8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
1/31
Quality Improvement: Problem Solving
Week 6AgenAgendada
Review Homework Problems Ch 3: 2, 4
Chapter 3: Problem Solving
Desksides: 7 QC Tools
Flow chart Run Chart Pareto Diagram Histogram Cause and Effect Diagram Check sheet Scatter diagram Control chart
Week 7 assignment Read chapter 4
Homework
problems: Ch 3
- 11, 12, 23, 28(c) Case Study: "How
We Slashed
Response Time"
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
2/31
Quality Improvement: Problem Solving
Seven QualitySeven Quality
ToolsToolsChapter 3: Problem
Solving
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
3/31
Quality Improvement: Problem Solving
Seven QualitySeven QualityControl ToolsControl Tools
Pareto Chart
Histogram
Process flow diagram
Check sheet
Scatter diagram
Control chart
Run Chart
Cause and Effect Diagram
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
4/31
Quality Improvement: Problem Solving
Pareto PrinciplePareto Principle
Vilfredo Pareto (1848-1923) Italian
economist
20% of the population has 80% of thewealth
Juran used the term vital few, trivial
many. He noted that 20% of the quality
problems caused 80% of the dollar loss.
7 Quality Tools7 Quality Tools
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
5/31
Quality Improvement: Problem Solving
Pareto chartPareto chart
7 Quality Tools7 Quality Tools
28
16
12 12
64 3
0
5
10
15
20
25
30
LooseThreads
Stitchingflaws
Buttonproblems
Materialflaws
%
Co
mplaints
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
6/31
Quality Improvement: Problem Solving
ParetoParetoChartChart
Percentfrom
eachcau
se
Causes of poor quality
Machine
calib
ratio
ns
Defec
tivep
arts
Wrong
dime
nsion
s
Poor
Design
Operato
rerro
rs
Defec
tivem
aterials
Surfa
ceabrasio
ns0
10
20
30
40
50
60
70(64)
(13)(10)
(6)(3) (2) (2)
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
7/31Quality Improvement: Problem Solving
HistogramHistogram
0
5
10
15
20
25
1.9
2.9
3.9
4.9
5.9
6.9
7.9
8.9
9.9
10.9
11.9
12.9
13.9
14.9
15.
9
Mo
re
Category
Frequency
7 Quality Tools7 Quality Tools
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
8/31Quality Improvement: Problem Solving
HistogramHistogram
0
510
15
20
2530
35
40
1 2 6 13 10 16 19 17 12 16 20 17 13 5 6 2 1
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
9/31Quality Improvement: Problem Solving
FlowchartsFlowcharts
Flowcharts Graphical description of how work is done.
Used to describe processes that are to beimproved.
7 Quality Tools7 Quality Tools
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
10/31Quality Improvement: Problem Solving
Flow DiagramsFlow Diagrams
" Draw a flowchart for whatever you do.
Until you do, you do not know what you
are doing,
you just have a job.
-- Dr. W. Edwards Deming.
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
11/31Quality Improvement: Problem Solving
FlowchartFlowchart
Activity
DecisionYesYes
NoNo
7 Quality Tools7 Quality Tools
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
12/31Quality Improvement: Problem Solving
FlowchartFlowchart
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
13/31Quality Improvement: Problem Solving
Flow DiagramsFlow Diagrams
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
14/31Quality Improvement: Problem Solving
Flow DiagramsFlow Diagrams
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
15/31
Quality Improvement: Problem Solving
Process ChartProcess ChartSymbolsSymbols
Operations
Inspection
Transportation
Delay
Storage
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
16/31Quality Improvement: Problem Solving
Process ChartProcess Chart
Ste
p
Opera
tion
Transport
Inspec
t
De
lay
Sto
rage
Dista
nce
(fee
t)
Tim
e
(min)Description
of
process
1
2
3
4
5
6
7
8
9
10
11
Unload apples from truck
Move to inspection station
Weigh, inspect, sort
Move to storage
Wait until needed
Move to peeler
Apples peeled and cored
Soak in water until needed
Place in conveyor
Move to mixing area
Weigh, inspect, sort
TotalPage 1 0f 3 480
30
5
20
15
360
30
20
190 ft
20 ft
20 ft
50 ft
100 ft
Date: 9-30-00
Analyst: TLR
Location: Graves Mountain
Process: Apple Sauce
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
17/31Quality Improvement: Problem Solving
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
18/31Quality Improvement: Problem Solving
Check SheetCheck SheetCheck SheetCheck Sheet
ShiftsShifts
D
efect
Type
D
efect
Type
7 Quality Tools7 Quality Tools
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
19/31Quality Improvement: Problem Solving
Check SheetCheck Sheet
COMPONENTS REPLACED BY LAB
TIME PERIOD: 22 Feb to 27 Feb 1998
REPAIR TECHNICIAN: Bob
TV SET MODEL 1013
Integrated Circuits ||||
Capacitors |||| |||| |||| |||| |||| ||
Resistors ||Transformers ||||
Commands
CRT |
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
20/31Quality Improvement: Problem Solving
Cause-and-EffectCause-and-EffectDiagramsDiagramsCause-and-EffectCause-and-EffectDiagramsDiagrams Show the relationships between a
problem and its possible causes.
Developed by Kaoru Ishikawa (1953) Also known as
Fishbone diagrams
Ishikawa diagrams
7 Quality Tools7 Quality Tools
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
21/31Quality Improvement: Problem Solving
Cause and EffectCause and EffectSkeletonSkeletonCause and EffectCause and EffectSkeletonSkeleton
Quality
Problem
Materials
EquipmentPeople
Procedures
7 Quality Tools7 Quality Tools
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
22/31Quality Improvement: Problem Solving
Fishbone DiagramFishbone Diagram
Quality
Problem
MachinesMeasurement Human
ProcessEnvironment Materials
Faulty testing equipment
Incorrect specifications
Improper methods
Poor supervision
Lack of concentration
Inadequate training
Out of adjustment
Tooling problems
Old / worn
Defective from vendor
Not to specifications
Material-handling problems
Deficienciesin product
design
Ineffective quality
management
Poor process
design
Inaccurate
temperature
control
Dust and
Dirt
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
23/31
Quality Improvement: Problem Solving
Cause and effectCause and effectdiagramsdiagrams Advantages
making the diagram is educational in itself
diagram demonstrates knowledge of
problem solving team
diagram results in active searches for
causes
diagram is a guide for data collection
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
24/31
Quality Improvement: Problem Solving
Cause and effectCause and effectdiagramsdiagrams
To construct the skeleton, remember:
For manufacturing - the 4 Ms
man, method, machine, material For service applicationsequipment, policies, procedures, people
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
25/31
Quality Improvement: Problem Solving
Scatter DiagramScatter Diagram
.
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
26/31
Quality Improvement: Problem Solving
Run ChartsRun Charts
Run Charts (time series plot) Examine the behavior of a variable over
time.
Basis forControl Charts
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
27/31
Quality Improvement: Problem Solving
Control ChartControl Chart
18
12
6
3
9
15
21
24
27
2 4 6 8 10 12 14 16
Sample number
Numberofd
efects
UCL = 23.35
LCL = 1.99
c = 12.67
Control ChartsControl Charts
Control Chartsontrol harts
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
28/31
Quality Improvement: Problem Solving
Control ChartsControl Charts Control Chartsontrol harts
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
29/31
Quality Improvement: Problem Solving
Stem and leafStem and leafdisplaysdisplays
4 . 6 4 . 0 3 . 7 4 . 1 4 . 1 5 . 6 4 . 5 6 . 0 6 . 0 3 . 4
3 . 4 4 . 6 3 . 7 4 . 2 4 . 6 4 . 7 4 . 1 3 . 7 3 . 4 3 . 3
3 . 7 4 . 1 4 . 5 4 . 6 4 . 4 4 . 8 4 . 3 4 . 4 5 . 1 3 . 9
Data
Integrated Circuit Response Time (ps)
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
30/31
Quality Improvement: Problem Solving
Stem and leafStem and leafdisplaysdisplays
3 7 4 4 7 7 4 3 7 9
4 6 0 1 5 6 2 6 7 1 1 5 6 4 8 3 4
5 6 1
6 0 0
Integrated Circuit Response Time (ps)
8/14/2019 Review Homework Problems Ch 3: 2, 4 Chapter 3:
31/31
Dot diagramsDot diagrams
3 4 5 6
Plant A
Plant B
Integrated Circuit Response Time (ps)