PVG/PIO 367,500 367,500
Sub-Total 4,997,600 0 - 4,997,600.00
IV. SCF GRANT
MEF/PMO 2,080,000 313,823.2 1,766,177
MAFF/NIO 2,000,000 2,000,000
MOWRAM/NIO 421,200 421,200
Sub-Total 4,501,200 - 313,823.2 4,187,377
V. RGC
MEF/PMO 1,928,800 173,452.8 1,755,347
MAFF/NIO 2,385,500 85,300.18 2,300,200
MOWRAM/NIO 1,970,200 20,000 87,792.4 1,862,408
MLMUPC/NIO 467,000 71,980.2 395,020
BTB/PIO 520,000 52,990.4 467,010
KPT/PIO 520,000 60,954.7 459,045
PVG/PIO 520,000 47,392.0 472,608
Sub-Total 8,311,500 20,000 579,862.8 7,711,637
GRAND TOTAL 86,485,300 20,000 2,432,339.63 56,375,509
Appendix 3
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
31
STATUS OF POLICY COMPLIANCE (30 June 2016)
No. Policy Actions for the Release of the Second Tranche Status Expected Date of
Compliance
1. MAFF will have issued the Cambodian Seed Policy. (Copy
of the issued Cambodian Seed Policy).
FIRST DRAFT
submitted to MEF. 30 October 2016
2. MAFF will have issued the National Seed Standards. (Copy
of the issued National Seed Standards).
FIRST DRAFT
submitted to MEF 30 October 2016
3.
MAFF will have issued the Prakas on Procedures for
Providing Seed Quality Certification. (Copy of the issued
Prakas on Procedures for Providing Seed Quality
Certification).
FIRST DRAFT
submitted to MEF 30 October 2016
4.
MAFF will have issued the General Introduction to the
Examination of Distinctiveness, Uniformity and Stability of
New Varieties of Plants. (Copy of the issued General
Introduction to the Examination of Distinctiveness,
Uniformity and Stability of New Varieties of Plants).
FIRST DRAFT
submitted to MEF 30 October 2016
5.
MAFF will have issued the Guidelines for the Conduct of
Tests for Distinctiveness, Uniformity and Stability of Rice.
(Copy of the issued Guidelines for the Conduct of Tests
for Distinctiveness, Uniformity & Stability of Rice).
FIRST DRAFT
submitted to MEF 30 October 2016
6.
The Government will have issued the Land Policy “White
Paper”, including a chapter on Land and Gender Policy.
(Copy of the issued Land Policy “White Paper”).
Issued on 28
August 2015
Complied
7.
MAFF will have drafted the Law on Management and Use of
Agricultural Land, focusing inter alia, on (a) women’s access
to information on land administration, management and
distribution; (b) women’s equal participation and
representation in all commissions and committees; and (c)
equal benefits for women in land related initiatives. (Copy
of the draft Law on Management and Use of Agricultural
Land).
FIRST DRAFT
submitted to MEF
consultations
30 December 2016
8.
MAFF will have prepared and submitted to the Council of
Ministers the national action program to combat land
degradation in Cambodia. (Copy of the national action
program to combat land degradation in Cambodia).
FIRST DRAFT
submitted to MEF 30 December 2016
9.
MAFF will have issued guidelines for establishing
agricultural land-use zones, incorporating measures and
targets for involving women in planning and decision
making. (Copy of the issued guideline for establishing
agricultural land-use zones).
FIRST DRAFT
submitted to MEF 30 December 2016
10.
MAFF will have submitted the draft Law on Agricultural
Cooperatives to the National Assembly. (Copy of the
submitted Law on Agricultural Cooperatives).
Law passed on
May 22, 2013 Complied
11.
MIH will have issued the standards for two varieties of
Cambodian milled rice, Phka Rumduol and Phka Chan
Sensor, (Copies of the issued standards for various
varieties of Cambodian milled rice).
FIRST DRAFT
submitted to Rice
Standards TWG
30 September
2016
12.
MAFF will have submitted the draft Law on Plant Protection
and Phytosanitary Measures to the Council of Ministers.
(Copy of the submitted Law on Plant Protection and
Phytosanitary Measures).
FIRST DRAFT
submitted to MEF 30 November 2016
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
32
Summary of Physical Progress
Output 2: Agricultural Land Use Zoning Improved
ACTIVITY 2.1: COMMUNE AGRO-ECOSYSTEMS ANALYSIS TO IDENTIFY ZONES FOR RICE CROPPING SYSTEMS
Activities:
- Preparation of CAEA training materials for conduct of ToT.
- Delivery of provincial ToTs in each target province.
- Conduct of field work for CAEAs in target communes.
- Preparation of CAEA reports
- Approval of CAEAs by the CCs.
- Entry of CACA data into the FSMIS.
- Endorsement of CAEAs to the PDLMUPC.
Province Quarterly Achievement
National
- After the completion of the ToT in BTB province a joint review of the CAEA results identified a number of lessons and necessary changes in the methodology. These
lessons were analysed and improvements agreed to by the GDA/DAE team, and the Extension Specialist revised the CAEA Manual accordingly. The review also
revealed a number of weaknesses and shortcomings in the RRA and Systems Analysis phases of the training that were not dealt with at the time due to the absence
of the Extension Specialist. These issues need to be addressed for the field work in the next CAEA TOT training.
Battambang
- The ToT for CAEA was completed with a total of 36 participants (6 women). The ToT extended over a 10-day period and included field practice in Knach Romeas
commune. The previous CAEA report had been obtained from the Dept. of Agricultural Extension archives. However, the bio-physical and socio-economic data for the
commune had not been downloaded from the DAE FSMIS database and plans, reports and details of the proposed rice-SDP sub-projects had not been copied. Also
soil maps and soil identification manuals had not been obtained for use during the CAEA. Finally, the data recording formats and templates for use on the field during
the TTA had not been prepared. These were all important lessons for the next ToT for CAEA.
- The field work for CAEA in other communes has not yet commenced due to uncertainty about the budget allocations and the mechanism for transfer of the funds form
the MAFF/NIO to the PIO.
Kampong Thom - The ToT for CAEA commenced on 27 June and will be concluded in mid-July.
Prey Veng - The ToT for CAEA is scheduled for August 2016.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
33
ACTIVITY 2.1: COMMUNE AGRO-ECOSYSTEMS ANALYSIS TO IDENTIFY ZONES FOR RICE CROPPING SYSTEMS
Activities:
- Conduct of national level ToT on CLUP process for NIO staff.
- Conduct of provincial TOTs on CLUP process for NIO staff.
- Deployment of CLUP consultants in each province.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of revised CAEA Manual produced manual 0 1 1 100 %
No. of provincial ToTs completed on CAEA courses 2 2 3 67 %
Total no. of participants at ToT on CAEA pax 74 74 90 82 %
Total no. of female participants at ToT on CAEA pax 13 13 30 43 %
No. of CAEAs completed communes 2 2 34 6 %
No. of CAEAs approved by the CC communes 0 0 34 0 %
No. of CAEAs with data entered into the FSMIS communes 0 0 34 0 %
No. of completed CAEAs submitted to PDLMUPC communes 0 0 34 0%
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
34
ACTIVITY 2.2: PREPARATION OF COMMUNE LAND USE PLANS
Activities:
- Revision of the guidelines for CLUP integrating the results of the CAEA.
- Conduct of ToT for CLUP for NIO staff and PIO representatives.
- Conduct of provincial level training on CLUP for PDLMUPC and district teams.
- No. of provincial hotspots maps produced.
- Consultation with farmer groups for CLUP preparation.
- No. of CLUPs prepared for target communes in each province.
Province Quarterly Achievement
National
- The guidelines for the CLUP were revised with the support of the PIC team members. The ToR for the external service providers who are to be contracted by
MLMUPC to undertake the CLUP were prepared and discussed a number of times with the MLMUPC NIO team. The ToR was revised a number of times and by the
end of the Q2 was still not finalised.
- The preparation of the training materials for the conduct of the ToT for the CLUP for NIO staff and NIO representatives commenced with the support of the PIC team.
Battambang - No activity planned in this quarter.
Kampong Thom - No activity planned in this quarter.
Prey Veng - No activity planned in this quarter.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
35
ACTIVITY 2.2: PREPARATION OF COMMUNE LAND USE PLANS
Activities:
- Revision of the guidelines for CLUP integrating the results of the CAEA.
- Conduct of ToT for CLUP for NIO staff and PIO representatives.
- Conduct of provincial level training on CLUP for PDLMUPC and district teams.
- No. of provincial hotspots maps produced.
- Consultation with farmer groups for CLUP preparation.
- No. of CLUPs prepared for target communes in each province,
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of national ToTs conducted on CLUP # 0 0 1 0 %
No. of participants attending national ToT on CLUP # 0 0 20 0 %
No. of female participants attending national ToT on CLUP # 0 0 7 0 %
No. of provincial ToTs conducted on CLUP # 0 0 3 0 %
Total no. of participants attending provincial ToT on CLUP # 0 0 60 0 %
Total no. of female participants attending national ToT on CLUP # 0 0 20 0 %
No. of provincial hotspot maps produced # 0 0 0 0 %
No. of CLUPs prepared # 0 0 0 0 %
Total no. of farmer groups consulted for CLUP preparation # 0 0 0 0 %
Total no. of women participating in farmer group consultations # 0 0 0 0 %
No. of national ToTs conducted on CLUP # 0 0 1 0 %
No. of participants attending national ToT on CLUP # 0 0 20 0 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
36
ACTIVITY 2.3: DEVELOPMENT OF PROVINCIAL RICE ECOSYSTEMS MAPS
Activities:
- Conduct of training for soil surveying.
- Preparation of rice eco-systems map for soil sampling in KPT
- Collection and analysis of soil samples.
- GIS training for PIO staff in each province.
National/
Province Quarterly Achievement
National - No activity planned in this quarter
Battambang - No activity planned in this quarter.
Kampong Thom
- MAFF/NIO have completed the training on Soil Surveying and Classification in KPT in June with participants from the PDAs and DOAs in that province. The training
covered the theoretical aspects of soil study and soil profiles and explained the key points for the rice soil classification. There was also field practice at five locations
in three communes in Santuk district for demonstrations of soil sampling techniques. .
Prey Veng - No activity planned in this quarter.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
37
ACTIVITY 2.3: DEVELOPMENT OF PROVINCIAL RICE ECOSYSTEMS MAPS
Activities:
- Conduct of training for soil surveying.
- Preparation of rice eco-systems map for soil sampling in KPT
- Collection and analysis of soil samples.
- GIS training for PIO staff in each province.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
Training on conduct of soil survey in KPT # 1 1 1 100%
No. of participants attending training on conduct of soil survey # 29 29 25 116%
No. of female participants attending training on conduct of soil survey # 9 9 10 90%
Preparation of rice eco-systems map for soil sampling for KPT # 0 0 1 0%
Collection of soil samples based upon rice eco-systems map # 0 0 200 0%
Analysis of soil samples # 0 0 200 0%
Training on GIS for PIO staff from each province # 0 0 1 0%
No. of participants attending GIS training # 0 0 15 0%
No. of female participants attending GIS training # 0 0 5 0%
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
38
Output 3: Development of Rice Value Chain Infrastructure
ACTIVITY 3.1: RECRUITMENT OF NATIONAL CONSULTANT FIRM TO CARRY OUT FEASIBILITY STUDY AND DETAILED DESIGNS ON SUB-PROJECTS FOR CLIMATE RESILIENT IRRIGATION REHABILITATION
Activities:
- Advertisement for EoIs for consultants for FS/DD/CS for Irrigation Sub-Projects, evaluation of submissions and RFPs issuance.
- Conduct of Feasibility Studies on selected irrigation sub-projects sites in each province.
- Preparation of Detailed Designs for feasible irrigation sub-projects in each province.
National/
Province Quarterly Achievement
National - MOWRAM recruited KCC to provide consultant team to support the FS/DD/CS for 19 selected irrigation sub-projects.
Battambang - KCC have mobilised to the province and have completed the revision of the Feasibility Study documents for Prey Sangha sub-project that were prepared during the
PPTA and these were submitted to ADB for no objection. They have commenced the preparation of the Detailed Design and are also updating the Resettlement Plan.
Kampong Thom - KCC have mobilised to the province and have completed the revision of the Feasibility Study documents for Chuck Khsak sub-project that were prepared during the
PPTA and these were submitted to ADB for no objection. They have commenced the preparation of the Detailed Design and are also updating the Resettlement Plan.
Prey Veng - No activity planned in this quarter.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
39
ACTIVITY 3.1: RECRUITMENT OF NATIONAL CONSULTANT FIRM TO CARRY OUT FEASIBILITY STUDY AND DETAILED DESIGNS ON SUB-PROJECTS FOR CLIMATE RESILIENT IRRIGATION REHABILITATION
Activities:
- Advertisement for EoIs for consultants for FSDDCS for Irrigation Sub-Projects, evaluation of submissions and RFPs issuance.
- Conduct of Feasibility Studies on selected irrigation sub-projects sites in each province.
- Preparation of Detailed Designs for feasible irrigation sub-projects in each province.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of contracts awarded for FS/DD/CS for irrigation sub-projects contracts 0 1 1 100 %
No. of FS reports completed for irrigation sub-projects reports 2 2 8 25 %
No. of DDs completed for irrigation sub-projects reports 0 0 8 0 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
40
ACTIVITY 3.2: RECRUITMENT OF NATIONAL CONSULTANT FIRM TO PREPARE FEASIBILITY STUDIES AND DETAILED DESIGNS OF PADDY AND COMMERCIAL SEED DRYING AND STORAGE FACILITIES
Activities:
- Advertisement for EoIs for consultants for FSs for Paddy and Commercial Seed Drying and Storage Facilities.
- Conduct of preliminary survey of selected paddy and commercial seed drying and storage facilities in each province to determine which are feasible to construct.
- Conduct of Feasibility Studies on selected paddy and commercial seed drying and storage facilities in each province.
- Advertisement for EoIs for consultants for DDs and CS for Paddy and Commercial Seed Drying and Storage Facilities.
- Preparation of Detailed Designs for viable paddy and commercial seed drying and storage facilities in each province.
National/
Province Quarterly Achievement
National
- ToR for the national consultant for FS/DD/CS that was the basis for the earlier round of invitation for EoIs was revised following the ADB Mission in May so that is was
split into two phases. The first phase covers the conduct of a preliminary survey of each of the selected sites to determine their suitability and the availability of the
land after which the FSs can be conducted. Based upon the outcome of the FSs the second phase will cover the conduct of the DDs for facilities that are found to be
viable.
Battambang - No activity planned in this quarter.
Kampong Thom - No activity planned in this quarter.
Prey Veng - No activity planned in this quarter.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
41
ACTIVITY 3.2: RECRUITMENT OF NATIONAL CONSULTANT FIRM TO PREPARE FEASIBILITY STUDIES AND DETAILED DESIGNS OF PADDY AND COMMERCIAL SEED DRYING AND STORAGE FACILITIES
Activities:
- Advertisement for EoIs for consultants for FSs for Paddy and Commercial Seed Drying and Storage Facilities.
- Conduct of preliminary survey of selected paddy and commercial seed drying and storage facilities in each province to determine which are feasible to construct.
- Conduct of Feasibility Studies on selected paddy and commercial seed drying and storage facilities in each province.
- Advertisement for EoIs for consultants for DDs and CS for Paddy and Commercial Seed Drying and Storage Facilities.
- Preparation of Detailed Designs for viable paddy and commercial seed drying and storage facilities in each province.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of contracts awarded for FSs for paddy and commercial seed drying and storage facilities contracts 0 0 1 0 %
No. of FSs completed for paddy drying and storage facilities reports 0 0 5 0 %
No. of FSs conducted for commercial seed drying and storage facilities reports 0 0 5 0 %
No. of contracts awarded for DDs for paddy and commercial seed drying and storage facilities contracts 0 0 0 0 %
No. of DDs completed for paddy drying and storage facilities reports 0 0 0 0 %
No. of DDs conducted for commercial seed drying and storage facilities reports 0 0 0 0 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
42
ACTIVITY 3.3: WORKS CONTRACT PROCUREMENT FOR REHABIITATION OF IRRIGATION SUB-PROJECTS
Activities:
- Advertisement for bidders for rehabilitation of each irrigation sub-projects (Single Stage: One Envelope).
- Bid evaluation and award of contract to winning bidders.
- Monitoring and Supervision of Construction by MOWRAM consultants for authorisation of progress payments to contractors.
- Final Inspection of civil works after warranty period for contract completion.
National/
Province Quarterly Achievement
National - Contract awards for rehabilitation of irrigation sub-projects will commence in 2017.
ACTIVITY 3.4: WORKS CONTRACT PROCUREMENT FOR CONSTRUCTION OF PADDY DRYING AND STORAGE FACILITIES
Activities:
- Advertisement for bidders for construction of paddy drying and storage facilities (Single Stage: One Envelope).
- Bid evaluation and award of contract to winning bidders.
- Monitoring and Supervision of Construction by MAFF consultants for authorisation of progress payments to contractors.
- Final Inspection of civil works after warranty period for contract completion.
National/
Province Quarterly Achievement
National - Due to delays in the commencement of the Feasibility Studies and Detailed Designs for the paddy drying and storage facilities the award of contracts for the civil works
construction is deferred to 2017.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
43
ACTIVITY 3.5: WORKS CONTRACT PROCUREMENT FOR CONSTRUCTION OF COMMERCIAL SEED DRYING AND STORAGE FACILITIES
Activities:
- Advertisement for bidders for construction of commercial seed drying and storage facilities (Single Stage: One Envelope).
- Bid evaluation and award of contract to winning bidders.
- Monitoring and Supervision of Construction by MAFF consultants for authorisation of progress payments to contractors.
- Final Inspection of civil works after warranty period for contract completion.
National/
Province Quarterly Achievement
National - Due to delays in the commencement of the Feasibility Studies and Detailed Designs for the commercial seed drying and storage facilities the award of contracts for the
civil works construction is deferred to 2017.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
44
ACTIVITY 3.6: ASSOCIATED INITIATIVES FOR IRRIGATION SUB-PROJECTS
Activities:
- Advertising for bidders to implement land levelling services.
- Organisation of land levelling demonstrations within irrigation sub-projects site areas.
- Recruitment of service providers to deliver agricultural extension services.
- Implementation of capacity building activities for Farmer Water User Groups/Communities (FWUGs/FWUC) within irrigation sub-project site areas.
- Recruitment of service providers for strengthening agricultural cooperatives and providing market facilitation support.
- Implementation of contract farming for rice seed production.
National/
Province Quarterly Achievement
National
- Concept paper on precision land levelling has been prepared with the support of the PIC team which examines the cost of doing land levelling by local contractors and
also considers the benefits for the farmer in terms of increased productivity. Proposals were also presented for the implementation of the land levelling through a PPP
arrangement where local contractors would be provided with the laser land levelling equipment by the PIOs.
Battambang
- Consultations with farmers within some of the irrigation sub-project site areas have been conducted to determine the level of contribution that they would be willing to
pay for the land levelling services.
- No activities have yet been implemented for strengthening agricultural extension services, capacity building of FWUGs/FWUCs, market facilitation support or contract
farming for rice seed production.
Kampong Thom
- Consultations with farmers within some of the irrigation sub-project site areas have been conducted to determine the level of contribution that they would be willing to
pay for the land levelling services. A regional workshop was conducted with local contractors from all three provinces to discuss the mechanism for implementing the
land levelling. However, there remain uncertainty on how to implement this activity.
- No activities have yet been implemented for strengthening agricultural extension services, capacity building of FWUGs/FWUCs, market facilitation support or contract
farming for rice seed production.
Prey Veng
- Consultations with farmers within some of the irrigation sub-project site areas have been conducted to determine the level of contribution that they would be willing to
pay for the land levelling services.
- No activities have yet been implemented for strengthening agricultural extension services, capacity building of FWUGs/FWUCs, market facilitation support or contract
farming for rice seed production.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
45
ACTIVITY 3.6: ASSOCIATED INITIATIVES FOR IRRIGATION SUB-PROJECTS
Activities:
- Advertising for bidders to implement land levelling services.
- Organisation of land levelling demonstrations within irrigation sub-projects site areas.
- Recruitment of service providers to deliver agricultural extension services.
- Implementation of capacity building activities for Farmer Water User Groups/Communities (FWUGs/FWUC) within irrigation sub-project site areas.
- Recruitment of service providers for strengthening agricultural cooperatives and providing market facilitation support.
- Implementation of contract farming for rice seed production.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of local agricultural contractors trained on land levelling. trainees 0 0 0 0 %
No. of contracts awarded for land levelling services contracts 0 0 0 0 %
No. of hectares of land levelled ha 0 0 0 0 %
No. of farmers who have levelled paddies farmers 0 0 0 0 %
No. of on-farm demonstration plots organised demos 0 0 0 0 %
No. of field days organised at sites of on-farm demonstrations days 0 0 0 0 %
No. of women attending the field days at sites of on-farm demonstrations women 0 0 0 0 %
No. of FFS organised training 0 0 0 0 %
No. of farmers graduating from FFSs farmers 0 0 0 0 %
No. of women graduating from FFSs women 0 0 0 0 %
No. of agricultural technical literature booklets/pamphlets printed documents 0 0 0 0 %
No. of capacity building trainings for FWUGs/FWUCs trainings 0 0 0 0 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
46
ACTIVITY 3.6: ASSOCIATED INITIATIVES FOR IRRIGATION SUB-PROJECTS
Activities:
- Advertising for bidders to implement land levelling services.
- Organisation of land levelling demonstrations within irrigation sub-projects site areas.
- Recruitment of service providers to deliver agricultural extension services.
- Implementation of capacity building activities for Farmer Water User Groups/Communities (FWUGs/FWUC) within irrigation sub-project site areas.
- Recruitment of service providers for strengthening agricultural cooperatives and providing market facilitation support.
- Implementation of contract farming for rice seed production.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of capacity building trainings for Agricultural Cooperatives trainings 0 0 0 0 %
No. of farmers attending the capacity building trainings for Agricultural Cooperatives farmers 0 0 0 0 %
No. of women attending the capacity building trainings for Agricultural Cooperatives women 0 0 0 0 %
No. of contracts signed between Agricultural Cooperatives and Rice Millers for rice seed production
contracts 0 0 0 0 %
Quantity of certified rice seed produced through contract farming agreements tons 0 0 0 0 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
47
ACTIVITY 3.7: PROCUREMENT OF PPPs FOR OPERATION OF RICE PADDY DRYING AND STORAGE FACILITIES
Activities:
- Advertisement for EoIs from private operators for participation in PPP agreements for paddy drying and storage facilities.
- Evaluation of EoIs received and sort listing of potential partners for PPP agreements.
- Signing of PPP Agreements for operation of the paddy drying and storage facilities
National/
Province Quarterly Achievement
National - PIC team have prepared outline concept paper identifying three potential models (options) for the PPP supporting paddy drying and storage. These will be presented
during a planned PPP Forum to be conducted in July with public and private sector stakeholders.
Battambang - PIO team assisted in facilitating field visits by PIC team to meet with rice millers within the province to assess the level of interest in participation in the PPP
agreements.
Kampong Thom - PIO team assisted in facilitating field visits by PIC team to meet with rice millers within the province to assess the level of interest in participation in the PPP
agreements.
Prey Veng - PIO team assisted in facilitating field visits by PIC team to meet with rice millers within the province to assess the level of interest in participation in the PPP
agreements.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
48
ACTIVITY 3.7: ASSOCIATED INITIATIVES FOR IRRIGATION SUB-PROJECTS
Activities:
- Advertisement for EoIs from private operators for participation in PPP agreements for paddy drying and storage facilities.
- Evaluation of EoIs received and sort listing of potential partners for PPP agreements.
- Signing of PPP Agreements for operation of the paddy drying and storage facilities
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of EoIs received from private operators EoI 0 0 0 0 %
No. of private operators shortlisted for PPP agreements for paddy drying and storage operators 0 0 0 0 %
No. of PPP agreements signed with private operators agreement 0 0 0 0 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
49
Output 4: Enhanced Rice Value Chain Support Services
ACTIVITY 4.1: INCREASED AVAILABILITY OF QUALITY RICE SEED
Activities:
- Rehabilitation of seed testing laboratory, procurement and installation of seed testing equipment.
- Training for laboratory staff in seed testing procedures.
- Development of operational guidelines for national seed certification scheme.
- LoAs with Tuolsomraong, Balang and Porlos Agriculture Stations for production of registered seed.
- Training on seed certification and seed production.
- ToT on rice seed production for district staff.
- Season long FFS on seed production for rice seed producers (Agricultural Cooperatives/Rice Seed Producer groups)
National/
Province Quarterly Achievement
National
- Office space within the MAFF/GDA compound has been allocated for the establishment of the seed testing laboratory. The bidding for the seed testing laboratory
equipment has been completed and the BER has been prepared and submitted to ADB for NOL
- Work has commenced on the production of a Rice Seed Action plan for GDA which includes operational guidelines for a national seed certification scheme.
- Details of the LoAs between Balang Agricultural Station and the GDA and KPT/PDA have been provided by the ADB funded TSSD projects and these are being used
as the basis for similar agreements with the three stations in BTB, KPT and PVG provinces.
- ToT on rice seed production for 10 district staff from the three provinces has commenced at Prey Phdao station in Kampong Speu province.
Battambang - No activity planned in this quarter
Kampong Thom - No activity planned in this quarter
Prey Veng - No activity planned in this quarter
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
50
ACTIVITY 4.1: INCREASED AVAILABILITY OF QUALITY RICE SEED
Activities:
- Rehabilitation of seed testing laboratory, procurement and installation of seed testing equipment.
- Training for laboratory staff in seed testing procedures.
- Development of operational guidelines for national seed certification scheme.
- LoAs with Tuolsomraong, Balang and Porlos Agriculture Stations for production of registered seed.
- ToT on rice seed production for district staff.
- Season long FFS on seed production for rice seed producers (Agricultural Cooperatives/Rice Seed Producer groups)
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
Contract award for procurement of laboratory equipment contract 0 0 1 0 %
Training for laboratory staff in seed testing procedures training 0 0 1 0 %
No. of laboratory staff attending training on seed testing procedures trainees 0 0 10 0 %
No. of female laboratory staff attending training on seed testing procedures women 0 0 3 0 %
Operational Guidelines for national seed certification scheme guideline 0 0 1 0 %
LoAs with Tuolsomraong, Balang and Porlos Agriculture Stations for production of registered
seed LoAs 0 0 3 0 %
No. of ToT on rice seed production training 1 1 1 100 %
No. of district staff attending the ToT on rice seed production trainees 30 30 30 100 %
No. of female district staff attending the ToT on rice seed production women n.a. n.a. n.a. n.a.
No. of season long FFS on seed production for rice seed production trainings 0 0
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
51
ACTIVITY 4.2: EXPANDED AND DEVELOPED TECHNICAL EXTENSION SERVICES
Activities:
- Training of extension staff on agricultural extension methodologies (3 months).
- Refresher training on post-harvest technologies to PDA, DOA and other stakeholders.
National/
Province Quarterly Achievement
National - No activity planned in this quarter.
Battambang - No activity planned in this quarter.
Kampong Thom - No activity planned in this quarter.
Prey Veng - No activity planned in this quarter.
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
52
ACTIVITY 4.2: EXPANDED AND DEVELOPED TECHNICAL EXTENSION SERVICES
Activities:
- Training of extension staff on agricultural extension methodologies (3 months).
- Refresher training on post-harvest technologies to PDA, DOA and other stakeholders.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of trainings of extension staff on agricultural extension methodologies training 0 0 1 0 %
No. of extension staff attending training on agricultural extension methodologies trainees 0 0 30 0 %
No. of female extension staff attending training on agricultural extension methodologies women 0 0 10 0 %
No. of refresher trainings on post-harvest technologies to PDA, DOA and other stakeholders trainings 0 0 1 0 %
No. of PDA, DOA and other staff attending refresher trainings on post-harvest technologies trainees 0 0 30 0 %
No. of female PDA, DOA and other staff attending refresher trainings on post-harvest
technologies women 0 0 10 0 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
53
Output 5: Feasibility Study, Design and Pilot Testing for WICI
ACTIVITY 5.1: FEASIBILITY STUDY AND DESIGN FOR WICI
Activities:
- Advertisement for EoIs for conduct of Feasibility and Design of WICI scheme.
- Contract award for conduct of Feasibility Study and design of WICI scheme.
- Conduct of field work in target provinces to gather information for use in design of the WICI scheme.
- Preparation of ToR for Phase 2: Pilot testing of the WICI in target provinces.
National/
Province Quarterly Achievement
National
- The advertisement for EoIs which was done on the basis of the original ToR for the combined feasibility study, design and pilot testing of the WICI failed to attract
sufficient bidders. During this quarter the ToR was completely revised and was split into two phases. Phase 1 covers the conduct of the Feasibility Study and the
Design of the scheme. Phase 2 covers the Pilot Testing if the outcome of the Phase is satisfactory. The advertisement for EoIs for Phase will be done in early Q3.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of contract awards for Phase 1: Feasibility Study and Design of WICI contracts 0 0 1 0 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
54
Output 6: Effective Project Management and Implementation
ACTIVITY 6.1: ESTABLISHMENT AND OPERATIONALISING PMO, NIOs and PIOs
Activities:
- Procurement of two additional vehicles.
- Procurement of motorcycles.
- Procurement of office furniture for PMO, NIOs and PIOs.
- Procurement of office equipment for PMO, NIOs and PIOs.
- Recruitment of Procurement Advisers for MAFF/NIO and Finance Adviser for MLMUPC.
National/
Province Quarterly Achievement
National
- PMO commenced the procurement of two additional vehicles to be available for the use of the PIC and NIOs upon request.
- PMO and two NIOs have commenced the procurement of a total of 64 motorcycles to be allocated to the PIO staff. MOWRAM awarded contract for procurement of 27
motorcycles in Q1.
- PMO completed the procurement and distribution of the office furniture and office equipment for the three PIOs.
- MAFF/NIO recruited and deployed Procurement Adviser and MIMULC/NIO recruited and deployed a Finance Adviser.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of contracts awarded for procurement of additional vehicles contract 0 0 1 0 %
No. of additional vehicles procured Vehicle 0 0 2 0 %
No. of contracts awarded for procurement of motorcycles contract 0 0 4 0 %
No. of motorcycles procured motorcycle 0 0 64 0 %
No. of contracts awarded for office furniture contract 1 1 1 100 %
No. of contracts awarded for office equipment contract 1 1 1 100 %
Recruitment of additional advisers by MAFF/NIO and MLMUPC/NIO contract 2 2 2 100 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
55
ACTIVITY 6.2: RECRUITING AND MOBILIZING PICs
Activities:
- PIC team provide continuing technical support to the PMO, NIOs and PIOs.
National/
Province Quarterly Achievement
National - During this quarter the PIC team provided a total input of 10.27 and 25.05 person months of inputs for international and national respectively. During this quarter the
international Business Finance and Credit Specialist commenced his first input.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of person months of input by international PIC team members months 10.27 21.64 56.1 38.6 %
No. of person months of input by national PIC team members months 25.05 48.05 112.3 52.1 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
56
ACTIVITY 6.3: DESIGN AND OPERATION OF GENDER DISAGGREGATED PPMS
Activities:
- Develop the PPMS based upon the three monitoring frameworks relating to the ADB, GAFSP and SCF funding.
- Provide capacity building training to NIO and PIO staff to enable them to gather the required data for the PPMS.
- Revise the Gender Action Plan to ensure effective monitoring of the gender issues.
National/
Province Quarterly Achievement
National - The PIC team have completed a first draft of the PPMS and this has been endorsed by the PMO to the ADB/CARM for review and comment. During the GAFSP
Mission in June there were comments made on the complexity of the PPMS and the need for simplification.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
Training for NIO and PIO staff on the PPMS structure and data collection requirements training 3 3 3 100 %
No. of NIO and PIO participants attending the PPMS training participant 30 30 30 100 %
No. of female NIO and PIO participants attending the PPMS training Women 3 3 10 33 %
Annex 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
57
ACTIVITY 6.4: UNDERTAKING INTERNAL AUDITS, MID TERM REVIEW AND PROGRAM COMPLETION REPORT
Activities:
- Recruitment of Internal Auditors by the PMO.
- Conduct of regular Review Missions by the ADB/CARM
National/
Province Quarterly Achievement
National - The internal auditors conducted the regular internal audit of the program financial progress and disbursement activities.
Indicators Unit Quarterly
Achievement
Annual
Cumulative
Achievement
Annual
Target
%
achievement
of annual
target
No. of contracts awarded for Internal Audits to be conducted contracts 1 1 1 100 %
No. of Regular Mission conducted of ADB/CARM mission 1 2 2 100 %
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
58
Project Progress Report (Period: January 1 2016 - June 30 2016)
1. Basic Project Information & Milestones
Project Cambodia - Climate-Resilient Rice Commercialization Sector
Development Program (Rice-SDP)
Supervising Entity (SE) ADB
SE Primary/Secondary team contact Chanthou Hem <[email protected]>
Project approval date by SE 27 June 2013
Project effectiveness date 13 November 2013
Date of first disb. of GAFSP funds 31 March 2014
Expected closing date of GAFSP funds 31 March 2020
If this has changed, enter new date:
Next planned supervision mission n.a.
Commitments and Disbursements
Commitment
($m)
Disbursed as of
June 2015 ($m)
Disbursed as of
Dec 2015 ($m)
Disbursed as of
June 30, 2016 ($m)
% of total
commitment
disbursed as of
June 30, 2016
Total
Project1 63.43 0 0.95 2.20 3.5 %
GAFSP
portion 14.6 0 0.21 0.50 3.4 %
SE’s Official Ratings2
Previous Rating
December 2015
Current Rating
Rating date: June 2016
Progress towards achieving PDO Moderately Satisfactory
(March 2016) Moderately Satisfactory
Overall implementation progress Moderately Satisfactory
(March 2016) Moderately Satisfactory
2. Implementation Status Overview
1) Provide a paragraph or two describing the project implementation progress, highlighting key outputs
and outcomes that have resulted during the reporting period of January 1, 2016 to June 30, 2016.
Focus on key outputs and outcomes as opposed to administrative or process-related activities.
Better progress has achieved under this reporting period. Under output 1, MAFF is in the process of complying
with the 12 policy conditions to obtain the release of the second tranche. Two conditions have been achieved.
Due to difficulty in coordinating among line ministries, the that compliance date for the second tranche policy
1 Including all financing sources, such as other donors, government, beneficiary, etc. 2 If the SE’s rating scale differs from a five point scale of Highly Satisfactory (HS), Satisfactory (S), Moderately Satisfactory (MS), Moderately Unsatisfactory (MU), and Unsatisfactory (U), then please attach an explanation of the scale being used.
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
59
conditions is extended from currently 30 June 2016 to 31 October 2016 not 31 December 2016 at the request of
MAFF.
Under Output 2 MOWRAM has recruited the consultants for the feasibility studies, detailed designs and
construction supervision of the proposed 19 irrigation sub-projects. The feasibility studies that were completed
during the PPTA for two irrigation sub-projects have been reviewed by the consultants and submitted to ADB for n
objection prior to recruitment of contractors for the civil works. The consultants are in the process of conducting
feasibility and detailed technical engineering designs for the remaining subprojects.
Under Output 3 the bidding for the procurement of equipment for the seed testing laboratory at MAFF/ GDA
has been completed and the bid evaluations submitted to ADB/CARM for no objection. Office space has been
identified within the MAFF/GDA building as the site for the laboratory. The PIC team have reviewed the
laboratory equipment to be purchased and have commenced the preparation of training materials for use later
this year when the laboratory has been established and the equipment installed. Under Output 6 (Effective
Project Management and Implementation) office equipment and furniture has been procured for all National
Implementation Offices (NIOs) and Provincial Implementation Offices (PIOs). The PIC team members have
continued to provide technical support to all the EA and all IAs, a contract variation was approved following
the ADB Mission in June 2016 that made adjustments to the inputs of some of the international team
members. The PPMS has been developed and initial training has been provided to NIO and PIO staff on its
use. The PMS will be used as the basis for quarterly reporting from Q2 2016.
2) Has project implementation been affected by the recent El Nino phenomena? If so, provide details.
The drought conditions experienced in Cambodia in 2016 were reported to be the worst for 50 years.
3) Has there been any political or social instability in the project target zone that have affected project
implementation? If so, provide details.
None reported so far.
4) Has the project undergone any official sanctions either by the Supervising Entity or the Government
(e.g. a qualified audit report, suspension, fraud allegation, investigation) during the reporting period
of January 1, 2016 to June 30, 2016?
Sanction by SE: YES ☐ NO ☒, if Yes, date:
Sanction by Government: YES ☐ NO ☒, if Yes, date:
No sanction during the reporting period but it had happened once which in the last reporting period which was
from June to July 2015 but consultants resumed work in August the same year. Probation period extended for
the following three months.
5) If you have answered Yes in 4), provide a brief explanation of the sanction.
n.a.
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
60
3. Project Results
1) Direct project beneficiaries (report for entire project totals – do not prorate for GAFSP
financing)
Unit
Reached
as of
June
2015
Reached
as of Dec
2015
Reached
as of
June 30,
2016
End of Project
Target
(Enter revisions
in the next
column)
Revisions
to Project
Target
(if any)
Total direct
beneficiaries
Individuals/
Persons 0 0 0 50,000 n.a.
Households - - - - n.a.
% women % 0 0 0 40% n.a.
2) Cross-cutting themes: How does your project contribute significantly to any of these
topics?
a) Nutrition: Does your project implement activities that directly and intentionally contribute to
improving nutritional status of its beneficiaries? YES ☐ NO ☒
Specifically, does your project implement any of the following activities?
• Dissemination of bio-fortified seeds/crops YES ☐ NO ☒
• Construction of homestead gardens YES ☐ NO ☒
• food fortification YES ☐ NO ☐
• promoting production of food with high nutrient content, e.g., horticulture, pulses, meat, dairy, fish)
YES ☐ NO ☒
• Nutrition education (through community programs or extension programs) YES ☐ NO ☒
• Awareness campaigns on breastfeeding YES ☐ NO ☒
• Providing supplements, e.g. folic acid, iron, calcium, multiple vitamin A, zinc) YES ☐ NO ☒
• Producing or distributing ready to use therapeutic foods YES ☐ NO ☒
• Other activities YES ☐ NO ☒
If you have answered YES above, please provide detail on activities carried out and its results to date.
b) Climate smart agriculture: Does your project implement activities that directly and intentionally
adapt to climate change or mitigate greenhouse gas emission? YES ☒ NO ☐
Specifically, does your project implement any of the following activities?
• Climate-resilient irrigation/water management practices (Describe the specific aspects of climate-
resilience in the text box below) YES ☒ NO ☐
• Traditional agronomic techniques such as mulching, intercropping, conservation agriculture, on-
farm water management, and/or pasture and livestock management YES ☒ NO ☐
• Innovative practices such as improved climate-resilient seed varieties, better production
management of emission-intensive crops, integrated pest and disease control technologies YES ☒
NO ☐
• Management systems using agro-climate data to better manage/predict climate variability risks YES
☒ NO ☐
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
61
• Extension services/training on climate-resilient farming techniques YES ☐ NO ☐
• Other activities YES ☒ NO ☐
If you have answered YES above, please provide detail on activities carried out and its results to
date.
Although no field activities have yet commenced the projects will include the following features:
Design of irrigation sub-projects projects will incorporate modified structures to mitigate for the
increased risk of flooding as well as more efficient water distribution; land leveling will be introduced
to reduce water requirements through increased water use efficiencies; drought tolerant rice
varieties will be introduced to farmers through demonstrations and seed production programs;
weather indexed crop insurance will be piloted in selected areas; agricultural extension messages
will incorporate climate smart agricultural techniques.
c) Jobs: Does your project implement activities that directly and intentionally lead to employment
creation? YES ☒ NO ☐
• Setting up of post-harvest facilities with new job opportunities YES ☒ NO ☐
• Cash/food for works schemes YES ☐ NO ☒
• Vocational training programs (only when post-training employment is specifically tracked)
YES ☒ NO
• Other activities YES ☐ NO ☒
If you have answered YES above, please provide detail on activities carried out and its results to
date (including numbers of jobs created).
Constructions of civil works will require local labor force.
3) GAFSP Core Indicators3 (report for entire project totals – do not prorate for GAFSP
financing)
GAFSP Core
Indicator Baseline
Reached
as of June
2015
Reached
as of Dec
2015
Reached
as of June
30, 2016
End of Project
Target (Enter
revisions in the
next column)
Revisions
(if any)
Number of client
days of extension
services provided
to farmers,
community
members etc.
(disaggregated by
gender)
- 0 0 0 20,000 client
days nil
Number of farmers
who have adopted
the technology
being promoted
- 0 0 0 30,000 farmers nil
3 If there have been any changes to the applicable GAFSP Core Indicators for your project, please add or delete them in the table.
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
62
GAFSP Core
Indicator Baseline
Reached
as of June
2015
Reached
as of Dec
2015
Reached
as of June
30, 2016
End of Project
Target (Enter
revisions in the
next column)
Revisions
(if any)
Number of
additional hectares
which have
adopted the
technology being
promoted
- 0 0 0 6,900 ha nil
Area with
improved/rehabilitat
ed irrigation and
drainage services
(ha)
- 0 0 0 23,000 ha nil
Number of water
users provided with
new/improved/reha
bilitated irrigation
and drainage
services
(disaggregated by
gender)
- 0 0 0 30,000 farmers nil
Number of
operational water
user associations
- 0 0 0 23 WUAs nil
Number of targeted
clients who are
members of an
association
including producer
association,
cooperative, water
user association
etc (disaggregated
by gender)
- 0 0 0 30,000 farmers nil
Volume of farm
produce under
improved post-
harvest
management
- 0 n.a. n.a. 40,000 tons nil
Number of private
or public-private
agro-processing
and quality control
facilities installed
- 0 n.a. n.a. 6 facilities nil
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
63
GAFSP Core
Indicator Baseline
Reached
as of June
2015
Reached
as of Dec
2015
Reached
as of June
30, 2016
End of Project
Target (Enter
revisions in the
next column)
Revisions
(if any)
Number of client
days of training on
better post-harvest
storage,
transportation,
and/or
management
practices provided
(disaggregated by
gender)
- 0 0 0 50,000 client
days nil
Number of systems
introduced or
restored to improve
food security
monitoring and
early warning for
weather-related
risks
- 0 n.a. n.a. 1 system nil
Number of policies,
strategies,
frameworks or
investment plans
adopted
- 0 n.a. n.a. 5 policies nil
Number of
participants in M&E
workshops, training
events, seminars,
conferences etc.,
(disaggregated by
gender and
affiliation)
0 0 0
235 (full
disaggrega
ted data
not
available
yet)
300 participants nil
Annex 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
64
GENDER ACTION PLAN
The program is categorized as effective gender mainstreaming. It will enhance access of women farmers to decision making, resources, and services. Gender issues were incorporated into appropriate tranche conditions as stated in the policy matrix and gender indicators were included in all program outputs.
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Output 1. A Conducive Legal and Regulatory Environment established to facilitate Climate Resilient Rice Commercialization
Gender issues will be subsequently main-streamed into the Agricultural Land Law and the Law on Management and Use of Agricultural Land Responsibility: MAF, PDS, GSS Time: dependent on progress in Output 1: Policy
Gender issues are reflected in Agricultural Land Policy and the Law on Management and Use of Agricultural Land; however, qualitative and quantitative sex-disaggregation of the beneficiaries are not yet reflected in reports.
The Agricultural Land Policy and the Law on Management and Use of Agricultural Land are of particular importance because they are conditional to the release of the second tranche of funds by ADB.
Considering MAFF is a pioneer in gender mainstreaming, it was a surprise that the issue has completely left out gender issues in Land Policy White Paper, Agricultural Land Policy and Law on Management and Use of Agricultural Land.
Ensure gender analyses included in development of all policies Responsibility: PMO, NIOs MAFF, and PDS, GSS Time: by Q1 2016
The ADB has very clear guidelines and policies on consultations and in general expects as full and as meaningful consultation as is practically possible with all PIOs but with more intensive consultations with primary stakeholders, which include groups of people that are targeted to benefit from projects it finances.
Review draft policy documents stated in the second tranche of the policy matrix before the Government’s submission to ADB to ensure inclusion of gender mainstreaming issues. (Relevant policy documents reviewed and include gender issues by Yr 3)
Ensure inclusion of gender expertise in working groups for policy development
Responsibility: PMO, NIOs, LUP/GIS Time: by Q3 2015
The terms of reference for the Gender Specialists have been carefully reviewed with a few queries that need to be clarified by ADB.
Women staff comprise 17.7 % of total 96 NOI, PMO, PICs staffs which is below the 30% target as per project GAP.
The ambitious percentages as indicated in the GAP for women participation vary from 30 % to 50% e. Within PIC team and PMO, NIOs and PIOs, it was interpreted with caution because from experience, conditional clauses especially in construction/civil works may hamper progress.
All laws and legal documents will be adequately disseminated among male and female groups. Responsibility: PMO, NIOs, MAFF, MLMUPC, MOWRAM, LUP/GIS Time: dependent on progress in Policy issues
Not yet accomplished
Content of documented material for dissemination to be determined
Annex 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
65
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Output 2. Agricultural Land Use Zoning Improved
The guidelines for Establishing Agricultural land-use Zones will incorporate measures for involving women in planning and decision making.
Responsibility: NIO, MAFF and LUP/GIS Time: by Q1 2016
Landownership as indicator of wealth is acceptable but should include female-headed households as a sub-indicator.
A balance will have to be accepted so that technical activities will not override gender issues and vice versa. This matter has been brought up with the Gender Consultant at ADB Cambodia Resident Mission.
Ensure participation of women and women heads of households in collection of data and information relating to land-use zoning through use of women focal group discussion meetings. 90 groups of farmers consulted (with at least 40% female representation) during the
preparation of commune land use plans by 2018 Responsibility: PDA, PDLMUPC, LUP/GIS Time: by 2018
Not yet accomplished
Time frame has to be fine-tuned and fitted in with the other activities
The Rice-SDP monitoring system will incorporate sex disaggregated data. The GAP will be implemented within each and every program activity where relevant.
The GAP is prepared in order to highlight and remind the implementing agencies of their responsibilities.
Output 3. Climate Resilient Rice Value Chain Infrastructure Developed
Women will comprise 50% of the community
membership of construction sub-committees Responsibility: PDWRAM, RIE-H, CMS Time: concurrent with rehabilitation activities
Not yet accomplished
In the planned updating of the project GAP next year at Q3, 2016, the targets will be re-validated through series of participatory data gatherings with project beneficiaries and other stakeholders.
Separate women farmers’ meetings to discuss their needs related to location, alignment and access to irrigation infrastructure Responsibility: PDWRAM, PIOs and CMS Time: concurrent with rehabilitation activities
Not yet accomplished
Pending on timeframe of implementation of irrigation-related sub-projects
Final designs on infrastructure investments will be signed by construction sub-committees and commune councils. Further changes to the design must again be approved by the construction sub-committee
Not yet accomplished
The process of approval is to be determined. Sub-projects implementation to commence after feasibility studies (for some) and detailed design (for all)
Annex 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
66
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Responsibility: PDWRAM RIE-H, CMS Time: concurrent with rehabilitation activities
In labor-based civil works, 40% of unskilled laborers will be women. Women will receive
equal pay for equal work. Child labor will not be employed. These conditions are to be included in all construction contracts Responsibility: PIOs, PDWRAM, PDA and
Procurement Specialists Time: during sub-project implementation
Not yet accomplished
Construction contracts of each sub-project have differing conditions, including targets and will be addressed as sub-projects become implemented
Employment opportunities targeted at men and women will be communicated to communities Responsibility: PIOs, PDA, PDWRAM, RIE-H, CMS Time: during sub-project implementation
Not yet accomplished
Targeted for implementation as project implementation progresses.
Target of at least 30% employment of women as unskilled laborers in rice drying and
warehousing facilities Responsibility: PIOs, PDA and Procurement Specialists Time: at pre-construction phase
Construction and other civil works will be started after recruitment of consulting engineers; some preliminary design activities are currently implemented
Evidenced from employment list of facility after it is in operation
The nature of construction works involving women will be determined during pre-construction orientation with contractors
Target 50% women’s employment as administrative staff in rice drying and storage
facilities Responsibility: PIOs, PDA, RIE-H, Procurement Specialists Time: post facility establishment
A balance will have to be accepted so that technical activities will not override gender issues and vice versa.
Contract stipulates special conditions. Employment list of facility after it is in operation
Target 50% women employed in seed production facilities as unskilled and semi-
skilled laborers, e.g. seed and seed bed preparation, weeding and seed grading and sorting, packaging etc.
Discussions have been held with Some Seed Growers’ Groups in Farmers’ Cooperatives in target areas. This process will be expanded.
Target in business contracts. List of employment in each and every production facility, after they are in operation
Annex 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
67
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Responsibility: PIOs, PDA, Facility Operators, Business Dev. & Comm. Specialists, PPP Specialist Time: post facility establishment
Occupational safety measures and training provided to all workers. Responsibility: PDA, Facility Operators and Business Dev. & Comm. Specialists, PPP Specialist Time: pre-construction
To be implemented during pre-construction phase Targeted for implementation as project
implementation progresses.
Farmer Water User Communities (FWUCs) will accept membership registrations from husband and wife – 50% target for each. Responsibility: PDWRAM, PIO and CMS Time: throughout sub-project development
Community Mobilization Specialist (CMS) has been increasing awareness and encouraging commune authority preparation for FWUC to increase the participation of women.
Formal documentation, public announcements and membership lists of each FWUC are to be developed
Target at least 30% women in management positions in FWUCs. Women will be provided
training on leadership and management and will be remunerated for their roles. Responsibility: PDWRAM, PIO and CMS Time: throughout sub-project development
Community mobilization specialist (CMS) has been providing awareness and encouraging commune authority preparation for FWUC to increase the participation of women.
FWUC in Battambang (Prey Sangha) were established by ECOSORN project and recognized by PDWRAM, but they require strengthening
Some FWUCs require strengthening
List of attendees in training to be assessed during implementation of each sub-project
FWUC advisory committees established to monitor FWUC activities will comprise 50% women. Responsibility: PDWRAM, PIO and CMS Time: throughout sub-project implementation
Not yet accomplished
Facilitate gender mainstreaming training at community level with all project financed activities.
PIOs undertake training in all sub-project activities
Affected members dissatisfied with FWUC resolutions of disputes have the right to appeal to the FWUC advisory committee. Responsibility: PDWRAM, PIO and CMS Time: during facility operation
Not yet accomplished
FWUC advisory committee has a procedure for disputes and appeals after FWUC formation, pending on each sub-project
Affected women/households in FWUC will be identified and the information will be transferred to MAFF and PDA in the 3 provinces to be
Annex 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
68
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
included and prioritized in work-plans and training activities.
Water provision where feasible, will include both irrigation and non-irrigation water needs of households.
Responsibility: FWUC, PDWRAM and CMS Time: during sub-project implementation
Not yet accomplished
Villagers consulted in each and every sub-project on irrigation; pending on timeframe of sub-project implementation
Output 4. Rice Value Chain Support Services Enhanced to improve Quality of Cambodian Rice
Target at least 30% women in management positions in farmer cooperatives Responsibility: PDA, PIO, CMS Time: during sub-project implementation
Not yet accomplished. Preliminary discussions held with farmer cooperatives in Battambang.
Women in farmer cooperatives are the primary recipients of the project’s livelihood skills training to be conducted tentatively by 2016
Women will be provided training on leadership and management of cooperatives Responsibility: PDA, PIO and CMS Time: during sub-project operation
The GSS’s TOR and PAM’s GAP guide gender mainstreaming targets in the 30 sub-projects.
The GAP has been discussed with the other PICs ensuring that it is understood and that they include the stipulated targets in their activities. Review of policies and development of M&E have resulted in full gender inclusion.
In the planned updating of the project GAP in early 2016, the targets will be re-validated through a series of participatory data gathering missions with project beneficiaries and other stakeholders.
Farmer cooperatives will target membership of 50% men and 50% women. Responsibility: PDA, PIO and CMS Time: during sub-project implementation
Not yet accomplished. Preliminary discussions held at target sites in Battambang.
In the planned updating of the project GAP in early 2016. The formation and structure of cooperatives depends on the specifications of each sub-project.
Women will comprise 50% of participants in all project supported training in extension and
water management. Responsibility: PDA, PIO and Extension
Specialist Time: 2015-2017
Not yet accomplished
Undertake gender training at central and provincial levels Training to be completed by Yr 3 (Many government staff have been trained from different projects in the past 10 years. Training if required will be repetitive.)
Annex 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
69
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Agricultural extension training materials and revision of technology implementation procedures will include specific training needs identified by women farmers on enhancing productivity, diversification of produce, animal husbandry and safety procedures and new income generating activities. Responsibility: PDA, PIO and Extension Specialist Time: throughout
Not yet accomplished
PIOs, the main provincial and district staff and contracted service providers will undertake training on relevant sub-project activities involving diversification to establish community-based sub-committees’ roles and responsibilities.
50% of farmers in pilot on farm trials and
demonstrations will be women. Responsibility: PDA, PIO and Extension
Specialist Time: during sub-project execution
Not yet accomplished. Discussions at sites in Battambang show awareness and practice of this to varying extents.
Selection procedure stipulates women participation at commune targets.
Extension training activities will ensure location and timing convenient for women. Responsibility: PDA, PIO and Extension Specialist Time: throughout
Not yet accomplished
Extension training schedule will be implemented at every sub-project from Year 2016
Training material will be designed to meet the needs of female and male farmers including illiterate farmers Responsibility: PIO, PDA and Extension Specialist Time: throughout
Not yet accomplished. Build upon work done by JICA and IRRI
Select material by considering women’s needs in the community.
Some 25% of agricultural extension workers
trained shall be women. Not yet accomplished
Facilitate the mainstreaming of safety issues into MAFF/PDA animal husbandry training
Annex 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
70
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Responsibility: PDA, PDWRAM and Extension Specialist Time: 2016 through sub-project operation
List of extension workers in each province provided for action in 2016
Mass media extension material to be gender sensitive. Responsibility: PIOs, PDAs and Extension Specialist Time: throughout
Not yet accomplished
PIO will monitor the mass media extension material.
Facilitate linkages with Ministry of Health/Communicable Disease Project Phase 2, the Zoonotic Disease Unit and MAFF/GDA to provide occupational health and safety training to especially women poultry raisers
Address lack of access to credit by women and poor households (similar to TOR item xii). Responsibility: PDA, PIO, BAFS and CMS Time: during sub-project implementation
Not yet accomplished
Train provincial and district staff and contracted service providers in establishing and strengthening women’s savings and loan groups
Training depends on the formation of co-operative in each sub-project (use cross- provincial expertise among the 3 provinces. Some PDAs have experience in facilitating savings and loan groups)
Output 5. Weather-Indexed Crop Insurance (WICI) piloted
Some 50% of farmers under the pilot insurance scheme will be women and 10% of these to be female headed households. Responsibility: PMO, NIOs, PIOs, PIC, WICI
Consultants Time: Q4 2018 if feasible
Not yet accomplished Activity depends on the results of the WICI scheme pilot program
Output 6. Efficient Program Management and Implementation
Support PMO and PIOs. Responsibility: PMO, ISS-PIOs, PIC-GSSs Time: throughout
An orientation on GAP has been undertaken for the PMO and NIO MAFF and 3 PIOs.
Continuing discussions with PMO regularly
Gender balance may be achieved after the series of gender sensitization workshops with NIO, PMO and PICs.
The PIO has members who were not at all involved in the PPTA so the awareness and knowledge of Rice-SDP is weak. Wonder,
Annex 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
71
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
however, why the Program set such high percentages especially in women participation as unskilled workers in construction / rehabilitation activities knowing that out-migration from villages has almost depleted the able-bodied population, both men and women. PPTA did not mention this phenomenon.
Ensure sex-disaggregated performance monitoring system is established and operational. Responsibility: PMO-M&E, GSSs, MIS/Database Specialist Time: pre-construction phase as sub-project
implementation progresses
The GSSs have contributed to the drafting of the TOR for FS of sub-projects. The GAP in English and Khmer versions has been widely distributed.
There are hurdles to be overcome including over-saturation of gender training, ambitious targets, imbedded preference for separate gender activities and perception that gender inclusion interferes in technical activities.
All PMO and PIO staff shall be provided with gender training and roles and responsibilities involved in implementing the GAP. Responsibility: PMO, PIOs and GSSs Time: Q4 2014 and continuous
Training materials were produced in Khmer language by national gender consultant and distributed to participants during the training.
Total participants attending the training was 85 of which 15 (18%) were women.
Some challenges were raised during the training:
- Lack of budget for gender activities: training, meeting for villagers ,etc
- Number of women participating in the project is high but less women at decision making level
Note: - Fewer women attended gender training in
line NIO, PMO and PICs.
About 30% of technical and administrative positions to be filled by women (originally by Q2, 2013). Responsibility: PMO and GSSs Time: Q4 2015 – Q4 2017
To be implemented
Facilitate gender mainstreaming training at community level within all project-financed activities by preparation of material by Yr 1 and Training during Yrs 1, 2 and 3 (use material from other relevant projects)
Ensure participatory evaluations are conducted with male and female farmer groups at mid-term and end of the project reviews. Responsibility: PMO and ADB Time: periodically throughout
To be implemented
Review/monitor program progress and monitoring reports including baseline surveys and end-line impact evaluation reports to ensure data is gender disaggregated (Review progress reports quarterly).
Appendix 7
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DSEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
72
Progress Report for Program Implementation Consultants (Q2 2016)
April 2016
- Further progress was made by the national Policy Development Specialist on the
review of the draft prakas on seed certification and the technical guidelines for
Distinctness, Uniformity and Stability of varieties. A meeting was attended on the
Taskforce on drafting the national strategy on land degradation. Also attended a
meeting of the Working Group on Plant Protection which is now chaired by the
GDA/Director General. The general specifications of seed certification were prepared.
There also a meeting with CARDI on seed production strategies and constraints. There
was a meeting of the working group for Agricultural Land Zoning and the composition
of the group had been changed. Further discussions were held with the head of this
working group on the regional technical workshops that will need to be conducted as
well as the overall slow progress in the development of the guideline for agricultural
land use zoning.
- The draft Concept Paper on Certified Rice Seed Production that had been prepared
by the MAFF/NIO team was reviewed by the Team Leader (TL) and Deputy Team
Leader (DTL) and substantial changes were made to expand the scope and content.
The initial draft focussed only on the conduct of the Farmer Field Schools for certified
seed production and did not discuss the activities needed to address the shortage of
foundation seed, the mechanisms for multiplication of registered seed and the support
for rice seed producer groups to strengthen their own production capacity.
- A draft Concept Paper on Land Levelling was prepared by the TL and sent to the
MAFF/NIO for review and comment. This document was prepared based upon
information that was collected during field trips to Battambang and Kampong Thom
provinces to meet with contractors and also meetings in Phnom Penh with local dealers
in agricultural machinery.
- The DTL attended the meetings between ADB/CARM Project Officer and MAFF/NIO,
MOWRAM/NIO and MLMUPC/NIO teams when briefings were provided on the status
of activities and there was discussion of coordination mechanisms, commune target
selection, Annual work Plans and Budgets and other related issues.
- All PIC members joined the Kick Off Meeting for the ADB Review Mission. PIC Team
Leader (TL) and DTL participated in the ADB Review Mission to each target province
including meetings with the PIOs and visits to selected sub-projects sites.
- DTL and Land Use Planning Expert joined meeting between MAFF/NIO and
MOWRAM/NIO on the selection of target communes. The Land Use Planning Expert
then coordinated with each PIO to achieve a consensus on the final selection of the
target communes.
- DTL and TL attended the discussion at ADB/CARM together with the PMO Finance
Adviser to clarify the fund allocations for each NIO and PIO under each Output.
- DTL joined meeting at MAFF/NIO to review the seed standard.
- Field visit was made to Kampong Thom and Battambang provinces by the PPP
Specialist, together with the international and national post-harvest specialists, to
identify opportunities for PPP investments and to discuss and analyse these
arrangements with operators in the rice sector. The field visits were facilitated BY THE
Implementation Support Specialists (ISSs) based in each province. In Prey Veng four
rice mills and three agricultural cooperatives were visited and the cross border trade
for paddy into Vietnam was also observed. In Battambang there were also visits to four
Appendix 7
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DSEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
73
rice mils and three agricultural cooperatives as well as discussions with paddy traders.
Possible business models are being developed based on the information gathered
from these consultations.
- The international M&E Specialist completed the reports for the PPMS training were
completed and the final version of the draft PPMS Manual was submitted to the PMO
and ADB for review. The excel worksheets for CLUP and irrigation sub-projects were
finalised and sent to the PIOs. A draft ToR for the baseline survey was prepared.
- The national M&E Specialist Rice SDP website was further refined through updating
the interface and content management. There was also further work done to develop
the needed documentation link between the CLUP and pre-CLUP.
- The national Environment and Climate Change Expert (ECCE) completed the
preparation of the materials for the environmental safeguarding training and conducted
the training in each target province for the PIO staff and also for the NIOs/PMO staff.
Upon completion of the training articles were prepared on the environment
safeguarding reporting and these were uploaded to the Rice SDP website.
- A workshop organised by the Ministry of Environment and IIED for the launch of the
Cambodia National Climate Change Monitoring and Evaluation Framework was
attended by the national ECCE and the TL. During the workshop the ECCE provided
inputs for the preparation of sectoral M&E frameworks for climate change for MAFF
and MOH.
- The provincial ISSs assisted the PIO team to develop the ToRs for each of their staff.
These were submitted to the PMO but needed to be assembled into a common ToR
for all three provinces which can be incorporated into the PAM. They also assisted in
the organisation and facilitation of the monthly coordination meetings in each province
and supported the PIO during the ADB Review Mission visit.
- In Kampong Thom the ISS assisted with the facilitation of a field visit by the
MOWRAM/NIO team and the FS consultants to visit five irrigation sub-projects during
which there were meetings with local authorities and residents. In Battambang
province the ISS joined a visit by the PIO to one irrigation sub-project which overlaps
with a JICA funded project.
May 2016
- Further work was achieved by the national Policy development Specialist on policy
compliance including the following (i) the draft technical guidelines on DUS were
reviewed; (ii) the draft outline for land use zoning were reviewed and discussions with
the chair of the WG for land use zoning on the progress of the draft law; (iii) agreement
was reached with the WG responsible for agricultural use zoning on the outline of the
guideline; (iv) the draft seed standards and draft technical guideline for seed
certification were reviewed; (v) there was a meeting of the task force on drafting of the
National Action Program on land degradation; and (vi) the draft NAPLD was reviewed.
- The TL and DTL participated fully in the ADB Review Mission which commenced in
late April and concluded on 10th May with the wrap up meeting at SNEC. All PIC team
members attended the wrap up meeting. The PIC team has commenced working with
the PMO and NIOs to implement the agreed actions contained in the Aide Memoire.
- The TL and the international climate change expert reviewed the ToRs for the
FSDDCS for Paddy Drying and Storage and also the WICI were reviewed and revised
top incorporate climate change mitigation aspects. The revised ToRs were given back
to MAFF/NO for consideration prior to the re-advertisement for EoIs.
Appendix 7
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DSEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
74
- Support was provided by the international Extension Expert to the conduct of the ToT
on CAEA in Battambang organised by MAFF/NIO. Following the completion of the
training the CAEA manuals were revised and plans were made for the conduct of the
next round of ToT in KPT province to commence on June 27th.
- The international PPP Specialist completed further field visits to KPT province during
which there were meetings with operators (rice mills and cooperatives). Other
meetings were held in Phnom Penh with AMRU and AQUIP. He also facilitated the
meeting with MAFF/NIO team members as well as other stakeholders on the PPP
mode of operation and how it might be applied to the Rice SDP.
- The international and national Postharvest Specialists joined the field visits on KPT
with the PPP Specialist and also conducted further meetings in Phnom Penh with rice
millers. He also contributed during the meeting with the MAF/NIO with presentations
on rice milling operations and rice milling standards that are is use in Thailand.
- The TL, DTL and Postharvest Expert attended the meeting at MAFF/NIO to discuss
land levelling together with ISS and PDA representatives from each province. There
was agreement reached for the conduct of consultations with farmers in each proposed
irrigation sub-project site area, which will be coordinated by the PIC/ISSs, to discuss
and gauge the reaction of farmers to contribution to the cost of land levelling
- The RiceSDP website was restructured and new content updates were made for the
NIOs. Further work was done on the FSMIS and data extracted fir use in the ToT for
CAEA un Battambang. The use of social media was shared with the NIO and PIC
teams for more effective sharing of information. Further discussions were held with the
three ISSs for updating and revision of the PPMS indicators.
- The national Postharvest Specialist assisted MAFF/NO to prepare the list of grain
sampling equipment for procurement.
- The national Environment and Climate Change Expert met with MOWRAM to discuss
the safeguard reporting for the first two irrigation sub-projects and also worked in
partnership with the international Environment and Climate Change Expert during the
initial meetings including discussions with PMO Project Manager on future roles.
- The national Land Use Planning Specialist facilitated discussions with each NIO and
PIO to re-evaluate the selection of the target communes. He also assisted the
international Extension Specialist during the review of the CAEA manual and
completed the preparation of the ToR for the CLUP ToT.
- The ISSs provide on-going support in each province to the PIOs for (i) translation of
the PPMS for each sector and review of the formats for the recording forms and the
indicators; (ii) joined field visits by the MOWRAM/FSDDCS team to selected irrigation
sub-projects sites; (iii) assisted the PIO team during the auditor visit; (iv) joined the
ADB/CARM Mission wrap up meeting in Phnom Penh; (v) participated in field
consultations with farmers on the land levelling proposals; (vi) assisted the PIOs to
develop ToRs for their team members and in the preparation for recruitment of
additional incremental staff; (vii) participated in meeting to revise the PPMS recording
formats and review the indicators.
June 2016
- All PIC team members participated in the AWPB Launching Workshop which took
place 9th of June 2016, and was also attended by PMO, NIO and PIO team members.
Appendix 7
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DSEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
75
- The IEEs for the first two priority irrigation sub-projects prepared by MOWRAM were
reviewed and suggestions made on improvement and updating as well as
incorporation of climate change elements. An agreement was reach with MOWRAM
for the PIC Environment and Climate Change Experts to be mobilised when needed to
support the review of future IEEs.
- The Terms of Reference for the FSDDCS and WICI were extensively revised following
a meeting at ADB with MFF/NIO Project Coordinator. The two consultancy packages
have been split into two stages and the new versions for Phase 1 of each study have
been submitted to ADB for no objection.
- The final version of the National Seed Policy was discussed at a workshop organized
by MAFF/GDA, and it has been agreed that the Khmer version will be reviewed prior
to submission to MAFF.
- Further work was done on the CLUP ToR and PIC members participated in discussions
with the MLMUPC/NIO. Work also commenced on the preparation of a Concept Note
for CLUP describing the roles and responsibilities of the MLMUPC national and sub-
national teams as well as the national consultant firm that will be hired to conduct the
CLUP.
- The GAFSP Review Mission took place where project progress what presented for the
PMO, and the TL participated in a field mission to KPT to visit sub-project sites and
PIC team members joined the Kick Off and Wrap Up Meetings.
- A Finance Assistant has been hired and will be mobilized in July to support BTB PIO,
and an advertisement for a Finance Assistant for PVG PIO was posted.
- A Precision Laser Land Levelling Assessment Report based upon the consultations
with farmers in each province has been compiled and submitted to PMO.
Annex 8
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
76
Time Bound Action Plan from May 2016 Mission
Ref.
Par.
Agreed Action Deadline Focal Point Progress
7
Make concerted efforts to meet policy compliance
for tranche 2 particularly
(i) MAFF will have drafted the Law on Management
and Use of Agricultural Land;
(ii) National Action Plan for Land Degradation will
be ready by June 2016.
(iii) MAFF will have prepared and the Government
will have adopted the national action program to
combat land degradation in Cambodia”
(iv) Ministry of Industry and Handicrafts can issue
the standard specifications for ten varieties of
Cambodian milled rice
By 25 June 2016
PMO,
MAFF
MIME
Not Completed
PMO have submitted letter to ADB/CARM on July
5 requesting an extension of the deadline to 31
December 2016.
10
Assess whether any of the target communes
already have AEAs and CLUP or not to avoid
overlapping
By 31 May 2016 PIOs
Not completed
Additional time is required to complete the
assessment in all provinces.
11
Engage one district staff from 13 districts from
MLMUPC line, TORs prepared by MLMUPC and
PIOs recruit. They will be equipped with a
motorbike.
Concept note detailing roles and responsibility
within CLUP will be prepared and submitted for
endorsement.
30 June 2016
30 June 2016
MLMUPC and
PIOs
Partly completed
The ToR for the district staff for MLMUPC has
been prepared. Draft Concept Note is under
preparation.
12
Complete the concept paper for land leveling for
endorsement
Recruit services to conduct land leveling with
contract signed activity started on the ground
July 2016
October 2016
MAFF NIO/PIC
MAFF NIO/PIO
On Going
Field consultations with farmers in each province
have been completed. Consultative workshop has
been conducted in KPT with contractors.
Annex 8
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
77
Ref.
Par.
Agreed Action Deadline Focal Point Progress
15
Follow and monitor closely the milestones for
irrigation as listed in Appendix 4.
No replacements subproject candidate to be
discussed at this stage and NIOs and PIOs will
have to prioritize the subprojects.
Discussion with other projects that have links
before any subprojects are constructed.
Ongoing MOWRAM
On Going
FSs for first two priority irrigation sub-projects have
been revised to include updated IEEs and climate
change considerations. No consideration yet of
replacement or discussions with other projects that
overlap/link with proposed sub-projects.
16
The concept on paddy drying and storage facility,
with recommendations for proposed PPP model is
ready for discussion.
PMO endorsed concept note submitted to ADB for
no objection
Feasibility study and design team should engaged
June 2016
July 2016
August 2016
MAFF NIO/PIC
MAFF NIO/PMO
MAFF/NIO
On Going
PPP Concept paper was produced and reviewed.
Consultative Workshop with private sector
stakeholders will be conducted in late July.
18 Submit request for budget reallocation with the
amount of $1.5 million for feasibility studies By July 2016
MAFF NIO /
PMO
Not completed
21 Engagement of the service provider for WICI MAO NIO
On Going
After consultations with ADB/CARM the he WICI
FS has been revised.
23
Organize national AWPB Launching Workshop for
all NIO Teams, PIO management teams plus
provincial focal points (PDA, PDOWRAM &
PDLMUPC) and PIC members.
20 May 2016 PMO/PIC
Completed
AWPB Launching Workshop was conducted on
June 10th.
24 Conduct regular coordination meetings On-going Steering
committee
Partially Completed
Regular monthly coordination meetings are being
organized by the PIOs and the MAFF/NIO. Other
coordination meetings have not yet commenced.
Annex 8
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
78
Ref.
Par.
Agreed Action Deadline Focal Point Progress
25
PPMS endorsement and put into use
Regular update of Program Website
Baseline Study conducted and information is
available.
15 June 2016
On-going
Q3 2016
PMO/ADB
PMO/NIOs/PIOs
PMO/PIC
On Going
PPMS has been submitted to the ADB/CARM.
During the GAFSP Mission in last week of June it
was agreed to revise the activity indicators to
simplify them and also to separate the three
monitoring frameworks.
26 Assign focal points to update website and social
media. By 31 May 2016 PMO/NIOs/PIOs
Completed
With support from the PIC team each NIO and PIO
has now an assigned focal point for uploading
material to the website and social media and
training has been provided.
27 Review the needs and procure two more vehicles By July 2016 PMO
On Gong
The Procurement Plan has been revised to include
the procurement of two additional vehicles.
32 Submit contract variation number 2 reflect the
changes made and the requirement for better
effectiveness
By 25 May 2016 PMO/PIC Completed
CV2 has been approved by ADB/CARM.
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
79
Status of procurement of contract packages (30 June 2016)
Contract Package / Description Status EA/ IA
No. of contracts
Date of Award
Estimated Value [USD]
Contract Amount [USD]
GOODS
GD-EQPT1 Supply and installation of paddy drying and storage equipment.
No Prequalification of Bidders. No. of packages to be determined after detailed designs completed.
MAFF n.a. - 3,800,000 n.a.
GD-EQPT2 Supply and installation of seed paddy drying and storage equipment.
No Prequalification of Bidders. No. of packages to be determined after detailed designs completed.
MAFF n.a. - 4,000,000 n.a.
GD-EQPT3 Procurement of office equipment.
No Prequalification of Bidders. Equipment for the PMO, NIOs and 3 PIOs was procured by respective PMO, NIO, and PIOs. Five contracts already signed for PMO, MAFF & MLMUPC computers.
PMO/MAFF/MOWRAM/ MLMUPC/
PIOs
5 2015 322,500 205,959
GD-EQPT4 Procurement of equipment for seed laboratory.
No Prequalification of Bidders. Bidding document: Goods Contract signed but goods not delivered yet.
MAFF 1 - 163,800 251,840
GD-FUR1 Office furniture for PMO and NIOs.
No Prequalification of Bidders.
PMO 1 28/12/15 50,000 47,483
GD-FUR2 Office furniture for PIOs. No Prequalification of Bidders. PMO 1 11/04/16 24,000 24,677
GD-MAT1 Producing certified / foundation seeds.
No Prequalification of Bidders. One contract completed in 2015.
MAFF 2 22/07/15 40,000 24,696
GD-VEH1 Procurement of vehicles. No Prequalification of Bidders. Procurement method includes UN method.
PMO/ NIOs
4 2015 361,000 339,400
GD-VEH2 Procurement of motorcycles. No Prequalification of Bidders. Total of 97 motorcycles: PMO (28), MAFF (26), MLMUPC (18) for PIO staff and one motorcycle for each NIO & PMO.
PMO/ MAFF/
MOWRAM/ MLMUPC
3 2016 175,000 134,829
GD-VEH3 Procurement of two vehicles for PMO.
No Prequalification of Bidders.
PMO 1 16/8/16 98,000 99,000
GD-EQPT5 Procurement of Training Tool Kits & one set of Grain Quality Testing Machine
No prequalification of Bidders.
MAFF 1 n.a. 20,000 n.a.
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
80
Contract Package / Description Status EA/ IA
No. of contracts
Date of Award
Estimated Value [USD]
Contract Amount [USD]
CIVIL WORKS
CW-FAC1 Construction of paddy drying and storage facilities.
No Prequalification of Bidders. No of packages to be determined after detailed designs are completed. Recruitment of consultants under CON-FS/DD/CS AGR (1 & 2) has made slow progress and construction will not commence until mid-2017.
MAFF n.a. n.a. 5,400,000 n.a.
CW-FAC2 Construction of seed drying and storage and Construction Supervision.
No Prequalification of Bidders. No of packages to be determined after detailed designs are completed. Recruitment of consultants under CON-FS/DD/CS AGR 1 & 2) has made slow progress and construction will not commence until mid-2017.
MAFF 4 n.a. 2,300,000 n.a.
CW-SP1 Civil works for irrigation rehabilitation subprojects.
No Prequalification of Bidders. Contract awards will commence after completion of detailed designs under CON-FS/DD/CS (IRR).
MORWAM 19 n.a. 14,310,000 -
CW-LL1 Precision land leveling contracts. No Prequalification of Bidders. Award of small land levelling contracts will be managed by the PIOs but no action yet on bidding process.
PIO 15 n.a. 1,200,000 -
CW-OFF1 Office renovation for PMO and NIOs.
No Prequalification of Bidders. PMO 1 17/11/15 70,000 63,849
CONSULTING SERVICES
CON-PIC1 Program Implementation Consultants.
Assignment: International Quality/Cost Ration: 80/20 Procurement by PMO in coordination with NIOs.
PMO 1 20/10/14 7,180,000 7,160,842
CON-FS/DD/CS (IRR) National for FS, detailed design and construction supervision for irrigation subprojects.
Assignment: National Contract awarded and consultants were mobilized in March 2016.
MOWRAM 1 15/02/16 2,100,000 2,054,485
CON-CIS (1) Firm for design and FS, and if feasible, pilot testing of WICI.
Assignment: International. Advertisement for EoIs in April was unsuccessful.
MAFF 1 n.a. 500,000 -
CON-CIS (2) Pilot testing of a weather-indexed crop insurance scheme.
Assignment: National. No action yet.
MAFF 1 n.a. 500,000 -
CON-FS/DD/CS (AGR 1) Feasibility Study of Rice Seed Processing, Paddy Drying and Storage Facilities.
Assignment: National. Advertisement for EoIs in March 2016 was unsuccessful.
MAFF 1 n.a. 200,000 -
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
81
Contract Package / Description Status EA/ IA
No. of contracts
Date of Award
Estimated Value [USD]
Contract Amount [USD]
CON-FS/DD/CS (AGR 2) Detailed Design of Rice Seed Processing, Paddy Drying and Storage Facilities.
Assignment: National. No action yet.
MAFF 1 n.a. 800,000 n.a.
CON-MS Miller service contracts for capacity development.
Assignment: National. No action yet.
MAFF 1 n.a. 500,000 n.a.
CON-BH1 Bulk handling study. Assignment: National. ToR is under preparation
MAFF 1 n.a. 18,200 n.a.
CON-ME1 Recruitment of independent monitoring entities.
Assignment: National. No action yet.
PMO 6 n.a. 557,200 n.a.
CON-LUP National for services to prepare CLUPs.
Assignment: National. ToR under preparation.
MLMUPC 1 n.a. 1,500,000 n.a.
CON-NIO1 Procurement specialists for MAFF/NIO.
Assignment: National. Expertise: Procurement
MAFF 1 04/05/16 90,000 31,740
CON-NIO2 Financial management specialists for NIOs.
Assignment: National Expertise: Financial Management
PMO/MAFF MOWRAM
3 2015/6 180,000 84,804
CON-PMO1 Procurement Specialist for PMO.
Assignment: National Expertise: Procurement
PMO 1 05/02/15 96,000 79,212
CON-PMO2 Financial Management Specialist for PMO.
Assignment: National Expertise: Financial Management
PMO 1 05/02/15 90,000 70,726
CON-AUD1 Program audit. Assignment: National No action yet.
PMO 1 - 74,200 n.a.
Annex 10
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOE DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
82
Summary of priority sub-projects
No. UnitRiels
(Billion)
USD
(Million)
B-7 Rehabilitation of Anglong Ruon system Thmor Korl Irrigation Rehabilitation of 6.3 km of link canal, 21 km of secondary canals and associated structures 1,200 ha 6 2 4 1,065 3 2
B-8 Rehabilitation of Ta Maov Irrigation System Thmor Korl Irrigation Rehabilitation of 4.0 km of link canal, 5.8 km (5) secondary canals and associated structures 200 ha 5 1 1 195 2 4
B-9 Rehabilitation of Mok Rea Secondary Canal Rokha Kiri Irrigation Rehabilitation of 5 km of secondary canal 800 ha 5 1 1 510 6 9
B-6 Rehabilitation of O’ Voir Irrigation System Moung Roussei Irrigation Construction of 1.9 km dike and rehabilitation of 7.3 km of canal and associated structures 1,800 ha 5 1 4 720 9 6
B-3Support for Seed Production in Chong Samnay
with Irrigation RehabilitationMoung Roussei Seed Production
Rehabilitation of 4 km of secondary canal and associated water management structures with support for
seed producing cooperative4,500 ha 2 1 19 5,343 4 5
B-2 Prey Sangha Rice Seed Production Bavel Seed ProductionRehabilitation of 4.4 km of main canal and associated water management structures with support for
seed producing cooperative1,145 ha 2 1 9 522 1 (RS) 1 (RS)
B-4 Seed Drying and Storage Facility Bavel Seed Production Construction of seed drying and storage facility for PPP operation (to be defined) 600 ton 7 2 9 522 5 3
B-5 Seed Drying and Storage Facility Moung Roussei Seed Production Construction of seed drying and storage facility for PPP operation (to be defined) 600 ton 7 2 19 5,343 7 7
B-1 Paddy Drying and Storage Facility Thmor Korl Paddy Storage Construction of 10,000 ton paddy drying and storage facility for PPP operation 10,000 ton 16 4 335 102,978 8 8
K-7 Rehabilitation of Chhuk Khsak Canal Barray Irrigation Rehabilitation of 9 km of secondary canal and associated structures 1,430 ha 4 1 9 1,253 1 (RS) 1 (RS)
K-10 Rehabilitation of Bat Trang Irrigation System Stoung Irrigation Construction of new 120 m weir and rehabilitation of 6 km of irrigation canals 2,000 ha 8 2 16 2,951 7 2
K-9 Rehabilitation of Ta Soong Canals Barray Irrigation Rehabilitation of 1 secondary canal and associated structures 1,330 ha 5 1 12 2,715 5 6
K-8Rehabilitation of Kampaeuy Secondary Canal of
Stung Chinit Irrigation SystemBarray Irrigation Rehabilitation of 7 km of secondary canal and associated structures 650 ha 6 1 4 1,234 4 4
K-3Support for Rice Seed Production with
Rehabilitation of Trach Canal
Stoung & Kg
SvaySeed Production
Support for seed production in San Kor Mean Chey, Kg Svay District, and Trach Canal Stoung District;
and rehabilitation of 4 existing canals and associated structures 947 ha 7 2 18 2,304 3 3
K-4Support for Rice Seed Production with
Rehabilitation of Pnov Irrigation SystemSantuk & Barray Seed Production
Support for rice seed production in Chhuk Ksach, Barray District, in Kvek Baray Dst, and Pnov, Santuk
Dst, and rehabilitation of 8.2 km of Pnov irrigation canal and associated structures1,056 ha 6 1 12 2,834 8 8
K-5 Seed Drying and Storage Facility Barray/ Stoung Seed Production Construction of seed drying and storage facility for PPP operation 600 ton 7 2 12 2,834 6 7
K-6 Seed Drying and Storage Facility Kg Svay/ Stoung Seed Production Construction of seed drying and storage facility for PPP operation 600 ton 7 2 18 2,304 10 10
K-1 Paddy Drying and Storage Facility Stung Sen Paddy Storage Construction of 10,000 ton paddy drying and storage facility for PPP operation 10,000 ton 16 4 59,000 2 5
K-2 Paddy Drying and Storage Facility Stoung Paddy Storage Construction of 10,000 ton paddy drying and storage facility for PPP operation 10,000 ton 16 4 331 60,000 9 9
P-10 Rehabilitation of Ansong Irrigation System Kg Trabek Irrigation Rehabilitation of 6 km of main and 24 km of secondary canals (6), and associated structures 1,192 ha 8 2 5 1,073 4 3
P-9 Rehabilitation of Anlong Char Canal Preah Sdach Irrigation Rehabilitation of 15km of main canal and structures 2,659 ha 7 2 10 2,135 6 7
P-11 Rehabilitation of Rumlech Irrigation system Sithor Kandal IrrigationRehabilitation of reservoir, rehabilitation of 130 m of existing dam, construction of new spillway, and
rehabilitation of 3 km of main and 9 km of secondary canals and associated structures2,117 ha 7 2 10 1,011 5 4
P-7Rehabilitation of Chhue Teal, Boeung Khanhey
Irrigation SystemSvay Antor Irrigation Rehabilitation of 4.8 km of existing dike and 8 km of main canal and associated structures 3,032 ha 6 2 26 2,602 9 8
P-8Rehabilitation of Chamcar Kuoy Canal
RehabilitationSvay Antor Irrigation Rehabilitation of 8.5 km of existing main canal and structures 1,900 ha 6 1 9 1,428 3 9
P-4Support for Seed Production Program at Russey
Sanh VillageSithor Kandal Seed Production
Capacity building in rice seed production, and rehabilitation of associated irrigation system, including
7.5km of main and 20km of secondary canals1,200 ha 7 2 9 3,447 8 2
P-3Support to Seed Production Program at Kg.
Thnal VillagePreah Sdach Seed Production Capacity building in rice seed production, and rehabilitation of 4 km of irrigation canals 550 ha 2 1 6 84 2 6
P-6 Seed Drying and Storage Facility Sithor Kandal Seed Production Construction of 600 Ton seed drying and storage facility for PPP operation 600 ton 7 2 9 3,447 7 5
P-5 Seed Drying and Storage Facility Preah Sdach Seed Production Construction of 600 Ton seed drying and storage facility for PPP operation 600 ton 7 2 6 n.a. 10 10
P-1 Paddy Drying and Storage Facility Svay Antor Paddy Storage Construction of 10,000 ton grain drying and storage facility for PPP operation 10,000 ton 16 4 9 1,623 1 (RS) 1 (RS)
P-2 Paddy Drying and Storage, Facility Preah Sdach Paddy Storage Construction of 10,000 ton grain drying and storage facility for PPP operation, at Kg Thnal Village 10,000 ton 16 4 375 72,732 11 11
Overall Totals 223 56 1,307 344,209
Priority
(2012)
Prov. Re-Priority
(Jan 2015)
BATTAMBANG PROVINCE
KOMPONG THOM PROVINCE
PREY VENG PROINCE
No Name of Subproject District Type Summary Description
Details Estimated CostNo. of
Villages
No of Direct
Beneficiaries
(HH)
Annex 11
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
83
Compliance with Loan and Grant Covenants (Q2 2016)
SN Covenant Reference in Loan / Grant
Agreement Status as of Q2 2016
Financial
1 (a) The Recipient shall (i) maintain separate accounts and records for the Project; (ii) prepare annual financial statements for the Project in accordance with accounting principles acceptable to ADB; (iii) have such financial statements audited annually by independent auditors whose qualifications, experience and terms of reference are acceptable to ADB, in accordance with international standards for auditing or the national equivalent acceptable to ADB; (iv) as part of each such audit, have the auditors prepare a report (which includes the auditors' opinion on the use of the Grant proceeds and compliance with the financial covenants of this Grant Agreement as well as on the use of the procedures for the imprest fund and statement of expenditures) and a management letter (which sets out the deficiencies in the internal control of the Project that were identified in the course of the audit, if any); and (v) furnish to ADB, no later than 6 months after the end of each related fiscal year, copies of such audited financial statements, audit report and management letter, all in the English language, and such other information concerning these documents and the audit thereof as ADB shall from time to time reasonably request. (b) ADB shall disclose the annual audited financial statements for the Project and the opinion of the auditors on the financial statements within 30 days of the date of their receipt by posting them on ADB's website. (c) The Recipient shall enable ADB, upon ADB's request, to discuss the financial statements for the Project and the Recipient's financial affairs where they relate to the Project with the auditors appointed pursuant to subsection (a) (iii) hereinabove, and shall authorize and require any representative of such auditors to participate in any such discussions requested by ADB. This is provided that such discussions shall be conducted only in the presence of an authorized officer of the Recipient, unless the Recipient shall otherwise agree.
Grant 0349, Section 4, para 2
The PMO and also NIOs and PIOs have all established separate Imprest Accounts for receipt of project loan and grant funds. Annual financial statements for end of financial year 2015 were prepared and external audits will be conducted in Q2 2016. PMO have provided training to the NIO and PIO accounting staff on the SOPs.
2 (a) The Borrower shall (i) maintain separate accounts and records for the Project; (ii) prepare annual financial statements for the Project in accordance with accounting principles acceptable to ADB; (iii) have such financial statements audited annually by independent auditors whose qualifications, experience and terms of reference are acceptable to ADB, in accordance with international standards for auditing or the national equivalent acceptable to ADB; (iv) as part of each such audit, have the auditors prepare a report (which includes the auditors' opinion on the use of the Loan proceeds and compliance with the financial covenants of this Loan Agreement as well as on the use of the procedures for the imprest fund and statement of expenditures) and a management letter (which sets out the deficiencies in the internal control of the Project that were identified in the course of the audit, if any); and (v) furnish to ADB, no later than 6 months after the end of each related fiscal year, copies of such audited financial statements, audit report and management letter, all in the English language, and such other information concerning these
Loan 3007, Article 4, para 2
The PMO and also NIOs and PIOs have all established separate Imprest Accounts for receipt of project loan and grant funds. Annual financial statements for end of financial year 2015 were prepared and external audits will be conducted in Q2 2016. PMO have provided training to the NIO and PIO accounting staff on the SOPs.
Annex 11
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
84
SN Covenant Reference in Loan / Grant
Agreement Status as of Q2 2016
documents and the audit thereof as ADB shall from time to time reasonably request. (b) ADB shall disclose the annual audited financial statements for the Project and the opinion of the auditors on the financial statements within 30 days of the date of their receipt by posting them on ADB's website. (c) The Borrower shall enable ADB, upon ADB's request, to discuss the financial statements for the Project and the Borrower's financial affairs where they relate to the Project with the auditors appointed pursuant to subsection (a)(iii) hereinabove, and shall authorize and require any representative of such auditors to participate in any such discussions requested by ADB. This is provided that such discussions shall be conducted only in the presence of an authorized officer of the Borrower, unless the Borrower shall otherwise agree.
3 (a) The Recipient shall (i) maintain separate accounts and records for the Project; (ii) prepare annual financial statements for the Project in accordance with accounting principles acceptable to ADB; (iii) have such financial statements audited annually by independent auditors whose qualifications, experience and terms of reference are acceptable to ADB, in accordance with international standards for auditing or the national equivalent acceptable to ADB; (iv) as part of each such audit, have the auditors prepare a report (which includes the auditors' opinion on the use of the Grant proceeds and compliance with the financial covenants of this Grant Agreement as well as on the use of the procedures for the imprest fund and statement of expenditures) and a management letter (which sets out the deficiencies in the internal control of the Project that were identified in the course of the audit, if any); and (v) furnish to ADB, no later than 6 months after the end of each related fiscal year, copies of such audited financial statements, audit report and management letter, all in the English language, and such other information concerning these documents and the audit thereof as ADB shall from time to time reasonably request. (b) ADB shall disclose the annual audited financial statements for the Project and the opinion of the auditors on the financial statements within 30 days of the date of their receipt by posting them on ADB's website. (c) The Recipient shall enable ADB, upon ADB’s request, to discuss the financial statements for the Project and the Recipient's financial affairs where they relate to the Project with the auditors appointed pursuant to subsection (a)(iii) hereinabove, and shall authorize and require any representative of such auditors to participate in any such discussions requested by ADB. This is provided that such discussions shall be conducted only in the presence of an authorized officer of the Recipient, unless the Recipient shall otherwise agree.
Grant 0350, Section 4, para 2
The PMO and also NIOs and PIOs have all established separate Imprest Accounts for receipt of project loan and grant funds. Annual financial statements for end of financial year 2015 were prepared and external audits will be conducted in Q2 2016. PMO have provided training to the NIO and PIO accounting staff on the SOPs.
Safeguards
4 The Borrower shall ensure that the preparation, design, construction, implementation and operation of the Project, each Subproject and all Project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the lEE, the EMP, and any corrective or preventative
Loan 3007, Schedule 5, para 2
Work has not yet commenced on the feasibility studies for the sub-projects.
Annex 11
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
85
SN Covenant Reference in Loan / Grant
Agreement Status as of Q2 2016
actions set forth in a Safeguards Monitoring Report.
5 The Borrower shall ensure that climate change considerations are incorporated in the design and implementation of the Subprojects.
Loan 3007, Schedule 5, para 3
Work has not yet commenced on the feasibility studies for the sub-projects.
6 The Borrower shall ensure that no subproject which meets ADB's category A environmental criteria set out in the Safeguard Policy Statement is included in the List of Candidate Subprojects, and that no subproject with category A environmental criteria is financed under the Project.
Loan 3007, Schedule 5, para 4
Work has not yet commenced on the feasibility studies for the sub-projects.
7 The Borrower shall ensure that all land and all rights-of-way required for the Project, each Subproject and all Project facilities are made available to the Works contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with (a) all applicable laws and regulations of the Borrower relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement Safeguards; (c) the RF; and (d) all measures and requirements set forth in the respective RP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Loan 3007, Schedule 5, para 5
Work has not yet commenced on the feasibility studies for the sub-projects.
8 Without limiting the application of the Involuntary Resettlement Safeguards or the RP, the Borrower shall ensure that no physical or economic displacement takes place in connection with the Project until: (a) compensation and other entitlements have been provided to affected people in accordance with the RP; (b) a comprehensive income and livelihood restoration program has been established in accordance with the RP; and (c) all land and all rights-of-way required for a Subproject is free of all encumbrances.
Loan 3007, Schedule 5, para 6
Work has not yet commenced on the feasibility studies for the sub-projects.
9 The Borrower shall ensure that no subproject which meets ADB's category A resettlement criteria set out in the Safeguard Policy Statement is included in the List of Candidate Subprojects, and that no subproject with category A Resettlement Criteria is financed under the Project.
Loan 3007, Schedule 5, para 6
Work has not yet commenced on the feasibility studies for the sub-projects.
10 The Borrower shall ensure that the Project does not have any indigenous peoples impact, all within the meaning of the Safeguard Policy Statement. In the event that the Project does have any such impact, the Borrower shall take all steps required to ensure that the Project complies with the applicable laws and regulations of the Borrower and with the Safeguard Policy Statement.
Loan 3007, Schedule 5, para 8
Work has not yet commenced on the feasibility studies for the sub-projects.
Social
11 The Borrower shall ensure that the GAP is fully implemented and that all Project related activities are designed and implemented in accordance with ADB's Policy on Gender and Development (1998). In particular, the Borrower shall ensure: (a) 50% female membership in community construction sub-committees; (b) 40% female employment as unskilled laborers in Works; (c) 30% female in management positions in farmer cooperatives and farmer water user's committees; (d) 50%
Loan 3007, Schedule 5, para 13
GAP is being updated as a part of the QPRs
Annex 11
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
86
SN Covenant Reference in Loan / Grant
Agreement Status as of Q2 2016
female farmers in pilot on farm trials and demonstrations and pilot crop insurance schemes; and (e) 50% female trainees in all Project training.
12 The Borrower shall ensure that Project Provinces promote active community awareness and stakeholder participation in the design, implementation and performance monitoring of the Subprojects, though (a) disseminating information regarding the nature of the Subprojects in open public forums, and (b) establishing a mechanism for public consultation.
Loan 3007, Schedule 5, para 17
Work has not yet commenced on the feasibility studies for the sub-projects.
Sector
13 The Borrower shall: (a) ensure that all policy actions adopted under the Program as set forth in the Policy Letter and the policy matrix continue to be in effect for the duration of the Program and subsequently; and (b) adopt all policy actions under the Program, as set forth in the Policy Letter and the policy matrix, in accordance with the planned schedule and shall ensure that such policy actions continue to be in effect for the duration of the Program and subsequently.
Loan 3006, Schedule 4, para 2
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
14 The Borrower shall keep ADB informed of policy discussions with other multilateral and bilateral aid agencies that may have implications for the implementation of the Program and shall provide ADB with an opportunity to comment on any resulting policy proposals. The Borrower shall take into account ADB's views before finalizing and implementing any such proposal.
Loan 3006, Schedule 4, para 3
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
15 The Borrower shall ensure that the Counterpart Funds are used to finance the structural adjustment costs relating to the implementation of the reforms under the Program and other activities consistent with the objectives of the Program. The Borrower shall further ensure that the Counterpart Funds are used in accordance with its Standard Operating Procedures.
Loan 3006, Schedule 4, para 4
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
16 The Borrower shall ensure that each contract for Eligible Items is awarded on the basis of the purchaser's normal commercial procurement practices in the case of procurement by the private sector, or the Borrower's prescribed procurement procedures in the case of procurement by the public sector, having due regard for principles of economy and efficiency.
Loan 3006, Schedule 4, para 5
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
17 The Borrower shall, and shall cause MEF, MAFF, MLMUPC and MIME to, (a) comply with ADB's Anticorruption Policy (1998, as amended to date) and acknowledge that ADB reserves the right to investigate directly, or through its agents, any alleged corrupt, fraudulent, collusive or coercive practice relating to the Program; and (b) cooperate with any such investigation and extend all necessary assistance, including access to all relevant books and records, for satisfactory completion of such investigation.
Loan 3006, Schedule 4, para 6
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
Others
18 The Borrower and MEF shall ensure that the Project is implemented in accordance with the detailed arrangements set forth in the PAM. Any subsequent change to the
Loan 3007, Schedule 5, para 1
Work on revision of the PAM will commence in Q2 led by the PIC team.
Annex 11
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
87
SN Covenant Reference in Loan / Grant
Agreement Status as of Q2 2016
PAM shall become effective only after approval of such change by the Borrower and ADB. In the event of any discrepancy between the PAM and this Loan Agreement, the provisions of this Loan Agreement shall prevail.
19 a) The Borrower shall maintain, or cause to be maintained, records and documents adequate to identify the Eligible Items financed out of the proceeds of the Loan and to record the progress of the Program. (b) The Borrower shall enable ADB's representatives to inspect any relevant records and documents referred to in paragraph (a) of this Section
Loan 3006, Article 4, para 2
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
20 (a) As part of the reports and information referred to in Section 6.05 of the Loan Regulations, the Borrower shall furnish, or cause to be furnished, to ADB all such reports and information as ADB shall reasonably request concerning (i) the Counterpart Funds and the use thereof; and (ii) the implementation of the Program, including the accomplishment of the targets and carrying out of the actions set out in the Policy Letter, (b) Without limiting the generality of the foregoing or Section 6,05 of the Loan Regulations, the Borrower shall furnish, or cause to be furnished, to ADB quarterly reports on the carrying out of the Program and on the accomplishment of the targets and carrying out of the actions set out in the Policy Letter.
Loan 3006, Article 4, para 3
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
21 The Borrower shall enable ADB's representatives to inspect the Project, the Goods and Works, and any relevant records and documents.
Loan 3007, Article 4, para 3
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
22 The Recipient shall enable ADB's representatives to inspect the Project, the Goods and Works, and any relevant records and documents.
Grant 0349, Article 4, para 3
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
23 The Recipient shall enable ADB's representatives to inspect the Project, the Goods and Works, and any relevant records and documents.
Grant 0350, Article 4, para 3
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
24 The Recipient shall (a) ensure that the proceeds of the Grant are used for the purposes of the Project and not diverted for any other purpose; (b) promptly inform ADB if it becomes aware that the proceeds of the Grant are being or have been used for the purpose of any payment to a person or entity, or for import of goods, if such payment or import is prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations; and (c) take necessary measures to ensure that entities to which the Recipient makes the proceeds of the Grant available comply with the provisions of this paragraph.
Grant 0349, Article 4, para 4
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
25 The Borrower shall make available necessary budgetary and human resources to fully implement each EMP and RP.
Loan 3007, Schedule 5, para 9
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
26 The Borrower shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to: (a) comply with the measures relevant to the contractor set forth in each lEE, EMP
Loan 3007, Schedule 5, para 10
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
Annex 11
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
88
SN Covenant Reference in Loan / Grant
Agreement Status as of Q2 2016
and RP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report; (b) make available a budget for all such environmental and social measures; (c) provide the Borrower with a written notice of any unanticipated environmental or resettlement risks or impacts that arise during construction, implementation or operation of the Project that were not considered in each lEE, EMP and RP; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and (e) fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.
27 The Borrower shall do the following: (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission; (b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in each lEE, EMP and RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and (c) report any actual or potential breach of compliance with the measures and requirements set forth in an EMP or RP promptly after becoming aware of the breach.
Loan 3007, Schedule 5, para 11
Work has not yet commenced on the feasibility studies for the sub-projects.
28 The Borrower shall ensure that no proceeds of the Loan are used to finance any activity included in the list of prohibited investment activities provided in Appendix 5 of the Safeguard Policy Statement.
Loan 3007, Schedule 5, para 12
Work has not yet commenced on the feasibility studies for the sub-projects.
29 The Borrower shall ensure that candidate subprojects in each Project Province are considered and feasibility studies and detailed design of such candidate subprojects are carried out in the order of priority indicated in the List of Candidate Subprojects.
Loan 3007, Schedule 5, para 14
Work has not yet commenced on the feasibility studies for the sub-projects.
30 After completion of the requisite feasibility studies, the Borrower shall cause the PMO to ascertain whether the candidate subprojects meet the following criteria to be eligible for financing under the Project: (a) a subproject should be technically feasible and economically viable. If the estimated economic rate of return is below 12%, other significant benefits shall be quantified to demonstrate economic viability of such subproject; (b) procurement package(s), method(s) of procurement and cost estimates shall have been prepared; (c) a detailed financing plan for operation and maintenance of the subproject shall have been prepared: (i) identifying the entity which shall be responsible for the operation and maintenance of the subproject; and (ii) confirming the Project Province's commitment though budgetary allocation to provide requisite funds needed for the operation and maintenance of the subproject; (d) public hearings on a subproject proposal shall have been held in concerned communes and villages, and beneficiary representatives shall have been included in
Loan 3007, Schedule 5, para 15
Work has not yet commenced on the feasibility studies for the sub-projects.
Annex 11
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
89
SN Covenant Reference in Loan / Grant
Agreement Status as of Q2 2016
the subproject implementation subcommittee to ensure continued public consultation and supervision; (e) the subproject must be shown to have no significant negative environmental or social impacts, and mitigation measures shall have been identified for minor impacts; (f) the subproject must be shown to have no significant resettlement impacts, and if such subproject Is categorized as Category B, a RP has been prepared in accordance with the RF, the Borrower's laws and regulations and the Safeguard Policy Statement; and (g) the subproject must be shown to have no outstanding social safeguards issues resulting from existing facilities. In case there are any such outstanding issues, the Borrower shall ensure that the PIO concerned shall have prepared a corrective action plan in accordance with the Safeguard Policy Statement to address the same.
31 In case that a candidate subproject does not meet the criteria provided in paragraph 15 above, it shall be replaced by the next priority candidate subproject for the respective Project Province under the List of Candidate Subprojects. If a candidate subproject not listed in the List of Candidate Subprojects is to be considered, such subproject shall be examined and screened by MEF with the support from an independent consultant acceptable to ADB and the Borrower and submitted to ADB for approval.
Loan 3007, Schedule 5, para 16
Work has not yet commenced on the feasibility studies for the sub-projects.
32 Within 12 months of the Effective Date, the Borrower shall cause MEF to engage a suitably qualified and experienced social science institute, university, consulting firm or a non-governmental organization, acceptable to ADB, to monitor Project benefits and submit annual benefit monitoring reports to the Borrower and ADB.
Loan 3007, Schedule 5, para 18
Not due yet.
33 The Borrower shall and shall cause MEF, MAFF, MOWRAM, MLMUPC and the Project Provinces to (a) comply with ADB's Anticorruption Policy (1998, as amended to date) and acknowledge that ADB reserves the right to investigate directly, or through its agents, any alleged corrupt, fraudulent, collusive or coercive practice relating to the Project; and (b) cooperate with any such investigation and extend all necessary assistance, including access to all relevant books and records, as may be necessary for the satisfactory completion of any such investigation.
Loan 3007, Schedule 5, para 19
Not due yet.
34 The Borrower shall and shall cause MEF, MAFF, MOWRAM, MLMUPC and the Project Provinces to ensure that the anticorruption provisions acceptable to ADB are included in all bidding documents and contracts, including provisions specifying the right of ADB to audit and examine the records and accounts of MEF, MAFF, MOWRAM, MLMUPC, Project Provinces and all contractors, suppliers, consultants, and other service providers as they relate to the Project.
Loan 3007, Schedule 5, para 20
Not due yet.
Annex 12
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
90
Rice-SDP RISK MANAGEMENT MATRIX
(L = Likelihood: (5 = Almost Certain; 4 = Likely; 3 = Possible; 2 = Unlikely; 1 = Rare; C = Consequence: (5 = Severe; 4 = Major; 3 = Moderate; 2 = Minor; 1 = Negligible) R = Risk Level: (4 = Extreme; 3 = High; 2 = Medium; 1 = Low)
Identified Risk Damage to Project L C R Risk Response Responsibility for
Managing
Project Outcome
Farmers fail to make the
transition from export of paddy
to Viet Nam / Thailand, to sell
to local millers and rice
exporters
Failure in transition would negate the
longer-term objectives of increase in
revenue from rice exports and increase
in net profit of rice exporters.
5 5 4
Ensure that a separate survey on baseline and target indicator is
conducted during the second year of the program to validate
information of informal paddy trade across the border with Thailand
and Viet Nam, as provided for in the PAM.
PMO & MAFF with
support from PIC
Project Outputs
Output 1: A Conducive Legal and Regulatory Environment Established to Facilitate Climate-Resilient Rice Commercialization
Delays in finalizing and
approving the Seed Policy
Delayed release of 2nd Tranche might
affect implementation of investment
components of the Project.
2 4 2 Ensure that the latest version of the Seed Policy is reviewed as
quickly as possible and passed to MAFF for approval MAFF
Delays in finalizing the Prakas
required to implement Chapter
3 of the Seed Law (2008)
Delayed release of 2nd Tranche might
affect implementation of investment
components of the Project; lack of good
Prakas will impede the implementation
of the seed certification scheme, which
is a key ‘value chain service’
3 4 2
The latest versions of the Prakas must be critically reviewed to
ensure that they provide a sound basis for the operation of the seed
certification scheme and of the seed testing laboratory.
MAFF
Delays in meeting the deadline
for submission of Law on
Agricultural Land Use and
Management by the Tranche 2
due date (June 2016).
Delayed release of 2nd Tranche might
affect implementation of investment
components of the Project.
4 3 2
Ensure that sufficient resources are available to GDA/MAFF on time
to carry out the required preparation of documents and
consultations. Agree on a timeline for preparation of intermediate
drafts of regulations. Recruit experts (e.g. for land and women
issues) to assist in the formulation of drafts for discussion. Use PIC
experts to facilitate review of documents and meetings.
MAFF
Appendix 12
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
91
Identified Risk Damage to Project L C R Risk Response Responsibility for
Managing
Output 2: Agricultural Land-use Zoning Improved
Implementation of CAEA and
CLUP is delayed and the
annual target cannot be met.
CEAE lays the foundation and provides
essential information to guide the
implementation of Rice SDP sub-
projects and other activities. Any delay
in CAEA implementation will have
serious impacts on all other project
components.
2 4 3
Despite good preparation (the CAEA manual has been upgraded,
training materials have been produced and communes prioritised
for CAEA implementation) there remains a risk of delay. Close
technical backstopping will be important to avoid this, especially in
the early rounds of CAEA until experience is gained. Un-coupling
CAEA from CLUP has significantly reduced the likelihood of delays
and the plan to involve the Rice SDP Extension Specialist in the 3
CAEA pilots will greatly reduce this risk.
MAF, DAE
backstopping, POIs,
Output 3: Climate Resilient Rice Value Chain Infrastructure Developed
Delay of the implementation of
the planned and scheduled
sub-projects
If the certain infrastructure/building
implementation projects are delayed,
that can cause in worst case almost one
year delay for implementation because
of the seasonal and weather conditions.
In addition this can have affect for the
other planned & scheduled activities.
3 4 2 Strong and on-going project management and following the critical
and scheduled milestones agreed. EAs/IAs/PIC
Output 4: Rice Value Chain Support Services Enhanced to Improve Quality of Cambodian Rice
Insufficient certified/improved
seed is available due to slow
implementation of the seed
certification scheme
Increase in paddy production and
improvements in quality of milling paddy
will not be achieved
4 3 2
Ensure that seed certification is implemented in line with the
Prakas and that all necessary resources are available to launch
certified seed production; this includes the availability of sufficient
basic (foundation) seed from CARDI, which may need to be
addressed by the project.
MAFF/CARDI
Use of certified seed is
unpopular among farmers due
to prohibitive price or other
reasons
This would adversely affect the targeted
increase in paddy production to 9.5
million tons in 2018.
3 4 2
What type or variety to plant is the decision of the farmer. If non-
certified seeds have a lower price and there is a ready market for
paddy from such seeds, a farmer will decide to use non-certified
seeds. Rice-SDP needs to strongly support dissemination of new
technologies to farmers such as the use of commercial seeds.
MAFF
Appendix 12
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q2 2016
92
Identified Risk Damage to Project L C R Risk Response Responsibility for
Managing
Mixture of different rice
varieties without clearly
identified will affect to the
rice market and export.
This mixture can be done in each
of rice value supply chain from
farming, trading, milling, exporting
for sake of the business, especially
the imitated fragrant rice variety
Sen Kraob mix with the original
fragrant rice Phka Romduol.which
hard to identify by normal physical
analysis.
4 4 3
GDA/MAFF must use Cambodia Rice Standard for all rice products
and set up Central Lab with adequate equipment to measure and
certify the rice samples in time.
Ministry of Commerce shall enforce all millers and rice exporters to
respect code of conduct and true to label.
MAFF/MoC
Output 5: Weather-indexed Crop Insurance Piloted
Farmers fail or have no interest
to buy insurance for their
crops.
Smallholder farmers still depending on
donation provided by relief agencies
when their crop damaged by disasters.
4 3 2
Crop insurance concept is new to Cambodia. Thus, it will require a
considerable effort to develop legal infrastructure, promote private
sector participation and raise awareness among stakeholders.
Government subsidies on the premium payout is one of the best
way to get farmer participating in the initial stage/piloting phase.
MAFF, MEF, PIC
Output 6: Efficient Program Management and Implementation
Coordination between all
involved agencies
As the project structure is complex and
there are many different stakeholders,
the coordination of the implementation
and other activities is crucial
3 3 2 PPMS and other management tools in place and effective use.
Strengthen the coordination role and mechanisms of the EA. EAs, IAs, PIC