Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
RESIDENTIAL PARKING DEMAND STUDY
FOR THE
MONTEREY STATION TRANSIT ORIENTED DEVELOPMENT
MARCH 2012
PREPARED BY
TABLE OF CONTENTS
1. INTRODUCTION ............................................................................................................................................ 1
PROJECT DESCRIPTION................................................................................................................................................................. 1
TRANSIT ACCESS ............................................................................................................................................................................. 4
CITY CODE PARKING REQUIREMENTS ................................................................................................................................... 5
STUDY PURPOSE.............................................................................................................................................................................. 7
ORGANIZATION OF REPORT ...................................................................................................................................................... 7
2. RESEARCH ON PARKING DEMAND ........................................................................................................... 8
TRANSIT ORIENTED DEVELOPMENT PARKING DEMAND RESEARCH ....................................................................... 8
SOUTHERN CALIFORNIA PARKING DEMAND RESEARCH ........................................................................................... 12
DOWNTOWN POMONA PARKING DEMAND RESEARCH ........................................................................................... 14
4. RECOMMENDED PROJECT PARKING RATIO .......................................................................................... 16
EVALUATION OF OVERALL PROJECT PARKING RATIO ................................................................................................. 16
EVALUATION OF HOUR-BY-HOUR PARKING DEMAND FOR LIVE/WORK UNITS .............................................. 17
5. PARKING GEOMETRICS AND DESIGN ..................................................................................................... 21
5. SUMMARY ................................................................................................................................................... 22
APPENDICES
APPENDIX A: PARKING COUNTS
APPENDIX B: SHARED PARKING SUMMARY TABLES
LIST OF FIGURES
FIGURE 1 – PROJECT LOCATION .................................................................................................................................................... 2
FIGURE 2 – PROJECT SITE PLAN ..................................................................................................................................................... 3
FIGURE 3 – COMPARISON OF TOD PARKING DEMAND RESEARCH ............................................................................ 16
FIGURE 4 – HOUR-BY-HOUR ACCUMULATION—RETAIL SCENARIO........................................................................... 19
FIGURE 5 – HOUR-BY-HOUR ACCUMULATION—RESTAURANT SCENARIO ............................................................. 19
LIST OF TABLES
TABLE 1 PROPOSED UNIT MIX ........................................................................................................................................................ 1
TABLE 2 PROPOSED PARKING SUPPLY........................................................................................................................................ 4
TABLE 3 EXISTING TRANSIT SERVICE ........................................................................................................................................... 5
TABLE 4 CITY CODE REQUIRED PARKING SUPPLY .................................................................................................................. 6
TABLE 5 UC TRANSPORTATION CENTER TOD PARKING DEMAND STUDY RESULTS ........................................... 10
TABLE 6 SJSU/VTA TOD PARKING DEMAND STUDY RESULTS ....................................................................................... 12
TABLE 7 SOUTHERN CALIFORNIA URBAN INFILL PARKING DEMAND STUDY RESULTS ..................................... 14
TABLE 8 PROPOSED PARKING PROVISION BY UNIT TYPE ............................................................................................... 17
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
1
1. INTRODUCTION
PROJECT DESCRIPTION
Project Location & Proposed Unit Mix
The Monterey Station Transit Oriented Development (TOD) project is a proposed residential development
to be located in Downtown Pomona, California. The project site is located immediately north of the
Metrolink railroad tracks, and is bounded by Monterey Avenue to the north, Gibbs Street to the east, and
Garey Avenue to the west. The project site is located immediately to the east of the Downtown Pomona
Amtrak/Metrolink train station and bus transit center across Garey Avenue, and is two blocks north of the
core area of Pomona’s Downtown, where Western University of Health Sciences is located. Figure 1
illustrates the location of the project in relation to the Downtown Pomona Transit Center, as well as three
municipally owned Vehicle Parking District (VPD) lots. Figure 2 presents the site plan for the project.
The project, as proposed, would be developed as a market-rate rental community which would include a
mix of studios, one-bedroom, two-bedroom, loft, and live/work rental units constructed in two separate
buildings as detailed in Table 1. In total, 222 units (64%) would be studio or one-bedroom apartments.
TABLE 1
PROPOSED UNIT MIX
Unit Type No. of Units
Building 1 172
Studio 34
1 bed/1 bath 75
2 bed/1 bath 13
2 bed/2 bath 22
Lofts 10
Live/Work 18
Building 2 177
Studio 24
1 bed/1 bath 89
2 bed/1 bath 15
2 bed/2 bath 20
Lofts 9
Live/Work 20
Total 349
Source: Monterey Station, LLC, 2012
BIKE STORAGE
BUILDING #1BUILDING #2
G-101
PARKING PROVIDED
Total 455
SITE STATISTICS
PARCEL #3
C C
C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C
C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C
TECHNICALSITE PLAN
Monterey Ave.
Gare
y A
venue
Locust S
treet
Commercial Street
Gibbs S
treet
CCCCCC
CCCCCCCCCCCCC
BIKE STORAGE
Open - On Site Spaces
Standard (9'-6" x 18') 198
Compact (8'-0" x 16') 98
Handicapped (9' x 18') 8
Handicapped Van (9' x 18') 2
Covered - On Site Spaces
Standard (9'-6" x 18') 106
Compact (8'-0" x 16') 36
On Street Spaces (Gibbs St.)
Standard (10'-0" x 25') 7
Total Open 306
Total Covered 142
Bicycle Stalls
24Covered Stalls
Uncovered Stalls
Total
22
46
BIK
E S
TO
RA
GE
0' 10' 20' 40' 80'
DATE: JANUARY 26TH 2012
BIKE STORAGE
CC
C C
C C
CC
SQUARE FOOTAGE MATRIX
Building 1
Studio B
Studio A
Live Work A
Live Work B
Unit 1B
Unit 1A
Unit 1C
Unit 2A
Unit 2D
Unit 2C
Unit 2B
Loft A
Corner Unit
380 s.f.
641 s.f.
966 s.f.
648 s.f.
618 s.f.
641 s.f.
880 s.f.
967 s.f.
946 s.f.
921 s.f.
512 s.f.
1079 s.f.
407 s.f.
unit s.f. 1st flr 2nd flr 3rd flr 4th flr
3
16
2
5
4
-
-
2
1
-
-
2
5
40 units
3
-
-
17
4
1
2
4
2
-
-
2
7
42 units
13
-
-
17
4
1
2
4
-
2
-
2
-
45 units
3
-
-
-
22
-
2
4
-
2
10
2
-
45 units
Total s.f.
8360 s.f.
10256 s.f.
1932 s.f.
24687 s.f.
20706 s.f.
1266 s.f.
5280 s.f.
13496 s.f.
2802 s.f.
3616 s.f.
5120 s.f.
8712 s.f.
4884 s.f.
Building 2
Live Work A
Live Work B
Unit 1B
Unit 1A
Unit 1C
Unit 2A
Unit 2D
Unit 2C
Unit 2B
Loft
Corner Unit
641 s.f.
966 s.f.
648 s.f.
618 s.f.
641 s.f.
880 s.f.
967 s.f.
946 s.f.
921 s.f.
512 s.f.
1079 s.f.
unit s.f. 1st flr 2nd flr 3rd flr 4th flr
18
2
7
4
-
-
2
1
-
-
2
41 units
-
-
20
4
2
2
4
2
-
-
2
42 units
-
-
20
4
2
2
4
-
2
-
2
47 units
-
-
2
24
-
2
4
-
2
9
2
47 units
Total s.f.
11538 s.f.
1932 s.f.
31752 s.f.
22248 s.f.
2564 s.f.
5280 s.f.
13538 s.f.
2838 s.f.
3684 s.f.
4608 s.f.
8632 s.f.
Studios
1 bed/1 bath
2 bed/1 bath
2 bed/2 bath
Lofts
Live Work
total units
22
12
34
39
2
6
4
3
14
8
10
16
2
172 total units
111,117 total unit s.f.
177 total units
123,322 total unit s.f.
Studios
1 bed/1 bath
2 bed/1 bath
2 bed/2 bath
Lofts
Live Work
Studio B
Studio A 380 s.f.
407 s.f.
-
5
-
6
10
1
2
-
4560 s.f.
4884 s.f.
total units
18
2
49
36
4
6
14
3
4
9
8
12
12
Site Totals:
Building 2
Building 1
177 123,322
unitssquare footage
172 111,117
234,439349
C C C C C C C C C C C C C C C C C C C C C
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
4
Proposed Parking Supply
The project, as currently proposed, would provide a total of 455 vehicular surface parking spaces
(including 448 off-street spaces, and 7 new on-street spaces), as detailed in Table 2. Most of the stalls
would be provided in the southern half of the parcel, but parking would also be provided fronting the
new site access aligned with Locust Street. A limited number of parallel parking stalls would also be
provided along the project’s eastern frontage where a new access point aligned with Gibbs Street would
be constructed. Based on this parking supply, a total of 1.30 spaces per dwelling unit will be provided.
TABLE 2
PROPOSED PARKING SUPPLY
Parking Stall Type No. of Stalls
Open – On Site Spaces 306
Standard (9’-6” x 18’) 198
Compact (8’-0” x 16’) 98
Handicapped (14’ x 18’ inclusive of
striped ADA pathway) 8
Handicapped Van (9’ x 18’) 2
Covered – On Site Spaces 142
Standard (9’-6” x 18’) 106
Compact (8’-0” x 16’) 36
On-Street Spaces (Gibbs St) 7
Total 455
Source: Monterey Station, LLC, 2012
In addition, 46 bicycle parking stalls would be provided (24 covered, 22 uncovered).
TRANSIT ACCESS
The project site is located directly to the east of the Amtrak/Metrolink Downtown Pomona transit station,
across Garey Avenue. This station is served by the Riverside Line of the Metrolink commuter rail, which
runs from Downtown Riverside to Downtown Los Angeles. A total of six trains running westbound (five
a.m. departures, one p.m. departure) and six trains running eastbound (six p.m. departures) serve the
station.
Amtrak provides limited service to the Downtown Pomona transit station. There are three departures
weekly on the Texas Eagle route, with service through Texas to Chicago, and three departures weekly on
the Sunset Limited route through the southwest to New Orleans. Both routes begin at Los Angeles Union
Station.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
5
The station is also served by bus transit from two agencies: Foothill Transit, serving the San Gabriel Valley,
and Omnitrans, serving San Bernardino County. Table 3 details the transit lines that serve the station. In
addition to Metrolink, a total of ten bus transit lines serve the station, with peak hour headways from 10
to 60 minutes. Foothill Transit’s Silver Streak line provides the most frequent service, operating 24-hours
a day between Downtown Los Angeles and Montclair.
TABLE 3
EXISTING TRANSIT SERVICE
Provider Route Service Area Service
Type
Hours of
Operation
Approximate
Peak Hour
Headway
Metrolink Riverside Line Downtown Riverside –
Downtown Los Angeles
COMMUTER
RAIL 5:15 A.M. - 7:20 P.M.
6 trains daily EB
& WB
Foothill Transit 195 Pomona TransCenter –
Devry Institute via Reservoir LOCAL 5:35 A.M. - 7:25 P.M. 1 hr
Foothill Transit 197 Pomona - Claremont - Montclair
via Fairplex & Arrow Hwy LOCAL 5:35 A.M. - 9:00 P.M. 30 min
Foothill Transit 286 Pomona - Diamond Bar - Brea
Mall LOCAL 7:30 AM. - 8:20 P.M. 60 min
Foothill Transit 291 La Verne - South Pomona
via Garey Ave LOCAL 4:30 AM. - 10:30 P.M. 15 min
Foothill Transit 292 Pomona TransCenter –
Claremont TransCenter LOCAL 5:45 A.M. - 4:30 P.M. 30 min
Foothill Transit 480 Montclair - Pomona –
West Covina via Mission Blvd LOCAL 5:00 A.M. - 1:10 A.M. 30 min
Foothill Transit 482 Pomona - Rowland Heights -
Puente Hills Mall LOCAL 4:00 A.M. - 12:50 A.M. 30 min
Foothill Transit 855 Pomona TransCenter –
Claremont LOCAL 6:30 A.M. - 3:50 P.M. 10-30 min
Foothill Transit Silver Streak Los Angeles –
Montclair EXPRESS 24-hours 10 min
Omnitrans 61 Fontana - Ontario –
Pomona LOCAL 4:20 A.M. - 11:10 P.M. 15 min
Source: Metrolink, Foothill Transit, Omnitrans, 2012
CITY CODE PARKING REQUIREMENTS
The City of Pomona’s Zoning Code stipulates the minimum number off street parking spaces required to
serve land uses in the City. As indicated in Table 4, for multi-family residential land uses, the Code
requires a minimum of one space per bachelor (studio) unit, 1.5 spaces per one-bedroom unit, and two
spaces per two-bedroom unit. Additionally, one guest parking space must be provided for every four
dwelling units.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
6
The Zoning Code does not stipulate the required parking ratio for loft units and live/work units. Based on
the proposed size of the loft and live/work units, a determination was made whether the units were most
appropriate to analyze as one-bedroom units or two-bedroom units. The proposed loft units would be
approximately 512 square feet (SF), and so have been analyzed as one-bedroom units (which range in size
from approximately 618 to 648 SF). One live/work unit type, as proposed, would be 641 SF, and the other
live/work unit type would be 966 SF. The smaller live/work unit has been analyzed as a one-bedroom
unit, and the larger live/work unit has been analyzed as a two-bedroom unit for the purposes of this
analysis.
Based on this approach, 58 bachelor (studio) units, 217 one-bedroom units, and 74 two-bedroom units
have been analyzed to determine required parking per the Zoning Code.
TABLE 4
CITY CODE REQUIRED PARKING SUPPLY
Unit Type City Code
Parking Ratio
Proposed
Units
Code Required
Parking Supply
Bachelor (Studio) 1 per unit 58 58
One-Bedroom 1.5 per unit 217 326
Two Bedroom 2 per unit 74 148
Subtotal 349 532
Guest 0.25 per unit N/A 88
Total 349 620
Source: Fehr & Peers , 2012 Per City of Pomona Zoning Code Sec 503-H
Per the Zoning Code, 532 spaces would be required for resident parking, and an additional 88 guest
spaces would be required, for a total of 620 spaces, a ratio of approximately 1.78 spaces per unit. As
proposed, the project is providing 448 spaces in off-street surface parking lots, and an additional 7 new
on-street spaces. Counting the off-street spaces only, the ratio would be approximately 1.28 spaces per
dwelling unit, approximately 28% less than is required by City Code. Including the 7 new off street spaces,
would mean a ratio of 1.30 spaces per unit, just under 27% under City Code. However, the Zoning Code
applies to the City of Pomona in its entirety, which is a mixture of suburban and urban development
patterns; thus the Zoning Code’s requirements may not be well suited for the project, given its location
across the street from a multi-modal transit center, and being in walking distance to Downtown Pomona,
and its employment, retail, and entertainment destinations, and Western University of Health Sciences.
Research detailed in subsequent chapters shows that TODs and projects located in walkable downtowns,
typically have peak parking demand ratios well below the minimum off-street spaces required by most
suburban zoning codes.
TODs and projects in downtowns often attract young single people and older couples whose children
have left home. For example in Downtown Pomona, Western University of Health Sciences is located a
few blocks from the project site, so it is anticipated that a portion of the future residents of the project
would be Western University students who would walk to their classes. In these types of projects, given
their market demographics, the need for larger units with higher parking requirements is reduced. This
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
7
leads to increased demand for one-bedroom units (occupied by one person) and more use of two-
bedroom units by a single person who uses the second bedroom as a study, home office, weekend
bedroom for a child in custody, or a guest bedroom for an occasional visitor. All of the above factors
influence the size of units (with more small units being built), the density of habitation (with more single
people occupying a one- or two-bedroom unit) and therefore, the amount of parking needed to serve the
new demographic.
STUDY PURPOSE
Given the unique qualities of this TOD project, the purpose of this report is to determine an appropriate
parking ratio for the project as an alternative to the strict application of the Zoning Code, which is more
applicable to projects with more suburban development patterns. Empirical data from research on
parking demand at TODs and in downtown areas are used to verify the appropriateness of the proposed
parking supply to meet expected demand. This report also evaluates the City’s parking design standards,
and evaluates whether the parking layout for the project, as currently proposed, is adequate..
ORGANIZATION OF REPORT
This report is divided into five chapters, including this introduction. Chapter 2 details recent research on
residential parking demand at TODs, as well as details the results of parking demand studies conducted in
Southern California, including in Downtown Pomona. Chapter 3 evaluates the proposed parking ratio for
the project based on the research documented in Chapter 2. Chapter 4 evaluates the parking layout for
the project, and Chapter 5 summarizes the report.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
8
2. RESEARCH ON PARKING DEMAND
This chapter summarizes research on parking demand at residential TOD’s primarily in California, as well
as research on residential projects located in downtown settings throughout Southern California,
including a study conducted for this report at a development in Downtown Pomona.
TRANSIT ORIENTED DEVELOPMENT PARKING DEMAND RESEARCH
Research on parking demand at TODs and urban infill residential developments is a growing body of
research, as consensus builds in the planning community that suburban oriented off-street parking codes
are not particularly applicable to residential projects located in walkable downtowns, and/or adjacent to
transit stations. This chapter details the findings of two recent studies that evaluated multiple residential
TODs.
University of California Transportation Center Study (2009)
Background
This study was led by UC Berkeley professor Robert Cervero. It evaluated parking demand at 31 different
TOD sites, located in the East Bay Area of Northern California (Fremont, Pleasant Hill, San Leandro, Union
City, and Walnut Creek) or the Metro Portland area of Oregon (Portland, Gresham, Hillsboro, and
Beaverton). These regions were chosen to correspond to an earlier study of reduced vehicle trip
generation rates at TOD sites in the same areas. All housing projects included in the study were within
two-thirds of a mile of a transit station, and were all for-rent apartment projects. The unit breakdown
(studios, versus one or two bedroom units, etc.) or the number of occupied units was not provided. The
number of off-street parking spaces was provided for the analyzed sites was provided by transit station
rather than broken down by individual development, so are not included in Table 5. For the Northern
California Sites, an average of 1.61 spaces per dwelling unit were provided, and for the Portland area sites,
an average of 1.45 spaces per dwelling unit were provided.
The Northern California TOD sites analyzed are located within a half mile of Bay Area Rapid Transit (BART)
stations, so have more frequent rail transit service than Downtown Pomona, though the Monterey Station
project site is located closer to the transit center than many of the analyzed sites. Bus service levels at the
analysis sites are similar or less than the levels of service provided at Downtown Pomona. The Portland
area TOD sites are located adjacent to MAX light rail stations so have more frequent rail service than
Downtown Pomona, but have more limited bus service compared with Downtown Pomona.
The study collected residential parking demand data during nighttime periods when residential parking is
at its peak during non-summer months when schools were in session.
Results
Peak parking demand was calculated for each project site by dividing the maximum number of vehicles
parked by the total dwelling units in the development. As shown in Table 5, the peak parking demand
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
9
ratio ranged from 0.53 spaces per dwelling unit to 1.69 spaces per dwelling unit for the data set, but 24
out of 31 TOD developments had a peak parking demand ratio of less than 1.3 spaces per dwelling unit.
The study discussed in particular the Freemont sites, which were the only sites with parking demand ratios
greater than 1.40 per dwelling unit. The study noted that the area around the Freemont sites with high
parking demand ratios is very auto-oriented, with limited pedestrian connectivity, wide and high-volume
arterials, and limited mixture of uses. Pedestrian access to the BART station is also limited, with over a
mile walk due to limited pedestrian connectivity (though the developments themselves are located within
a ½ mile). In contrast, the Monterey Station project, is located across the street from the transit center,
and adjacent to a walkable, mixed use downtown with much better pedestrian connectivity than the
Freemont sites with high parking demand ratios. The Beaverton sites, which are the only other sites with
parking demand ratios greater than 1.3, have a similar urban form to Fremont, and have no retail uses
within walking distance, which are reasons the study suggests that the parking demand ratios are higher
compared with other Portland area sites, and stand in contrast to the urban form and retail proximity of
the Monterey Station project site.
The study calculated a weighted average across all TOD project sites, as well as by geographic area. The
total weighted average peak parking demand ratio was 1.15 parking spaces per dwelling unit, with an
average of 1.20 spaces per dwelling unit for the California developments, and 1.07 parking spaces per
dwelling unit for the Oregon developments.
Best-fitting multiple regression equations were used to investigate which variables had the most influence
on project parking demand. The two most significant factors identified were walking distance between the
site and the station and the size of the parking supply. When the distance between a site and a station
increased, the parking demand increased. When the number of parking spaces per dwelling unit
increased, the parking demand increased. This finding is relevant to the Monterey Station project, as it is
located across the street from the transit center (as opposed to several of the sites analyzed in the study),
and seeks to provide parking at a ratio appropriate for a TOD (rather than providing too much parking
supply that would induce demand). While the study sites have more frequent rail transit service than
Downtown Pomona, which would suggest a slightly higher parking demand ratio for the Monterey Station
project site, but the level of bus service is the same or less than Downtown Pomona, suggesting a similar
parking ratio.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
10
TABLE 5
UC TRANSPORTATION CENTER TOD PARKING DEMAND STUDY RESULTS
ID Site Location Dwelling Units Peak Parking
Demand
Ratio (occupied
space/DU)
Weighted
Average Ratio
C1 Fremont 60 89 1.48
1.20
C2 Fremont 442 747 1.69
C3 Fremont 336 495 1.47
C4 Freemont 323 468 1.45
C5 Pleasant Hill 147 181 1.23
C6 Fremont 211 267 1.27
C7 Fremont 453 611 1.35
C8 San Leandro 145 155 1.07
C9 Union City 208 235 1.13
C10 Fremont 432 532 1.23
C11 Union City 282 314 1.11
C12 Walnut Creek 360 393 1.09
C13 Pleasant Hill 854 901 1.06
C14 Pleasant Hill 510 471 0.92
C15 Pleasant Hill 136 101 0.74
C16 Pleasant Hill 252 201 0.80
C17 Portland 36 42 1.17
1.07
C18 Portland 51 45 0.88
C19 Portland 51 33 0.65
C20 Portland 62 49 0.79
C21 Beaverton 207 283 1.37
C22 Gresham 90 90 1.00
C23 Beaverton 264 326 1.23
C24 Beaverton 711 940 1.32
C25 Beaverton 216 241 1.12
C26 Portland 57 30 0.53
C27 Beaverton 252 263 1.04
C28 Beaverton 144 130 0.90
C29 Portland 144 118 0.82
C30 Beaverton 396 356 0.90
C31 Hillsboro 264 200 0.76
Source: Are TODs Over-Parked?, University of California Transportation Center, 2008
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
11
San José State University/Santa Clara Valley Transportation Authority Study (2010)
Background
This study was led by Eduardo Serafin, PE, AICP, an adjunct lecturer at San José State University (SJSU),
and Robert Swierk, AICP, a senior transportation planner at Santa Clara Valley Transportation Authority
(VTA). It evaluated parking demand at 12 different TOD sites in the San Jose area, including TODs located
near VTA light rail stations and Caltrain commuter rail stations. Some of the studied TODs were
condominium communities, while others offered rental apartments. Sites were selected that met the
following criteria:
- Within one half-mile of a transit station
- Minimum occupancy of 85%
- Older than one year
- Do not charge for parking
- Sites with parking for the exclusive use of residents
- Sites with more than 80 units or 100 parking spaces
- Sites with exclusively residential parking supplies
- Sites with parking that can be easily survey for data collection (i.e. no individual garages)
Sites are located within a ½ mile of Caltrain and/or VTA Light Rail stations, so have more frequent rail
transit service than Downtown Pomona, though the Monterey Station project site is located closer to the
transit center than many of the analyzed sites. Bus service levels at the analysis sites generally less than
the levels of service provided at Downtown Pomona. As discussed above, the greater frequency of rail
service compared with Downtown Pomona would suggest a higher parking ratio would be appropriate for
the Monterey Station project, but the level of bus service available in Downtown Pomona, compared with
the analyzed sites, would suggest a parking ratio equivalent to the analyzed sites. Many of the analyzed
sites are located farther from the transit station, which suggests that the proximity of the Project Site to
the transit station would mean a lower parking demand ratio would be expected.
As with the University of California Study, parking demand counts were conducted during nighttime
periods when residential parking is at its peak. The study did not detail the unit mix provided at each site.
Results
Peak parking demand was calculated for each project site by dividing the maximum number of vehicles
parked by the total dwelling units in the development. As shown in Table 6, the peak parking demand
ratio ranged from 0.84 spaces per dwelling unit to 1.54 spaces per dwelling unit between the surveyed
locations. Of the sites with parking demand ratios greater than 1.30, most were located in areas with less
pedestrian connectivity, larger blocks, and less mixture of uses as the Monterey Station project site. Sites
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
12
14 and 16 are located within an area of San Jose that is more comparable to Downtown Pomona.
However, Site 14 provides significantly more parking supply than any of the other surveyed sites,
consistent with research literature that suggests providing too much parking can actual stimulate parking
demand. For this reason, the Monterey Station project proposes a parking supply more appropriate for
projects located adjacent to transit stations.
The study calculated a weighted average peak parking demand ratio of 1.25 occupied spaces per dwelling
unit across all TOD sites. The researchers had access to occupancy data within the studied development
sites, and found a weighted average peak parking demand ratio of 1.31 occupied spaces per occupied
dwelling unit.
TABLE 6
SJSU/VTA TOD PARKING DEMAND STUDY RESULTS
ID Site Location Dwelling
Units
%
Occupied
Parking
Supply
Peak
Parking
Demand
Ratio
(occupied
space/DU)
Weighted
Average Ratio
(per Total Units)
S1 Mountain View 294 98% 438 365 1.27
1.25
S2 Santa Clara 306 96% 568 439 1.49
S4 Santa Clara 924 90% 1,654 1282 1.54
S5 San Jose 2760 95% 4,605 3409 1.30
S6 Sunnyvale 186 98% 317 262 1.44
S11 San Jose 93 100% 122 99 1.06
S13 San Jose 210 95% 373 271 1.36
S14 San Jose 104 96% 240 148 1.48
S16 San Jose 115 98% 186 132 1.17
S18 San Jose 176 99% 338 241 1.39
S20 San Jose 250 97% 387 287 1.19
S21 San Jose 383 100% 523 320 0.84
Source: A Parking Utilization Survey of Transit-Oriented Development Residential Properties in Santa Clara County, SJSU,
VTA, 2010
SOUTHERN CALIFORNIA PARKING DEMAND RESEARCH
In addition to reviewing the recent study literature on TOD parking demand, Fehr & Peers has evaluated
residential parking demand data at twelve for-sale or rental residential developments throughout
Southern California, which provide empirical data on the usage of parking in residential developments
comparable to the Monterey Station project. Each of the surveyed sites were located in urban areas that
are well served by transit, including light rail in Long Beach and San Diego, and high-quality bus service in
Los Angeles, Santa Monica and Marina del Rey. Additionally, like the project site, all of the survey
locations are located in close walking distance to shops, restaurants, and other services. All of the
developments were nearly 100% occupied at the time of the survey. Compared with the project site, the
Long Beach and San Diego sites that were analyzed have more frequent rail transit service in proximity to
the surveyed site, and similar levels of bus service. The Los Angeles and Santa Monica sites have more
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
13
extensive and frequent bus service, but no rail service. The Marina dey Rey site has no rail service, and
more limited bus service compared with Downtown Pomona. All of the analyzed sites provide parking
free of charge to residents, and have parking exclusively used by residents. Sites SC-3 and SC-4 below
provide additional spaces shared between residential guest parking and visitor parking for the on-site
retail.
Methodology
The selected Southern California survey sites were visited late at night, to document the peak period for
residential parking demand. The peak number of parked vehicles were counted at each site, and used to
calculate parking demand ratios per dwelling unit.
Results
Parking demand was calculated by dividing the observed maximum number of parked vehicles by the
number of dwelling units in the development. As shown in Table 7, peak parking demand ratios ranged
from 0.66 occupied spaces per dwelling unit to 1.52 occupied spaces per dwelling unit. Eight of the
twelve surveyed sites had parking demand ratios of less than 1.30. Consistent with the methodology
documented in the University of California and San José State University studies, a weighted average of
1.11 occupied spaces per dwelling unit was calculated across all of the surveyed Southern California
residential developments. Site SC-2, located in Downtown Long Beach, includes three bedroom
apartments in the unit mix, which is the reason why the parking demand ratio exceeds 1.30. Site SC-6 has
over 50% two-bedroom units, which is the reason why the parking demand ratio exceeds 1.30. Site SC-7
only provides two-bedroom units, which is the reason why the parking demand ratio exceeds 1.30. The
particular unit mix is not available for Site SC-10. However, it is a mixture of apartments and
condominiums, and condos tend to exhibit higher parking demand patterns. Additionally, it is located on
Via Marina, within Marina del Rey, so has very little accessible transit service.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
14
TABLE 7
SOUTHERN CALIFORNIA URBAN INFILL PARKING DEMAND STUDY RESULTS
ID Site Location
Total
Dwelling
Units
%
Occupied
% Studio/
One-
Bedroom
Parking
Supply
Peak
Parking
Demand
Ratio
(occupied
space/DU)
Weighted
Average
Ratio
SC-1 Los Angeles 214 100% N/A N/A 268 1.25
1.11
SC-2 Long Beach 538 100% N/A N/A 818 1.52
SC-3 Long Beach 142 97% 61% 212/397* 174 1.26
SC-4 Long Beach 142 100% 61% 212/397* 168 1.18
SC-5 Long Beach 160 100% N/A 248 148 0.93
SC-6 Long Beach 220 98% 48% 529 294 1.36
SC-7 Santa Monica 88 100% 0% 192 126 1.43
SC-8 Santa Monica 532 94% 62% 700 455 0.91
SC-9 Marina del Rey 224 94% 65% 332 256 1.22
SC-10 Marina del Rey 168 100% N/A 351 237 1.42
SC-11 San Diego 387 98% 92% 387 251 0.66
SC-12 San Diego 192 98% 86% 241 145 0.77
Notes: [a] N/A – Data not available
[b] 212 spaces are provided for resident parking. An additional 185 spaces are shared between residential guest parking
and visitor parking for the on-site retail in this mixed-use development.
Source: Fehr & Peers, 2012. Sites SC- 1 to SC-3 based on survey data collected in 2008, remaining sites based on survey data
collected in 2001
DOWNTOWN POMONA PARKING DEMAND RESEARCH
Because each downtown area has a unique set of characteristics (walkability, adjacency to transit, mixture
of land uses), an effort to locate a comparable residential property to study in Downtown Pomona was
conducted. The Helix, a residential development located at 519 East 3rd Street in Downtown Pomona was
selected for evaluation. This 100 unit rental apartment project is located approximately five blocks from
the Monterey Station project site. The Helix has 24 studios, 24 one-bedroom units, and 52 two-bedroom
units (48% of units are studios and one-bedroom units). In contrast, the Monterey Station project, as
proposed, would be 64% studios and one-bedroom units. If lofts or live/work units were counted, the
percentage of two-bedroom units in the Monterey Station project would be even lower. Typically, units
with more bedrooms are more likely to have additional residents who may have cars. Therefore, the unit
make up for the project is such that lower parking demand might be expected.
The Helix is located adjacent to Western University of Health Sciences and within close walking distance of
the restaurants and shops of Downtown Pomona, similar to the proposed Monterey Station project.
Parking for the Helix is provided in a 90-space surface parking lot on the southern half of the block. Some
Helix residents also park on-street, with a total of 28 hang tags have been distributed to residents that
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
15
enable them to park on Downtown streets overnight. The apartments of The Helix are predominantly, but
not exclusively, leased by Western University students. At the time of the study, 93 units were leased by
students, and 7 unites were leased by others. The development is nearly 100% occupied. The applicant
anticipates that the project will lease a sizable portion of the units to Western University students.
Methodology
Weekday nighttime parking demand counts were collected in February, 2012 at The Helix. Because some
Helix residents receive hangtags to park on city streets, vehicles parked on the blocks adjacent to the
Helix were also included in the parking demand counts. All vehicles on adjacent blocks were included in
the count, whether or not they had a Helix hangtag. The peak parking demand (including the surface lot,
and blocks adjacent to The Helix) was 117 parked vehicles. The count sheet for the survey at The Helix
can be found in Appendix A.
Results
The peak parking demand ratio for The Helix was calculated by dividing the observed maximum number
of parked vehicles by the number of dwelling units in the development. The peak parking demand ratio
was 1.17 occupied spaces per dwelling unit.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
16
4. RECOMMENDED PROJECT PARKING RATIO
EVALUATION OF OVERALL PROJECT PARKING RATIO
Based on the range of parking ratios detailed in research on TODs and the average empirical parking
demand found at residential developments in Southern California, a reduction to the required parking
ratios found in the Pomona City Code would be appropriate given the nature of the Monterey Station
TOD development.
Figure 3 summarizes average ratios derived from the UC and SJSU/VTA study, Fehr & Peers’ Southern
California parking demand studies, the recent study Fehr & Peers conducted in Downtown Pomona at The
Helix, and the parking supply ratio of 1.30 spaces per dwelling unit proposed for the Monterey Station
TOD project.
Figure 3 – Comparison of TOD Parking Demand Research
Based on the review of available research, including the new study conducted in Downtown Pomona, the
parking ratio of 1.30 spaces per dwelling unit proposed for the Monterey Station TOD project is an
appropriate parking supply to meet parking demand, given the project’s adjacency to transit, and
proximity to Downtown Pomona. As shown in Table 8, this total parking supply ratio of 1.30 spaces per
dwelling unit can be met by providing one space per studio and one-bedroom unit, and two spaces per
two-bedroom unit. The remaining spaces could be for guest parking (just shy of 0.10 spaces per unit).
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
17
However, it is anticipated that parking for the project would not be reserved, and would be open to
residents and guests on a first come first served basis.
TABLE 8
PROPOSED PARKING PROVISION BY UNIT TYPE
Unit Type Proposed
Parking Ratio
Proposed
Units
Proposed
Parking Supply [a]
Bachelor (Studio) 1 per unit 58 58
One-Bedroom 1 per unit 217 217
Two Bedroom 2 per unit 74 148
Subtotal 349 423
Guest 0.09 per unit N/A 32
Total 349 455
Note: [a] Proposed parking supply includes 7 new on-street parking spaces
Source: Fehr & Peers , 2012
EVALUATION OF HOUR-BY-HOUR PARKING DEMAND FOR LIVE/WORK UNITS
While most of the units are for-rent apartments, 38 of the units are proposed to be live/work units. The
use of live/work units can vary depending upon its resident. Often, live/work units will be rented by
freelance professionals, such as graphic designers, artists, accountants, etc., who may live in the unit, but
also conduct business, typically with few or no employees, and only occasional client visitors, so will
exhibit parking demand patterns not unlike residential units where a resident does not work outside the
home. However, live/work units could be rented by residents who would operate other businesses that
might require more employees, or could attract customers to the project site with greater frequency than
residents with the types of businesses described above.
Assumptions have been developed for the expected business uses of the live/work units for the purpose
of analyzing the project’s potential for traffic impacts, and for potential inclusion in conditions of approval
set forth by the City of Pomona. These assumptions include:
• A maximum of 50% of live/work units could be used for business activities, which would be
approximately 12,829 SF of non-business uses (50% of the planned square footage of live/work
units)
• 1/3 of the non-residential floor area could be used for food/drink/retail type uses (4,234 SF)
• 2/3 of non-residential floor area would be dedicated to professional/artisan type uses (8,595)
• A maximum of two employees would be permitted for each live/work unit
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
18
These assumptions have been used to assess the level of parking demand associated with the live/work
units. Because the live/work units would generate parking demand not already accounted for in the
residential parking demand (which should be fully accommodated with the proposed parking supply of
1.30 spaces per dwelling unit), a supplemental analysis has been conducted using the Shared Parking
Model, developed as a companion to Shared Parking, 2nd
Edition, (Urban Land Institute [ULI], 2005), a
study of parking demand in mixed-use developments. Differing land uses will often experience their peak
parking demand at different times of day. For example, an office typically experiences its peak parking
demand during the day, and a restaurant will typically experience its peak parking demand in the evening.
Shared Parking, based on empirical research, documented typical usage patterns and peak parking
demand ratios for a variety of land uses typically found in mixed use developments.
To quantify the potential parking demand from the live/work units, two shared parking analyses have
been conducted, one which analyzes the 4,234 SF of food/drink/retail as retail, and the other which
analyzes it as restaurant. For both analyses, a 20% reduction in parking demand has been assumed for a
non-auto mode adjustment, as a portion customers and employees of the businesses operated out of the
live/work units would walk from Downtown or would take transit. A 25% internal reduction has been
applied to the employee portion of parking demand for office, retail, and restaurant uses, assuming that
that portion of employees would be residents of the units. For both analyses, the residential parking
demand ratio of 1.30 spaces per dwelling unit has been assumed.
Even with the reductions detailed above, the shared parking analysis is quite conservative, as the base
parking demand ratios for retail, restaurant, and office, developed in Shared Parking, are for more typical
applications of those types of businesses (e.g. a standalone restaurant). The space available in live/work
units is sufficiently small that a sit-down restaurant (which is the biggest generator of parking demand), is
unlikely to be a business that is developed within the live/work units. However, the shared parking
analysis is used as a theoretical upper bound for parking demand.
The peak parking demand for the analysis assuming retail use was 458 spaces (10 spaces more than the
proposed 448 space off-street supply, but only 3 spaces more than the proposed total supply of 455
spaces including the 7 new on-street spaces), suggesting that parking demand for the retail/office uses of
the live/work units, could essentially be fully accommodated in the off-street parking supply, because the
peak for those uses would typically occur during daytime hours when most apartment residents would be
at work. Figure 4 details the estimated hour-by-hour parking accumulation for this scenario.
The peak parking demand for the analysis assuming restaurant use was 513 spaces (65 spaces more than
the proposed 448 space off-street parking supply, but 58 spaces more than the proposed total supply of
455 spaces including the 7 new on-street spaces). Based on this analysis, it would be expected that there
would be some customer parking demand that would need to be satisfied on streets adjacent to the
project site. However, as described above, the restaurant analysis is very conservative. As detailed in
Figure 5, the estimated hour-by-hour parking accumulation for this scenario would only exceed supply in
the evening hours, assuming the food uses within the live/work units had a sit-down dinner. If the uses
are more limited (e.g. coffeeshop, lunch café), the demand would be unlikely to exceed supply. Detailed
shared parking tables are provided in Appendix B.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
19
Figure 4 – Hour-by-Hour Accumulation—Retail Scenario
Figure 5 – Hour-by-Hour Accumulation—Restaurant Scenario
448 Off-Street Spaces
448 Off-Street Spaces
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
20
Evaluation of Available Off-Site Parking Supply
To determine the availability of area parking to accommodate any potential spillover from the business
portions of the live/work units, the Downtown Pomona Parking Plan (Fehr & Peers, 2008), prepared for the
City of Pomona Vehicle Parking District, and Redevelopment Agency was reviewed. Blocks within close
walking distance to the east, west, and south, (the area bounded by Monterey Avenue to the north, 3rd
Street to the south, Main Street to the west, and Palomares Street to the east) have approximately 500 on-
street parking spaces available, including the block where the project would be located. There is
additional on-street parking supply north of the project site, but those blocks were not surveyed in the
Downtown Pomona Parking Plan, so the on-street parking supply located in convenient walking distance
to the project site would be well over 500 spaces. At the time of the study, the daytime peak parking
occupancy was around 52% on these blocks. The study determined that daytime midday was the overall
peak for parking demand in Downtown Pomona, when local businesses and Western University are at
their peak for activity levels.
Additionally, the Vehicle Parking District operates several parking lots in a short walking distance to the
project site. Lots 4-1 and 4-2 are just north of the site, and Lot 2-1 is just south of the site. Those lots
have approximately 384 spaces. At the time of the study, combined parking occupancy for those lots was
only 23%.
Given the level of available parking supply adjacent to the project, the estimated range of spillover
parking from the live/work units should be easily accommodated.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
21
5. PARKING GEOMETRICS AND DESIGN
The Pomona Code stipulates parking stall and aisle dimensions for off-street parking facilities. As Table 7
indicates, the Code requires parking spaces to be 10 feet by 20 feet in garages and carports, 9.5 feet by 18
feet in open parking lots, and 10 feet by 25 feet for parking stalls parallel to drive aisles. Compact stalls
(allowed by the Code for up to 25% of the parking spaces in excess of 10 spaces provided), are to be 8
feet by 16 feet. The Code requires that drive aisles range from 16 feet to 25 feet, depending on the angle
of the parking stalls and whether the aisle is one-way or two-way.
The project complies with the City Code required dimensions as detailed above for its uncovered standard
and compact parking stalls, and the Project would provide 25 foot drive aisles, meeting Code
requirements.
The project, as currently designed, would provide covered stalls of the same size (9.5 feet by 18 feet for
standard, and 8 feet by 16 feet for compact stalls) as the Code required dimensions for open lots, but
would not meet the Code requirements for garage/covered parking spaces. However, the proposed
overhang for the covered spaces would be cantilevered over parked vehicles, and would only be
supported by a post at the front of the stall. Thus, there would be no potential obstructions on the sides
of parking spaces that would make maneuvering into and out of them difficult. Therefore, the City Code
dimensions for stalls in open parking lots should be adequate for both the covered and uncovered stalls
as proposed for the project.
The project would provide approximately 30% of total stalls as compact stalls, exceeding the maximum of
25% as stipulated in the Code. There is no strict rule of thumb for a reasonable number of compact
parking stalls in parking lots. Area jurisdictions, such as the City of Los Angeles allow a greater
percentage of compact stalls in parking lots (City of Los Angeles allows up to 40% of a parking lot to be
striped with compact stalls). Thus, while the project would not meet the Code requirement, it would still
provide an acceptable number of standard stalls.
Based on this review of the project site plan, the parking layout appears to be adequate, meeting many,
but not all City Code requirements.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
22
5. SUMMARY
The purpose of this report was to determine the appropriate parking ratio for the Monterey Station
residential development in Pomona. As discussed in Chapter 2, empirical evidence suggests that parking
demand at TOD sites, and in other urban residential developments in Southern California, would be less
than the 1.30 space per dwelling unit parking supply as proposed for the project, meaning that the project
would provide adequate parking to accommodate demand from its residential units. Chapter 3 provided
a shared parking analysis of parking demand for the business components of live/work units. Parking
demand would vary based on the type of uses in each unit. However, demand from retail and office uses
could be accommodated with the proposed parking supply. In the unlikely event that some live/work
units would have restaurant uses that would operate in the evenings, the proposed parking supply would
be insufficient to accommodate all of the demand. On-street parking would be needed to accommodate
the demand of some customers and employees. Chapter 4 analyzed the parking stall and aisle
geometrics required in the Code, and found the proposed parking layout for the project adequate,
although it would not fully meet Code requirements.
Residential Parking Demand Study
Monterey Station Transit Oriented Development, Pomona, CA
March 2012
23
REFERENCES
A Parking Utilization Survey of Transit-Oriented Development Residential Properties in Santa
Clara County, SJSU/VTA, November 2010
Are TODs Over-Parked?, UCTC, 2009
Shared Parking, Second Edition, Urban Land Institute, 2005.
Zoning Code, City of Pomona, February 2012.
APPENDIX A
PARKING COUNTS
Location: Parking Study Day: Thursday
City: Pomona Date: 2/9/2012
With Helix Tag Without Helix Tag ���� With Helix Tag No Tag Combined
Spaces 4 94 9:00 PM 104 6 110
9:00 PM 81 1 0 82 10:00 PM 112 4 116
10:00 PM 85 1 0 86 11:00 PM 112 5 117
11:00 PM 85 1 0 86
Palomares St (West Side)
With Helix Tag Without Helix Tag ���� 24 Minute Parking Regular
Spaces 2 2 14 Spaces 2
9:00 PM 6 2 0 0 8 9:00 PM 0
10:00 PM 9 1 0 0 10 10:00 PM 0
11:00 PM 8 2 0 0 10 11:00 PM 0
With Helix Tag Without Helix Tag With Helix Tag Without Helix Tag
Spaces 14 Spaces 9
9:00 PM 1 0 1 9:00 PM 4 1 5
10:00 PM 1 0 1 10:00 PM 5 1 6
11:00 PM 0 0 0 11:00 PM 5 1 6
With Helix Tag Without Helix Tag
Spaces 18
9:00 PM 12 2 14
10:00 PM 12 1 13
11:00 PM 14 1 15
18
90
TOTALS
3rd St (South Side)TOTALS
9
TIMELinden St (West Side)
TOTALS
TIME TOTALS TIME
14
3rd St (North Side)
10
TOTALS TIME
TIMEMain Lot
TIMEPalomares St (East Side)
APPENDIX B
SHARED PARKING SUMMARY TABLES
Table A1 3/30/2012
Monterey Station TOD Shared Parking Analysis
Retail Assumption
SHARED PARKING DEMAND SUMMARY
PEAK MONTH: DECEMBER -- PEAK PERIOD: 10 PM, WEEKEND
Weekday Weekend Weekday Weekend
Non- Non- Peak Hr Peak Mo Estimated Peak Hr Peak Mo Estimated
Base Mode Captive Project Base Mode Captive Project Adj Adj Parking Adj Adj Parking
Land Use Quantity Unit Rate Adj Ratio Rate Unit Rate Adj Ratio Rate Unit 10 PM December Demand 10 PM December Demand
Community Shopping Center (<400 ksf) 4,234 sf GLA 2.90 0.80 1.00 2.32 /ksf GLA 3.20 0.80 1.00 2.56 /ksf GLA 0.30 1.00 3 0.35 1.00 4
Employee 0.70 0.80 0.75 0.42 /ksf GLA 0.80 0.80 0.75 0.48 /ksf GLA 0.40 1.00 1 0.45 1.00 1
Residential, Rental, Shared Spaces 349 units 1.21 1.00 1.00 1.21 /unit 1.21 1.00 1.00 1.21 /unit 1.00 1.00 422 1.00 1.00 422
Reserved sp/unit 0 1.00 1.00 0 /unit 0 1.00 1.00 0 /unit 1.00 1.00 0 1.00 1.00 0
Guest 349 units 0.09 1.00 1.00 0.09 /unit 0.09 1.00 1.00 0.09 /unit 1.00 1.00 31 1.00 1.00 31
Office <25 ksf 8,595 sf GLA 0.30 0.80 1.00 0.24 /ksf GLA 0.03 0.80 1.00 0.02 /unit 0.00 1.00 0 0.00 1.00 0
Employee 3.50 0.80 0.50 1.40 /ksf GLA 0.35 0.80 0.50 0.14 /unit 0.01 1.00 0 0.00 1.00 0
ULI base data have been modified from default values. Employee 1 Employee 1
Customer 3 Customer 4
Resident 422 Resident 422
Guest 31 Guest 31
Total 457 Total 458
Project Data
Table A1 3/30/2012
Monterey Station TOD Shared Parking Analysis
Restaurant Assumption
SHARED PARKING DEMAND SUMMARY
PEAK MONTH: DECEMBER -- PEAK PERIOD: 10 PM, WEEKEND
Weekday Weekend Weekday Weekend
Non- Non- Peak Hr Peak Mo Estimated Peak Hr Peak Mo Estimated
Base Mode Captive Project Base Mode Captive Project Adj Adj Parking Adj Adj Parking
Land Use Quantity Unit Rate Adj Ratio Rate Unit Rate Adj Ratio Rate Unit 10 PM December Demand 10 PM December Demand
Fine/Casual Dining Restaurant 4,234 sf GLA 15.25 0.80 1.00 12.20 /ksf GLA 17.00 0.80 1.00 13.60 /ksf GLA 0.95 1.00 49 0.90 1.00 52
Employee 2.75 0.80 0.75 1.65 /ksf GLA 3.00 0.80 0.75 1.80 /ksf GLA 1.00 1.00 7 1.00 1.00 8
Residential, Rental, Shared Spaces 349 units 1.21 1.00 1.00 1.21 /unit 1.21 1.00 1.00 1.21 /unit 1.00 1.00 422 1.00 1.00 422
Reserved sp/unit 0 1.00 1.00 0 /unit 0 1.00 1.00 0 /unit 1.00 1.00 0 1.00 1.00 0
Guest 349 units 0.09 1.00 1.00 0.09 /unit 0.09 1.00 1.00 0.09 /unit 1.00 1.00 31 1.00 1.00 31
Office <25 ksf 8,595 sf GLA 0.30 0.80 1.00 0.24 /ksf GLA 0.03 0.80 1.00 0.02 /unit 0.00 1.00 0 0.00 1.00 0
Employee 3.50 0.80 0.50 1.40 /ksf GLA 0.35 0.80 0.50 0.14 /unit 0.01 1.00 0 0.00 1.00 0
ULI base data have been modified from default values. Employee 7 Employee 8
Customer 49 Customer 52
Resident 422 Resident 422
Guest 31 Guest 31
Total 509 Total 513
Project Data