S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
1 8 DOCUMENT
CONTROL SHEET
4. Last Date & Time for Bid submission. 01st -June-
2020 up to 16:30 hours
Please provide extension of submission of date of the RFP to
12th June 2020. Please suggest if we can send do online
submission of the proposals rather than physical submission,
which is bit challenging in the current lockdown situations?
It is hereby informed that extension of
submission date is not possible.
2 8 DOCUMENT
CONTROL SHEET
8. Bid fee The bid fee being non refundable should be revised to
RS10000/- which is based on standard practice. Please revise
this from mentioned RS 30,000 considering the current
scenario.
It is hereby informed that the Bid fee cannot be
revised.
3 8 DOCUMENT
CONTROL SHEET
9. EMD EMD of INR 30,00,000 is very high.Please revise this to INR
10,00,000 so that all bidders can afford under the current
situation.
It is hereby informed that the EMD amount
cannot be revised.
4 8 DOCUMENT
CONTROL SHEET
Performance Bank Guarantee The PBG requirements are not clear as it is mentioned in may
forms. Normal standards of PBG is limited to 10% of the bid
value and nothing more. Can you revise the norms mentioned in
the RFP to single PBG of 10% of the PO/Contract value? Also
clarify the retention amount and the clause mentioned in liue of
the PBG. This requires omission.
It is hereby informed that the PBG amount
cannot be revised.
5 11 5.1. General vi. Support maintenance activities like day end,
month end, quarter ends, and year ends, uploads,
downloads, trouble shooting, problem resolution,
servicing and maintenance etc.
“day end, month end, quarter ends, and year ends, uploads,
downloads, trouble shooting,” will be part of L1 onsite helpdesk
job profile. Hope one onsite engineer can suffice this
requirement post production and the cost for this service be
included in the support cost? Please clarify.
It can be onsite or offsite dedicated support, the
cost to be inbuilt in TCO, no separate cost will
be reimbursed for this.
6 11 5.1. General vii. If the supplied software version is declared ‘End
of Support’ by the OEM/Bidder, new version with
all the existing customizations should be
implemented by the Bidder with no extra cost to the
Bank.
End of support will be the end of contract period of 7 years for
the version implemented. Any form of support extension post
this period will be at revised cost. Please clarify?
Post end of contract period of 7 years, the Bank
will have the right to continue with the exisitng
version with AMC and without any upgrade as
it will be a perpetual license.
7 11 5.1. General ix. Bidder has to supply, install and configure all
the required software etc. for the successful
implementation of the proposed solution at both DC
& DR sites at CBD Belapur and Chennai
respectively, of the Bank and renewal thereafter on
mutual agreement from time to time.
Does this mean all required software like, application server
(web sphere / jboss / web logic) / oracle software or any third-
party software to be supply /installation / configuration done by
CMS supplier /bidder. Are environment software part of the
scope? Hope the scope to this project is limited to
implementation of CMS application software?
Normally Hardware, Database and OS will be
provided by bank. Any other third party
software/ utility required for running the
software solution, with all required licenses
should be provided by the Bidder.
If bidder is unable to provide any other
software/utility required for running the solution
, bidder should provide the cost break-up of
each software and can recommend the vendor
of their choice
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
Page 1 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
8 11 5.1. General x. Creating and managing environments for
Integration testing and UAT (User Acceptance
Testing).
We provide one-time training for application deployment and
all creation and managing of each environment is bank's
responsibility. Please clarify for Creating & Managing
requirement.
The clause refers to creation of UAT
environment for user testing, not training.
9 11 5.1. General
xii. The Bidder shall be responsible for Supply,
Installation, Integration, Rollout, Operational
configuration, failover testing and Maintenance of
Software Solution for CMSes in the Bank.
Please provide more detail for this requirement. It is self explanatory
10 11 5.1. General xi. Provide specific tools and utilities required for
implementation of Software Solution for CMS in
production, development and test environment
without any extra cost to Bank.
Kindly elaborate on the expectation on the tools. Please provide
more detail for tools and utilities required.
If your solution requires any specific tools or
utilities for implementation, then the
responsibility of providing such tools and
utilities lies with you.
11 11 5.1. General xix. The proposed solution shall also be compatible
with Finacle version 10x and above.
Kindly share the exact version of finacle implemented in the
bank and the year of implementation
The Finacle 10x version implemented in 2020
12 12 5.1. General xviii. Bidder will configure the server and software
to enable integration with the Bank’s existing
application / interface / middleware / third party
software and any other interface/application in
future, e.g. Bank’s existing applications such as
Finacle, SFMS for NEFT/RTGS, IMPS, UPI,
Virtual Accounts, FRMS, Rapid Pay, B- DEM etc.
What does bank understand by server configuration? Kindly
elaborate.
Ideally the configuration and maintenance to the server and
third party server like web server, database server or database,
middle ware etc. are being configured by the bank's IT team.
The CMS vendor will be responsible for implementing and
configuring only cash management solution at the bank.
Bidder has to integrate with the Bank’s existing
application / interface / middleware / third party
software and any other interface/application in
future
13 12 5.1. General xxi. The Bidder should be responsible for resolving
any compatibility issues with existing hardware &
software infrastructure during deployment and
maintenance of the Solution.
Ideally the configuration and maintenance to the hardware
servers and third party server like web server, database server or
database, middle ware etc. are being configured by the bank's
IT team. The vendor will be responsible for implementing and
configuring only cash management solution at the bank. Please
clarify?
Bidder shuould be responsible for resolving any
compatibility issues with existing hardware &
software infrastructure during deployment and
maintenance of the Solution.
14 12 5.1. General The Bidder shall be responsible for data migration
from existing system of the Bank to the new system
in a seamless way and also the reconciliation of data
tables including General Ledgers while migration
from existing CMS system of the Bank to the new
CMS system.
Please provide clarification for the below mentioned
information
1) Kindly share the data size of the migration data and also
please confirm the scope of migration that whether customer
data is to be migrated or the customer plus transaction data
2)Please provide details for which all module data to be
migrated? What is the existing data size per module? 3)What is
the existing archival data size ?
Data size of the migration data would be shared
with the successful Bidder post finalization of
migration approach with the business team.
Page 2 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
15 12 5.1. General xxvi. The Bidder shall be responsible for migration
of all existing reports, standard as well as
customized of existing clients.
Please share the number of reports and what is the data size? Details will be shared with the successful bidder
16 13 5.1. General xxxi. The Bidder shall be responsible for all
patches/updates required in the offered solution for
smooth installation of solution without any extra
cost to the Bank. All patch update and patch
management of Solution modules has to be
deployed by the selected Bidder after obtaining
approval from the Bank.
Hope this is limited to the CMS solution only and during the
execution of the project? What is the approval mechanism ?
Please elaborate.
Yes, only related to CMS Solution. Approval
here means without referring to the Bank, the
patch update should be a suo moto implemented
by the provider.
17 13 5.1. General xxxii. Bidder has to install / re-install, configure / re-
configure the supplied software (including, third
party software) in the servers (physical / virtual)
and support the same during warranty and AMC
period without any extra cost to the Bank.
Please clarify which all third-party software requirement as the
scope of this project is limited to CMS software implementation
and support by the bidder.
Normally Hardware, Database and OS will be
provided by bank. Any other third party
software/ utility required for running the
software solution, with all required licenses
should be provided by the Bidder.
If bidder is unable to provide any other
software/utility required for running the solution
, bidder should provide the cost break-up of
each software and can recommend the vendor
of their choice
18 13 5.1. General xxxiii. Bidder must maintain and support the
interfaces, software and other infrastructure at Data
Centre & Disaster Recovery Centre and DR (if any)
as proposed and provided as a part of this project.
Please clarify or provide more details for “maintain”
requirement. Please clarify as the scope is not clear
Ideally the configuration and maintenance to the hardware
servers and third party server like web server, database server or
database, middle ware etc. are being configured by the bank's
IT team. The vendor will be responsible for implementing and
configuring only cash management solution at the bank
Normally Hardware, Database and OS will be
provided by bank. Any other third party
software/ utility required for running the
software solution, with all required licenses
should be provided by the Bidder and their
maintainance to be handled by the bidder
19 13 5.1. General xxxv. Bidder must provide required support during
periodic VAPT (External & Internal), IS Audit,
Security Audit, various compliances specially
government and regulatory, cyber related, etc., to
the Bank. Also rectification of deficiencies pointed
out during IS Audit should be done at no additional
cost to the Bank.
Kindly share the list of external/internal security guidelines
which the vendor is required to be compliant with.
The list of external/internal security guidelines
can be shared upon selection as successful
bidder.
Page 3 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
20 13 5.1. General xxxix. Bidder is required to set up DR without any
extra cost to the Bank. Presently Bank is having tie-
up with IBM for Sanobi Software for conduction
DR Drill automatically, the application software
shall be compatible for handling DR drill
automatically with above software or any other
software.
DR set up is genrally done by the bank team as we being the
CMS vendor will deploy the application in UAT and post
testing bank will move this into production and DR with our
support. Please clarify the scope and understanding here.
Bidder has to deploy the application software in
UAT environment and DC & DR Live
environment.
21 13 5.1. General xl. Escrow arrangement for applications needs to be
maintained. An escrow agreement is a tripartite
arrangement between the Bank, Software vendor
and the escrow agent. By this arrangement, the
source code of application is kept with escrow
agent, which can be made available to the Bank in
the event the vendor goes out of business. The
Successful Bidder is required to execute documents
/agreements in this regard as prescribed by Bank
from time to time.
Please clarify who will choose the Escrow aganet and who will
bear the cost of escrow placement and annual updates?
Escrow agent will be selected by the Bank, the
cost of which shall be borne by the Bidder.
22 13 5.1. General xlii. Bidder shall be responsible for addressing
VAPT & APPSEC issues during the contract
period. All the necessary patches related to OS,
Database and application etc for addressing the
VAPT & APPSEC issues should be installed by the
Bidder. Details are mentioned under section:
Maintenance and Support
This will not fall into our scope being a CMS vendor as
environment software is out of scope to this project for the
bidder. Please clarify?
VAPT and APPSEC of CMS Software will fall
under scope of CMS Vendor
23 13 5.1. General xlix. Further, the Bidder should ensure of updating
software / application or updating patches whenever
it is released at no extra cost during
warranty/Support/maintenance contract period.
Hope this is limited to the CMS solution only? Please clarify. Yes, the understanding is correct.
24 13 5.1. General
l. The Vendor/Bidder shall ensure that the
stipulated Support and maintenance facilities on
the hardware/ software will be available for a
minimum period of 7 years. The vendor will
constantly update Purchaser/IDBI Bank Ltd. on
new technologies that could prove cost effective.
Please clarify the scope of support here as the bidder is not
supposed to deliver and maintain Hardware and environment
software other than the CMS platform?
The bidder is expected to update IDBI Bank Ltd
on new technologies that could prove cost
effective during the contract period.
Page 4 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
25 14 5.1. General xlviii. Bidder should carry out preventive and
corrective maintenance activities to ensure that all
Hardware / Software/System perform without
defect or interruption for ensuring availability of
systems.
Please clarify the scope of support here as the bidder is not
supposed to deliver and maintain Hardware and environment
software other than the CMS platform?
Yes, the understanding is correct.
26 15 5.3. Data Migration Data Migration : The Bidder will be responsible for
uploading the data entered by the Bank through the
manual data entry screens, programs/ applications.
Manual data collection is not in scope but in case of
data gaps, the vendor may be required to create data
capture tools
Is the bank expecting that manual data entry will be done by
vendor ? Please provide more detail. The data migration scope
and approach recommended is not clear.
In case the bidder is not able to migrate the data
with data capture tools, it is expected that the
migration will be completed with data entry
facilitated by the bidder to complete the
migration.
27 17 5.6. Technical
Inspection and
Performance
Evaluation
iv. The Bid is being issued to the Bidders whose
role as tender respondent is reiterated below:
a. The Bidder is expected to propose solutions
which are integrated. b. Hardware proposed should
be sized properly and sizing should be certified by
the application OEM. Hardware for the application
including OS and Database (SQL and Oracle) only
will be provided by Bank. Any other software need
shall also be provided by Bidder. All related OEM’s
support for database need to be provided by the
Bidder.
Please reclarify the deliverables from the bidder who is a CMS
vendor. Hope only Cash management solution is in scope and
bank will provide Hardware & environment software for the
installation? We as a bidder only need to provide the right
sizing and configuration of the hardware + environment
software ( DB+ MW and any storage etc)
Yes, the understanding is correct.
28 17 5.6. Technical
Inspection and
Performance
Evaluation
v. The solution proposed by the Bidder should be
able to migrate to the newer version of Operating
Systems/Data Base Systems/Browsers without any
extra cost to the Bank.
We understand that the newer version upgrade will be to the
same operating system/data base/middleware. Please confirm.
Yes, the understanding is correct.
29 18 5.7. System
Commissioning &
Deliverables
iv. Any gaps identified during product
demonstration, functional requirements
specifications study, system testing, user acceptance
testing, business process reengineering and pilot
implementation should be included by the Bidder as
implementation efforts. Bank will not pay the
Bidder any additional charges for all such
customizations. Bidder shall take up all such
amendments as required by the Bank on a priority
basis as decided by the Bank.
Scope Sign off gap document or Gap sign off document will be
considered as a final copy for the scope and any changes for
references during the project and after go live. Anything beyond
this has to go though change control board and additional
budget approvals. Kindly confirm this standard process
followed by all banks.
Any gaps identified during the project
implementation should be included by the
Bidder as implementation efforts. Bank will not
pay the Bidder any additional charges for all
such customizations.
Page 5 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
30 23 5.14. General Terms iii. The Bidder should quote AMC separately as per
Commercial Bid format; the AMC shall be quoted
as percentage of Software Cost and not in absolute
terms. In case of decline in quotation after reverse
auction, the AMC amount shall also be revised as
percentage of revised quote.
Is the bank going to conduct an reverse auction, however apart
from the mentioned clause nowhere the bank has mentioned
about the reverse auction to be conducted in the RFP. Kindly
confirm. How do we price for the onsite resource in the AMC if
it has to be only proposed in %?
No, reverse auction is not proposed, however as
per clause Viii of Commercial Bid format, Bank
reserves the right to negotiate the Total Cost of
CMS Solution , with the finally successful
Bidder before awarding the contract.
31 23 5.15. Hardware
Requirements
All the Hardware, OS and database will be
provided by Bank. The configuration should specify
OS and Database with version numbers. Any other
software/utility required for running the Solution,
with all required licenses should be provided by
Bidder.
Our understanding is bank will provide all third-party hardware
for all environments including third party certificates etc. Please
clarify all hardware and third-party software related licenses.
Normally Hardware, Database and OS will be
provided by bank. Any other third party
software/ utility required for running the
software solution, with all required licenses
should be provided by the Bidder.
If bidder is unable to provide any other
software/utility required for running the solution
, bidder should provide the cost break-up of
each software and can recommend the vendor
of their choice
32 24 6.4. Penalty amount
will be charged as
defined as below, if
Bidder fails to meet the
SLA as mentioned
below :
We would like propose our SLA's which are being followed by
our other PSU clients in India.
Refer sheet 2 for the same. The proposed SLAs by the bank is
not practcially feasible. Kinldy revist in this in the amendment.
The SLAs are common for all bidders and are
non negotiable
33 28 11. WARRANTY &
AMC
11.2. During the contract period if OEM of OS/DB
solution announces regarding the End of Support,
the successful Bidder will migrate the solution to
the newer version of OS/DB without additional cost
to the Bank. All updates and upgrades of OS & DB
have to be done by the selected Bidder without any
extra cost to the Bank during contract period.
However, licenses will be provided by the Bank.
Ideally the configuration and maintenance to the hardware
servers and third party server like web server, database server or
database, middle ware etc. are being configured by the bank's
IT team. The vendor will be responsible for implementing and
configuring only cash management solution at the bank . Please
clarify the scope as we as a bidder are not the supplier for bank's
OS & DB to provide any support for upgrades. This is highly
conflicting and needs clarification.
Yes, the understanding is correct.
Page 6 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
34 28 11. WARRANTY &
AMC
11.5. Post warranty period, Bank may enter into
AMC/ATS support with successful vendor/OEM
for next 10 years and Bank will issue Purchase
Order on every year based on satisfactory
performance of the vendor in previous year. Post
warranty, the application will be covered under the
AMC / ATS by the OEM. The Bidder should
ensure, as part of AMC / ATS that the OEM to
provide following service(s):
a. OEM has to maintain the source code and
provide bug fixes for the defects / bugs noticed in
the application without any additional cost.
b. Round the Clock support on 24x7x365 basis for
bug fixes, any other technical support.
We assume the contract period including warranty and AMC is
of 7 years and not 10 years, kindly confirm. Round the Clock
support on 24x7x365 basis for bug fixes, any other technical
support - why do bank insist 24x7 support as this is a corporate
banking application and the support window should be during
bank's business hours and days. Please clarify?
AMC period will be equal to Contract period
i.e. 7 years, unless extended on mutually
accpeted terms. Round the clock support is
required in view of recent RBI guidelines of
24*7 NEFT Transactions proceessing.
35 36 5. BID FORM: 5.1. ENVELOPE-I (Technical Bid): The Technical
Bid super-scribed as “Technical Bid for RFP for
Procurement of Software Solution for Cash
Management Services (CMS) ” should be sealed
and complete in all respects and contain all
information asked for, except prices. The
documents mentioned in Annexure -18 have to be
submitted by Bidders in the Technical Bid.
5.2. ENVELOPE-II (Commercial Bid): The
Commercial Bid super-scribed as“Commercial Bid
for RFP for Procurement of Software Solution for
Cash Management Services (CMS)” should be
sealed and submitted in the specified format
provided in the RFP / Bid Document and should not
contradict the Technical Bid in any manner. The
prices quoted in the Commercial Bid should be
without any conditions.
5.3. Both the envelopes must be put together in a
single cover / envelope super-scribed with the
following information:
• Type of bid (Technical or Commercial)
• REF No: IDBI/ITD/RFP/2020-21/006 dt. 11-
May-2020
• Last date of submission: XX XXXX, 2020 XX:
XX Hrs.
• Name of Bidder
In the current covid-19 situation and the lockdown in the state
can we submit the proposal document online with protected
password for the financial bid?
Online submission is not possible, the bid is
required to be submitted as specified in the Bid
Document.
Page 7 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
36 49 11. PAYMENT
TERMS
The Payment terms given by the bank are unfavorable and
cannot be complied .
We will propose our own payment terms as under. Kindly
revisit the terms as to maintain project discipline there should be
payments on contract sign off/post gaps sign off/post delivery of
the softwarw/post UAT sign off and go live..
License:-
01.On signing the contract 40%
02.On delivery, configuration and successful installation of at
least 2 modules i.e. Payments and collections/DIR module:40%
03.On implementation of at least 2 modules i.e. Payments and
collections/ DIR module :15%
04. On implementation of balance modules: 5%
Implementation and other costs:-
1. On delivery, configuration and successful installation of
Payments module: 20 %
2. On UAT and testing of Payments module: 10 %
3. On delivery, configuration and successful installation of
Collections module: 20 %
4. On UAT and testing of Collections Module 10 %
3. On delivery, configuration and successful installation of all
other modules: 20 %
4. On UAT and testing of all other modules 10%
5. On go live of all modules 10 %
The payment terms are common for all bidders
and non negotiable.
37 50 11. PAYMENT
TERMS
11.12. Bidder has to submit the performance
security (in the manner and form as provided in the
RFP) for 10% of total contract value upfront at the
time of signing of the contract.
Is this apart from the 15% bank guarantee mentioned? Why is
bank taking 25% as PBG in total. This is very and not
acceptable. Please amend/remove this clause to standard
practice and limit to max of 10%.
PBG is for 18 months i.e. 6 months
implementation period and 1 year claim period
thereafter. Security shall remain with the bank
till end of contract, It is not 10% of contract
value, it is 5% of the Total cost of CMS
solution as defined in part ‘A’ of the
commercial bid i.e. the PO amount
38 9 10 Security Deposit why is this required apart from BG? Please remove this as it is
not viable for vendors to provide such huge amounts as security
deposit for no reasons.
The term is non negotiable
Page 8 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
39 10 5.1 ii Scope of Work- General How many interfaces are contemplated here?
Further, we understand the maintenance of interface will be
charged which will be included in AMC.
Therefore we would request to omit the word 'maintain' from
here
Mainteance will be part of AMC, it cannot be
removed.
40 11 5.1 v Scope of Work- General Please help us to understand what is covered in version
migration?
Further, we understand that during the warranty period these
will be provided without any cost however, after warranty
period these will be cored in respective AMC agreement for
which separate AMC fees will be charged.
If bank decides to upgrage the hardware, OS,
environment software, oracle DB to higher
version, then bidder has to provide the support
at no extra cost.
41 11 5.1 vii Scope of Work- General The industry may change and we may have to upgrade the
software accordingly. Therefore, in case of end of support and
in case of implementation of new version implementation and
other fees can be agreed mutually.
During the Contract period, software upgrade
should be free of cost
42 12 5.1 xxii Scope of Work- General Bidder and the Bank would already have agreed on the
implementation aspects and commercials for the version in
implementation. Therefore, upgration to new version without
any commercial impact does not seem feasible.
During the Contract period, software upgrade
should be free of cost
43 13 5.1 xxxix Scope of Work- General The solution will be implemented at the Bank's premises.
Therefore, the Bank will have to set the DR. however, the
Bidder will be happy to assist in the same
Bidder has to deploy the application software in
UAT and DC & DR live environments
44 14 5.1 xliv Scope of Work- General Please help us to understand the duration of this on-site support Duration cannot be decided upfront.
45 16 5.4 l Interfaces this clause is wide and open. The term enhancement/
modification comprise of multiple activities and the scope of
such modifications and enhancement will vary depending upon
the requirement and criticality of such enhancement or
modification. Therefore, the time period of 5 days may not be
sufficient for some modifications. Therefore we would request
to revisit this clause at the time of finalization of contract.
This enhancement/ modifications referred to in
this clause are specific to interfaces.
46 17 6 Implementation Please help us to understand the tentative number of
corporates/customers and volumes
The tentative number of Corporate Client codes
are 10000 at present, a CAGR of 40% may be
taken for forecasting the future customer base.
Page 9 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
47 18 5.7 iii System Commissioning & Deliverables Source for the customized solution will be developed on the
proprietary product of supplier or third parties. Therefore such
source code will be the property of supplier or respective third
party. We request to finalize this clause at the time of
contracting.
The Bidder should either provide the source
code itself with necessary documentation or
arrange to keep it under escrow arrangement.
48 21 5.13 Software Licenses Upgradation of software may require carrying out of the entire
implementation and other activities. Therefore, upgradation can
be done at the mutually agreed commercials. We would request
to finalize this clause at the time of contracting.
During the Contract period, software upgrade
should be free of cost
49 24 6.2 Upgrades and Updates The bidder will be happy to provide the updates in AMC
without any additional costs however, as per industry practice
upgrades can be provided at mutually agreed commercials. We
would request to finalize this clause at the time of contracting.
This clause is referring to upgrades and
uppdates, not AMC. AMC amount to be quoted
in the commercial bid which will be part of
TCO
50 23-24 6.4 Penalty amount We would request that the penalty to be levied only in cases
where the bidder fails to resolve for the reasons solely
attributable to bidder since resolution of defect may depend on
resolution of pre dependencies by the Bank. Further we would
request to have a cap i.e. maximum cumulative penalty which
can be charged under this. We propose to have cap of 1% of
AMC amount. Please issue amendment to this regard.
This is standard clause of the Bank for any
procurement and no changes, including capping
of the same, shall be allowed. Hence, this clause
is non negotiable
51 25 6.5 a) Penalty for non- implementation of product features
by committed time:
We would request to have a reduced amount of penalty of 1%.
This clause needs amendment..
This is standard clause of the Bank for any
procurement and no changes shall be allowed.
Hence, this clause is non negotiable
52 25 6.5 b) Timeline and Penalty for delay in project
implementation:
We would request to have a reduced amount of penalty of 1%.
This clause needs amendment..
This is standard clause of the Bank for any
procurement and no changes shall be allowed.
Hence, this clause is non negotiable
53 25 6.5 b) iii) Timeline and Penalty for delay in project
implementation:
Since the penalty provisions are already mentioned and the
Bank in addition to that also has the right to seek damages in
addition to termination of contract, we are not agreeable for the
refund of the fees and interest. Therefore we request to omit this
clause.
This is standard clause of the Bank for any
procurement and no changes shall be allowed.
Hence, this clause is non negotiable
54 26 6.5 d) Penalty for delay migration / migration not to the
satisfaction of the Bank.
We would request to omit this clause since multiple penalties
have already been mentioned above which are in addition to the
remedy of damages available. Further, the term 'to the
satisfaction of the Bank' is wide and open ended term. We
would request these open ended terms in the entire contract/
RFP document.
This is standard clause of the Bank for any
procurement and no changes shall be allowed.
Hence, this clause is non negotiable
Page 10 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
55 28- 29 11 WARRANTY & AMC please help us to understand what is expected in upgrade of
OS/DB
Bidder has to provide necessary support for
upgrade of OS or Database without any extra
cost during the contract period and bidder has to
certify that upgraded OS and Databse is
compatible with the application software
56 39-40 12 Bid Security/ EMD We would request that the EMD forfeiture events to be finalized
at the contracting stage.
EMD forfeiture may be prior to the execution of
contract in the even occurrence of terms
mentioned in the RFP. Further, RFP is public
document no further change shall be allowed in
future i.e. once successful bidder finalized and
contract documents are to be executed so as to
avoid any Vigilance Angle on such negotiations.
57 40-41 13 Performance Bank Guarantee We would request to finalize this clause at the time of
contracting stage.
The bidder required to provide PBG as per the
terms of RFP and all the prospective bidder
shall know the same at the time of bidder.
Negotiation with successful bidder for the
amount of PBG shall not possible as this is a
Public RFP.
58 46 3 Conditions Precedent We would request to finalize this clause at the time of
contracting stage.
Since this is a Public RFP, no further change
shall be allowed in future.
59 47 7 Indemnity For the claims arising out of contract, remedy of damages is
already available with the Bank. Therefore, we would suggest
to limit the indemnity to the third party claims of IPR
infringement. We would suggest to finalize this clause at the
time of contracting stage.
Indemnity clause is standardized clause for the
Bank and non negotiable. Further, negotiation
of clause at the contracting stage shall not be
possible as negotiation with successful bidder
attracts Vigilance angle.
60 47-48 8 Intellectual Property Rights and Patent Rights The nature of arrangement will involve installation and
implementation of proprietary product of bidder and/or third
parties. The arrangement does not involve any bespoke software
development. Therefore, bidder cannot agree that the IPR will
vest in the Purchaser. These need to be vested in the Bidder
and/or respective third parties. We would suggest to finalize this
clause at the time of contracting stage.
The bidder required to foresee whether IPR
required with respect to services to provided are
vesting with bidder itself or with third party and
accordingly formulate the bid and all the
prospective bidder shall know the same at the
time of bidder. Negotiation with successful
bidder for the same shall not possible as this is a
Public RFP.
61 48 9 Inspection and Quality Control test/check The nature of arrangement involves provisioning of licenses and
installation of software however, it does not involve supply of
goods. The clause is related to supply of goods. Therefore, we
would suggest to remove the same.
This clause is non negotiable
Page 11 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
62 49-50 11 Payment Terms As per our standard practice we would suggest that the license
payment to be made upfront and other payment milestones and
terms to be agreed at the contracting stage.
Payment structure shall be as per the terms
mentioned in the RFP and no upfront payment.
Hence, this clause is non negotiable
63 51 14 Incidental services The sub points iv and v are wide and open ended. Further the
scope of the incidental services can be agreed mutually.
Therefore we would request to finalize this clause at the time of
contracting.
No negotiations shall be possible after selection
of bidder. The Bidder has to foresee all such
eventualities while bidding. Hence, this clause is
non negotiable
64 52 15.1 Change Orders/ Alteration/ Variations This clause is wide and open ended and may be construed that
the bidder will not be paid even for the additional work carried
out. The bidder would have framed its commercials based on
the specifications mentioned in the bid documents. Therefore, it
would be unreasonable for not making the payment for any
additional work carried out because of the discrepancy in the
Bid documents. Therefore, we would request to finalize this at
the time of contracting.
Bidder may factor such change orders while
framing its commercials and mutual agreement
once selection of bidder is final may not be
possible.
65 52 15.2 Change Orders/ Alteration/ Variations Since the bidder would have framed its commercials
considering the scope of specifications and services, any change
in the same need to be agreed mutually between the parties.
Bidder may factor such change orders while
framing its commercials and mutual agreement
once selection of bidder is final may not be
possible.
66 52 15.7 Change Orders/ Alteration/ Variations work constituting change order will impact both the parties,
therefore need to be agreed mutually. In the event of dispute we
would suggest to resolve the dispute as per the dispute
resolution mechanism.
RFP contemplates that there may change order
due to any upward revisions and/or additions of
quantities, specifications sizes given in
specifications, charts, etc. Hence, bidder has to
accept the clause and provide for as per the
change order. The Bidder shall not dispute the
change order.
67 52-53 17 Liquidated damages (LD) For the events of delay or failure the penalties are already
prescribed. In addition to that the Bank may terminate the
contract and claim damages for breach of contract. Therefore,
we suggest to omit this entire LD clause.
This clause is non negotiable
Page 12 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
68 53 18 Deficiency in the Bidder's performance This clause states that the bidder will have to carry out the
services as per the scope of work prescribed by the Bank which
can be construed that the Bank may prescribe or change scope
of work from time to time. We would be happy to provider
services as per agreed scope in the RFP. however, any change
thereto need to be agreed mutually. Therefore we would request
to omit the unilateral phrases. We would also suggest that the
extension shall not be withheld unreasonably since the delay
may happen because of the reasons not attributable to the bidder
such as non-procurement of required infra by the Bank in time.
Further, since the provision of penalty is already prescribed we
are not agreeable for forfeiture of performance security.
This clause is non negotiable
69 54 19.3 Dispute resolution Receipt of payments will be inevitable for provision of services.
Therefore the bidder will not be able to continue provision of
services in the event of non-receipt of fees beyond 60 days.
Therefore we would request to omit this clause.
This clause is non negotiable
70 56 23 Successful bidder obligation We would request to omit the unilateral phrases such as
'directions/ instructions issued by the Purchaser'
This clause is non negotiable
71 56 25.3 No Set-off, Counter claim, Cross claims we would suggest to make the clause mutual and accordingly
omit this clause since the accounts of two lines of business are
kept different as per the practice.
This clause is non negotiable
72 57 26 The Tri-Partite Agreement Please help us to understand who are such other related parties
with whom bidder will have to enter into tri-partite or multi-
partite agreement?
At any future date, any customer availing the
CMS services or their service provider or any
third party software / middleware providers etc.
Which require integration with the CMS
solution, if specifically ask for entering in such
agreements.
73 58 28.2 Statutory Requirements We would request the Bank to provide at least 15 business days
prior written notice before the audit.
The notice period cannot be fixed upfront, since
it will be as per requirements of statutory
agency requiring audit, Bank will try to
accomodate as far as possible.
74 58 29 Purchaser's right of inspection and periodic audit We would request that prior written notice of at least 15
business days have to be provided for such audit/inspection.
Further such audit/ inspection can be carried out once in a year
and the cost and expenses to be borne by the Bank.
The notice period cannot be fixed upfront, since
it will be as per requirements of statutory
agency requiring audit, Bank will try to
accomodate as far as possible.
Page 13 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
75 58-59 30 Contract Price As acknowledged by the Bank itself there might be change in
the prices in the market. Therefore, the Bidder need to have the
flexibility to change the prices in the event of changes in prices
by third party vendors, or in case of increased taxes, etc.
Further in case of additional services these can be provided at
mutually agreed commercials. Therefore the price i.e. contract
value will change in such cases. Therefore, we would request to
finalize this clause at the time of contracting stage.
This clause is non negotiable
76 60 32 Ownership and Retention of documents The ownership of proprietary documents of bidder or third
parties will remain vested with them. Therefore, we would
request to modify this clause accordingly.
This clause is non negotiable
77 60 33.3 Representations and Warranties Since the bidder has provided the warranties pursuant to the
agreement these need to be valid only till the term of the
agreement. Therefore, we would request to omit this clause.
This clause is non negotiable
78 60-61 33.5 Representations and Warranties development, deployment , updation, upgradation, etc. will be
subject to mutually agreed commercials terms. Therefore we
request to omit this clause or to modify the same to include the
statement that this will be subject to mutually agreed
commercials.
This clause is non negotiable
79 61 33.7 Representations and Warranties We would be happy to maintain the insurances which are
mandatorily required to be maintained pursuant to applicable
law. Therefore, we would request to modify this clause
accordingly. We can finalize this clause at the contracting stage.
This clause is non negotiable
80 61 33.9 Representations and Warranties we can surely provide the warranties as on the date of contract
however, few of them are beyond our control such as litigation
and other matters are beyond our control. Therefore, it is not
possible for the bidder to provide the warranty that warranties
provided will continue. Therefore, we would request to omit
this clause.
This clause is non negotiable
81 62 33.17 Representations and Warranties Bidder is not creating any interest in its property, revenue or
asset in favor of the Bank. The arrangement involves granting
of licenses i.e. installation and implementation of software
however, no intellectual property rights of software are being
assigned. Therefore, please omit this clause.
This clause is non negotiable
82 62 34.1.4 Confidentiality We would request that the confidentiality of critical confidential
has to be maintained indefinitely. The critical confidential
information may include the architecture of the product, source
code, etc. We would request to finalize this clause at the
contracting stage.
This clause is non negotiable
Page 14 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
83 66-67 38.1 (c) Termination for convenience Since the bidder will have to incur opex and capex to execute
the project, it is not agreeable for the termination for
convenience.
This clause is non negotiable
84 66-67 38 termination We would request to add the clause for the termination right of
the bidder i.e. bidder to have termination rights in cases of non-
payment, insolvency of the Bank, etc. The clause can be
finalized at the contracting stage.
Since this is a Public RFP, no further change
shall be allowed in future.
85 67 39 Consequence of termiantion The transition support contemplated under this clause can be
provided at the mutually agreed commercials. We would
request to finalize this clause at the time of contracting stage.
Since this is a Public RFP, no further change
shall be allowed in future.
86 68 41 Assignment we would request to make this clause mutual no party can
assign this contract to third party without prior written consent
of the other party. This would be imperative for the bidder since
the licenses of proprietary product will be provided.
This clause is non negotiable
87 69 48 Insurance We would be happy to maintain the insurances which are
mandatorily required to be maintained pursuant to applicable
law. Therefore, we would request to modify this clause
accordingly. We can finalize this clause at the contracting stage.
This clause is non negotiable
88 70 49.1 b) iii) Limitation of liability We cannot agree to provide uncapped liability for indemnity
except for the third party IPR infringement claims which is
already covered above. Therefore, request to omit this clause.
This clause is non negotiable
89 70 49.1 c) Limitation of liability Neither party shall be liable for other for indirect, consequential
damages. We request to modify the clause accordingly to make
this mutual. We would request to finalize this entire clause 49
at the contracting stage.
This clause is non negotiable
90 71-72 Section 3 1. Technical Bid form We would suggest to read this form in conjunction with the
above comments. Accordingly we request to omit para 4,5 and
6 and to finalize this form at the time of contracting stage.
This clause is non negotiable
91 76 Section 3 4. Unconditional acceptance of terms & conditions
of the RFP
The contract being bilateral need to be finalized mutually.
Therefore, we would request to omit this annexure. In the event
it has to be submitted, then it need to be read in conjunction
with our comments, replies.
This clause is non negotiable
92 77 Section 3 5. Self Declarations The contract being bilateral need to be finalized mutually.
Therefore, we would request to omit this annexure. In the event
it has to be submitted, then it need to be read in conjunction
with our comments, replies.
This clause is non negotiable
Page 15 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
93 80 Section 3 7. Contract form We would request to add certain additional terms at the time of
contracting such as licensing terms, Bank's responsibilities,
Bank's warranties, etc. we would also request to incorporate the
references of bidder replies in the contract and accordingly RFP
to be read in conjunction of the replies of the vendor. We would
request to finalize this form at the time of contracting.
This clause is non negotiable
94 82-84 Section 3 8. Performance Bank Guarantee We would request that the guarantee to be invoked upon
demonstration of the failure of the vendor. Therefore, we would
request to finalize the format at the contracting stage.
This clause is non negotiable
95 88-90 Section 3 10. Deed of indemnity As stated in the foregoing comments the indemnity can be
provided for the third party claims of infringement of their IPR
by the software of the bidder. Therefore we would request to
reduce the draft to that effect. We would suggest to finalize the
draft at the contracting stage.
This clause is non negotiable
96 118 3.11 Integrity Pact This clause too broad and difficult to track practically unless
the Bank provides us all of its employees, officers and their
relatives data. Therefore, we would suggest to modify this to
include only the officers who are connected in provision of
services from both parties. We would request to finalize this
Integrity Pact at the contracting stage.
This clause is non negotiable
97 118 5.1 Integrity Pact-
Earnest Money Deposit
We would request to mutually finalize the events in which
EMD can be invoked by the Bank and in case of demonstration
of occurrence of such event to the satisfaction of the bidder, the
Bank can invoke the EMD. We would also propose to shift this
clause to the agreement. We would request to finalize this entire
clause 5 at the contracting stage.
This clause is non negotiable
98 120 6.3 Integrity Pact This clause is unilateral. Breach of the provision of the Integrity
Pact need to be demonstrated by the Bank to the satisfaction of
the bidder since it will have sever adverse effect on the bidder.
We would request to finalize this clause at the contracting
stage.
This clause is non negotiable
99 120 7 Integrity Pact
Fall clause
We would request to omit this clause since the scope and other
consideration might be different from the transaction
contemplated with the Bank.
This clause is non negotiable
100 121-122 12 Integrity Pact We would request to link the validity of the pact either with non-
selection of us or with the term of the contract where the
contract is awarded to us. We would further request to omit the
unilateral phrases.
This clause is non negotiable
Page 16 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
101 Additional clauses We would request to mutually agree upon the additional
clauses at the contracting such as licensing terms, interest on
delayed payment, non-solicitation of resources, audit of licenses
granted, etc.
This clause is non negotiable
102 94 3 Templeton Report (deposit/ instruments/ date
of deposition / date of realization )
We refer to Templeton as a client and would request to
elaborate more on the format and report
Yes, its client specific report who wants reports
based on various combinations.
103 94 2 Upload of data for CHQ issuance through off-site
vendor for uploading in core (Finacle)
Please elaborate more on the requirement with an example or a
use case.
We have cheque printing vendors, who print the
cheques requested by our clients, post printing
the cheque overprinting data and MICR details
are to be uploaded in the system. We require
that facility to be at vendor end
104 94 3 Automated updation in core (Finacle) for CHQ
issuance directly from software
Does the requirement relate to positive pay? Please elaborate
more in detail.
It refers to cheque printing request initiated by
customer, the CMS system should be capable
for updating the printed cheques details in Core
without Manual Intervention105 95 1 System should facilitate communication with NPCI
for registration of E-NACH mandates through API
Does the bank require the vendor to initiate the mandate
registration request and hand it over to NPCI or even the
initiation & processing of the direct debit transaction? Please
confirm.
This clause is regarding functionality of API
based E-NACH registraion with NPCI.
106 96 1(b) Bulk Payment through RTGS/NEFT/ FT/
NACH/IMPS
/UPI/API DD/CHQ
Please elaborate more on API DD with an example? It may be read as API / DD
107 97 9 Temporary disabling option of clients to stop any
fresh booking, other activity should be allowed, like
liquidation of open entry, charge recover (if any).
Please elaborate more on the requirement with a use case?
In fresh booking, is the bank trying to explain deposit of new
instruments?
Yes, the understanding is correct.
108 97 10 Cheque Purchase – automated entries, Report
required of entries for which Cheque Purchase
Reversal
is pending
Please elaborate more on the requirement with a use case?
By cheque purchase does bank mean guaranteed credit/day 0
credit and cheque purchase reversal is the reversal of GC on
retuned cheques?
Yes, the understanding is correct.
109 97 12 Setting of booking amt limit(min/max) at product
level
In the mentioned requirement, Does bank mean limits for
Guaranteed credit?
No, It means setting of booking amount limit at
each product such as local cheques, outstation
cheques, non-IDBI location cheques lodged at
partner bank locations, non-IDBI location
cheques lodged at drawee bank locations etc.
Page 17 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
110 98 14 Document upload/ download/ deletion options
(master setup related
documents at various levels
Please give examples for the upload of master documents?
What is the list of documents which the bank is expecting the
vendor to upload in the system? Also request to specify the
levels at which this upload and download are expected?
Document can be any supporting physical copy
of document collected from customer such as
Agreeement, Board resolution, CAS,
Guaranteed credit limit enhancement /
reduction, change of signatory or any other
change request etc.
111 98 17 Linking of at least two accounts for recovery of
collection charges with auto switch option
Please elaborate on the requirement with a use case. Charge recovery is normally done from one
account, but if balance is not available in the
charge recovery account, the system should
facilitate recovery from next account, if the
balance is availble in the account.
112 98 19 Payout details i.e. beneficiary/other bank details
should be entered in system and the entry of payout
to clients should flow directly from system to
Finacle and payout through RTGS should happen
directly by system
The expectation from this requirement is transferring the
collection credit to the account in other banks through RTGS.
We have to provide this instruction to the core bank for further
generation of messages. Please confirm our understanding
Yes, the understanding is correct.
113 98 24 Corrbank Withdrawal Please elaborate on the requirement with a use case. In case of Correspendent Bank, positive
corrbank is done before schedule liquidation.
114 98 28 Schedule Liquidation :- Manual Inputting Please elaborate on the requirement with a use case. When deposit level entry is done in the system
and some cheques return, these return cheques
are maually inputted in the system before
schedule liquidation.
115 98 29 Account statement – (Consol / Location wise /
Deposit level / instrument level/deposit with
enrichment/ instrument with
enrichment)
Please elaborate if the account statement required at the client
level or the client product level?
Generation of customised account statement as
per client's requirement
116 99 45 Voucher Checking reports Please elaborate on the requirement with a use case and data
expected in this report.
Reports for checking entries done
117 99 47 Schedule pending reports Please specify the list of the pending report which should be
scheduled.eg.cheque liquidation pending report and so on
Schedules pertaining to cheque clearance which
are pedning for liquidations
118 99 51 Hand off file for income distribution to respective
branch income accounts
with GST
Please elaborate on the requirement with a use case. System should provide monthly branch/state-
wise income report
Page 18 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
119 100 52 Invoice generations Please elaborate on the requirement with a use case. It is with reference to Charges, the system
should facilitate Invoice generation with
breakup of Taxes and Charges, as some clients
have arrangements where we generate the
invoice first and debit the charges to customer
account, only on acceptance of invoice from the
customer.
120 100 53 Additional option for client pricing which can be
customized by Bank
Please elaborate on the requirement with a use case. Does the
bank wish to develop additional charging methods/category?
This is part of Charge Matrix wherein
customisation option may be provided in
addition to the options indicated in Sr.No. 45.
121 101 14 SMS Alerts/Email Alerts-for Payment advice/on
uploading/on verification
We assume that the bank is trying to explain the SMS
Alerts/Email Alerts on transaction file upload and
authorization.
Please confirm.
Yes
122 101 19 Converter for file conversion Please elaborate on the requirement with a use case in detail. This is with reference to file converor for
converting the transaciton files as per CMS
solution input requirement from the client
output format.
123 101 21 Document upload/ download/ deletion options
(master setup/other
relevant) at various levels
Please elaborate on the requirement with a use case in detail.
Also please provide the examples of documents required at
various stages?
Document can be any supporting physical copy
of document collected from customer such as
copy of agreement, Board Resolution, CAS,
Guaranteed credit limit enhancement /
reduction, change of signatory or any other
change request etc.
124 101 23 Splitting of files as per Bank’s other middleware
requirements.
Please elaborate on the logic for splitting. Will it be based on
the number of transactions/payment type/file size etc? Which
middleware is being used.
The logic for splitting can be number of
transactions and /or payment type. The
middleware being used presently is I-Connect
however it can be any other upgradation in
future compatible with Finacle.
125 101 24 Uploading of files from multiple accounts Please elaborate on this requirement. Is it referring to user
access?
A client code can have multiple accounts linked
to it, the system should facilitate uploading
transaction files from any of the accounts, based
on account number and client / corporate code
combination
126 102 38 CHQ data download for issuance during the day for
uploading in core (Finacle)
Please elaborate on the requirement with a use case? It refers to cheque printing request initiated by
customer the details of which is required to be
updated in Core
127 103 46 Additional option which can be customized by
Bank
Please elaborate on the requirement with a use case and we
assume that the Bank is referring to charges, from this
requirement.
This is with refence to Master Setup, where
bank wants blank / additional fields for client
specific requirement.
Page 19 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
128 105 9 Alert or Report to be generated/ scheduled of all the
accounts where 7 years
to be completed from date of first credit
Assuming that the credit account referred here is the Dividend
funding account. Can a format/fields required in the report be
shared?
The report parameters would be generic in
nature such as account number, account type,
client code, client name, dividend year, amount
lying in account, due date for transfer to IEPF
etc and /or any other statuory requirement
raised by SEBI > IEPF in future.
129 105 11 Unique field-wise status identification of previous
and present DIR
Kindly elaborate on this requirement. In our system we have a
history of transaction lifecycle report. Will this suffice?
A unique identified is required such as folio
number which will identify the transaction
throughout its entire lifecycle journey i.e. Seven
years post which it will be transferred to IEPF.
130 105 13 Dividend Interest Redemption(DIR) Module for
managing Dividend Business, as per SEBI
Compliance, to provide Recon, Dividend
redemption and payment
services
HDFC has been using the Aurionpro system for more than 10
years and it is SEBI compliant. Is there any specific SEBI
circular or requirement expected from the system? Please share
with us the requirement/circular.
Please refer SEBI circular
SEBI/HO/MIRSD/DOP1/CIR/P/2018/73 dated
April 20, 2018.
131 105 1 System should facilitate recording, retrieval, MIS
and dashboard view of data related to E-NACH and
Physical NACH, Direct Debit Mandates registered.
Is Processing of Direct Debits in the scope of this RFP? If Yes,
is a handoff expected to middleware / Core Banking service or
is the vendor application expected to do end to end Direct Debit
processing?
Yes, it is there in scope of RFP, handoff to be
done directly with CBS and Vendor application
both, as some of the existing clients are using
vendor application and may not migrate to CMS
system.
132 106 6 System should facilitate Proper posting of
transactions in case of change in client account or
client branch.
What is the expectation of our system? The posting would be as
per the CMS accounts mapped from Core Banking System and
setups are done by Bank in our system.
Clients are tagged to a partciluar branch. In case
tagging is changed, there should not be any
issue in transation processing
133 106 8 System should provide Manual option for
Temporary Stop and Start process of selected
Product code
Kindly elaborate on this requirement. Is this part of the EOD
process?
Not only related to EOD but at any given
time,the option to be there.
134 106 10 System should provide Web based support, App
based support on Android, IOS OS, on handheld
devices and Mobile Phones.
Kindly elaborate this requirement. Is the bank looking for a
Mobile App ? If Yes, What features / modules are required in
the mobile App ?
Yes, Mobile app is required.
135 94 4 The system should integrate client ERP in a
seamless manner through host to host/API
connectivity. It should be also capable of extracting
the data from client ERP (SAP/Oracle) in their ERP
specific format.
What are the file formats of ERP (SAP/Oracle) expected to be
supported for the specified requirement
All file formats accepted by ERP should be
supported.
136 106 12 System should have the feature of raising invoice by
User and Authentication of the Invoice using Maker-
Checker Matrix along with payment files which
shall be processed only on
authorization of Invoice.
As part of payment file upload, our system allows attaching
enrichments like Invoices. Is the requirement to view invoices
and then approve payment? Or a separate UI is required for
invoice approval along with Payment approval?
The proposed system sound sufficient, subject to
approval during demo
Page 20 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
137 99 49 GST calculations as per act such as IGST, CGST,
and SGST bifurcation
Our system is capable of maintaining the CGST (9%) & SGST
(9%) rate slabs. We shall compute the applicable GST for
Financial Services and handoff to your accounting / Tax system
for further bifurcation & reporting. Is this approach okay ?
GST calculation should be GST compliant with
bifurcation as IGST, CGST and SGST
138 18 5.7 Source code for customized application and
documentation of the solution shall be the property
of the Bank from the start of the contract period.
Bank would guarantee that it would not use the
source code for commercial purposes and
documents in case the vendor/Bidder so desires. In
case the Bidder fails to customize the software the
Bank reserves the right to modify the software to
suit business requirements without any additional
liability whatsoever. The Bidder should either
provide the source code itself with necessary
documentation or arrange to keep it under escrow
arrangement.
Source cannot be bank's property. We are Ok to place this on
Escrow. Please clarify. Source code to be handed over will
increase the purchase cost fo the bank. Is bank ready for that?
Please clarify
Refer to the clause you can either place it with
escrow agent or keep it safely with the Bank.
139 18 5.7 vii. The selected Bidder will be responsible for
migrating Bank’s existing Archival Data from
existing system into the proposed Archival Solution.
Archival Solution should be implemented as part of
GO Live of the solution and having Data retention
for at least 10 years or as per Bank’s Data/Invoice
retention policy.
What is this archival solution mentioned? Please clarify? Bidder should provide their own archival
solution along with the application software.
Bank's existing Archival Data to be migrated to
the proposed Archival Solution
140 21 5.13 c. All software envisaged is required to be on-
premises irrevocable perpetual software licensed to
IDBI Bank, right to use the software even after the
contract period. Only licensed copies of software
shall be supplied and ported. Further, all software
supplied shall be of latest version.
The right to use remians with the bank after the contract period
but there wont be any commitment ot render support from the
vendor without an upgrade.
During the contract period , bidder should
provide necessary support and upgraded version
of the application software or any third party
software without any extra cost
141 26 7.1 7.1. The Delivery and time limit for commencement
of work shall be done at the specified locations
(Belapur, Navi Mumbai & DRC Chennai) within 1
Week from the issuance of Purchase Order.
Delivery of the equipment shall be made by the
Vendor in accordance with the system approved /
ordered. The details of the documents to be
furnished by the Vendor are specified hereunder :-
Please clarify how this is applicable in the cae of CMS vendor? Within one week of issuance of Purchase Order,
bidder has to commence the work related CMS
solution implementatin at the specified
locations.
Page 21 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
142 40 13.5 13.5. The Bank will retain 5% of the Total cost of
CMS solution as defined in part ‘A’ of the
commercial bid i.e. the PO amount, as security
towards satisfactory performance, till the estimated
useful life of the solution i.e. 7 years.
why is this retention when you have asked for PBG? These are
not practical and needs to be omited.
This clause is non negotiable
143 50 11.17 11.17. Post Warranty, the vendor has to provide
uninterrupted AMC support for minimum7 yrs.
AMC amount has to be paid by the Bank in
advance every year after deducting the penalties, if
any.
Please speicify the AMC period post warranty. Is it 7 or 10
years? In another clause bank has mentioned that AMC PO will
be issued for 10 years!
AMC period will be equal to Contract period
i.e. 7 years, unless extended on mutually
accpeted terms.
144 60 31.8 31.8. The Bidder shall abide to the Information
Security Policy (ISP) and Cyber Security Policy
(CSP) of the Bank (as amended from time to time),
which will be shared by the Bank with the L1
Bidder on need to know basis. The L1 Bidder shall
ensure that the equipment/application/software
supplied under the RFP shall be complacent with
the ISP and CSP at all times.
Please elaborate current ISP and CSP followed in the bank As mentioned, it will be shared only with the L1
vendor, being confidential in nature.
Hardware sizing -Pls share details as mentioned. We would request bank to provide volume details to arrive at
Hardware and software sizing in the below format
Hardware and software sizing shall be discussed
with successful bidder.
Total Corporates (including sole prop) Data can be shared on finalisation of L1
No of active corporates for projected years The tentative number of Corporate Client codes
are 10000 at present, a CAGR of 40% may be
taken for forecasting the future customer base.
Total Corporate users for projected years as above
Total active corporate users for projected years as above
Total Bank users for projected years Refer clause Vi(b), Vii(b) and VIII(b) of
Technical scoring matrix page 95 and 96
Total Branches for projected years
No of concurrent bank users accessing through internet for first
(base) year
Refer clause Vi(b), Vii(b) and VIII(b) of
Technical scoring matrix page 95 and 96
No of concurrent corporate users accessing through internet for
first (base) year
Refer clause Vi(b), Vii(b) and VIII(b) of
Technical scoring matrix page 95 and 96
YOY growth for concurrency for bank Users in percentage
from second year
A CAGR of 40% may be taken for forecasting
the future customer base.
YOY growth for concurrency for Corporate Users in percentage
from second year
A CAGR of 40% may be taken for forecasting
the future customer base.
Total average transactions per day through internet for first year
including all modules
Refer clause Vi(b), Vii(b) and VIII(b) of
Technical scoring matrix page 95 and 96
YOY growth for transaction volume in percentage from second
year
A CAGR of 40% may be taken for forecasting
the future customer base.
- -145
Page 22 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
How many years to be considered for projection The contract period of 7 years can be taken
No of Inquiry / report to be downloaded from system for first
year
Cannot be projected at this stage
If current database to be migrated than what is data file size The details will be shared with the L1 Bidder
Any Preference on Application Server / Web Server / DB
Server
Already indicated in Bid document
Any Preference on OS platform Already indicated in Bid document
146 - - Forms on the stamp paper-like POWER-OF-
ATTORNEY, Contract form, NDA, Indemnity, and
Integrity pact
In midst of lockdown, it would be difficult for us to arrange
stamp paper or stamps so would request bank if they can allow
us submission of forms like power of attorney, contract form,
NDA, Indemnity and Integrity pact etc on our company letter
head only.
Once lockdown is over, we can reexecute the same forms on
stamp papers and submit it to the bank.
E-stamps are available in Banks easily
147 10 5.1 General
ii.
Build and maintain the interfaces with the relevant
Application systems for automatically uploading /
downloading of data at no extra cost to the Bank
Whats the relevant application system referred here and what
sort of data expected to upload/download. Giving a sample case
will help us to better understand the requirement
This clause refers to building any interfaces, if
required to access the prospoed solution and
uploading / downloading of data using SFTP /
API connectivity without any manual
intervention
148 12 5.1 General
xviii.
Bidder will configure the server and software to
enable integration with the Bank’s existing
application / interface / middleware / third party
software and any other interface/application in
future, e.g. Bank’s existing applications such as
Finacle, SFMS for NEFT/RTGS, IMPS, UPI,
Virtual Accounts, FRMS, Rapid Pay, B-DEM etc
Any interfaces / application integration requirement in future to
be treated as billable based on gap analysis on the requirement
These are minimum applications required to be
integrated and hence the cost of integration, if
any, to be inbuilt in the quotation. No seperate
billing will be entertained for such integration.
149 12 5.1 General
xix.
The proposed solution shall also be compatible with
Finacle version 10x and above
Whats the current version of Finacle being used The current version is Finacle 10
150 12 5.1 General
xxvi.
The Bidder shall be responsible for migration of all
existing reports, standard as well as customized of
existing clients
Approximate count of customised reports provided to existing
clients will help us to gauge the size for migration
The same can be shared only with L1 Bidder
due to confidentiality
151 13 5.1 General
xxxviii.
The solution should support the Web browsers viz.
Internet Explorer 8 & above, Google Chrome and
Mozilla Firefox.
IE 8 is outdated and not more supported version. Latest UX
features are not supported. This to be treated as IE 10
It may be treated as a limitation, as many clients
are still using this version.
152 14 5.1 General
xlviii.
Bidder should carry out preventive and corrective
maintenance activities to ensure that all Hardware /
Software/System perform without defect or
interruption for ensuring availability of systems.
Scope of Hardware/OS maintenances are to be kept out of
application provider. Generally these are maintained bank Infra
team.
The scope of selected bidder is limited to
Sofware Solution. However, bidder should
provide support during Hardware and OS
maintenance activities and ensure application
should be compatible with the upgraded version
- -145
Page 23 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
153 14 5.1 General
xlix.
Further, the Bidder should ensure of updating
software / application or updating patches whenever
it is released at no extra cost during
warranty/Support/maintenance contract period
Scope of Software/Application to be limited to the application
supplied by bidder and shouldn’t cover on OS or any other
licences procured by bank
The scope of selected bidder is limited to
Sofware Solution. However, bidder should
provide support for any Hardware changes and
upgradation and ensure application should be
compatible with the upgraded version
154 14 5.1 General
l.
The Vendor/Bidder shall ensure that the stipulated
Support and maintenance facilities on the hardware/
software will be available for a minimum period of
7 years. The vendor will constantly update
Purchaser/IDBI Bank Ltd. on new technologies that
could prove cost effective
Scope of Hardware/OS maintenances are to be kept out of
application provider. Generally these are maintained bank Infra
team.
Yes, the understanding is correct, the scope of
selected bidder is limited to Sofware Solution
and the necessary support to be provided by the
bidder.
155 12 5.1 General
xviii.
Bidder will configure the server and software to
enable integration with the Bank’s existing
application / interface / middleware / third party
software and any other interface/application in
future, e.g. Bank’s existing applications such as
Finacle, SFMS for NEFT/RTGS, IMPS, UPI,
Virtual Accounts, FRMS, Rapid Pay, B-DEM etc.
Is the expectation to have the proposed CMS to integrate with
banks existing Virtual Account platform
Yes, the understanding is correct.
156 14 5.2 Gap Identification
and Resolution
The Bidder will ensure that all gaps identified at the
time of system testing with respect to Functional
Requirement Specifications (FRS), will be
immediately resolved at no extra cost
It's recommended to keep a Gap Analysis session and
document, prior to the customisation/implementation stage.
This will help bank for a smoother and faster implementation
The referred section is meant for Gap Analysis
only and at the time of testing if any gaps are
identified , need to be resolved at no extra cost
157 17 5.6. Technical
Inspection and
Performance
Evaluation
i.
Bidder shall be required to do POC at the Bank
premises, if required by the Bank at no extra cost
for which hardware will be provided by the Bank
At what stage of RFP, the POC is expected, will there be a
scope defined for POC?
If required, it will be during technical
evaluation stage.
158 18 5.7. System
Commissioning &
Deliverables
v.
Customization in the present application and all
future customization irrespective of regulatory in
nature or Bank specific will be developed or built in
by Bidder at no additional cost during contract
period. Bidder should carry out Detailed
Requirement Gathering (DRG) and share Gap
Analysis document for Bank’s existing solution
Future customisations scope to be binded with a boundary.
Regulatory requirements on existing delivered
products/payments can be covered, However if a new payment
product or a mass change in the existing product beyond regular
regulatory updates to be considered as CR
This clause is non negotiable
159 22 5.14. General Terms SSO Login Bank’s Internet Banking / Mobile
Banking Channels
In order to have the SSO handling, the customer & user
information to be replicated in proposed solution, can the
proposed solution do a fetch from the Internet Banking system
to have all the necessary customer/user information's
The internet banking details can be shared and
validated through API
Page 24 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
160 24 6. SERVICE LEVEL
EXPECTATIONS
AND PENALTY
6.4
Penalty amount will be charged as defined as
below, if Bidder fails to meet the SLA as mentioned
below .Penalty Amount: The SLA measure for
calculating Penalty amount shall hours of delay.
The penalty amount will range from Rs.1000/- per
hour to Rs.5000/- per hour, depending
on the delay, as stated under:
SLA definitions & Penalty clause to be revised t. The penality
clause should be weekly on the rate of 1000 per day & 5000
per week depenign on the delay as stated in the tender
This clause is non negotiable
161 26 7. DELIVERY AND
TIME LIMIT FOR
COMMENCEMENT
OF WORK: PERIOD
AND LOCATION
The Delivery and time limit for commencement of
work shall be done at the specified locations
(Belapur, Navi Mumbai & DRC Chennai) within 1
Week from the issuance of Purchase Order.
Delivery of the equipment shall be made by the
Vendor in accordance with the system approved /
ordered. The details of the documents to be
furnished by the Vendor are specified hereunder
Delivery time line of 1 Week is not enough post PO submission.
Its recommended to re-look in to the timelines considering the
gap analysis, identification, interface point identifications, sign-
off on necessary documents and then customisations
This clause is non negotiable
162 27 9. MIGRATION The Bidder can request for details of work related
to migration required to be done and assess the
effort required accordingly
At what stage of RFP, the details will be shared for evaluation Upon selection as L1 Bidder, the bidder can ask
for details
163 27 9. MIGRATION Time is the essence of this Contract / Agreement
and entire project should be completed maximum
within 12 months from the date of issuance of
Contract. A tentative schedule for project
implementation has been provided under Section 5,
Clause 9: Schedule, which can be used as reference
/guidelines.
Not able to identify the Section-5, Clasue-9 for the schedule.
Please share same
Please read the same as section 2, clause 35 at
page number 63 and 64 of the Bid document.
164 96 13.TECHNICAL
CAPABILITIES
(ANNEXURE – 13)
Block II(b)- CMS-
Payments Module
The system should integrate client ERP in a
seamless
manner through host to host/API connectivity. It
should be also capable of extracting the data from
client ERP (SAP/Oracle) in their ERP specific
format.
Functions mentioned here to be treated as two separate
requirement. Interface Integration via API and Extraction
Module are two different item
The successful bidder is expected to provide
both the functionalities as different customers
have differrent needs.
165 97 13.TECHNICAL
CAPABILITIES
(ANNEXURE – 13)
Block V(b)-Common
Features
System should facilitate Generation of Handoff file
for Manual transactions
Need more clarity; what type of manual transactions are
referred here and what file format to be generated
The clause is related to EOD handoff from
CMS System to CBS
Page 25 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
166 99 13.TECHNICAL
CAPABILITIES
(ANNEXURE – 13)
Block I(a)-CMS
Collections Module
Master Copy Facility Need more clarity on the expected functionality Copy of entire master set up of a particluar
client to use for another client
167 109 13.TECHNICAL
CAPABILITIES
(ANNEXURE – 13)
Block V(a)-Common
Features
System should have the feature of raising invoice by
User and Authentication of the Invoice using Maker-
Checker Matrix along with payment files which
shall be
processed only on authorisation of Invoice
Is the expectation to have payable invoice maintenances, need
more clarity on the expected requirement
Yes, the understanding is correct. Along with
payment instruction file, the facility of
uploading invoice with functionality of
accepting / rejecting invoice by the authorisor
168 16.ELIGIBILITY
CRITERIA
COMPLAINCE
SHEET (ANNEXURE
– 16)
The Bidder/ OEM should have a valid ISO
9001 and ISO 27001 certificate.
ISO 9001 is for Product Manufacturing companies. For
IT/Software ISO 27001 is relevant certification
Whichever applicable, is required
169 9 Security Deposit The value of 1st Performance Bank Guarantee
(PBG) will be 15% for the Total cost of CMS
Software Solution (as defined in part ‘A’ of
Commercial Bid) and should be valid for a period
of 18 months (6 Months Warranty Period + 1 Year
claim period) from the date of issue of PBG.
The Bank shall retain a part of Total cost of CMS
Software solution as security towards satisfactory
performance, till the estimated useful life of the
solution i.e. 7 years. The details of the same are
mentioned in clause 13.4 of Chapter C.
If the successful Bidder is desirous of getting this
security deposit released, the Bidder can submit a
2nd Performance Bank Guarantee (PBG)
equivalent to the security amount in lieu of the
same which will be valid for a period of 8 years (7
years Period post go live Plus 1 year claim period)
from the issue of PBG.
Requesting the Bank to consider Performance Bank Guarantee
of 10% of the total cost of CMS Software Solution.
This clause is non negotiable
Page 26 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
170 13 5 Scope of Work
5.1 (xl.)
Escrow arrangement for applications needs to be
maintained. An escrow agreement is a tripartite
arrangement between the Bank, Software vendor
and the escrow agent. By this arrangement, the
source code of application is kept with escrow
agent, which can be made available to the Bank in
the event the vendor goes out of business. The
Successful Bidder is required to execute documents
/agreements in this regard as prescribed by Bank
from time to time.
Bank is requested to add that the cost of Escrow arrangement
will bear by the Bank.
This clause is non negotiable
171 10 6. SERVICE LEVEL
EXPECTATIONS
AND PENALTY
6.1 (iv)
The Bidder may have to enter into a service level
contract with the Bank before the award of the
contract as per the format provided by the Bank.
The terms of SLA shall be mutually agreed between the parties. The terms of SLA are pre-defined in the RFP
document and it being a public RFP, the terms
cannot be changed at later stage.
172 28 11. WARRANTY &
AMC
11.6
No variation in or modification of the terms of the
Contract shall be made.
Bidder request the Bank to delete this clause, since the terms of
Contract need to be mutually agreed between the parties.
The clause is non negotiable
173 11. PAYMENT
TERMS
11.8
Under no circumstances IDBI Bank shall be liable
to the Successful Bidder and/or its
employees/personnel/representatives/agent etc. for
direct, indirect, incidental, consequential, special or
exemplary damages arising from termination of the
Contract;
The Bank is requested to make the clause mutual as under:
Under no circumstances parties shall be liable to each other or
their employees/personnel/representatives/agent etc. for direct,
indirect, incidental, consequential, special or exemplary
damages arising from termination of the Contract;
The clause is non negotiable
174 50 11. PAYMENT
TERMS
11.12
Bidder has to submit the performance security (in
the manner and form as provided in the RFP) for
10% of total contract value upfront at the time of
signing of the contract.
Bank to clarify the percentage of performance Security, as per
the RFP it is 5% in the form of PBG.
Yes, It is 5% and it can be in the form of PBG
175 54 19. DISPUTE
RESOLUTION
19.3
The Vendor shall not be entitled to suspend the
provision of the Services or the completion of the
job, pending resolution of any disputes between the
Parties and shall continue to render the Services in
accordance with the provisions of the Contract
notwithstanding the existence of any dispute
between the Parties or the subsistence of any
arbitration or other proceedings.
The Bank is requested to make the clause reciprocal by adding
that the Bank shall not withhold any payment to the Bidder
notwithstanding the existence of any dispute between the Parties
or the subsistence of any arbitration or other proceedings.
The clause is non negotiable
Page 27 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
176 57 25. NO SET-OFF,
COUNTER-CLAIMS,
CROSS-CLAIMS
In case the Bidder has any other business
relationship with Purchaser, no right of set-off,
counter-claim and cross-claim and or otherwise will
be available under this Contract to the Bidder for
any payments receivable under and in accordance
with that business.
25.2. In case the Bidder has any claim, no right of
set-off, counter-claim and cross-claim and or
otherwise will be available under this Contract to
the Bidder for any payments receivable under and
in accordance with that business.
25.3. However, IDBI Bank shall have such rights
against the successful Bidder up to maximum of
100% of the contact value.
Bank is requested to make the clause mutual and remove the
part: However, IDBI Bank shall have such rights against the
successful Bidder up to maximum of 100% of the contact
value.
The clause is non negotiable
177 66 Termination for Convenience: Notwithstanding the
provisions of the Contract and/or the Bid
Documents, the Purchaser at its sole discretion and
without prejudice to any other right or remedy and
without assigning any reasons, by written 30 days’
notice sent to the Bidder, may terminate the
Contract, in whole or in part, at any time for its
convenience. The notice of termination shall specify
that termination is for Purchaser’s convenience, the
extent to which performance of the Bidder under
and in accordance with the Contract is terminated,
and the date upon which such termination becomes
effective.
Bidder would request the Bank to delete the termination for
convenience clause. This is not a standard industry practice and
not acceptable by the Bidder.
The clause is non negotiable
Page 28 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
178 69 48. INSURANCE 48.1. The Bidder shall:
I. take out and maintain at their own cost but on
terms and conditions approved by Purchaser,
insurance against the risks, and for the coverage, as
shall be specified below.
ii. at the Purchaser’s request, provide evidence to
the Purchaser showing that such insurance has been
taken out and maintained and that the current
premiums therefore have been paid.
48.2. Third party liability insurance with a
sufficient coverage for the period of the Contract
48.3. Professional liability insurance, with a
minimum coverage equal to estimated remuneration
and reimbursable.
48.4. Employer's liability and workers'
compensation insurance in respect of the personnel
of the Bidder, in accordance with the relevant
provisions of the applicable law, as well as, with
respect to such personnel, any such life, health,
accident, travel or other insurance as may be
appropriate; and
48.5. Insurance against loss of or damage to (I)
equipment(s) / software purchased in whole or in
part with funds provided under this Contract or
otherwise, (ii) the Bidder’s property used in the
performance of the Services, and (iii) any
documents prepared by the Bidder in the
performance of the Services.
This shall be governed according to the Bidder's existing
insurance policies and the Bidder shall not be obligated to take
fresh insurance policies.
The Bank shall not have any objection to it, as
long as the policy also covers the proposed
instance of the solution to be installed at IDBI
Bank.
179 69 49. LIMITATION OF
LIABILITY
Bidder’s aggregate liability shall be subject to an
overall limit of 100% of the Total Project Cost for
the Contract period.
Bank is requested to modify the clause as : Bidder’s aggregate
liability shall be subject to an overall limit of20% of the Total
Project Cost for the Contract period.
The clause is non negotiable
180 110 16.ELIGIBILITY
CRITERIA
COMPLAINCE
SHEET (ANNEXURE
– 16) Point 4
The Bidder in last 5 years should have
successfully implemented and is
currently supporting the offered solution
for at least two of the modules* in one or
more PSU / Private Bank in India having a
business mix of Rs.50,000 Crore and
above.(Bidder should submit proof for
the above).
* The two implemented Modules counted for the
eligibility purpose can only be 1) Payments and
2) Collections or Dividend
The bidder in last 3 years should have successfully
implemented
the offered solutions for at least two of the modules in one or
more banks in India or aboard having mix business of 50,000
crs and above.
The two implemented Modules counted for the
eligibility purpose can only be 1)
Payments
2) Collections or Dividend
The referred clause in eligbility criteria cannot
be modified.
Page 29 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
181 110 16.ELIGIBILITY
CRITERIA
COMPLAINCE
SHEET (ANNEXURE
– 16) Point 2
Bidder should have minimum annual
turnover of Rs.100 crores each during the
last three financial years that is 2016-17,
2017-18 and 2018-19 as per audited
financial statements. This must be
individual company and not of any
group of companies
In terms of the Govt. of India guidelines on Public Procurement
Policy for MSMEs,requesting the bank to consider the annual
average turn over to be 20 crs for each financial year. This
must be individual company and not of any
group of companies
Pre-qualification criteria with respect to Prior
Turnover and Prior experience shall be relaxed
for Micro & Small Enterprises as per GOI
guidelines subject to meeting of quality and
technical specifications.
182 111 16.ELIGIBILITY
CRITERIA
COMPLAINCE
SHEET (ANNEXURE
– 16) Point 3
Proposed software/solution should have been
implemented and live for last 3 months in at least 1
Banking / financial institution / PSU / Government
Organisation
Proposed software/solution should have been implemented and
live for last 3 months in at least 1 Bank in India or abroad
The referred clause in eligbility criteria cannot
be modified.
183 26 6.5
Point c) Penalty for
downtime for Post
implementation:
Uptime in percentage (%) The up time charges should be charged below 90 % The clause is non negotiable
184 27 6.5
Point d) Penalty for
delay migration /
migration not to the
satisfaction of the
Bank.
Penalty to the extent of 5% of the Project Cost can
be levied in case of situation
such as delay in migration of master and transaction
database of the existing
customers and / or migration not to the satisfaction
of the Bank. The final decision
in this regard will be as per Bank’s discretion and
no right to representation shall be
available with the successful Bidder
Penalty to the extent of1 % of the Project Cost can be levied in
case of situation
such as delay in migration of master and transaction database of
the existing
customers . Migration completely depends upon the bank
existing vendor & the support
The clause is non negotiable
185 22 5.14. General Terms
i. Bank is desirous of
onboarding vendor for
upgrading following
modules
The Bidder should quote AMC separately as per
Commercial Bid format; the
AMC shall be quoted as percentage of Software
Cost and not in absolute terms.
In case of decline in quotation after reverse auction,
the AMC amount shall also
be revised as percentage of revised quote.
Will their be a reverse auction as the bank has not mentioned
in the process of BID
No, reverse auction is not proposed, however as
per clause Viii of Commercial Bid format, Bank
reserves the right to negotiate the Total Cost of
CMS Solution , with the finally successful
Bidder before awarding the contract.
186 110 Eligibility Criteria.
Point No 2
Bidder should have minimum annual turnover of
Rs.100 crores each during the last three financial
years that is 2016-17, 2017-18 and 2018-19 as per
audited financial statements. This must be
individual company and not of any group of
companies
Bidder should have minimum annual turnover of Rs.500 crores
each during the last three financial years that is 2016-17, 2017-
18 and 2018-19 as per audited financial statements. This must
be individual company and not of any group of companies. This
will help the Bank to have
The suggestion is welcome however it cannot be
changed at this moment as this is a Public RFP
and the terms cannot be changed after
publication date.
Page 30 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
187 8 Earnest Money Deposit Rs. 30,00,000/-(Rupees Thirty Lacs only). (EMD
can be deposited by means of a Demand Draft / Pay
Order, drawn in favor of IDBI BANK LIMITED,
payable at Mumbai to be submitted along with the
Bid.)
Or
The same can be deposited by the bidder through
electronic mode (NEFT) to IDBI Bank’s
Current Account No 18337000010052 IFSC code
– IBKL0000183 at its branch situated at Belapur,
Mumbai - 400614. Tenders not accompanied with
EMD’s Receipt will not be considered. In terms of
the Govt. of India guidelines on Public Procurement
Policy for MSMEs, registered MSEs under the
MSMED Act, will be exempted from payment of
Earnest Money Deposit (EMD) subject to providing
proof of document (Copy of MSME Registration
Certificate).
Request the Bank to allow submission of Performane Bank
gurantee for the EMD amount of Rs 30,00,000/- as well. In the
current situation it will be very difficult to block such huge
funds for any organisation.
This term is non negotiable
Page 31 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
188 49 Payment Terms License Cost 1. On delivery, configuration and
successful installation of software solution 40% 2.
On implementation of atleast 2 modules i.e.
Payments and Collections / DIR Module 40% 3. On
Implementation of Balance Modules 15% 4.
Balance to be kept till expiry of useful life of
Software i.e. 7 years from warranty expiry date.*
5%
Implementation and other misc cost such as
Training, Migration etc.
1 On Successful Implementation of Payments
Module 20%
2. On Successful Implementation of Collections
Module 10%
3. On Successful Implementation of DIR Module
10%
4.On Successful Implementation of Balance
Modulesand Solution 30%
5. Upon UAT and Testing 10%
6. On Go-Live 10%
7. After Warranty Period 5%
8.Balance to be kept till expiry of useful life of
Softwarei.e. 7 years from warranty expiry date.*
5%
Please consider the following payment terms:
License Fee - 50% Along with Purchase Order
Balance 50% Due On Delivery ,configuration and successful
installation of software solution
Implementation Fee - 20% on Purchase Order, 20% on
completion of product walkthrough, 20% on implementation of
Payments module, 10% on implementation of Collections
module, 20% on implementations of Balance modules, 5%
upon UAT Completion, 5% on Go-Live
Taxes and Statutory Levies - Actuals
This term is non negotiable
189 24 Upgrades and Updates The Bidder shall be required to provide all future
updates and upgrades for the proposed software free
of cost during contract period. If however, the
upgrades/updates is not available then the support
for the implemented solution should be available at
any point of time.
Upgrades cannot be provided free of cost. Request the bank to
exclude the same from the scope of RFP.
It is clarified that total revamp of solution
technology wise or functionality wise will be
excluded from update and upgrade definition
referred here.
190 23 Penalty We propose Penalty clauses to be reviewed and agreed
mutually.
The clause is non negotiable
191 Termination of
Contract
Request bank to kindly amend the clauses to include the delay
which is 'solely' attributable to the bidder only since there can be
delays at the bank's end as well
The clause is non negotiable
Page 32 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
192 66 Termination for
Convenience
Notwithstanding the provisions of the Contract
and/or the Bid Documents, the Purchaser at its sole
discretion and without prejudice to any other right
or remedy and without assigning any reasons, by
written 30 days’ notice sent to the Bidder, may
terminate the Contract, in whole or in part, at any
time for its convenience. The notice of termination
shall specify that termination is for Purchaser’s
convenience, the extent to which performance of the
Bidder under and in accordance with the Contract is
terminated, and the date upon which such
termination becomes effective.
Termination of convenience has to be with necessary protection
on goods and services delivered. We propose minimum 90
days notice and that all fees for Software and Services shall
become due and payable and any fees already paid shall be
deemed to be non refundable or Request the bank to please
consider removal of Termination of convenience or to be open
for vendor compensation during termination for convenience
The clause is non negotiable
193 69 LIMITATION OF
LIABILITY
Bidder’s aggregate liability shall be subject to an
overall limit of 100% of the Total Project Cost for
the Contract period.
We propose to place the liability limited to the amount of the
fees received by Intellect for each transaction for the Licensed
Software and for the Maintenance Services. The liability may
please be limited to the Maintenance Fees paid in the year in
which the loss or damage arose.
The clause is non negotiable
194 53 LIQUIDATED
DAMAGES
If the Vendor fails to deliver any or all of the
Service(s) / Systems or perform the Services within
the time period(s) specified in the Contract /
Agreement / fails to meet the Service Level
Requirements, IDBI / Purchaser shall, without
prejudice to its other rights and remedies under and
in accordance with the Contract / Agreement,
deduct from the Contract price, as liquidated
damages, a sum equivalent to 0.50% per week or
part thereof of cost of the contract subject to
maximum deduction of 10% of ‘cost of the
contract’ of the delayed Service(s) or unperformed
Service(s). However, Bank reserve the right to
terminate the contract at any time, if the project is
not delivered as per scheduled timelines and Bank
will claim entire amount paid to the vendor with
simple interest @18% p.a. along with additional
10% of ‘cost of the contract’, as compensation.
We propose LD with a caveat for delays solely caused by
bidders failure to meet the milestone of 0.5% per week up to a
maximum of 5% of the Services Fees for the milestone in
delay. LD’s shall only apply for implementations and
customization fees not total fees for solution
The clause is non negotiable
195 76 Unconditional
Acceptance of Terms
and Conditions
Annexure 4 We request bank to modify this clause from Unconditional
acceptance - to acceptance of terms and conditions to be
mutually agreed.
The clause is non negotiable
Page 33 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
We assume that the Core/Distribution Switches, Firewalls,
Application Firewall, Load Balancer's, WAN devices along
with the new Infrastructure/System like server ,storage ,SAN
switch , Virtualization tool will be provided by the bank.?
Please confirm
Infrastructure will be provided by the bank
We assume that the Bank will provide the
monitoring/patching/sever automation/HIPS/Antivirus
tools/Disaster Recovery mangement (DRM )Tool for the new
server environment ? Please confirm
Infrastructure will be provided by the bank
We assume that Backup Server /software along with the Tape
drive/Tape Media will be provided by the bank for the server
environment?please confirm.
Infrastructure will be provided by the bank
197 17 5.6/iV/b:Hardware
proposed should be
sized properly and
sizing should be
certified by the
application OEM.
Hardware for the
application including
OS and Database (SQL
and Oracle) only will
be provided by Bank.
Any other software
need shall also be
provided by Bidder. All
related OEM’s support
for database need to be
provided by the Bidder.
Please confirm if Bank can also provide the Oracle weblogic
application server license along with the Oracle Databse license
.
Normally Hardware, Database and OS will be
provided by bank. Any other third party
software/ utility required for running the
software solution, with all required licenses
should be provided by the Bidder.
If bidder is unable to provide any other
software/utility required for running the solution
, bidder should provide the cost break-up of
each software and can recommend the vendor
of their choice
196 23 5.15/ Hardware
Requirements
Page 34 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
198 20 5.12. Disaster
Recovery
Mechanism/b) The
Bidder needs to submit
the technical
architecture relating to
data replication
between primary and
secondary site. The
Recovery Time
Objective (RTO) and
Recovery Point
Objective (RPO) for the
proposed solution
should be 30 minutes
and 15 minutes
respectively.
From an application perspective, the services can be started with
in 60 mins. However the switching over of database, DNS re-
directions etc (which are outside the application control) may
take time depending on the size of database. Typically the RTO
requirements are in the range of 2-4 hours.Request the bank to
please update the RTO to 120 Minutes.
RTO will be 60minutes, as in our current
production setup DC to DR switch of
application takes place maximum 60minutes.
Switching off DB and DNS replication will be
taken care by bank . Bidder has to ensure CMS
application software should be up and running
in 30 minutes
Please provide the name of country for which the following data
is going to be provided and provide separate data for each
country.
It is applicable currently to India
Can the various country data be hosted on same physical
servers or do we need to have separate physical setup for each
country
It is applicable currently to India
Total corporate users across all the modules connecting through
Internet.
Refer clause 5.1.xli, on page 13
Total Concurrent users across all the modules connecting
through Internet.
Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total Back Office users across all the modules. Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total Concurrent Back Office users across all the modules. Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total Customers / Accounts The present customers are approx 10000
Total Online (during banks business hours) Sweeps transactions
per day. ( This includes the transactions that are orginating from
all the channels e.g file upload , Web services )
Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total Peak Online (during banks business hours) Sweeps
transactions per day. ( This includes the transactions that are
orginating from all the channels e.g file upload , Web services )
Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total Batch Sweeps transactions per day. ( During the EOD) Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
23199 5.15/ Hardware
Requirements
Page 35 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
Online (during banks business hours) Pooling transactions per
day. ( This includes the transactions that are orginating from all
the channels e.g file upload , Web services )
Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Peak Online (during banks business hours) Pooling
transactions per day. ( This includes the transactions that are
orginating from all the channels e.g file upload , Web services )
Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total Batch Pooling transactions per day. ( During the EOD) Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Number of Supply chain finance users ( Total / concurrent ) Supply Chain Module not proposed, hence not
applicable
Number of Supply chain finance transactions on a daily basis (
Average/ Peak )
Supply Chain Module not proposed, hence not
applicable
Number of Trade finance users ( Total / concurrent ) TF module not proposed hence not applicable
Total Number of Virtual Accounts VA module not proposed hence not applicable
Total Number of Transaction for Virtual Accounts. VA module not proposed hence not applicable
Concurrent users for Virtual Accounts VA module not proposed hence not applicable
Total Online (during banks business hours) Collections and
Recievables transactions per day. ( This includes the
transactions that are orginating from all the channels e.g file
upload , Web services )
Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total Batch Collections and Recievables transaction s per day. (
During the EOD)
Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total number of H2H transaction per day Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Payments transactions per day. ( This includes the transactions
that are orginating from all the channels e.g file upload , Web
services )
Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Total Peak Payments transactions per day. ( During the EOD) Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Batch transactions per day (via File Upload) Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Peak batch transactions per day (via File Upload) Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
Average File Size (in KB)
Average number of transactions per file Refer Block Vi(b), Vii(b) and Viii(b) of
Technical scoring matrix on page 96
23199 5.15/ Hardware
Requirements
Page 36 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
What is the typical time window in which the transactions need
to be processed ( e.g 4 Hrs, 8 Hrs, 24 Hrs). This is to determine
the TPS (Transaction Per second) requirements of the solution.
Time window referred for arriving at TPS is 8
hours
Year on Year Growth Rate The average growth rate is approx 40% over
last few years which can be taken for reference
subject to any exceptional event in market /
industry growth rate.
200 22 5.14 UPI Payments – Is the requirement about the standard UPI Payment or anything
in specific? Need more information
Payment mode as UPI in payment file uploads
201 22 Interactive Dashboard with report query tools Need more information Can be discussed during pre-bid meeting or
demonstration
202 46. Additional option which can be customized by
Bank
Need more information This is part of Charge Matrix wherein
customisation option may be provided in
addition to the options indicated in Sr.No. 45.
203 9.) Alert or Report to be generated/ scheduled of all
the accounts where 7 years to be completed from
date of first credit
What is the logic of 7 Years? Need more information Seven years is the time limit for which Dividend
account remains with the Dividend Mandate
Handling Bank as per SEBI Guidelines. After
the period of 7 years the amount is transferred to
IEPF
204 12) Uploading and processing of single file
containing Cancellation /Reissuance/Stop Pay apart
from existing
Are you refering to a single file which contain Cancellation /
Reissue / Stop pay? Need more information
This is in continuation to Clause 5 of the DIR
module.
205 96 8) System should provide Manual option for
Temporary Stop and Start process of selected
Product code
Which product are we refering in this point?
Need more information
Any product offered to the clients.
206 97 2 Master Copy Facility Is expectation is Master Template Maintenance? Need More
Information
Copy of entire master set up to use for another
client
207 97 9 Temporary disabling option of clients to stop any
fresh booking, other activity should be allowed, like
liquidation of open entry, charge recover (if any).
Only the New Collection Booking to be Disabled ?
Is this required product wise or for all product?
Yes, product level and client level both options
208 98 28 Schedule Liquidation :- Manual Inputting Need more information Manual liquidation marking and bulk upload in
case of large volme
209 99 45 Voucher Checking reports Are we refering to Accounting? Need more information Reports for checking entries done
210 99 46 Manual entry reports Need more information In case any rectification entry is done manually,
such report should be available
211 99 51 Hand off file for income distribution to respective
branch income accounts with GST
Should this be an additional information in Charges Report for
Bank?
System should provide monthly branch/state-
wise income report
23199 5.15/ Hardware
Requirements
Page 37 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
212 105 1 System should facilitate recording, retrieval, MIS
and dashboard view of data related to E-NACH and
Physical NACH, Direct Debit Mandates registered.
Reqirement is for Reporting or for Reconciliation? Require
more details for this Lineitem.
Client Dashboard view of NACH Mandates and
processed files
213 106 6 System should facilitate Proper posting of
transactions in case of change in client account or
client branch.
Need more information Clients are tagged to a partciluar branch. In case
tagging is changed, there should not be any
issue in transation processing
214 24 6.2 The Bidder shall be required to provide all future
updates and upgrades for the proposed software free
of cost during contract period. If however, the
upgrades/updates is not available then the support
for the implemented solution should be available at
any point of time
Implemenation cost will be factored for any Technical Upgrade. This clause is non negotiable
215 27 9 MIGRATION What is the scope of Migration. Customer Reference Data,
Transactional data
Scope of Migration will be discussed in detail
with L1 Bidder and will be documented
accordingly. The expectation of the Bank is to
provide access to Master Data, Setup and
Transaciton data access to its users and
customers.
Bid Fee Request Bank for deviation on this clause
i.e Bid fee to be removed
Non Refundable fee of Rs.30,000/- + Applicable
Taxes (Currently 18% GST)(Rupees Thirty
Thousand Plus Applicable taxes only )Pay Order
/ Demand Draft, drawn in favor of IDBI BANK
LIMITED, payable at Mumbai to be submitted
along with the Bid
or
The same can be deposited by the bidder through
electronic mode (NEFT) to IDBI Bank’s Current
Account No 18337000010052 IFSC code –
IBKL0000183 at its branch situated at Belapur,
Mumbai - 400614. Tenders not accompanied with
Bid Fee Receipt will not be considered.
It is hereby informed that the Bid fee cannot be
waived.
216
Page 38 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
In terms of the Govt. of India guidelines on Public
Procurement Policy for MSMEs, registered MSEs
under the MSMED Act, will be exempted from
payment of Earnest Money Deposit(EMD)
subject to providing proof of document(Copy of
MSME Registration Certificate
Earnest Money Deposit
Rs. 30,00,000/-(Rupees Thirty Lacs only). (EMD
can be deposited by means of a DemandDraft
/ Pay Order, drawn in favor of IDBI BANK
LIMITED, payable at Mumbai to be submitted
alongwithOr
The same can be deposited by the bidder through
electronic mode (NEFT) to IDBI Bank’s Current
Account No 18337000010052 IFSC code
– IBKL0000183 at its branch situated at Belapur,
Mumbai - 400614. Tenders not accompanied with
EMD’s Receipt will not beconsidered.
In terms of the Govt. of India guidelines on Public
Procurement Policy for MSMEs, registered MSEs
under the MSMED Act, will be exempted from
payment of Earnest Money Deposit (EMD) subject
to providing proof of document(Copy of MSME
Registration Certificate)
The value of 1st Performance Bank Guarantee
(PBG) will be 15% for the Total cost of CMS
Software Solution (as defined in part ‘A’ of
Commercial Bid) and should be valid for a period
of 18 months (6 Months Warranty Period
+ 1 Year claim period) from the date of issue of
PBG.
It is hereby informed that the Bid fee cannot be
waived.
This clause is non negotiable
Security Deposit It is hereby informed that the PBG cannot be
waived
As per company policy Nucleus does not prefer bank
guarantees.Request bank for deviation on this point.
As per organizationpolicy, Nucleus does not accept any kind of
guarantees. Request bank for deviation on this point.
216
217
218
Page 39 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
The Bank shall retain a part of Total cost of CMS
Software solution as security towards satisfactory
performance, till the estimated useful life of the
solution i.e. 7 years. The details of the same are
mentioned in clause 13.4 of Chapter C.
If the successful Bidder is desirous of getting this
security deposit released, the Bidder can submit a
2ndPerformance Bank Guarantee (PBG) equivalent
to the security amount in lieu of the same which
will be valid for a period of 8 years (7 years Period
post go live Plus 1 year claim period) from the
issue of PBG.
5. Scope of work
xxiii.
5. Scope of Work Request Bank for deviation on this point
xxv. I.e – point to be removed
5. Scope of Work Request Bank for deviation on this point
xxxv. I.e – Periodic VAPT, without any addition cost.
5. Scope of Work
xli.
5. Scope of Work Request Bank for Deviation on this point,
xlix. i.e – Updating software without any addition cost. Any upgrade
in contract period will attract additional implementation cost.
Bidder must provide required support during
periodic VAPT (External & Internal), IS Audit,
Security Audit, various compliances specially
government and regulatory, cyber related, etc., to
the Bank. Also rectification of deficiencies pointed
out during IS Audit should be done at no additional
cost to the Bank.
Security Deposit It is hereby informed that the PBG cannot be
waived
This clause is non negotiable
The Bidder shall be responsible for data migration
from existing system of the Bank to the new system
in a seamless way and also the reconciliation of data
tables including General Ledgers while migration
from existing CMS system of the Bank to the new
CMS system.
This clause is non negotiable
This clause is non negotiable
This clause is non negotiable
Further, the Bidder should ensure of updating
software / application or updating patches whenever
it is released at no extra cost during
warranty/Support/maintenance contract period.
There should not be any licensing concept on user
level and there should not be any limit on number of
users also.
As per standard Policy Nucleus does not provide unlimited
Licenses. License shall be bound by terms and number of
Named Users. Request bank for deviation on this point.
As per company policy Nucleus does not prefer bank
guarantees.Request bank for deviation on this point.
In case the solution offered has End of Life /
Support already announced or announced by
OEM/principal vendor/IPR owner during contract
period, the service provider (Bidder) has to ensure
that the same will be supported till the validity of
the contract / or replace / upgrade the same on its
own cost without any disruption in the ongoing
business.
Request Bank for deviation on this point
This clause is non negotiable223
218
219
220
221
222
Page 40 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
a) The Bidder will ensure that all gaps identified at
the time of system testing with respect to Functional
Requirement Specifications (FRS), will be
immediately resolved at no extracost.
Request Bank for Deviation on this point.
5.1 Gap
Identification and
Resolution
b) The Bidder will ensure that gaps pointed out by
the audit and inspection team, statutory and
regulatory bodies, or any other third party agency
engaged by the Bank will be resolved within
reasonable time during the contract period at no
extra cost.
i.e – System testing w. respect to (FRS) with no extra cost.
Request bank to remove this clause as it is impossible to
forecast the effort for any gaps and quantum of work that might
be involved.
c) The Bidder shall resolve gaps by proposing a
suitable work around or customizing the proposed
solution by way of modifications / enhancements, as
necessary, to the proposed software solution at no
extracost.
d) The Bidder will ensure that they have the
necessary infrastructure and resource in place to
resolve all the gaps within the time lines agreed, for
theimplementation.
e) The Bidder shall customize all gaps observed in
the Functional / Technical Requirements, Product
Demo, Current Systems Study, Training and UAT
and pilot rollout. The cost of customization should
be included in the price bid. The Bank will not pay
any additional customization costs. The Bidder
shall document all gaps observed by the Bank at
various stages of implementation including their
solution and monitor and track the status of the
same throughout the implementation.
f) The Bidder shall deliver latest product in UAT
environment of theBank.
5.2 Bank to provide deviation on this point
Interfaces i.e. - customizing, testing and maintaining with no extra cost.
We can confirm the commercials basis the integration listed in
Scope of work i.e. agreed for implementation but not for
contract period. Request bank to remove this clause.
5.3
Implementation
Further, the Bidder should ensure of updating
software / application or updating patches whenever
it is released at no extra cost during
warranty/Support/maintenance contract period.
This clause is non negotiable
This clause is non negotiable
g) The Bidder will be responsible for customizing,
testing and maintaining all the required interfaces
during the contract period at no extra cost to the
Bank. In case of any subsequent change,
modification or alteration to the Banks existing
Application software packages, the Bank will
obtain the API for such existing Application and
provide the same to The Bidder for interface at no
This clause is non negotiable
This clause is non negotiableBidder has to implement the CMS Solution for all
the application/interface/corporates as per the Bank
As per standard Policy Nucleus does not provide unlimited
Licenses. License shall be bound by terms and number of
223
224
225
226
Page 41 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
i. All copies should be delivered in hard & soft
media. Source code for customized application and
documentation of the solution shall be the property
of the Bank from the start of the contract period.
Bank would guarantee that it would not use the
source code for commercial purposes and
documents in case the vendor/Bidder so desires. In
case the Bidder fails to customize the software the
Bank reserves the right to modify the software to
suit business requirements without any additional
liability whatsoever. The Bidder should either
provide the source code itself with necessary
documentation or arrange to keep it under
escrowarrangement.
v. Customization in the present application and all
future customization irrespective of regulatory in
nature or Bank specific will be developed or built in
by Bidder at no additional cost during contract
period. Bidder should carry out Detailed
Requirement Gathering (DRG) and share Gap
Analysis document for Bank’s existing solution.
vii. The selected Bidder will be responsible for
migrating Bank’s existing Archival Data from
existing system into the proposed Archival Solution.
Archival Solution should be implemented as part of
GO Live of the solution and having Data retention
for at least 10 years or as per Bank’s Data/Invoice
retention policy.
a. Provide Corporate Licenses for Data Centre
(DC) setup, Disaster Recovery Site (DRS), Near
Disaster Recovery (NDR) and UAT setup for
unrestricted use across the organization viz.
Branches, Location, clients etc. irrespective of
locations or number of users.
Request Bank for Deviation on this clause
227
228
The Bank has also provided option of keeping it
with escrow agent, which may be considered in
case the bidder is not aggreable for keeping
source code with the Bank.
This clause is non negotiable
Nucleus will always be the owner of its software or any
customizations to the same. It is not shareable for product
companies as it governed by IPR. IPR is an intellectual property
of vendor and hence source code can't be shared considering the
business risk for vendor. Request bank for removing this clause.
5.5 System
Commissioning &
Deliverables
5.13 Software
Licenses
Page 42 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
c. All software envisaged is required to be on-
premises irrevocable perpetual software licensed to
IDBI Bank, right to use the software even
afterduring the contract period. Only licensed copies
of software shall be supplied and ported. Further, all
software supplied shall be of latest version.
i.e Corporate license on data recovery etc. irrespective of
location or no. of users and point. C is not acceptable.
5.13.
General Terms
ii. The successful Bidder has to comply with
all Service Level Agreements (SLAs) as mentioned
in this RFP to ensure adherence to project timelines,
quality and availability of services. Also, Bidder
has to ensure compliance with the Bank’sPolicies.
iii. The Bidder may have to enter into a service
level contract with the Bank before the award of the
contract as per the format provided by the Bank.
6.4. Penalty amount
Breach of service levels expectations consistently on
part of the Bidder may lead to invocation of clause
for “Termination for Default”
Penalty Amount: The SLA measure for calculating
Penalty amount shall hours of delay. The penalty
amount will range from Rs.1000/- per hour to
Rs.5000/- per hour, depending on the delay, as
stated under:
Hours of Operation: The support should be
available on 24*7 and 365 days basis without any
holiday excluding planned downtime for
maintenance.
6.5. Standard of Performance and Service
Level Definition and Measurement
Penalty for non- implementation of product features
by committed time:
228
229
This clause is non negotiable
This clause is non negotiable
6. Service level
expectation and
penalty
This clause is non negotiableNucleus works on partnership model with Bank and would
strive to complete the project within mutually discussed
timelines. As per the company policy, we do not prefer penalty
clause/liquidated damages and hence request bank for removal
of this clause at this stage. However, the same can be discussed
at a later stage of contract closure. Request bank for deviation
on this point.
i. Any other lock in terms such as Software
License Cost, AMC cost etc shall result in
disqualification of the vendor from thebid.
Request Bank for deviation on this point as we have requested
changes in other related points.
5.13 Software
Licenses
This clause is non negotiable
6.4 Since this is a Public RFP, no further change in
terms shall be allowed in future.
Since this is a Public RFP, no further change in
terms shall be allowed in future.
Nucleus works on partnership model with Bank and would
strive to complete the project within mutually discussed
timelines. As per the company policy, we do not prefer penalty
clause/liquidated damages and hence request bank for removal
of this clause at this stage.
As per the company policy, we do not prefer penalty clause,
hence request bank for removal of this clause at this stage.
6.2 6.2. The Bidder shall be required to provide
all future updates and upgrades for the proposed
software free of cost during contract period. If
Request Bank for deviation on this point.
Since this is a Public RFP, no further change in
terms shall be allowed in future.
Nucleus works on partnership model with Bank and would
strive to complete the project within mutually discussed
timelines. As per the company policy, we do not prefer penalty
clause/liquidated damages and hence request bank for removal
of this clause at this stage.
6.5
233
234
232
230
231
Page 43 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
Successful Bidder shall be required to provide an
undertaking to the Bank, with regard to features
which are not available in their present solution and
which can be provided in 3M/6M as confirmed by
the Bidder in Technical Bid. In case of failure of the
Bidder to provide the features / modules in
committed timelines, the Bank reserves the right to
impose penalty which can be upto 5% of the Total
cost of CMS Software Solution as specified in Part
‘A’ of Commercial Bid Format and / or cancel the
contract.
ii. In the event of Successful Bidder’s failure to
deliver and / or implement all required components
of a fully functional system (pertaining to the scope
of the project) within the stipulated time schedule or
by the date extended by the Bank, unless such
failure is due to reasons entirely attributable to the
Bank, it will be a breach of contract. In such case,
the Bank would be entitled to charge a penalty.
Penalty will be applicable for late delivery of the
customized software where 0.5% of ‘cost of the
deliverable ’ will be deducted as penalty per week
or part thereof for failure as indicated in the RFP
with the maximum penalty of 10% of ‘cost of the
contract’.
However, Bank reserve the right to terminate the
contract at any time, if the project is not delivered as
per scheduled timelines and Bank will claim entire
amount paid to the vendor with simple interest
@18% p.a. along with additional 10% of ‘cost of
the contract’, as compensation.
The CMS Software Solution has to be up for at
least 99.50%. The CMS Software Solution is
deemed to be up if the users are able to log into the
system.
c) Penalty for downtime
for Post implementation
d) Penalty for delay migration / migration not to the
satisfaction of the Bank.
Since this is a Public RFP, no further change in
terms shall be allowed in future.
Since this is a Public RFP, no further change in
terms shall be allowed in future.
Nucleus works on partnership model with Bank and would
strive to complete the project within mutually discussed
timelines. As per the company policy, we do not prefer penalty
clause/liquidated damages and hence request bank for removal
of this clause at this stage.
Nucleus works on partnership model with Bank and would
strive to complete the project within mutually discussed
timelines. As per the company policy, we do not prefer penalty
clause/liquidated damages and hence request bank for removal
of this clause at this stage.
6.5234
235
Page 44 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
Penalty to the extent of 5% of the Project Cost can
be levied in case of situation such as delay in
migration of master and transaction database of the
existing customers and / or migration not to the
satisfaction of the Bank. The final decision in this
regard will be as per Bank’s discretion and no right
to representation shall be available with the
successful Bidder.
11.1. The Bidder / Vendor will provide 6
Months warranty from the date of issuance of
Acceptance Certificate (Go Live) accompanied with
necessary onsite resources for the project
implemented. Any defects / bugs noticed in the
migrated/implemented applications shall be
reworked and / or replaced by the Bidder / Vendor
with defect-free components free-of-cost. The
Bidder shall conform the integrity of the solution
supplied i.e. the solution is free from bugs,
malware, covert channels in codeetc.
11.2. During the contract period if OEM of
OS/DB solution announces regarding the End of
Support, the successful Bidder will migrate the
solution to the newer version of OS/DB without
additional cost to the Bank. All updates and
upgrades of OS & DB have to be done by the
selected Bidder without any extra cost to the Bank
during contract period. However, licenseswill be
provided by theBank.
11.3. Bidder should setup one centralized L2
Support at Belapur, Navi Mumbai (DC), till the
completion of warranty support. The Bank has a
right to interview and reject resources deployed by
theBidder.
Since this is a Public RFP, no further change in
terms shall be allowed in future.
Warranty & AMC 1.1 Since this is a Public RFP, no further change in
terms shall be allowed in future.
'As per company standard we provide one-month onsite support
after GO Live. Post onsite support, our support (AMC, ASF)
will start. However the need varies depending upon the project
size, activity set agreed upon etc. so this can be discussed with
customer and mutually agreed upon.
Nucleus works on partnership model with Bank and would
strive to complete the project within mutually discussed
timelines. As per the company policy, we do not prefer penalty
clause/liquidated damages and hence request bank for removal
of this clause at this stage.
235
236
Page 45 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
11.4. Post warranty period, Bank may enter
into AMC/ATS support with successful
vendor/OEM for next 10 years and Bank will issue
Purchase Order on every year based on satisfactory
performance of the vendor in previous year. Post
warranty, the application will be covered under the
AMC / ATS by the OEM. The Bidder should
ensure, as part of AMC / ATS that the OEM to
provide followingservice(s):
Request Bank for deviation on this clause
i.e - price quoted must be inclusive of cost of supply,
installation and providing services during the serviceperiod
11.1. The Bidder and any of their personnel or
agents / subcontractors will be granted permission
by Bank to enter upon its premises and lands for the
purpose of such inspection, but only upon the
express condition that the Bidder, their personnel
and agents/ subcontractors shall be responsible for
personal injury (whether fatal or otherwise), loss of
or damage to life, property and other loss damage,
costs andexpenses.
11.2. It will be imperative for each Bidder to
fully inform themselves of all legal conditions and
factors which may have any effect on the execution
of the contract as described in the Bid Documents.
Bank shall not entertain any request for clarification
from the Bidder regarding such localconditions.
9. Firm Prices Prices quoted must be firm and final and shall not
be subject to any re-openers or upward
Request Bank for deviation on this clause
As per the company policy, we do not prefer liquidated
damages and hence request bank for removal of this clause at
this stage. However, the same can be discussed at a later stage
of contract closure.
237
238
239
240
241
Warranty & AMC 1.1 Since this is a Public RFP, no further change in
terms shall be allowed in future.
Since this is a Public RFP, no further change in
terms shall be allowed in future.
4.7 General Instruction The Bid Security as specified in Section II should
be paid along with the Bid Document during
submission. Bids without the Bid Security shall
As per company policy we do not accept bank guarantees.
Request bank for deviation on this point.
Bid price & Validity of
Bid
'As per company standard we provide one-month onsite support
after GO Live. Post onsite support, our support (AMC, ASF)
will start. However the need varies depending upon the project
size, activity set agreed upon etc. so this can be discussed with
customer and mutually agreed upon.
2. Bid Evaluation
Criteria
2.2 The Bidder shall submit their offers strictly in
accordance with the terms and conditions of the Bid
Nucleus shall not be able to accept all terms and conditions
mentioned in the RFP at this stage as some of them do not align
236
This clause is non negotiable
The prices quoted will be exclusive all applicable
taxes. The total price quoted must be inclusive of
cost of supply, installation and providing services
This clause is non negotiable
This clause is non negotiable
11 Local Condition Since this is a Public RFP, no further change in
terms shall be allowed in future.
Page 46 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
11.3. It is the responsibility of the Bidder that
such factors have properly been investigated and
considered while submitting the bid proposals and
that no claim whatsoever including those for
financial adjustment to the contract awarded under
the Bid Documents will be entertained by Bank and
that neither any change in the time schedule of the
contract nor any financial adjustments arising
thereof shall be permitted by Bank on account of
failure of the Bidder to appraise themselves of local
laws /conditions.
12.1. The Bidder shall furnish as a part of its
Bid, a Bid Security as mentioned in the “Document
Control Sheet” by way of demand draft or Bankers
cheque or pay order in favor of ‘IDBI Bank
Limited’ payable at Mumbai. This Bid Security
must accompany the technical bid or Bidder can
transfer the amount through NEFT in the IDBI
Bank account. The details of the Bank account
mentioned in the control sheet. The Bidder must
carry an EMD receipt as a proof of payment and
submit the same at the time of opening ofBid.
12.2. Rejection of Bid: Any technical Bid not
accompanied by EMD as mentioned above, shall be
summarily rejected by IDBI Bank, without any
furthercorrespondence.
12.3. The Bid Security shall beforfeited:
(i) if a Bidder withdraws his bid
during the bid validity period;or
(ii) if a Bidder makes any statement or
encloses any form which turns out to be false,
incorrect and/or misleading at any time prior to
signing of contract and/or conceals or suppresses
material information;or
Bid Security/Earnest
Money Deposit
As per the company policy, we do not prefer liquidated
damages and hence request bank for removal of this clause at
this stage. However, the same can be discussed at a later stage
of contract closure.
241 11 Local Condition Since this is a Public RFP, no further change in
terms shall be allowed in future.
As per company policy, we do accept any kind of guarantees.
Request bank for deviation on this point.
242
Page 47 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
(iii) If the Successful Bidder fails to
sign the contract or furnish performance security
and other guarantee(s)/security in the form and
manner to the satisfaction of IDBI Bank, as
mentioned in the Bid Documents;or
(iv) In the event of any evasion,
avoidance, refusal or delay on the part of the
Successful Bidder to sign and execute the order/
purchase order/ service order or any document, as
may be required by IDBI Bank in case the Bid
isaccepted.
12.4. The Bid Security shall not bear
anyinterest.
12.5. The Bid Security of unsuccessful Bidders
will be refunded within 30 (Thirty) days fromthe
conclusion of contract/RFP.
12.6. The Bid Security of Successful Bidder will
be refunded on execution of all legal documents
including the submission of the PerformanceBank.
12.7. The Bidders have to submit the duly
signed EMD Refund letter at the time of submission
of Biids. Refer EMD Refund format mentioned in
theRFP.
12.8. Any decision by IDBI Bank in this regard
shall be final, conclusive and binding on the
Bidder/s.
13.1. The Successful Bidder shall furnish the
performance Bank guarantee within 15 days of the
receipt of acceptance by Bank, as per the format in
Section-3.
13.2. The value of the 1stPerformance Bank
Guarantee will be 15 % for the total cost of solution
(as specified in Part ‘A’ of commercial Bid) to be
submitted by the successful vendor.
13.3. The Performance Bank Guarantee (PBG)
should be issued by a scheduled commercial Bank
(other than IDBI Bank) and directly forwarded to
the Bank.
13.4. PBG should be valid for a period of 18
months (6Months Warranty Period + 1 Year claim
period) from the date of issue of PBG.
As per company policy we do not accept bank guarantees and
penalties. Request bank for deviation on this point.
Bid Security/Earnest
Money Deposit
13. Performance Bank
Guarantee
This clause is non negotiable
As per company policy, we do accept any kind of guarantees.
Request bank for deviation on this point.
242
243
Page 48 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
13.5. The Bank will retain 5% of the Total cost of
CMS solution as defined in part ‘A’ of the
commercial bid i.e. the PO amount, as security
towards satisfactory performance, till the estimated
useful life of the solution i.e. 7 years.
If the successful Bidder is desirous of getting this
security deposit released, the Bidder can submit a
2nd Performance Bank Guarantee (PBG)
equivalent to the security amount in lieu of the
same which will be valid for a period of 8 years (7
years Period post go live Plus 1 year claim period)
from the issue of PBG.
1.11 Payment will be made in phases after
obtaining a “Letter of satisfaction” and clearance
for Payment from the concerned dealinggroup.
Please allow Nucleus to share their terms of payments for
further discussion at appropriate stage of engagement. Request
bank for deviation on this point at this stage.
1.12 The Bidder/OEM must accept the
payment terms proposed by the Bank. Any
deviation from the proposed payment terms would
not be accepted. The Bank shall have the right to
withhold any payment due to the System Integrator
(SI), in case of delays or defaults on the part of the
Bidder. Such withholding of payment shall not
amount to a default on the part of theBank.
As per the company policy, we do not prefer penalty clause
1.13 The Successful Bidder shall be solely
liable for the payment of all the past, present and
future Central, State and local levies, direct/indirect
taxes, duties, fines and penalties (including without
limitation, excise duties and customs duties, etc.) by
whatever name called, as may become due and
payable in relation to theServices.
1.14 All out of pocket expenses, travelling,
boarding and lodging expenses for the entire Term
of this RFP and subsequent agreement is included in
the amounts quoted and the Bidder shall not be
entitled to charge any additional costs on account of
any items or services or by way of any out of pocket
expenses, including travel, boarding andlodging.
As per company policy we do not accept bank guarantees and
penalties. Request bank for deviation on this point.
13. Performance Bank
Guarantee
This clause is non negotiable243
244 4. Payment Terms This clause is non negotiable
Page 49 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
1.15 Under no circumstances IDBI Bank
shall be liable to the Successful Bidder and/or its
employees/personnel/representatives/agent etc. for
direct, indirect, incidental, consequential, special or
exemplary damages arising from termination of
theContract;
1.16 IDBI Bank shall not have any liability
whatsoever in case of any third party claims,
demands, suit, actions or other proceedings against
the Successful Bidder or any other person engaged
by the Successful Bidder in the course of
performance of theService.
1.17 IDBI Bank reserves the rights to dispute
/ deduct payment / withhold payments / from dues
payable to the Successful Bidder under the
Contract, if the Successful Bidder has not
performed or rendered the Services in accordance
with the provisions of the Contract which the IDBI
Bank at its sole discretionadjudge.
Post Warranty, the vendor has to provide
uninterrupted AMC support for minimum7 yrs.
AMC amount has to be paid by the Bank in
advance every year after deducting the penalties,
ifany
244 4. Payment Terms This clause is non negotiable
Page 50 of 51
S. NoRFP Ref
Page noRFP Clause no Existing clause Details Clarification Sought Bank's Response
Bank's Response to the Pre Bid Queries, Pre Bid Meeting dated 18.05.2020
REQUEST FOR PROPOSAL [RFP] FOR
Procurement of Software Solution for Cash Management Services (CMS)
(REF No: IDBI/ITD/RFP/2020-21/006 Dated 11th –May-2020)
17.1. If the Vendor fails to deliver any or
all of the Service(s) / Systems or perform the
Services within the time period(s) specified in the
Contract / Agreement / fails to meet the Service
Level Requirements, IDBI / Purchaser shall,
without prejudice to its other rights and remedies
under and in accordance with the Contract /
Agreement, deduct from the Contract price, as
liquidated damages, a sum equivalent to 0.50% per
week or part thereof of cost of the contract subject
to maximum deduction of 10% of ‘cost of the
contract’ of the delayed Service(s) or unperformed
Service(s). However, Bank reserve the right to
terminate the contract at any time, if the project is
not delivered as per scheduled timelines and Bank
will claim entire amount paid to the vendor with
simple interest @18% p.a. along with additional
10% of ‘cost of the contract’, ascompensation.
17.2. If the Vendor fails to complete the
entire works / Service(s) before the scheduled
completion date or the extended date or if the
Vendor repudiates the Contract before completion
of the Services, IDBI / the Purchaser may without
prejudice to any other right or remedy available to
IDBI / the Purchaser as under the Contract recover
from the Vendor, as ascertained and agreed
liquidated damages and not by way ofpenalty:
18.4. delay by the Successful Bidder in
the performance of its Contract obligations shall
render the Successful Bidder liable to any or all the
following sanctions:
i. Forfeiture of its performancesecurity
ii. Termination of the Contract fordefault
As per the company policy, Nucleus would not accept the
termination for convenience by bank, and hence request
removal of it from the T&C's.
This clause is non negotiable
18. DEFICIENCY IN
BIDDERS
PERFORMANCE
This clause is non negotiable
'Vendor works on partnership model with Bank and would
strive to complete the project within mutually discussed
timelines. As per the company policy, we do not prefer penalty
clause/liquidated damages and hence request bank for removal
of this clause at this stage.