Restoration of Durbar
Hall at University
College for Women,
Koti, Hyderabad
Progress Report
March 2016
WORLD
MONUMENTS
FUND
Phase IRestoration of Darbar Hall at University College for Women, Koti, Hyderabad
CONSULTANTS
Ar. Ravi Gundu Rao
Ar. B. Sarath Chandra
Ar. Anuradha Naik
Ar. Tapan Mittal Deshpande
Ar. Apoorva Pillay
Ar. Anshul Rawat
JEERNODHAR CONSERAVTORS PVT. LTD.
Nilesh Thakkar
Gautam Ramesh
WORLD
MONUMENTS
FUND
STATE ARCHAEOLOGY DEPARTMENT
N.R. Visalatchy, Director
Raheem Shah, Deputy Director
OSMANIA UNIVERSITY
UNIVERSITY COLLEGE FOR WOMEN
Prof. B.T. Seetha, Principal
Prof. Y.L. Srinivas, PRO
BUILDING DIVISION
B.L.N. Reddy, Consulting Chief Engineer
Srinivas Reddy, Executive Engineer (EE)
V. Devapriya, Dy EE
D. Anjali, AEE
PROJECT TEAM
Phase IRestoration of Darbar Hall at University College for Women, Koti, Hyderabad
COMPLETED Exceeding Quantity DURATION OF WORK LEFT
Items of Work
1. Dismantling wooden structural system: timber in roofs and floors
2. Clean removal of cement plaster from walls and raking out joints
3. Laying lime concrete 1:1½:2 (1 lime: 1½ sand: 2 Brick Agregate)
4. Provision of Teak Wood to be put up for main structural beams
5. Providing Anti termite treatment as per IS 6315
6. Providing and applying steel protection coating
7. Plastering with Lime Surkhi plaster of thickness 25mm including preparation of mortar
8. Additional thickness of 20mm of Lime plaster as per the original thickness of the plaster
9. Stitching of cracks using stone lintels (50x150x1000mm)
10. Recycling old wood dismantled from the building for restoration purposes
Phase IRestoration of Darbar Hall at University College for Women, Koti, Hyderabad LOWER GROUND FLOOR
STAGES OF WORK → 1 2
Stone and mud masonry visible after dismantling cementplaster near the staircase.
Openings below the staircase, filled up with brick masonry.
CLEARANCE AND DISMANTLING- CEMENT PLASTER
STAGES OF WORK → BEFORE AFTER
Stone slab at the base of anarch, which was once closedwith brick masonry.
The stone slabs were demolished and the arches were openedup.
CLEARANCE AND DISMANTLING- EASTERN OPENINGS
Starting of work: 04.03.2016Status: On-going
Duration of work: 2 DaysStatus: Completed
Phase I
STAGES OF WORK → BEFORE AFTER
Careful removal of cement plaster and damaged lime plaster from walls of oval room for opening up of cracks
Restoration of Darbar Hall at University College for Women, Koti, Hyderabad
CLEARANCE AND DISMANTLING- PLASTER REMOVAL
↑N
Cement plaster layer removed Lime plaster layer removed
FIRST FLOOR
Duration of work: 17 DaysStatus: Completed
STAGES OF WORK → 1 2
Decayed wooden beams at the top of surrounding wallsin first floor lobby, have beendismantled completely, to preventfurther structural damage due towood decay.
CLEARANCE AND DISMANTLING- WOODEN BEAM
Duration of work: 7 DaysStatus: Completed
Phase IRestoration of Darbar Hall at University College for Women, Koti, Hyderabad
STAGES OF WORK → 1
Wooden beams have been replaced with brick masonry inlime mortar to pack the vacant space.The wooden beam is carefully pulled down and the vacantspace is cleaned and washed.After cleaning, the consolidation of brick wall is carriedout with new brick masonry in lime mortar.This intervention would further prevent structural damageto the building due to wood decay.
STRUCTURAL CONSOLIDATION- BRICK WORK
STAGES OF WORK →
Crack stitching with granite lintel (50mmx150mmx1000mm).The crack is opened up, the loose masonry is removed and thenthe void is washed properly with a jet sprayThe granite stone is then placed carefully in the void.After the insertion of granite block, the crack is tightly packed withbrick and lime. A nozzle is inserted for further grouting
STRUCTURAL CONSOLIDATION- CRACK STITCHING
Duration of work: 2 DaysStatus: Completed
Opening in the wall visible after removal of plaster
FIRST FLOOR
Duration of work: 7 DaysStatus: Completed
Phase IRestoration of Darbar Hall at University College for Women, Koti, Hyderabad FIRST FLOOR
STAGES OF WORK → 1 2
Old decayed wooden lintels were carefully dismantled from the openingsafter propping them,and replaced withnew, chemicallytreated wood.
Replaced newwooden lintel
STRUCTURAL CONSOLIDATION- WOODEN LINTEL IN OPENINGS
STAGES OF WORK →
The picture shows the application of anti-termite paint onthe wooden lintel of size (6’’x4’’x7’).
Replaced new wooden lintel in the opening in one of therooms on first floor.
STRUCTURAL CONSOLIDATION- WOODEN LINTEL IN OPENINGS
Duration of work: 4 DaysStatus: Completed
Duration of work: 2 DaysStatus: Completed
Phase I
3
Planks are screwed (8mm ø; 2’’ long screws) onto thewooden rafters.Wooden flooring after the completion of fixing floorplanks to the wooden rafter frame below.
Restoration of Darbar Hall at University College for Women, Koti, Hyderabad FIRST FLOOR
STAGES OF WORK → 1 2
After the restoration of damaged wooden rafters, woodenfloor planks are laid over the structural frame.
Planks are joined together with a tongue and groove jointat the ends.
STRUCTURAL CONSOLIDATION- WOODEN FLOORING
↑NNew rafters
Duration of work: 17 DaysStatus: Completed
SECTION OF WOODEN FLOORING
BEAM SECTIONBEAM & RAFTER DETAILJOINARY DETAIL OF RAFTERS
Phase I
The consolidated old beam is tied and then lift witha crane. After the beam has been lifted up, themajor task is to place the beam inside the wallend. The whole process requires a lot of manpower.Crane lifting capacity: 100 tonnesTime taken: 40minMan power: 8-10 people
Restoration of Darbar Hall at University College for Women, Koti, Hyderabad
STAGES OF WORK → 1 2
The remaining wooden part of the old beam inside the wall,is removed completely
The debris is removed and the space is cleaned properlyfor placing the beam
STRUCTURAL CONSOLIDATION- PLACEMENT OF BEAM
↑N
Duration of work: 14 DaySStatus: Completed
FIRST FLOOR
Phase I
Cross-section of Dome 3
Application of final finish of smooth lime plaster (niru maal) onthe dome.
Restoration of Darbar Hall at University College for Women, Koti, Hyderabad
STAGES OF WORK → 1 2
1.5’’ thick rough lime plastering was applied as the firstlayer on the external surface of dome after carefulremoval of cement plaster.
The 2nd layer of lime plaster is ¼ ’’ thick.
TERRACE
↑N
CONSOLIDATION- LIME PLASTERING ON DOME
Duration of work: 28 DaysStatus: Completed
Phase IRestoration of Darbar Hall at University College for Women, Koti, Hyderabad TERRACE
STAGES OF WORK → 1 2
A solution of slaked lime mixed with water, saras(animalfat), jaggery, surkhi(brick powder) and marble powder isprepared as a grouting solution, which is poured on theground so that it gets into each crack in the floor.
After 1st layer of grouting, a thin layer of waterproofingcloth material is laid on the ground, over which anotherlayer of viscous grouting mixture is laid uniformly.
↑N
CONSOLIDATION- WATERPROOFING
Duration of work: 24 DaysStatus: Completed
4 3
The first layer of kappi is compacted well, using wooden batsto repeatedly strike the ground.
Mixture of lime and brick bats are laid evenly on ground andcompacted well. The first layer of kappi (lime concrete) is4’’ thick overall and 2.5’’ thick towards the drain.
Phase I
7
After the completion of waterproofing, gunny bags are laid overit and water is sprinkled all over, to keep the waterproofing wetthroughout in order to prevent cracks.
Restoration of Darbar Hall at University College for Women, Koti, Hyderabad
5 6
2nd layer of lime concrete (3’’ thick) is laid over the 1st layer.Through repeated compaction, the surface is given an even surface, with a clear slope towards the drain.
Waterproofing layer after the completion of compaction.
4:7 Gradient towards the drain
4:7 Gradient towards the drain
TERRACE
Phase IRestoration of Darbar Hall at University College for Women, Koti, Hyderabad
MATERIAL MATERIAL PROCUREMENT/ PROCESSING
1. Lime Preparation of niru maal on siteThis is a type of fine plaster which is applied over mota maal (which is the rough first layer of lime plaster on any surface).Niru maal is applied for final smoother finish on surface.One truck load of lime ordered in March
2. Wire cut bricks
Bricks have been cut on site as per desired/required size for various on site construction/consolidation works
3. Beam The irregular edges of the beam were chiselled off and were given a sharpedge. The wood was treated and processed to give a finished look.
Preparation of beamfor oval room- The damagedbeam would beconsolidated usingwooden pieces ofrequired sizes andfurther joinedtogether usingSS clamps.- It would be furtherheld together with ametal capping.
MATERIAL PREPARATION
Mortise and tenon joint for joining wooden parts
to the old beam
Placing of wooden parts on the beam
Phase IRestoration of Darbar Hall at University College for Women, Koti, Hyderabad
MATERIAL MATERIAL PROCUREMENT/ PROCESSING
3. Beam Fixing of all the partsof the beam togetherto complete thecomposite beam forthe western oval room
Anticorrosive paint is applied on thebeam and once it dries, SS clamps arefixed with screws at the consolidated end,to hold the joints together.