Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
R&D Meeting, March 23th, 2017 1
Review on Crab Test at SPS
Facility
Salvador Sosa
Old Dominion University
R&D Meeting, March 23th, 2017 2
Material from the 6th HL-LHC Collaboration Meeting (Nov 2016)
– https://indico.cern.ch/event/549979/
Crab Cavity SPS Test (Jan 2016)
– https://indico.cern.ch/event/463435/
4th Joint HiLumi LHC-LARP Annual Meeting (Nov 2014)
– 2017-2018 CC Validation Run: Status and Issues, A. McPherson
– https://indico.cern.ch/event/326148/contributions/1711560/attachm
ents/633139/871382/SPS_Crabs_HL_LHC.pdf
This presentation composed of…
R&D Meeting, March 23th, 2017 3
Cavity validation with beam (field, ramping, RF controls, impedance)
– Operation of such type of cavities in high current and high energy CW (proton) circular
machines has not been done before.
Cavity Transparency
– Injection, capture, acceleration where the cavities are carefully counter-phased.
– Ultra-precise control of cavity voltage and phase guarantees the preservation of beam
quality throughout the cycle.
Collimation, machine protection, RF noise, emittance growth, non-linearities, Instrumentation
and interlocks.
Guarantee the operation of cavities with a trip rate significantly below the LHC availability. To
validate this is in SPS is pre-requisite both with and w/o beam.
Unlike electrons, there are many aspects (emittance growth, machine protection, RF non-
linearity, instabilities) where proton beam tests are the only conclusive answer.
Goals of CC Test at SPS
logo
area
Impact of (Cost & Schedule) Reviews
4
▪ SPS Tests
▪ Prepare & test one cryomodule in the SPS before 2018
▪ SPS-LSS6 dedicated test stand for beam tests in 2018
▪ Integration almost complete, installation starts in 2 months
▪ LHC
▪ ½ system (16 cavities) as a new baseline
▪ New production strategy with industry starting 2017
▪ UK pre-series cryostat & US contribution (10 RFD dressed Cav)
▪ RF power infrastructure reduction to 40 kW-CW (80 kW peak)
logo
area
SPS Tests Program – Weekly Schedule
5
EN-MME BE-RF/SRF EN-ACE TE-CRG TE-VSCBE-RF
Cavity #1
ready
22/12/16
Cavity #2
ready
02/02/17
Cavity #2
pieces
produced
28/10/16
Cavity #1
pieces
produced
03/10/16
String
assembled
27/07/17
CM
assembled
06/12/17
CM
commissioned
In SPS
23/02/18
Missing
12 days
logo
area6
7
MD Parameters
• For crab cavity tests with proton beams in the SPS
Units Value
Energy GeV 26 − 450
Coast Energy GeV 55, 120, 270
Intensity p/bunch 0.05 − 1.3 × 1011
RF Voltage MV 3.0 − 7.0
4th Harmonic Voltage MV 0.0
Bunch Length ns < 2.0
Longitudinal Emittance eVs 0.35 − 0.5
Betatron Tunes 26.12, 26.18
𝛽𝑥,𝑦 m 40, 80
Dispersion m −0.5
logo
area8
logo
area
Prototype Cryomodules
9
Vertical crossing for ATLAS,
first one to go to SPS 2018
Horizontal crossing for CMS
Cavities starting 2017
300K
10−10mbar~10−7mbarAtm Pressure
2K − 80K
2K2K
300K
10
Mechanical Parameters
• SPS between QDA.61710 – MST61779
• In the SPS alignment tolerances are generally more relaxed. However
the tighter tolerances derived for the LHC are kept for validation.
Units Value
Total Cryomodule length m 2.9
Total Bypass length m 9.5
Cavity Aperture mm 𝟖𝟒
Transverse Cavity Alignment
mm ≤ 0.5
Transverse Tilt degrees < 0.3
11
Cavity Parameters
Two cavity types (Ver & Hor) (ATLAS & CMS)
Vertical cavities will go first in the SPS
Units Value
Frequency MHz 400.79
Number of Cavities 2
Kick Voltage/cavity MV 3.4
R/Q (linac convention) Ω ∼ 400
Max RF Power kW 40 (80)
Cavity detuning kHz ±100 (−60)
Cavity bandwidth Hz 800
DQW RFD
Pictures courtesy EN-MME
logo
area
SPS Cavities, 2K Volume
12
Bulk Nb cavities, Dipolar symmetry
𝑉𝑇 = 3.4 MV (𝐸𝑝, 𝐵𝑝 ≤ 40 MV/m, 70 mT)
Stored energy ~ 10 − 12 J
CERN insourced DQW production
Nov 2015
DQW RFD
logo
area13
Dressed Cavities (2K volume)Fundamental
Power Coupler
Tuning
Mechanism
HOM
Coupler
(Niobium)
Hel-Vessel
(Titanium)
CavityCold
Magnetic
Shield
Tuner frame
(Titanium)
Pickup HOM
HOM
Main Mechanical interfaces:
He-vessel: Bolted-welded concept
Cold magnetic shield
Tuner: Sym. tuning with warm actuation
Three point support + alignment system
Main RF interfaces
1 FPC: Single ceramic coaxial line
3 HOMs: Two stage filter, coaxial
1 PU: Cu-Nb for field probe + HOM
Similar concept for RFD with different HOM interfaces
Some Final Comments• A new paradigm on SC compact deflecting cavities will soon
be validated with the highest energy protons for the first
time in the world
• There is an intense level of activity on many fronts
• USLARP & UK collaborations were an integral part w/o
which it SPS tests be impossible
• The design choices for the CM & RF services (after many
iterations) are robust. We have validated most important
elements by prototyping (cavity, tuner, He-vessel…)
14
R&D Meeting, March 23th, 2017 15
Extra Slides
logo
area16
17
Test Program Summary
• In-situ cryomodule RF commissioning/testing in park position
• RF commissioning with low-intensity beam, 1-12 bunches
• Establish proper RF parameters (operating frequency, amplitude, and phase)
• Verify that CCs are transparent (cavity counter-phasing and detuning)
• High intensity single bunch up to 4x72 trains
• Impact on cavity performance (including transient behavior), impedance, stability
& machine protection as a function of beam current; interlocks
• Verify cavity stability over many hours (relevant for LHC physics fill)
• Long-term behavior of coasting beams in the SPS with 1-bunch
• Study the effects of cavity drifts, emittance growth, non-linear effects such as RF
multipoles
Goal of this meeting to define a detailed & prioritized program that would
constitute the success of the SPS tests and min goals for 2018
l/4 TEM Cavity – BNL (Ilan Ben-Zvi)
• Cavity is very short in the direction of opposing beamline.
• Nearest HOM is far away.
400 MHz Cavity Comparison
RF Dipole (ODU)
4-Rod(UK)
¼ Wave (BNL)
Cavity Radius [mm]
147.5 143/118 142.5
Cavity Length[mm]
~600 ~500 ~400
Beam Pipe [mm]
84 84 84
Peak E field 33 29.5 32.3
Peak B- Field 56 59.5 57.3
RT/Q 287 915 318