Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Reserves on Schedule to Go (STG) Based on Historical Data
Bob Bitten, Bob Kellogg, Marc Hayhurst, Shirin Eftekharzadeh The Aerospace Corporation
Voleak Roeum NASA Headquarters
2014 NASA Cost Symposium 12-14 August 2014
2
Outline
• Introduction/Background
Methodology
Results from PDR, CDR, SIR, and PSR
Recommendations & Summary
•
•
•
3
Introduction
• NASA Center guidance requires that a mission hold Funded ScheduleReserve (FSR) corresponding to the remaining Schedule to Go (STG) atan increasing rate over the development lifecycle
The rates of required FSR may not be adequate given that many projects have experienced significant schedule growth
This study looks at the project-held FSR and actual schedule growth for a variety of NASA missions at the Preliminary Design Review (PDR), Critical Design Review (CDR), Systems Integration Review (SIR), and Pre-Ship Review (PSR)
The data can then be used as guidance for adjusting project FSR requirements and for establishing additional reserves at the center or HQ level for future missions
•
•
•
NASA Project Lifecycle
• BackgroundProject
Phase
Phase A:
Conceptual
Design
Phase B:
Preliminary
Design
Phase C:
Final Design
&
Fabrication
Phase D:
System
Assembly,
Integration &
Test, Launch &
Checkout
Phase E:
Operations
Milestones
Reviews
KDP-B KDP-C KDP-D KDP-E
Launch
PDR CDR SIR PSR LRD
• Definitions:– KDP = Key Decision Point = Transition from one Phase to the next
– PDR = Preliminary Design Review
– CDR = Critical Design Review
– SIR = Systems Integration Review
– PSR = Pre-Ship Review
– LRD = Launch Readiness Date
4
5
Reserve Tracking Assumptions
• JPL and GSFC Guidelines specify funded schedule reserves in months forPhases C & D
Milestone
PDR (KDP-C)
to
SIR (KDP-D)
to
Ship
to
SIR (KDP-D) Ship Launch
JPL & GSFC Reserve Guidelines Schedule Margin Rate 1 month/year 2 month/year 1 week/month
• Most projects track Funded Schedule Reserve (FSR) in weeks or days– 1 Month = 4 weeks
– 1 Week = 5 working days
Phase Months/Year Weeks/Year Days/Year
KDP-C to KDP-D 1 4 20
KDP-D to Ship 2 8 40
Ship to Launch 3 12 60
• Weeks used in this analysis for consistency across all projects
6
Example Project Lifecycle
Total
• Funded Schedule Reserve (FSR) = No planned activities, but funded schedule• FSR Rate = FSR/(Planned Activity + FSR) = FSR / (P + FSR)
KDP-B KDP-C KDP-D KDP-E
Launch
PDR CDR SIR PSR LRD
Ship
Critical Path
P FSR P P
Planned
Activity
Funded
Schedule
Reserve
Schedule
FSR FSR
Phase ATP to PDR to SIR SIR to PSR PSR to Launch Total
PDR
Example Duration 0.75 2.0 1.0 0.25 4.0 (years)
Guideline FSR Rate 0 4 weeks/year 8 weeks/year 12 weeks/year
Guideline FSR 0 8 8 3 19 (weeks)
7
Outline
• Introduction/Background
• Methodology
• Results from PDR, CDR, SIR, and PSR
• Recommendations & Summary
Large Diversity of Missions Included in Analysis • Data collected from 37 science missions providing a representative mix
ct
R
MissionLaunch
Date ThemeMission
Type Lead Org.
AIM Apr-07 Helio CAT 3 OtherCloudsat Apr-06 Earth CAT 2 JPLDAWN Sep-07 Planetary CAT 2 JPLDeep Impa Jan-05 Planetary CAT 2 JPLEO-1 Nov-00 Earth CAT 2 GSFCGALEX Apr-03 Astro CAT 3 JPLGENESIS Aug-01 Planetary CAT 2 JPLGLAST Jun-08 Astro CAT 2 GSFCGRAIL Sep-11 Planetary CAT 2 JPLIBEX Oct-08 Helio CAT 3 OtherICESAT Jan-03 Earth CAT 2 GSFCKepler Mar-09 Astro CAT 2 JPLLRO Jun-09 Planetary CAT 2 GSFCMER Jul-03 Planetary CAT 1 JPLMESSENGE Aug-04 Planetary CAT 2 APLMRO Aug-05 Planetary CAT 1 JPLNew Horiz Jan-06 Planetary CAT 1 APLOCO Feb-09 Earth CAT 2 JPLPHOENIX Aug-07 Planetary CAT 2 JPL
MissionLaunch
Date ThemeMission
Type Lead Org.
RHESSI Feb-02 Helio CAT 3 OtherSDO Feb-10 Helio CAT 1 GSFCSpitzer Aug-03 Astro CAT 1 JPLStardust Feb-99 Planetary CAT 2 JPLSTEREO Oct-06 Helio CAT 2 GSFCSwift Apr-04 Astro CAT 2 GSFCTerra Dec-99 Earth CAT 1 GSFCWISE Jun-09 Astro CAT 2 JPLGLORY Mar-11 Earth CAT 2 GSFCGPM Feb-14 Earth CAT 2 GSFCIRIS Jun-13 Helio CAT 3 LMJuno Aug-11 Planetary CAT 1 JPLLADEE Sep-13 Planetary CAT 2 ARCLDCM Feb-13 Earth CAT 2 GSFCMAVEN Nov-13 Planetary CAT 3 GSFCMSL Nov-11 Planetary CAT 1 JPLRBSP Aug-12 Helio CAT 2 APLNuSTAR Jun-12 Astro CAT 3 JPL
• Inclu– 15
des mix of Science ThemesPlanetary, 7 Astrophysics, 8 Earth Science and 7 Heliophysics
• Includes mix of different sized missions based on NASA 7120.5E Mission Category– 8 Category 1 (CAT 1) missions with Life Cycle Cost (LCC) > $1B FY12$
– 22 Category 2 (CAT 2) missions with LCC >$250M but < $1B FY12$
– 7 Category 3 (CAT 3) missions with LCC < $250M FY12$
Study Definitions – Project Actual Margin (FSR) = Actual historical margin held by project at milestone
– Actual Required Margin = Project Actual Margin + Schedule Growth = FSR + G
– Actual Schedule Margin Rate =
• Actual Required Margin/(Planned Activity + Project Actual Margin) = (FSR + G) / (P + FSR)
Planned Duration
Actual Duration
P
G
FSR
– External Events: factors resulting increased schedule growth which were outside of the control of
NASA and/or the project and unreasonable to anticipate and plan for
• NASA External: Contractor closes and relocates facility; labor strike; Hurricane delays launch• Project External (Including above): center/headquarters directed launch date move; funding cut;
stand down
– Actual Required Margin less External Events =
• Actual Required Margin – External Event Duration = (FSR + G) - E– Actual Required Margin Rate less External =
• Actual Required Margin less External Events/(Planned Activity + Project Actual Margin)• ((FSR + G) – E) / (P + FSR)
9
Planned Duration
Actual Duration
P
E
FSR
G
10
Outline
• Introduction/Background
• Methodology
• Results from PDR, CDR, SIR, and PSR
• Recommendations & Summary
11
Average All Causes Average NASA External Removed
Average Project External Removed Current FSR Guidelines
Results of Historical Mission Examination FSR Rates - All Missions
13.5
20.5
33.9
42.7
10.6
14.9
28.4
19.2
10.5
14.7
24.3
13.0
4.0 4.0
8.0
12.0
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
50.0
PDR to SIR CDR to SIR SIR to PSR PSR to Launch
Wee
ks p
er y
ear
bet
we
en M
ilest
on
e
Schedule Phase
Weeks per year calculations
-Numbers: average weeks per year used between each milestone
-Orange line: unadjusted calculation from the raw schedule data
-Purple line: adjusted calculation removing NASA external events
- Blue line: adjusted calculation removing Project external events
-Black line: current FSR guidelines
12
Average All Causes Average NASA External Removed Average Project External Removed
Current FSR Guidelines Avg. Launched On Schedule
Results of Historical Mission Examination FSR Rates - All Missions
13.5
20.5
33.9
42.7
10.6
14.9
28.4
19.2
10.5
14.7
24.3
13.0
4.0 4.0
8.0
12.0
7.1
12.7 8.812.5
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
50.0
PDR to SIR CDR to SIR SIR to PSR PSR to Launch
Wee
ks p
er y
ear
bet
we
en M
ilest
on
e
Schedule Phase
On Schedule Missions
-Green line: average of the 8 missions launched on schedule
-The FSR they budgeted was approximately the actual required FSR
Results of Historical Mission Examination
13.510.6
20.5
14.9
14.7
1
4.0
7.
0.5
4.0
1
12.7
8.0
8.8
PDR to SIR CDR to SIR
Schedu
SIR to PSR PSR to Launch
le Phase
Average Project External RemovedAverage All Causes
Current FSR Guidelines
Average NASA External Removed
Avg. Launched On Schedule
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
50.0
Wee
ks p
er y
ear
bet
wee
n M
ilest
on
e 4
192
12.012.5
FSR Rates - All Missions
1 w3.0e
13
PDR and CDR to SIR
-Minimal usage of FSR prior to CDR
-Increase in required FSR at CDR is partly an artifact of non-usage from PDR to CDR
-PDR to SIR: 2 years; 8 wks FSR = 4 wks/yr -CDR to SIR: 1 year; 8 wks FSR = 8 wks/yr
-Most missions had modest schedule growth between PDR and SIR
-Missions that had growth post CDR were mostly attributable to instruments
13.5
33.9
42.7
28.4
19.2
24.3
13.0
8.0
12.08.8
12.5
SIR to PSR PSR to Launch
le Phase
10.6
14.9
10.5
14.7
4.0 4.0
7.1
12.7
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
50.0
Wee
ks p
er y
ear
bet
wee
n M
ilest
on
e
PDR to SIR CDR to SIR
Schedu
2d0u.5l
SIR to PSR
-Even with external events removed the I&T phase is the most prominent with largest variance from guidelines
- Expected as the most intense development effort takes place in this phase
-Values near the guidelines were sufficient for missions launched on schedule
-Nearly all missions launched on schedule also had constrained launch windows
Average Project External RemovedAverage All Causes
Current FSR Guidelines
Average NASA External Removed
Avg. Launched On Schedule
Results of Historical Mission Examination FSR Rates - All Missions
14
15
4.000.
SIR to PSR PSR to LaunchPDR to SIR CDR to SIR
Schedule Phase
Average Project External RemovedAverage All Causes
Current FSR Guidelines
Average NASA External Removed
Avg. Launched On Schedule
13.5
20.5
10.6
14.9
10.5
14.7
4.0
7.1
12.7
0
.0
.0
.0
.0
5.
10
15
20
25
30.0
35.0
40.0
45.0
50.0
Wee
ks p
er y
ear
bet
wee
n M
ilest
on
e
19.2
24.3
13.0
8.0
12.08.8
12.5
33.9
42.7
28.4
PSR to Launch
-External events such as launch vehicle
technical delays & range conflicts drive the
needs for FSR from ship to launch
- When these events are removed the
guidelines appear adequate for a nominal
launch processing phase
Results of Historical Mission Examination FSR Rates - All Missions
16
Further Analysis
• Examination of the average can be useful to asses overall trends– However, there is much variation present in the schedule data
– Some missions were affected by “extraordinary” events which could not be planned for
– Data points to the far right can unfairly influence the average
Another approach is to examine a cumulative distribution of the data to identify the most probable outcomes – Distributions were examined for potential FSR guidance consistent with NASA policy
• The 50% confidence level on the curve with Project External events removed issuggested for Project held reserves
• The 70% confidence level on the curve with NASA External events removed issuggested for HQ/Center held reserves
The following slides show the cumulative distributions at the guideline specified milestones (PDR, SIR, PSR) with the 50% and 70% levels highlighted
•
•
Required Schedule Reserve at PDR Guideline: 4 weeks/year
17
4
4
7.213.5
7.1
10.6
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 5 10 15 20 25 30 35 40 45 50
Cu
mu
lati
ve P
rob
abili
ty
Weeks Per Year
Required FSR @ PDR
Current FSR Guideline
All Causes
NASA External Removed
Project External Removed
Launched On Schedule
50% w/o Project External
7
70% w/o NASA
External
15
Required Schedule Reserve at SIR Guideline: 8 weeks/year
18
8
8
24.3
33.9
8.8
28.4
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 5 10 15 20 25 30 35 40 45 50
Cu
mu
lati
ve P
rob
abili
ty
Weeks Per Year
Required FSR @ SIR
Current FSR Guideline
All Causes
NASA External Removed
Project External Removed
Launched On Schedule
50% w/o Project External
13
70% w/o NASA
External
18
Required Schedule Reserve at PSR Guideline: 12 weeks/year
19
12
12
11.8
42.7
13.4
19.2
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 5 10 15 20 25 30 35 40 45 50
Cu
mu
lati
ve P
rob
abili
ty
Weeks Per Year
Required FSR @ PSR
Current FSR Guideline
All Causes
NASA External Removed
Project External Removed
Launched On Schedule12
70% w/o NASA
External
17
50% w/o Project External
20
Outline
• Introduction/Background
• Methodology
• Results from PDR, CDR, SIR, and PSR
• Recommendations & Summary
21
Recommendations
Examination of the cumulative distributions of historical data yielded the following recommended values of FSR given the example project schedule
ATP to PDR PDR to SIR SIR to PSR PSR to Total Total
Launch (Years) (months)
Example Duration (years) 0.75 2.0 1.0 0.25 4.0 48
Phase
Current Guidelines FSR Rate (wks/year) 0 4 8 12 Total Total
(Weeks) (months)
Total FSR (weeks) 0 8 8 3 19 4
Recommended Project FSR at 50% confidence level FSR Rate (wks/year) 0 7 13 12 Total Total
(Weeks) (months)
Total FSR (weeks) 0 14 13 3 30 7
Recommended Center/HQ FSR at 70% confidence level FSR Rate (wks/year) 0 15 18 17 Total Total
(Weeks) (months)
Total FSR (weeks) 0 30 18 4.25 52.25 12
FSR above Proj. (wks) 0 16 5 1.25 22.25 5
•
22
Summary
• This study aimed to assess if the adequacy of the current guidelines forcarrying funded schedule reserve based on schedule-to-go
Historical data from 37 missions were assessed to determine required FSR over the project lifecycles – Average weeks per year assessed for overall trends
– Cumulative distributions examined to establish recommendations for specific
confidence levels
Recommended FSR rates are listed below
•
•Phase PDR to SIR SIR to PSR PSR to Launch
Current Guidelines 4 8 12
Recommended Project FSR
at 50% confidence (weeks per year) 7 13 12
Recommended Additional Center/Headquarters FSR
at 70% confidence (weeks per year) 8 5 5
Recommended Total Project + Center/Headquarters FSR
at 70% confidence (weeks per year) 15 18 17