Upload
dolien
View
221
Download
4
Embed Size (px)
Citation preview
JR( )OS
15-112
REPUBLIC OF INDONESIA
REPUBLIC OF INDONESIA
PREPARATORY SURVEYON
NORTH SUMATRAMINI HYDROPOWER PROJECT
(PPP INFRASTRUCTURE PROJECT)
FINAL REPORT
JANUARY 2016
JAPAN INTERNATIONAL COOPERATION AGENCY
NIPPON KOEI CO., LTD.
REPUBLIC OF INDONESIA
REPUBLIC OF INDONESIA
PREPARATORY SURVEYON
NORTH SUMATRAMINI HYDROPOWER PROJECT
(PPP INFRASTRUCTURE PROJECT)
FINAL REPORT
JANUARY 2016
JAPAN INTERNATIONAL COOPERATION AGENCY
NIPPON KOEI CO., LTD.
Source: SRTM DEM Data (http://srtm.csi.cgiar.org)
Figure I Location Map
Source: JICA Survey Team
Figure II Project Layout
Poring-1:Intake-1
Poring-1: Powerhouse-1
Poring-1: Waterway-1
Poring-2: Waterway-2
Poring-2: Powerhouse-2
Jakarta
Medan
Project Location
Table I Principle Features of Hydropower Formulation Key Item Poring-1 Small Hydropower Poring-2 Small Hydropower
Hyd
rolo
gica
l Fea
ture
s
River (River System)
Poring River (Sibundong River System)
Poring River (Sibundong River System)
Catchment Area 87.45 km2 91.02 km2 River Runoff Max. 14.79 35-day 9.97
95-day 8.09 185-day 6.61 275-day 5.67 355-day 4.58
Min. 4.35 Mean 7.10
Max. 15.40 35-day 10.3895-day 8.42 185-day 6.88 275-day 5.91 355-day 4.76
Min. 4.52 Mean 7.39
Address of the Project Desa Siantar Naipospos Kecamatan Adian Koting Kabupaten Tapanuli Utara Provinsi Sumatera Utara
Desa Siantar Naipospos Kecamatan Adian Koting Kabupaten Tapanuli Utara Provinsi Sumatera Utara
Ope
ratio
n F
eatu
res
Type of Hydropower Run-of-River Type Run-of-River Type Full Supply Level at Intake EL. 646.50 m EL. 441.60 m Tail Water Level EL. 441.50 m EL. 192.70 m Gross Head 205.40 m 249.30 m Effective Head Max. 197.50 m Max. 240.40 m Plant Discharge Max. 6.00 m3/s Max. 5.00 m3/s Installed Capacity 2 × 4,850 kW 2 ×4,850 kW Annual Power Generation 69.1 GWh/year 75.3 GWh/year
Fac
ilit
y O
utli
nes
Intake Weir Type Concrete Gravity Type Nil Height 7.00 m
Crest Length 44.50 m Power Intake Free Flow Conduit, 7.00~4.00 m
(W), 3.50 m (H), 16.40 m (L) Nil
Sand Trap Basin Open Type with Side Spillway, 2-Bay, 3.00 m (W), 4.00~7.50 m
(H), 34.4 m (L) Nil
Headrace Free Flow Conduit and Channel, 1.70 m (W), 2.00~2.15 m (H), 2,471
m (L)
Free Flow Conduit and Channel, 1.60 m (W), 1.90~2.15 m (H), 2,581
m (L) Head Tank Open Type with Side Spillway,
1.70~6.00 m (W), 3.00~5.00 m (H), 25.20 m (L)
Open Type with Side Spillway, 1.60~5.00 m (W), 3.00~5.00 m (H),
24.00 m (L) Penstock Exposed Type, 1-Lane, φ1.35~1.00
m, 431.63 m (L), Steel (SM400) Exposed Type, 1-Lane, φ1.25~0.90
m, 858.87 m (L), Steel (SM400) Pipe Spillway Exposed Type, 1-Lane, φ0.95 m,
431.06 m (L), Steel Pipe (SM400)Exposed Type, 1-Lane, φ1.25 m,
854.90 m (L), Steel Pipe (SM400)Tailrace Free Flow Conduit, 4.00~2.00 m
(W), 3.10~1.00 m (H), 33.10 m(L)Free Flow Channel, 3.00 m (W),
3.10~1.00 m (H), 9.00 m (L) Powerhouse Above-ground Type Above-ground Type Hydro Turbine Type Horizontal Francis, 2-unit Horizontal Francis, 2-unit Type of Generator 3-Phase Synchronous, 2-unit 3-Phase Synchronous, 2-unit
Riv
er U
tili
zati
on
Environmental Discharge 0.31 m3/sec Nil Flow Utilization Factor 69.8% 66.0% Capacity Factor 82.7% 89.8% Plant Factor 82.1% 89.6%
Source: JICA Study Team
Table II Facility Features of Hydropower Project Key Item Poring-1 Small Hydropower Poring-2 Small Hydropower
[MAJOR STRUCTURAL FEATURES] Intake Weir Type Concrete Gravity Type
Nil Dimensions 7.0 m (H), 33.00 m (W), Crest Length 44.50 m
(W) Sand Flush Steel Roller Gate, 1-No, 2.00m (W), 2.00m (H)
Power Intake
Type Free Flow RC Conduit Nil Dimensions 7.00~4.00 m (W), 3.50 m (H), 16.40 m (L)
Screen 2-No, 3.00 m (W), 2.00 m (H) Gate Steel Roller Gate, 2-No, 2.00m(W), 2.00m(H) Steel Roller Gate, 1-No, 2.00m(W), 2.00m(H)
Sand Trap Basin
Type Free Flow RC Channel
Nil
Dimensions 2-No, 2.00 m (W), 4.00~7.50 m (H), 31.90 m (L), Side Spillway Crest 18.00 m (W), Invert
Slope 1:10 Sand Flush Gate Steel Roller Gate, 2-No, 1.00 m(W), 1.00 m(H)Screen 2-No, 2.00 m (W), 3.50 m (H)
Headrace Type Free Flow RC Conduit and Channel Free Flow RC Conduit and Channel Dimensions 1.7 m (W), 2.00~2.15 m (H), 2,471 m (L),
Invert Slope 1/500 1.6 m (W), 1.90~2.15 m (H), 2,581 m (L),
Invert Slope 1/500 Head Tank Type Free Flow RC Channel Free Flow RC Channel
Dimensions 1.70~6.00 m(W), 3.00~5.00 m(H), 25.20 m(L) 1.60~5.00 m(W), 3.00~5.00 m(H), 24.00m(L)Screen 1-No, 6.00 m (W), 3.50 m (H) 1-No, 5.00 m (W), 3.50 m (H)
Penstock Type, Lane Exposed Type with Saddle Support, 1 Lane Exposed Type with Saddle Support, 1 LaneMaterial SM400 SM400 Inner Diameter 1.35 ~ 1.00 m 1.25 ~ 0.90 m Steel Thickness 6~18 mm 6~20 mm Length 431.63 m 858.87 m Anchor Block 7-No 11-No Support Type Saddle Support, 59-No, Max. Span 6.00 m Saddle Support, 122-No, Max. Span 6.00 m
Pipe Spillway
Type, Lane Exposed Type with Saddle Support, 1 Lane Exposed Type with Saddle Support, 1 LaneMaterial SM400 SM400 Inner Diameter 0.95 m 1.25 m Steel Thickness 6 mm 6 mm Length 431.06 m 854.90 m Anchor Block 7-No 9-No Support Type Saddle Support, 60-No, Max Span 6.00 m Saddle Support, 123-No, Max Span 6.00 m
Tailrace Channel
Type Free Flow Conduit Free Flow Channel Dimensions 4.00~2.00 m(W), 3.10~1.00 m(H), 33.10 m(L) 3.00 m (W), 3.10~1.00 m (H), 9.00 m (L)
Tailrace Outlet
Type Side Overflow Type Free Flow RC Channel Dimensions Crest Length 14.00 m (W) 3.00 m (W), 1.40 m (H)
Powerhouse
Type Above-ground, RC type Above-ground, RC type Dimensions 10.8 m (W), 38.0 m (L), 9.0 m (H) 10.8 m (W), 38.0 m (L), 9.0 m (H)
Turbine Type Horizontal Francis Type Horizontal Francis Type Output, No 5,000 kW, 2-No 5,000 kW, 2-No Rotation 750 rpm 750 rpm Specific Speed 73.8 mkW 58.7 mkW Inlet Valve Through Flow Butterfly Type Through Flow Butterfly Type
Generator Type 3-Phase Synchronous Type 3-Phase Synchronous Type Capacity, No 5,380 kVA, 2-No 5,380 kVA, 2-No Voltage 6,600 V 6,600 V Rotation 750 rpm 750 rpm Frequency 50 Hz 50 Hz
Transmission Line 3-Phase, 33 kV, 2-Circuits with 1 pole arrangement, 33.8 km (L)
3-Phase, 33 kV, 2-Circuits with 1 pole arrangement, 36.7 km (L)
Access Road 4.47 km (L) × 4.0 m (W) including 1.0 m (W) Shoulder
4.14 km (L) × 4.0 m (W) including 1.0 m (W) Shoulder
Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini i Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Executive Summary
1. Background and Necessity of the Project
(1) Government Policy on Power Sector in Indonesia
The government of Indonesia has been promoting new power development through the first Crash
Programme in year 2006, and the second Crash Programme in 2010 to cope with the rapid growth of
electricity demand in Indonesia. Both of the Crash Programme aimed to encourage private investment
into Indonesian power sector to increase power generation capacity. The second Crash Programme in
2010 is focused on acceleration of the renewable energy development especially for small hydropower to
harness Indonesian’s abundant hydropower potential. However, as it is difficult for PLN to arrange all of
the necessary power development investment, the government of Indonesia introduced Feed-in Tariff
(FIT) system to small scale renewable energy development to fill the investment gap for renewable
energy development by the private sector.
(2) Small Hydropower Development in Indonesia
Under these circumstances, the number of private companies interested to small hydro IPPs has been
increasing significantly, although actual physical construction has not been progressing smoothly.
According to RUPTL 2013-2022, the small hydropower potential in Indonesia was estimated to
7,500MW but only 86.1MW of the potential had been developed so far. The developed capacity is just
over 1% of its potential in the country. In May 2014, in order to accelerate the small hydropower
development, the government of Indonesia increased tariff for 40% and simplify the licensing procedure.
In July 2015, the tariff was again increased and the new tariff was linked to USD currency.
(3) Situation of Power Supply and Small Hydropower Development in North Sumatra
According to the latest RUPTL 2015-2024, installed capacity of North Sumatra is estimated to 2,487 MW,
however the effective installed capacity, which deducts halted generators due to breakdown or
overhauling, is estimated to 1,872 MW. While, the peak power demand of the region is recorded 1,450
MW and the reserve margin of power supply is calculated to 23% which is lower than the PLN’s target of
35%. The growth rate of power electricity demand for next 10 years is estimated to 13.1% and it
necessitates generation capacity expansion of over 500 MW per year. Alleviation of stringent tight power
supply demand balance by investment of power supply facilities are of the important issues in Indonesia.
According to the “Project for the Master Plan Study of Hydropower Development in Indonesia” which
was conducted by JICA in 2011, the un-developed hydropower potential was estimated to 435 MW and it
is expected the power development harnessing abundant hydropower potential in North Sumatra.
Final Report
Preparatory Survey on North Sumatra Mini ii Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(4) Development of the Mini Hydropower Development in North Sumatra by the Indonesian Private
Company
The subject North Sumatra mini hydropower project has been planned to apply FIT, and the project’s
development permits has been by special purpose company (PT. JDG, hereinafter referred to as JDG).
The project is the two mini hydropower development using water flow of the Poring river that flow
through North Tapanuli regency in North Sumatra Province in Sumatra. JDG has conducted
pre-feasibility study in 2013 and Nippon Koei Co., Ltd. (hereinafter referred to as Nippon Koei) has
conducted review of the pre-feasibility study. The project viability was confirmed in the two studies,
and JDG has decided to promote the project under support of Nippon Koei.
2. Objectives of this Survey
JICA Survey Team conducted the survey to develop detailed plan of this Project for expected JICA’s
Private Sector Investment Fund (PSIF) application. The survey includes current status of power sector,
project scope, project cost, funding for the project, project schedule, construction method, project
implementation system, operation and maintenance system, natural and social environmental
consideration, financial analysis, project scheme and risk analysis.
3. Outlines of the Survey
3.1 Hydrology
(1) Collection of Hydrological Data and Hydrological Monitoring
The hydrological data is collected from the existing seven rainfall gauging stations and five water level
gauging stations near the Poring River basin. The Survey Team visited the rainfall gauging stations and
confirmed the observation method, and conducted verification of the collected data. The water level
monitoring of the Poring River and neighboring Pargaringan River has been conducted since December
2014, and July 2014, respectively. The rainfall monitoring has been conducted since December 2014 to
September 2015.
(2) Low Flow Analysis
The rainfall analysis is conducted and calculates the annual basin rainfall of the Poring site to 4,889
mm/year. The figure is considered adequate since neighboring rainfall monitoring station recorded annual
average of 4,714 mm/year. The continuous long-term duration daily stream flow at Poring-1 intake site is
estimated for 10 years duration. The ten years duration data is prepared by adopting stream flow
monitoring data of the Poring River, converting from neighboring station, and estimated by hydrological
model. As the result, the average discharge from January 2005 to September 2015 is estimated to 7.5
m3/s.
Final Report
Preparatory Survey on North Sumatra Mini iii Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(3) Flood Analysis
For calculation of the flood peak discharge at project site, the probable rainfall is calculated from the
observed rainfall data at Hobuan rainfall gauging station, where is located close to the project site. The
flood peak discharge is calculated for 100 years return period, and the peak discharge of Poring-1 and
Poring-2 planned intake site are 680 m3/s and 710 m3/s, respectively.
3.2 Geology
Based on the geological surface investigation, 11 holes 150 m in total core drilling were carried out for
major structures. Geological and geotechnical conditions were evaluated from the results of standard
penetration test (SPT), penetration test, in-situ tests.
The basement of proposed structures in the project area, mainly consists of hard granite (the Sibolga
Granite Complex), locally of soft welded tuff (Toba Tuff). Accordingly, it was confirmed the stability
of structural foundation.
3.3 Layout Study
(1) Waterway Layout
1) The layout of Intake Weir and Headrace, the layout of Penstock and Powerhouse is determined by
optimization of construction cost and energy loss as well as geological condition, environment, etc.
2) The waterway alignment is designed to go through the terrain obtained in the topographic survey in
this Project. Available gross head for hydropower generation is 205.4 m for Poring-1 and 249.3 m
for Poring-2.
(2) Maximum Plant Discharge
1) Maximum plant discharge is selected comparing the benefit and cost from 10 alternative installed
capacities between 6 and 15 MW. The installed capacity 10 MW is the most optimum for both
Projects due to the highest IRR, and the maximum plant discharge is set at 6.0 m3/s for Poring-1 and
5.0 m3/s for Poring-2,
2) Based on the maximum plant discharge, the maximum effective head is 197.50 m for Poring-1 and
240.40 m for Poring-2 as well as the installed capacity is 10 MW.
3) Accordingly, the annual energy generation is simulated to be 69.1 GWh for Poring-1 and 75.3 GWh
for Poring-2.
3.4 Basic Design of Major Facilities
(1) Poring-1 Small Hydropower Project
Final Report
Preparatory Survey on North Sumatra Mini iv Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The major civil facilities are composed of; 1) Intake Weir, 2) Headrace, 3) Head Tank, 4) Penstock and Pipe
Spillway, 5) Powerhouse and 6) Tailrace.
(2) Poring-2 Small Hydropower Project
The major civil facilities are composed of; 1) Headrace, 2) Head Tank, 3) Penstock and Pipe Spillway, 4)
Powerhouse and 5) Tailrace.
As a result of geological investigation, it was revealed that the Intake Weir for Poring-2 is located on the thick
and weak talus deposit. Therefore, the Intake Weir was cancelled and designed to directly intake the power
discharge from Poring-1.
3.5 Basic Design of Electro-Mechanical Equipment and Transmission Line
Installed turbine capacity will be 2 units × 5,000 kW, installed generator capacity will be 2 units × 5,380
kVA and the capacity of main transformer will be 1 unit × 11,000 kVA for both hydropower plants.
Generated electricity shall be transmitted to the existing Tarutung Substation by 33 kV transmission line
with 35 km long four circuits with two pole arrangement along the existing road to Tarutung. The 33 kV
voltage of transmission line was selected due to the optimization study comparing the cost and transient
analysis of 20 kV, 33 kV and 150 kV. At the end of transmission line, the electricity shall step-down to
20 kV and hand over to PLN at the Tarutung Substation.
3.6 Construction Plan and Cost Estimates
Construction period for preparatory access road work is 6 months, and Main work is 36 months, by the
planning of method statement and quantities which is made from basic condition. Each commissioning
test at construction schedule was estimated for Poring-1 mini hydropower project at 27 months and
Poring-2 mini hydro project at 36 months including 4 month allowance. The critical path of the Project
will be on the construction of both Headraces.
3.7 Environmental Considerations
(1) Initial Environmental Examination (IEE)
After conducting the IEE in examining available data, hearing from stakeholders, carrying out site
reconnaissance, conducting site survey and laboratory analysis, it is concluded that impact resulting from
the Project will be not significant. The predicted impacts could be avoided or minimized in applying
countermeasures.
(2) Impact on Social Environment
Effort was made to avoid any resettlement due to constructing project facilities. Consequently, there will
be no resettlement from constructing the Project facilities. The compensation for about 40 ha of
Final Report
Preparatory Survey on North Sumatra Mini v Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
acquired land shall be disbursed appropriately based on the prepared land acquisition plan (LAP). It is
highly recommended to provide assistances to the affected community continuously in an operation
phase.
(3) Impact on Natural Environment
No particular impact on natural environment such as fish and fishery for the recession section between
Intake Weir and Poring-2 Powerhouse, since the environmental flow is designed to discharge 0.31 m3/s
uniformly from Intake Weir.
(4) Environmental Permissions
Developer have already obtained the Environmental monitoring/management permission (UKL-UPL) for
hydropower facility area and under the process of the UKL-UPL for Transmission Lines.
3.8 Law
The legal bases of this IPP project is Electricity Law (Law No.30/2009). In Indonesia, many IPP projects
has been done already and there are no major legal obstacle. The Feed in Tariff (FIT) regulation was
amended at the end of Jun, 2015 (MEMR Regulation No.19/2015) and the currency basis was shifted
from Indonesian Rupiah (IDR) to US Dollar (USD). The FIT in North Sumatra shall be 13.2 cents/kWh
from year 1 to year 8 and 8.25 cents/kWh from year 9 to year 20. Foreign investment in Indonesia is
regulated and limited by sector basis (Presidential Regulation No.39/2014, “Negative List”) and the
maximum investment ratio of foreign investor for this project is 49%.
Final Report
Preparatory Survey on North Sumatra Mini vi Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(Blank page)
Final Report
Preparatory Survey on North Sumatra Mini i Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
REPUBLIC OF INDONESIA
PREPARATORY SURVEY ON NORTH SUMATRA MINI HYDROPOWER PROJECT (PPP INFRASTRUCTURE PROJECT)
FINAL REPORT
TABLE OF CONTENTS
Figure I Location Map
Figure II Project Layout
Table I Principle Features of Hydropower Formulation
Table II Facility Features of Hydropower Project
Executive Summary
Page
CHAPTER 1 BACKGROUND AND PURPOSE OF THE SURVEY ........................................ 1-1
1.1 Background ............................................................................................................................. 1-1
1.2 Outline of the Project .............................................................................................................. 1-2
1.3 Purpose of the Survey .............................................................................................................. 1-4
1.4 Project Area ............................................................................................................................. 1-4
1.5 Indonesian Concerned Authority ............................................................................................. 1-4
CHAPTER 2 POWER SECTOR SURVEY .................................................................................. 2-1
2.1 Socioeconomic Status .............................................................................................................. 2-1
2.1.1 Socioeconomic Status of Indonesia ........................................................................... 2-1
2.1.2 Socioeconomic Status of North Sumatra ................................................................... 2-3
2.1.3 Economic Development Policy of Indonesia ............................................................. 2-6
2.2 Overview of the Policies and Institutions of the Indonesian Government .............................. 2-8
2.2.1 Policy and Institutions on Electric Power Development ........................................... 2-8
2.2.2 Electric Power Development System......................................................................... 2-9
2.2.3 Power Development Plan ........................................................................................... 2-9
2.2.4 Electricity Tariff ....................................................................................................... 2-12
2.2.5 Budget and Financial Sources .................................................................................. 2-14
2.2.6 Acceleration of Private Investment and Development ............................................ 2-15
2.3 Current Status of Development Policy for Promotion of Private Sector Participation on
Small Hydropower Business ................................................................................................. 2-18
2.3.1 Regulation of the Ministry of Energy and Mineral Resources ................................ 2-18
2.3.2 PPA and Power Tariff ............................................................................................... 2-20
2.3.3 Revision of PPA ....................................................................................................... 2-22
Final Report
Preparatory Survey on North Sumatra Mini ii Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
2.3.4 Permission/License Required for Small Hydropower Business ............................... 2-22
2.3.5 Development Status of Small Hydropower ............................................................. 2-23
2.3.6 Issues on Small Hydropower Development ............................................................. 2-25
2.4 Status of Power Supply and Power Development Plan in North Sumatra ............................ 2-26
2.4.1 Current Status of Power Supply in North Sumatra .................................................. 2-26
2.4.2 Power Demand Projection of North Sumatra .......................................................... 2-31
2.4.3 Generation Expansion Plan in North Sumatra ......................................................... 2-32
2.4.4 Issue of Power Supply and Demand Balance in North Sumatra .............................. 2-34
2.5 Significance of The Project in North Sumatra ....................................................................... 2-34
2.5.1 Effect of The Project to Power Supply and Demand Balance in North Sumatra ..... 2-34
2.5.2 Significance of the Project to the Power System in North Sumtra .......................... 2-35
CHAPTER 3 SITE CONDITIONS ............................................................................................... 3-1
3.1 Site Conditions ........................................................................................................................ 3-1
3.2 Access to the Site .................................................................................................................... 3-2
3.3 Topography .............................................................................................................................. 3-3
3.3.1 Topography of the Site ............................................................................................... 3-3
3.3.2 Topographic Survey ................................................................................................... 3-4
3.4 Hydrology ................................................................................................................................ 3-7
3.4.1 Study Area ................................................................................................................. 3-7
3.4.2 Available Hydrological Data ...................................................................................... 3-9
3.4.3 Rainfall Data ............................................................................................................ 3-12
3.4.4 Runoff Data ............................................................................................................. 3-16
3.4.5 Low Flow Analysis .................................................................................................. 3-18
3.4.6 Flood Analysis ......................................................................................................... 3-27
3.5 Geology ................................................................................................................................. 3-41
3.5.1 Regional Geology .................................................................................................... 3-41
3.5.2 Geological Investigation .......................................................................................... 3-42
3.5.3 General Geology around the Proposed Structure ..................................................... 3-43
3.5.4 Site Geology and Evaluation ................................................................................... 3-45
3.5.5 Construction Materials ............................................................................................. 3-63
3.5.6 Seismic Risk Study .................................................................................................. 3-63
CHAPTER 4 OPTIMIZATION OF DEVELOPMENT PLAN .................................................. 4-1
4.1 Optimization of Development Plan ......................................................................................... 4-1
4.1.1 Limitations of Development Plan .............................................................................. 4-1
4.1.2 Optimization of Development Plan ........................................................................... 4-1
4.2 Installed Capacity .................................................................................................................... 4-2
4.3 Optimization of Layout ........................................................................................................... 4-3
4.3.1 Layout Study of Poring-1 Intake Weir and Headrace ................................................ 4-3
Final Report
Preparatory Survey on North Sumatra Mini iii Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
4.3.2 Layout Study of Poring-2 Intake Weir and Headrace ................................................ 4-5
4.3.3 Layout Study of Poring-1 Penstock and Powerhouse ................................................ 4-7
4.3.4 Layout Study for Poring-2 Penstock and Powerhouse ............................................... 4-9
4.4 Head Loss and Effective Head .............................................................................................. 4-10
4.4.1 Effective Head ......................................................................................................... 4-10
4.4.2 Type and Efficiency of Turbine and Generator ........................................................ 4-11
4.5 Plant Discharge ...................................................................................................................... 4-13
4.6 Annual Energy ....................................................................................................................... 4-15
CHAPTER 5 BASIC DESIGN ....................................................................................................... 5-1
5.1 Basic Design of Civil Works ................................................................................................... 5-1
5.1.1 Poring-1 Intake Weir .................................................................................................. 5-1
5.1.2 Poring-1 Headrace Channel ....................................................................................... 5-7
5.1.3 Poring-1 Head Tank ................................................................................................. 5-10
5.1.4 Poring-1 Penstock .................................................................................................... 5-13
5.1.5 Poring-1 Head Tank Spillway .................................................................................. 5-16
5.1.6 Poring-1 Powerhouse ............................................................................................... 5-18
5.1.7 Poring-2 Power Intake ............................................................................................. 5-21
5.1.8 Poring-2 Headrace ................................................................................................... 5-22
5.1.9 Poring-2 Head Tank ................................................................................................. 5-25
5.1.10 Poring-2 Penstock .................................................................................................... 5-27
5.1.11 Poring-2 Head Tank Spillway .................................................................................. 5-31
5.1.12 Poring-2 Powerhouse ............................................................................................... 5-32
5.2 Basic Design of Hydro-Mechanical Works ........................................................................... 5-35
5.2.1 General ..................................................................................................................... 5-35
5.2.2 Sand Flush Gate and Hoist ....................................................................................... 5-35
5.2.3 Sand Flush Gate stoplog .......................................................................................... 5-36
5.2.4 Power Intake Trashrack ........................................................................................... 5-37
5.2.5 Power Intake Gate and Hoist ................................................................................... 5-37
5.2.6 Power Intake Stoplog ............................................................................................... 5-38
5.2.7 Sand Drain Gate and Hoist at Sand Trap ................................................................. 5-39
5.2.8 Sand Trap Trashrack ................................................................................................ 5-39
5.2.9 Sand Drain Gate and Hoist at Head Tank ................................................................ 5-40
5.2.10 Head Tank Trashrack ............................................................................................... 5-40
5.2.11 Penstock and Spillway Pipe ..................................................................................... 5-41
5.3 Basic Design of Electro-Mechanical Works .......................................................................... 5-43
5.3.1 Basic Design Conditions .......................................................................................... 5-43
5.3.2 Hydraulic Turbines .................................................................................................. 5-43
5.3.3 Generators ................................................................................................................ 5-47
5.3.4 Main Transformers ................................................................................................... 5-48
Final Report
Preparatory Survey on North Sumatra Mini iv Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.3.5 Basic Electrical Connection in Power Station ......................................................... 5-49
5.3.6 Powerhouse Crane ................................................................................................... 5-50
CHAPTER 6 CONSTRUCTION PLAN ....................................................................................... 6-1
6.1 Construction Plan .................................................................................................................... 6-1
6.1.1 Basic condition .......................................................................................................... 6-1
6.1.2 Construction Schedule ............................................................................................... 6-2
6.1.3 Preparatory Access Road Work .................................................................................. 6-5
6.1.4 Temporary Facility Plan ............................................................................................. 6-5
6.1.5 Spoil Bank ................................................................................................................. 6-6
6.1.6 Poring-1 Main Construction Works ........................................................................... 6-7
6.1.7 Poring-2 Main Construction Works ......................................................................... 6-13
CHAPTER 7 NATURAL AND SOCIAL ENVIRONMENTAL CONSIDERATION ............... 7-1
7.1 Project Components with Potential Impacts on the Environment ........................................... 7-1
7.2 Present Conditions in the Project Area .................................................................................... 7-2
7.2.1 Natural Environment ................................................................................................. 7-2
7.2.2 Social Environment ................................................................................................... 7-5
7.3 Legal and Institutional Framework ....................................................................................... 7-22
7.3.1 Legislation on Natural and Social Environmental Considerations .......................... 7-22
7.3.2 Institutional Framework ........................................................................................... 7-26
7.4 Alternatives ........................................................................................................................... 7-27
7.5 Scoping .................................................................................................................................. 7-28
7.6 Initial Environmental Examination (IEE) .............................................................................. 7-32
7.6.1 Terms of Reference (TOR) of the IEE ..................................................................... 7-32
7.6.2 Results of the IEE .................................................................................................... 7-34
7.7 Environmental Management ................................................................................................. 7-50
7.7.1 Institutional Arrangement ........................................................................................ 7-50
7.7.2 Mitigation Measures and Monitoring Plan .............................................................. 7-51
7.7.3 Implementation Schedule ........................................................................................ 7-57
7.8 Stakeholder Meeting .............................................................................................................. 7-59
7.9 Estimation of Reduction of Greenhouse Gas ........................................................................ 7-62
7.10 Conclusions and Recommendations ...................................................................................... 7-63
7.10.1 Conclusions.............................................................................................................. 7-63
7.10.2 Recommendations .................................................................................................... 7-63
Final Report
Preparatory Survey on North Sumatra Mini v Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
List of Tables
Page
Table 1.2.1 Features of the Project ............................................................................................... 1-3
Table 2.1.1 Population of Indonesia ............................................................................................. 2-2
Table 2.1.2 Principal Economy Index of Indonesia ...................................................................... 2-2
Table 2.1.3 Ratios of the Principal Industries of Indonesia to GDP ............................................. 2-3
Table 2.1.4 Trend of the Regional GDP of North Sumatra ........................................................... 2-3
Table 2.1.5 Percentage of Major Industries to the Regional GDP of North Sumatra ................... 2-4
Table 2.1.6 Population of Regencies in North Sumatra Province ................................................. 2-5
Table 2.1.7 Poverty Ratio of North Sumatra Province ................................................................. 2-5
Table 2.1.8 Indonesia Economic Policies ..................................................................................... 2-6
Table 2.2.1 Outline of Crash Program ....................................................................................... 2-11
Table 2.2.2 35 GW Power Development Plan (2015-2019) ....................................................... 2-11
Table 2.2.3 Share of Each Region under the 35 GW Power Development Plan (2015-2019) ... 2-11
Table 2.2.4 Share of Each Source under the 35 GW Power Development Plan (2015-2019) .... 2-12
Table 2.2.5 Electricity Tariff of PLN (1/2) ................................................................................. 2-13
Table 2.2.5 Electricity Tariff of PLN (2/2) ................................................................................. 2-14
Table 2.2.6 Subsidy from the Government to PLN .................................................................... 2-15
Table 2.2.7 Power Generation Cost by Sources ......................................................................... 2-15
Table 2.3.1 Power Purchase Price for Small Hydropower Project ............................................. 2-20
Table 2.3.2 Power Purchase Price for Small Hydropower Project Utilizing Existing
Structures ................................................................................................................. 2-20
Table 2.3.3 Power Purchase Price for Small Hydropower Project Under Operation or
Already Contracted PPA .......................................................................................... 2-21
Table 2.3.4 Permission/License for Small Hydropower Business .............................................. 2-22
Table 2.3.5 Renewable Energy Potentials .................................................................................. 2-23
Table 2.3.6 Development Plan of Renewable Energy ................................................................ 2-23
Table 2.3.7 Status of Small Hydropower Development (As of February 2015) ......................... 2-25
Table 2.4.1 Electric Energy Consumption by Type of Users in North Sumatra in 2014 ............ 2-29
Table 2.4.2 Power Stations Currently Operated in North Sumatra ............................................. 2-30
Table 2.4.3 Abbreviation of Generation Type Used by PLN ...................................................... 2-31
Table 2.4.4 Power Demand Projection in North Sumatra ........................................................... 2-31
Table 2.4.5 Necessary Expansion for Generation Capacity, Transmission, and Substations
between 2015 and 2024 ........................................................................................... 2-32
Table 2.4.6 Generation Expansion Plan of North Sumatra ......................................................... 2-33
Table 2.4.7 Necessary Investment of Generation Capacity from 2015 to 2024 ......................... 2-33
Table 3.3.1 Available Topographic Data ....................................................................................... 3-4
Table 3.3.2 Scope of New Topographical Survey and Mapping .................................................. 3-5
Table 3.3.3 National Benchmark for the Topographic Survey ..................................................... 3-6
Table 3.3.4 Coordinates of Project Benchmarks........................................................................... 3-6
Final Report
Preparatory Survey on North Sumatra Mini vi Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.1 Mean Monthly and Annual Rainfall around the Poring River Basin ......................... 3-8
Table 3.4.2 Mean Daily Evaporation around the Poring River Basin .......................................... 3-9
Table 3.4.3 Availability of Daily Rainfall and Daily Discharge / Water Level Data .................. 3-10
Table 3.4.4 Availability of Monthly Rainfall Data ..................................................................... 3-10
Table 3.4.5 Observation of Hydrological Data by the JICA Survey Team ................................. 3-12
Table 3.4.6 Equation of Regression Line and Correlation Coefficient ....................................... 3-14
Table 3.4.7 Estimated Basin Rainfall at Poring-1 Intake Site..................................................... 3-15
Table 3.4.8 Estimated Basin Rainfall at the Kolang Water Level Gauging Station .................... 3-16
Table 3.4.9 Summary of Discharge Data around the Poring River Basin .................................. 3-17
Table 3.4.10 Comparison of Hydrological and Geological Features ............................................ 3-20
Table 3.4.11 Runoff Coefficient Estimated by Observed Data in 2014-2015 .............................. 3-23
Table 3.4.12 Reference of the Poring-1 Intake Site Daily Flow ................................................... 3-26
Table 3.4.13 Monthly Average Discharge at the Poring-1 Intake Site .......................................... 3-27
Table 3.4.14 Annual Maximum Daily Rainfall at the Hobuan Gauging Station .......................... 3-29
Table 3.4.15 Probable Maximum Daily Point Rainfall at Hobuan ............................................... 3-30
Table 3.4.16 Probable Basin Mean Rainfall for the Poring River Basin ...................................... 3-31
Table 3.4.17 Runoff Coefficient Depending on the Catchment’s Feature .................................... 3-34
Table 3.4.18 Peak Flood Discharge at the Proposed Intake Sites by SCS Method ....................... 3-34
Table 3.4.19 Peak 100-year Discharge Estimated by Rational Formula ...................................... 3-35
Table 3.4.20 Comparison of Peak Flood Discharges .................................................................... 3-36
Table 3.4.21 Maximum Daily Rainfall during January-July at the Hobuan Gauging Station ...... 3-38
Table 3.4.22 Probable Maximum Daily Point Rainfall for the Dry Season in Hobuan ................ 3-39
Table 3.4.23 Peak Flood Discharge at the Proposed Intake Sites in the Dry Season .................... 3-40
Table 3.5.1 PGA and Probability of Earthquake in the Project Area .......................................... 3-64
Table 3.5.2 Design Peak Ground Acceleration for the Project ................................................... 3-65
Table 3.5.3 Classification of the Site for Ground Surface .......................................................... 3-65
Table 3.5.4 Design Earthquake Coefficient ................................................................................ 3-65
Table 4.4.1 Head Loss and Discharge......................................................................................... 4-11
Table 4.4.2 Design Water Level .................................................................................................. 4-11
Table 4.5.1 Plant Discharge and Installed Capacity of Poring-1 and Poring-2 ........................... 4-14
Table 4.6.1 Annual Energy for Poring-1 and Poring-2 ............................................................... 4-15
Table 5.1.1 Relationship of Slope of Stream Bed and Design Water Depth ................................. 5-3
Table 5.1.2 Non-uniform Flow Calculation Result of Headrace Channel-1 ................................. 5-9
Table 5.1.3 Target Water Levels for Poring-1 Head Tank .......................................................... 5-12
Table 5.1.4 Water Hammer Analysis and Penstock Steel Thickness for Poring-1 ...................... 5-15
Table 5.1.5 Non-Uniform Flow Analysis for Overflow Spillway Pipe for Poring-1 .................. 5-17
Table 5.1.6 Poring-1 Powerhouse Setting Level......................................................................... 5-19
Table 5.1.7 Non-uniform Flow Calculation Result of Headrace Channel-2 ............................... 5-23
Table 5.1.8 Target Water Levels in Poring-2 Head Tank ............................................................ 5-26
Table 5.1.9 Water Hammer Analysis and Poring-2 Penstock Steel Thickness ........................... 5-30
Final Report
Preparatory Survey on North Sumatra Mini vii Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 5.1.10 Non-Uniform Flow Analysis for Overflow Spillway Pipe for Poring-2 .................. 5-31
Table 5.1.11 Poring-2 Powerhouse Setting Level......................................................................... 5-33
Table 5.2.1 Equipment List of Hydro-Mechanical Works .......................................................... 5-35
Table 5.2.2 Specification of Sand Flush Gate ............................................................................. 5-36
Table 5.2.3 Specification of Sand Flush Gate Stoplog ............................................................... 5-37
Table 5.2.4 Specification of Power Intake Trashrack ................................................................. 5-37
Table 5.2.5 Specification of Power Intake Gate ......................................................................... 5-38
Table 5.2.6 Specification of Power Intake Gate Stoplog ............................................................ 5-38
Table 5.2.7 Specification of Sand Drain Gate at Sand Trap Basin ............................................. 5-39
Table 5.2.8 Specification of Sand Trap Trashrack ...................................................................... 5-39
Table 5.2.9 Specification of Sand Drain Gate at Head Tank ...................................................... 5-40
Table 5.2.10 Specification of Head Tank Trashrack ..................................................................... 5-40
Table 5.2.11 Material Comparison between Steel and FRP ......................................................... 5-41
Table 5.2.12 Specification of Penstock ......................................................................................... 5-42
Table 5.2.13 Specification of Head Pond Spillway Pipe .............................................................. 5-42
Table 5.3.1 Operating Water Level Conditions .......................................................................... 5-43
Table 5.3.2 Turbine Output ......................................................................................................... 5-44
Table 5.3.3 Specific Speed (Ns) ................................................................................................. 5-45
Table 5.3.4 Turbine Setting Level .............................................................................................. 5-45
Table 5.3.5 Maximum Runaway Speed ...................................................................................... 5-45
Table 5.3.6 Comparison of Performance of Inlet Valves ............................................................ 5-46
Table 5.3.7 Types and Ratings of Drainage Pumps .................................................................... 5-46
Table 5.3.8 Power Output of Generator ...................................................................................... 5-47
Table 5.3.9 Fly Wheel of Turbine and Generator ....................................................................... 5-48
Table 5.3.10 Necessary Fly Wheel of Turbine and Generator ...................................................... 5-48
Table 5.3.11 Outline Specification for Powerhouse Crane ........................................................... 5-50
Table 6.1.1 Quantities of Access Road Work ............................................................................... 6-1
Table 6.1.2 Quantities of Main Work ........................................................................................... 6-1
Table 6.1.3 Quantities of Access Road Work ............................................................................... 6-5
Table 7.1.1 Project Component .................................................................................................... 7-1
Table 7.2.1 Maximum and Minimum Temperatures in North Sumatra ........................................ 7-2
Table 7.2.2 Population, Ethnicity, Language, and Religion .......................................................... 7-5
Table 7.2.3 Income ....................................................................................................................... 7-6
Table 7.2.4 Main Income Source .................................................................................................. 7-7
Table 7.2.5 Vulnerable Households in Total Affected Households .............................................. 7-8
Table 7.2.6 Rice Production ......................................................................................................... 7-9
Table 7.2.7 Rice Sufficiency ....................................................................................................... 7-10
Table 7.2.8 Rice Shortage Management (Ranking) .................................................................... 7-10
Table 7.2.9 Type of Trees and Area for Plantation (ha) .............................................................. 7-11
Table 7.2.10 Literacy Rate ............................................................................................................ 7-12
Final Report
Preparatory Survey on North Sumatra Mini viii Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.11 School Enrolment .................................................................................................... 7-13
Table 7.2.12 Education Infrastructure .......................................................................................... 7-14
Table 7.2.13 Health Infrastructure (Distance to Village) .............................................................. 7-15
Table 7.2.14 Access from the Village to the Main Road .............................................................. 7-16
Table 7.2.15 Electrification Rate .................................................................................................. 7-17
Table 7.2.16 Source of Water........................................................................................................ 7-18
Table 7.2.17 Sources of Energy for Cooking................................................................................ 7-19
Table 7.2.18 Means of Transportation .......................................................................................... 7-20
Table 7.2.19 Places for Medical Treatment .................................................................................. 7-21
Table 7.2.20 Number of Cases and Deaths within 12 Months...................................................... 7-22
Table 7.3.1 Summary of Statutory Order in Indonesia ............................................................... 7-23
Table 7.3.2 Key Legislations Regarding Environmental Impact Assessment ............................ 7-23
Table 7.3.3 Contents of UKL-UPL ............................................................................................. 7-24
Table 7.3.4 State of Environmental Procedure and Further Requirements ................................. 7-25
Table 7.3.5 Governmental Administrative Bodies Relevant to the Project ................................ 7-26
Table 7.4.1 Alternatives .............................................................................................................. 7-27
Table 7.5.1 Anticipated Impact on Component 1 (Hydropower Plants) ..................................... 7-28
Table 7.5.2 Anticipated Impact on Component 2 (Transmission Lines) .................................... 7-30
Table 7.6.1 TOR of the IEE ........................................................................................................ 7-32
Table 7.6.2 IEE Results .............................................................................................................. 7-35
Table 7.6.3 Summary of the Survey Result ................................................................................ 7-41
Table 7.6.4 Location of Fish Species Survey ............................................................................. 7-42
Table 7.6.5 Result of Identified Fish Species ............................................................................. 7-42
Table 7.6.6 Type of Fish, Volume of Catch, and Economic Value .............................................. 7-44
Table 7.6.7 Location of the Water Sampling .............................................................................. 7-45
Table 7.6.8 Results of the Water Sampling ................................................................................. 7-45
Table 7.6.9 Summary of Affected Area, Households and Assets ................................................ 7-47
Table 7.6.10 Entitlement Matrix ................................................................................................... 7-49
Table 7.7.1 Roles and Responsibilities of Institutions Concerned in the Pre-construction /
Construction Phase .................................................................................................. 7-50
Table 7.7.2 Proposed Roles and Responsibilities for CSR Activity during the Operation
Phase ....................................................................................................................... 7-51
Table 7.7.3 Mitigation Measures and Monitoring Plan .............................................................. 7-51
Table 7.8.1 Summary of Focused Group Meeting ...................................................................... 7-59
Table 7.8.2 Summary of Public Consultation Meetings ............................................................. 7-60
List of Figures
Page
Figure 2.1.1 Economic Corridors Set in MP3EI ............................................................................ 2-7
Figure 2.2.1 BKPM One Stop Service Related to Power Generation Business ...................... 2-17
Final Report
Preparatory Survey on North Sumatra Mini ix Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Figure 2.3.1 Procedure for Small Hydropower Development ...................................................... 2-19
Figure 2.3.2 Planned Accumulated Renewable Energy Generation Capacity.............................. 2-24
Figure 2.4.1 Power Grid and Existing and Planned Power Stations ............................................ 2-27
Figure 2.4.2 Power Sector in North Sumatra Generation Unit..................................................... 2-28
Figure 3.1.1 River Profile of the Poring River ............................................................................... 3-1
Figure 3.2.1 Location Map of the Project ...................................................................................... 3-3
Figure 3.2.2 Conditions of the Existing Public Road ..................................................................... 3-3
Figure 3.3.1 Location Map of the Survey and Mapping Area ........................................................ 3-5
Figure 3.4.1 Watershed Area of Poring River ................................................................................ 3-7
Figure 3.4.2 Climate Patterns in Hutaraya near the Poring River Basin ........................................ 3-8
Figure 3.4.3 Mean Monthly Rainfall around the Poring River Basin ............................................ 3-9
Figure 3.4.4 Gauging Stations around the Poring River Basin .................................................... 3-11
Figure 3.4.5 Water Level Monitoring Stations at Kolang, Poring Bridge, and Pargaringan
Bridge ...................................................................................................................... 3-12
Figure 3.4.6 Double Mass Curve for Each of the Rainfall Gauging Station ................................ 3-13
Figure 3.4.7 Thiessen Polygon for Poring-1 Intake Site and Kolang Water Level Observatory .. 3-15
Figure 3.4.8 Monthly and Annual Basin Mean Rainfall of Poring-1 Intake Site ......................... 3-16
Figure 3.4.9 Monthly and Annual Basin Rainfall at the Kolang Water Level Gauging Station ... 3-16
Figure 3.4.10 Duration Curves of Collected Discharge Data ......................................................... 3-17
Figure 3.4.11 Daily Water Level at the Kolang Water Level Gauging Station .............................. 3-18
Figure 3.4.12 Outline of Low Flow Analysis ................................................................................. 3-19
Figure 3.4.13 Scatter Plot of Stream Flow Measured at Poring Bridge and Kolang
Observatories (June 2015 to July 2015) .................................................................. 3-21
Figure 3.4.14 Discharge Data Measured by BWS Sumatera II and Revised H-Q Curve .............. 3-22
Figure 3.4.15 H-Q Rating Curves at Discharge Measurement Points ............................................ 3-23
Figure 3.4.16 Daily Rainfall and Discharge at the Intake Sites ..................................................... 3-23
Figure 3.4.17 Tank Model Parameter for the Runoff at the Poring Bridge .................................... 3-25
Figure 3.4.18 Discharge Hydrograph of Simulated and Observed Discharge of the Poring River
at the Poring Bridge from 2014 to 2015 .................................................................. 3-25
Figure 3.4.19 Comparison of Flow Duration Curve of the Simulated and Observed Stream
Flow Discharge of the Poring River at the Poring Bridge ....................................... 3-26
Figure 3.4.20 Flow Duration Curve at the Poring-1 Intake Site from January 2005 to
September 2015 ....................................................................................................... 3-27
Figure 3.4.21 Area-Adjustment of Point Rainfall .......................................................................... 3-29
Figure 3.4.22 Annual Maximum Daily Rainfall with Different Distribution Types ...................... 3-30
Figure 3.4.23 Standard Dimensionless Hydrograph by SCS ......................................................... 3-31
Figure 3.4.24 Hydrograph for 20-year, 100-year, and 200-year Floods at the Intake Sites ........... 3-34
Figure 3.4.25 Topographical Measurement Points for Rational Formula Method ......................... 3-35
Figure 3.4.26 Comparison with 20-year Floods under Various Schemes in Sumatra .................... 3-37
Figure 3.4.27 Comparison with 100-year Floods under Various Schemes in Sumatra .................. 3-38
Final Report
Preparatory Survey on North Sumatra Mini x Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Figure 3.4.28 Comparison with 200-year Floods under Various Schemes in Sumatra .................. 3-38
Figure 3.4.29 Hourly Rainfall and Discharge in Poring in the Dry Season ................................... 3-39
Figure 3.4.30 Dry Season’s Flood Hydrographs for the Maximum Runoff Coefficients .............. 3-40
Figure 3.5.1 Geological Map of North Sumatera ......................................................................... 3-41
Figure 3.5.2 Location Map of Drilling Sites ................................................................................ 3-42
Figure 3.5.3 Geological Image of the Project Site ....................................................................... 3-45
Figure 3.5.4 Geological Map around Poring-1 Intake Weir ......................................................... 3-47
Figure 3.5.5 Geological Section along the Poring-1 Intake Weir Axis ........................................ 3-47
Figure 3.5.6 Geological Map around Poring-1 Head Tank .......................................................... 3-49
Figure 3.5.7 Poring-1 Head Tank Profile along the Penstock Alignment .................................... 3-49
Figure 3.5.8 Geological Map around Poring-1 Penstock ............................................................. 3-50
Figure 3.5.9 Geological Profile along Poring-1 Penstock ............................................................ 3-50
Figure 3.5.10 Geological Map around Poring-1 Powerhouse ........................................................ 3-52
Figure 3.5.11 Geological Profile along Poring-1 Powerhouse ....................................................... 3-52
Figure 3.5.12 Geological Condition around Poring-2 Intake ......................................................... 3-55
Figure 3.5.13 Geological Section along Poring-2 Intake Weir Axis .............................................. 3-55
Figure 3.5.14 Geological Map around Poring-2 Head Tank .......................................................... 3-58
Figure 3.5.15 Geological Profile along Poring-2 Head Tank ......................................................... 3-59
Figure 3.5.16 Geological Map around Poring-2 Penstock ............................................................. 3-60
Figure 3.5.17 Geological Profile along Poring-2 Penstock ............................................................ 3-61
Figure 3.5.18 Geological Map around Poring-2 Powerhous .......................................................... 3-62
Figure 3.5.19 Geological Profile along Poring-2 Powerhouse ....................................................... 3-62
Figure 3.5.20 Indonesia Earthquake Hazard Map .......................................................................... 3-63
Figure 3.5.21 Correlation between PGA and Annual Probability of Exceedance .......................... 3-64
Figure 4.1.1 Flowchart of Optimization of Dvelopment Plan ........................................................ 4-2
Figure 4.3.1 Alternative Location of Poring-1 Intake Weir ........................................................... 4-4
Figure 4.3.2 Alternative Layout of Poring-1 Intake Weir and Headrace ........................................ 4-4
Figure 4.3.3 Alternative Location of Poring-2 Intake Weir ........................................................... 4-6
Figure 4.3.4 Alternative Layout of Poring-2 Intake Weir and Headrace ........................................ 4-7
Figure 4.3.5 Alternative Location of Poring-1 Powerhouse .......................................................... 4-8
Figure 4.3.6 Alternative Layout of Poring-1 Penstock and Powerhouse ....................................... 4-8
Figure 4.3.7 Alternative Location of Poring-2 Powerhouse .......................................................... 4-9
Figure 4.3.8 Alternative Layout of Poring-2 Penstock and Powerhouse ..................................... 4-10
Figure 4.4.1 Turbine Selection Chart ........................................................................................... 4-12
Figure 4.4.2 Efficiency of Turbine and Generator ....................................................................... 4-13
Figure 4.5.1 Plant Discharge for Poring-1 ................................................................................... 4-15
Figure 4.5.2 Plant Discharge for Poring-2 ................................................................................... 4-15
Figure 4.6.1 Dependable Output and Energy for Poring-1 .......................................................... 4-16
Figure 4.6.2 Dependable Output and Energy for Poring-2 .......................................................... 4-16
Figure 5.1.1 H-Q Curve at Poring-1 Intake Weir Site .................................................................... 5-2
Final Report
Preparatory Survey on North Sumatra Mini xi Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Figure 5.1.2 Location of Poring-1 Intake Weir Axis ...................................................................... 5-2
Figure 5.1.3 Location of Poring-1 Intake Weir Site ....................................................................... 5-2
Figure 5.1.4 Flood Discharge Rating Curve at Intake Weir ........................................................... 5-3
Figure 5.1.5 Location of Counter Dam .......................................................................................... 5-4
Figure 5.1.6 Front View of Main Dam ........................................................................................... 5-5
Figure 5.1.7 Plan of Intake -1 ......................................................................................................... 5-5
Figure 5.1.8 Profile of Intake -1 Portal .......................................................................................... 5-5
Figure 5.1.9 Profile of Poring-1 Power Intake and Sand Trap Basin ............................................. 5-6
Figure 5.1.10 Suspended Sediments of Poring River ....................................................................... 5-7
Figure 5.1.11 Typical Section of Poring-1 Headrace ....................................................................... 5-8
Figure 5.1.12 Locations of River Crossings for Poring-1 .............................................................. 5-10
Figure 5.1.13 Typical Section of River Crossings .......................................................................... 5-10
Figure 5.1.14 Longitudinal Profile of Poring-1 Head Tank ........................................................... 5-12
Figure 5.1.15 Plan and Profile of Poring-1 Penstock ..................................................................... 5-13
Figure 5.1.16 Optimum Closing Time of Turbine and Generator .................................................. 5-14
Figure 5.1.17 Comparison of Pipe Spillway .................................................................................. 5-16
Figure 5.1.18 Type Selection Chart of Energy Dissipater .............................................................. 5-17
Figure 5.1.19 An Example of Impact Type Energy Dissipater ...................................................... 5-17
Figure 5.1.20 Typical Dimensions of Impact Type Energy Dissipater ........................................... 5-18
Figure 5.1.21 H-Q Curve at Powerhouse-1 Site ............................................................................. 5-19
Figure 5.1.22 Plan of Poring-1 Powerhouse .................................................................................. 5-20
Figure 5.1.23 Profile of Poring-1 Powerhouse ............................................................................... 5-20
Figure 5.1.24 Longitudinal Profile between Poring-1 Tailrace and Poring-2 Power Intake .......... 5-21
Figure 5.1.25 Typical Section of Poring-2 Headrace ..................................................................... 5-22
Figure 5.1.26 Layout of Headrace Channel Crossing the Village .................................................. 5-23
Figure 5.1.27 Typical Section of Village Crossing ......................................................................... 5-24
Figure 5.1.28 Locations of River Crossings ................................................................................... 5-24
Figure 5.1.29 Typical Section of River Crossings .......................................................................... 5-25
Figure 5.1.30 Longitudinal Profile of Poring-2 Head Tank ........................................................... 5-26
Figure 5.1.31 Plan and Profile of Poring-2 Penstock ..................................................................... 5-28
Figure 5.1.32 Optimum Closure Time of Turbine and Generator .................................................. 5-29
Figure 5.1.33 H-Q Curve at Powerhouse-2 Site ............................................................................. 5-32
Figure 5.1.34 Plan of Poring-2 Powerhouse .................................................................................. 5-33
Figure 5.1.35 Profile of Poring-2 Powerhouse ............................................................................... 5-34
Figure 5.3.1 Selection Chart for Turbine Type ............................................................................. 5-44
Figure 6.1.1 Preparatory Access Road Work .................................................................................. 6-3
Figure 6.1.2 Main Work Schedule .................................................................................................. 6-4
Figure 6.1.3 Concrete Pouring Schedule ........................................................................................ 6-5
Figure 6.1.4 Schedule for Number of Generator on Site ................................................................ 6-6
Figure 6.1.5 Layout of Project Road and Temporary Access Road ............................................... 6-8
Final Report
Preparatory Survey on North Sumatra Mini xii Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Figure 6.1.6 Figure 3.4.19 Flow Duration Curve at Poring-1 Intake Site ...................................... 6-9
Figure 6.1.7 Layout of Project Road and Temporary Access Road ............................................... 6-9
Figure 6.1.8 Typical Section of Diversion Work 1st Stage .......................................................... 6-10
Figure 6.1.9 Typical Section of Diversion Work 2nd Stage ......................................................... 6-10
Figure 6.1.10 Drainage Capacity of Diversion Work 2nd Stage .................................................... 6-11
Figure 7.2.1 Maximum and Minimum Temperatures in North Sumatra ........................................ 7-2
Figure 7.2.2 National Park in Sumatra Island ................................................................................ 7-3
Figure 7.2.3 Land Usage ................................................................................................................ 7-4
Figure 7.2.4 Public Water Supply Space ...................................................................................... 7-18
Figure 7.4.1 Original Layout and Alternative Layout for Headrace Channel .............................. 7-27
Figure 7.7.1 Implementation Schedule ........................................................................................ 7-58
Final Report
Preparatory Survey on North Sumatra Mini xiii Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Abbreviations
(1) Organization
JICA Japan International Cooperation Agency
IIF Indonesia Infrastructure Finance
PLN PT. PLN (Persero)
PU Department of Public Works
Samuel PT. Samuel International
JDG PT. Jaya Dinamika Hydroenergi
NK Nippon Koei Co., Ltd.
NEF New Energy Foundation
(2) Measurement
mm millimeter
cm centimeter
m meter
km kilometer
km2 square kilometer
m3 cubic meter
m3/s cubic meter per second
kV kilovolt
kW kilowatt
MW megawatt
kWh kilowatt hour
GWh gigawatt hour
kVA kilovolt ampere
kg kilogram
ton metric ton
sec, s second
min minute
hr hour
yr year
IDR Indonesian Rupiah
US$ US Dollar
US¢ US Cent
¥ Japanese Yen
(3) Elevation
EL. Elevation above sea level
WL Water Level
FSL Full Supply Water Level
FWL Flood Water Level
TWL Tail Water Level
RWL Rated Water Level
(4) Economy and Finance
IRR Internal Rate of Return
EIRR Economic Internal Rate of Return
FIRR Financial Internal Rate of Return
ROE Return of Equity
FC Foreign Currency
LC Local Currency
LS Lump Sum
(5) Others
Pre-FS Pre Feasibility Study
FS Feasibility Study
BD Basic Design
DD Detailed Design
CS Construction Supervision
IPP Independent Power Producer
BOT Build, Operate and Transfer
CW Civil Works
MW Metal Works
E&M Electrical and Mechanical Works
SS Sub-station
TL Transmission Line
(6) Exchange Rate as at October 2015
US$ 1.00 = IDR 13,300
¥ 1.00 = IDR
Final Report
Preparatory Survey on North Sumatra Mini xiv Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(Blank page)
Final Report
Preparatory Survey on North Sumatra Mini 1-1 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
CHAPTER 1 BACKGROUND AND PURPOSE OF THE SURVEY
1.1 BACKGROUND
(1) Current Situation and Issues on the Power Sector in Indonesia
According to the PT. PLN (Persero) Electricity Supply and Business Plan from 2015 to 2024 (RUPTL
2015-2024), the peak load demand of Indonesia is 33,157 MW, while the generation capacity of the
country is 43,457 MW. The reserve margin of the power supply is 31%, which is lower than the target of
35% according to PLN policy. The electric demand of the country from 2009 to 2013 has kept increasing
with an annual growth rate of 7.8% and the electric demand is deemed to continue with high annual
growth rate of approximately 8%. This tight power supply and demand balance in the country becomes an
imminent issue in Indonesia’s power sector. Especially, as the Sumatra power system expected the rapid
increase of peak power demand, the peak power demand of 5,017 MW in 2014 is expected to be 13,141
MW by 2024. The existing generating capacity of the Sumatra power supply is 6,116 MW; therefore,
power development is urgently needed in the Sumatra Region.
(2) Government Policy on Power Sector in Indonesia
In order to cope with the rapid growth of electric demand, the Government of Indonesia has been
promoting new power development through the first Crash Program in 2006, and the second Crash
Program in 2010. Both of these Crash Programs aimed to encourage private investment into Indonesia’s
power sector to increase power generation capacity. The second Crash Program in 2010 is focused on
acceleration of renewable energy development especially for small hydropower to harness Indonesia’s
abundant hydropower potential. However, as it is difficult for PLN to arrange all of the necessary power
development investment, the Government of Indonesia introduced the Feed-in Tariff (FIT) system for
small-scale renewable energy development to fill the investment gap of renewable energy development
by the private sector.
(3) Small Hydropower Development in Indonesia
Under these circumstances, private companies tend to be interested in small hydro development and the
number of such companies has been increasing significantly, although actual physical construction has
not been progressing smoothly. According to RUPTL 2013-2022, the small hydropower potential in
Indonesia was estimated at 7,500 MW but only 86.1 MW of the potential had been developed so far. The
developed capacity is just over 1% of its potential in the country. In May 2014, in order to accelerate
small hydropower development, the Government of Indonesia increased its tariff by 40% and simplify the
licensing procedure. In July 2015, the tariff was again increased and the new tariff was linked to
Final Report
Preparatory Survey on North Sumatra Mini 1-2 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
US$ currency.
(4) Situation of Power Supply and Small Hydropower Development in North Sumatra
According to the latest RUPTL 2015-2024, the installed capacity of North Sumatra is estimated to be
2,487 MW; however, the effective installed capacity, which deducts halted generators due to breakdown
or overhauling, is estimated at 1,872 MW. Meanwhile, the peak power demand of the region is recorded
at 1,450 MW and the reserve margin of power supply is calculated to be 29% which is lower than the
PLN’s target of 35%. The growth rate of power electricity demand for the next ten years is estimated at
13.1% and it necessitates generation capacity expansion of over 500 MW per year. According to the
“Project for the Master Plan Study of Hydropower Development in Indonesia” (JICA 2011), the
undeveloped hydropower potential was estimated at 435 MW and an increase in power development is
expected by harnessing the abundant hydropower potential in North Sumatra.
(5) Mini Hydropower Development in North Sumatra by Indonesian Private Company
The North Sumatra Mini Hydropower Project has been planned to apply FIT, and the project’s
development permits have been secured by the special purpose company (PT. Jaya Dinamika
Hydroenergi hereinafter referred to as JDG). The project is the development of two mini hydropower
stations using water flow of the Poring River that originates in the mountain range of North Tapanuli
Regency in North Sumatra Province, Sumatra, and flows to the Indian Ocean. JDG has conducted a
pre-feasibility study in 2013 and Nippon Koei Co., Ltd. (hereinafter referred to as Nippon Koei) has
conducted a review of the pre-feasibility study. Project viability was confirmed in these two studies, and
JDG has decided to promote the project under the support of Nippon Koei.
1.2 OUTLINE OF THE PROJECT
(1) Purpose of the Project
The purpose of the project is to supply electricity to North Sumatra through the development of mini
hydropower plants, which are supposed to have less environmental impact compared with large- to
medium-scale hydropower plants. The project aims at contributing to the regional and national economic
development as well as improving the living standard of the people in and around the project area.
(2) Project Site/Names of Places
The project consists of the two project sites below. These are located in the western part of Tapanuli Utara
Regency (Kabupaten) of North Sumatra Province. The project area is about 10 to 20 km away westward
from Tartung, the capital town of Tapanuli Utara Regency.
・Poring-1 Mini Hydropower Station
・Poring-2 Mini Hydropower Station
Final Report
Preparatory Survey on North Sumatra Mini 1-3 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(3) Outline of the Project
The project will construct two mini hydropower stations (Poring-1 and Poring-2) on the Poring River.
These power stations will take water from the Poring River and generate 19,400 kW of electricity, in
total.
Table 1.2.1 Features of the Project
Poring-1
Mini Hydropower PlantPoring-2
Mini Hydropower Plant
Basin Area (km2) 88.1 91.5
Annual Precipitation (mm) 4,889 4,889 Annual Average River Discharge (m3/s)
7.53 -
Maximum Plant Discharge (m3/s)
6.0 5.0
Effective Head (m) 197.5 240.4
Installed Capacity (kW) 9,700 kW
(4,850 kW x 2 units)9,700 kW
(4,850 kW x 2 units) Annual Electrical Energy (GWh)
69.1 75.3
Source: Nippon Koei Co., Ltd.
(4) Implementation of the Project
i. Project Implementation, Operation and Maintenance (both Public and Private)
Upon completion of this study, and after confirmation of the financial and environmental viability,
Nippon Koei will plan to participate in the equity portion of the special purpose company (SPC).
The SPC is already established for each of the mini hydropower projects, namely, Poring-1 and
Poring-2 mini hydropower projects. The construction, operation and maintenance of the project
will be managed by the SPC, and the SPC will obtain necessary permits and licenses from PLN,
and the central/local government.
ii. Operation and Management Plan
The project will yield profit by selling electricity under the FIT price system, and the revenue of
selling electricity will cover the cost of the project such as construction cost, and operation and
maintenance cost.
(5) Project Implementation Schedule
Calendar Year 2014 2015 2016 2017 2018 ・・・ 2040
Schedule
Application for Licenses and Loan
D/D, Bid
Construction 2 years
Operation 20 years
F/S Survey
Final Report
Preparatory Survey on North Sumatra Mini 1-4 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(6) Project Effect
i. Expected Quantitative Effect
Expected quantitative effects of the two mini hydropower projects are as follows:
Poring-1 Mini Hydropower Project : Annual Energy 69.1 GWh (equivalent to 47,400
households electricity demand)
Poring-2 Mini Hydropower Project : Annual Energy 75.3 GWh (equivalent to 51,600
households electricity demand)
ii. Expected Qualitative Effect
Poring-1 and Poring-2 will improve the tight electricity demand and supply balance and
contribute to economic growth. Additionally, the project fits the national policy since it will
expedite the usage of renewable energy.
1.3 PURPOSE OF THE SURVEY
The JICA Survey Team (hereinafter referred to as the JICA Survey Team) will conduct a survey to
develop a detailed plan of the North Sumatra Mini Hydropower Project expected for JICA’s Private
Sector Investment Fund (PSIF) application. The survey includes the current status of the power sector,
project scope, project cost, funding for the project, project schedule, construction method, project
implementation system, operation and maintenance system, natural and social environmental
consideration, financial analysis, project scheme, and risk analysis.
1.4 PROJECT AREA
In and around North Tapanuli Regency in North Sumatra Province, Indonesia.
1.5 INDONESIAN CONCERNED AUTHORITY
The JICA Survey Team conducted the preparatory survey on North Sumatra Mini Hydropower Project in
the Republic of Indonesia under the cooperation of local partner companies, namely, PT. Samuel
International (Samuel) and JDG.
Final Report
Preparatory Survey on North Sumatra Mini 2-1 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
CHAPTER 2 POWER SECTOR SURVEY
2.1 SOCIOECONOMIC STATUS
2.1.1 SOCIOECONOMIC STATUS OF INDONESIA
(1) Indonesia Economy Outlook
Indonesia retains its rank as the largest economy among the member countries of the Association of
Southeast Asian Nations (ASEAN), and the 16th largest worldwide in terms of gross domestic product
(GDP). The country has maintained a strong GDP growth rate of 6.0% from 2006 to 2012 except during
the global financial crisis in 2009, but the stable economic development has made significant strides in
reducing the incidence of poverty1. Although the economic growth rates after 2011 tend to slow down,
the country’s presence as the economic giant in the ASEAN region will stay unchanged.
In order to seek Indonesia’s further economic development, the Government of Indonesia announced the
Masterplan for Acceleration and Expansion of Indonesia's Economic Development (abbreviated as
MP3EI) in May 2011. By utilizing MP3EI, Indonesia aims to earn its place as one of the world’s
developed countries by 2025 with six times nominal GDP of its figure in 2010. President Joko Widodo
was inaugurated in 2014 and promulgated the policies, stated as election promises, which include
strengthening infrastructure investment in the rural areas, maritime infrastructure, and expediting private
investment. The new National Medium-term Development Plan (Rencana Pembangunan Jangka
Menengah Nasional: RPJMN 2015-2019) involves these election promises targeting to strengthen the
national identity as a maritime nation, as well as food security, energy security, and rural development.
(2) Population
The population of Indonesia has steadily increased to 253 million in 2014. The growth rate of the
population was kept around 1.4% until the early 2000s, but this number tends to go down in the recent
five years; it was recorded at 1.17% in 2014. Indonesia’s labor population with age range from 15 to 64
was 66.2% in 2014; this figure is higher than the figure of Japan (61%2). The chronological changes of the
Indonesian population are shown in Table 2.1.1.
1 “Asian Development Bank and Indonesia, Fact Sheet”, Asian Development Bank, 2014 2 Statistics published by the Statistics Bureau of the Ministry of Internal Affairs and Communications in Japan
Final Report
Preparatory Survey on North Sumatra Mini 2-2 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.1.1 Population of Indonesia
Source: World Bank
(3) Economy Index
The Indonesia economy index for the recent ten years is shown in Table 2.1.2. As shown in the table, the
average GDP growth rate in the past ten years is 5.72% and the figure varies around 6% except during the
global financial crisis in 2009. This stable growth contributes in the improvement of the poverty ratio3
from 16% in 2005 to 11.30% in 2014, and the unemployment ratio to the labor population is improved
from 11.20% in 2005 to 6.3% in 2013. These facts indicate that the stable economic growth contributes in
the improvement of poverty reduction and unemployment rate.
Table 2.1.2 Principal Economy Index of Indonesia
Source: World Bank
(4) Industry
The major industries in Indonesia are the manufacturing (motorbike), forest and fishery (e.g., palm oil/
rubber tree plantation), commercial/hotel/restaurant, and mining. The ratios of these industries to the
3 According to the Statistics Agency of Indonesia, poverty line is defined as the food and non-food poverty line. The food poverty line refers to the daily minimum requirement of 2,100 kcal per capita per day. The non-food poverty line refers to the minimum requirement for household necessities such as clothing, education, health, and other basic individual needs.
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Population 106 persons 224 228 231 234 237 241 244 247 250 253 239
Population Growth % 1.43 1.43 1.42 1.41 1.38 1.33 1.29 1.25 1.21 1.17 1.33
Population ages
between 15 ‐ 64% 65.13 65.10 65.06 65.04 65.06 65.16 65.34 65.60 65.89 66.22 65.36
Life Expectancy at
BirthYears 68.85 69.15 69.42 69.69 69.93 70.17 70.39 70.61 70.82 ‐ 69.89
YearAverageItem Unit
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Gross Domestic
Productmillion USD* 285,869 364,571 432,217 510,229 539,580 755,094 892,969 917,870 910,479 888,538 649,741
GDP Growth % 5.69 5.50 6.35 6.01 4.63 6.22 6.17 6.03 5.58 5.02 5.72
Consumer Price
Index (2010 = 100)68.68 77.69 82.67 90.75 95.12 100.00 105.36 109.86 116.91 124.39 97.14
Inflation, GDP
deflator% 14.33 14.09 11.26 18.15 8.27 15.26 7.47 3.75 4.71 5.39 10.27
Exchange Rate IDR per USD 9,705 9,159 9,141 9,699 10,390 9,090 8,770 9,387 10,461 11,865 9,766.79
Poverty Ratio % 16.00 17.80 16.60 15.40 14.20 13.30 12.50 12.00 11.40 11.30 14.05
Unemployment
Ratio% 11.20 10.30 9.10 8.40 7.90 7.10 6.60 6.10 6.30 ‐ 8.11
Foreign direct
investment, net
inflows
million USD 8,336 4,914 6,928 9,318 4,877 15,292 20,565 21,201 23,344 ‐ 12,753
*Dollar figures for GDP are converted from domestic currencies using single year official exchange rates.
Item UnitYear
Average
Final Report
Preparatory Survey on North Sumatra Mini 2-3 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
nation’s GDP from 2010 to 2013 are shown in Table 2.1.3.
Table 2.1.3 Ratios of the Principal Industries of Indonesia to GDP
Source: “Statistical Yearbook of Indonesia, 2014” Statistics Agency of Indonesia
2.1.2 SOCIOECONOMIC STATUS OF NORTH SUMATRA
North Sumatra Province, whose capital is Medan, is where the subject mini hydropower project is located.
The province has a land area of 71,681 km2, which is equivalent to 3.8% of the country, and has a
population of 13.33 million in 2013, which is 5.3% of Indonesia’s population. The economic growth rate
of North Sumatra is around 6% which is the same as the national figure. The major industries of the
province are agriculture (palm oil and rubber), manufacturing (food processing), trading, and
hotel/restaurant. The regional GDP of North Sumatra is Rp351,090 billion (equivalent to US$37.4
billion); this figure is 5.2% of the national GDP.
(1) Economy
The regional GDP of North Sumatra is the fifth largest among the 33 provinces in Indonesia, and the
figure is one-third of the value of the largest province which is the Special Capital Region of Jakarta. The
trend of the regional GDP of North Sumatra, which is published by the Statistics Agency of Indonesia is
shown in Table 2.1.4.
Table 2.1.4 Trend of the Regional GDP of North Sumatra
Source: 1) “Statistical Yearbook of Indonesia 2014” and “Statistical Yearbook of Indonesia 2013”, Badan Pusat Satistik (BPS) Indonesia, 2) World Bank, 3) “Sumatera Utara in Figures, 2014” and “Sumatera Utara in Figures, 2013”, BPS Statistics of Sumatera Utara Province
2010 2011 2012 2013
Agriculture, Livestock, Forestry, and Fishery 15.3% 14.7% 14.5% 14.4%
Mining and Quarrying 11.2% 11.8% 11.8% 11.2%
Manufacturing Industry 24.8% 24.3% 24.0% 1.7%
Electricity, Gas, and Water Supply 0.8% 0.8% 0.8% 0.8%
Construction 10.3% 10.2% 10.3% 10.0%
Trade, Hotel, and Restaurant 13.7% 13.8% 14.0% 14.3%
Transport and Communication 6.6% 6.6% 6.7% 7.0%
Financial, Real Estate, and Business Services 7.2% 7.2% 7.3% 7.5%
Services 10.2% 10.6% 10.8% 11.0%
YearIndustry
Province Unit 2009 2010 2011 2012 2013
Gross Regional Domestic Product 1) billion IDR 236,354 275,057 314,372 351,090 403,933
Exchange Rate (IDR to USD) 2) IDR/USD 10,390 9,090 8,770 9,387 10,461
Gross Regional Domestic Product million USD 22,748 30,258 35,845 37,403 38,612
Economic Growth Rate3) % 5.1% 6.4% 6.63% 6.22% 6.01%
Final Report
Preparatory Survey on North Sumatra Mini 2-4 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Industry
The major industries of the province are agriculture (palm oil and rubber), manufacturing (food
processing), trading, and hotel/restaurant. The ratio of these industries to the regional GDP of North
Sumatra is around 20%. The percentage of these industries in the regional GDP is shown in Table 2.1.5.
Table 2.1.5 Percentage of Major Industries to the Regional GDP of North Sumatra
Source: “Statistik Daerah Provinsi Sumatera Utara 2014”, BPS Statistics of Sumatera Utara Province
In North Sumatra, agriculture and manufacturing are the principal industries. Major agriculture crops in
North Sumatra are rubber tree, palm, coconuts, cacao, and coffee. For manufacturing, food processing,
rubber, plastic factory, and timber processing are the major activities.
(3) Population
According to the Statistics Agency of Indonesia, the population of North Sumatra in 2013 was estimated
in the census conducted in 2010, with a population growth rate of 1.22%. The estimated populations of
the regencies in North Sumatra Province are shown in Table 2.1.6.
Industry 2011 2012 2013
1. Agriculture 22.5% 21.9% 21.3%
2. Mining and Quarrying 1.4% 1.3% 1.3%
3. Manufacturing 22.5% 22.1% 21.6%
4. Electricity , Gas & Water Supply 0.9% 0.9% 0.8%
5. Construction 6.4% 6.7% 6.9%
6. Trade, Hotel & Restaurant 19.2% 19.1% 19.3%
7. Transportation & Communication 9.2% 9.4% 9.5%
8. Financial Intermediaries, Insurance,Real Estate
& Ownerships of Dwelling Business Service7.0% 7.5% 7.7%
9. Social Community & Personal Service 10.9% 11.1% 11.5%
Final Report
Preparatory Survey on North Sumatra Mini 2-5 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.1.6 Population of Regencies in North Sumatra Province
Source: “Statistik Daerah Provinsi Sumatera Utara 2014”, BPS Statistics of Sumatera Utara Province
The population of North Tapanuli Regency, where the project is located, is estimated at 286,000 persons.
(4) Poverty Ratio
The poverty ratio of North Sumatra Province is shown in Table 2.1.7. As shown in the table, the poverty
ratio of the province decreased from 15.66% in 2006 to 10.06% in 2013. The poverty ratio of the province
is slightly lower than that of the national average as shown in Table 2.1.2.
Table 2.1.7 Poverty Ratio of North Sumatra Province
Source: “Statistik Daerah Provinsi Sumatera Utara 2014”, BPS Statistics of Sumatera Utara Province
According to statistics, the poverty ratio of North Tapanuli Regency in 2013 was 11.68% and the figure is
higher than that of the provincial average.
Total Area Number of Population Population Density
(km2) (person) (km
2)
01. Nias 98,032 133,388 136
02. Mandailing Natal 662,070 413,475 62
03. Tapanuli Selatan 4,353 268,824 62
04. Tapanuli Tengah 2,158 324,006 150
05. Tapanuli Utara 3,765 286,118 76
06. Toba Samosir 2,352 175,069 74
07. Labuhanbatu 2,561 430,718 168
08. Asaha n 3,676 681,794 185
09. Simalungun 4,369 833,251 191
10. Dairi 1,928 276,238 143
11. Karo 2,127 363,755 171
12. DeliSerdang 248,614 1,886,388 759
13. Langkat 6,263 978,734 156
14. Nias Selatan 1,626 295,968 182
15. Humbang Hasundutan 229,720 176,429 77
16. Pakpak Bharat 1,218 42,144 35
17. Samosir 243,350 121,924 50
18. Serdang Bedagai 1,913 605,583 317
19. Batu Bara 90,496 382,960 423
20. Padang Lawas Utara 3,918 232,746 59
21. Padang Lawas 389,274 237,259 61
22. Labuhanbatu Selatan 311,600 289,655 93
23. Labuhanbatu Utara 3,546 337,404 95
24. Nias Utara 1,502 129,053 86
25. Nias Barat Kota/City 54,409 82,854 152
71. Sib olg a 1,077 85,981 7983
72. Tanjungbalai 6,152 158,599 2578
73. Pematangsiantar 7,997 237,434 2969
74. Tebing Tinggi 3,844 149,065 3878
75. M ed an 26,510 2,123,210 8009
76. Bin j a i 9,024 252,263 2795
77. Padangsidimpuan 11,465 204,615 1785
78. Gunungsitoli 46,936 129,403 276
Sumatera Utara 71,681 13,326,307 186
Regency /City
Year 2005 2006 2007 2008 2009 2010 2011 2012 2013
% 14.68 15.66 13.9 12.55 11.51 11.31 11.33 10.67 10.06
Final Report
Preparatory Survey on North Sumatra Mini 2-6 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
2.1.3 ECONOMIC DEVELOPMENT POLICY OF INDONESIA
Indonesia’s economic policy is composed of the nation’s long-term plan entitled the National Long-term
Development Plan (Rencana Pembangunan Jangka Panjang Nasional: RPJPN 2005-2025) and
short-term implementation plan entitled the National Medium-term Development Plan (Rencana
Pembangunan Jangka Menengah Nasional: RPJMN). RPJPN 2005–2025 serves as the basis for
development programs for 20 years commencing from 2005 to 2025. In addition, RPJPN 2005-2025 also
serves as a guideline for the preparation of the National Medium-term Development Plan (RPJMN),
which is the development program for the next five years. The government formulates and enacts the
annual government action plan (Rencana Kerja Pemerintah: RKP). These economic policies formulated
by the central government are further segmented to sectoral midterm strategic plan (Renstra KL) and
implementation plan (Renja KL). The structure of the economic development plan of the country is
shown in Table 2.1.8.
Table 2.1.8 Indonesia Economic Policies
National Level Development Plan Regional (Province, Regency, City) Level
Development Plan Sectoral
Development Plan General
Development PlanSectoral
Development PlanGeneral
Development PlanLong-term Plan
(20 years) National Long-term
Development Plan (RPJP Nasional)
Regional Long-term development plan
(RPJP Daerah) Mid-term Plan
(5 years) Central Government
Strategic Plan (Renstra KL)
National Medium-term
Development Plan (RPJM Nasional)
Regional Sectoral Strategic Plan
(Renstra SKPD)
Reginoal Medium-term
Development Plan (RPJM Daerah)
Implementation Plan (1 year)
Central Government Implementation Plan (Renja KL)
National Implementation
Plan (RKP)
Regional Sectoral Implementation
Plan (Renja SKPD)
Regional gov. Implementation
plan (RKP Daerah)Source: “Outline of World Land Policy”, Ministry of Land, Infrastructure, Transportation and Tourism
(1) National Medium-term Development Plan (RPJMN)
The Government of Indonesia formulated the National Long-term Development Plan (RPJPN 2005-2025)
with the vision and mission of (i) development and self-sustainability, (ii) justice and democracy, and (iii)
peace and unity. Under these visions and missions, the main objectives of the RPJPN 2005-2025 are set
to strengthen the competitiveness of agriculture and industry by reinforcing production efficiency,
targeting annual household income of US$60,000 by 2025, and improving food self-sufficiency. The
National Medium-term Development Plan (RPJMN) was formulated every five years following the
context of the RPJPN 2005-2025. The current medium-term plan is in the third phase of the planning
horizon (2015-2019), and was enacted in January 2015. RPJPN 2005-2025 assigned the following four
standards as national development norms, and set the priority development policy, which includes human
development, development of prioritized industry, rectifying regional disparities, and fair development:
a. Improvement of quality of life for society and individual;
b. Improved efforts for welfare, prosperity, and productivity should not create widened inequality;
Final Report
Preparatory Survey on North Sumatra Mini 2-7 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
c. Special attention is given to lower and middle income people to improve their productivity without blocking, inhibiting, shrinking, and reducing their flexibility as major actors and continue to be agents of growth; and
d. Development activities must not impair or reduce the carrying capacity of the environment and the balance of the ecosystem.
RPJMN prioritizes infrastructure development in the sectors of energy and electricity, road, railway,
airport, marine port, water supply, and sewage. The necessary investment for these infrastructure
developments in five years is estimated to be US$45.80 billion, 50% of which (US$23 billion) needs to
be funded from non-governmental institutes such as the private sector.
(2) Master Plan for Acceleration and Expansion of Indonesia's Economic Development (MP3EI)
In May 2011, the Government of Indonesia announced the MP3EI as the center of the long-term plan
from 2010 to 2025. The plan aims to sextuplicate the current nominal GDP and for the country to be
ranked 10th in terms of GDP scale around the world by 2025. MP3EI adopts the basic vision of
development by creating a self-sufficient, advanced, just, and prosperous Indonesia; and the infrastructure
is focused on energy/electricity development, road construction, and railway construction, among others.
MP3EI sets six economic corridors, and assigns development targets for each corridor that aim to harness
the competitive advantages that are uniquely inherent in each of the six chosen corridors.
Source: KP3EI
Figure 2.1.1 Economic Corridors Set in MP3EI
The North Sumatra Mini Hydropower Project is located in North Sumatra Province and belongs to the
proposed Sumatra Economic Corridor in MP3EI. The development target of the corridor is to be a center
for production and processing of natural resources and as the nation’s energy reserve.
Final Report
Preparatory Survey on North Sumatra Mini 2-8 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
2.2 OVERVIEW OF THE POLICIES AND INSTITUTIONS OF THE INDONESIAN GOVERNMENT
2.2.1 POLICY AND INSTITUTIONS ON ELECTRIC POWER DEVELOPMENT
Indonesia's energy policy is established based on the National Energy Policy (Kebijakan Energi Nasional:
KEN) and the National Energy Total Plan (Rencana Umum Energi Nasional: RUEN). Under these
policies, the National Electric Power General Plan (Rencana Umum Ketenagalistrikan Nasional: RUKN)
and Electric Power Implementation Plan (Rencana Umum Penyediaan Tenaga Listrik: RUPTL) are
prepared as implementation plans of these energy policies. The National Energy Policy (KEN) was
revised in January 2014 and the target values for each electric power energy resource were set as follows:
- Oil: less than 25% by 2015 and less than 20% by 2050.
- Natural gas: more than 22% by 2025 and more than 24% by 2050.
- Coal: less than 30% by 2025 and less than 25% by 2050.
- Renewable energy: more than 23% by 2025 and more than 31% by 2050.
In addition, the electrification rate was targeted at 85% by 2015 and nearly 100% by 2020. Domestic
primary energy was planned to be utilized for domestic purposes as much as possible. As for a related
policy, the National Energy Management Blueprint (Blueprint Pengelolaan Energi Nasional: BP-PEN)
2006-2025 was established and national targets related to energy were set. Based on the policy stated in
KEN, the Ministry of Energy and Mineral Resources (MEMR) established the National Electric Power
General Plan (RUKN) for electric power sector, then PLN which is the Indonesian government-owned
corporation prepares the Electric Power Implementation Plan (RUPTL), and PLN is principal entity to
implement it. The RUPTL envisions ten years horizon; however, it is revised annually.
The laws on energy and power sector in Indonesia include: 1) Energy Law (2007), 2) Electric Power Law
(2009), 3) Decree on Save Energy (2009), and 4) Geothermal Power Law (2003). The Energy Law of
2007 prescribes the management and usage of all energy resources such as 1) management of energy
resources by the government, 2) achievement of stable energy supply, 3) acceleration of resources
development, 4) formulation of national energy policy and energy plan, and 5) promotion of renewable
energy use. The new power law (2009) is a revision of the old energy law enacted in 1985. The Power
Law stated that the government is responsible for power supply. However, the law enables public
enterprises, private enterprises, cooperatives, and civic groups to participate in the power generation
business aiming to improve power supply ability. RUKN and the revision of power tariff require
parliament approval. The decree on energy-saving regulates that energy saving is imposed on large
energy consumers. The geothermal law allows private investors to participate development of geothermal
projects including steam development and supply, and power generation through geothermal development.
The processes of getting permits and licenses in each phase of geothermal energy development have
become clear by the law.
Final Report
Preparatory Survey on North Sumatra Mini 2-9 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
2.2.2 ELECTRIC POWER DEVELOPMENT SYSTEM
As the administrative organization for the electricity sector, the formulation of the overall policy for the
development and use of energy is done by the National Energy Board ((Dewan Energi Nasional: DEN).
The Ministry of National Planning and Development (Badan Perencanaan Pembangunan Nasional:
BAPPENAS) manages the national project development policy and coordination. The MEMR is the
administrative organization for the entire energy sector including the power sector. The PLN and
state-owned enterprises are under the control of the Ministry of State-Owned Enterprise (MSOE), while
the Ministry of Finance (MOF) manages the budget.
The MEMR is the supervisory institution for the energy sector and performs management and regulation
of state-owned energy companies in addition to policy planning. The Directorate of Electricity in MEMR
acts as the electric power administrator of the electricity sector and plays the role of regulation and
supervision, including coordination of the formulation of policy, procedures, and standards. It is
responsible for the formulation of the National Electric Power General Plan (RUKN).
In 2010, MEMR has organized the Directorate of New and Renewable Energy and Save Energy
(DGNREEC) for the development of renewable energy. The geothermal section of the Directorate of
Minerals, Coal and Geothermal, and renewable section of the Directorate of Electricity were integrated
into the DGNREEC. In the power generation business in Indonesia, PT. PLN and its subsidiary
companies and independent power producers (IPPs) are carrying out power generation. For transmission
and distribution of electricity, PLN has monopoly.
The Java-Bali system has larger scale power generation and supply. Power generation is being undertaken
by PLN, its subsidiary companies such as Indonesia Power (IP), Pumbankit Jawa Bali (PJB), and IPPs.
Transmission and distribution of the Java-Bali system are managed by the Power Transmission and
Distribution Center (P3B Jawa Bali) and five distribution offices. In Sumatra, two generation units
supervise regional power generation. As for the transmission and distribution, the Sumatra Power
Transmission and Distribution Center (P3B Sumatra) and seven regional offices are doing these tasks. In
other areas, the regional branch offices are carrying out integrated operation of power generation,
transmission, and distribution.
Sumatra generation unit consists of the North Sumatra generation unit (abbreviated as Sumbagut or
KITSBU) and South Sumatra generation unit (abbreviated as Sumbagsel or KITSBS). These generation
units were established in 2004 as part of the reorganization of PLN generation and distribution unit.
Sumbagut’s service area covers Ache, North Sumatra, and Riau provinces, while that of Sumbagsel
covers West Sumatra, Jambi, Bengkulu, South Sumatra, and Lampung provinces. In 2014, net installed
capacity of Sumbagut was 1,463 MW and that of Sumbagsel was 2,127 MW.
2.2.3 POWER DEVELOPMENT PLAN
Based on the national energy policy, the MEMR established RUKN and consequently, the RUPTL is
Final Report
Preparatory Survey on North Sumatra Mini 2-10 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
prepared, and power development is carried out by PLN. The RUKN describes major development
policies as shown below.
(1) Power supply planning policy
• Support MP3EI (2011-2025 in the Indonesian accelerated and enlarged economic development master plan);
• Avoidance of lack of power supply;
• Sufficient energy reserves;
• Development of peak load power plants by gas, pumped storage power plant; and
• Competitive electricity tariff structure.
(2) Diversification of power source
• Enhancement in the use of new and renewable energy;
• Establishment of sustainable power supply system for various energy power sources; and
• Support of gas supply for gas power generation and storage of coal for coal-fired power generation as a reduction measure for oil-dependency of fuel.
The RUPTL is a ten-year plan, but due to actual delays of the plan and changes in conditions, it is
updated every year. It is a power development plan prepared based on the present situation. The power
development plan is established to satisfy the electricity demand which is forecasted with considering
future economic and population growths. Construction of the transmission and distribution networks is
planned in order to harmonize with the power development plan. Further, the required construction costs
for these electric power development and fuel costs required for operation are estimated.
(3) Crash Program
In order to overcome the power shortage, the Government of Indonesia formulated the power plant
expansion plan (first Crash Program) in July 2006, focusing on coal-fired steam power plant
development. In January 2010, the second Crash Program was formulated replacing the first Crash
Program. The second Crash Program is more focused on power source diversification and introducing
renewable energy rather than coal-fired power plant development. The projects listed in the first and
second Crash Programs are called as fast-track program (FTP) I and FTP II, respectively, and those
projects were regarded as high priority projects in the country. The outline of the first and second Crash
Programs is shown in Table 2.2.1.
Final Report
Preparatory Survey on North Sumatra Mini 2-11 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.2.1 Outline of Crash Program Item First Crash Program Second Crash Program
Development Plan Period (Initial)
2006-2009 2010-2014
Developer PLN: 100% PLN: 37.4%, IPP: 62.6% Developed Capacity 10,000 MW
10,000 MW Review in 2012 and 2013, with 18,000 MW as the target.
Purpose Emergency power development in Java-Bali system mainly - Reduction in dependence on oil
Emergency power supply development - Power source diversification - Utilization of renewable energy
Power Supply Configuration
Coal: 100% Renewable energy: 54% (Geothermal: 41%, Hydro: 13%) Fossil fuel: 46% (Coal: 36%, Gas: 1%, Combined Cycle: 9%)
Progress in 2014 Completed: 7,368 MW In progress: 2,439 MW
Completed: 55 MW In progress: 17,403 MW
Legal Basis Presidential Decree No.71/2006 Presidential Decree No.04/2010 Source: PLN
Both of these Crash Programs are experiencing significant delays, main reasons for which are delays in
land acquisition and numerous licensing/permission procedures. Projects in the first Crash Program were
mainly contracted with Chinese companies. However, many problems such as lack of cash for
construction have been reported. Moreover, there were many defective and insufficient rated output of
power generation equipment, even if they were completed.
Furthermore, the new 2014 president, Mr. Jokowi, announced his ambitious plan to develop a 35 GW
power plant over the next five years. The shares of each region and power source under the 35 GW
Power Development Plan are shown in Table 2.2.3 and Table 2.2.4, respectively.
Table 2.2.2 35 GW Power Development Plan (2015-2019)
No. Status of Process Owner Total
Capacity PLN IPP
1 Construction 4.2 3.2 7.4
2 Committed 2.9 4.3 7.2
3 Procurement 2.2 11.3 13.6
4 Plan 5.1 9.6 14.7
Total (incl. Construction) 14.4 28.5 42.9
(excl. Construction) 10.2 25.2 35.5 Source: PLN
Table 2.2.3 Share of Each Region under the 35 GW Power Development Plan (2015-2019) (Unit: GW)
Sumatra Jawa-Bali
Kaliman tan
Sulawesi MalukuNusa
Tenggara Papua Total
PLN 1.1 5 0.9 2 0.3 0.7 0.2 10.2
IPP 7.6 15.9 1 0.7 0 0 0.1 25.3
Total 8.7 20.9 1.9 2.7 0.3 0.7 0.3 35.5Source: PLN
Final Report
Preparatory Survey on North Sumatra Mini 2-12 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.2.4 Share of Each Source under the 35 GW Power Development Plan (2015-2019) (Unit: GW)
Steam
Steam (Mine
Mouth)
Gas/ Combined
Hydro Geo-
thermal Others Total
PLN 5.6 - 7.2 1.4 0.1 0.1 14.4
Extension 5.2 - - - - - 5.2
IPP 12.3 1.6 6.2 0.2 1.1 0.7 22.1
Captive - 1.2 - - - - 1.2
Total 23.1 2.8 13.4 1.6 1.2 0.8 42.9*)Source: PLN
2.2.4 ELECTRICITY TARIFF
Indonesia's electricity tariff has been kept low by government subsidies. However, in order to mitigate the
financial burden of the government, an increase in electricity tariff and reduction of subsidies were
approved by the parliament in 2013. The increase in electricity tariff is done gradually. The power cost
deficit, which cannot be covered by PLN’s income from electricity sales, is made up by government
subsidies. Government subsidies are calculated by the Ministry of Finance. By these subsidies, electricity
tariff has been kept to a low and stable level without the effect of fuel costs. Government subsidies were
Rp3-4 trillion in the early 2000s. After then, due to the rise in oil prices, the power generation fuel price
has also increased. Finally, government subsidies were increased to Rp101 trillion in 2013. In 2013,
although the average generation cost was Rp1,207/kWh, the average sold electric price is Rp818.4/kWh.
Electrical tariff was increased by about 15% in October 2013. In addition, electricity tariffs for industrial
use (large-demand customer) were changed from 01 May 2013. Tariff for the customer with contract
capacity of more than 200 kVA increased by 38.9% but this was implemented at 8.6% every two
months. For contract of more than 30,000 kVA, tariff increase is 64.7%, but was implemented at 13.3%
every two months. In November 2014, another price increase was conducted.
The revised tariffs are as follows:
Final Report
Preparatory Survey on North Sumatra Mini 2-13 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.2.5 Electricity Tariff of PLN (1/2)
Source : PLN
Basic Tariff
(Rp./kVA/month) Condition before2013 Oct.2013 Nov.2014
Social
S‐1/TR 220 VA (per month) 14800 14800 14800
Block I : 0 ‐ 30 kWh 123 123 123
Block II : 30 ‐ 60 kWh 265 265 265
Block III : > 60 kWh 360 360 360
Block I : 0 ‐ 20 kWh 200 200 200
Block II : 20 ‐ 60 kWh 295 295 295
Block III : > 60 kWh 360 360 360
S‐2/TR 1,300 VA 605 708 708
S‐2/TR 2,200 VA 650 760 760
S‐2/TR 3,500 VA‐200 kVA 755 900 900
Peak K x P x 605 K x P x 735 K x P x 735
Off peak P x 605 P x 735 P x 735
kVArh ‐ 925 925
Residential
Block I : 0 ‐ 30 kWh 169 169 169
Block II : 30 ‐ 60 kWh 360 360 360
Block III : > 60 kWh 495 495 495
Block I : 0 ‐ 20 kWh 275 275 275
Block II : 20 ‐ 60 kWh 445 445 445
Block III : > 60 kWh 495 495 495
R‐1/TR 1,300 VA 790 979 1352
R‐1/TR 2,200 VA 795 1004 1352
R‐2/TR 3,500 VA‐5,500 VA 890 1145 1352
Block I H1 x 890
Block II H2 x 1,380
Business
Block I : 0 ‐ 30 kWh 254 254 254
Block II : > 30 kWh 420 420 420
Block I : 0 ‐ 108 kWh 420 420 420
Block II : > 108 kWh 465 465 465
B‐1/TR 1,300 VA 790 966 966
B‐1/TR 2,200 VA‐5,500 VA 905 1100 1100
Block I H1 x 900
Block II H2 x 1,380 1352 1352
Peak K x 800 K x P x 1,020 K x P x 1,020
Off peak 800 P x 1,020 P x 1,020
kVArh ‐ 1117 1117
13521352
900 VA 26500
23500450 VA
B‐3/TM more than 200 kVA
Customer/
CategoryContract Voltage
Usage Tariff(Rp./kWh)
450 VA 10000
900 VA
B‐1/TR
B‐1/TR
B‐2/TR 6,600 VA‐200 kVA
R‐1/TR
R‐3/TR more than 6,600 VA
900 VA 20000
S‐3/TM more than 200 kVA
R‐1/TR 11000less than 450 VA
S‐2/TR
S‐2/TR 15000
Final Report
Preparatory Survey on North Sumatra Mini 2-14 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.2.5 Electricity Tariff of PLN (2/2)
Notes, 1) K : Factor for cost between peak and off-peak in each system (region) decided by PLN (1.4 < K < 2.0)
2) P : Factor for social building, (Pure social building : 1.0, General social building : 1.3 ) 3) kVArh : If monthly average power factor is less than 85%, electric tariff for kVarh is added. 4) H1 : National average % saving on Lighting Time x Connected Power (kVA) 5) H2 : Energy consumption - H1 6) Q : Factor depending on commercial use and non-commercial use decided by PLN (08 < Q < 2.0)
Source: PLN
2.2.5 BUDGET AND FINANCIAL SOURCES
Budget for electric power business basically depends on PLN as the national executing agency and IPP
as the private investor. Income of PLN is composed of electricity sales and government subsidy, and
expenditure is composed of the purchase cost of electricity from IPP, fuel costs, maintenance costs, labor
costs, and depreciation cost. The electricity tariffs are decided by MEMR and should obtain the approval
Condition before 2013 Oct.2013 Nov.2014
Industry
Block I : 0 ‐ 30 kWh 160 160 160
Block II : > 30 kWh 395 395 395
Block I : 0 ‐ 72 kWh 315 315 315
Block II : > 72 kWh 405 405 405
I‐1/TR 1,300 VA 790 930 930
I‐1/TR 2,200 VA 905 960 960
I‐1/TR 3,500 VA‐14 kVA 915 1112 1112
Peak K x 800 K x P x 972 K x P x 972
Off peak 800 P x 972 P x 972
kVArh ‐ 1057 1057
Peak K x 680 K x P x 803 K x P x 1,115
Off peak 680 P x 803 P x 1,115
kVArh ‐ 864 1200
Peak & Off Peak 605 723 1191
kVArh ‐ 723 1191
Government Office & Public Use
P‐1/TR 450 VA 20000 575 575 575
P‐1/TR 900 VA 24600 600 600 600
P‐1/TR 1,300 VA 880 1049 1049
P‐1/TR 2,200 VA‐5,500 VA 885 1076 1076
H1 x 885
H2 x 1,380 1352 1352
Peak K x P x 750 K x P x 947 K x P x 1,115
Off peak P x 750 P x 947 P x 1,115
kVArh ‐ 1026 1200
P‐3/TR 997 1352
Railway
Peak K x 390 K x 483 K x 483
Off peak 390 483 483
kVArh ‐ 808 808
Bulk Use for Large Custome r
Peak & Off Peak K x 445 Q x 707 Q x 707
kVArh 445 Q x 707 Q x 707
Emergency/Multipurpos e
L/TR, TM, TT 1450 1650 1650
Contract VoltageCustomer/
Category
UsageTariff(Rp./kWh)
26000450 VAI‐1/TR
31500
Basic Tariff
(Rp./kVA/month)
6,600 VA‐200 kVAP‐1/TR
P‐2/TM more than 200 kVA
900 VAI‐1/TR
14 kVA‐200 kVAI‐2/TR
I‐4/TT more than 30 MVA
more than 200 kVAI‐3/TM
23,000 (30,950
after 2013)
T/TM more than 200 kV
more than 200 kVC/TM 30000 ( 0 after
2013)
Final Report
Preparatory Survey on North Sumatra Mini 2-15 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
of the parliament.
IPP investors invest in the construction and operating costs and its return to investment is through the
selling price to PLN. To cope with the rapid growth of electricity demand, the construction costs of the
power plants, transmission lines, and distribution grids are covered by official funds as bilateral/
multilateral aid funds or official development assistance (ODA) funds through the Indonesian
government, funds of the Government of Indonesia, and PLN’s own funds. However, because of the lack
of official funds, use of private funds like IPP development such as export credit prepared by the
contractor/supplier and finance from banks has increased.
Government subsidies are compensating the deficit amount not covered by the income from the PLN
electricity fee. Subsidy amount is calculated based on the decree of the Ministry of Finance. If the
electricity sales price is lower than the generation cost in each category, PLN can receive the difference
in the amount as subsidy. The stable electric tariffs are being realized by this system without relation to
the fluctuation of fuel cost. However, progressively revising the electrical tariff to mitigate the financial
burden is aimed at reducing subsidies. Subsidy amount from 2008 to 2013 is shown in Table 2.2.6 below.
Table 2.2.6 Subsidy from the Government to PLN Year 2008 2009 2010 2011 2012 2013
Subsidy (Rp10^12) 78.6 53.7 58.1 93.2 103.3 101.2 Source:PLN Statistics 2013
As reference, generation costs of each power source are shown in Table 2.2.7.
Table 2.2.7 Power Generation Cost by Sources
Source:PLN Statistics 2013
2.2.6 ACCELERATION OF PRIVATE INVESTMENT AND DEVELOPMENT
As described above, in order to cope with the rapid growth in electricity demand, construction of power
plants is necessary; however, there is a limitation of official funds to cover the said costs. Investment
Final Report
Preparatory Survey on North Sumatra Mini 2-16 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
and development in the power sector through private funds are being enhanced. In 2013, about 24%
of electric power was supplied through IPPs. In the second Crash Program, which is currently in
progress, out of the 79 projects in total, with a capacity of 17,918 MW, 59 projects with 12,169 MW
capacity are IPP projects. Also, of the 35 GW power scheduled for completion by 2019, about 25.3 GW
are from IPP projects.
In order to enhance the development of small hydropower plants with less than 10 MW by private
investors, the Indonesian government provided the FIT system and set the electricity price somewhat
higher. Due to the requested large amount of equity and fund for small hydropower plant, IPPs and
numerous private investors showed interest and submitted IPP proposals to PLN. On the other hand, for
medium and large power projects of more than 10 MW, MEMR indicated the standard purchase prices
from IPP in the ministry decree for enhancement of private investment. In addition, due to complaints
received from the investors on the complicated and needed steps to get permits and licenses, the
Government of Indonesia opened and launched a one-window process system named as Pelayanan
Terpadu Satu Pintu (PTSP) PUSAT in the Investment Coordinating Board (Badan Koordinasi
Penanaman Modal: BKPM) in January 2015. Its purpose is to mitigate and speed up the process of
investment. As shown in Figure 2.2.1, application and acquisition of various permissions and licenses
such as Izin Lokasi (permission of land acquisition) by local government, electricity business license (Izin
Usaha Penyedia Tenaga Listrik: IUPTL) by MEMR, and power purchase agreement (PPA) by PLN are to
be done at BKPM.
The Government of Indonesia has put in place several incentive policy programs in order to promote
renewable energy development, which include the following:
• Income Tax:Developers can obtain 5% reduction in the income tax rate of its investment each year for a period of six years.
• Accelerated Depreciation:Depreciation of fixed assets can be completed within ten years; hence, reduce the income tax.
• Incentives for Foreign Companies:Income tax on dividends of foreign investors can be 10%.
• Import Duty:The import duty is exempted for equipment and machinery that cannot be procured in Indonesia.
Final Report
Preparatory Survey on North Sumatra Mini 2-17 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: BKPM
Figure 2.2.1 BKPM One Stop Service Related to Power Generation Business
One Stop Service Centeral Level
BKPM
PLN
MEMR
Min. of Finance
National Land Agency
One Stop Service Provincial
One Stop Service
Regency Level
1. Principle Permit/IUPL2. APIP (Inatrade)3. Import Duty Facility (DBC)*4. NIK (DBC)*5. Business Permits for Electricity Provision (IUPTL)6. Operation Permits7. Establishment of Business Area*on‐line by investor
1. RUPTL2. Procurement (Bidding, Direct Selection & Direct Appointment)3. PPA4. Financial Date
1. Registration SLO (Certificate Feasibility Operations) online
1. Letter of guarantee of feasibility
1. Technical Considerations2. Procurement of land (implementation stage)3. Certification
Min. of Forest &
Environment
Min. of transportation
Min. of Economy
MIn. of Manpower
Min. of PublicWorks
1. IPKH2. AMDAL
1. Permit Special Terminal2. Permits Navigation3. Permit Railroad Crossing
1. Persetujuan PKLN
1. IMTA2. Boiler Operator License3. Permission transport aircraft4. Permit Lightning5. Health and Safety at Work Permit PLN
1. Permission Dam2. Construction Permit
Local Govenment
1. Letters of support from local government* If the location of cross‐district / city permit required provincial level Locations
Local Govenment
1. IMB (Regency / City) 3. Permit Location (Regency / City) 5. TDP2. Environmental Permit 4. Permit Disorders
INVESTO
R
Final Report
Preparatory Survey on North Sumatra Mini 2-18 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
2.3 CURRENT STATUS OF DEVELOPMENT POLICY FOR PROMOTION OF PRIVATE SECTOR PARTICIPATION ON SMALL HYDROPOWER BUSINESS
2.3.1 REGULATION OF THE MINISTRY OF ENERGY AND MINERAL RESOURCES
(1) Procedures for Small Hydropower Development
Indonesia is currently promoting private sector investment for small hydropower development through the
FIT system. The legal basis for this policy is the Regulation of the Minister of Energy and Mineral
Resources of Indonesia –Number 12 of 2014 (2 May 2014).
Private companies that apply for generation business through the FIT system need to submit the
following documents with their application prior to business commencement:
a. Overview of the company;
b. License documents based on laws and regulations from the government and local government;
c. Result of the pre-FS study confirmed by PLN;
d. Expected total investment amount;
e. Construction schedule until the commercial operation date (CoD);
f. Documents showing that land is available for the project;
g. Confirmation letter to make a deposit of 5% of the total investment amount within 30 business days after the decision of the business owner;
h. Document confirming the implementation of PPA issued by PLN; and
i. Confirmation letter that accepts the above conditions.
The project will follow the appraisal and approval processes based on these documents. This process
aimed to sort out the problematic projects and promote moving projects. The procedure for the
development process is presented in Figure 2.3.1:
Final Report
Preparatory Survey on North Sumatra Mini 2-19 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: Nippon Koei
Figure 2.3.1 Procedure for Small Hydropower Development
(2) Negative List
The latest version of the Investment Negative List, which entered into effect on 24 April 2014,
clarifies the situation regarding foreign direct investment (FDI) in the mini hydro sector. Under the
previous version of the list, such investment was stated as being 100% open to FDIs subject to a
“partnership arrangement” with a local firm.
However, as it was unclear what precisely was meant by a “partnership arrangement,” this tended to
discourage foreign investors. By contrast, the regulation states that the small hydro sector is now open up
to 49% FDI.
(3) Issues on Process of Appraisal and Approval
The current issues on the process of appraisal and approval for small hydro IPPs can be identified as
follows:
・ When a developer has an issue on debt financing, the developer recognizes that the period from the agreement of PPA to financial closure is short.
・ When the viability of a project has an issue on revenue and power tariff, the schedule for the feasibility study may be delayed.
・ A developer identified the need for PLN and MEMR to strengthen their coordination in providing a clear direction for the application of the regulations such as PPA.
years years
Final Report
Preparatory Survey on North Sumatra Mini 2-20 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
2.3.2 PPA AND POWER TARIFF
In 2012, the MEMR issued t h e Ministry Decree No.4/2012 and fixed the purchase price of renewable
energy, which is aimed to enhance the development of renewable energy. Further, in 2014, a revision on
the portions of small hydropower was made through the Ministry Decree No.12/2014, and PLN has to
purchase power at a fixed price from small-scale IPPs having less than 10 MW. The Ministry Decree
No.12/2014 clearly shows procedures necessary for implementing small hydropower projects such as
required documents, permits, approvals, and necessary period. The fixed purchase price was increased in
the Ministry Decree No.12/2014, and the price was again raised in the Ministry Decree No.22/2014. In
the Ministry Decree No.22/2014, the fixed price was newly set for the project that harnesses existing
weir/dam facilities for small hydropower development.
In July 2015, the Ministry Decree No.19/2015 was issued and the FIT fixed price was again increased and
linked to US dollars. Now, the FIT fixed price is set to US dollars and the payment is made by Indonesian
rupiah. The fixed purchase price is US¢12.00/kWh for the first eight years and US¢7.5/kWh for the
succeeding period up to 20 years. These fixed prices shall be multiplied by the regional coefficient. The
fixed purchase prices are shown in Table 2.3.1 below.
Table 2.3.1 Power Purchase Price for Small Hydropower Project
Voltage/Capacity Feed-In-Tariff (US¢/kWh)
F Factor, depending on the location General Small Hydro Projects
Medium Voltage
(up to 10 MW)
Year 1 - 8 : 12.00 x F Java, Bali and Madura: 1.0 Sumatra: 1.1 Kalimantan and Sulawesi: 1.2 West and East Nusa Tenggara: 1.25 Maluku and North Maluku: 1.3 Papua and West Papua: 1.6
Year 9 - 20 : 7.50 x F
Low Voltage
(up to 250 kW)
Year 1 - 8 : 14.40 x F
Year 9 - 20 : 9.00 x F Source: Regulation of the Minister of Energy and Mineral Resources of Indonesia No. 19/2015
Table 2.3.2 below summarizes the FIT currently applicable to small hydropower projects utilizing
existing structures.
Table 2.3.2 Power Purchase Price for Small Hydropower Project Utilizing
Existing Structures
Voltage/Capacity
Feed-In-Tariff (US¢/kWh)
F Factor, depending on the location Small Hydro Projects Utilizing
Multipurpose Dams and/or Irrigation
Medium Voltage
(up to 10 MW)
Year 1 - 8 : 10.80 x F Java, Bali and Madura: 1.0 Sumatra: 1.1 Kalimantan and Sulawesi: 1.2 West and East Nusa Tenggara: 1.25 Maluku and North Maluku: 1.3 Papua and West Papua: 1.6
Year 9 - 20 : 6.75 x F
Low Voltage
(up to 250 kW)
Year 1 - 8 : 13.00 x F
Year 9 - 20 : 8.10 x F Source: Regulation of the Minister of Energy and Mineral Resources of Indonesia No. 19/2015
Final Report
Preparatory Survey on North Sumatra Mini 2-21 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Small hydropower projects under operation or the projects that have already concluded their contracts can
apply the tariff shown in Table 2.3.3.
Table 2.3.3 Power Purchase Price for Small Hydropower Project Under Operation or
Already Contracted PPA
Voltage/Capacity Feed-In-Tariff (US¢/kWh)
F Factor, depending on the location General Small Hydro Projects
Medium Voltage
(up to 10 MW) Year 1 - 20 : 9.30 x F
Java, Bali and Madura: 1.0 Sumatra: 1.1 Kalimantan and Sulawesi: 1.2 West and East Nusa Tenggara: 1.25 Maluku and North Maluku: 1.3 Papua and West Papua: 1.6
Low Voltage
(up to 250 kW) Year 1 - 20 : 11.00 x F
Source: Regulation of the Minister of Energy and Mineral Resources of Indonesia No. 19/2015
The salient features of the power tariff can be described as follows:
(1) No Escalation
The FIT regulation explicitly states that the prescribed FIT prices, as set out above, are not subject to any
escalation. The existence of this provision will prohibit parties to agree on any tariff escalation/indexation
in the PPA. Consistent with this restriction, the standard PPA as published by PLN does not provide for
any escalation mechanism. However, as the FIT price is on US dollar basis, the escalation risk becomes
less than that of the rupiah-based tariff.
(2) Transmission
The FIT price needs to include the costs of procuring the transmission lines connecting the plant to the
PLN grid. Accordingly, hydro plants that are located close to an adjacent grid will be at a significant cost
advantage. On the other hand, if the transmission line is long, a project has more exposure to land
acquisition risks and will be less competitive.
(3) Transitional Arrangement
Prices agreed for power supplied by small hydro plants prior to the coming into effect of the regulation
will continue to be governed by MEMR’s Regulation No.04/2012, No.12/2014, and No.19/2015.
However, prices may be adjusted upwards (except in the case of a plant that has reached the
commissioning stage) provided the project sponsor first secures a designation by the directorate as
hydropower producer. Such adjustment will be based on an agreement between PLN and the project
sponsor, but may not be higher than the weighted average price set out in the regulation, which is adjusted
based on voltage and location. The new price is fixed and must be directly set out in a PPA. It remains valid
for the duration of the PPA. The price adjustment process must be completed within 90 working days
upon the designation of the project sponsor as a hydropower producer. The adjusted price must also be
approved by the minister.
Final Report
Preparatory Survey on North Sumatra Mini 2-22 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(4) Hydropower Plants of More than 10 MW
The power tariff from hydropower plants of more than 10 MW is stipulated in the MEMR’s Regulation
No.03/2015. The power tariff is charged at a maximum of US¢9.00/kWh for 10 MW to 50 MW,
US¢8.50/kWh for 50 MW to 100 MW, and US¢8.00/kWh for more than 100 MW. The purchase price
is subject to the agreement between PLN and the developer.
2.3.3 REVISION OF PPA
PLN is currently revising the template of the PPA. The contents appear to be slightly modified compared
with the previous version. Out of the 315 projects that submitted their application, approximately half of
them have already signed the PPA. The major points can be identified and reviewed as follows:
(1) Termination of Agreement
The clause stipulates the conditions for contract termination. It raises the event when the buyer (PLN)
fails to make payment for three months. On the other hand, the penalty payment for PPA termination is
not mentioned. The event can be covered by the Civil Law of Indonesia (Clause No.1243), which
stipulates the claim for damages due to non-fulfillment of obligation.
(2) Supplemental Document
The PPA requires a certificate of cash deposit of 30% of the paid-in owned capital. This condition would
raise the hurdle for developers, and the developers may wish to discuss the condition.
2.3.4 PERMISSION/LICENSE REQUIRED FOR SMALL HYDROPOWER BUSINESS
In addition to the establishment of a special purpose company (SPC), the permissions and licenses
required for small hydropower business are as follows:
Table 2.3.4 Permission/License for Small Hydropower Business
No. Name Type Licenser
1 Izin Princip Development permission Local government
2 UKL and UPL Environmental permission Local government
3 Izin Lokasi Land acquisition license Local government
4 HGB Land register Local government
5 IMB Construction permission Local government
6 HO Obstacle permission Local government
7 SIPTPP River use permission River administrator
8 SIPPA Water use permission River administrator
9 HPO*) (Hydropower Operation License) Hydropower plan permission MEMR (EBTKE)
Final Report
Preparatory Survey on North Sumatra Mini 2-23 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
10 IUPTLS Provisional electricity license MEMR (Kelistrikan)
11 IUPTL Electricity business license MEMR (Kelistrikan)
*) Tentative name because there is no official name Source: ESDM
• No.1 to No.8 can be processed in parallel and the period is estimated to be around nine months.
• No.2 (UKL and UPL) is usually prepared during the pre-FS stage.
• After No.3 (Izin Lokasi), land acquisition is carried out and then HGB is obtained.
• For application of No.9 (HPO), No.1, pre-FS report and No.3-N.8 are required.
In case that the project area includes public forest, Izin Penggunaan Kawasan Hutan (Forest Use
Permission) from the Ministry of Forest is required.
2.3.5 DEVELOPMENT STATUS OF SMALL HYDROPOWER
(1) Hydropower Potential
In 1999, World Bank conducted a study4 to identify the hydropower potential in Indonesia. In the study,
hydropower potential amounting to 22.0 GW passed the third screening including planning and
implementation. Furthermore, the Indonesia Hydropower Master Plan in 2011 estimated that a potential
capacity of 14.6 GW will be implemented until 2027. According to RUPTL (2015-2024), the potential of
renewable energy is as follows:
Table 2.3.5 Renewable Energy Potentials
No. New and Renewable
Energy Potential
1 Geothermal 29,164 MW
2 Hydro 75,000 MW
3 Biomass 49,810 MW
4 Solar Power 4.80 kWh/m2/day
5 Wind Power 3-6 m/s
6 Ocean 49 GWSource:RUPTL 2015-2024
Table 2.3.6 Development Plan of Renewable Energy
*Megawatt Peak: Watt value under the standard condition Source: RUPTL 2015-2024
4 World Bank: “Hydro Inventory and Pre-Feasibility Study”, 1999
No Power Type Unit 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Total
1 Mini Hydro MW 67 40 156 172 123 135 272 297 130 150 1,542
2 Solar MWp* 6 20 25 30 35 35 35 40 45 50 321
3 Wind MW ‐ 40 40 40 40 40 50 50 50 50 400
4 Biomass MW 15 30 40 50 50 50 50 50 50 50 435
5 Ocean MW ‐ 1 1 3 3 5 5 5 5 10 38
Total MW 88 131 262 295 251 265 412 442 280 310 2,736
Final Report
Preparatory Survey on North Sumatra Mini 2-24 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The accumulated planned generating capacity for each generation type is shown in Figure 2.3.2. As
shown in the figure, the small hydropower has important role for renewable energy development as it has
56% of the planned renewable energy development.
Source: RUPTL 2015-2024
Figure 2.3.2 Planned Accumulated Renewable Energy Generation Capacity
In the JICA study, namely, “Survey for Enhancement of Private Sector Investment on Small Hydropower
IPP Projects in Indonesia”(2015), it was reported that there were 318 small hydropower projects that
submitted their application for selling electricity with the FIT price system. The status of the 318 projects
is as follows: 49 projects are under operation, 49 projects are under construction, and 220 projects are at
the stage before financial closure.
0
500
1,000
1,500
2,000
2,500
3,000
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
Accumulative
Additional Capacity
(MW)
Year
Ocean
Biomass
Wind
Solar
Mini Hydro
Final Report
Preparatory Survey on North Sumatra Mini 2-25 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.3.7 Status of Small Hydropower Development (As of February 2015)
Source: PLN
2.3.6 ISSUES ON SMALL HYDROPOWER DEVELOPMENT
As a result of the introduction of FIT for small hydropower sector, and further increasing FIT fixed price
linked to US dollar, small hydropower development becomes an attractive business for small hydropower
developers. On the other hand, it is recognized that small hydropower business promotion is always
associated with various risks such as construction risk. According to the JICA study on the “Survey for
Enhancement of Private Sector Investment on Small Hydropower IPP Projects in Indonesia” (2015), the
following risks are described for small hydropower development:
(1) Construction Risk
The construction risk, which may have the most significant impact on the profitability of the project, is
affected by the initial capital expenditure (CAPEX) for the construction of the IPP facilities because the
revenue side of the cash flow is practically assured under the FIT system. It should be noted that
insufficiency in feasibility study (FS), basic/detailed design, and capability of contractor cause serious
problems of cost overrun of the construction. Particularly in Indonesia, this risk is relatively higher than
in the developed countries. Well prepared FS and basic/detailed design, and careful selection of high
quality contractor are indeed important to mitigate the risk.
For the contract form, the lender generally prefers the EPC full turnkey contract as this type of contract
transfers all risks of cost and construction time to the contractor and does not allow the contractor to
recover cost overrun and modify the completion date.
Status Number Capacity (kW)
Indonesia Timur 84 305,720
Operation 21 59,840
Construction 11 39,700
Financing Proces 7 32,700
PPA Process 21 88,330
Proposal 24 85,150
Jawa Bali 114 413,885
Operation 17 17,870
Construction 15 60,070
Financing Proces 10 62,620
PPA Process 33 111,206
Proposal 39 162,119
Sumatera 120 713,730
Operation 11 37,625
Construction 23 156,458
Financing Proces 26 162,948
PPA Process 27 185,700
Proposal 33 170,999
Grand Total 318 1,433,335
Final Report
Preparatory Survey on North Sumatra Mini 2-26 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
However, as private sector infrastructure projects are financed through corporate finance scheme, and the
construction contract is generally a unit price contract, payment is made by the actual quantity with unit
price. The JICA Survey Team interviewed the contractors in Indonesia, and it was found out that the EPC
contract in Indonesia is generally a unit price contract although it is stated as an EPC contract.
(2) Drought, Flood, and Discharge Risks
In order to ensure the revenue in the cash flow projection, it is important to take into account the drought,
flood, and other discharge risks in small hydropower IPP projects. Sometimes, sufficient discharge data
may not be available in small rivers for small hydropower IPPs, and practical treatment should be made
on a case-by-case basis by referring to similar projects. Engineering analysis with regard to the discharge
risks is important, but it is also worth considering a financial solution such as increasing the provision for
the debt service reserve account in order to cover the drought risk for one or two years.
(3) Other Risks
Other risks associated with the small hydropower development are as follows:
- Risks related to PPA to be signed with PLN;
- Sponsor risks of the developers;
- Legal risks for real estate-related contract, water utilization and other licenses including those by the local government;
- Environmental and social risks; and
- Ability to properly respond to an accident or natural disaster.
2.4 STATUS OF POWER SUPPLY AND POWER DEVELOPMENT PLAN IN NORTH SUMATRA
2.4.1 CURRENT STATUS OF POWER SUPPLY IN NORTH SUMATRA
(1) Outlook of Power Supply and Demand in North Sumatra
The current power grid of North Sumatra, which consists of 150 kV and 275 kV transmission lines, is
connected to the neighboring provinces of Ache and Riau via the 150 kV transmission line. The power
grid and existing and planned power stations are shown in Figure 2.4.1.
Final Report
Preparatory Survey on North Sumatra Mini 2-27 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: RUPTL 2015-2024
Figure 2.4.1 Power Grid and Existing and Planned Power Stations
PLN’s power stations in North Sumatra are under the control of North Sumatra Generation Unit
(Sumbagut). The power supply system of Sumbagut is divided into six power sectors, where four of them
cover the power supply for North Sumatra. The power sector in North Sumatra Generation Unit is shown
in Figure 2.4.2.
Final Report
Preparatory Survey on North Sumatra Mini 2-28 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: Website of PT PLN (Persero) Pembangkitan Sumatera Bagian Utara
http://www.pln.co.id/kitsbu/wilayah-kerja/
Figure 2.4.2 Power Sector in North Sumatra Generation Unit
The power sectors that cover North Sumatra are Belwan, Medan, Pandan, and Labuhan Angin. The
capital of North Sumatra is Medan, and the population of the city is ranked fourth in the entire Indonesia.
The city consumes 60% of the total electricity demand in North Sumatra. According to RUPTL, the rapid
demand growth of Medan leads to power supply deficit in the region, and PLN has to limit the number of
new demand connections to suppress the demand growth. RUPTL 2015-2025 describes another issue of
power supply that there is a problem of low quality of electricity supply due to voltage drop. RUPTL
explained that the length of the distribution line is too long to stabilize the voltage.
In order to overcome these situations, RUPTL explained that urgent power station construction is
necessary to catch up with the growing demand and by constructing 150 kV line to stabilize the voltage.
(2) Power Demand in North Sumatra
According to RUPTL 2015-2024, the peak electricity demand in North Sumatra reaches to 1,450 MW and
the power is supplied by power stations controlled by the four power sectors as well as interchange from
Ache and the private sector such as PT. Inarum. Small hydropower stations, geothermal IPPs, and other
small-scale IPPs supply electricity through the distribution line (22 kV).
According to PLN statistics, the electric energy consumption in North Sumatra in 2014 is estimated to be
8,271 GWh, and the electric energy consumption by type of users is shown in Table 2.4.1.
Final Report
Preparatory Survey on North Sumatra Mini 2-29 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.4.1 Electric Energy Consumption by Type of Users in North Sumatra in 2014
Source: PLN Statistics 2014
(3) Power Supply Capacity in North Sumatra
Power stations that are currently being operated in North Sumatra are shown in Table 2.4.2. As shown in
the table, the installed capacity of the power stations in North Sumatra is 2,487.2 MW, but the net
capacity, which is effective capacity for power supply, is reduced to 1,872.4 MW. Considering that the
peak demand in 2014 was 1,450 MW and net power supply capacity was 1,872.4 MW, the reserve margin
is calculated at 29%. According to RUPTL 2015-2024, PLN targets the Loss of Load Probability (LOLP)
at 0.274% and this requires 35% of reserve margin. The current reserve margin of 29% does not satisfy
the PLN target and securing reserve capacity is also an issue on the PLN’s power generation expansion
plan.
Residential Industrial Business SocialGov. Office
Building
Public Street
LightsTotal
Energy Consumption
(GWh)4,177 2,094 1,252 255 97 396 8,271
Ratio (%) 50.5% 25.3% 15.1% 3.1% 1.2% 4.8% 100%
50.5%
25.3%
15.1%
3.1% 1.2% 4.8%
Residential
Industrial
Business
Social
Gov. Office Building
Public Street Lights
Energy Consumption by Type of Customer
Final Report
Preparatory Survey on North Sumatra Mini 2-30 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.4.2 Power Stations Currently Operated in North Sumatra
Source: RUPTL 2015-2024
Powerstations Type Type OwnerInstalled Capacity
(MW)
Net Capacity
(MW)
I BELAWAN SECTOR 1527.3 1092.4
1 PLTU Belawan #1 PLTU HSD PLN 65 40
2 PLTU Belawan #2 PLTU HSD PLN 65 32.5
3 PLTU Belawan #3 PLTU HSD PLN 65 33.5
4 PLTU Belawan #4 PLTU HSD PLN 65 44.4
5 PLTGU Belawan GT 1.1 PLTGU HSD PLN 117 81
6 PLTGU Belawan GT 1.2 PLTGU HSD PLN 128.8 81
7 PLTGU Belawan ST 1.0 PLTGU HSD PLN 149 50
8 PLTGU Belawan GT 2.1 PLTGU HSD PLN 130 118
9 PLTGU Belawan GT 2.2 PLTGU HSD PLN 130 100
10 PLTGU Belawan ST 2.0 PLTGU HSD PLN 162.5 112
11 PLTG Belawan (TTF) PLTG HSD PLN 120 70
12 PLTMG Belawan PLTG HSD Lease 40 40
13 PLTD Sewa Belawan MFO PLTD MFO Lease 120 120
14 PLTD Sewa Tersebar 150 MW (BIO FUEL) PLTD HSD Lease 150 150
15 PLTD Sewa Glugur 20 MW PLTD HSD Lease 20 20
II MEDAN SECTOR 225.8 192.2
1 PLTG Glugur (TTF) PLTG HSD PLN 11.9 11
2 PLTG Paya Pasir #7 (TTF) PLTG HSD PLN 34.1 34
3 PLTD Titi Kuning #1 PLTD HSD PLN 4.1 2.5
4 PLTD Titi Kuning #2 PLTD HSD PLN 4.1 2
5 PLTD Titi Kuning #3 PLTD HSD PLN 4.1 2.5
6 PLTD Titi Kuning #4 PLTD HSD PLN 4.1 3
7 PLTD Titi Kuning #5 PLTD HSD PLN 4.1 2.5
8 PLTD Titi Kuning #6 PLTD HSD PLN 4.1 2.7
9 PLTD Sewa Paya Pasir (Arti Duta) PLTD HSD rent 30 11
10 PLTD Sewa Paya Pasir #2 (BGP) PLTD HSD rent 40 40
11 PLTD Sewa Paya Pasir #3 (BUGARAWA) PLTD HSD rent 20 16
12 PLTD Sewa Belawan (AKE) PLTD HSD rent 65 65
III PANDAN SECTOR 139.6 125
1 PLTMH Total PLTA Air PLN 7.6 5
2 PLTA Sipansihaporas #1 PLTA Air PLN 33 33
3 PLTA Sipansihaporas #2 PLTA Air PLN 17 17
4 PLTA Lau Renun #1 PLTA Air PLN 41 30
5 PLTA Lau Renun #2 PLTA Air PLN 41 40
IV LABUHAN ANGIN SECTOR 230 120
1 LABUHAN ANGIN # 1 PLTU Batubara PLN 115 50
2 LABUHAN ANGIN # 2 PLTU Batubara PLN 115 70
V IPP 180 170
1 Asahan I.1 PLTA Air IPP 90 85
2 Asahan I.2 PLTA Air IPP 90 85
VI Lease from Inalum and Excess Power 184.5 172.8
1 INALUM PLTA Air rent 90 90
2 PLTP SIBAYAK PLTP GEO rent 10 3
3 PLTMH Parlilitan PLTA Air rent 7.5 8
4 PLTMH Sei Silau 2 PLTA Air rent 8 8.8
5 PLTMH Parluasan PLTA Air rent 5 5
6 PLTMH Hutaraja PLTA Air rent 5 5
7 PLTMH KARAI 13 PLTA Air rent 5 5
8 PT GSI‐1 (Excess Power) PLTD HSD rent 6 ‐
9 PT GSI‐2 (Excess Power) PLTD HSD rent 9 9
10 PT Pertumbuhan Asia (Excess Power) #1 PLTD HSD rent 10 10
11 PT Pertumbuhan Asia (Excess Power) #2 PLTD HSD rent 10 10
12 PT Inalum Porsea (Excess Power 2 MW) PLTD HSD rent 2 2
13 PT Nubika (Excess Power GI R. Prapat) PLTD HSD rent 6 6
14 PT Victorindo (Excess Power GI Sidempuan) PLTD HSD rent 5 5
15 PT Harkat Sejahtera (GI P.SIANTAR) PLTD HSD rent 1 1
16 PTPN III Sei Mangkai (GI KISARAN) PLTD HSD rent 3 3
17 PT Evergreen (Excess Power GI T. Morawa) PLTD HSD rent 2 2
Total 2487.2 1872.4
Final Report
Preparatory Survey on North Sumatra Mini 2-31 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The abbreviations of power generation type shown in Table 2.4.3 are as follows:
Table 2.4.3 Abbreviation of Generation Type Used by PLN
Source: RUPTL 2015-2024
2.4.2 POWER DEMAND PROJECTION OF NORTH SUMATRA
In RUPTL 2015-2024, the power demand in North Sumatra is projected based on the economic growth
and population growth. The projected power demand in North Sumatra presented in RUPTL 2015-2024 is
shown in Table 2.4.4.
Table 2.4.4 Power Demand Projection in North Sumatra
Year Energy SalesEnergy
Production Peak Load
(GWh) (GWh) (MW)
2015 9,293 10,244 1,886
2016 10,374 11,426 2,054
2017 11,597 12,754 2,189
2018 13,002 14,283 2,398
2019 14,623 16,046 2,636
2020 16,445 18,031 2,899
2021 18,674 20,465 3,222
2022 21,321 23,351 3,602
2023 24,436 26,746 4,125
2024 28,090 30,728 4,676
Growth Rate 13.10% 13.00% 10.60%
Source: RUPTL 2015-2024
As shown in the table, the power demand of North Sumatra is projected with high annual growth rate of
13.0%. According to RUPTL 2015-2024, the power demand projection of Indonesia is estimated between
8.4% and 9.0%, and that of Sumatra is in the range from 11.7% to 12.2 %. This fact indicates that North
Sumatra has faster growth rate of power demand than that of other provinces in Sumatra and the average
of Indonesia.
According to RUPTL, residential use has the largest electricity consumption as it shares around 60% of
the total demand of Sumatra. Other major consumption of electricity is business, industry, and public use.
Abbr. Full name English
PLTA : Pusat Listrik Tenaga Air Hydropower (middle and large scale)
PLTB : Pusat Listrik Tenaga Bayu Wind power
PLTD : Pusat Listrik Tenaga Diesel Diesel
PLTG : Pusat Listrik Tenaga Gas Gas turbine
PLTGU : Pusat Listrik Tenaga Gas & Uap Combined cycle
PLTM/MH : Pusat Listrik Tenaga Mini/Mikro Hidro Mini/Micro Hydrp
PLTMG : Pusat Listrik Tenaga Mesin Gas Gas Engine
PLTN : Pusat Listrik Tenaga Nuklir Nuclear
PLTP : Pusat Listrik Tenaga Panas Bumi Geothermal
PLTS : Pusat Listrik Tenaga Surya Solar Power
PLTU : Pusat Listrik Tenaga Uap Steam
PTMPD : Pembangkit Termal Modular Pengganti Diesel Modular Replacement Diesel
Final Report
Preparatory Survey on North Sumatra Mini 2-32 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The details of the type of use for the projected power demand of North Sumatra are not shown in RUPTL.
2.4.3 GENERATION EXPANSION PLAN IN NORTH SUMATRA
According to RUPTL 2015-2024, North Sumatra has abundant substation natural resources for power
generation, especially for hydropower and geothermal power. RUPTL 2015-2024 explains about the
necessary expansion plan of generating capacity, substation, and transmission line, and necessary
investment cost.
Table 2.4.5 Necessary Expansion for Generation Capacity, Transmission, and Substations
between 2015 and 2024
Source: RUPTL 2015-2024
As shown in the table, North Sumatra needs an additional 5,186 MW in ten years from 2015. PLN
formulates the generation expansion plan of North Sumatra based on the planned facilities investment as
shown in Table 2.4.6.
YearAdding
CapacitySub Station
Tranmission
Line
Investment
Cost
(MW) (MVA) (km) (106 USD)
2015 231 1,700 1,154 6592016 441 840 976 5872017 272 1,140 395 8092018 970 880 596 1,6812019 914 310 226 1,1492020 100 840 890 6632021 250 240 162 6062022 688 480 44 1,1352023 910 680 150 1,5142024 410 700 ‐ 711
Total 5,186 7,810 4,593 9,514
Final Report
Preparatory Survey on North Sumatra Mini 2-33 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 2.4.6 Generation Expansion Plan of North Sumatra
Source: RUPTL 2015-2024
As shown in the table, the planned PLN generation capacity is 3,304 MW and this indicates that the PLN
planned capacity is not able to cover the required capacity of 5,186 MW. Generation expansion by IPPs is
indispensable for generation expansion in North Sumatra. The planned generation expansion for each
power generation type is shown in Table 2.4.7.
Table 2.4.7 Necessary Investment of Generation Capacity from 2015 to 2024
Source: RUPTL 2015-2024
As shown in the table, majority of generation expansions are large-scale hydropower and steam power
plants such as coal-fired power plant. Then, geothermal and combined cycle and gas turbine power
No Project Type OwnerCapacity
(MW)COD
1 Pangkalan Susu #2 (FTP1) PLTU PLN 440 2015
2 PLTMH Tersebar Sumut PLTM IPP 10.9 2015
3 Truck Mounted Sumut PLTG/MG PLN 100 2016
4 Barge Mounted Sumut PLTG/MG PLN 250 2016
5 Mobile PP Nias PLTG/MG PLN 25 2016
6 Nias (FTP2) PLTU PLN 7 2016
7 Wampu (FTP2) PLTA IPP 45 2016
8 PLTMH Tersebar Sumut PLTM IPP 63 2017
9 PLTMH Tersebar Sumut PLTM IPP 98.7 2017
10 Sarulla I (FTP2) PLTP IPP 330 2017‐2018
11 Pangkalan Susu #4 (FTP2) PLTU PLN 200 2018
12 Sumbagut‐1 Peaker PLTGU/MGU PLN 250 2018
13 Sumut‐1 PLTU IPP 300 2018
14 Asahan III (FTP2) PLTA PLN 174 2019
15 Hasang (FTP2) PLTA IPP 40 2019
16 Pangkalan Susu #3 (FTP2) PLTU PLN 200 2019
17 Sumbagut‐3 Peaker PLTGU/MGU PLN 250 2019
18 Sumbagut‐4 Peaker PLTGU/MGU PLN 250 2019
19 Nias PLTMG PLN 20 2020
20 Sorik Marapi (FTP2) PLTP IPP 240 2020‐2021
21 Simonggo‐2 PLTA PLN 90 2021
22 Batang Toru (Tapsel) PLTA IPP 500 2022
23 Kumbih‐3 PLTA PLN 48 2022
24 Sibundong‐4 PLTA IPP 120 2022
25 Sipoholon Ria‐Ria (FTP2) PLTP IPP 20 2022
26 Simbolon Samosir (FTP2) PLTP IPP 110 2023
27 Sumatera Pump Storage‐1 PLTA PLN 500 2023
28 Sumut‐2 PLTU IPP 600 2023 ‐ 2024
29 Sarulla II (FTP2) PLTP IPP 110 2024
30 Sumatera Pump Storage‐2 PLTA PLN 500 2024
PLN Total 3,304
IPP Total 2,588
PLN + IPP Total 5,892
Generation Type Capacity (MW)
Hydropower PLTA 2,017
Geothermal PLTP 810
Gas turbine PLTG/MG 395
Combined cycle PLTGU/MGU 750
Steam PLTU 1,747
Mini Hydro PLTM 173
Final Report
Preparatory Survey on North Sumatra Mini 2-34 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
stations follow.
2.4.4 ISSUE OF POWER SUPPLY AND DEMAND BALANCE IN NORTH SUMATRA
As described in the preceding chapter, the ten year electricity demand projection of North Sumatra from
2015 is estimated at an annual growth rate of 13.0% of electric energy consumption, and 10.6% of peak
power demand, and these figures are higher than those of other provinces in Indonesia. In order to catch
up with this rapid growth of electricity demand, additional generation capacity of 5,186 MW is needed for
ten years from 2015. This requires large-scale 500 MW power plants to be constructed every year.
Meanwhile, the South Sumatra Generation Unit (Sumbagsel) has power supply surplus against the power
demand in the service area; however, only limited amount of surplus electricity can be transferred to
North Sumatra due to constraints in the transmission line capacity. Therefore, power deficit is worsening
and the rapid growth of electricity demand in North Sumatra should be addressed by the expansion of
generation capacity of the North Sumatra Generation Unit and IPPs.
Currently, as the power supply capacity cannot fulfill the demand in North Sumatra, PLN limits the
number of new connections of electricity users. In 2014, the number of applicants who are waiting for
connection to PLN power supply was 14,346 and 70.6 MVA is needed; hence, these numbers are
increasing annually. Under these circumstances, North Sumatra needs additional generation capacity as
soon as possible to solve the issue of power deficit and catch up with the rapid demand growth.
2.5 SIGNIFICANCE OF THE PROJECT IN NORTH SUMATRA
2.5.1 EFFECT OF THE PROJECT TO POWER SUPPLY AND DEMAND BALANCE IN NORTH SUMATRA
The combined capacity of the two mini hydropower projects in North Sumatra is approximately 20 MW.
This accounts to just 1% of the total necessary additional generation capacity of 5,892 MW and 11.6% of
the planned additional mini hydropower generating capacity of 173 MW.
The estimated electrical energy production of the two mini hydropower projects is 144.4 GWh.
According to the statistics of North Sumatra, the electrical energy consumption per household is 1,458.8
kWh/year. This means that the project can afford to supply electricity to around 99,000 households
(around 425,700 persons, calculated from the average of 4.3 person per household in North Sumatra). The
population of North Tapanuli Regency is 286,000 persons, and the neighboring Central Tapanuli Regency
has a population of 268,000. Therefore, the project can serve electricity to 78% of the two regencies
combined.
It can be concluded that although the impact of the project to the power supply system in North Sumatra
is limited, the impact to the distribution level, where the projects will connect to, is significant as the
project can supply electricity to almost 80% of the population of the two regencies.
Final Report
Preparatory Survey on North Sumatra Mini 2-35 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
2.5.2 SIGNIFICANCE OF THE PROJECT TO THE POWER SYSTEM IN NORTH SUMTRA
As described in the previous chapter, the project will have a large positive impact to the region as the
project can serve almost 80% of the population of the two regencies. As North Sumatra has abundant
hydropower potential, developing small hydropower by harnessing rich hydropower potential will
contribute to reinforcing the power supply in the project area. This will finally contribute to the economic
development in the region.
Moreover, power development through small hydropower conforms to the national policy of expediting
renewable energy as clean energy with low carbon dioxide emissions.
Final Report
Preparatory Survey on North Sumatra Mini 2-36 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(Blank Page)
Final Report
Preparatory Survey on North Sumatra Mini 3-1 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
CHAPTER 3 SITE CONDITIONS
3.1 SITE CONDITIONS
The Project is located in the province of North Sumatra, which stretches across the island of Sumatra
between the Indian Ocean and the Strait of Malacca. It borders Aceh Province in the northwest and Riau
and West Sumatra provinces in the southeast. The province contains a broad and low plain along the
Strait of Malacca Coast, the provincial capital, Medan, is located in the north coastal plain. In the south
and west, the land rises to the mountain range that runs the length of Sumatra; the mountains are
dominated by Lake Toba, formed by the caldera of an ancient volcano. The province of North Sumatra
has a land area of 71,680 km2. Pattern of land use in this province is characterized by relatively large area
for agricultural sector (mostly plantation), followed by forest.
The project area is located in North Sumatra Province, and mostly mountainous area covered by
production forests. Rubber plantation fields are also sparsely located on the flatter slope lands along the
existing roads and villages. The existing power line is available along the existing public roads between
Kolang and Pargaringan and between Tarutung and Pancurbatu, but the project area is unelectrified area
and no grid connection to the existing power line.
The Poring River originates from the mountainous area in southwest Tarutung, which elevation ranges
between 1,100-1,200 meters above sea level (masl), and flows along a gorge and meets the Sibundong
River at a length of about 20 km from the sources. Then, the Sibundong River flows into the Indian
Ocean at a length of about 42 km.
Source: JICA Survey Team
Figure 3.1.1 River Profile of the Poring River
Intake-1EL.646.5
Head Tank-1EL.641.0
Powerhouse-1EL.442.0
(Intake-2)EL.441.6
Head Tank-2EL.436.5
Powerhouse-2EL.192.1
Footpath Bridge
EL.675.0
Poring BridgeEL.350.0
100
200
300
400
500
600
700
800
-1,000 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000
Elev. (m)
River Station starting from Footpath Bridge (m)
Poring River Profile
Hydropower Facility
Poring-1 Small Hydro Project Poring-2 Small Hydro Project
SibundongRiver
Final Report
Preparatory Survey on North Sumatra Mini 3-2 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The project aims to generate hydropower energy by utilizing the difference of the river elevation of 450 m
in the 5-km long section of the Poring River before the confluence to the Sibundong River. Cascade
waterfalls start from the Poring-1 Intake to the confluence of the Sibundong River. According to the
counter map from satellite, the elevation of the river is 645 m in Poring-1 Intake, 442 m in Poring-1
Powerhouse, 442 m in Poring-2 Intake and 192 m in Poring-2 Powerhouse.
3.2 ACCESS TO THE SITE
The project is located in North Tapanuli Regency in North Sumatra Province, 20 km westward of
Tarutung, which is the regency capital of Tapanuli Utara, and 25 km northward of Sibolga, which is the
regency capital of Central Tapanuli. The following two accesses are currently available to reach the
project site:
Route-1: Sibolga – Kolang – Project Site: 40 km (2.0 hours drive by 4WD car)
The road from Sibolga to Kolang (25 km long) is a provincial road and paved in an excellent condition.
Then, the road branches in Kolang to the project site with regional road about 3.0 m wide, which is paved
but potholed. The road condition, particularly in the last 5.0 km close to the project site, is extremely
steep and poor and hard for driving without using a 4WD vehicle.
Route-2: Tarutung – Pancurbatu – Project Site: 30 km (3.0 hours drive by motorbike)
The road from Tarutung to Hutaraja (3 km long) is also a provincial road and paved in an excellent
condition. Then the road branches in Hutaraja to Pancurbatu (8 km long) which is a regional road,
partly potholed but still in good condition. The remaining road to the project site (20 km long) is only
passable by motorbikes (mostly unpaved road but partly paved by stone pitching and asphalt).
It is noted that this road was originally planned by the PU regional office and started the excavation
works in 2000 but was not completed because of budget shortage according to the village people.
Therefore, this route will also be accessible to the project site by improving the steep longitudinal profile
and narrow cross sections.
Final Report
Preparatory Survey on North Sumatra Mini 3-3 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.2.1 Location Map of the Project
Route-1 Existing Public Road near the Project Area Route-2 Existing Bike Road near Tarutung Source: JICA Survey Team
Figure 3.2.2 Conditions of the Existing Public Road
3.3 TOPOGRAPHY
3.3.1 TOPOGRAPHY OF THE SITE
North Tapanuli Regency is located in the North Sumatra highlands at an altitude between 300-1500 masl.
Topography and terrain of North Tapanuli District is relatively flat variegated (3.16%), ramps (26.86%),
oblique (25.63%), and steep (44.35%).
In the geographic coordinate system, North Tapanuli is in the position of 1 ° 20 '- 2 ° 41' north latitude
and 98 ° 05'm - 99 ° 16' east longitude. As for the geographical location, North Tapanuli District is
flanked or directly adjacent to five districts, namely, in the north bordering the Toba Samosir Regency, in
the east by Labuhan Batu District, in the south by South Tapanuli District, and in the west by the District
Final Report
Preparatory Survey on North Sumatra Mini 3-4 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Humbang Hasundutan and Central Tapanuli.
3.3.2 TOPOGRAPHIC SURVEY
(1) Available Topographic Data
1) Background of Additional Survey
In the course of the study, the topographic survey and mapping were carried out to obtain the topographic
data/information and survey products as topographic maps required for the Project not only on the overall
project area but also on each structure, i.e., intake weir site, headrace channel, head tank, penstock,
powerhouse, access roads, temporary construction yard, and transmission line.
The topographic survey and mapping were conducted by PT. Geomarinedex (Subcontractor) under the
supervision of the JICA Survey Team. The survey and mapping works started on 26 March 2015 and
were completed on 29 June 2015 after receiving their final report.
2) Topographic Information and Data
During the study period, the JICA Survey Team collected the available topographic data related to the
project area as shown in Table 3.3.1 below, which were used for site reconnaissance and preliminary
design.
Table 3.3.1 Available Topographic Data
Data Scale Remark
1 Topographic map with 25 m contour interval 1/50,000 Covers the whole project area
2 Digital elevation model (DEM) from ALOS1 1/25,000 Covers the whole project area Source: JICA Survey Team
(2) Topographic Survey
1) Scope of the Topographic Survey
The scope of work for the new topographic survey and mapping are shown in the table below:
The Subcontractor executed the topographic survey and mapping for the following areas:
a. All Hydropower Facility Site: 1/1,000 scale map
b. Major Facility Site, 1:100 scale map: Intake Weir-1, Head Tank-1, Powerhouse-1, Intake Weir-2, Head Tank-2, and Powerhouse-2
c. Existing Public Road Improvement Site (Preparatory Works): 1/1,000 scale map
d. River Cross Section Survey: 4-No for Intake Weir-1, 5-No for Powerhouse-1, 4-No for Intake Weir-2, and 5-No for Powerhouse-2
1 ALOS (Advanced Land Observing Satellite / Daichi) is a Japanese Earth-observation satellite, developed by the Japan
Aerospace Exploration Agency (JAXA), to obtain a data with sufficient resolution to be able to generate 1:25,000 scale maps, but
unables to observe land surface conditions by penetrating vegetation such as forests.
Final Report
Preparatory Survey on North Sumatra Mini 3-5 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The locations of the above survey and mapping areas are shown in the following figure.
Table 3.3.2 Scope of New Topographical Survey and Mapping Item Unit Quantity Scale Remarks
Poring-1 Intake ha 1.5 1/100 Head Tank ha 1 1/100 Powerhouse ha 1 1/100 Intake ha 14.5 1/1,000 Waterway ha 22.5 1/1,000 Head Tank and Penstock ha 18 1/1,000 Powerhouse ha 4 1/1,000 Excluding 8 ha for Poring-2 Intake
Poring-2 Intake ha 2.5 1/100 Head Tank ha 1 1/100 Powerhouse ha 1 1/100
Intake ha 8 1/1,000 Excl. 4 ha for Poring-1
Powerhouse Waterway ha 23.5 1/1,000
Head Tank, Penstock, Powerhouse
ha 39.5 1/1,000
Total Area of Topographic Survey ha 138 - 8 ha (1/100 scale), 130 ha (1/1,000)Access Road
Route Survey km 23 - Cross Section Survey No 1,150 - Current road width, every 20 m,
River Cross Section Survey No 18 - 9 Nos (Poring-1), 9 Nos (Poring-2)Source: JICA Survey Team
Source: JICA Survey Team
Figure 3.3.1 Location Map of the Survey and Mapping Area
2) Benchmarks
The national benchmark obtained from the National Survey Mapping Agency (Badan Informasi
Geospasial: BIG) isshown in Table 3.3.3. The benchmark is located in the yard of Post Office (Kantor
Pos & Giro) Pandan, about 9 km in the southwest side of Sibolga City, Jalan Padang Sidempuan- Sibolga
km 78+500.
Final Report
Preparatory Survey on North Sumatra Mini 3-6 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.3.3 National Benchmark for the Topographic Survey
ID Geodetic Coordinates (WGS84 Datum) UTM Coordinates, Zone 48 South Elevation
Latitude Longitude E. Height East (X) North (Y) Scale Factor MSL Datum
N.1045/
TTG-864
1°41’
13.7520”N
98°49’
07.7021”E
-9.631 m 479,846.309
m
186,482.616
m
0.999605 3.042 m
Source: National Survey Mapping Agency (Badan Informasi Geospasial: BIG)
Six project benchmarks were established within the project area with reference to the national benchmark.
Their XYZ coordinates were surveyed by using geodetic global positioning system (GPS) receiver with
static baseline measurements by means of tied survey to determine the coordinate horizontal and vertical
control points. Furthermore, 12 project benchmarks were additionally established along the 17-km access
road from Tarutung in the same method.
Table 3.3.4 Coordinates of Project Benchmarks
ID UTM, Zone 47 North TTG
ID UTM, Zone 47 North TTG
Northing (m) Easting (m) MSL Datum Northing (m) Easting (m) MSL Datum
PR-01 216,777.224 474,452.337 413.337 PR-10 217,519.345 481,228.617 848.520
PR-02 216,818.588 474,480.567 420.460 PR-11 216,498.255 484,901.095 1,031.491
PR-03 217,087.808 475,603.194 693.662 PR-12 216,504.325 484,959.293 1,024.679
PR-04 217,796.596 475,416.754 459.084 PR-13 216,351.030 489,091.094 1,030.869
PR-05 217,917.492 477,468.628 703.308 PR-14 216,394.104 489,175.650 1,042.057
PR-06 217,891.129 477,536.105 716.995 PR-15 218,525.678 491,731.220 1,190.784
PR-07 216,823.227 473,393.303 209.703 PR-16 218,600.085 491,767.843 1,189.924
PR-08 216,739.282 473,359.957 194.543 PR-17 220,014.447 495,182.559 1,058.197
PR-09 217,492.780 481,193.449 848.150 PR-18 220,119.610 495,223.714 1,060.799 Source: Topographic Survey Report by PT. Geomarindex
The benchmarks were surveyed by traversing and levelling survey measurements. The traversing survey
measurement was done by using a total station to distribute the deviation of horizontal angle within the
specified standard for both inside and outside angles. The levelling survey measurement was by automatic
levelling equipment to make a closed loop or tied at both ends to satisfy the standard.
3) Topographic Map
Data processing was carried out to draw the contour maps below by using AutoCAD Civil 3D for the data
of GPS measurement, traversing, leveling, and detailed topographic spot height. Data verification was
also performed to review the quality and accuracy to comply with the tolerance specified in the typical
standard.
Final Report
Preparatory Survey on North Sumatra Mini 3-7 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
3.4 HYDROLOGY
3.4.1 STUDY AREA
(1) River Basin Characteristics
As shown in the location map in Figure 3.4.1, the Poring
River and its longest tributary, the Batutunggal River,
originate from the peaks of Mt. Tor Tunjul at El.1,534 m
and Mt. DK. Siborboron at El.1,480 m, about 5 km west
of Tarutung Town, and flow from the east to southwest
through forest and mountainous areas. Joined by the
Batutunggal River at El.750 m, the Poring River enters
into the gorge at around El.625 m where the proposed
project site near Siantar Naipospos Village exists and
merges with the Sibundong River, which eventually
flows to the Indian Ocean.
Its total river lengths to the proposed intake sites of Poring-1 and Poring-2 are about 20 km and 22 km,
respectively, with total height differences of 855 m and 1,093 m between the proposed intake sites and the
top of Mt. DK. Siborboron, which provides the longest stream length. Catchment areas at the proposed
intake sites of Poring-1 and Poring-2 are 87 km2 and 91 km2, respectively.
Source: JICA Survey Team
Figure 3.4.1 Watershed Area of Poring River
(2) Climate Conditions
The project site is located in a tropical rainforest climate (Af) area where the climate is characterized by
two vague rainy seasons from March to April and October to December as shown in Figure 3.4.2.
Photo taken by the JICA Survey Team
Poring River near the Proposed Intake Site
Poring River
Batutunggal River
Final Report
Preparatory Survey on North Sumatra Mini 3-8 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Although air temperatures vary by altitude, the mean monthly air temperature in Hutaraya, which is close
to the project site and located at similar altitude, is about 23.7 ºC, which is stable for the whole year.
Average Rain Days, Precipitation and Sunshine %
Average Temperatures
Note: The above graphs are based on the data over the last 20 years in Hutaraya, North Sumatra, Indonesia. Source: Chinci World Atlas, http://www.chinci.com/
Figure 3.4.2 Climate Patterns in Hutaraya near the Poring River Basin
Mean annual rainfall at each gauging station around the project site largely varies from area to area as
shown in Table 3.4.1 and Figure 3.4.3. Mean daily evaporation at surrounding stations, which is
computed by the Indonesian Agency for Meteorology (Badan Meteorologi, Klimatologi, dan Geofisika:
BMKG)2, is summarized in Table 3.4.2. These stations are shown in Figure 3.4.4 later.
Table 3.4.1 Mean Monthly and Annual Rainfall around the Poring River Basin
2 Badan Meteorologi, Klimatologi, dan Geofisika (Indonesian Agency for Meteorology)
37.5
40
42.5
45
47.5
50
52.5
0
5
10
15
20
25
30
35
40
Jan FebMar Apr May Jun Jul Aug Sep Oct Nov DecSu
nny (%
)
Rain DaysPrecipitationSunny %
Rain (D
ays/m
onth) / Precipitation (10mm/m
onth)
16
18
20
22
24
26
28
30
Jan FebMar Apr May Jun Jul Aug Sep Oct Nov Dec
Temperatures (°C)
Maximum Temp.Minimum Temp.Mean Temp.
(Unit: mm)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Tarutung 1954~2000 BMKG 167 185 146 275 132 66 85 87 143 167 225 199 1,878
2 Bandara Silangit 2008~2015 BMKG 199 140 204 249 247 92 104 175 190 242 280 282 1,920
3 Pinangsori 2002~2015 BMKG 333 300 361 353 289 198 311 428 404 524 607 464 4,588
4 Hutaraya 1954~1999 BMKG 174 171 228 243 141 98 106 118 166 216 255 245 2,160
5 Adian Koting 2002~2011 BMKG 240 238 270 265 214 158 135 181 270 310 353 277 2,911
6 Hobuan 2005~2014 BWS S‐II*1 238 228 291 249 213 130 134 303 237 426 487 316 3,252
7 Sarulla 2001~2014 BWS S‐II*1 366 347 422 485 265 187 156 402 331 525 562 492 4,540
8 Sibolga 2002~2014 BWS S‐II*1 231 314 320 364 276 143 230 371 306 382 512 368 3,816
Note: *1 Balai Wilayah Sungai Sumatera II (Regional Office of the Ministry of Public Works)
Annual
Mean
Mean Monthly RainfallNo. Station Name
Data
PeriodSource
Final Report
Preparatory Survey on North Sumatra Mini 3-9 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: BMKG, BWS S‐II
Figure 3.4.3 Mean Monthly Rainfall around the Poring River Basin
Table 3.4.2 Mean Daily Evaporation around the Poring River Basin
(3) Target Survey
In this survey, the project is designed to take river water only at Poring-1 Intake. The Poring-2 Mini
Hydropower plans to directly utilize the power discharge of Poring-1, as described in Chapter 4. This
means that the stream flow of the Poring River is diverted at Poring-1 Intake site only. Therefore, the low
flow analysis focuses on the estimation of continuous long-term stream flow at Poring-1 Intake site. As
for flood analysis, since the flood peak discharge is necessary to determine the height of structures for
Poring-1 and Poring-2, therefore, the flood peak discharge is estimated for both sites.
3.4.2 AVAILABLE HYDROLOGICAL DATA
(1) Collection of Existing Hydrological Data
The availability of collected daily hydrological data is summarized in Table 3.4.3. Besides, monthly
rainfall data was collected from the pre-FS review report3 as shown in Table 3.4.4. The locations of
respective stations are shown in Figure 3.4.4. As seen in the tables below, many of the stations have had
interruption of observations over a long period.
3 Review of Hydrology Analysis in the Pre-Feasibility Study Reports for Mini Hydro Power Projects in North Sumatra, Indonesia, January 2014, Nippon Koei Co., Ltd.
0
100
200
300
400
500
600
700
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Mean
Monthly Rainfall
(mm/m
onth)
Sarulla
Sibolga
Hobuan
Adian Koting
Hutaraya
Tarutung
Pinangsori
Bandara Silangit
(Unit: mm/day)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Tarutung 2005~2014 BMKG 2.39 2.12 2.21 2.09 2.47 2.35 2.25 2.24 2.18 2.00 1.77 3.04 2.26
2 Sibolga 2005~2014 BMKG 5.27 4.35 5.03 5.55 4.89 4.60 4.70 4.48 4.90 4.12 4.44 4.44 4.73
Source: BMKG
No.Station
Name
Data
PeriodSource
Mean Daily Evaporation Annual
Mean
Final Report
Preparatory Survey on North Sumatra Mini 3-10 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.3 Availability of Daily Rainfall and Daily Discharge / Water Level Data
Table 3.4.4 Availability of Monthly Rainfall Data
Unfortunately, there is no existing rainfall gauging station in the Poring River basin. The JICA Survey
Team collected daily rainfall data observed at the rainfall gauging stations near the Poring River basin
from BMKG and the Regional Office of the Ministry of Public Works (Balai Wilayah Sungai: BWS)
Sumatera II4. However, since the observation system as well as data management of BWS is poor, daily
rainfall data in the northern side of the project area is not available for this study.
Furthermore, the Poring River had no water level gauging station before the commencement of this
preparatory survey. For this reason, the Kolang River basin, one of the neighboring basins around the
project site, is selected as an alternative basin for estimating long-term discharge at the project site. The
following subsections will therefore focus on the Kolang River basin as well. The detailed process of
selecting the Kolang River basin is described in Clause 3.4.5 (2) later.
4 Regional Office of the Ministry of Public Works, Indonesia, for river basin management in the Sumatra II Region
YearMonth
Station NameRainfall
PinangsoriBandara SilangitSarullaSibolgaHura BalangHobuanPengkolanPoring Bridge
Source: BMKG (for Pinangsori and Bandara Silangit), JDG (for Poring Bridge), BWS Sumatera II (for the others)Legend: Month Availability : Complete Data : Incomplete Data : No Data9 10 11 121 2 3 4 5 6 7 8
2013 20142007 2008 2009 2010 2011 20122001 2002 2003 2004 2005 2006
YearMonth
Station NameDischarge
Pasar SirongitDolok SanggleMaradeKolangHapesong Baru
Water LevelKolang
Source: BWS Sumatera IILegend: Month Availability : Complete Data : Incomplete Data : No Data
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
1 2 3 4 5 6 7 8 9 10 11 12
Year
Station NameSegala *1Batang Toru *1Aek Pahu *1Tarutung *1Hutaraya *1Barus *1 *2Siborong-borong *1Dolok Sanggul *1Gugur Balige *1Adian Koting *3
Legend: : Complete Monthly Data : Incomplete Monthly Data : No DataNote: *1: (Monthly data) Hydroinventory and prefeasibility studies, Nippon Koei Co. Ltd., 1999
*2: (Monthly data) Project for the Master Plan Study of Hydropower Development in Indonesia, Nippon Koei Co. Ltd., 2011*3: (10-day data) Pargaringan Pre-FS, PT. Jaya Dinamika Geohidroenergi, 2012. Reliability of data is questionable.
19
61
19
62
19
63
19
64
19
65
19
66
19
67
19
68
19
69
19
70
19
71
19
72
19
73
19
74
19
75
19
76
19
77
19
78
19
79
19
80
19
81
19
82
19
83
19
84
19
85
19
86
19
87
19
88
19
89
19
90
19
91
19
92
19
93
19
94
19
95
19
96
19
97
19
98
19
99
20
00
20
01
20
02
20
09
20
10
20
11 Data
Source20
03
20
04
20
05
20
06
20
07
20
08
Final Report
Preparatory Survey on North Sumatra Mini 3-11 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.4.4 Gauging Stations around the Poring River Basin
(2) Confirmation of Rainfall Observation System
In order to confirm that the rainfall data was obtained through appropriate manner of measurement, the JICA
Survey Team visited rainfall gauging stations and interviewed the gauge keepers for their measuring method.
The JICA Survey Team was able to contact the gauge keepers of the following stations:
- Pinangsori (BMKG)
- Bandra Silangit (BMKG)
- Hutabalang (BWS)
- Sibolga (BWS)
- Sarulla (BWS)
According to the result of the hearing, it was confirmed that all the stations use proper measuring instruments
such as rainfall collector and measuring cylinder. However, it was found that some of the rainfall gauging
stations run by BWS do not measure the rainfall at the designated time. Besides, tall trees are planted close to
the rainfall collector and some leaves cover it, especially in Sarulla and Sibolga. Therefore, data observed at
such stations are considered not reliable.
(3) Observation of Hydrological Data by the Survey Team
In order to know the hydrological relationship between the Poring River basin and the neighboring basins,
the following hydrological monitoring has been conducted in and around the Poring River basin. For the
Final Report
Preparatory Survey on North Sumatra Mini 3-12 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Poring River basin, the water level is monitored at the bridge located 1.1 km downstream from the
proposed Poring-1 Powerhouse site, and a rainfall collector is placed and monitored at a flat area close to
the bridge. Since the watershed of the Pargaringan River is quite similar to the Poring River in terms of
geological and topographical features, it is expected that their hydrological behaviors are alike. The water
level of the Pargaringan River is also monitored at the bridge over the Pargaringan River located 2 km
southward from the Poring Bridge.
Source: JICA Survey Team
Figure 3.4.5 Water Level Monitoring Stations at Kolang, Poring Bridge, and
Pargaringan Bridge
Table 3.4.5 Observation of Hydrological Data by the JICA Survey Team No. Data Item Interval Period Location Method
1 Rainfall Daily 15 June – 30 November 2014 Pargaringan Bridge *1 Manual
2 Hourly 5 Dec. 2014 – 11 Sept. 2015 Poring Bridge *2 Automatic
3 Water Level Daily (twice/day) 17 June – 30 November 2014 Pargaringan Bridge *1 Manual
4 Hourly 9 Dec. 2014–12 May 2015 *3 Poring Bridge *2 Automatic
5 Daily (twice/day) 25 April – 18 Sept. 2015 Poring Bridge *2 Manual
6 Pargaringan Bridge *1 Manual
7 Discharge Biweekly 16 May– 19 Sept. 2015 Poring Bridge *2 Using a current meter
8 Pargaringan Bridge *1 Note: *1 The Pargaringan Bridge is located along the Pargaringan River, an adjacent river to the Poring River. (CA = 76.5 km2)
*2 The Poring Bridge is 1.1 km downstream of the Poring-2 Intake site. (CA = 91.5 km2) *3 The gauge sensor had a serious malfunction since 13 May 2015. *4 The gauge sensor had a serious malfunction since 11 September 2015.
Source: JICA Survey Team
3.4.3 RAINFALL DATA
(1) Daily Rainfall of the Respective Rainfall Gauging Stations
The locations of rainfall gauging stations around the Poring River basin are shown in Figure 3.4.4 above.
The double mass curves (DMC) were prepared by using available raw data only as shown in Figure 3.4.6
to see the relationship of the monthly rainfall between each of the two gauging stations. Although DMC is
usually prepared by using annual rainfall data, this report presents DMCs of monthly data because annual
data is not calculable in many years due to a lot of missing data. The DMCs revealed that there are some
significant deviations among the data of the rainfall gauging stations in Sallura and it may be caused by
Kolang
Pargaringan Br.
Poring-1 Poring-2 Poring Br. Poring River
Pargaringan River
Kolang River
Final Report
Preparatory Survey on North Sumatra Mini 3-13 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
the inappropriate manner of measurement as aforementioned. For DMCs of Pengkolan and Hobuan, there
are some deviations observed around some extreme torrential rainfall events of more than 1,000
mm/month such as in October-November 2008.
Source: JICA Survey Team
Figure 3.4.6 Double Mass Curve for Each of the Rainfall Gauging Station
For estimation of long-term basin mean rainfall between 2005 and 2014, missing daily rainfall data is
filled by applying linear regression lines. The linear regression lines are used to generate the data
according to the level of correlation, i.e., the missing data is synthesized from the highest correlated data.
However, as some of the rainfall monitoring stations run by BWS do not correctly measure the rainfall,
the priority of such data is arbitrarily lowered. Besides the data where the correlation coefficient to the
target station is less than 0.4 is not considered for synthesizing the missin data. The regression equation
lines as well as correlation coefficients between each rainfall station are presented in Table 3.4.6.
Bandara Silangit Poring Bridge
Pin
an
g S
ori
Sa
rulla
Sib
olg
a
Pinang Sori Sarulla Sibolga Hura Balang Kolang / Hobuan Pengkolan
Hu
ra B
ala
ng
Ko
lan
g /
Ho
bu
an
Pe
ng
kola
nB
an
da
ra S
ilan
git
Po
rin
g B
rid
ge
0
10
20
30
40
50
0 20 40 60
R2(1,000mm)
R1 (1,000mm
0
10
20
30
40
0 20 40 60
R3(1,000mm)
R1 (1,000mm
0
5
10
15
20
25
0 10 20 30
R5(1,000mm)
R1 (1,000mm
0
10
20
30
40
50
0 20 40 60
R4(1,000mm)
R1 (1,000mm
0
5
10
15
20
0 10 20 30
R6(1,000mm)
R1 (1,000mm
0
10
20
30
40
50
0 20 40 60
R1
(1,000mm)
R2
(1,000mm0
5
10
15
20
25
30
0 10 20 30 40
R3
(1,000mm)
R2
(1,000mm0
5
10
15
20
0 10 20 30
R5
(1,000mm)
R2
(1,000mm0
5
10
15
20
25
30
35
0 20 40 60
R4
(1,000mm)
R2
(1,000mm0
5
10
15
20
0 10 20 30
R6
(1,000mm)
R2
(1,000mm)
0
10
20
30
40
0 10 20 30
R2
(1,000mm)
R3
(1,000mm
0
10
20
30
40
50
0 20 40
R1
(1,000mm)
R3
(1,000mm
0
5
10
15
20
0 10 20 30
R5
(1,000mm)
R3
(1,000mm
0
10
20
30
40
0 10 20 30 40
R4
(1,000mm)
R3
(1,000mm
0
5
10
15
20
0 10 20
R6
(1,000mm)
R3
(1,000mm
0
10
20
30
40
50
0 20 40
R2
(1,000mm)
R4
(1,000mm
0
10
20
30
40
50
0 20 40 60
R1
(1,000mm)
R4
(1,000mm
0
5
10
15
20
25
30
35
0 10 20 30 40
R3
(1,000mm)
R4
(1,000mm
0
5
10
15
20
0 10 20 30
R5
(1,000mm)
R4
(1,000mm
0
5
10
15
20
0 10 20 30
R6
(1,000mm)
R4
(1,000mm
0
5
10
15
20
25
0 10 20
R2(1,000mm)
R5 (1,000mm
0
5
10
15
20
25
30
0 10 20 30
R1(1,000mm)
R5 (1,000mm
0
5
10
15
20
25
0 10 20
R3(1,000mm)
R5 (1,000mm
0
5
10
15
20
25
0 10 20
R4(1,000mm)
R5 (1,000mm
0
2
4
6
8
10
0 5 10 15
R6(1,000mm)
R5 (1,000mm
0
5
10
15
20
25
0 10 20
R2
(1,000mm)
R6
(1,000mm
0
5
10
15
20
25
30
0 10 20
R1
(1,000mm)
R6
(1,000mm
0
5
10
15
20
0 10 20
R3
(1,000mm)
R6
(1,000mm)
0
2
4
6
8
10
12
14
0 5 10
R5
(1,000m
R6
(1,000mm
0
5
10
15
20
25
0 10 20
R4
(1,000mm)
R6
(1,000mm
0
1
2
3
4
5
6
7
0 5 10 15
R7(1,000mm)
R1 (1,000mm
0
1
2
3
4
5
6
0 5 10
R7
(1,000mm)
R2
(1,000mm)
0
1
2
3
4
5
6
0 5 10
R7
(1,000mm)
R3
(1,000mm
0
1
2
3
4
5
6
0 5 10 15
R7
(1,000mm)
R4
(1,000mm
0
1
1
2
2
3
0 2 4 6
R7(1,000mm)
R5 (1,000mm
0
1
2
3
4
5
6
0 5 10
R7
(1,000mm)
R6
(1,000mm
0
1
2
3
4
5
6
0 2 4 6
R8(1,000mm)
R1 (1,000mm
0
1
1
2
2
3
3
0 1 2 3
R8
(1,000mm)
R2
(1,000mm)
0
1
1
2
2
3
0 1 2 3
R8
(1,000mm)
R3
(1,000mm
0
1
2
3
4
5
6
0 2 4 6
R8
(1,000mm)
R4
(1,000mm
0
1
2
3
4
0 1 2 3
R8
(1,000mm)
R6
(1,000mm
0
2
4
6
8
10
0 2 4 6
R2
(1,000mm)
R7
(1,000mm
0
2
4
6
8
10
12
14
0 5 10
R1
(1,000mm)
R7
(1,000mm
0
2
4
6
8
0 2 4 6
R3
(1,000mm)
R7
(1,000mm)
0
1
2
3
4
5
6
0 1 2 3
R5
(1,000m
R7
(1,000mm
0
2
4
6
8
10
12
0 2 4 6
R4
(1,000mm)
R7
(1,000mm
0
2
4
6
8
0 2 4 6
R6
(1,000m
R7
(1,000mm
0
1
2
3
4
5
0 1 2 3
R8
(1,000mm)
R7
(1,000mm
0
1
1
2
2
3
0 1 2 3
R2
(1,000mm)
R7
(1,000mm
0
1
2
3
4
5
0 2 4 6
R1
(1,000mm)
R7
(1,000mm
0
1
1
2
2
3
3
0 1 2 3
R3
(1,000mm)
R7
(1,000mm)
0
1
2
3
4
5
6
0 2 4 6
R4
(1,000mm)
R7
(1,000mm
0
1
1
2
2
3
0 2 4
R6
(1,000m
R7
(1,000mm
0
1
1
2
2
3
0 2 4 6
R7
(1,000mm)
R7
(1,000mm
DataNot Available
DataNot Available
Final Report
Preparatory Survey on North Sumatra Mini 3-14 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.6 Equation of Regression Line and Correlation Coefficient
Source: JICA Survey Team
(2) Basin Mean Rainfall
The basin mean rainfall for the Poring Intake site and Kolang Water Level Gauging Station is obtained by
Thiessen method. Thiessen’s polygons made over the Poring and Kolang River basins are shown in
Figure 3.4.7. As the number of rainfall stations near the Poring River basin is limited, the basin rainfall
for the Poring Intake site is only covered by the data at the Poring Bridge. For the Kolang River basin, the
basin rainfall is calculated by the data of Hobuan (Thiessen’s coefficient: 18.0%), Poring Bridge (80.1%),
and Pinangsori (1.9%) stations.
Base Station Coefficient of Observation
No. Target Station Priority No. Station Name Correlation Condition Station y = a * ( Station x )
(y) (x) (x) ( R2) (z)
1 Pinangsori 1 Poring Bridge 0.600 Good Pinangsori = 0.811 * ( Poring Bridge )
2 Huta Balang 0.795 Fair Pinangsori = 1.043 * ( Huta Balang )
3 Bandara Silangit 0.455 Good Pinangsori = 1.583 * ( Bandara Silangit )
2 Sarulla 1 Poring Bridge 0.872 Good Sarulla = 0.724 * ( Poring Bridge )
2 Bandara Silangit 0.453 Good Sarulla = 1.546 * ( Bandara Silangit )
3 Pengkolan 0.584 Fair Sarulla = 1.306 * ( Pengkolan )
3 Sibolga 1 Poring Bridge 0.836 Good Sibolga = 0.990 * ( Poring Bridge )
2 Pinangsori 0.533 Good Sibolga = 0.793 * ( Pinangsori )
3 Huta Balang 0.619 Fair Sibolga = 0.870 * ( Huta Balang )
4 Huta Balang 1 Pinangsori 0.795 Good Huta Balang = 0.894 * ( Pinangsori )
2 Poring Bridge 0.617 Good Huta Balang = 0.878 * ( Poring Bridge )
3 Sibolga 0.619 Fair Huta Balang = 1.000 * ( Sibolga )
4 Bandara Silangit 0.421 Good Huta Balang = 1.498 * ( Bandara Silangit )
5 Hobuan 1 Bandara Silangit 0.602 Good Hobuan = 2.309 * ( Bandara Silangit )
2 Pengkolan 0.701 Fair Hobuan = 1.441 * ( Pengkolan )
3 Pinangsori 0.404 Good Hobuan = 0.708 * ( Pinangsori )6 Pengkolan 1 Poring Bridge 0.592 Good Pengkolan = 0.575 * ( Poring Bridge )
2 Pinangsori 0.510 Good Pengkolan = 0.615 * ( Pinangsori )3 Bandara Silangit 0.506 Good Pengkolan = 1.345 * ( Bandara Silangit )4 Hobuan 0.701 Fair Pengkolan = 0.576 * ( Hobuan )
7 Bandara Silangit 1 Poring Bridge 0.783 Good Bandara Silangit = 0.437 * ( Poring Bridge )2 Pinangsori 0.455 Good Bandara Silangit = 0.501 * ( Pinangsori )3 Hobuan 0.602 Fair Bandara Silangit = 0.311 * ( Hobuan )
8 Poring Bridge 1 Bandara Silangit 0.783 Good Poring Bridge = 2.038 * ( Bandara Silangit )2 Pinangsori 0.600 Good Poring Bridge = 1.077 * ( Pinangsori )3 Sibolga 0.836 Fair Poring Bridge = 0.938 * ( Sibolga )4 Huta Balang 0.617 Fair Poring Bridge = 0.987 * ( Huta Balang )5 Pengkolan 0.592 Fair Poring Bridge = 1.466 * ( Pengkolan )
Regression Equation Line : y = ax
Final Report
Preparatory Survey on North Sumatra Mini 3-15 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.4.7 Thiessen Polygon for Poring-1 Intake Site and Kolang Water Level Observatory
The calculated basin mean rainfall for Poring-1 Intake site and the Kolang water level gauging stations
are shown in Table 3.4.7, Figure 3.4.8, Table 3.4.8, and Figure 3.4.9. As shown in the figure and table,
ten-year average of annual basin mean rainfall of Poring-1 Intake site and Kolang stations are 4,889
mm/year and 4,714 mm/year, respectively. The basin rainfall for the Kolang stations by BMKG’s isohyet
map is calculated at 3,448 mm/year, therefore, the calculated basin mean rainfall by Thiessen method is
higher by around 1,000 mm/year than that is estimated by BMKG’s isohyet map. The annual rainfall at
Pinangsori rainfall gauging station, which is located close to the project site, recorded 4,588 mm/year
from 2002 to 2015, and therefore, the basin rainfall given by Thiessen method is not far deviated from the
actual record.
Table 3.4.7 Estimated Basin Rainfall at Poring-1 Intake Site
Source: JICA Survey Team
(unit: mm)
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total2005 236 206 296 186 100 189 374 789 335 1,038 603 485 4,8382006 418 523 392 519 206 200 245 383 606 735 522 597 5,3472007 444 420 367 260 301 226 684 243 552 1,018 688 378 5,5812008 321 337 110 183 304 204 311 603 323 476 590 473 4,2342009 300 321 726 121 224 87 202 227 567 438 501 338 4,0522010 626 460 738 381 445 457 391 434 525 383 830 356 6,0272011 325 351 450 529 222 158 249 444 348 671 887 1,032 5,6652012 121 418 348 484 211 209 491 388 274 335 708 735 4,7222013 389 677 234 404 333 121 145 348 301 362 269 817 4,4002014 218 98 137 538 503 269 179 418 191 378 803 294 4,0242015 502 408 434 671 218 286 287 279 454 ‐ ‐ ‐ ‐
Minimum 121 98 110 121 100 87 145 227 191 335 269 294 4,024Maximum 626 677 738 671 503 457 684 789 606 1,038 887 1,032 6,027Average 355 383 385 389 279 219 323 414 407 583 640 550 4,889
Note: "-" denotes no data
Poring-1 Intake Catchment
Kolang Catchment Hobuan
Poring Br.
Pinangsori
Final Report
Preparatory Survey on North Sumatra Mini 3-16 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.4.8 Monthly and Annual Basin Mean Rainfall of Poring-1 Intake Site
Table 3.4.8 Estimated Basin Rainfall at the Kolang Water Level Gauging Station
Source: JICA Survey Team
Source: JICA Survey Team
Figure 3.4.9 Monthly and Annual Basin Rainfall at the Kolang Water Level Gauging Station
3.4.4 RUNOFF DATA
(1) Daily Discharge Data
Initially, the runoff data around the Poring River basin were collected from BWS Sumatera II in the form
of discharge data as summarized in Table 3.4.9. The specific discharges per catchment area of 100 km2
range from 2.6 to 8.2 m3/s/100 km2 except Sipansihaporas. According to the collected data, runoffs for
Dolok Sanggle and Marade are relatively high considering the isohyetal lines between 1,500 and 2,500
mm/year as shown in Figure 3.4.4.
0
100
200
300
400
500
600
700
Jan
Feb
Mar
Apr
May Jun
Jul
Aug
Sep Oct
Nov
Dec
Average
Monthly Rainfall
(mm/m
onth)
Year: 2005‐2015 (Sep.)
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
Maxim
um Monthly Rainfall
(mm/year)
Average: 4,889 mm/year
Year: 2005‐2015 (Sep.)
(unit: mm)
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total2005 226 204 305 191 128 195 349 746 313 929 604 441 4,6322006 386 501 388 496 201 190 250 367 570 685 486 556 5,0762007 420 381 354 248 285 221 590 219 486 909 624 352 5,0902008 311 310 178 220 285 193 321 585 343 579 695 488 4,5082009 282 329 627 144 224 127 194 276 513 387 469 312 3,8832010 564 437 666 372 451 395 346 395 482 442 776 329 5,6552011 322 355 427 492 236 175 230 458 339 614 812 941 5,4012012 113 392 326 453 198 196 461 385 247 317 663 688 4,4402013 357 598 214 384 317 142 135 336 271 328 353 782 4,2162014 210 85 132 537 535 271 168 496 229 411 830 333 4,2372015 513 339 431 643 261 261 280 282 469 ‐ ‐ ‐ ‐
Minimum 113 85 132 144 128 127 135 219 229 317 353 312 3,883Maximum 564 598 666 643 535 395 590 746 570 929 830 941 5,655Average 337 357 368 380 284 215 302 413 388 560 631 522 4,714
Note: "-" denotes no data
0
100
200
300
400
500
600
700
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Average
Monthly Rainfall
(mm/m
onth)
Year: 2005‐2015 (Sep.)
0
1,000
2,000
3,000
4,000
5,000
6,000
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
Maxim
um Monthly Rainfall
(mm/year)
Average: 4,714 mm/year
Year: 2005‐2015 (Sep.)
Final Report
Preparatory Survey on North Sumatra Mini 3-17 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.9 Summary of Discharge Data around the Poring River Basin
Source: BWS Sumatera II
While, there is a hydropower project, namely: Sipansihaporas Hydroelectric Power Project near Sibolga.
The project was constructed with the assistance of Japanese official development assistance (ODA) loan,
and the site is located around 30 km toward the southeast from the Poring 1 and Poring 2 project sites.
The project is designed along the Sibuluan River flowing to the Indian Ocean. According to the feasibility
study on the Sipansihaporas project5, the specific discharge of the Sipansihaporas Hydroelectric Power
Project was calculated at 10.0 m3/s/100 km2 which is larger than any other neighboring basin. However,
according to a technical article6 published in 2008, the catchment area of the project is revised to 240 km2.
With this figure of 240 km2, the specific discharge of the Sipansihaporas project is calculated at 8.2
m3/s/100 km2 which is the same value as that of Kolang Water Level Gauging Station.
Figure 3.4.10 presents the comparison of duration curves of collected discharge data between the above
five stations except Sipansihaporas. Only the years 2009 and 2011 provide a series of complete data for
the stations. The graphs also express that the specific discharge of Marade is larger than the others.
However, the other gauging stations show similar trends of specific discharge and gradual decrease rate
particularly in the low flow part.
Source: BWS Sumatera II
Figure 3.4.10 Duration Curves of Collected Discharge Data
5 JICA, “Feasibility Study on Sipansihaporas Hydroelectric Power Development Project” July 1990, Japan. 6 Nishiguchi, et al, “Issues and Countermeasures for Construction of Sipansihaporas Hydroelectric Power Project in Indonesia ” 37th Symposium for Rock-Mechanics, Japan Society of Civil Engineering, January, 2008 (translated from Japanese)
Catchment Area Average Discharge Speci fic Discharge Runoff
Year Months [ km2] [ m
3/s ] [ m
3/s/100km
2 ] [ mm/year ]
Pasar Si rongi t Aek Sigeaon 1992~2013 178 350.6 12.7 3.6 1,142
Dolok Sanggle Aek Sibundong 2001~2013 149 50 2.6 5.2 1,629
Marade Aek Si lang 2000~2013 153 163.8 8.1 5.0 1,564
Kolang Aek Kolang 2005~2013 80 464.4 38.0 8.2 2,577
Hapesong Baru Aek Batang Toru 1992~2013 183 2773 73.3 2.6 834
Sipans ihaporas Aek Sibuluan 1978~1985 96 196 19.7 10.0 3,163
Avai labi l i tyStation Name River Name
0
5
10
15
20
25
30
35
40
45
50
0 30 60 90 120 150 180 210 240 270 300 330 360
Specific Discharge
(m3/s/100km
2)
Day
Pasar Sirongit (350.6 km2)Dolok Sanggle (50 km2)Marade (163.8 km2)Kolang (464.4 km2)Hepsong Baru (2773 km2)
Year: 2009
0
5
10
15
20
25
30
35
40
45
50
0 30 60 90 120 150 180 210 240 270 300 330 360
Specific Discharge
(m3/s/100km
2)
Day
Pasar Sirongit (350.6 km2)Dolok Sanggle (50 km2)Marade (163.8 km2)Kolang (464.4 km2)Hepsong Baru (2773 km2)
Year: 2011
Final Report
Preparatory Survey on North Sumatra Mini 3-18 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Water Level Records at Poring Bridge Water Level Observatory
The water level monitoring of the Poring River at the Poring Bridge has been conducted since December
2014, and the water level of the Pargaringan River has been monitored since July 2014. From May to
September 2015, the JICA Survey Team conducted discharge measurements at the Poring Bridge and
Pargaringan Bridge. The water level data until August 2015 was adopted in this hydrological analysis.
The result and discussion of the discharge measurement are described in Section 3.4.5 (5).
(3) Water Level Records at Kolang Water Level Observatory
The daily water level records at the Kolang Gauging Station were collected as shown in Figure 3.4.11
below. According to BWS Sumatera II, large-scale water utilization including irrigation scheme is neither
implemented nor planned in the Kolang watershed at present as is the case with the Poring watershed.
Source: BWS Sumatera II
Figure 3.4.11 Daily Water Level at the Kolang Water Level Gauging Station
Besides, although the water level data for 2014 are collected as expressed in the above graph, it was
found through the field reconnaissance that the 2014 data is unreliable because it was measured by means
of a movable gauge after the fixed gauge was flushed away by flood in early 2014. Thus, the water level
data for 2014 is not used in the following analysis. In June 2015, a new water level gauge was installed
and fixed to the foundation at Kolang Water Level Gauging Station.
3.4.5 LOW FLOW ANALYSIS
(1) General Approach
The continuous long-term runoff data for a time period of more than ten years at the proposed intake weir
site is normally required for evaluating an optimum development scale of the project through power
output computation. Further, it is highly expected that the runoff data should be of high accuracy because
measurement on economic viability of project is highly dependent on the reliability of available runoff
records. On the Poring-1 and Poring-2 MHPP, daily runoff data are required because the type of
hydropower development scheme is run-of-river type. However, as stated in Section 3.4.1 (3), river water
is taken only at the Poring-1 Intake Weir and the water is used for the power generation of both Poring-1
and Poring-2, therefore, the long-term low flow is estimated only at the proposed Poring-1 Intake site.
In the low flow analysis, water level of the Kolang River is measured at the Kolang Water Level Gauging
Station for the duration of 6.6 years, that is from 2005 to 2015 except 2008, 2013, and 2014. Out of the
0.0
0.5
1.0
1.5
2.0
2.5
3.0
05 06 07 08 09 10 11 12 13 14
Daily W
ater Level (m)
Year
no use in analysis due to inaccurate measurement
Final Report
Preparatory Survey on North Sumatra Mini 3-19 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
period of which the Kolang River discharge data is not available, the water level records measured at the
Poring Bridge and the Pargaringan Bridge are used. The period where is no stream flow record at Poring
Bridge and Pargaringan Bridge is not available, stream flow during such period is estimated by the
hydrological model which can simulate hydrologic behavior of rainfall to runoff of the Poring River at the
Poring Intake site. For simulation by the hydrological model, the input is the estimated basin rainfall as
described in Section 3.4.3, and daily runoff is estimated through the model.
The outline of low flow analysis is summarized in Figure 3.4.12.
As for the hydrological model, the Tank Model Method (Sugawara, 1956) was adopted for this low flow
analysis. Whereas, hydropower projects in Indonesia usually use i) FJ Mock, ii) National Rural Electric
Cooperative Association (NRECA), or iii) Tank Model, however, the said models i) and ii) are able to
assess only monthly discharge. Since this analysis requires estimating daily discharge, iii) Tank Model
was adopted.
Source: JICA Survey Team
Figure 3.4.12 Outline of Low Flow Analysis
(2) Selection of an Alternative River Basin
Since no stream flow measurement for the Poring River had been conducted until this preparatory survey,
it is necessary to select an alternative basin which is located close to the project area and has long-term
stream flow data available. The hydrological and geological features of the neighboring river basins were
compared as shown in Table 3.4.10. Although it is desirable to select a similar basin to the Poring River
basin from every point of view, the respective neighboring basins indicate both merits and demerits.
Collection of Existing Daily Runoff Records around Poring River
Selection of Alternative River Basin (A)
Conversion of Runoff Data from the Basin (A) into the Poring Basin
Reliability Check of Runoff Records at the Basin (A)
Synthesizing Lacked Data
CorrelationAnalysis of Alternative Basin (A) and the Poring River
Test of Consistency of Rainfall Records
CorrelationAnalysis of Rainfall Records
Estimation of Daily Rainfall
Collection of Rainfall Data
Confirmation of Measurement Condition
Observation of Rainfall&Runoff Data in the Poring Basin
Development of Rainfall‐RunoffSimulation Model (Tank Model)
Estimation of Long‐term Runoff at the Poring Intake Sites
Synthesizing Data by Tank Model Simulation
Runoff Analysis Development of HydrologicalModel Rainfall Analysis
Final Report
Preparatory Survey on North Sumatra Mini 3-20 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.10 Comparison of Hydrological and Geological Features No. River Basin Catchment Area Isohyetal Line Runoff Data Availability*1 Major Geology*2 Remarks
1 Poring-1 87.5 km2
2,500~3,000 mm 2014 to date MPisl, Tmvo Study Area Poring-2 91.0 km2
2 Pasar Sirongit 350.6 km2 1,500~2,000 mm 1991~2013 Qvt, Tmvo
3 Dolok Sanggle 50 km2 1,500~2,500 mm 2001~2013 Qvt
4 Marade 163.8 km2 1,500~2,500 mm 2000~2013 Qvt
5 Kolang 464.4 km2 2,500~4,000 mm 2007~2013 MPisl, Tmba
6 Hapesong Baru 2,773 km2 1,500~4,000 mm 1992~2013 Qvt, Tmvo
7 Sipansihaporas 196.0 km2 3,500~4,000 mm Not obtainable Qvt, Tmba Existing HPP
Note: *1: Out of available years, only the first and last years are shown. *2: MPisl = Sibolga Granite Complex (granodiorites, granites and diorites), Tmvo = Toru Volcanic Formation (andesites, agglomerates, and breccias), Qvt = Toba Tuff (rhyodacitic ignimbrites), Tmba = Barus Formation (coarse to fine sandstones sometimes arkosic and/or micaceous, carbonaceous shales, and coals)
Source: BWS Sumatera II, BMKG, and Geological Research and Development Centre, Indonesia
Under these circumstances, the following river basins were excluded from the alternative subject area
with different reasons.
a) The catchment area of Pasar Sirongit has been already developed and therefore its land use situation is quite different from the Poring River basin. It will be necessary to consider the impact of water utilization to the discharge data. Actually, the average discharge is decreasing in recent years from 18.20 m3/s (1992~1998) to 11.03 m3/s (2006~2013).
b) The discharge data of Dolok Sanggle is not reliable because the same H-Q curve is used even after the gauging station was moved to 5 km downstream in the mid-2000s. Pre-FS review report also pointed out that its runoff coefficient is over 100%.
c) The Silang River that has the Marade Gauging Station flows into the Straits of Malacca side, although the Poring River flows to the Indian Ocean. Besides, since its watershed is located at high ground, the topographic condition is different from the Poring watershed.
d) Hapesong Baru has a too-large catchment area compared with the Poring catchment. Also, the watershed has various geological features due to its large area. This makes hydrological simulation complex and uncertain.
e) The discharge data of Sipansihaporas were not provided by PLN despite the repeated request by the JICA Survey Team.
The only remaining alternative is the Kolang River basin. Actually, its catchment area is almost five times
larger than the Poring-1 intake catchment, however the geological and topographical conditions are
similar to the Poring River as shown in Table 3.4.10. The Kolang River originates from the same
mountain range as the Poring River and flows into the Indian Ocean. Besides, the Kolang River basin has
not developed yet and therefore it is covered mostly by forest as is the case with the Poring River basin.
Therefore, the Kolang River basin was selected as an alternative basin.
1) Correlation of the Stream Flow between Poring Bridge and Kolang Stations
As described in Section 3.4.5 (3), a new water level gauge is installed and fixed to the foundation at
Kolang Water Level Gauging Station in July 2015.
Final Report
Preparatory Survey on North Sumatra Mini 3-21 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Figure 3.4.13 shows the scatter plot of concurrent
observed stream flow data at Poring Bridge and
Kolang Station from June 2015 to July 2015. It is
noted that the old rating curve that converts water
level to discharge, is tentatively used to estimate
the discharge of the Kolang River since the rating
curve for the new water level gauge has not been
updated yet. As shown in the figure, the data is
spotted close to the regression line. And the
correlation coefficient is calculated at 0.82, which
is high enough to say they are well correlated.
Accordingly, it is adequate to select the Kolang
River basin as the alternative basin for the Poring
River.
(3) Review of H-Q Curve (Water Level – Discharge Rating Curve)
Figure 3.4.14 (A) presents three kinds of H-Q curve as well as the plots of discharge data measured by
BWS Sumatera II (BWS) at the Kolang Gauging Station between 1986 and 2014. According to BWS, the
discharge data of Kolang is calculated by using these H-Q curves, which were developed by Puslitbang
SDA7. Since the trend of measured discharge largely changed from 1990 to 2000, and there are large gaps
in the water level record between the discharge measurement and water level monitoring record before
2010, it was determined that only 2010 data is used in this study. Accordingly, the H-Q curve is
constructed using discharge measurement data after 2010 as shown in Figure 3.4.14 (B).
7 Pusat Penelitian dan Pengembangan Sumber Daya Air (Center for Research and Development of Water Resources)
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
0.0 20.0 40.0 60.0
Poring Bridge
Discharge
(m3/s)
Korang Discharge (m3/s)
Source: JICA Survey Team
Figure 3.4.13 Scatter Plot of Stream Flow Measured at Poring Bridge and Kolang Observatories (June 2015 to July 2015)
Final Report
Preparatory Survey on North Sumatra Mini 3-22 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(A) Measured Discharge Data and H‐Q Curve of BWS Sumatera II (B) Revised H‐Q Curve
Source: BWS Sumatera II, the JICA Survey Team
Figure 3.4.14 Discharge Data Measured by BWS Sumatera II and Revised H-Q Curve
By using the discharge measurement data since 2010, the following H-Q rating curve was obtained.
Q = 4.928 x (H + 2.139)2
where, Q: discharge (m3/s),
H: water level (m)
(4) Converting Discharge at Kolang Gauging Station to the Proposed Poring-1 Intake Site
The discharge of the Kolang Station is converted to the discharge at the proposed Poring-1 Intake site by
using the following formula.
Where, QPoring(y, m, d) : daily discharge at the proposed Poring-1 Intake site on day d, month m, and year
y (d/m/y) (m3/s)
QKolang(y, m, d) : daily discharge at Kolang Station on d/m/y (m3/s)
RainPoring(y, m) : monthly basin rainfall at the proposed Poring-1 Intake site on m/y (mm/month)
RainKolang(y,m) : monthly basin rainfall at Kolang Station on m/y (mm/month)
C.A.Poring : catchment area of the proposed Poring-1 Intake (km2)
C.A.Kolang : catchment area of the Kolang Station (km2)
As shown in the equation, the discharge at Kolang Station is converted by the ratio of basin mean rainfall
and ratio of catchment area. By using the above equation, 6.6-year data from 2005 to 2015 except the
missing period is estimated.
(5) Discharge Measurement of the Poring River at the Poring Bridge
1) Discharge Measurement at Poring Bridge and Pargaringan Bridge
After May 2015, discharge measurement was conducted 10 times at the Poring Bridge and the
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 10 20 30 40 50 60
Water Level (m)
Discharge (m3/s)
1986/11/171992/8/301992/10/131992/10/171993/1/241993/6/291993/10/131993/12/51994/5/51994/5/291995/1/312002/4/162007/7/192008/10/142009/6/82010/6/192010/10/82011/3/262011/9/232013/5/52014/5/72014/10/72014/12/10HQ 2007HQ 2009‐11,13HQ 2012
Year
2007 Q= 99.7 (H‐ 0 ) 2.8
2008
2009 Q= 41.65 (H‐ 0.1 ) 1.375
2010 Q= 41.65 (H‐ 0.1 ) 1.375
2011 Q= 41.65 (H‐ 0.1 ) 1.375
2012 Q= 45.5 (H+ 0.02 ) 2.15
2013 Q= 41.65 (H‐ 0.1 ) 1.375
1990‐2011
1991‐2011
1990‐2008
no information
‐‐‐
H‐Q Curve
no water level record
Base Discharge
1986‐1996
1986‐1996
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
0.0 20.0 40.0 60.0 80.0 100.0
Gau
ge Heigh
t (m
)
Discharge (m3/s)
H‐Q Rating Curve at Kolang WL .Gauge
Station
H‐Q Curve
Observed Discharge
(2010 ‐ 2014)
Kolang
Poring
Kolang
PoringKolangPoring AC
AC
myRain
myRaindmyQdmyQ
..
..
,
,,,,,
Final Report
Preparatory Survey on North Sumatra Mini 3-23 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Pargaringan Bridge, respectively. The Pargaringan Bridge is located along the Pargaringan River, an
adjacent river to the Poring River, and more accessible by car compared with the Poring Bridge. By using
the measurement results, H-Q rating curves are prepared as shown in Figure 3.4.15.
Poring Bridge (C.A.= 91.5 km2) Pargaringan Bridge (C.A.= 76.5 km2)
Source: JICA Survey Team
Figure 3.4.15 H-Q Rating Curves at Discharge Measurement Points
2) Observed Runoff Data
By using the above H-Q curves and daily water level records from June 2014 to September 2015, daily
discharge is computed as shown in Figure 3.4.16. Since water level records from June to November 2014
are available only at Pargaringan Bridge, the discharge at Pargaringan Bridge is converted to the planned
intake sites of Poring-1 and Poring-2 with the respective catchment area ratios. Thus, more than one year
continuous runoff data is obtained. The runoff coefficient of one year from September 2014 to August
2015 is estimated at 68.3% as shown in Table 3.4.11.
Table 3.4.11 Runoff Coefficient Estimated by Observed Data in 2014-2015 Rainfall at Poring Bridge (1-year: 1 September 2014 ~ 31 August 2015) 4,605 mm
Runoff at Poring Intake Sites (1-year: 1 September 2014 ~ 31 August 2015) 3,147 mm Runoff Coefficient 68.3%
Source: JICA Survey Team
Source: JICA Survey Team
Figure 3.4.16 Daily Rainfall and Discharge at the Intake Sites
0.0
0.2
0.4
0.6
0.8
1.0
0 5 10 15 20
Gauge
Height (m
)
Discharge (m3/s)
H‐Q Curve
Obs.Q
Q = 13.84* (H + 0.357 )^2
0.4
0.6
0.8
1.0
1.2
1.4
0 5 10 15 20
Gauge
Height (m
)
Discharge (m3/s)
H‐Q Curve
Obs.Q
Q = 15.21 * (H ‐ 0.282 )^2
0
20
40
60
80
100
120
140
1600
10
20
30
40
50
60
70
80
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Daily Rainfall (m
m/day)
Daily Average
Discharge
(m
3/s)
Rainfall
Poring Bridge
Discharge Measurement (Poring Bridge)
Converted from Pargaringan Data
Year: 2014 Year: 2015
Final Report
Preparatory Survey on North Sumatra Mini 3-24 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(6) Daily Stream Flow Simulation by Tank Model
For the period where the Kolang discharge data is not available, the stream flow at the proposed Poring-1
Intake site is directly estimated by hydrological model, and “Tank Model” was selected as the
hydrological model.
The parameter of the tank model is determined to minimize the square root of the sum of the square of the
difference between the calculated and observed discharge as shown in the following equation:
Min ∑ , , . , ,
Where, Qobs(y, m, d) : observed daily discharge at the Poring Bridge on d/m/y (m3/s)
Qcalc.(y, m, d) : calculated daily discharge of the Poring River at the Poring Bridge on d/m/y (m3/s)
N : number of data
For minimization of above equation, an optimization program is applied to search the Tank Model
parameters. There are several studies to apply the optimization program for determining Tank Model
parameter such as Tanakamaru 8 , and recently the tank model parameter is sought by applying
metaheuristic optimization techniques. In this survey, particle swarm optimization9,10 is used as a
metaheuristic optimization method and tank model parameters are determined so as to minimize the
deviation between observed and calculated expressed by the equation above.
The tank model parameter determined by the optimization program is shown in Figure 3.4.17. Figure
3.4.18 shows the hydrograph of simulated and observed discharge at the Poring Bridge. The duration
curve of the simulated and observed discharge at the Poring Bridge is shown in Figure 3.4.19.
8 H.Tanakamaru, “Parameter Estimation for the Tank Model using Global Optimization”, Journal of Agricultural Engineering No.178, pp103-112, 1995. 9 T. Tada, “Optimization of Runoff Model Parameter by PSO Algorithm”, Journal of Hydrology and Water Resources, Vol 20, No.5 September 2007. (Original article is written in Japanese.) 10 C.A.G.Santos et al. “Application of a Particle Swarm Optimization to the Tank Model”, Risk in Water Resources Management (Proceedings of Symposium H03 held during IUGG2011 in Melbourne, Australia, July 2011) (IAHS Publ. 347, 2011).
Final Report
Preparatory Survey on North Sumatra Mini 3-25 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.4.17 Tank Model Parameter for the Runoff at the Poring Bridge
Source: JICA Survey Team
Figure 3.4.18 Discharge Hydrograph of Simulated and Observed Discharge of the Poring River
at the Poring Bridge from 2014 to 2015
As seen in Figure 3.4.19, the simulation results of low flow discharge indicate relatively acceptable
correspondence with the observed discharges, and therefore, it is supposed to be accurate enough to
estimate low flow to be used for the design of hydropower facilities.
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
160.00
180.00 0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00
45.00
50.00
2014/Jul 2014/Aug 2014/Sep 2014/Oct 2014/Nov 2014/Dec 2015/Jan 2015/Feb 2015/Mar 2015/Apr 2015/May 2015/Jun 2015/Jul 2015/Aug
Rainfall (m
m)
Discharge
(m3/s)
Year/Month
Rainfall
Observed
Calculated
h1, 3
h1,2 h1,1
h2, 2
h2,1
wl1
d1, 4
d1,3
d1,2
d1,1
d2,1
d2,2 wl2
wl4
wl3 d3,1
h3, 1
h4, 1 d4,1
Inf.1
Inf.2
Inf.3
Inf.4
Abbr. Tank Col‐1
Initial depth wl1 20
No. of lateral hole 3 3
Height of hole 1 h1,1 117.972
Size of hole 1 d1,1 0.214
Height of hole 2 h1,2 68.306
Size of hole 2 d1,2 0.075
Height of hole 3 h1,3 0.047
Size of hole 3 d1,3 0.000
Height of infil. Hole d1,4 1.920
Size of infil. hole Inf.1 0.524Initial depth wl2 30
No. of lateral hole 2 2
Height of hole 1 h2,1 20.000
Size of hole 1 d2,1 0.099
Height of hole 2 h2,2 0.012
Size of hole 2 d2,2 0.001
Size of infil. hole Inf.2 0.525
Initial depth wl3 50
No. of lateral hole 1 1
Height of hole 1 h3,1 5.000
Size of hole 1 d3,1 0.050
Size of infil. hole Inf.3 0.492
Initial depth wl4 500
No. of lateral hole 1 1
Height of hole 1 h4,1 0.162
Size of hole 1 d4,1 0.007
Size of infil. hole Inf.4 0.003
Top Tank
2nd Tank
3rd Tank
4th Tank
Parameter of Tank Model Parameter Identification Found by Optimization Model
Final Report
Preparatory Survey on North Sumatra Mini 3-26 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.4.19 Comparison of Flow Duration Curve of the Simulated and Observed Stream
Flow Discharge of the Poring River at the Poring Bridge
(7) Compilation of the Result of Low Flow Analysis
As the result of the above low flow analysis, the continuous long-term daily flow of the Poring River at the
Poring-1 Intake site is estimated for approximately ten-year duration from January 2005 to August 2015. For
the preparation of the daily flow data, 79 months data is estimated from the Kolang River discharge data, five
months data is converted from the Pargaringan River, nine months duration is taken from the Poring River
stream flow monitoring result. The rest of 35 months duration data is estimated by the Tank Model. The
reference of the data for estimation of the daily flow at Poring-1 Intake site is shown in Table 3.4.12.
Table 3.4.12 Reference of the Poring-1 Intake Site Daily Flow
Source: JICA Survey Team
The monthly average of the estimated stream flow of the Poring River at the Poring Bridge is shown in Table
3.4.13, and flow duration curve is shown in Figure 3.4.20.
According to the result, the standard deviation of the annual average of the Poring River discharge at the
Poring Bridge is 0.87 m3/s, and this value corresponds to 11.5% of the average flow. Thus, the yearly
fluctuation of annual average is judged to be small.
0
5
10
15
20
25
30
35
40
45
50
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Discharge
(m3/s) [ Full Scale ]
Exceedance Probability in Percent (%)
Comparison of Calculated Q and Obserbed Q at Poring.
Calculated Daily Dsicharge
Observed Daily Dsicharge
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2005 K K K K K K K K K K K K
2006 K K K K K K K K K K K T2007 K K K K K K K K K K K K2008 T T T T T T T T T T T T2009 K K K K K K K K K K K K2010 K K K K K K K K K K K K2011 K K K K K K K K K K K K2012 T T T K K K K K K K K T2013 T T T T T T T T T T T T2014 T T T T T T Parg. Parg. Parg. Parg. Parg. Po2015 Po Po Po Po Po Po Po Po
"K": Estimated from the Kolang River discharge"T": Estimated by tank model"Parg.": Measured record at the Pargaringan bridge"Po": Measured record at the Poring bridge
Final Report
Preparatory Survey on North Sumatra Mini 3-27 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.13 shows that the site has no distinct wet and dry season, and the difference of the monthly average
discharge of the wettest month (December) and the driest month (July) is around 3 m3/s and the minimum
monthly flow is over 4.4 m3/s as shown in the table.
Table 3.4.13 Monthly Average Discharge at the Poring-1 Intake Site
Source: JICA Survey Team
Figure 3.4.20 Flow Duration Curve at the Poring-1 Intake Site from January 2005 to
September 2015
3.4.6 FLOOD ANALYSIS
(1) General Approach
The data related to the flood discharge at the project site is extremely limited, and long-term hourly
rainfall records are not available in and around the project area. Therefore, the following methods were
applied to obtain a comprehensive solution for the flood discharges through comparison:
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Average
2005 6.25 6.27 6.05 6.14 6.72 5.95 6.11 5.98 6.26 6.47 6.91 6.53 6.30
2006 6.87 6.18 7.25 6.22 6.17 6.14 7.13 8.25 8.44 8.37 8.32 12.11 7.622007 6.52 6.05 6.79 6.23 6.39 6.23 6.30 6.72 7.57 6.43 6.35 6.47 6.502008 8.41 10.05 6.23 5.38 5.00 5.86 5.24 8.16 7.15 8.79 9.70 10.41 7.532009 10.54 7.96 8.20 6.60 5.90 6.21 7.48 6.65 6.24 7.62 8.36 6.63 7.372010 7.46 8.90 7.82 8.78 8.09 6.06 6.13 5.92 6.40 7.52 6.89 6.36 7.192011 7.34 6.47 6.24 6.68 6.60 5.99 6.06 6.66 7.18 7.44 9.11 10.96 7.232012 10.42 9.75 9.63 6.65 6.13 6.20 6.52 7.38 8.98 9.43 16.73 11.80 9.142013 10.35 12.39 10.07 9.73 8.95 6.14 5.32 5.49 6.99 6.14 5.47 10.84 8.162014 7.93 5.50 4.40 6.98 8.06 7.37 5.18 6.13 6.38 6.33 12.87 8.76 7.162015 8.39 8.69 9.46 9.80 10.54 8.80 7.37 7.41 8.81
Average 8.23 8.02 7.47 7.20 7.14 6.45 6.26 6.80 7.16 7.45 9.07 9.09 7.53
Stand. Dev. 1.58 2.16 1.76 1.52 1.60 0.88 0.82 0.91 0.94 1.13 3.40 2.40 0.87Maximum 10.54 12.39 10.07 9.80 10.54 8.80 7.48 8.25 8.98 9.43 16.73 12.11 9.14Minimum 6.25 5.50 4.40 5.38 5.00 5.86 5.18 5.49 6.24 6.14 5.47 6.36 6.30
0
10
20
30
40
50
60
70
0% 20% 40% 60% 80% 100%
Discharge
(m3/s)
Exceedance Probability in Percent
Discharge
(m3/s )
Discharge 95‐day 25% 8.1
Discharge 185‐day 50% 6.7
Discharge 275‐day 75% 5.9
Discharge 292‐day 80% 5.7
Discharge 328‐day 90% 5.4
Discharge 355‐day 97% 4.5
Maximum 61.9
Minimum 3.3
Average 7.5
Standard Deviation 3.0
Duration
Final Report
Preparatory Survey on North Sumatra Mini 3-28 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Synthetic Unit Hydrograph Method of U.S. Soil Conservation Service (SCS)11
Rational Formula Method to estimate peak flood discharge
Checking using the Creager’s Curve
(2) Rainfall Analysis
1) Depth-Area-Duration (DAD) Analysis
1-a) Depth-Duration (DD) Analysis
Generally, heavy rainfall occurs intensively in a short duration and sporadically in a limited area.
Although it is desirable to take into account the actual rainfall patterns that occurred in the target area
in the past, enough hourly rainfall data is not available in and around the Poring River basin.
Therefore, the design rainfall curve is determined as a centralized type of hyetograph.
1-b) Depth-Area (DA) Analysis
Considering the abovementioned particularity of heavy rainfall occurrence, the average depth of
storm rainfall (basin mean rainfall) is likely to be smaller than the point depth of storm rainfall. To
estimate the basin mean rainfall from the point rainfall, the area reduction factor showing the ratio of
basin mean rainfall to point rainfall is introduced as expressed below.
Pb = fa x P0
where, Pb : Basin mean rainfall [mm] P0 : Point rainfall [mm] fa : Area reduction factor
The area reduction factor (fa) was decided according to the criteria. As shown in Figure 3.4.21, the
area reduction factor of both Poring-1 and Poring-2 was estimated at 0.96
11 Former name of Natural Resources Conservation Service (NRCS), U.S. Department of Agriculture
Final Report
Preparatory Survey on North Sumatra Mini 3-29 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: Department of the Army, United States Army Corps of Engineers, Engineer Manual “Flood – Runoff Analysis”
Figure 3.4.21 Area-Adjustment of Point Rainfall
2) Probable Point Rainfall
The Hobuan Rainfall Gauging Station is used for flood analysis because it provides the longest term of
annual maximum rainfall record and also it is the nearest station to the project area. The annual maximum
daily rainfall at Hobuan Station for 21 years in total between 1984 and 2014 are enumerated in Table
3.4.14.
Table 3.4.14 Annual Maximum Daily Rainfall at the Hobuan Gauging Station Year 1984 1985 1986 1987 1988 1989 1991 1992 1993 1994 1997
Date 26-Feb 19-Aug 1-Nov 1-May 5-Mar 11-Nov 27-Nov 6-May 22-Apr 24-Aug 23-Aug
Rainfall (mm/day) 130.9 77.0 180.5 97.5 94.0 59.4 97.5 94.2 90.0 70.2 40.0
Year 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 ---
Date 24-Aug 6-Sep 5-Nov 7-Nov 21-Jun 15-May 4-Nov 26-Aug 10-Dec 14-May ---
Rainfall (mm/day) 200.0 137.0 150.0 220.0 210.0 200.0 145.5 99.3 190.4 130.0 ---
Note: The data of the years 1990, 1995, 1996 and 1998 to 2004 were not obtainable.
Source: BWS Sumatera II
The frequency curves of maximum daily point rainfall at the Hobuan Rainfall Gauging Station is given in
Figure 3.4.22. Different distribution types of curves are plotted on a lognormal probability paper. Besides,
the probable maximum daily rainfalls estimated for the respective return periods with the respective
distribution types are summarized in Table 3.4.15.
≈96
Poring1 : 87.4 km2 (33.75 mi2)
Poring‐2 : 91.0 km2 (35.14 mi2)
96.3
96.0
Final Report
Preparatory Survey on North Sumatra Mini 3-30 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Lognormal Probability Paper
Legend: Exp = Exponential distribution Gumbel = Gumbel distribution SqrtEt = SQRT‐wxponential type maximum
distribution Gev = Generalized extreme value distribution LP3Rs = Log Pearson type III distribution
(real number space method) LogP3 = Log Pearson type III distribution
(logarithmic space method) Iwai = Iwai distribution Note: The graph is created by the hydrological statistics program developed by Japan Institute of Country‐ology and Engineering.
Source: JICA Survey Team
Figure 3.4.22 Annual Maximum Daily Rainfall with Different Distribution Types
Table 3.4.15 Probable Maximum Daily Point Rainfall at Hobuan Distribution Type Exp Gumbel SqrtEt Gev LP3Rs LogP3 Iwai
SLSC (99%) 0.075 0.051 0.058 0.046 0.04 0.035 0.04 Return Period (yrs) Daily Point Rainfall (mm/day)
100 354.7 310.7 391.6 277.3 222.7 273.7 283.4 50 311.3 279.2 336.4 257.9 217.5 255.3 260.4 20 254.0 237.2 268.8 229.0 207.1 227.6 228.2 10 210.7 204.7 221.2 203.8 194.7 203.2 201.9 5 167.3 170.8 176.1 174.7 175.9 174.4 172.7 2 110.0 119.7 116.5 124.4 130.8 123.9 123.8
Note: The rainfall was computed by the hydrological statistics program developed by the Japan Institute of Country-ology and Engineering. Source: JICA Survey Team
As seen in the figure, appropriate plots for judging the compatibility of 100-year probable rainfall were
not obtained from the limited data of 21 years.
In general, the distribution types of Gumbel, SqrtEt, or Gev should be preferentially selected rather than
the others if their SLSC12 values are less than 0.04, which is a criterion value for the selection of
distribution type, because the said three types are based on the extremal theory, while the other types are
determined by specific regional characteristics13.
In this study, the SLSC values of Gumbel, SqrtEt, and Gev are 0.051, 0.058, and 0.046, respectively.
12 SLSC value is an index to estimate compatibility with observed data. It is obtained by indexing the difference of probable rainfalls between “when the observed data are aligned by a plotting position formula” and “when estimated by probability distributions”. The compatibility is better as a SLSC value is small. 13 Draft Handbook on Planning for Small and Mideun-sized Rivers (September 1999, Japan Institute of Country-ology and Engineering)
Final Report
Preparatory Survey on North Sumatra Mini 3-31 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Only the Log Pearson type III, logarithmic space method (LogP3) provides an acceptable SLSC value of
0.035, which is lower than 0.04. Furthermore, even compared with Gev, which is the second-best
distribution type in term of adaptability and reliability, the differences of daily point rainfall for each
return period between LogP3 and Gev are less than 2%, and also both distribution curves are quite similar
particularly in the range of high probable scales including 100-year and 200-year. Thus, LogP3 is adopted
as a distribution type for this study.
3) Probable Basin Mean Rainfall
Applying the design area reduction factor of 0.96, the probable basin mean one-day rainfall with various
return periods at the intake sites of Poring-1 and Poring-2 are estimated as follows:
Table 3.4.16 Probable Basin Mean Rainfall for the Poring River Basin Return Period [year] 2 5 10 20 50 100 200 400
Probable Daily Basin Rainfall [mm/day] 119 167 195 218 245 263 279 293
Source: JICA Survey Team
(3) Design Flood
1) SCS Unit Hydrograph
A flood hydrograph is required for the planning of intake weirs. The unit hydrograph method established
by the U.S. Soil Conservation Service (SCS), which has been employed for various water resource
development projects to date, was applied to estimate the flood hydrograph simply from the probable
rainfalls. Originally, the SCS suggested that this method is applied to the catchment area not exceeding 20
ml2 (= 51.8 km2). However, even the lower Poring River basin represents the characteristic of
mountainous river, and thus, there is no significant difference in catchment characteristics between upper
and lower catchments even if the entire catchment of about 90 km2 is devided into two parts. Therefore, it
was determined in this study that the SCS method is applied to the entire catchment collectively. The
standard dimensionless unit hydrograph given by the SCS synthetic method is shown in Figure 3.4.23
Source: US Soil Conservation Service
Figure 3.4.23 Standard Dimensionless Hydrograph by SCS
The calculation procedures to determine the SCS unit hydrograph are described below.
0.00.10.20.30.40.50.60.70.80.91.0
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Q/Q
p
T/Tp
Final Report
Preparatory Survey on North Sumatra Mini 3-32 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
SCS Unit Hydrograph Poring-1 Poring-2 Qp = 0.208 * A * Q / tp (US Soil Conservation Service Unit Hydrograph)
Qp : Peak discharge [m3/sec] 9.1 9.5 [m3/sec/mm]A : Catchment area [km2] 87 91 [km2] Q : Total volume of the unit graph (= 1 mm) 1 1 [mm] tp : Time to peak [hours] 2.00 2.00 [hours]
Time to Peak tp = 2 * tc / 3 2.0 2.0 [hours]
1.73 1.73 [hours] Rainfall Duration
D = 0.133 * tc 1.0 1.0 [hours] 0.35 0.35 [hours]
Flood Concentration Time tc = 3.97 * L0.77 * S-0.385 (Kirpich's formula) 2.6 2.6 [hours]
tc : Flood concentration time [min] 156 157 [min] L : Maximum length of travel of water [km] 19.7 22.2 [km] S : Average slope (= H/L) 0.028 0.035 H : Difference in elevation between the remote point in the basin and the outlet 550 788 [m]
The SCS unit hydrograph is derived based on the flood concentration time and mean rainfall in the unit
basin. The unit hydrograph is constructed for a unit rainfall of 1.0 mm. The peak discharge of the unit
hydrograph is calculated as follows:
pp t
QAQ 208.0
where, Qp : Peak discharge [m3/sec]
A : Catchment area [km2]
Q : Total volume of the unit graph (= 1 mm)
tp : Time to peak [hours]
The relationship of the time to peak (tp), and rainfall duration (D) with the time to concentration (tc) is
given below.
32 c
p
tt
0.133
Flood Concentration Time
Flood concentration time is defined as the traveling time from the most remote point in the catchment to
the forecast point, is given by the following formula.
385.077.097.3 SLtc (Kirpich's formula)
where, tc : Flood concentration time [min]
L : Maximum length of travel of water [km]
S : Average slope (= H/L)
H : Difference in elevation between the remote point in the basin and the outlet
The calculation results for Poring-1 and Poring-2 are respectively as follows:
Final Report
Preparatory Survey on North Sumatra Mini 3-33 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Poring-1 Poring-2
tc = 156 minutes (= 2.6 hours), 157 minutes (= 2.6 hours)
Qp = 9.1 m3/sec/mm, 9.5 m3/sec/mm
tp = 2.0 hours, 2.0 hours
D = 1.0 hour, 1.0 hour
Design Hyetograph
As there are no hourly rainfall data available in/around the project site, the design rainfall pattern
hyetograph was assumed using the following formula:
[Mononobe's Formula] 3
2
24 24
24
t
Rrt
[mm/hr] (for 24 hours)
where, rt : Average rainfall intensity in flood duration [mm/hr]
R24 : Probable daily rainfall [mm/day]
t : Time of concentration of runoff [hour]
A type of rainfall intensity pattern, namely, central concentration pattern in 24 hours is assumed for the
hyetograph for the reasons set forth below.
i) In general, the central concentration pattern is stochastically highly-reproducible compared with the forwards or backwards concentration patterns.
ii) The average of 48 rainfall patterns created based on the recorded hourly rainfall data in other areas in Indonesia became a central concentration pattern in terms of results.
Base Flow
In order to estimate the direct flood runoff, the base flow should be separated from the hydrograph. Based
on the observed discharge of the Poring River from January 2015 to May 2015, the base flow in both of
the Poring-1 and Poring-2 River basins during rainy season was estimated at 9 m3/s.
Direct Runoff Coefficient
In order to estimate the flood hydrograph by mean of unit-graph, it is required to compute the excess
rainfall by separating effective rainfall from storm rainfall, which generally includes losses from
interception, depression, soil moisture change, evaporation, and transpiration. Based on the observed
discharge and rainfall of the Poring River from January 2015 to May 2015, the maximum direct runoff
coefficient is 0.5 among floods which have hourly rainfall intensity of more than 20 mm. In this study,
the direct runoff coefficient for the proposed intake sites was assumed at 0.625 from the empirical runoff
coefficients provided in the Japanese Investigation Manual. This value is the average of the runoff
coefficients for the appropriate topographic features for the project site, as shown in Table 3.4.17.
Final Report
Preparatory Survey on North Sumatra Mini 3-34 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.17 Runoff Coefficient Depending on the Catchment’s Feature Topography or River Runoff Coefficient f Adopted Features
Steep mountains 0.75~0.90 - Tertiary mountains or hills 0.70~0.80 - Gently undulating lands and forest 0.50~0.75 0.625 Flat cultivated fields 0.45~0.60 - Paddy field under irrigation 0.70~0.80 - Mountainous river 0.75~0.85 - Small river in flat land 0.45~0.75 - Large river in flat land 0.50~0.75 -
Source: Technical Criteria for River Works: Practical Guide for Investigation (Ministry of Land, Infrastructure, Transport and Tourism, Japan)
Design Flood Hydrographs
The design flood hydrographs were obtained using the SCS unit hydrograph. Figure 3.4.24 shows the
hydrographs for 20-year, 100-year, and 200-year probable floods as well as their hyetographs. The peak
discharge for each flood is summarized in Table 3.4.18.
Poring‐1 Poring‐2 Source: JICA Survey Team
Figure 3.4.24 Hydrograph for 20-year, 100-year, and 200-year Floods at the Intake Sites
Table 3.4.18 Peak Flood Discharge at the Proposed Intake Sites by SCS Method Return Period
Daily Point Rainfall
Area Reduction Factor
Daily Basin Rainfall R24
Direct Runoff
Coefficient
Base Flow (assumed)
Flood Peak Discharge
R24 Poring-1 Poring-2 Poring-1 Poring-2 Poring-1 Poring-2[Year] [mm] [%] [%] [mm] [mm] (assumed) [m3/sec] [m3/sec] [m3/sec]
2 123.9 96 96 119 119 0.625 9.0 320 330 5 174.4 96 96 167 167 0.625 9.0 440 460
10 203.2 96 96 195 195 0.625 9.0 510 540 20 227.6 96 96 218 218 0.625 9.0 570 600 50 255.3 96 96 245 245 0.625 9.0 640 670
100 273.7 96 96 263 263 0.625 9.0 680 710 Source: JICA Survey Team
2) Rational Formula
Flood peak discharges for 100-year return period at the intake sites of Poring-1 and Poring-2 are
estimated at 887 m3/s and 866 m3/s, respectively, by means of the rational formula method as shown in
Table 3.4.19 below. They are about 1.30 and 1.22 times as large as the 100-year flood discharge
estimated by SCS Method. The details are described below.
0
20
40
60
800
200
400
600
800
1,000
0 12 24 36 48 60 72
Effective Rainfall [m
m/hour]
Discharge
[m3/sec]
Time [hours]
Rainfall: 200‐yrRainfall: 100‐yrRainfall: 20‐yrDischarge: 200‐yrDiischarge: 100‐yrDischarge: 20‐yr
0
20
40
60
800
200
400
600
800
1,000
0 12 24 36 48 60 72
Effective Rainfall [m
m/hour]
Discharge
[m3/sec]
Time [hours]
Rainfall: 200‐yrRainfall: 100‐yrRainfall: 20‐yrDischarge: 200‐yrDischarge: 100‐yrDischarge: 20‐yr
Final Report
Preparatory Survey on North Sumatra Mini 3-35 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.19 Peak 100-year Discharge Estimated by Rational Formula Description Poring-1 Poring-2 Unit Remarks
Catchment Area at the Intake Site A 87.4 91.0 km2 Map 1:50,000
Runoff Coefficient f 0.625 0.625 --- Gently undulating lands and forest
Inflow Time from the Most Upstream Area T1 0.38 0.38 hr 1.18 km2 shown in Figure 3.4.26
Elevation at (U) shown in Figure 3.4.26 HU 1,175 1,175 El.m Map 1:50,000
Elevation at (D) shown in Figure 3.4.26 HD 625 387.5 El.m Map 1:50,000
Distance between (U) and (D) L 19,744 22,189 m Map 1:50,000
Slope of River: I = (HU-HD) / L I 0.0279 0.0355 --- = 1 / 37, 1 / 29
Flood Propagation Velocity W 3.5 3.5 m/s I = 1/100 or more
River Flow Time: T = (1/3,600) x (L/W) T2 1.57 1.76 hr Kraven’s formula
Flood Concentration Time: T = T1 + T2 T 1.95 2.14 hr ---
Daily Basin Rainfall R24 263 263 mm/day 100-yr rainfall
Average Rainfall Intensity: RT = (R24/24) x (24/T)2/3 RT 58.4 54.8 mm/hr Mononobe's formula
Peak Runoff Discharge: Qp = (1/3.6) x f x RT x A Qp 887 866 m3/s Rational formula
Source: JICA Survey Team
Source: JICA Survey Team
Figure 3.4.25 Topographical Measurement Points for Rational Formula Method
Rational Formula
[Rational Formula] ARfQ Tp 6.3
1 [m3/s]
where, Qp : Peak runoff discharge [m3/s]
f : Runoff coefficient
RT : Rainfall intensity of time duration [mm/hour]
A : Catchment area [km2]
Runoff Coefficient
The runoff coefficient was set as 0.625 for the same reason as the case of SCS unit hydrograph method as
mentioned above.
Flood Concentration Time
The flood concentration time was estimated as the total values of i) necessary inflow time to the most
upstream point of river and ii) necessary flowing time from the most upstream (U/S) point to the most
HU
HD‐1HD‐2
Poring‐1 Intake
Poring‐2 Intake
Most upstream area of 1.18 km2
Final Report
Preparatory Survey on North Sumatra Mini 3-36 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
downstream (D/S) point of river, which is the intake site in this case.
i) Necessary inflow time to the most upstream point of river In general, in the case of mountainous area, 30 minutes (0.5 hrs) are required for flowing into the most upstream point of river from its catchment area of 2 km2. In the Poring River basin, the time is 0.38 hours computed by multiplying 0.5 hours by a square root of the catchment area ratio (1.18/2.0).
ii) Necessary flowing time from the most U/S point to the most D/S point of the river The flowing time is estimated by Kraven’s formula
[Kraven’s Formula] W
LT
600,3
1 [hr]
I >1/100 1/100 - 1/200 <1/200
W 3.5 m/s 3.0 m/s 2.1 m/s
where, T : Total concentration time [hour]
L : Length of river [m]
W : Flood velocity [m/sec]
I : River slope
Rainfall Intensity
The rainfall intensity was estimated by using a common method of Mononobe’s Formula.
[Mononobe’s Formula] 3
2
24 24
24
T
RRT
[mm/hour]
where, RT : Rainfall intensity of time duration [mm/hour]
R24 : Daily rainfall [mm/day]
T : Total concentration time [hour]
3) Comparison of Design Flood by Various Methods
The peak flood discharges estimated by the SCS unit hydrograph method and the Rational Formula are
summarized in Table 3.4.20 for comparison. There are no definite reasons to justify the design flood
because of the limited availability of the flood records and hourly rainfall. However, the discharges
estimated by the SCS method almost fall within the acceptable range of Creager’s Curve, while each of
Rational Formula is considerably out of the range. It is therefore judged that the SCS method could be
applied for the study. The details of Creager’s Curve are described in the following clause.
Table 3.4.20 Comparison of Peak Flood Discharges
Return Period
Daily Basin Rainfall (LogP3 Distribution)
Flood Peak Discharge SCS Method Rational Formula Creager’s Curve
Poring-1 Poring-2 Poring-1 Poring-2 Poring-1 Poring-2 Poring-1 Poring-2 [year] [mm/day] [mm/day] [m3/sec] [m3/sec] [m3/sec] [m3/sec] [m3/sec] [m3/sec]
2 119 119 320 330 401 392 --- --- 5 167 167 440 460 563 550 --- ---
10 195 195 510 540 657 642 --- --- 20 218 218 570 600 735 718 186~371 190~381 50 245 245 640 670 826 807 --- ---
100 263 263 680 710 887 866 371~557 381~571 Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 3-37 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(4) Creager's Curve
The peak discharges of 20-year, 100-year, and 200-year probable floods were examined by plotting them
on the Creager’s Curve, which provides a comprehensive range of the regional characteristics of floods,
together with the discharges of other schemes in Sumatra Island as shown in Figures 3.4.26 to 28.
Flood peak discharges for the return periods of 20-year, 100-year, and 200-year in Sumatra Island are
supposed to be plotted on the Creager’s Curve with C = 10~20, 20~30, and 20~4014, respectively. The
Creager’s curve is computed by the following equations:
[Creager’s Curve] ap ACQ )3861.0()02832.046(
048.0)3861.0(894.0 Aa
where, Qp : Peak discharge of probable flood [m3/sec]
A : Catchment area [km2]
C : Creager's coefficient
Although the Creager’s Curve may provide only a rough indication, Figures 3.4.26 to 28 below indicates
that the 20-year, 100-year, and 200-year flood discharges estimated by SCS Method at the proposed
intake sites are within reasonable ranges as compared with the other projects in the region.
Source: JICA Survey Team
Figure 3.4.26 Comparison with 20-year Floods under Various Schemes in Sumatra
14 Hydroinventory and prefeasibility studies, Nippon Koei Co. Ltd., 1999
570
10
100
1,000
10,000
1 10 100 1,000 10,000
Discharge (m
3/s)
Catchment Area (km2)
Poring‐1
Other Schemes (20‐yr)C= 20C= 10Poring‐1
C=10
C=20
600
10
100
1,000
10,000
1 10 100 1,000 10,000
Discharge (m
3/s)
Catchment Area (km2)
Poring‐2
Other Schemes (20‐yr)C= 20C= 10Poring‐2
C=10
C=20
Final Report
Preparatory Survey on North Sumatra Mini 3-38 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.4.27 Comparison with 100-year Floods under Various Schemes in Sumatra
Source: JICA Survey Team
Figure 3.4.28 Comparison with 200-year Floods under Various Schemes in Sumatra
(5) Estimation of Probable Flood during Dry Season
The peak discharges of small-scale probable floods during the dry season from January to July are
estimated for the purpose of construction planning. The annual maximum daily rainfalls limited to the dry
season are enumerated in Table 3.4.21.
Table 3.4.21 Maximum Daily Rainfall during January-July at the Hobuan Gauging Station Year 1984 1987 1988 1991 1992 1993 1994 1997 2005 Date 26-Feb 1-May 5-Mar 13-Feb 6-May 22-Apr 12-Feb 17-May 2-Mar
Rainfall (mm/day) 130.9 97.5 94.0 60.4 94.2 90.0 51.2 40.0 118.0 Year 2006 2007 2008 2009 2010 2011 2012 2013 2014 Date 12-Mar 18-Feb 17-Mar 21-Jun 15-May 29-Mar 24-Jul 27-Feb 14-May
Rainfall (mm/day) 81.0 89.0 130.0 210.0 200.0 130.0 97.3 78.2 130.0 Note: The data of the years 1985, 1986, 1989, 1990, 1995, 1996 and 1998 to 2004 were not obtainable. Source: BWS Sumatera II
Although the SLSC values of all distribution types exceed 0.04, the LogP3 type provides the lowest value
of 0.042. The LogP3 type is therefore adopted as a distribution type for the dry season as well. The
probable maximum daily point rainfalls estimated with LogP3 are summarized in Table 3.4.22.
680
10
100
1,000
10,000
1 10 100 1,000 10,000
Discharge (m
3/s)
Catchment Area (km2)
Poring‐1
Other Schemes (100‐yr)C= 30C= 20Poring‐1
C=20
C=30
710
10
100
1,000
10,000
1 10 100 1,000 10,000
Discharge (m
3/s)
Catchment Area (km2)
Poring‐2
Other Schemes (100‐yr)C= 30C= 20Poring‐2
C=20
C=30
720
10
100
1,000
10,000
1 10 100 1,000 10,000
Discharge (m
3/s)
Catchment Area (km2)
Poring‐1
Other Schemes (200‐yr)C= 40C= 20Poring‐1
C=20
C=40
760
10
100
1,000
10,000
1 10 100 1,000 10,000
Discharge (m
3/s)
Catchment Area (km2)
Poring‐2
Other Schemes (200‐yr)C= 40C= 20Poring‐2
C=20
C=40
Final Report
Preparatory Survey on North Sumatra Mini 3-39 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 3.4.22 Probable Maximum Daily Point Rainfall for the Dry Season in Hobuan Return Period (yrs) 400 200 150 100 80 50 30 20 10 5 3 2 Rainfall (mm/day) 277.8 258.5 250.3 238.5 232.0 218.0 202.2 189.4 166.2 140.9 119.9 100.5
Note: The rainfall was computed by the hydrological statistics program developed by the Japan Institute of Country-ology and Engineering. Source: JICA Survey Team
Basically, the flood discharges are estimated by the SCS unit hydrograph method in the same way as the
above design flood. However, a runoff coefficient for the dry season is determined with a different
viewpoint. A runoff coefficient in the dry season is usually considered lower than the rainy season
because unsaturated soil absorb rain water particularly at the beginning of rainfall event, and therefore,
runoff becomes small compared with the case of rainy season. In this study, a runoff coefficient is
estimated by using hourly rainfall and hourly discharge data observed from January to May 2014 as
shown in Figure 3.4.29. The maximum hourly discharge during this period at the intakes of Poring-1 and
Poring-2 are estimated at 48 m3/s and 50 m3/s, respectively.
Note: Hourly discharge data between February 9 and 23 is missing. Source: JICA Survey Team
Figure 3.4.29 Hourly Rainfall and Discharge in Poring in the Dry Season
Since this rainfall is point rainfall, in some cases, the rainfall pattern does not directly correspond to the
discharge fluctuation. According to the observations of several hydrograph curves that produce favorable
response to hourly rainfall exceeding 20 mm/hr, it was found that the maximum runoff coefficient is
almost 0.35. Figures 3.4.30 expresses the flood hydrographs that produce the largest and second-largest
runoff coefficients during the observation period.
0
10
20
30
40
50
60
70
80
90
1000
10
20
30
40
50
60
70
80
90
100
1‐Jan 15‐Jan 29‐Jan 12‐Feb 26‐Feb 12‐Mar 26‐Mar 9‐Apr 23‐Apr 7‐May
Hourly Rainfall (m
m/hr)
Hourly Discharge
(m
3/s)
Rainfall Discharge: Intake‐1 Discharge: Intake‐2
Final Report
Preparatory Survey on North Sumatra Mini 3-40 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.4.30 Dry Season’s Flood Hydrographs for the Maximum Runoff Coefficients
By using the runoff coefficients of 0.35, the peak discharges of small-scale floods are estimated in the
same manner with the above design floods as summarized in Table 3.4.23. The peak discharge of 2-year
probable flood is estimated at 150 m3/s for both Poring-1 and Poring-2. This is almost three times larger
than the maximum hourly discharge recorded during the latest dry season and therefore it is considered
reasonable and safe.
Table 3.4.23 Peak Flood Discharge at the Proposed Intake Sites in the Dry Season Return Period
Daily Point Rainfall
Area Reduction Factor
Daily Basin Rainfall R24
Direct Runoff
Coefficient
Base Flow (assumed)
Flood Peak Discharge
R24 Poring-1 Poring-2 Poring-1 Poring-2 Poring-1 Poring-2[Year] [mm] [%] [%] [mm] [mm] (assumed) [m3/sec] [m3/sec] [m3/sec]
2 100.5 96 96 96 96 0.35 6.0 150 150 5 140.9 96 96 135 135 0.35 6.0 200 210
10 166.2 96 96 160 160 0.35 6.0 240 250 20 189.4 96 96 182 182 0.35 6.0 270 280
Source: JICA Survey Team
0
10
20
30
40
50
600
10
20
30
40
50
60
15‐Apr 5:00
15‐Apr 7:00
15‐Apr 9:00
15‐Apr 11:00
15‐Apr 13:00
15‐Apr 15:00
15‐Apr 17:00
15‐Apr 19:00
15‐Apr 21:00
15‐Apr 23:00
16‐Apr 1:00
16‐Apr 3:00
Hourly Rainfall (m
m/hr)
Hourly Discharge
(m
3/s)
Rainfall
Discharge: Intake‐1Discharge: Intake‐2
Runoff Coefficient = 0.332
0
10
20
30
40
50
600
10
20
30
40
50
60
7‐M
ay 5:00
7‐M
ay 7:00
7‐M
ay 9:00
7‐M
ay 11:00
7‐M
ay 13:00
7‐M
ay 15:00
7‐M
ay 17:00
7‐M
ay 19:00
7‐M
ay 21:00
7‐M
ay 23:00
8‐M
ay 1:00
8‐M
ay 3:00
Hourly Rainfall (m
m/hr)
Hourly Discharge
(m
3/s)
Rainfall
Discharge: Intake‐1Discharge: Intake‐2
Runoff Coefficient = 0.352
Final Report
Preparatory Survey on North Sumatra Mini 3-41 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
3.5 GEOLOGY
3.5.1 REGIONAL GEOLOGY
The geology of project site is classified as a part of the Sibolga Granite Complex. In early Permian, the
Sibolga Granite Complex intruded into the Kluet formation of Carboniferous to early Permian
meta-sediments. Outcrops of Kluet formation occur as roof pendants in the Sibolga Complex are strongly
hornfelsed.
In the late Oligocene, the earlier Palaeogene sediments were deformed and uplifted to produce an
extensive erosional unconformity. This area remained emergent until the early Miocene when a
widespread transgression occurred. In the present onshore area this resulted in the deposition of the
largely non-marine Barus formation which overstepped onto the geanticlines. Toba Tuff of the late
Pleistocene age covered the preformed valleys. Following the eruption of the Toba Tuffs, further
movements occurred. Although depressions may have existed along the faults prior to the Toba event, the
distribution of tuffs and the apparent lack of a thick ignimbrite sequence, suggest that these grabens
largely post-date this event.
Legend:
ALLUVIUM: coastal and fluviatile clays, silts, sands, and gravels, also fan deposits, landslips and in grabens some peat.
OLDER ALLUVIUM: sands, silts, and clays, minor gravels.
TOBA TUFF: rhyodacitic ignimbrites BARU FORMATION: coarse to fine sandstones sometimes arkosic and/or micaceous carbonaceous shales and coals.
KLUET FORMATION: metaarenites and argillites, often hornfelsed.
SIBOLGA GRANITE COMPLEX: granodiorites, granites and diorites
Source: Geological Map of the Padangsidempuan and Sibolga Quadrangles, Sumatra, Geological Survey Institute of Indonesia
Figure 3.5.1 Geological Map of North Sumatera
Puk
Tmba
Mpisl
Qvt
Qh Qp
Final Report
Preparatory Survey on North Sumatra Mini 3-42 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
3.5.2 GEOLOGICAL INVESTIGATION
(1) Scope of Work
The geological investigation composed of core drilling
with in-situ tests and laboratory tests was carried out for
the purpose of obtaining subsurface geological data of the
structures such as intake weir, head tank, penstock, and
powerhouse sites. Investigation items and their purposes
are as mentioned below.
a) Ground Mapping (Proposed Structural Layout Area)
b) Core Drilling (11 holes, 150 m in total)
Standard Penetration Test (SPT) in Soil (9 holes, 88
nos. in total)
Permeability Test in Soil (5 holes, 7 nos. in total)
Lugeon Test in Rock (3 holes, 3 nos. in total)
c) Laboratory Test (3 holes, and boulders sampled from
riverbed)
Location of geological investigation and location of drill points are shown in Figure 3.5.2.
Note: B-3 was cancelled because of rapid river flow Source: JICA Survey Team
Figure 3.5.2 Location Map of Drilling Sites
Source: JICA Survey Team B-4 (Head Tank-1) Drilling
Final Report
Preparatory Survey on North Sumatra Mini 3-43 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Results of the Investigations
The survey team received the summary of the drill-core observation with the results of in-situ tests, such
as Standard Penetration Test (SPT), Constant Head Test (CHT), and Lugeon Test.
3.5.3 GENERAL GEOLOGY AROUND THE PROPOSED STRUCTURE
The basement of the proposed structures in the project area, mainly consists of hard granite (the Sibolga
Granite Complex), locally of soft welded tuff (Toba Tuff). The geology of the project is composed of the
following:
(1) Granite (Gt)
The fresh part of base rock around the project site mainly consists of granite, which is coarse grained,
white to grey coloured, and very solid categorized in CH to CM rock grades. The preliminary joints
showing three directions are observed in 0.5-3 m unit, which are partly open and indicate high
permeability.
The thickness of weathered zone of granite increases up the slope, although fresh rock is observed around
the riverbed. From the middle to high elevation of slope, extremely weathered granite is discovered on the
surface outcrops, showing compacted sandy soil containing hard granite boulders of 1–3 m in diameter.
The layer of extremely weathered granite is assumed at 1-5 m thick in the lower slope, 15-20 m thick in
the higher slope. However, the thickness of extremely weathered layer may possibly become more than
20-30 m, locally around the landslide block and/or along the joint or fault.
(2) Tuff (Tf)
The tuff layer is distributed above the granite, especially on the ridge around the proposed Penstock-2 in
the west part of project area. The fresh part of tuff shows fine to medium grained, grey coloured, very
dense indicating 50+ of N-value, silty to sandy cores like a hardpan in drilling samples (Drill No.B-11).
Inside the project area, the tuff outcrops are not discovered with the exception of the tuff fragments on the
surface. Conversely, the large and fresh outcrops of the same tuff can be observed around the Pargaringan
Bridge, located along the Pargaringan River, at 1 km south from the Poring River.
Such no-welded to weak-welded tuff consists of relatively hard (soft rock) and soft (very dense soil)
layers. Plenty of piping holes with water flow in the soft part were observed, while some water leakages
along the columnar joints are in the hard part.
(3) Terrace Deposits 1 and 2 (tr 1 and tr 2)
Two stages of terrace plain are confirmed at least, on both banks along the Poring River, as follows:
Terrace deposit in the middle stage (tr 1): 5-10 m height from the recent river flow level in the dry
season
Terrace deposit in the low stage (tr 2) : 2-4 m height from the recent river flow level in the dry
Final Report
Preparatory Survey on North Sumatra Mini 3-44 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
season
Terrace deposits of both stages consist of loose to slightly dense sandy soil, showing brown color,
containing large amount of round-shaped gravels and boulders of 1-100 cm in diameter.
(4) Talus Deposit 1 (tℓ1)
The talus deposit relatively formed in old age is covering base rock widely, especially around the low to
middle elevation of the river banks and along the creeks. This deposit basically forms convex and hilly
morphological shape, showing gentle slope covered by dense vegetation such as trees and grasses. On the
other hand, this deposit partly cannot be found from morphological information, because it was formed in
the old age and with recent morphological shape.
It was confirmed in this investigation stage that the basement elevation of some old talus deposits shows
2 m lower than the recent riverbed level in Drill No. B-6 (Poring-1 Powerhouse), and 9 m lower than the
recent riverbed level in Drill No. B-8 and B-9 (Poring-2 Intake).
The old talus deposit consists of dense partly loose gravelly to sandy soil, showing brown color, largely
containing angular- to sub-angular- shaped gravels and boulders of 1-150 cm in diameter.
(5) Talus Deposit 2 (tℓ2)
The talus deposit relatively formed in new age is distributed covering base rock, around the lower part of
river banks and along the creeks in small and narrow areas. This deposit forms concave shape, basically
shows bare ground on deposit surface without trees nor grasses.
The new talus deposit consists of loose gravelly to sandy soil, showing brown color, largely containing
angular-shaped gravels and boulders of 1 cm to 2.0 m in diameter.
(6) Landslide (Ls)
Several landslides and potential landslides were located around the project area, by field reconnaissance
after checking the morphological shapes based on the recent topographic maps and the view from
opposite bank of the river. The base geology of these landslides is thick weathered layer of granite, and
extracted landslides seem to increase up the slope.
In this investigation stage, potential landslide blocks were classified to two categories as follows, based
on the probability of the morphological landslide shapes.
a) Landslide (Ls): red solid line in the drawings CW-GEO-03 ~ 08
Landslide shape with high to medium possibility
Steps on the top and middle of the block = relatively clear
Curve of the creek on both sides of the block = relatively clear
Collapse around the end of the block = unclear, locally clear
b) Potential Landslide ((Ls)): pink dashed line in the drawings CW-GEO-03 ~ 08
Final Report
Preparatory Survey on North Sumatra Mini 3-45 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Landslide shape with medium to low possibility
Steps on the top and middle of the block = relatively unclear
Curve of the creek on both sides of the block = relatively clear
Collapse around the end of the block = unclear
(7) Riverbed Deposit (rd)
The riverbed deposit consists of loose sand, gravels, and large amount of solid granite boulders of 0.5-5.0
m in diameter. The boulders exist on the full width of the river, especially at the inner elbows of the river.
The gravel parts include very small amount of sandstone which are fine-grained and very solid. In the
Poring River area, large sand sedimentation is very rare.
An enormous number of boulders is assumed to be formed after passing the process that rapid river water
flow have eroded the base granite rock or/and the collapses from the river banks over the years.
Considering the risk of debris flow, it is judged that the big sized boulders such as more than 1 m in
diameter have not flowed down in this 30 years at least.
Figure 3.5.3 shows the geological image profile around the project site.
Source: JICA Survey Team
Figure 3.5.3 Geological Image of the Project Site
3.5.4 SITE GEOLOGY AND EVALUATION
The geotechnical evaluation is described for each proposed structure, considering surface condition by the
field reconnaissance and sub-surface condition by the drilling with in-situ tests such as standard
penetration test (SPT) and permeability test.
Left Bank
River
Gt (very hard)
Gt (highly weathered=sandy soil with boulders)
Tf (weathered, some part of ridge only)
Landslide ?
Gt (highly weathered=sandy soil)
tℓ1 (old talus)
tℓ1 (old talus)
Many hard Gt boulders
tr1 tr2
tℓ2 (new talus)
rd
Final Report
Preparatory Survey on North Sumatra Mini 3-46 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(1) Poring-1 Intake
(Surface Condition)
Proposed weir axis is located across the narrow
pass of river which is approximately 20 m in
width. Extremely solid granite outcrops are
discovered in the both bank of river.
Thickness of riverbed deposit is assumed less
than 1 m, poorly containing big sized boulders.
Both banks show steep slope without clear steps,
in which be not assumed to exist the unstable
blocks such as landslide or large talus deposit.
(Sub-surface Condition)
Drill No. B-1 (left bank, total length=10 m): The solid granite appears from the surface (d=0.00 m) to
the end of borehole (d=10.00 m), mostly with CH class in rock grade. The permeability indicates
high value, as 2.18E-03 in 1.00-5.00 m and 19.2 Lu in 5.00-10.00 m section. It is definitive evidence
for high permeability that the oxidized influx soil is observed on the surface of several joints in the
whole section of core samples.
Drill No.B-2 (right bank, total length=10 m): 0.00-0.40 m is top soil. In 0.40-1.60 m, the cracky
granite is observed categorized to CL class. 1.60-10.00 m is the solid granite categorized to
CM-CH classes. The permeability indicates high value, as 1.26E-03 in 1.00-5.00 m and 10.4 Lu in
5.00-10.00 m. It is definitive evidence for high permeability that the oxidized influx soil is
observed on the surface of several joints in the 1.00-5.00 m core samples.
(Geotechnical Evaluation)
The base rock has enough bearing capacity and shear strength for the proposed construction.
The solid rock may appear after excavation of 0.00 to 1.60 m in thickness around the river banks.
The grouting for the high permeable open-joints is required. These open-joints indicate mostly
45-85 deg., with 1-3 m unit.
Both banks seem to be stable without any landslide and large talus deposit.
The risk of debris flow is low, considering few big sized boulders around upstream area of the site.
However, the driftwoods in which diameter approximately less than 40 cm have frequently flowed
down, especially in rainy season.
Source: JICA Survey Team
Weir axis (d/s site) view from upstream side
Final Report
Preparatory Survey on North Sumatra Mini 3-47 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.5.4 Geological Map around
Poring-1 Intake Weir
Source: JICA Survey Team
Figure 3.5.5 Geological Section along the
Poring-1 Intake Weir Axis
(2) Poring-1 Headrace
(Geotechnical Evaluation)
Foundation of proposed structure is highly weathered granite categorized to D class in rock grade.
In the most section, dense partly loose sandy soil may appear with large amount of hard gravels and
boulders which are 1-2 m in diameter. According as going up the slope, the content rate of gravels
and boulders may decrease and sandy matrix become looser.
Landslides and potential landslides are rare along the Poring-1 Headrace. Conversely, several
potential landslides are assumed to exist around the end section of Poring-1 Headrace and Head
Tank.
The proposed alignment of Poring-1 Headrace is partly passing through the large talus deposit areas.
Consideration shall be given to slope protection measures to ensure the stability of slope and the
water drainage in talus deposit areas which consist of loose sand and gravel containing hard
boulders.
The highly weathered granite may become the supply source of large amount of sandy soil.
Therefore, it is recommended that the cutting slope along the Poring-1 Headrace should be covered
by the dry laid masonry, for protecting the erosion and sediment discharge.
Source: JICA Survey Team Source: JICA Survey Team
Upstream section of Poring-1 Headrace Upstream to middle section of Poring-1 Headrace
Poring-1 Headrace
large talus deposit
Poring-1
Headrace
Final Report
Preparatory Survey on North Sumatra Mini 3-48 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team Source: JICA Survey Team
Middle section of Poring-1 Headrace Middle section of Poring-1 Headrace
(3) Poring-1 Head Tank
(Surface Condition)
The proposed structure is located on the gentle and
wide ridge.
Foundation of proposed structure is highly
weathered granite categorized to D class in rock
grade.
Thick highly weathered zone is assumed under
surface of the foundation, considering the lack of
any fragments and boulders around the site.
Around the proposed structure, several potential
landslides may exist, based on the morphological
analysis.
(Sub-surface Condition)
Drill No.B-4 (total length=20 m):
Base rock cannot be confirmed after
the drilling of 20 m length.
0.00-0.50 m is top soil. 0.50-20.00
m is highly weathered granite
categorized to D class, consisting of
silty sand largely containing gravels
and boulders which are 0.4-3.1 m in
diameter. Below 4.50 m seems
dense, partly remaining the granite
rock texture. Zone of N>50
appears below 4.00m in depth, while
N-value indicates 22 to 35 in the
Narrow talus deposit
Poring-1 Headrace
Poring-1
Headrace
Source: JICA Survey Team
Poring-1 Head Tank Site
Source: JICA Survey Team
Potential landslides around the Poring-1 Head Tank
* Red solid line: Landslide (probability high to medium) * Red dashed line: Potential landslide (probability medium to low)
Waterway-1 Headtank-1
Penstock-1
Final Report
Preparatory Survey on North Sumatra Mini 3-49 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
depth of 14.00-16.00 m. Ground water is never seen in the borehole.
(Geotechnical Evaluation)
Foundation rock cannot be expected for the proposed structure.
Assumed bearing capacity is 300-600 kPa, considering the N-value indicating more than 50 for
dense sandy soil or dense gravelly soil, below the 4.50 m in depth.
Several potential landslides may exist around the proposed structure, based on the morphological
analysis. It should be considered the slope stability and the drainage during the construction.
Source: JICA Survey Team Source: JICA Survey Team
Figure 3.5.6 Geological Map around
Poring-1 Head Tank
Figure 3.5.7 Poring-1 Head Tank Profile
along the Penstock Alignment
(4) Poring-1 Penstock
(Surface Condition)
The proposed structure is located on the gentle and wide
ridge.
Basement of proposed structure is highly weathered
granite categorized to D class in rock grade.
In upper section of Poring-1 Penstock alignment, thick
highly weathered zone may exist under surface of the
foundation, considering the lack of any fragments and
boulders around the site.
In lower section of Poring-1 Penstock alignment, the
thickness of highly weathered zone may decrease
(assuming 5-10 m), according as going down the slope,
considering granite boulders of 1-2 m in diameter are
discovered on the ridge.
Around the proposed structure, one (1) potential
landslide may exist, based on the morphological
analysis.
Source: JICA Survey Team Drilling No.B-5 along Poring-1 Penstock
Penstock-1
Source: JICA Survey Team Lower Section of Poring-1 Penstock
Final Report
Preparatory Survey on North Sumatra Mini 3-50 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(Sub-surface Condition)
Drill No. B-5 (total length=15 m): Base rock cannot be confirmed after the drilling of 15 m length.
0.00-0.30 m is top soil. 0.30-0.70 m is soft to firm silty clay. 0.70-15.00 m is highly weathered
granite categorized to D class, consisting of silty sand largely containing gravels and boulders which
are 0.4-1.5 m in diameter. Below 0.7 m seems dense, partly remaining the granite rock texture.
Zone of N>50 appears below 5.00 m in depth. Ground water is never observed in the borehole.
(Geotechnical Evaluation)
Rock cannot be expected for the foundation of proposed structure.
Assumed bearing capacity is 300-600 kPa, considering the N-value indicating >50 for dense sandy
soil or dense gravelly soil, below 5.00 m in depth around the site of Drilling No.B-5.
One (1) potential landslide may exist around the upper section of structure alignment, based on the
morphological analysis. It should be considered the slope stability and the water drainage during
the construction.
Source: JICA Survey Team Source: JICA Survey Team
Figure 3.5.8 Geological Map
around Poring-1 Penstock
Figure 3.5.9 Geological Profile along Poring-1
Penstock
(5) Poring-1 Powerhouse
(Surface Condition)
The proposed structure is located in gentle slope at the end of ridge and beside the river. The width
of gentle slope is approximately 10-15 m.
The gentle slope is the surface of talus deposit supplied from upstream creek in which have grown
palm trees sparsely and tall grasses densely. Considering the vegetation, this talus is assumed to
have deposited within recent 10-20 years, although large deposit has not been supplied in this 1-2
Final Report
Preparatory Survey on North Sumatra Mini 3-51 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
years.
In rainy season, the water from upstream creek flows
down on surface of the gentle slope, passing through
the proposed structure site.
The ridge slope upside of structure site is relatively
steep and seems stable, in which hard granite
boulders are partly observed.
(Sub-surface Condition)
Drill No. B-6 (total length=10 m): 0.00-0.20 m is top
soil. 0.20-5.00 m is talus deposit which consists of
moderately loose silty sand, largely containing
angular-shaped gravels. The bottom elevation of
talus deposit is 2 m below the recent riverbed level.
N-value indicates 40-45 (N’=33-36) in 1.00-3.50 m
and 50+ below 4.00 m. 5.00-10.00 m is slightly
weathered granite categorized CM class in rock
grade, hard with oxidized joints. Ground water
level is -5.00 m during drill-operation time.
(Geotechnical Evaluation)
The base rock (CM class) below 5.00 m in depth has
enough bearing capacity for proposed structure.
Lower part of silty sand with gravels is assumed to be old talus deposit, because the bottom elevation
of this deposit exists 2 m below the recent riverbed level. Old talus deposit around the project area
distributes so widely and deeply, that possibly appears on the cutting slope for the structure of
Powerhouse-1.
The thickness of old talus deposit around the proposed cutting slope is estimated 3-4 m in this
investigation stage, although it is difficult to presume accurately because this deposit was formed in
old age and exists not concerned with recent morphological shape.
The water drainage is required on the construction time, considering the water from upstream creek
flows down on surface of the gentle slope, passing through the proposed structure site in rainy
season.
Source: JICA Survery Team
Upside slope of Poring-1 Powerhouse
Source: JICA Survery Team
Proposed Poring-1 Powerhouse Site
Final Report
Preparatory Survey on North Sumatra Mini 3-52 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Source: JICA Survey Team
Figure 3.5.10 Geological Map around
Poring-1 Powerhouse
Figure 3.5.11 Geological Profile along
Poring-1 Powerhouse
As an additional topic, relatively new and large talus deposit is discovered at the right bank of Poring
River around 150 m upstream of Poring-1 Powerhouse site. This deposit has been supplied from
large collapse around the off-road in high elevation of river right bank. In future, large volume
sediment might be discharged from this deposit reaching to downstream structure, such as Poring-2
Intake.
proposed powerhouse-1 site
new talus deposit
Source: JICA Survey Team
Proposed Poring-1 Powerhouse Site
Final Report
Preparatory Survey on North Sumatra Mini 3-53 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Source: JICA Survey Team
Large collapse around the off-road Large talus deposit at the end of right bank
(6) Poring-2 Intake Weir
(Surface Condition)
Proposed weir axis is located across the narrow pass of river which is approximately 20-25 m in
width.
Solid granite outcrops are discovered in the left river bank.
In left bank, the terrace plain exists at 7 m height from the recent river flow level in dry season.
Upside slope above the terrace plain seems stable containing granite boulders.
In right bank, the solid boulders of granite were observed, which cannot be judged before drilling
that are eroded base rock or floating boulders.
In right bank, unstable factors such as talus deposit or landslide are possibly distributed, considering
the condition of relatively steep slope with ups and downs. The slope stability depends on the
height of cutting slope related with unstable factors scale.
Riverbed deposit slightly contains big sized boulders around the riverbed surface.
(Sub-surface Condition)
Drill No. B-7 (left bank, total length=10 m): 0.00-0.45 m is top soil. 0.45-4.00m is terrace deposit
consists of sandy soil with large amount of round-shaped gravels and boulders of 10-20 cm in
diameter. N-value indicates more than 45 below 2.00 m in depth. In 4.00-6.00 m, cracky granite
is observed categorized to CL class in rock grade. 6.00-10.00 m is the solid granite categorized to
CM classe. The permeability indicates very high value, as 2.53E-02 in 0.00-4.00 m and 42.7 Lu in
6.50-10.00 m. It is definitive evidence for high permeability that the oxidized influx soil is
observed on the surface of joint around 7.90 m in core samples.
Drill No.B-8 (right bank, total length=15 m): 0.00-0.60 m is top soil. 0.60-5.40 m is new talus deposit,
consists of loose to moderately dense silty sand with large amount of angular-shaped gravels and boulders.
5.40-7.00 m is riverbed deposit layer of which elevation is same as recent riverbed level, consists of loose
Final Report
Preparatory Survey on North Sumatra Mini 3-54 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
sandy gravels showing round-shape. 7.00-13.50 m is old talus deposit, consists of dense silty sand
largely with angular- to sub-angular-shaped gravels of granite and sandstone. 13.50-15.00 m is fresh
granite rock categorized to CH class. N-value indicates 31-45 in 1.00-2.50 m in depth, and 50+ in
8.50-9.50 m sections. The permeability shows very high value, as 4.27E-02 in 0.00-4.00 m and 3.13E-03
in 8.00-10.00 m.
Drill No.B-9 (riverbed, total length=10 m): 0.00-2.70 m is riverbed deposit, consists of loose sandy
gravels showing round-shape. 2.70-9.10 m is old talus deposit, consists of dense silty sand largely
with angular- to sub-angular-shaped gravels of granite and sandstone. 9.10-10.00 m is fresh granite
rock categorized to CH class. N-value indicates 45 in 2.00-2.50 m in depth, and 50+ in 7.00-9.10 m
sections. The permeability shows very high value, as 1.02E-02 in 0.00-4.20 m and 3.13E-03 in
8.00-10.00 m.
(Geotechnical Evaluation)
It was confirmed in this investigation that the basement elevation of old talus deposits shows 9 m
lower than recent riverbed level in Drill No. B-8 and B-9 (see Figure 3.5.13). The old talus deposit
consists of dense gravelly to sandy soil, showing brown colour, largely containing angular- to
sub-angular- shaped gravels and boulders.
Rock cannot be expected for the foundation of proposed structure, considering the excavation cost.
Alternative site was not observed around this weir site, since the old talus deposit may distribute
largely and deeply in the right bank to riverbed area.
It is recommended that alternatively constructing a floating weir. The old talus deposit seems to
have enough bearing capacity (estimate 300-600 kPa) for the small scaled intake weir, based on the
N-value analysis. In case of constructing floating weir, it should be required to consider the
treatment for protecting or decreasing the extreme erosion of sandy soil matrix in old talus deposit.
The risk of debris flow may be low, while the driftwoods in which diameter approximately less than
40 cm have frequently flowed down, especially in rainy season.
Final Report
Preparatory Survey on North Sumatra Mini 3-55 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Figure 3.5.12 Geological Condition around Poring-2 Intake
Source: JICA Survey Team
Figure 3.5.13 Geological Section along Poring-2 Intake Weir Axis
Weir axis view from left bank
Large old talus in right bank
Intake-2
old talus
50m
Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 3-56 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(7) Poring-2 Headrace
(Geotechnical Evaluation)
Basement of proposed structure is highly weathered granite categorized to D class in rock grade. In
the most section of waterway basement, dense partly loose sandy soil may appear with large amount
of hard gravels and boulders which are 1-4 m in diameter. According as going up the slope, the
content rate of gravels and boulders may decrease and sandy matrix become looser.
Comparing to the condition along Waterway-1, landslides and assumed landslides are more
recognized along the Poring-2 Headrace. Especially, several potential landslides in small scale are
assumed to exist around the end section of Poring-2 Headrace and Head Tank.
The proposed alignment of Poring-2 Headrace is partly passing through the large talus deposit areas.
It should be considered the slope stability and the water drainage in talus deposit areas which consist
of loose sand and gravel containing hard boulders.
The highly weathered granite may become the supply source of large amount of sandy soil.
Therefore, it is recommended that the cutting slope along the Poring-2 Headrace should be covered
by the dry laid masonry, for protecting the erosion and sediment discharge.
Source: JICA Survey Team
Large collapse around the off-road in high elevation of left bank is providing large amount of
sediments to the creek (see Appendix 1). Approximately 80 m downstream point of Intake-2, the
Waterway-2 alignment is passing through this creek. At the moment (May 2015), the end of
sediments was reached to 100 m in height above the Poring-2 Headrace. It is recommended to
regularly monitor the expansion of these collapse and sediments, in consideration of the risk of
sediments influx to the Poring-2 Headrace.
Slope-cut of canal near the Poring-1 Powerhouse
Waterway-2
Downstream section of Poring-2 Headrace
Waterway-2
Middle section of Poring-2 Headrace
Final Report
Preparatory Survey on North Sumatra Mini 3-57 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
(8) Poring-2 Head Tank
(Surface Condition)
The proposed structure is located on the gentle and wide ridge in high elevation closed to watershed.
Foundation of proposed structure is highly weathered granite categorized to D class in rock grade.
Highly weathered granite consists of dense to loose sandy soil with poor boulders, based on the
observation of outcrops along the off-road.
The proposed structure may be located at the upper portion of potential landslide which shows
relatively clear morphological factors such as steps on the top and middle, curve of the creek in the
both sides, and collapse around the end.
Source: JICA Survey Team Source: JICA Survey Team
Potential landslide around Poring-2 Head Tank Outcrop of Highly Weathered Granite
potential landslide
Head Tank-2
Large collapse providing sediments to the creek upside of Waterway-2
Poring-2 Headrace
End of discharged sediments
Final Report
Preparatory Survey on North Sumatra Mini 3-58 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team Source: JICA Survey Team
Drilling No.B-10 site Downside slope of Drilling No.B-10 site
(Sub-surface Condition)
Drill No.B-10 (total length=20 m): Bedrock can be confirmed below 17.80 m in depth. 0.00-0.30 m
is top soil. 0.30-17.80 m is highly weathered granite categorized to D class. 0.30-3.25 m is soft
clayey silt. 3.25-17.80 m consists of moderately dense sandy silt with very poor gravels, partly
remaining granite rock texture. N-value indicates 4 to 13 in depth of 1.00-5.50 m, 19 to 21 in depth
of 6.00-15.50 m, and 31 to 36 in depth of 16.00-17.50 m. Ground water was not observed in the
borehole.
(Geotechnical Evaluation)
Rock cannot be expected for the foundation of proposed structure, considering too deep (17.80 m)
excavation is necessary to reach the bedrock.
For basement of structure, it is should be judged which to choose between the layer of N>20 after
excavation of 6 m depth, and the layer of N>30 after excavation of 16 m depth.
Several potential landslides may exist around the proposed structure, based on the morphological
analysis. It should be considered the slope stability and the water drainage during the construction.
Source: JICA Survey Team
Figure 3.5.14 Geological Map around Poring-2 Head Tank
50m
Final Report
Preparatory Survey on North Sumatra Mini 3-59 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.5.15 Geological Profile along Poring-2 Head Tank
(9) Poring-2 Penstock
(Surface Condition)
Most part of proposed Penstock-2 is located on the relatively narrow ridge.
Basement of the middle section (50 % of alignment length) is formed by tuff, with consideration that
fragments of tuff are discovered around the ridge.
In the upper and lower sections, basement of Penstock-2 is highly weathered granite categorized to D
class in rock grade.
In upper section of Penstock-2 alignment, thick highly weathered zone may exist under surface of the
foundation, considering poor distribution of fragments and boulders around the site.
In lower section closed to proposed Powerhouse-2 site, the old talus deposit is largely covered
around the concave-shaped slope. This deposit is eroded by water flow of creek in centre of the
concave- shaped slope, and forming gully erosion.
Around the proposed structure, no potential landslide may exist, based on the morphological
analysis.
(Sub-surface Condition)
Drill No.B-11 (total length=20 m): 0.00-0.20 m is top soil. 0.20-8.00 m is highly weathered tuff
categorized to D class, consisting of light-brown silty sand with poor rock fragments, indicating 5 to
38 in N-value. 8.00-20.00 m is moderately weathered tuff categorized CL class in rock grade for
soft Tertiary rock, showing fine to medium grained, grey coloured, very dense indicating 50+ of
N-value, silty to sandy cores like a hardpan. Ground water is never seen in the borehole.
(Geotechnical Evaluation)
In upper section, rock cannot be expected for the foundation of proposed structure. Assuming the
condition of the upper section is similar to the Headtank-2 situation, it is should be judged which to
choose between the layer of N>20 after excavation of approximately 6 m depth, and the layer of
Final Report
Preparatory Survey on North Sumatra Mini 3-60 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
N>30 after excavation of 16 m depth.
In middle section of alignment, the moderately weathered tuff of 50+ in N-value is expected for
basement of proposed structure, appearing 8 m in depth below the surface. Allowable bearing
capacity is estimated to be 300 kPa.
Around the proposed structure, potential landslide is not existing with the exception of the high
elevation area closed to the Poring-2 Head Tank site.
In lower section closed to proposed Poring-2 Powerhouse site, the old talus deposit is largely existing
around the concave-shaped slope. It is recommended that Poring-2 Penstock alignment should be
deployed with avoid of the concave centre in which assumed to distribute the thick talus deposit. In
addition, it is required to attend with the slope stability and the treatment such as water drainage for
protecting the erosion of talus deposit.
Source: JICA Survey Team, photo taken by JICA Survey Team
Figure 3.5.16 Geological Map around Poring-2 Penstock
Middle section of Poring-2 Penstock
Penstock-2
Lower section of Poring-2 Penstock
Penstock-2
centre of old talus deposit
100m
Final Report
Preparatory Survey on North Sumatra Mini 3-61 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 3.5.17 Geological Profile along Poring-2 Penstock
(10) Poring-2 Powerhouse
(Surface Condition)
Proposed structure is located on the flat plain of 15-20 m in width, which is the surface of terrace
deposit existing at 8-10 m height from the recent river flow level in dry season.
In the upside slope behind proposed Powerhouse-2, the old talus deposit is largely existing around
the concave-shaped slope, of which thickness assumed to be 5 m in maximum. While the solid
granite rock wall of 4-8 m in height is existing between this concave-shaped slope and the proposed
site.
Solid granite outcrops are continuously distributed around the river area, which is categorized to
CH-CM class in rock grade. The upper end of these outcrops reaches 4-5m in height from recent
riverbed level in both banks of river.
(Sub-surface Condition)
Drill No.B-12 (total length=10 m): 0.00-0.15 m is top soil. 0.15-1.70 m is new talus deposit which
consists of soft brown sandy silt, containing angular-shaped fragments. 1.70-5.80 m is terrace
deposit which consists of gray sandy silt containing round-shaped fragments and boulders of 40 cm
in maximum diameter. N-value indicates very low, such as 3 to 8 in 1.00-5.50m section.
5.80-10.00 m is fresh granite categorized CH class in rock grade. Ground water level is -1.80 m
during drill-operation time.
(Geotechnical Evaluation)
The base rock appearing 5.8 m in depth below the surface is very suitable for the foundation of
proposed Powerhouse-2.
Upper layer consisting of talus and terrace deposit is not suitable for the foundation of structure,
considering low N-value such as 3 to 8 in this layer.
The solid granite wall seems to be good protection from the instability of upside slope, for the
proposed structure. It is recommended to deploy the structure without the large slope-cutting as
reaching to the upside slope, if it is possible.
Final Report
Preparatory Survey on North Sumatra Mini 3-62 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The water drainage layout is required with consideration of the existence of shallow ground water
level and creek water flow.
Source: JICA Survey Team
Source: JICA Survey Team Source: JICA Survey Team
Figure 3.5.18 Geological Map
around Poring-2 Powerhous
Figure 3.5.19 Geological Profile along Poring-2
Powerhouse
Poring-2 Powerhouse Site
Solid granite wall
Solid granite around riverbed
olid granite wall
Solid granite wall protecting Poring-2 Powerhouse Site
Final Report
Preparatory Survey on North Sumatra Mini 3-63 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
3.5.5 CONSTRUCTION MATERIALS
For the rock materials such as stone masonry can be obtained from the riverbed deposit. The granite
boulder is very solid and suitable for the stone masonry. For crushing the solid and massive boulder to
make rock materials of suitable size, it is recommended to use blasting.
Other construction materials such as concrete aggregate and sand are scheduled to be purchased from
Tarutung with consideration a) blasting is required for crushing, b) concrete volume is relatively small, c)
higher cost, and d) additional permission required.
3.5.6 SEISMIC RISK STUDY
Indonesia is located in a tectonically very active area at the point of convergence of the three major plates
and nine smaller plates creating a complex network of plate boundaries. The existence of interactions
between these plates puts Indonesia in an earthquake prone region.
The Government of Indonesia published the Seismic Hazard Map “Peta Zonasi Gempa Indonesia” in
2010. This is the Indonesian National Design Code and is widely used for planning and design of
earthquake resistant infrastructure. These maps includes maps of peak ground acceleration (PGA)
representing three levels of seismic hazard at 500, 1,000, and 2,500 years or have the possibility to exceed
10% in 50 years, 10% in 100 years, and 2% in 50 years as shown below.
PGA at bedrock having a probability
of exceedance of 10% in 50 years PGA at bedrock having a probability of exceedance of 10% in 100 years
PGA at bedrock having a probability of exceedance of 2% in 50 years
Source: Peta Zonasi Gempa Indonesia, PU, 2010
Figure 3.5.20 Indonesia Earthquake Hazard Map
For major facilities in hydropower projects, the design requirements shall satisfy both of the OBE15 and
MDE16 in accordance with the Earthquake Design and Evaluation of Concrete Hydraulic Structures
15 Operating Basis Earthquake (OBE) is a level of ground motion that is reasonably expected to occur within the service life of the project, that is, with a 50-percent probability of exceedance during the service life. (This corresponds to a return period of 72 years for a project with a service life of 50 years). 16 Maximum Design Earthquake (MDE) is the maximum level of ground motion for which a structure is designed or evaluated. The MDE
0.3-0.4g 0.4-0.5g 0.5-0.6g
Final Report
Preparatory Survey on North Sumatra Mini 3-64 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(EM1110-2-6053).
Furthermore, critical structures such as intake weir are the structures whose failure will result in loss of
life shall satisfy not MDE but MCE17.
On the other hand, Indonesia has a design earthquake which is defined in the national standard (SNI), and
has widely applied the 10% probability earthquake in 50 years (SNI 03-1726-2002 Standard Perencanaan
Ketahanan Gempa untuk Struktur Bangunan Gedung, Reference 2002). Thus, for a structure other than
intake weir, as the largest earthquake may be assumed to apply it instead of the MDE earthquake.
The following table summarizes the relation of PGA and its probability of earthquake in the project area.
The correlation of the PGA and probability of earthquake revealed the range of PGA at each frequency of
earthquake.
Table 3.5.1 PGA and Probability of Earthquake in the Project Area
Probability of Exceedance
(Pe, %)
Exposure Time (Te, years)
Return Period (Tr=-Te/ln(1-Pe),
years)
Annual probability of exceedance (λm=1/Tr)
“Peta Zonasi Gumpa 2010”
Remarks Minimum PGA (g)
Maximum PGA (g)
50% 50 72 0.01386 (0.18) (0.22) OBE 10% 20 190 0.00527 (0.24) (0.30) 10% 50 475 0.00211 0.30 0.40 Indonesia 10% 100 949 0.00105 0.40 0.50 MDE 2% 50 2,475 0.00040 0.50 0.60 MCE
Source: JICA Survey Team
Source: JICA Survey Team
Figure 3.5.21 Correlation between PGA and Annual Probability of Exceedance ground motion has a 10% chance of being exceeded in a 100-year period, (or a 1,000- year return period). For critical structures (part of a high hazard project and whose failure will result in loss of life), the MDE ground motion is the same as the MCE ground motion. 17 Maximum Considerable Earthquake (MCE) is defined as the largest earthquake that can reasonably be expected to occur on a specific source, based on seismological and geological evidence. Alternatively, MCE is calculated with a uniform probability of exceedance of 2% in 50 years (return period of about 2,500 years).
(0.18g)
(0.23g)
0.30g
0.40g
0.50g
(0.22g)
(0.30g)
0.40g
0.50g
0.60g
0.0001
0.0010
0.0100
0.1 1.0
An
nu
al P
rob
abil
ity
of E
xcee
dan
ce, λ
m
Peak Ground Acceleration (PGA, g)
MDE: 10% PE in 100-year (= 949-year Return Period)
OBE: 50% PE in 50-year (=72-year Return Period)
Design Earthquake: 10% PE in 50-year(=475-year Rerutn Period)
MCE: 2% PE in 50-year (=2,475-year Return Period)
10% PE in 20-year (=190-year Return Period)
0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
Final Report
Preparatory Survey on North Sumatra Mini 3-65 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
With the consideration of 20 years service life, the assumed PGA applied the minimum PGA.
Accordingly, the design PGA applied in this project is tablulated below.
Table 3.5.2 Design Peak Ground Acceleration for the Project
Design Earthquake OBE MDE or MCE
Intake Weir 0.18g 0.50g
Other Structures 0.18g 0.30g Source: JICA Survey Team
The peak acceleration at the ground surface can be obtained using the following equation:
PGAM = FPGA × SPGA
where, PGAM is the value at the peak ground acceleration based on the classification of the site and FPGA
is the amplification factor for the PGA.
To get the peak ground acceleration at ground surface, the classification of the site should be determined
for a layer thickness of 30 m in accordance with the definitions in the following table which are based on
the correlation of the results of the soil investigation field and laboratory.
Among the major structures in this project, intake weir and powerhouse are designed to be located on the
exposed rock (FPGA =0.8), and other major structures such as headrace, head tank, and anchor blocks for
penstock is located on the weathered rock (FPGA=1.0).
Table 3.5.3 Classification of the Site for Ground Surface
Site Classification Shear Velocity
Vs (m/sec)
N-Value Undrained Shear
Strength, Su (kPa)
PGA
≤ 0.1
PGA
= 0.2
PGA
= 0.3
PGA
= 0.4
PGA
≥ 0.5
Hard Rock (SA) Vs ≥ 1,500 N/A N/A 0.8 0.8 0.8 0.8 0.8
Rock (SB) 750 < Vs ≤ 1,500 N/A N/A 1.0 1.0 1.0 1.0 1.0
Very Solid Soil and Soft Rock (SC)
350 < Vs ≤ 750 N ≥ 50 Su ≥ 100 1.2 1.2 1.1 1.0 1.0
Medium Soil (SD) 175 < Vs ≤ 350 15 < N ≤ 50 50 < Su ≤ 100 1.6 1.4 1.2 1.1 1.0
Soft Soil (SE) Vs ≤ 175 N < 15 Su < 50 2.5 1.7 1.2 0.9 0.9
Other Soil (SF) Locations that require geotechnical investigation and analysis of specific response
SS SS SS SS SS
Note: SS=Locations that require geotechnical investigation and analysis of specific response.
Source: Peta Zonasi Gempa Indonesia, PU, 2010
As a result, the design earthquake for Poring-1 and Poring-2 is summarized below.
Table 3.5.4 Design Earthquake Coefficient
Design Earthquake OBE MDE or MCE
Intake Weir Kh=0.8×0.18=0.14 Kh=0.8×0.50=0.40
Powerhouse (Poring-1 and Poring-2) Kh=0.8×0.18=0.14 Kh=0.8×0.30=0.24
Other Structures Kh=1.0×0.18=0.18 Kh=1.0×0.30=0.30 Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 3-66 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(Blank Page)
Final Report
Preparatory Survey on North Sumatra Mini 4-1 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
CHAPTER 4 OPTIMIZATION OF DEVELOPMENT PLAN
4.1 OPTIMIZATION OF DEVELOPMENT PLAN
In undertaking this study, a review of the development plans for the project has been undertaken
considering the existing plans proposed in the pre-feasibility study, legal and other limitations imposed by
existing regulations and permit requirements, and design issues that were determined during the site visits,
additional and supplementary surveys, and analysis undertaken as part of this study. The results of the
review for the optimization of the development plans are described in this chapter.
4.1.1 LIMITATIONS OF DEVELOPMENT PLAN
To establish hydropower development plan, the project is premised on applying the FIT program, which
is in accordance with the ESDM Regulation on Purchase of Electricity for connection of Renewable
Energy Generation Plant (REGP). The following are the limitations for applying the FIT program in the
development of small hydropower facilities:
No larger than 10 MW in nameplate capacity
To be connected to PLN’s distribution system at 20 kV or lower voltage level
To study the alternative layout plan, there are limitations for the application of the location permit
(Izin Lokasi) and environmental monitoring plan (UKL/UPL), which the developer has already
obtained prior to this optimization study.
Location permit (Izin Lokasi) has been obtained from North Tapanuli Regency where the project is
located. If the project is located over two regencies, the location permit should be newly obtained
from North Sumatra Province and this will likely result in the delay of implementation,
The developer has already obtained the environmental monitoring plan (UPL/UKL) for this project.
The limitations for the UPL/UKL are that the installed capacity shall not be larger than 10 MW, the
weir height should not be greater than 15 m, and the transmission line should not be larger than 150
kV. Development plans outside of these limitations require a full environmental impact assessment
(AMDAL).
The development plans were studied taking into account the above limitations.
4.1.2 OPTIMIZATION OF DEVELOPMENT PLAN
In the course of the optimization of the development plan, the studies for the optimization of the installed
capacity, maximum plant discharge, and facilities layout were undertaken. Each parameter is a key
parameter to determine the others, so that repeated calculations are required.
Final Report
Preparatory Survey on North Sumatra Mini 4-2 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
In this project, the installed capacity is the most critical parameter to apply the FIT program. Therefore,
repeated calculations were carried out based on the assumption of installed capacity (not more than 10
MW). The flowchart of the optimization is illustrated in Figure 4.1.1 below.
Source: JICA Survey Team
Figure 4.1.1 Flowchart of Optimization of Dvelopment Plan
4.2 INSTALLED CAPACITY
More river discharge is available in this project than the requirement of 10 MW, so that the installed
capacity is not determined by the maximum plant discharge, but the maximum plant discharge is
determined by the installed capacity of 10 MW under the limitation of the FIT program. Therefore, it is
determined by the optimization of the unit generation cost.
The maximum plant discharge is selected to be optimized by comparing the benefit and cost from five
alternatives not larger than 10 MW under the FIT program and from five more alternatives larger than 10
Review of the Pre-FS
Law and Permissions Review of Hydrology
Topographic Survey Geological Investigation
Layout Study
Site Reconnaissance
Selection of Intake Weir and Headrace Channel Site
Selection of Penstock and Powerhouse Site
Calculation of Effective Head
Determination of Maximum Plant Discharge
Calculation of Energy Generation
Estimate of Construction Cost and Financial Evaluation
Determination of Optimum Project Development Plan
Selection of Installed Capacity
Hydrology
Layout Study
Layout Study
Head Loss
Final Report
Preparatory Survey on North Sumatra Mini 4-3 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
MW which apply the normal tariff for middle-scale hydropower plant in Indonesia. The maximum plant
discharge, optimum waterway layout, construction cost, and energy generation are studied respectively,
and compared with the net present value (discount rate, r=8.2%).
Accordingly, the installed capacity of 10 MW is selected based on the largest net present value among the
ten alternatives. Therefore, the effective head and maximum plant discharge are studied to achieve this 10
MW.
4.3 OPTIMIZATION OF LAYOUT
4.3.1 LAYOUT STUDY OF PORING-1 INTAKE WEIR AND HEADRACE
To determine the position of weir, the criteria are: 1) exposed foundation rock or shallow excavation
toward the rock, 2) low risk for erosion of the downstream river bank by flood flow, 3) easiness of river
closure and diversion during construction, 4) no impact on upstream sections due to backwater of weir,
and 5) convenience of construction and O&M of intake facilities.
Two alternative locations and headrace channel routes are shown in the following Figure 4.31. The
schematic design is studied for the alternatives, which are included for optimal arrangement in
consideration of the headrace extension.
Alternative-1 (Upstream Weir Site)
The difference of elevation of 17 m may be utilized additionally for power generation compared with
Alternative-2 (Downstream Site). The upstream intake weir site is expected to have more stable rock
slope and foundation according to the site conditions. However, a larger volume of rock excavation is
expected. It is noted that there are no impacts on the upstream cultivated land (paddy field) by the
construction of intake weir in this area.
To access the construction site, the existing bike road which is about 2.5 m wide and 1.15 km long
will be used after improvement to allow construction traffic access. No particular problems were
observed for this improvement work because the slope is relatively gentle. In comparison with the
alternative downstream weir location, the length of headrace channel-1 will be increased by 0.41 km,
but the length of the newly constructed access road will be decreased by 0.45 km.
Alternative-2 (Downstream Site)
The intake weir at the downstream location can be expected to have stable foundation based on the
known geology in the area. Also, rock excavation is expected to be smaller than Alternative-1
(Upstream Site). Existing upstream facilities will not be impacted by the intake weir construction in
this location.
For access to the construction site, the bike road of about 2.5 m width on the right bank side will be
used. In order to undertake construction of the intake weir, this road will need to be improved for a
distance of 1.15 km. In addition, new access road is required over a distance of 0.45 km.
Final Report
Preparatory Survey on North Sumatra Mini 4-4 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Alternative-1 Upstream Intake Site Alternative-2 Downstream Intake Site Source: JICA Survey Team
Figure 4.3.1 Alternative Location of Poring-1 Intake Weir
Poring-1 Headrace is designed to intake the river discharge from the full supply level of the intake weir,
and to go along almost same elevation through the relatively gentle slope on the left bank with a 2.5 km
long channel to connect to the Poring-1 Head Tank. The channel crosses several rivers on the way but the
crossing or diversion of these rivers is not considered to be a significant impediment because the rivers
have small catchment areas and small discharges. The waterway near the head tank is located in a rather
steeper and weathered area, increasing the risk for sliding. It is recommendable to apply a waterway with
box culverts.
Accordingly, the two alternative layouts for Poring-1 Intake Weir and Headrace in Figure 4.3.2 were
studied and compared.
Source: JICA Survey Team
Figure 4.3.2 Alternative Layout of Poring-1 Intake Weir and Headrace
Intake Alt.-1 U/S Site
Intake Alt.-2D/S Site
Headrace Alt.-2L=2.50 km
Headrace Alt.-1 L=2.91 km
Head Tank Alt.-1
Head Tank Alt.-2
Access RoadL=0.45 km
Poring River
Existing Bike Road L=1.15 km
Public Road
Final Report
Preparatory Survey on North Sumatra Mini 4-5 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The plant discharge used in order to ensure maximum output of 10 MW has been set. Within this
limitation, the unit construction cost is compared considering the cross section, slope, energy generation,
construction cost of intake weir and headrace channel, and construction method.
Alternative-1 has 2.6 GWh/year more annual power generation compared to Alternative-2. However, the
construction cost is higher than that of Alternative-2. Alternative-2 will be more economical. It is noted
that both alternatives for the intake weir will be constructed on hard rock, and there are no impacts on the
environment.
Therefore, Alternative-2 (donstream layout) was selected.
4.3.2 LAYOUT STUDY OF PORING-2 INTAKE WEIR AND HEADRACE
Poring-2 Intake Weir in the Pre-FS is located in the mouth of a 70 m high waterfall. Therefore, the 800 m
long section upstream toward Poring-1 Powerhouse is a candidate location of Poring-2 Intake Weir. An
alternative such as direct connection from Poring-1 Powerhouse to Poring-2 Headrace instead of
construction of Poring-2 Intake Weir was also studied for comparison.
It is designed to go through sparse rubber plantation on the left bank via a 2.5 km long channel to connect
to Poring-2 Head Tank. On the way, the headrace crosses the existing village (Siantar Naipospos Village)
and existing public road, in which around 30 houses including church and school are scattered on the
slope.
Alternative-1 Downstream Site:
The weir axis proposed in the Pre-FS is located slightly upstream of the waterfall where the Poring
River flows gently. Because of the exposed rock, the foundation is stable for constructing the weir.
The river width is enough for diversion works. However, the difference of elevation between
Poring-1 Tailrace is approximately 60 m.
Alternative-2 Upstream Site:
The river goes to the right in front of Poring-1 Powerhouse and then narrows to 20 m wide at 100 m
downstream. Poring-2 Intake Weir is designed here because: 1) this position contains fewer boulders
compared with the upper section where the river is covered with huge boulders and 2) the river flows
relatively quietly and not in supercritical flow in this section.
As a result of geological investigation, rock was exposed in the left bank but it is widely covered by
old talus deposit in the right bank. It is possible to construct a floating type weir but the
countermeasures to prevent erosion and seepage of foundation will be required.
Final Report
Preparatory Survey on North Sumatra Mini 4-6 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Alternative-2 Upstream Intake Site Alternative-1 Downstream Intake Site Source: JICA Survey Team
Figure 4.3.3 Alternative Location of Poring-2 Intake Weir
Alternative-3 Direct Connection
The alternative to cancel the Poring-2 Intake Weir and make a connection directly from Poring-1
Powerhouse to Poring-2 Headrace was studied. Diverting the power discharge through the pipe
spillway enables the operation of Poring-2 Powerhouse during the maintenance period of Poring-1
Powerhouse. At the end of the pipe spillway, additional energy dissipator is designed to release the
discharge to the tailrace.
The design and operation and maintenance concept for the direct connection is summarized below:
Bypass of discharge: Diverting the power discharge through the pipe spillway and directly
connecting to Poring-2 Headrace during the non-operation of Poring-1
Powerhouse.
Impact on tailrace: Energy dissipater is designed to reduce the discharge velocity and
release to the tailrace. To reduce the water surface fluctuation of the
tailrace channel, wider channel is designed to reduce the velocity.
Design change due to
weir cancellation:
The intake facility and sand trap basin are also cancelled in the case of
cancellation of Poring-2 Intake Weir since it is not taking river water.
It is noted that intake gate is required at the connection channel
between Poring-1 Tailrace and Poring-2 Headrace.
Additional facility: Regardless of the operation of Poring-1 Powerhouse, the discharge for
Poring-2 Powerhouse shall be controlled. To satisfy this condition,
Poring-1 Sand Trap Basin is designed to have two bays to prevent
stopping the discharge by flushing the sedimentation.
It is noted that the unforeseeable accident of Poring-1 Headrace and its
repair period are not considered in the above assumption.
Accordingly, the following three alternative layouts for Poring-2 Intake Weir and Headrace were studied
and compared.
Final Report
Preparatory Survey on North Sumatra Mini 4-7 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 4.3.4 Alternative Layout of Poring-2 Intake Weir and Headrace
Accordingly, Alternative-3 (Direct Connection), which is not dominant in terms of geology, will be the
most economical and advantageous in risk mitigation and environment aspects, despite of a rather
complicated operation compared with the other alternatives.
Therefore, Alternative-3 (Direct Connection) was selected.
4.3.3 LAYOUT STUDY OF PORING-1 PENSTOCK AND POWERHOUSE
The location of powerhouse is studied together with the alignment of the penstock. The penstock
alignment shall be along the ridge line and as straight as possible to prevent sliding and rolling stones
considering easiness of construction. The powerhouse is located at the end of the penstock, which is
arranged to have the shortest length along the ridge slope. The criteria for the location of powerhouse are
generally the following: 1) stable foundation rock, 2) safe location from flood discharge, and 3) no risk
for landslide. Furthermore, Poring-1 Powerhouse shall be located in the middle of the available head
between Poring-1 and Poring-2. Accordingly, the following two layouts are considered for Poring-1
Penstock and Powerhouse.
It is noted that the further upstream alternatives are not suitable because of lower head due to continuous
cascades toward the upstream and longer distance between the head tank and the river. Furthermore, the
further downstream alternatives are not considered because of the relatively large tributary with landslides
at about 250 m downstream of the head tank.
Alternative-1 Upstream Site
Penstock alignment is on the ridge line, and the powerhouse is located on a relatively gentle slope at
the foot of the penstock slope where the Poring River is curving but the flood flow does not reach the
powerhouse yard.
Intake Alt.-2 U/S Site
Headrace Alt.-1L= 1.93 km
Headrace Alt.-3L=2.58 km Headrace Alt.-2
L=2.45 km
Head Tank Alt.-2
Head Tank Alt.-3
Public Road
Poring River
Siantar Naipospos
Head Tank Alt.-1
Intake Alt.-3 Weir Cancel
Intake Alt.-1 D/S Site
Bike Road
Final Report
Preparatory Survey on North Sumatra Mini 4-8 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Alternative-2 Downstream Site
Penstock alignment is on the ridge line but longer than in Alternative-1. Powerhouse is located on
exposed hard rock site, but the yard is on the slope and the space is limited so that the excavation is
larger.
Alternative-1 Upstream Powerhouse Site Alternative-2 Downstream Powerhouse Site Source: JICA Survey Team
Figure 4.3.5 Alternative Location of Poring-1 Powerhouse
Accordingly, the following two alternative layouts for Poring-1 Penstock and Powerhouse were studied
and compared.
Source: JICA Survey Team
Figure 4.3.6 Alternative Layout of Poring-1 Penstock and Powerhouse
Accordingly, Alternative-1 will be the most economical and it will have more available flat construction
space as well as require less excavation for the powerhouse.
Penstock Alt.-1 L=430 m
Penstock Alt.-2 L=554 m
Head Tank
Tributary with Large Landslide
Powerhouse Alt.-2 D/S Site
Powerhouse Alt.-1 U/S Site
Headrace Channel Collpased Deposit
Headrace Channel
Poring River
Final Report
Preparatory Survey on North Sumatra Mini 4-9 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Therefore, Alternative-1 (Upstream Layout) was selected.
4.3.4 LAYOUT STUDY FOR PORING-2 PENSTOCK AND POWERHOUSE
Based on the penstock alignment on the ridge line, Poring-2 Powerhouse is located on a relatively gentle
slope at the foot of the penstock slope, which is geologically stable and where the flood flow does not
reach the powerhouse yard. The following two alternative layouts are selected for comparison:
Alternative-1 Upstream Site
Penstock is aligned in the shortest route along the ridge line but the slope is steep and mostly covered
by thick talus deposit. Powerhouse is located on the exposed rock but there is no flat space along the
river. The Poring River around this site is continuously cascading. The difference of elevation is 50
m higher than in the Alternative-2 Downstream Site. The route to access this site is limited due to the
steep slope around this site. Therefore, the road construction will be longer than in Alternative-2.
Alternative-2 Downstream Site
Penstock is aligned along the narrow edge line so that the longitudinal gradient is gentle and the
length of penstock will be longer. Powerhouse is located at the edge of an alluvial fan and the
powerhouse yard will be constructed on the stable terrace of the river. The geological conditions are
sufficient for the powerhouse because rock foundation is observed at a depth of 6.0 m.
Alternative-1 Upstream Powerhouse Site Alternative-2 Downstream Powerhouse Site Source: JICA Survey Team
Figure 4.3.7 Alternative Location of Poring-2 Powerhouse
Accordingly, the following two alternative layouts for Poring-2 Penstock and Powerhouse were studied
and compared:
Final Report
Preparatory Survey on North Sumatra Mini 4-10 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 4.3.8 Alternative Layout of Poring-2 Penstock and Powerhouse
Accordingly, Alternative-2 will be more economical, has better geological conditions and shorter access
to the powerhouse. Therefore, Alternative-2 (Downstream Layout) was selected.
4.4 HEAD LOSS AND EFFECTIVE HEAD
4.4.1 EFFECTIVE HEAD
The effective head is the total water head acting on the hydraulic turbine during operation, which is the
difference of water head before and after the turbine. The effective head for Francis turbine (reaction
type) is calculated by the following equation:
He Hg HL1 HL2 HL3
Where,
Hg is the Gross Head, the difference in elevation between the water level at the intake weir and at the
tailrace site,
He is the Effective Head,
HL1 is the head loss between intake and head tank,
HL2 is the head loss between head tank and turbine,
HL3 is the head loss between draft pond and tailrace outlet, and
v22/2g: is the velocity head at the tailrace weir.
Penstock Alt.-2L=862 m
Penstock Alt.-1 L=568 m
Head Tank Public Road
Poring River
PowerhouseAlt.-2 D/S Site
Powerhouse Alt.-1 U/S Site
Poring River
Project Road to Powerhouse
Final Report
Preparatory Survey on North Sumatra Mini 4-11 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
v22/2g HL3 is calculated from critical water depth at the tailrace overflow weir crest, and the head
loss between the intake and head tank (HL1 is equivalent to the elevation difference of waterway invert
slope. The head loss between head tank and inlet of turbine (HL2 is related to the discharge and flow
velocity depending on the two-unit and one-unit operation as shown below.
Accordingly, the relationship between head loss and discharge is tabulated depending on the unit number
of operation.
Table 4.4.1 Head Loss and Discharge
Item Poring-1 Poring-2
2-unit Operation 1-unit Operation 2-unit Operation 1-unit Operation
Head Loss 6.00 m 2.00 m 11.10 m 3.30 m
Loss Coefficient 212,179 × 10-6 × Q2 222,158 × 10-6 × Q2 478,143 × 10-6 × Q2 527,907 × 10-6 × Q2
Source: JICA Survey Team
Consequently, the calculation of effective head is summarized in Table 4.4.2 below.
Table 4.4.2 Design Water Level Item Poring-1 Poring-2
Intake Water Level (at Intake Weir) Full Supply Water Level (FSL)
EL. 646.5 m
EL. 441.6 m
Intake Water Level (at Head Tank) Full Supply Water Level (FSL) Rated Water Level Minimum Operational Level (Two-unit)Minimum Operational Level (One-unit)
EL. 641.0 m EL. 641.0 m EL. 640.8 m EL. 640.6 m
EL. 436.4 m EL. 436.4 m EL. 436.2 m EL. 436.0 m
Tail Water Level Flood Water Level Water Level at Two-unit Operation Water Level at One-unit Operation Low Water Level (No-flow)
EL. 441.5 m EL. 441.8 m EL. 441.5 m EL. 441.1 m
EL. 192.7 m EL. 193.0 m EL. 192.7 m EL. 192.3 m
Head Loss Head Loss due to Two-unit Operation Head Loss due to One-unit Operation
6.0 m 2.0 m
11.1 m 3.3 m
Gross Head and Net Head Maximum Gross Head: Hg Maximum Net Head: Hmax *1 Design Head (Rated Head): Hd *2 Minimum Net Head: Hmin *3
646.5-441.1=205.4 m
641.0-441.5-2.0=197.5 m 641.0-441.8-6.0=193.2 m 640.6-441.8-6.0= 192.8 m
441.6-192.3=249.3 m
434.4-192.7-3.3=240.4 m 436.4-193.0-11.1=232.3 m436.0-193.0-11.1= 231.9 m
Note: *1=1-unit operation at rated output, *2=2-unit operation at rated output, *3=2-unit operation when guide vanes are fully opened Source: JICA Survey Team
4.4.2 TYPE AND EFFICIENCY OF TURBINE AND GENERATOR
(1) Selection of Turbine and Generator
The type of turbine is selected from the following selection chart based on a maximum plant discharge of
6.0 m3/s and rated effective head of 193.2 m for Poring-1, and maximum plant discharge of 5.0 m3/s and
Final Report
Preparatory Survey on North Sumatra Mini 4-12 Nippon Koei Co., Ltd.
Hydropower Project (PPP Infrastructure Project)
rated effective head of 232.3 m for Poring-2.
Vertical Francis, Turgo impulse, and Pelton turbines are also within the applicable range, but horizontal
Francis turbine is selected because it is the most widely applied in small- to medium-scale hydropower
plants and accordingly, the most cost effective.
Figure 4.4.1 Turbine Selection Chart
The type of generator selected is not an induction type but synchronous type, which enables the supply of
electricity independently from the transmission system.
Synchronous type generators cost more than induction type generators because they require an additional
exciter in order to synchronize voltage, frequency, and phase with the system.
(2) Number of Unit and Unit Capacity
The number of unit (turbine and generator) is normally more than two units for hydropower projects
considering the following:
Efficiency of Turbine and Generator: In case of one-unit operation, the plant discharge for power
generation is smaller in range due to larger minimum discharge, and the efficiency of turbine and
generator is smaller at low plant discharge operations,
Operation and Maintenance: More than two units enable the inspection and overhaul of the turbine
and generator one by one during the dry season so that it is more economical.
In case of 2-units × 5,000 kW, such periodic inspection is normally carried out during the dry season
when the river discharge is less and sufficient only for 1-unit operation, so that it will not affect power
Poring-1
Poring-2
1
10
100
1000
0.01 0.1 1 10 100
He (m)
Q (m3/sec)
Poring-1
Poring-2
Pelton
Turgo Impulse
Francis (H)
Francis (V)
Kaplan
Reverse Pump
Propeller (Siphone)
Crossflow
Submersible Pump
Tubular (S)
Propeller (Inline)
Source: NEF Small Hydropoewr Guidebook, 2005
Final Report
Preparatory Survey on North Sumatra Mini 4-13 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
generation. However, 1-unit × 10,000 kW will force to stop the operation during each inspection.
Accordingly, the number of unit and unit capacity is set at 2 units × 5,000 kW for both Poring-1 and
Poring-2.
(3) Efficiency of Turbine and Generator
The turbine efficiency is the product of the maximum turbine efficiency and the relative turbine efficiency
depending on the turbine manufacturer. Approximately, the maximum turbine efficiency is 88.6% and the
relative turbine efficiency is related to the discharge. The combined turbine efficiency is illustrated in the
following Figure 4.4.2.
The generator efficiency is the product of the maximum generator efficiency and the relative generator
efficiency. Approximately, the maximum generator efficiency is 97.0% based on the relation between
rotor pole number and installed capacity, and the relative generator efficiency is related to the load ratio.
The combined generator efficiency is illustrated in the following Figure 4.4.2.
Poring-1 Turbine and Generator Poring-2 Turbine and Generator
Source: JICA Survey Team
Figure 4.4.2 Efficiency of Turbine and Generator
4.5 PLANT DISCHARGE
Plant discharge for hydropower development includes maximum plant discharge and firm plant discharge.
The maximum plant discharge is the discharge for maximum output in the powerhouse and used for the
design of waterway, turbine, and generator. The firm plant discharge is the discharge available throughout
355 days, which is determined by the drought discharge (355-day dependable) minus water use and
maintenance discharge.
(1) Maintenance Discharge
The flow duration curve of the Poring River as described in Chapter 3.4 (Hydrology) is used to estimate
the available plant discharge. It is recommended to consider the minimum maintenance flow discharge of
the Poring River in order to maintain the existing river environment. In this project, the intake discharge
is set to satisfy the maintenance discharge and water use discharge by comprehensively considering
tributary inflows from the remaining basin area and outflow of excess discharge at Poring-1 Powerhouse.
60%
70%
80%
90%
100%
30% 40% 50% 60% 70% 80% 90% 100%110%
Eff
icie
ncy
Discharge Ratio, Q/Qmax
TurbineGeneratorCombined
Source: NEF Hydropower Guide Book
60%
70%
80%
90%
100%
30% 40% 50% 60% 70% 80% 90% 100%110%
Eff
icie
ncy
Discharge Ratio, Q/Qmax
TurbineGeneratorConbined
Source: NEF Hydropower Guide Book
Final Report
Preparatory Survey on North Sumatra Mini 4-14 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The maintenance discharge is the minimum discharge during drought season to conserve the natural
environment for fish, animals, and other flora and fauna1. In this study, the maintenance discharge is set at
0.35 m3/s per 100 km2, which is in reference to the natural environmental study. The maintenance
discharge of 0.35 m3/s per 100 km2 is generally applied as maintenance discharge of Japanese river
facilities.
The water use discharge is the existing discharge for irrigation and water supply. According to the site
reconnaissance, no particular activity such as irrigation intake, paddy fields, and crops was observed
between the intake weir and the powerhouse for both projects. Therefore, this water use discharge is not
applied in this study, which is in reference to the social environmental study.
Accordingly, the maintenance flow discharge requirement is calculated to be 0.31 m3/s for the 87.45 km2
catchment area of Poring-1.
(2) Plant Discharge
Determination of the maximum plant discharge is not specified by law and regulation, so that it is
normally determined by an optimization of the unit generation cost. Generally, the maximum plant
discharge is determined, based on the capacity factor (= average plant discharge/maximum plant
discharge), to be around 70%. This is assuming that the generated energy is difficult to evacuate in the
grid system. The optimization of maximum plant discharge is selected from 3-5 alternatives depending on
the capacity factor and compared with unit generation costs.
In this project more river discharge is available than the requirement of 10 MW, so that the installed
capacity is not determined by the maximum plant discharge, but the maximum plant discharge is
determined by the installed capacity of 10 MW under the limitation of the FIT program.
Accordingly, the maximum plant discharge is summarized in Table 4.5.1 below. The minimum plant
discharge for Francis type turbine is estimated at 40% of the maximum plant discharge.
Table 4.5.1 Plant Discharge and Installed Capacity of Poring-1 and Poring-2
Item Poring-1 Poring-2
Installed Capacity 10.0 MW 10.0 MW
Rated Effective Head 193.2 m 232.3 m
Maximum Plant Discharge 6.00 m3/s 5.00 m3/s
Minimum Plant Discharge 1.20 m3/s 1.00 m3/s
River Utilization Factor (Plant Factor) 69.8% (82.1%) 66.0% (89.6%) Source: JICA Survey Team
The plant discharge will cover the flow range of duration curve at each intake site as shown in the
following figures.
1 Guideline of River Maintenance Flow, Ministry of Land, Infrastructure, Transport and Tourism
Final Report
Preparatory Survey on North Sumatra Mini 4-15 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Figure 4.5.1 Plant Discharge for Poring-1
Figure 4.5.2 Plant Discharge for Poring-2
4.6 ANNUAL ENERGY
Power simulations are undertaken to estimate energy production using the daily discharge for the latest
ten years from January 2004 to December 2014 obtained through the low flow analysis. The basic
conditions and the simulation results are shown in the following Table 4.6.1.
Table 4.6.1 Annual Energy for Poring-1 and Poring-2
Item Poring-1 Mini Hydropower Poring-2 Mini Hydropower
Anual Energy Generation 69.1 GWh/yr 75.3 GWh/yr Source: JICA Survey Team
The following figures illustrate the average annual output and annual energy in the above simulation.
0
3
6
9
12
15
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Dis
char
ge (m
3 /se
c)
Probability
Plant Discharge
Mean Runoff m3/sec
Max. Plant Discharge m3/sec
Min. Plant Discharge m3/sec
7.10
6.00
1.20
Source: JICA Study Team
0
3
6
9
12
15
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Dis
char
ge (m
3/s
ec)
Probability
Plant Discharge
Mean Runoff m3/sec
Max. Plant Discharge m3/sec
Min. Plant Discharge m3/sec
7.39
5.00
1.00
Source: JICA Study Team
Final Report
Preparatory Survey on North Sumatra Mini 4-16 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 4.6.1 Dependable Output and Energy for Poring-1
Source: JICA Survey Team
Figure 4.6.2 Dependable Output and Energy for Poring-2
Annual energy generation was calculated based on the assumption of 10 MW installed capacity and
optimization of the layout, effective head, and maximum plant discharge obtained through the above
repeated calculations.
0
50
100
150
200
250
2,000
4,000
6,000
8,000
10,000
12,000
0% 20% 40% 60% 80% 100%
Dep
enda
ble
Ene
rgy
(MW
h)
Dep
enda
ble
Out
put
(kW
)
Probability
Generator Output (kW)
Turbine Output (kW)
Dependable Daily Energy (MWh)
0
50
100
150
200
250
2,000
4,000
6,000
8,000
10,000
12,000
0% 20% 40% 60% 80% 100%
Dep
enda
ble
Ene
rgy
(MW
h)
Dep
enda
ble
Out
put
(kW
)
Probability
Generator Output (kW)
Turbine Output (kW)
Dependable Daily Energy (MWh)
Final Report
Preparatory Survey on North Sumatra Mini 5-1 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
CHAPTER 5 BASIC DESIGN
5.1 BASIC DESIGN OF CIVIL WORKS
5.1.1 PORING-1 INTAKE WEIR
(1) Site Conditions
The selected position of intake weir satisfies the following criteria:
The foundation should be a sound bedrock with little sediment deposit,
A relatively small excavation should reach the well consolidated layer suitable for foundation of the
structure when constructing on deep river deposit,
Scouring is not expected on the river banks and riverbed immediately downstream after the weir
construction,
Ease of river diversion and coffering works during construction,
Cross section can safely release the flood discharge despite future sedimentation, and
The intake weir is placed perpendicular to the river bank.
(2) Intake Weir Axis
The axis of the intake weir is selected as follows: 1) exposed granite foundation, 2) on a straight river
section rather than curved river section, 3) away from landslide areas on the right bank, and 4) allow
convenience of construction away from the waterfalls. Spillway for intake weir is set at 33.0 m according
to downstream river width. The design flood for Poring-1 Intake Weir is 100-year probable flood (Q=680
m3/s), so that the water depth is 6.15 m above the riverbed (EL. 645.65 m).
Below is the H-Q Curve at Poring-1 Intake Weir Site to estimate flood water level based on flood
discharge in the hydrological study and the results of river cross section survey by non-uniform flow
analysis.
Final Report
Preparatory Survey on North Sumatra Mini 5-2 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.1 H-Q Curve at Poring-1 Intake Weir Site
The minimum height of the intake weir is constructed at the weir axis and the overflow crest elevation is
EL. 646.50 m as the full supply water level (FSL).
Source: JICA Survey Team
Figure 5.1.2 Location of Poring-1 Intake Weir Axis
Looking Downstream of Weir Axis Looking Upstream of Weir Axis Source: JICA Survey Team
Figure 5.1.3 Location of Poring-1 Intake Weir Site
100-yr FloodQ= 680 m3/s H= 6.15 m
0.0
2.0
4.0
6.0
8.0
0 100 200 300 400 500 600 700 800
Wat
er D
epth
(m
)
Discharge (m3/s)
Poring-1 Intake Site, Tentatively Assumed River H-Q Curve
Non-uniform Flow Analysisby River Cross Section SurveyRoughness coefficient: n=0.05
Weir Axis Weir Axis
Mouth of Waterfall
Collapsed Old Talus
Poring River
Intake Weir-1
Power Intake-1
Project Road to Intake-1 Sand Trap Basin-1
Headrace Channel-1
35m
Final Report
Preparatory Survey on North Sumatra Mini 5-3 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(3) Structure Type and Weir Height
The intake weir is a 7.0 m high non-gated concrete gravity structure to provide the full supply water level
at EL. 646.5 m. Weir shape will consider abrasion by falling gravel which downstream surface gradient of
1:0.2 is adopted, and upstream surface gradient has been set at 1:0.5 based on the stability analysis.
(4) Overflow Depth and Freeboard
The intake weir is 33.0 m wide crest to discharge 100-year flood of 680 m3/s. The flood water levels
are estimated at EL. 651.09 m for 100-year flood, which is 4.95 m above the crest elevation as shown in
the following formula. In addition, freeboard was calculated by using the slope of stream bed from the
following formula. Non-overflow section height has been set at 6.2 m (= 4.95 m + 1.25 m).
WeirofwidthSpillwayBmdepthOverflowhWhere
sm
mChBhQ
hBBgCQ
:1),(:3;
)/68068295.4)0.3377.195.471.0(
)5.0,6.0(,)77.171.0(
,23215
2
32/3
2/3313
2/3321
Source: :Technical Criteria for River Works in Japan
Source: JICA Survey Team
Figure 5.1.4 Flood Discharge Rating Curve at Intake Weir
Table 5.1.1 Relationship of Slope of Stream Bed and Design Water Depth Slope of Stream Bed Freeboard/Design Depth
More than 1/10 0.50 1/10 to 1/30 0.40 1/30 to 1/50 0.30 1/50 to 1/70 0.25
Source: Technical Criteria for River Works in Japan
50/1:
)70.652.25.145,.651.(25.124.195.425.0
bedstreamofSlopeWhere
mELELboadFree
Final Report
Preparatory Survey on North Sumatra Mini 5-4 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(5) Location and Height of Counter Dam
Intake weir is concrete gravity dam type that does not have a spillway gate. The intake weir is designed to
be placed on the fresh granite foundation rock. The apron for overflow discharge is not provided because
there is low risk for erosion of riverbed. Drop will occur in the river channel by the construction of intake
weir. The consultant proposed a stilling basin between the main dam and counter dam. Counter dam
height and installation position are planned using the following formula:
)95.4(:3
)0.7(:1;
239.23~9.17)95.40.7(0.2~5.1
)31(0.2~5.1
mdepthOverflowh
mheightWeirHWhere
m
hHL
m
ElfoundationdamMain
ElspillwaydamCounterH
mHHWhere
mHH
75.150.63925.641
)(
)(:2
)0.7(1;
75.1~33.24/1~3/12
Source: :Technical Criteria for River Works in Japan
Source: JICA Survey Team
Figure 5.1.5 Location of Counter Dam
(6) Stability Analysis of Weir
The section is determined so as to satisfy the following conditions:
1) no overturning, 2) no sliding, and 3) no settlement
Stability calculations are calculated for the following four locations:
- Spillway section and non-overflow section of main dam.
- Spillway section and non-overflow section of counter dam.
The dimensions of the typical section are determined to satisfy the above requirement.
Counter-dam spillway
Main-dam foundation
Final Report
Preparatory Survey on North Sumatra Mini 5-5 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.6 Front View of Main Dam
Intake Weir
PowerIntake
(7) Environmental Discharge Facilities
Environmental discharge facilities are
installed in the purpose of maintaining the
normal function of the river flowing water.
Installation position of outlet valve must set
to always can flow elevation and location.
Environmental discharge will be set
Q=0.31m3/s.
Facilities are set the diameter φ300 of pipe
and discharge adjustable valve.
(8) Sand Flushing Way
The reservoir sedimentation of intake weir
will be relatively large and it will easily
get full in a short period because of rapid
river flow. Therefore, scouring way is
required to maintain the inflow discharge
and to prevent sedimentation from flowing
into the waterway.
The scouring way is located in front of the
intake on the left bank with 2.0 m width
and 2.0 m height to discharge the
sedimentation by opening the gate
particularly at the end of the flood flow.
The invert elevation of the scouring way is
designed to be lower than the invert elevation of the intake by more than 1.0 m.
(9) Power Intake
The site of power intake is selected so that
the design discharge can be taken from the
river without being affected by
sedimentation behind the weir, and it is
free from damage caused by flood flow
and drift wood. The intake is aligned at
right angle or at a slightly lesser angle to
the river.
The floor level of Poring-1 Power Intake is
set at EL. 644.2 m, which is 1.5 m above
Source: JICA Survey Team
Figure 5.1.7 Plan of Intake -1
Source: JICA Survey Team
Figure 5.1.8 Profile of Intake -1 Portal
Final Report
Preparatory Survey on North Sumatra Mini 5-6 Nippon Koei Co., Ltd.
Hydropower Project (PPP Infrastructure Project)
that of the scouring way. The intake is designed to control velocities smaller than 0.5 m/s when the
maximum plant discharge is taken. Two sets of intake trashracks with dimensions of 3.0 m (width) and
2.0 m (height) are provided to avoid floating debris from entering the waterway. The intake gate deck is
placed at EL. 652.7 m with a freeboard of 1.0 m above the flood water level during a 100-year flood.
Source: JICA Survey Team
Figure 5.1.9 Profile of Poring-1 Power Intake and Sand Trap Basin
One of the serious risks to be considered for the design of a run-of-river scheme is excessive inflow into
the waterway during flooding, taking into account the difficulty for timely operation of the intake gate,
particularly for rivers like the Poring River where a peak flood rises quickly. An overflow depth is
estimated by low flow analysis for maximum discharge on the weir crest, and therefore, two protective
walls at the entrance and the intake gate are essential to block harmful discharge as well as floating debris
from entering the channel. Closing of the intake gate is assumed based on river discharge of 60 m3/s.
Headrace channel will be overflow to the road side which exceeding the discharge capacity of headrace
channel. Even if gate was not closed that Impact to the facilities would be small.
In addition, sand trap basin is planned in two-way lane for future maintenance. Maximum inflow
discharge to the intake from one-way operation will be Q=3.5 m3/s.
(10) Sand Trap Basin
River water contains a certain volume of suspended sediments. During flood, sediment concentration
increases substantially. In run-of-river plants, suspended sediments are deposited in the waterway, and
choke its sectional area. It is also the cause of erosion of the penstocks and turbines. To settle and flush
this sediment, it is necessary to install a sand trap basin close to the intake. The sand trap basin having
dimensions of 3.0 m (width) × 2 (lane) × 4.7 m (height) on average × 28.5 m (length) is provided between
the power intake and the headrace channel. The sand trap basin plan were considered at the sediment
depth of 1m.
Final Report
Preparatory Survey on North Sumatra Mini 5-7 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
River Discharge in Dry Season River Discharge in Flood Season Source: JICA Survey Team
Figure 5.1.10 Suspended Sediments of Poring River
(11) Side Spillway
An 18.0 m long side spillway is provided with the sand trap basin to release excessive discharge. It will
be available for flood control with additional second spillway (B=13.0m) for the discharge.
(12) Emergency Closing Gate System
The gate of the intake is planned to be closed by detection system using optical fiber sensor cable for the
following measures:
- Slope collapse of the headrace channel (including penstock)
- Damage of the waterway due to natural disasters such as debris flow and falling rocks
Optical fiber cable shall be installed between Intake-1 and Powerhouse-1. Light pulse is sent to the cable
to detect strain and disconnection of the sensor cable.
5.1.2 PORING-1 HEADRACE CHANNEL
(1) Site Conditions
The headrace channel is designed to be a non-pressure
type waterway. In terms of hydraulics, the non-pressure
waterway is an open channel with free water surface.
Poring-1 Headrace passes over flat terrain to connect
Poring-1 Sand Trap Basin and Poring-1 Head Tank by
reinforced concrete (RC) channel and box culverts.
The alignment of the headrace channel is set to avoid
landslide locations, embankments, and large excavated
slopes.
The slope is to be excavated steeply to prevent the slopes
from being eroded by rainfall discharge. The channel is aligned on the relatively flat terrain of rubber
Source: JICA Survey Team
Site Condition of Poring-1 Headrace
Final Report
Preparatory Survey on North Sumatra Mini 5-8 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
plantation, but partially goes through steep cliffs.
Proper slope drainage is important for open channel for future slope stability. The maintenance road and
drain ditch are provided along the channel, and crossing drainage pipe below the channel is also prepared.
Furthermore, the headrace channel passes along several local rivers and river crossing structures are
prepared at these locations.
(2) Typical Section of Headrace
Typical sections of alternative cases (wet masonry, RC concrete channel, and box culvert) were planned
for comparison.
Furthermore, applying a steeper longitudinal profile enables reduction in the concrete volume. Open
headrace channels are at risk of closure/blockage due to landslides and collapses which will result in
halting power generation. Therefore, in order to avoid this risk, covered concrete culvert may be used as
an alternative.
Therefore, headrace channel is planned not as a masonry channel but as a combination of open concrete
channel and box culvert in consideration of the stability of future excavated slope.
The criteria for selecting box culvert are excavation height of more than 6.0 m and original slope gradient
to be steeper than 30 degrees. Also, at the section of steep slopes, the possibility of falling rocks and
landslides, rain flow from the slopes, river crossings, and village crossings are considered.
Box Culvert Section
Open Channel Section Source: JICA Survey Team
Figure 5.1.11 Typical Section of Poring-1 Headrace
(3) Longitudinal Gradient of Headrace
The size of headrace channel is determined by the flow velocity which is dominated by the longitudinal
gradient. In general, steeper longitudinal gradient leads to smaller cross sections but more head loss so
that it is not always economical. Conversely, gentler longitudinal gradient requires greater flow area as
well as the risk of more sediment settlement due to smaller flow velocities.
Within these limitations, the optimum cross section to transport the maximum plant discharge is
compared considering the cross section, slope gradient, energy generation, construction cost of headrace
channel, and construction method. Headrace channel is designed so as to satisfy the following conditions.
Final Report
Preparatory Survey on North Sumatra Mini 5-9 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Headrace channel gradient adopted is i = 1/500 according to the comparison study.
(4) Typical section and freeboard
Typical section to ensure the ability to safely flow down the maximum plant discharge are used.
Optimization of headrace channel was performed by having the lowest excavation amount. The loss
calculation of the curved portion will be used for the headrcae channel curvature radius of R=4.0 m
(R/D>2). Non-uniform flow calculation provides the starting water level in the head tank.
Table 5.1.2 Non-uniform Flow Calculation Result of Headrace Channel-1
[Design Condition] Q=6.0 m3/s, i=1/500, n=0.014 Shape: 1.7 m (base) x 2.20 m (height)
Calculation Method Water Depth (m) Uniform flow 1.63 Non-uniform flow 1.68 Non-uniform flow + turning loss
2.05
The freeboard of 15 cm, even when considering
the loss of the curved portion, will safely ensure
the allowable discharge.
Source: JICA Survey Team
(5) River Crossing Structures
The headrace channels are designed to cross the local rivers at five positions for Poring-1 project area and
the crossing structures are designed to be box culverts with concrete retaining walls downstream of the
local rivers. Gabion mattress will be installed in the inlet and outlet of crossings. The surface of the river
crossing is covered with concrete pavement and the river discharges are maintained with small ditches.
Design discharge was determined by the rational formula to calculate the catchment area of the crossing
section of river. Target discharge of the facilities will be set by the 10-year probability of rainfall scale.
Edge of cross-section for the river crossing facilities are estimated from existing river width. The position
of critical depth will be occurred by the narrowed area. Cross section shape of the river crossing facilities
assumes that the critical depth occurs at the end of the crossing structure to determine the width and
height for a given discharge.
Final Report
Preparatory Survey on North Sumatra Mini 5-10 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.12 Locations of River Crossings for Poring-1
Source: JICA Survey Team
Figure 5.1.13 Typical Section of River Crossings
5.1.3 PORING-1 HEAD TANK
(1) Site Conditions
Poring-1 Head Tank is located at the top of the penstock
which is aligned perpendicular to the slope along the ridge
behind the powerhouse. The headrace channel is extended
downward as much as possible to reduce the length of the
penstock.
The head tank is located on a 30 degree steep slope, and the
surface is covered by thick weathered talus deposit.
However, the geological condition at a depth lower than 4.5
m shows an N-value of more than 50.
Accordingly, the head tank is designed to be constructed in
this area. The construction yard for the head tank will be 15 m (width) × 30 m (length), so that the large
excavated slope is to be protected from landslide and collapse.
Source: JICA Survey Team
Site Condition of Poring-1 Head Tank
Poring-1 Poring-2ST.0+247.76 ST.0+221.35ST.0+ 999.36 ST.1+267.86ST.1+625.70 ST.1+ 486.58ST.2+212.57ST.2+395.420
Final Report
Preparatory Survey on North Sumatra Mini 5-11 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Minimization of Head Tank
The head tank functions to balance the discharges between the headrace and penstock at sudden load
change at the powerhouse, e.g., to supply water at sudden load increment and to spill out the excess water
during emergency stop. Also, it functions to trap and discharge the inflow sediment before the turbines to
prevent damage.
The capacity of the head tank is normally designed to store 2-3 minutes volume of maximum plant
discharge but this is on the assumption of no inflow from the headrace. The recent trend of design is
minimizing the storage volume of the head tank assuming inflow from the headrace.
(3) Controlling Water Level
Head tank water level varies depending on operation (controlling discharge into the turbines by
adjusting the opening of guide vane depending on the head tank water level),
Required water surface area to prevent vibration of water level: A 10Qmax
Required water volume to supply discharge at the emergency water level: V 11Qmax
Overflow discharge at emergency circuit: providing spillway for safely releasing the maximum
design discharge through side spillway without increasing water level when operation is suddenly
stopped because of the emergency circuit such as transmission system accident,
Gradual transition between headrace channel and head tank so as not to cause whirl or deviation
flow,
Water depth at the inlet of penstock is twice greater than the penstock inner diameter in order to,
Not necessary to provide a gate in the head tank
(4) Sand Trap
Average flow velocity in the head tank: smaller than 0.3 m/s.
Required length to settle the suspended load: (L):L u, where, vg: allowable settlement
velocity of sand particle (larger than 0.5-1.0 mm) which is targeted to settle (vg = 0.1 m/s), h:
average water depth of head tank, u: average velocity of head tank
Transition section at the inlet of head tank is designed to have enlarged angle smaller than 40
degrees so as not to reduce settlement function by drift or deviation of flow, otherwise providing
guide wall,
Invert slope of head tank is 1:10 for flushing the sediment same as sand trap basin,
Providing sand flush gate and channel
(5) Structural Outline
The head tank having dimensions of 6.0 m (width) × 3.5 m (height) on average × 25.4 m (length) is
provided between the waterway and the steel penstock.
Final Report
Preparatory Survey on North Sumatra Mini 5-12 Nippon Koei Co., Ltd.
Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.14 Longitudinal Profile of Poring-1 Head Tank
(6) Target Water Levels
Power operation is undertaken by monitoring the water level in the head tank to select an appropriate
operation mode: i) two-unit operation, ii) one-unit operation, or iii) suspension of operation. The head
tank is designed to have sufficient supply volume to allow reasonable period required for shifting the
operation modes by the following operation criteria:
Table 5.1.3 Target Water Levels for Poring-1 Head Tank
Design Condition 2-unit Rated
Operation
1-unit Rated
Operation
1-unit Minimum
Operation
Max. plant discharge for 2-unit operation 6.0 m3/s 3.0 m
3/s 1.2 m
3/s
Inside water surface area of head tank 131.1 m2 ( > 10 Q = 60 m
2)
Effective water volume of head tank 458.9 m3 ( >11 Q = 66 m
3)
Formation height of waterway EL. 639.27 m
Uniform depth at EP of waterway 1.63 m 0.94 m 0.46 m
Water level at EP of waterway EL. 640.90 m EL. 640.21 m EL. 639.73 m
Crest of side spillway (full supply level) EL. 641.00 m
Minimum operation level EL. 640.20 m EL. 639.70 m EL. 639.70 m
Water level for emergency closure EL. 639.70 m EL. 639.20 m
Minimum water level of head tank --- EL. 638.70 m Source: JICA Survey Team
(7) Side Spillway
A side spillway with a crest length of 12.0 m is provided for the case when the power operation is
suspended, and is designed to release the maximum plant discharge of 6.0 m3/s. The overflow discharge
flows into an open channel beside the head tank and connects to the spillway pipe along the penstock.
Final Report
Preparatory Survey on North Sumatra Mini 5-13 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.1.4 PORING-1 PENSTOCK
(1) Site Conditions
Penstock is designed along the ridge line of the slope
between the head tank and powerhouse to avoid the route
from crossing over the local stream to reduce the damage
and erosion of penstock foundation by flood flow, land
sliding, and rolling stones.
The ridge line is excavated along the penstock so as to
locate the steel pipe on the ground by concrete or masonry
saddle supports.
Seven anchor blocks are designed and concrete saddles
with an interval of 6.0 m will be provided to support the
penstock between anchor blocks. The excavated sides and
bottom surfaces are protected by wet stone masonry with drainage pipes and ditches for surface drainage.
The following Figure 5.1.15 shows the plan and profile as well as typical cross section.
Source: JICA Survey Team
Figure 5.1.15 Plan and Profile of Poring-1 Penstock
Source: JICA Survey Team
Site Condition of Poring-1 Penstock
Final Report
Preparatory Survey on North Sumatra Mini 5-14 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The alignment of Poring-1 Penstock is along the relatively narrow ridge line which is 430.9 m long and
194.4 m high. The profile is 27.3 degrees on average and the maximum angle is 41.2 degrees at the
section behind the powerhouse.
At the lower horizontal section, shortly after the last bend, the penstock connects to a Y-branch pipe, then
it will be divided into two lanes and finally connects to each unit.
(2) Optimum Penstock Diameter
The penstock diameter is determined by the flow velocity and it is normally set at 2.0-4.0 m/sec (NEF
Guide Book for Small Hydropower). The high head hydropower plants such as this Project tend to be
more advantage of cost comparison with smaller diameter and larger head loss to some extent.
Therefore, the average flow velocity is set at around 4.0 m/sec, which is widely applied in small
hydropower projects.
(3) Water Hammer and Closing Time
The closure time of turbine and generator is determined by the comparison of steel weight of penstock
and flywheel of turbine and generator. The longer the closure time, the smaller the penstock weight due to
the smaller pressure rise in the penstock, but it requires heavier weight of flywheel of turbine and
generator. Accordingly, the closure time is set at 5 s.
Source: JICA Survey Team
Figure 5.1.16 Optimum Closing Time of Turbine and Generator
(4) Optimum Thickness of Penstock
Accordingly, the dimensions of Poring-1 Penstock are summarized in the following Table 5.1.4.
Furthermore, the required thickness of steel penstock is calculated from internal pressure including static
head and water hammer, and from external pressure at empty condition. It is noted that the water hammer
analysis applies the Allievi Formula.
1.76
1.78
1.80
1.82
1.84
1.86
2.0 3.0 4.0 5.0 6.0 7.0 8.0
Pen
stoc
k +
Gen
erat
or
Cos
t (U
SD M
il.)
Closing Time (sec.)
Assumption: Unit Rate of Steel Penstock=4,000 USD/tonGenerator=1.084 M USD/2-unit for T=5.0 sec.
Final Report
Preparatory Survey on North Sumatra Mini 5-15 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 5.1.4 Water Hammer Analysis and Penstock Steel Thickness for Poring-1
Design Condition:
Discharge : Qmax = 6.0 m3/s
Static head : H0 = 199.00 m
Closing time of guide vane T = 5.0 s
Allievi Formula for water hammer:
.
√1.25 n . %
θ 5.463 ρ 1.013 n 0.185
No. Length (m)
Diameter (m)
Wave Velocity
(m/s)
Discharge Velocity
(m/s)
Coefficient of Allievi
Static Head (m)
t for int. pressure
(mm)
t for ext. pressure
(mm)
Thicknesst
(mm) 1 4.00 1.350 789 4.192 0.850 4.6 1.9 6.0 6 2 93.67 1.350 789 4.192 0.850 53.0 5.6 6.0 6 3 136.79 1.350 925 4.192 0.996 98.0 9.1 6.0 10 4 72.75 1.350 972 4.192 1.046 129.0 11.5 6.0 12 5 105.72 1.350 1,068 4.192 1.150 199.0 17.5 6.0 18 6 4.00 1.350 1,068 4.192 1.150 199.0 17.5 6.0 18 7 12.00 1.000 1,063 3.820 1.043 199.0 12.9 5.0 13 8 2.70 1.000 1,063 3.820 1.043 199.0 12.9 5.0 13
Total or Average
430.88 (=L0)
1.338 943 (=α)
4.179 (=V0)
1.012 (=ρ)
--- --- --- 11.6
Source: JICA Survey Team
Consequently, a closing time of 5.0 s, maximum water head of 247.3 m, and maximum pressure rise of
24.3% are applied in the design of the Poring-1 Penstock.
(5) Y-Branch and Branch Pipes
Penstock is divided into two lanes to connect hydraulic turbines at the lower horizontal section in front of
the powerhouse. Y-branch is applied to be open to 60 degrees for 12 m distance from the turbines and the
branch pipes are 1.0 m in diameter.
(6) Saddle Support
Type of intermediate support is divided into two types, i.e.: saddle support for relatively smaller diameter
penstock and ring girder support for relatively larger diameter penstock. Since the construction cost of saddle
support is generally much smaller than that of ring girder support, the saddle support is selected in this project.
(7) Anchor Blocks
At the position of no bends, the penstock is supported by concrete anchor blocks. Intermediate positions
between anchor blocks are supported by concrete saddles against vertical load. The overflow spillway
pipe is also aligned parallel to the penstock, so that the supports of the anchor blocks and saddles will
utilize the ones provided for the penstock.
The stability conditions (overturning, sliding, and bearing stabilities) are to be confirmed against each
combination of dead load, combined water pressure, deflection due to temperature change, and seismic
load.
The dimensions of anchor blocks are determined to satisfy the above requirement.
Final Report
Preparatory Survey on North Sumatra Mini 5-16 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.1.5 PORING-1 HEAD TANK SPILLWAY
(1) Type of Pipe Spillway
Head tank spillway is provided to discharge excess water to the river through open channel, closed
conduit, or pipeline (steel pipe, RC pipe, FRP). The overflow spillway is normally designed on steep
slope along the steel penstock with the same head and discharge so that it requires the facility with safety
discharge.
The discharge from the head tank spillway depends on the turbine emergency stop. Therefore, it is
prohibited to discharge into the recession river section between intake and powerhouse without a flood
warning system because it may be fatal to human life or to just discharge at the downstream of tailrace
outlet.
It is possible to shorten the length of head tank spillway when a local stream is available to discharge the
water. However, careful attention is required not to cause erosion of the riverbed. Moreover, in case there
is no exposed rock in the local stream, it will be higher risk for erosion, and it may cause large-scale
landslide. As there are no local streams with the required geological conditions in the area of the head
tank, the pipe spillway is designed parallel to the penstock in this project.
Particularly for Poring-1, the pipe spillway is used as a bypass waterway for Poring-2 due to elimination
of Poring-2 Intake Weir.
Source: Cianten Small Hydropower Project in Indonesia
Example of Spillway Releasing to Local StreamSource: NEF “Design Manual of Simplified Generation System”
Example of Pipe Spillway Figure 5.1.17 Comparison of Pipe Spillway
After the pipe spillway at the head tank, the excess water is discharged by side channel to the inlet of pipe
spillway. Then, an overflow weir is provided at the inlet of pipe spillway to provide smooth discharge.
The flow inside the pipe spillway is supercritical flow with high velocity so that air pipes are designed at
every bend of the pipe spillway.
An energy dissipater is also designed at the end of the pipe spillway below the erection bay of the
powerhouse because the design discharge with high head will be released. Finally, the excess discharge
connects to Poring-1 Tailrace.
Final Report
Preparatory Survey on North Sumatra Mini 5-17 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Diameter of Pipe Spillway
The flow inside the pipe spillway is supercritical flow with high velocity. It is noted to reduce curves of
pipe so as to allow smooth discharge. The higher discharge velocity allows the pipe to have a smaller
diameter and lower construction cost. However, the reduction of pipe diameter is not applied because
transition pipe is expensive and difficult to set. To maintain less than 50% of flow area ratio (=flow
area/pipe area) for safe discharge condition as shown in the following Table 5.1.5, the pipe diameter
should be 0.95 m.
Table 5.1.5 Non-Uniform Flow Analysis for Overflow Spillway Pipe for Poring-1
Source: JICA Survey Team
(3) Energy Dissipater
An energy dissipater for killing the hydraulic energy is
provided at the end of the pipe spillway for safe
release of spillout discharge.
The types of energy dissipater are 1) impact type, 2)
shaft type, and 3) hydraulic jump type. In case
Q+P 25 Q 15m /s, P 20MW , an impact
type energy dissipater is within the applicable range.
Typical dimensions of impact type energy dissipater are shown in Figure 5.1.20 below. The width
requirement is about 4.5 m for 5~6 m3/s discharge, so that the energy dissipater will be placed below the
Length Depth Area Velocity V head Wet R Invert EL. Slope Ratio Frude
(m) h (m) A (m2) V (m/s) V^2/2g (m) P (m) R (m) (m) θ deg <50% Fr>1
Sta.0 0.0 0.200 0.213 28.19 40.6 1.5 0.1 638.125
Sta.5 4.7 0.220 0.224 26.73 36.5 1.5 0.2 635.725 27.25 31.7% 18.2
Sta.99 94.0 0.406 0.321 18.68 17.8 1.5 0.2 587.325 27.25 45.3% 9.4
Sta.236 137.5 0.457 0.346 17.37 15.4 1.5 0.2 542.325 18.13 48.7% 8.2
Sta.309 72.5 0.378 0.307 19.55 19.5 1.5 0.2 511.325 23.15 43.3% 10.2
Sta.417 108.7 0.285 0.260 23.07 27.2 1.5 0.2 438.975 33.66 36.7% 13.8
Sta.431 13.8 0.385 0.311 19.30 19.0 1.5 0.2 438.975 0.00 43.9% 9.9
Station
Source: http://www.kanapipeline.com/images/energy-dissipator.html
Figure 5.1.19 An Example of Impact Type Energy Dissipater
Source: T. Inamatsu, Standard Form Selection of Headtank Spillway and Energy Killer in Water Power Plant, 1983
Figure 5.1.18 Type Selection Chart of Energy Dissipater
Final Report
Preparatory Survey on North Sumatra Mini 5-18 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Photo taken by the JICA Survey Team
Site Conditions of Poring-1 Powerhouse
concrete slab at the erection bay of the powerhouse.
Source: Equations of Hydraulic Engineering, JSCE
Figure 5.1.20 Typical Dimensions of Impact Type Energy Dissipater
5.1.6 PORING-1 POWERHOUSE
(1) Site Conditions
The position of powerhouse was selected
as shown in the alternative layout study.
Poring-1 Powerhouse is, based on the
penstock alignment on the ridge line,
located on a relatively gentle slope at the
foot of the penstock slope.
The geological investigation revealed
that rock foundation (fresh granite) will
be exposed after 5.0 m. The concrete slab
of powerhouse will be constructed on this rock surface. The penstock slope is stable against sliding
despite being covered with talus deposit and lying 40 degrees due to angular gravel content in the talus.
However, the design is limited to the excavation of the slope toe.
Access to Poring-1 Powerhouse is along the Poring-2 Headrace Channel from Siantar Naipospos Village.
Also, the temporary construction road will be constructed by widening the existing footpath during the
construction.
Final Report
Preparatory Survey on North Sumatra Mini 5-19 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Setting Levels
The design flood for Poring-1 Powerhouse is 100-year probable flood (Q = 710 m3/s), so that the water
depth is 3.29 m above the riverbed (EL. 441.50 m).
Below is the H-Q Curve at Powerhouse-1 Site by non-uniform flow analysis.
Source: JICA Survey Team
Figure 5.1.21 H-Q Curve at Powerhouse-1 Site
The powerhouse yard elevation, EL. 442.50 m, is determined from the 100-year probable flood water
level of the Poring River with a 1.0 m freeboard based on the H-Q curve. The slab elevation is 200 mm
higher than the yard elevation to prevent rainfall discharge into the powerhouse.
Turbine center level as well as tailwater level and penstock center level are determined as explained in the
electro-mechanical design.
Table 5.1.6 Poring-1 Powerhouse Setting Level
Turbine Center Elevation EL. 443.40 m (≤ TWL + Hs*)
Surface Level of Powerhouse Concrete EL. 442.70 m (Yard Level + 0.20 m)
Powerhouse Yard Level (Yard EL) EL. 442.50 m (= FWL + freeboard (= 1.00 m)
Penstock Center Elevation (PCL) EL. 442.00 m (= Turbine Center - A*)
Tailwater Level (TWL) EL. 442.00 m (=FWL + 0.50 m)
Flood Water Level (FWL) (100-year Probable Flood) EL. 441.50 m (from H-Q Curve)
Note: Hs* and A* are explained in the design of the electro-mechanical equipment. Source: JICA Survey Team
(3) Superstructure
The superstructure of the Poring-1 Powerhouse shall incorporate two units of turbine and generator,
erection bay, and control room for operation with dimensions of 10.8 m (width) × 38.0 m (length) × 9.0 m
(height).
The superstructure of the powerhouse for ceiling and overhead crane is designed to be a steel frame
structure. The capacity of overhead crane is 20 ton and crane girder is provided.
The plan and profile of Poring-1 Powerhouse are shown below.
100-yr FloodQ= 710 m3/s H= 3.29 m
0.0
1.0
2.0
3.0
4.0
0 100 200 300 400 500 600 700 800
Wat
er D
epth
(m
)
Discharge (m3/s)
Poring-1 Powerhouse Site, Tentatively Assumed River H-Q Curve
Non-uniform Flow Analysisby River Cross Section SurveyRoughness coefficient: n=0.05
Final Report
Preparatory Survey on North Sumatra Mini 5-20 Nippon Koei Co., Ltd.
Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.22 Plan of Poring-1 Powerhouse
Source: JICA Survey Team
Figure 5.1.23 Profile of Poring-1 Powerhouse
(4) Powerhouse Yard
Powerhouse yard is a space to accommodate the powerhouse building and tailrace culvert as well as
auxiliary facilities such as main transformer, emergency diesel, and transmission line equipment.
Powerhouse yard with dimensions of 50 m × 20 m requires relatively large excavation at the foot of the
steep slope of the penstock. To reduce the excavation volume, excavation with slope of 1:0.5 and covered
with protection is provided. The protection work is designed to be reinforced concrete frame.
(5) Type of Turbine and Generator
As described in the previous chapter, hydraulic turbine is 2 units × 5,000 kW and generator is 2 units ×
5,380 kVA.
Final Report
Preparatory Survey on North Sumatra Mini 5-21 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.1.7 PORING-2 POWER INTAKE
The tailrace of Poring-1 Powerhouse and Poring-2 Headrace are directly connected without discharging
back to the Poring River so that the construction of Poring-2 Intake Weir was cancelled. The water level
of the draft pond varies depending on the plant discharge, but it is important to keep the water level
higher to prevent air from entering into the draft tube. To control the water level, an overflow weir is
designed at the tailrace.
The water level of the tailrace pond is determined by the turbine discharges. To prevent air from entering
into the draft tube at the minimum plant discharge, the overflow weir is designed at the end of the tailrace.
The velocity of tailrace discharge is designed to be smaller than 0.5 m/s by increasing the cross sectional
area to reduce water surface fluctuation and head loss.
When the Poring-2 is under stop operation, the plant discharge will be released back to the Poring River
via tailrace side spillway, having a 14 m wide crest, by closing the intake gate of Poring-2 Power Intake.
The power intake is designed to be equipped with one intake gate downstream of the side spillway.
Source: JICA Survey Team
Figure 5.1.24 Longitudinal Profile between Poring-1 Tailrace and Poring-2 Power Intake
EL.441.60 m
Intake Gate
TWL 442.00 mSide Spillway
Overflow Crest 441.00 m Bottom EL. 440.09 m
Final Report
Preparatory Survey on North Sumatra Mini 5-22 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.1.8 PORING-2 HEADRACE
(1) Site Conditions
The headrace channel is designed to be a non-pressure type
waterway. In terms of hydraulics, the non-pressure waterway
is an open channel with free water surface.
Poring-2 Headrace passes over flat terrain to connect
Poring-2 Intake and Poring-2 Head Tank by RC channel and
box culvert.
The alignment of Poring-2 Headrace is set to avoid landslide
locations, embankments, and large excavated slopes.
The slope is to be excavated steeply to prevent the slopes
from being eroded by rainfall discharge and the road will be
the space to stop local collapse.
Headrace is designed to go through sparse rubber plantation on the rather gentle left bank. On the way,
the headrace crosses the existing village (Siantar Naipospos Village) and the existing village road. The
houses are scattered on the slope. Therefore, the project will be required to pay maximum consideration
to avoid the resettlement of village people.
Proper slope drainage is important for open channel for future slope stability. The maintenance road and
drain ditch are provided along the channel, and crossing drainage pipe below the channel is also prepared.
Furthermore, the headrace channel passes several local rivers; thus, river crossing structures are prepared
at these locations.
(2) Typical Section of Headrace
Similar design concepts for the selection of typical section for Poring-1 Headrace have been applied for
Poring-2. Therefore, Poring-2 Headrace is planned not as a masonry channel but as a combination of open
concrete channel and box culvert in consideration of the stability of the future excavated slope.
Box Culvert Section
Open Channel Section
Source: JICA Survey Team
Figure 5.1.25 Typical Section of Poring-2 Headrace
Source: JICA Survey Team
Site Condition of Poring-2 Headrace
Final Report
Preparatory Survey on North Sumatra Mini 5-23 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(3) Longitudinal Gradient of Headrace
Similar design concepts for the determination of longitudinal gradient for Poring-1 Headrace have been
applied for Poring-2. Headrace channel is designed so as to satisfy the conditions at the maximum plant
discharge of Q=5.0 m3/s. Accordingly, the longitudinal gradient of 1/500 was the most economical and
selected.
(4) Typical section and freeboard
Typical section to ensure the ability to safely flow down the maximum plant discharge are used.
Optimization of headrace channel was performed by having the lowest excavation amount. The loss
calculation of the curved portion will be used for the headrace channel curvature radius of R=4.0 m
(R/D>2). The result of the non-uniform flow calculation for the given starting water level in the head tank
is shown in Table 5.1.7 below.
Table 5.1.7 Non-uniform Flow Calculation Result of Headrace Channel-2 [Design Condition] Q=5.0 m3/s, i=1/500, n=0.014 Shape: 1.6 m (base) x 2.15 m (height)
Calculation Method Water Depth (m) Uniform flow 1.51 Non-uniform flow 1.55 Non-uniform flow + turning loss
1.74
The freeboard of 41 cm, even when considering
the loss of the curved portion, will safely ensure
the allowable discharge.
Source: JICA Survey Team
(5) Crossing of the
Village
Poring-2 Headrace shall be
laid out to avoid crossing the
villages and designed to
provide 1.0 m wide walkway
along the channel during the
construction. Also, staircases
will be prepared at the side
of the headrace channel to
ensure the trafficability for
the villagers.
Source: JICA Survey Team
Figure 5.1.26 Layout of Headrace Channel Crossing the Village
Final Report
Preparatory Survey on North Sumatra Mini 5-24 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.27 Typical Section of Village Crossing
(6) River Crossing
The headrace channels are designed to cross the local rivers at three positions for Poring-2 and the
crossing structures are designed to be box culverts with concrete retaining walls downstream of the local
rivers. Gabion mattress will be installed in the inlet and outlet of crossings. The surface of the river
crossing is covered with concrete pavement and the river discharges are maintained with small ditches.
Design discharge was determined by rational formula to calculate the catchment area of the crossing
section of the river. Target discharge of the facilities will be set by the 10-year probability of rainfall scale.
Edge of cross-section for the river crossing facilities are estimated from existing river width. The position
of critical depth will be occurred by the narrowed area. Cross section shape of the river crossing facilities
assumes that the critical depth occurs at the end of the crossing structure to determine the width and
height for a given discharge.
Source: JICA Survey Team
Figure 5.1.28 Locations of River Crossings
Poring-1 Poring-2ST.0+247.76 ST.0+221.35ST.0+ 999.36 ST.1+267.86ST.1+625.70 ST.1+ 486.58ST.2+212.57ST.2+395.420
Final Report
Preparatory Survey on North Sumatra Mini 5-25 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.29 Typical Section of River Crossings
5.1.9 PORING-2 HEAD TANK
(1) Site Conditions
Poring-2 Head Tank is located at the top of the penstock which
is aligned perpendicular to the slope along the ridge behind the
powerhouse. The headrace channel is extended downward as
much as possible to reduce the length of the penstock.
The existing slope of the head tank is around 25 degrees steep,
and the surface is covered by thick weathered talus deposit.
The surface geological conditions at lower than 6.0 m deep
show an N-value of more than 20.
Poring-2 Head Tank is designed to be constructed in this area by excavating the layer with N-value of less
than 20. Furthermore, precast concrete piles will be provided where required.
The construction yard for the head tank will be 15 m (width) × 30 m (length), so that the large excavated
slope is to be protected from landslide and collapse.
Similar design concepts for Poring-1 Head Tank have been applied for Poring-2 Head Tank.
Minimization of Head Tank
Controlling Water Level
Sand Trap
(2) Structural Outline
Poring-2 Head Tank, having dimensions of 5.0 m (width) × 3.5 m (height) on average × 24.5 m (length),
is provided with the above functions as illustrated below.
Source: JICA Survey Team
Site Conditions of Poring-2 Head Tank
Final Report
Preparatory Survey on North Sumatra Mini 5-26 Nippon Koei Co., Ltd.
Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.30 Longitudinal Profile of Poring-2 Head Tank
(3) Target Water Levels
Power operation is undertaken by monitoring the water level in the head tank to select an appropriate
operation mode: i) two-unit operation, ii) one-unit operation, or iii) suspension of operation. The head
tank is designed to have sufficient supply volume to allow reasonable period required for shifting the
operation modes through the following operation manners:
Table 5.1.8 Target Water Levels in Poring-2 Head Tank
Design Condition 2-unit Rated
Operation
1-unit Rated
Operation
1-unit Minimum
Operation
Max. plant discharge for 2-unit operation 5.0 m3/s 2.5 m
3/s 1.0 m
3/s
Inside water surface area of head tank 131.1 m2 ( > 10 Q = 50 m
2)
Effective water volume of head tank 458.9 m3 ( >11 Q = 55 m
3)
Formation height of waterway EL. 434.85 m
Uniform depth at EP of waterway 1.51 m 0.88 m 0.45 m
Water level at EP of waterway EL. 436.36 m EL. 435.73 m EL. 435.30 m
Crest of side spillway (full supply level) EL. 436.40 m
Minimum operation level EL. 435.80 m EL. 434.80 m EL. 434.80 m
Water level for emergency closure EL. 435.30 m EL. 434.80 m
Minimum water level of head tank --- EL. 434.30 m Source: JICA Survey Team
(4) Side Spillway
The side spillway with a crest length of 12.0 m is provided for the case when the power operation is
suspended, and is designed to release the maximum plant discharge of 5.0 m3/s. The overflow discharge
flows into an open channel beside the head tank and connects to the spillway pipe along the penstock.
Final Report
Preparatory Survey on North Sumatra Mini 5-27 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.1.10 PORING-2 PENSTOCK
(1) Site Conditions
The alignment of Poring-2 Penstock is along the relatively
narrow ridge line to connect Poring-2 Head Tank and
Poring-2 Powerhouse.
Ten anchor blocks are designed and concrete saddles with
an interval of 6.0 m will be provided to support the
penstock between anchor blocks.
The excavated sides and bottom surfaces are protected by
wet stone masonry with drainage pipes and ditches for
surface drainage.
The Poring-2 Penstock is 861.6 m long and 235.8 m high, and has gradient of 16.6 degrees on average
and with the maximum angle of 35.4 degrees at the section behind the powerhouse.
At the lower horizontal section, shortly after the last bend, the penstock will connect to a Y-branch pipe,
then it will be divided into two lanes and finally connect to each turbine unit.
The following Figure 5.1.29 shows the plan and profile as well as typical cross section of the penstock.
Source: JICA Survey Team
Site Conditions of Poring-2 Penstock
F
inal Report
Preparatory Survey on N
orth Sumatra M
ini 5-28
N
ippon Koei C
o., Ltd.
Hydropow
er Project (P
PP
Infrastructure Project)
S
ource: JICA
Survey Team
Figu
re 5.1.31 P
lan an
d P
rofile of Poring-2 P
enstock
Final Report
Preparatory Survey on North Sumatra Mini 5-29 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Optimum Penstock Diameter
The penstock diameter is determined by the flow velocity and it is normally set at 2.0-4.0 m/sec (NEF
Guide Book for Small Hydropower). The high head hydropower plants such as this Project tend to be
more advantage of cost comparison with smaller diameter and larger head loss to some extent.
Therefore, the average flow velocity is set at around 4.0 m/sec, which is widely applied in small
hydropower projects.
(3) Water Hammer and Closing Time
The closure time of turbine and generator is determined by the comparison of steel weight of penstock
and flywheel of turbine and generator. The longer the closure time is, the smaller the penstock weight is
due to the smaller pressure rise in the penstock. However, it requires heavier weight of flywheel of
turbine and generator. Accordingly, the closing time is set at 7 s.
Source: JICA Survey Team
Figure 5.1.32 Optimum Closure Time of Turbine and Generator
(4) Optimum Penstock Thickness
The dimensions of Poring-2 Penstock are summarized in the following Table 5.1.9. Furthermore, the
required thickness of steel penstock is calculated from internal pressure including static head and water
hammer, and from external pressure at empty condition. It is noted that the water hammer analysis applies
the Allievi Formula.
2.30
2.40
2.50
2.60
2.70
2.80
3.0 5.0 7.0 9.0 11.0
Pen
stoc
k +
Gen
erat
or
Cos
t (U
SD M
.)
Closing Time (sec.)
Assumed: Unit Rate of Steel Penstock=4,000 USD/tonGenerator=1.084 Mil. USD/2-unit for T=5.0 sec.
Final Report
Preparatory Survey on North Sumatra Mini 5-30 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 5.1.9 Water Hammer Analysis and Poring-2 Penstock Steel Thickness
Design Condition:
Discharge : Qmax = 5.0 m3/s
Static head : H0 = 241.80 m
Closing time of guide vane T = 7.0 s
Allievi Formula for water hammer:
.
√1.25 n . %
θ 4.034 ρ 0.854 n 0.211
No. Length (m)
Diameter (m)
Wave Velocity
(m/s)
Discharge Velocity
(m/s)
Coeff. of Allievi
Static head (m)
t for int. pressure
(mm)
t for ext. pressure
(mm)
Thicknesst
(mm) 1 4.00 1.250 810 4.074 0.697 0.0 1.5 6.0 6 2 113.05 1.250 810 4.074 0.697 45.1 4.9 6.0 6 3 90.50 1.250 851 4.074 0.733 67.1 6.5 6.0 7 4 108.69 1.250 887 4.074 0.764 78.6 7.3 6.0 8 5 103.57 1.250 887 4.074 0.764 83.1 7.7 6.0 8 6 92.24 1.250 887 4.074 0.764 87.1 8.0 6.0 8 7 84.65 1.250 945 4.074 0.814 102.1 9.1 6.0 10 8 122.68 1.250 1,044 4.074 0.900 175.1 14.5 6.0 15 9 120.49 1.250 1,107 4.074 0.954 238.9 19.9 6.0 20
10 4.00 0.900 1,107 4.074 0.954 238.9 19.9 6.0 20 11 12.00 0.900 1,116 3.930 0.927 238.9 14.3 6.0 15
Total or Average
858.87 (=L0)
1.244 937 (=α)
4.072 (=V0)
0.806 (=ρ)
--- --- --- 10.7
Source: JICA Survey Team
Consequently, closing time of 7.0 s, maximum water head of 306.9 m, and maximum pressure rise of
28.5% are applied in the design of the Poring-2 Penstock.
(5) Y-Branch and Branch Pipes
The penstock is divided into two lanes to connect hydraulic turbines at the lower horizontal section in
front of the powerhouse. Y-branch is applied to be open to 60 degrees for 12 m distance from the turbines
and the branch pipes are 0.9 m in diameter.
(6) Anchor Blocks
At the position of 10-No bends, the penstock is supported by concrete anchor blocks. Intermediate
positions between anchor blocks are supported by concrete saddles against vertical load. The overflow
spillway pipe is also aligned parallel to the penstock, so that the supports of the anchor blocks and saddles
will utilize the ones provided for the penstock.
The stability conditions (overturning, sliding, and bearing stabilities) are to be confirmed against each
combination of dead load, combined water pressure, deflection due to temperature change, and seismic
load.
The dimensions of anchor blocks are determined to satisfy the above requirement.
(7) Saddle Supports
Similarly, saddle support is selected and the intervals of support are 6 m.
Final Report
Preparatory Survey on North Sumatra Mini 5-31 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.1.11 PORING-2 HEAD TANK SPILLWAY
Similar design concept for Spillway-1 described in Section 5.1.7 has been applied for Poring-2 head tank
spillway. The head tank spillway is designed to be steel pipe in parallel with the penstock line instead of
discharging to the local river by open channel because of additional countermeasures to prevent the
erosion of channel foundation.
An overflow weir is provided at the inlet of the spillway pipe to allow smooth discharge. Also, an energy
dissipater is designed at the end of the pipe spillway below the erection bay of the powerhouse because
the design discharge with high head will be released. Then, the excess discharge will be released to the
Poring River.
(1) Diameter of Pipe Spillway
The flow inside the spillway pipe is supercritical flow with high velocity. To maintain less than 50% of
flow area ratio (=flow area/pipe are) for safe discharge condition as shown in the following Table 5.1.10,
the pipe diameter should be 1.25 m.
Table 5.1.10 Non-Uniform Flow Analysis for Overflow Spillway Pipe for Poring-2
Source: JICA Survey Team
(2) Energy Dissipater
It is noted that the impact type energy dissipater is provided below the concrete slab of erection bay in the
powerhouse.
Length Depth Area Velocity V head Wet R Invert EL. Slope Ratio Frude
(m) h (m) A (m2) V (m/s) V^2/2g (m) P (m) R (m) (m) θ deg <50% Fr>1
Sta.0 0.0 0.300 0.396 12.61 8.1 2.0 0.2 433.215 7.4
Sta.4 4.4 0.274 0.377 13.26 9.0 2.0 0.2 431.475 21.76 30.7% 8.1
Sta.118 114.0 0.174 0.294 17.03 14.8 1.9 0.2 386.375 21.58 23.9% 13.1
Sta.207 88.2 0.296 0.393 12.71 8.3 2.0 0.2 364.375 14.00 32.1% 7.5
Sta.315 108.4 0.447 0.499 10.03 5.1 2.0 0.3 352.875 6.06 40.6% 4.8
Sta.419 104.0 0.660 0.636 7.86 3.2 2.0 0.3 348.375 2.48 51.8% 3.1
Sta.512 92.5 0.636 0.620 8.06 3.3 2.0 0.3 344.375 2.48 50.5% 3.2
Sta.595 83.7 0.257 0.364 13.74 9.7 2.0 0.2 329.375 10.16 29.6% 8.7
Sta.717 122.1 0.123 0.244 20.48 21.5 1.9 0.1 256.375 30.88 19.9% 18.7
Sta.842 124.9 0.209 0.325 15.41 12.1 1.9 0.2 190.275 27.89 26.4% 10.8
Sta.855 12.7 0.288 0.387 12.90 8.5 2.0 0.2 190.275 0.00 31.6% 7.7
Station
Final Report
Preparatory Survey on North Sumatra Mini 5-32 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Site Conditions of Poring-2 Powerhouse
5.1.12 PORING-2 POWERHOUSE
(1) Site Conditions
The position of the powerhouse was
selected as shown in the alternative
layout study.
Powerhouse-2 is, based on the penstock
alignment on the ridge line, located on a
relatively gentle slope at the foot of the
penstock slope.
The geological investigation revealed
that rock foundation (fresh granite) will
be exposed after 5.0 m deep excavation.
The concrete slab of powerhouse will
be constructed on this rock surface. Turbine setting level is determined above this concrete slab to avoid
deep excavation in the rock foundation.
The access to the powerhouse is a newly constructed project road at the slope beside the penstock. The
difference of elevation from the existing village road to the powerhouse is 188 m and the length is 1,405
m.
Below is the H-Q Curve at Poring-2 Powerhouse Site to estimate flood water level based on flood
discharge in the hydrological study and the results of river cross section survey by non-uniform flow
Figure 5.1.33 H-Q Curve at Powerhouse-2 Site
Outlets are discharged directly into the Poring River from the front of the powerhouse. The tailrace water level
is required at more than 50 cm from the flood level. The design flood for Poring-2 Powerhouse is 100-year
probable flood (Q = 740 m3/s), so that the water depth is 12.55 m above the riverbed (EL. 193.2 m).
(2) Powerhouse Setting Levels
The powerhouse yard elevation of EL. 193.50 m is determined from the 100-year probable flood water
level of the Poring River with a freeboard of 1.0 m based on the H-Q curve below.
100-yr FloodQ= 740 m3/s H= 12.55 m
0.0
5.0
10.0
15.0
0 100 200 300 400 500 600 700 800
Wat
er D
epth
(m
)
Discharge (m3/s)
Poring-2 Powerhouse Site, Tentatively Assumed River H-Q Curve
Non-uniform Flow Analysisby River Cross Section SurveyRoughness coefficient: n=0.05
Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 5-33 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The slab elevation is 20 cm higher than the yard elevation to prevent rainfall discharge into the
powerhouse.
Turbine center level as well as tail water level and penstock center level are determined as explained in
the electro-mechanical design.
Table 5.1.11 Poring-2 Powerhouse Setting Level
Turbine Center Elevation EL. 194.40 m (≤ TWL + Hs*)
Surface Level of Powerhouse Concrete EL. 193.70 m (Yard Level + 0.20 m)
Powerhouse Yard Level (Yard EL) EL. 193.50 m (= FWL + freeboard (= 1.00 m)
Penstock Center Elevation (PCL) EL. 193.00 m (= Turbine Center - A*)
Tailwater Level (TWL) EL. 193.00 m (=FWL + 0.50 m)
Flood Water Level (FWL) (100-year Probable Flood) EL. 192.50 m (from H-Q Curve)
Note: Hs* and A* are explained in the design of the electro-mechanical equipment. Source: JICA Survey Team
(3) Superstructures
The Poring-2 Powerhouse shall incorporate two units of turbine and generator, erection bay, and control
room for operation with dimensions of 10.8 m (width) × 38.0 m (length) × 9.0 m (height).
The superstructure of the powerhouse for ceiling and overhead crane is designed to be a steel frame
structure. The capacity of overhead crane is 20 ton and crane girder is provided.
The plan and profile of Poring-2 Powerhouse are shown below.
Source: JICA Survey Team
Figure 5.1.34 Plan of Poring-2 Powerhouse
Final Report
Preparatory Survey on North Sumatra Mini 5-34 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 5.1.35 Profile of Poring-2 Powerhouse
(4) Powerhouse Yard
Powerhouse yard is a space to accommodate the powerhouse building and tailrace culvert as well as
auxiliary facilities such as main transformer, emergency diesel, and transmission line equipment.
Powerhouse yard with dimensions of 50 m × 20 m requires relatively large excavation at the foot of the
steep slope of penstock. To reduce the excavation volume, the excavation slope should be 1:0.5 and
covered with protection. The protection work is designed to be reinforced concrete frame.
(5) Powerhouse Yard
As described in the previous chapter, hydraulic turbine is 2 units × 5,000 kW and generator is 2 units ×
5,380 kVA.
(6) Tailrace
Poring-2 Tailrace is directly discharged to the Poring River. The water level of the draft pond varies
depending on the plant discharge, but it is important to keep the water level higher to prevent the air from
entering into the draft tube.
To control the water level, an overflow weir is designed at the tailrace. The velocity of the tailrace is
designed to be smaller than 1.0 m/s by increasing the cross sectional area to reduce water surface
fluctuation and head loss.
Final Report
Preparatory Survey on North Sumatra Mini 5-35 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.2 BASIC DESIGN OF HYDRO-MECHANICAL WORKS
5.2.1 GENERAL
The hydro-mechanical works (gates and penstock) of the project includes the work items in Table 5.2.1.
Table 5.2.1 Equipment List of Hydro-Mechanical Works
No. Major Structure Hydro-Mechanical Equipment Poring-1 Poring-2
1 Intake Weir Sand Flush Gate and Hoist 1 set Nil
Sand Flush Gate Stoplog (1 set) Nil
2 Intake Facility Power Intake Trashrack 2 sets Nil
Power Intake Gate and Hoist 2 set 1 set
Power Intake Stoplog (1 set) (1 set)
3 Sand Trap Basin Sand Drain Gate and Hoist 2 set Nil
Sand Trap Basin Trashrack 2 set Nil
4 Head Tank Sand Drain Gate and Hoist 1 set 1 set
Sand Trap Basin Trashrack 1 set 1 set
5 Penstock Steel Penstock including Bifurcation 1 lane 1 lane
6 Head Tank Spillway Steel Spillway Pipe 1 lane 1 lane Source: JICA Survey Team
The conceptual designs of the hydro-mechanical works are made based on the principal design conditions,
i.e., water levels, size, quantity, sill elevation, diameter and length of penstocks, which are determined by
the overall optimization studies for this project, as described in the other sections of this study.
This section outlines the main features of the hydro-mechanical works, i.e., type, materials, construction,
for which the project costs are estimated.
The principal and fundamental factors and requirements of the hydro-mechanical works are:
to have sufficient strength and stiffness against the expected load,
to have enough watertightness for the intended purpose,
to have easy and reliable operation,
to be durable and of robust construction for long-term use,
to have no vibration when used, and
to have easy maintenance.
5.2.2 SAND FLUSH GATE AND HOIST
One sand flush gate at the intake weir will be provided at the fixed weir for flushing the sediments
accumulated in front of the intake so as to secure water intake at any time, as well as for discharging and
controlling the excessive water during flood condition.
The size of this gate is determined to be 2.0 m wide by 2.0 m high.
Final Report
Preparatory Survey on North Sumatra Mini 5-36 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(1) Gate Leaf
The plate girder, fixed-wheel steel gate is selected for the sand flush gate, among others, because of
simple and durable construction and easy and fast manufacturing and installation.
The gate leaf is all-welded steel made of 4-edge rubber seals at the upstream side of the gate leaf.
(2) Hoist
The manually operated stationary rack type hoist is applied for this gate to reduce the lifting force because
of its relatively large lifting load.
(3) Guide Frame
The guide frame is provided to guide the gate leaf in smooth operation and to transmit the water load
acting on the gate leaf to the concrete structures, to keep the watertightness with the rubber seals of the
gate leaf. The bearing plates and sealing plates are made of corrosion-resisting steel because it is difficult
to keep paints on the plates.
Table 5.2.2 Specification of Sand Flush Gate
Item Design Data
Type Plate Girder, Fixed-wheel Steel Gate
Hoist Manual Rack Type
Water-tightness 4-edge Rubber Seals at Upstream Side of Gate
Size Clear Span of 2.0 m × Clear Height of 2.0 m
Guide Frame 11.0 m (height)
Sill EL. EL. 641.7 m
Design Water Level FWL. 651.45 m Source: JICA Survey Team
5.2.3 SAND FLUSH GATE STOPLOG
The slot of one vertical lift slide gate type stoplog will be provided at the upstream side of the sand flush
gate for the purpose of maintenance and repair of Sand Flush Gate and its guide frames.
(1) Gate Leaf
The gate leaf of the sand flush gate stoplog is not provided, because the Stoplog leaf is transported and
utilized for the sand flush gate maintenance.
(2) Hoist
Because of drare operation, permanent hoist is not provided. The Stoplog leaf is lifted up and lowered
down by using manually operated chain block, etc. For the handling of stoplog, a mobile crane will be
used when required.
Final Report
Preparatory Survey on North Sumatra Mini 5-37 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(3) Guide Frame
The concrete slot is provided at 2.0 m upstream side of the Sand Flush Gate. Guide Frames are not
provided taking operation frequency and required water-tightness into consideration.
Table 5.2.3 Specification of Sand Flush Gate Stoplog
Item Design Data
Type Plate Girder, Slide Type Steel Stoplog (common use with sand flush gate stoplog)
Hoist Manually Operated Lifting Tools (Temporary)
Water-Tightness 4-Edge Rubber Seals at Downstream Side of Gate
Slot 2.0 m wide and 11.0 m high
Sill EL. EL. 641.80 m
Design Water Level EL. 646.50 m Source: JICA Survey Team
5.2.4 POWER INTAKE TRASHRACK
Two sets of trashracks will be provided at the inlet of the power intake in order to prevent drifting foreign
material from entering into the sand trap basin. Trash caught by the trashrack will be removed manually.
The trashracks are to have sufficient strength and suitable structure to withstand the impact force, static
and all other loads and vibration phenomena which would likely occur due to the inflow of water. The
water head difference of 1.0 m is applied for the design head of the trashracks.
Table 5.2.4 Specification of Power Intake Trashrack
Item Design Data
Type Fixed Type Bar Screen
Size Clear Span of 3.0 m × Vertical Height of 2.0 m (Inclination 1:0.5)
Bar Pitch 100 mm
Sill EL. EL. 643.5 m
Design Head 1.0 m across the screen Source: JICA Survey Team
5.2.5 POWER INTAKE GATE AND HOIST
(1) Gate Leaf
Two power intake gates will be provided at the inlet of the intake channel for shutting off the water flow
to the sand trap basin. The plate girder, fixed-wheel steel gate is selected for the power intake gate.
(2) Hoist
The stationary rack type hoist is applied because the power intake gate has to have a function of shutting
off at one/both sand traps under [Q = 6.0 m3/s for 100% power generation] without electricity to protect
the waterway from fatality in the case of emergency situation. This gate will be operated frequently
Final Report
Preparatory Survey on North Sumatra Mini 5-38 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
because it controls water flow with gate position. With such situation, motor driven type is applied to
reduce work load of operator. It will be controlled only with local control because the operators always
are at local control room.
(3) Guide Frame
The guide frame is provided to keep the watertightness with the rubber seals of gate leaf, to guide the gate
leaf during operation, and to transmit the water load acting on the gate leaf to the concrete structures. The
sealing frames consist of sealing plate made of corrosion-resisting steel plate and are connected to the sill
beam and front frames.
Table 5.2.5 Specification of Power Intake Gate
Item Design Data
Type Plate Girder, Fixed-wheel Steel Gate
Hoist Motorized Rack Type
Water-Tightness 4-edge Rubber Seals at Upstream Side of Gate
Quantity 2 Sets
Size Clear Span of 2.0 m × Clear Height of 2.0 m
Guide Frame 9.20 m high
Sill EL. EL. 643.50 m
Design Water Level FWL. 651.45 m Source: JICA Survey Team
5.2.6 POWER INTAKE STOPLOG
Two sets of vertical lift slide gate type stoplog will be provided at the upstream side of the power intake
gates for the purpose of maintenance and repair of the gate and its guide frames. The stoplogs have the
same functions and component of the stoplog for the sand flush gate. Because of drare operation,
permanent hoist is not provided. The Stoplog leaf is lifted up and lowered down by using manually
operated chain block, etc. For the handling of stoplog, a mobile crane will be used when required.
Table 5.2.6 Specification of Power Intake Gate Stoplog
Item Design Data
Type Plate Girder, Slide Type Steel Stoplog (common use with tailrace stoplog)
Hoist Manually Operated Lifting Tools
Water-Tightness Nil
Size Clear Span of 2.0 m × Clear Height of 2.0 m
Slot 2.00 m wide and 9.20 m high
Sill EL. EL. 643.5 m
Design Water Level FSL. 646.50 m Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 5-39 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.2.7 SAND DRAIN GATE AND HOIST AT SAND TRAP
Two sand drain gates will be provided in front of the starting point of the headrace channel for flushing
the sediments such as sand and mud accumulated in the sand trap. As the gate size is small, slide type
gate is selected instead of roller gates. Manual spindle type hoist will be applied for the sand drain gate
because of a few oppotunity of operation and small operating loads.
In addition, a valve for environmental maintenance will be provided at the sand trap.
Table 5.2.7 Specification of Sand Drain Gate at Sand Trap Basin
Item Design Data
Type Plate Girder, Slide Type Steel Gate
Hoist Manual Spindle Type
Water-Tightness 4-edge Rubber Seals at Upstream Side of Gate
Quantity 2 Sets
Size Clear Span of 1.0 m × Clear Height of 1.0 m
Guide Frame 7.50 m high
Sill EL. EL. 640.0 m
Design Water Level EL. 647.01 m (FWL in Sand Trap)
Type of Valve Butterfly Valve
Diameter of Valve φ300
Valve EL. EL. 642.5m Source: JICA Survey Team
5.2.8 SAND TRAP TRASHRACK
Two trashracks will be provided at the end of the de-silting basin in order to prevent drifting foreign
matters from entering into the headrace channel. The trashrack has sufficient strength, stiffness and
suitable structure to withstand the impact force, static and all other loads, and vibration phenomena which
would likely occur due to the inflow of water. Trash caught by the trashrack will be removed manually.
The water head difference of 1.0 m is applied for the design head of the trashracks.
Table 5.2.8 Specification of Sand Trap Trashrack
Item Design Data
Type Fixed Type Bar Screen
Size Clear Span of 3.0 m × Vertical Height of 3.5 m (Inclination: 1:0.5)
Quantity 2 Sets
Bar Pitch 100 mm
Sill EL. EL. 644.0 m
Design Head 1.0 m across screen Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 5-40 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.2.9 SAND DRAIN GATE AND HOIST AT HEAD TANK
One sand drain gate will be provided at each head tank for flushing the sediments such as sand and mud
accumulated in the head tank. Slide type gate is selected instead of roller gates as well as the de-silting
basin sand drain gate. Manual spindle type hoist will be applied for the sand drain gate because of few
operations and small operating loads.
Table 5.2.9 Specification of Sand Drain Gate at Head Tank
Item Poring-1 Poring-2
Type Plate Girder, Slide Type Steel Gate Plate Girder, Slide Type Steel Gate
Hoist Manual Spindle Type Manual Spindle Type
Quantity 1 Set 1 Set
Water -Tightness 4-Edge Rubber Seals at Upstream Side
of Gate
4-Edge Rubber Seals at Upstream Side
of Gate
Size Clear Span of 1.0 m × Clear Height of
1.0 m
Clear Span of 1.0 m × Clear Height of
1.0 m
Guide Frame 4.20 m high 4.20 m high
Sill EL. EL. 636.80 m EL. 432.20 m
Design Water Level EL. 641.00 m (Spillway crest level) EL. 436.40 m (Spillway crest level) Source: JICA Survey Team
5.2.10 HEAD TANK TRASHRACK
One trashrack will be provided at each inlet of the penstock in order to prevent drifting foreign material
from entering into the hydraulic turbines. The trashracks are to have sufficient strength and suitable
structure to withstand the impact force, static and all other loads, and vibration phenomena which would
likely occur due to the inflow of water. The water head difference of 1.0 m is applied for the design head
of the trashracks.
Table 5.2.10 Specification of Head Tank Trashrack
Design Conditions Poring-1 Poring-2
Type Fixed Type Bar Screen Fixed Type Bar Screen
Size Clear Span of 6.00 m × Vertical Height
of 3.50 m (Inclination of 1:0.3)
Clear Span of 5.00 m × Vertical Height
of 3.50 m (Inclination of 1:0.3)
Bar Pitch 70 mm 70 mm
Sill EL. EL. 638.50 m EL. 433.90 m
Design Head 1.0 m across screen 1.0 m across screen Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 5-41 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.2.11 PENSTOCK AND SPILLWAY PIPE
(1) Material for Penstock and Spillway Pipe
Steel has been widely used for penstock as a conventional material, but recently, fiber (fiberglass)
reinforced plastic (FRP) has been used as an alternative material for steel. The comparison study between
steel and FRP pipes to be used for penstock is shown in the following table:
Table 5.2.11 Material Comparison between Steel and FRP
Description Steel FRP
Structure
Unit steel pipes are connected by welding and form a continuous beam. There is no joint except the expansion joint provided between anchor blocks. Steel pipe is supported on saddles and fixed by anchor block.
Each unit pipe is connected with a coupling provided to each pipe, and accordingly there are joints at the respective couplings. Each unit pipe is fixed by thrust collar at each saddle support.
Design Standard Established and verified from experiences for long time
Recently established and not so long experience
Verification of Strength Conservatively verified by allowable stress method
Verified by similar allowable stress method or other method
Ease of Construction
Welding for unit pipe connection is slightly complicated.
Compared with steel pipe, as weight of FRP pipe is lighter, the handling for construction is easier than steel pipe. The connection of unit pipe is simple and easy with slip-on coupling.
Corrosion Resistance Steel tends to be corroded if no protection. Plastic is stable against chemical reaction such
as corrosion.
Abrasion Resistance Compared with plastic, steel is stable against abrasive material such as sand.
Without protection, plastic is weak against abrasive material.
Weathering Resistance
Steel will be corroded under acid environment. If properly protected, long lifetime will be expected.
If plastic is exposed under the conditions of high temperature and/or strong UV ray, it will be deteriorated in a short time.
The stability of structure is essential for the function of penstock considering safety of high pressure
waterway. Taking into account the established and verified technology of steel penstock, steel should be
adopted as the material of penstock and spillway pipe for conservative design in this stage. Because FRP
has merits during the construction stage and O&M, it might be applied to penstock and spillway pipe
provided that further study should be considered for the structural stability and durability against
abrasion/weathering resistance.
Expansion joint
Saddle supports
Steel pipe
Final Report
Preparatory Survey on North Sumatra Mini 5-42 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Steel Penstock
One complete lane of steel penstock with one bifurcation and two branches will be provided for supplying
the water from the head tank to two hydraulic turbines in the powerhouse. The diameters of penstock are
1.35 m and 1.25 m for the one lane section, and 1.0 m and 0.9 m after the two branches.
The internal pressure is the sum of static head and the pressure rises due to water hammer. The shell
thickness of the steel penstock is designed so that the shell itself have sufficient strength against the
design internal pressure without expecting any support from the surrounding concrete/rock.
Expansion joints are provided at the immediate downstream of each anchor block to absorb the
longitudinal movements due to alteration of temperature.
Ventilation pipes are provided at bend to avoid damages by negative pressure.
Y-type bifurcation is provided at the inclined bottom portion of the penstock to be encased with concrete
and backfilled in front of the powerhouse.
Table 5.2.12 Specification of Penstock
Item Poring-1 Poring-2
Diameter 1.35 m (1 lane) ~ 1.00 m (Branch pipe: 2 lanes)
1.25 m (1 lane) ~ 0.90 m (Branch pipe: 2 lanes)
Total Length 430.9 m 857.3 m
Static Head 199.5 m 243.2 m
Water Hammer 30.0% at center line of Water Turbine 30.0% at center line of Water Turbine
Thickness 6.0 mm ~ 12.0 mm 6.0 mm ~ 19.0 mm Source: JICA Survey Team
(3) Spillway Pipe
The head tank spillway steel pipe is provided in parallel to the steel penstock to safely release the excess
discharge of the head tank to the tailrace. To maintain less than 50% of flow area ratio (=flow area/pipe
area) for safety discharge condition, the pipe diameters are 0.95 m for Poring-1 and 1.25 m for Poring-2.
The design load is the deadweight of the pipe and water. The internal pressure is not applied because the
excess discharge will flow with the free water surface. Ventilation pipes will be installed at the bend to
prevent negative pressure.
Table 5.2.13 Specification of Head Pond Spillway Pipe
Item Poring-1 Poring-2
Diameter 0.95 m 1.25 m
Total Length 430.4 m 854.5 m
Thickness 6.0 mm 6.0 mm Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 5-43 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.3 BASIC DESIGN OF ELECTRO-MECHANICAL WORKS
5.3.1 BASIC DESIGN CONDITIONS
(1) Applied Standards
All electrical and electromechanical equipment are designed to comply with the latest revision of the
authorized standards of the International Electro-technical Commission (IEC) as much as applicable.
(2) Service Conditions
All electrical and electromechanical equipment are designed for satisfactory operation under the
following service conditions:
Ambient temperature : Not exceeding 40C
Water temperature : Not exceeding 28C
Altitude : Not exceeding 1,000 m
5.3.2 HYDRAULIC TURBINES
(1) Operating Water Level Conditions
Hydraulic turbines are designed to operate under the following conditions:
Table 5.3.1 Operating Water Level Conditions Item Poring-1 Poring-2
Intake Water Level (at Intake Weir) Full Supply Water Level (FSL)
EL. 646.5 m
EL. 441.6 m
Intake Water Level (at Head Tank) Full Supply Water Level (FSL) Rated Water Level Minimum Operational Level (two-unit) Minimum Operational Level (one-unit)
EL. 641.0 m EL. 641.0 m EL. 640.8 m EL. 640.6 m
EL. 436.4 m EL. 436.4 m EL. 436.2 m EL. 436.0 m
Tail Water Level Flood water level Water Level at Two-unit Operation Water Level at One-unit Operation Low Water Level (no-flow)
EL. 441.5 m EL. 441.8 m EL. 441.5 m EL. 441.1 m
EL. 192.7 m EL. 193.0 m EL. 192.7 m EL. 192.3 m
Head Loss Head Loss due to Two-unit Operation Head Loss due to One-unit Operation
6.0 m 2.0 m
11.1 m 3.3 m
Gross Head and Net Head Maximum Gross Head: Hg Maximum Net Head: Hmax *1 Design Head (Rated Head): Hd *2 Minimum Net Head: Hmin *3
646.5-441.1=205.4 m
641.0-441.5-2.0=197.5 m 641.0-441.8-6.0=193.2 m 640.6-441.8-6.0= 192.8 m
441.6-192.3=249.3 m
434.4-192.7-3.3=240.4 m 436.4-193.0-11.1=232.3 m436.0-193.0-11.1= 231.9 m
Note: *1 = 1-unit operation at rated output, *2 = 2-unit operation at rated output, *3=2-unit operation at guide vanes fully opened Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 5-44 Nippon Koei Co., Ltd.
Hydropower Project (PPP Infrastructure Project)
(2) Turbine Output
The turbine rated output is expressed by the following equation:
(kW)
where, is the turbine output (kW), is the unit discharge (m3/s), is the rated head (m), is the
turbine efficiency = 0.92.
Table 5.3.2 Turbine Output
Item Poring-1 Poring-2
Unit discharge: 6.0 / 2 = 3.0 m3/s/ 5.0 / 2 = 2.5 m
3/s
Rated head: 193.0 m 232.2 m
Turbine efficiency: 88.6% 92.4%
Turbine output: 5,000 kW 5,000 kW Source: JICA Survey Team
(3) Type of Turbine
Referring to the selection chart for turbine type, a horizontal-shaft Francis turbine is selected for the rated
output of 5,000 kW and rated heads (design head) of 193.0 m for Poring-1 and 232.2 m for Poring-2.
Figure 5.3.1 Selection Chart for Turbine Type
(4) Rated Speed and Specific Speed
In general, the larger rotational speed is proportional to the smaller size turbine and generator, which
result in an advantage of equipment cost. Due to the limitation of the specific speed, smaller than 1,000
rpm is applicable for the rotational speed.
However, the turbine and generator setting is deeper than the ground level at N=1,000 rpm because the
Poring-1
Poring-2
1
10
100
1000
0.01 0.1 1 10 100
He (m)
Q (m3/sec)
Poring-1
Poring-2
Pelton
Turgo Impulse
Francis (H)
Francis (V)
Kaplan
Reverse Pump
Propeller (Siphone)
Crossflow
Submersible Pump
Tubular (S)
Propeller (Inline)
Source: NEF Small Hydropoewr Guidebook, 2005
Final Report
Preparatory Survey on North Sumatra Mini 5-45 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
draft head (Hs) is smaller, and the turbine center is lower than the tailwater level, so that civil
construction cost will be increased by greater rock excavation as well as care of water and slope
protection during construction, higher powerhouse building, and for ease of construction. Such risks are
normally prevented particularly for horizontal axis turbine and generator. Accordingly, rated rotational
speed of N=750 rpm was selected.
Table 5.3.3 Specific Speed (Ns)
Item Poring-1 Poring-2
Limitation of Specific Speed Ns 143 mkW 128 mkW
Limitation of Rotational Speed N 1,458 rpm 1,640 rpm
Nearest Rotational Speed N 750 rpm 750 rpm
Calculated Specific Speed Ns 74 mkW 59 mkW Source: JICA Survey Team
(5) Turbine Setting Level and Runaway Speed
The turbine setting level is defined as the elevation of the centerline of turbine distributor and is
calculated from the tailrace water level at one-unit operation.
Table 5.3.4 Turbine Setting Level
Item Poring-1 Poring-2
Cavitation Coefficient, σp 0.031 0.022
Rated Head, Hd 193.00 m 232.20 m
Atmospheric Pressure at TWL, Ha 9.80 m 10.10 m
Vapour Pressure at Water Temperature T=22C, Hv 0.30 m 0.30 m
Suction Head, Hs 3.62 m 4.78 m
Distance between Turbine and Runner Centers, I 0.35 m 0.40 m
Tailrace Water Level at One-unit Full Operation, TWL EL. 441.60 m EL. 192.60 m
Maximum Turbine Center Setting Level Lower than
EL. 444.90 m
Lower than
EL. 197.00 m Source: JICA Survey Team
Table 5.3.5 Maximum Runaway Speed
Item Poring-1 Poring-2
Runaway Speed (Nr) 1,208 rpm 1,191 rpm
Maximum Runaway Speed (Nrmax) 1,218 rpm 1,206 rpm Source: JICA Survey Team
(6) Inlet Valve
The maximum static water pressure head for the inlet valve is 640.0-443.5=196.5 m for Poring-1 and
434.0-194.5= 239.5 m for Poring-2. Referring to Table 5.3.6 below, through-flow type butterfly valve is
applied to the inlet valve with maximum static head of around 200 m.
Final Report
Preparatory Survey on North Sumatra Mini 5-46 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 5.3.6 Comparison of Performance of Inlet Valves
Item Spherical Valve Butterfly Valve Through-flow Valve
Applicable head (max. static head) Above 200 m Below 200 m Below 300 m
Coefficient of head loss of inlet valve Very small Large Relatively small
Allowable leakage water from main valve Very small Large Relatively small
Price High Low Low Source: JICA Survey Team
(7) Main Water Supply System
The main water supply system designed to provide the cooling water to the turbine guide bearing,
generator thrust, and guide bearings and turbine sealing water for Poring-1 and Poring-2 is based on a
direct water supply system from the penstock. The necessary cooling water quantity will be relatively
little because the air cooling method is applied to the generater as mentioned below. By applying a direct
water supply system, pressure reducer shall be installed near the intake point in consideration of the rated
heads of Poring-1 and Poring-2.
(8) Water Drainage and Dewatering System
The water drainage system is required to discharge the water from the station sump pit to the tailrace. On
the other hand, the dewatering system is required to discharge the water in the draft tube to the tailrace
espacially during maintenace of the turbine runner. In case of Poring-1 and Poring-2, the turbine center
level will be set higher than the tailrace water levels, then the maintenance of the turbine runner can be
carried out without dewatering in the draft tube. When dewatering in the draft tube is required, once the
water in the draft tube is discharged to the station sump pit, the water is discharged to the tailrace by the
water drainage pumps.
The water drainage system will consist of two AC motor-driven drainage pumps, two water level
switches, and water piping complete with all necessary pipes and valves to discharge the water in the
station sump pit to the tailrace. Two pumps for drainage water system will be arranged for
normal/standby duty operation.
Types and ratings of the water drainage pumps are determined as shown in Table 5.3.7 below.
Table 5.3.7 Types and Ratings of Drainage Pumps
Items Specifications
(a) Type of drainage pump Submersible type
(b) Displacement volume of each pump 1.0 m3/min
(c) Pumping head 30 m Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 5-47 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
5.3.3 GENERATORS
(1) Generator Output
The generator output (Pg) is calculated from the turbine output by the following equation:
Pg Pt ∙ ηg ∙ 1/cosθ (kVA)
where, Pt is the turbine output (kW), ηg is the generator efficiency and cosθ is the power factor.
Table 5.3.8 Power Output of Generator
Item Poring-1 Poring-2
Turbine Output, Pt 5,000 kW 5,000 kW
Generator Efficiency, ηg 97.0% 97.0%
Power Factor, cosθ 0.90 0.90
Generator Output, Pg 5,380 kVA 5,380 kVA Source: JICA Survey Team
(2) Type of Generator
The generators for Poring-1 and Poring-2 are of three-phase, horizontal-shaft, synchronous alternator
type.
(3) Generator Rated Voltage
The generator rated voltage of Poring-1 and Poring-2 is selected as 6.6 kV.
(4) Generator Neutral Grounding System
The neutral point of the generator stator winding will be grounded through a neutral grounding
transformer with a secondary resistor.
(5) Synchronizing Method of Generator
The generator synchronizing will be made by the 6.6 kV circuit breaker on the generator circuit.
(6) Flywheel Effect (GD2) of Generator
Flywheel Effect of Turbine and Generator
In accordance with the USBR Standard1, the flywheel effect of the turbine (GD t) and generator (GD n
is calculated by the following equation:
GD t 3.9428 ∙ Pt/N . . (tonm2)
GD n 60 Pg/N . . (tonm2)
1 Engineering Monograph No. 20 of US Bureau of Reclamation (Revised in 1976)
Final Report
Preparatory Survey on North Sumatra Mini 5-48 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
where, Pt is the turbine output (kW), Pg is the generator output (kW), N is the rated rotational speed
(rpm).
Table 5.3.9 Fly Wheel of Turbine and Generator
Item Poring-1 Poring-2
Turbine Output, Pt 5,000 kW 5,000 kW
Generator Output, Pg 4,850 kW, 5,380 kVA 4,850 kW, 5,380 kVA
Rated Rotational Speed, N 750 rpm 750 rpm
Flywheel Effect of Turbine, GD t 0.68 tonm2 0.68 tonm2
Flywheel Effect of Generator, GD n 11.24 tonm2 11.24 tonm2 Source: JICA Survey Team
The flywheel effect of a generating unit (turbine and generator) shall be sufficient to insure prompt
response to changes in load demands.
Conditions to respond to changes in load demands: GD21
Conditions to respond to speed rise and pressure rise: GD22
The required flywheel effect of the generator (GD2r) is determined to satisfy the following relationship:
GD2r GD2u GD2t (tonm2)
where, GD is the required flywheel effect of generator, = GD and GD whichever is larger, and
GD is the required flywheel effect of turbine.
Table 5.3.10 Necessary Fly Wheel of Turbine and Generator
Item Poring-1 Poring-2
Required Flywheel Effect of Turbine, GD2t 0.68 tonm2 0.68 tonm2
Required Flywheel Effect of Generating Unit, GD2u 10.46 tonm2 15.58 tonm2
Required Flywheel Effect of Generator, GD2r 9.78 tonm2 14.90 tonm2 Source: JICA Survey Team
As studied above, the additional fly wheel will not be required for the generator in Poring-1. However, for
Poring-2, it will be necessary to install the additional fly wheel which has a weight of 32.5% of its
generator.
5.3.4 MAIN TRANSFORMERS
(1) Type and Cooling Method
The main transformers are of single-phase, oil-immersed, two-winding, outdoor installation type intended
to be connected directly to the 6.6 kV busbar in the power station. The cooling method is selected to be
natural oil circulation forced air cooling (ONAF). In case some problems occur in the cooling fans, the
main transformer is able to be operated under ONAN mode which has 70% capacity of the rated power of
the main transformer.
Final Report
Preparatory Survey on North Sumatra Mini 5-49 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Main Transformer Rated Power
The rated power of the main transformers should be 11,000 kVA for three-phase which corresponds to the
generated power of two units.
(3) Main Transfomer Rated Voltage
The rated voltage of the main transformers should be 6.6 kV at primary winding and 33 kV at secondary
winding. Main transformer is equipped with on-load tap changer of ±1.5%
5.3.5 BASIC ELECTRICAL CONNECTION IN POWER STATION
(1) Transmission System
The generated power of Poring-1 and Poring-2 power stations is evacuated to PLN’s Tarutung Substation
located approximately 35 km by two 33 kV circuits with one pole line for each power station, which will
be constructed along the existing public road and operated and maintained by the project. The above 33
kV transmission line is a branch line for power supply to the equipment and facilities at the intake weir
and head tank of Poring-1 and Poring-2, respectively.
(2) Main Circuit
Control of Generating Unit
The generating units are designed to be operated and controlled from the control room of the Poring
power stations, and remote control from the PLN substation is not required.
Synchronizing of Generator
The generator is designed to make synchronization by a generator voltage (6.6 kV) circuit breaker or a
distribution line (33 kV) circuit breaker. In case of start/stop operation of a generating unit, the
synchronization is made by a generator voltage circuit breaker to conveniently carry out changeover of
the station service.
Generator Voltage (6.6 kV) Switchgear
The generator voltage switchgear is designed for the following ratings:
(a) Rated voltage : 7.2 kV
(b) Rated normal current : 630 A
(c) Rated short-time withstand current : 25 kA
Station Service Power Supply System
The electric power to the equipment and facilities in the power station is supplied from 6.6/0.4 kV station
service transformer which is a three-phase, indoor installation and dry type transformer connected to 6.6
kV busbar. In case of shutdown of station service or black start of generator, an emergency diesel engine
generator is operated.
Final Report
Preparatory Survey on North Sumatra Mini 5-50 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
DC Power Supply System
DC 110 V supply system is required to be installed in the powerhouse for the operation voltage of the
switchgear. The stationary batteries will be designed as follows:
(a) Type : Sealed construction, valve regulated type, lead acid batteries
(b) Capacity : 300 AH at 10-hour discharge rate
(c) Number of cells : 53 cells/set
5.3.6 POWERHOUSE CRANE
(1) Lifting Capacity
The required lifting capacity of the powerhouse crane will be determined from the estimated weight of the
generator rotor.
The weight of the generator rotor will be estimated from the generator output and rotational speed using
the following formula:
Water Power and Dam Construction (Nov. 1978)
Wr = 50*(Pg/N0.5)0.74 (ton)
Wr = 50*(5.38/7500.5)0.74 (ton)
= 15.0 (ton)
Where, Wr: Rotor weight (ton), Pg: Generator output (MVA), N: Rotational Speed (rpm)
Static Data in Japan for Semi-Umbrella Type Generator
Wr = 1.5393*(Pg*1,000)0.7166*N-0.6001 (ton)
Wr = 1.5393*(5.38*1,000)0.7166*750-0.6001 (ton)
= 13.7 (ton)
As shown above, the weight of the generator rotor is calculated as 15.0 ton.
(2) Lifting Capacity
The following Table 5.3.11 shows the specification of the powerhouse crane for Poring-1 and Poring-2.
Table 5.3.11 Outline Specification for Powerhouse Crane
Powerhouse Crane Poring-1 Poring-2
Estimated weight of generator rotor 15.0 ton 15.0 ton
Estimated weight of lifting beam 2.0 ton 2.0 ton
Required lifting capacity 17.0 ton 17.0 ton
Rated lifting capacity of main hook 20 ton x 1 20 ton x 1
Span of crane rails 8.7 m 8.7 m Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 6-1 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
CHAPTER 6 CONSTRUCTION PLAN
6.1 CONSTRUCTION PLAN
6.1.1 BASIC CONDITION
Major structure in this project are shown below
- Access Road : length of refurbishment (24 km, including vertical aliment improvement 6.8 km3)
Earth work volumes of access road were estimated by the average cross-sectional method from
cross-section of the 25m interval. Earth Fill materials are used to the excavation materials.
Table 6.1.1 Quantities of Access Road Work
Unit Quantity
Excavation m3 260,000
Earth fill m3 91,000 Source: JICA Survey Team
- Poring-1 : Intake (width33.0 m ×height 7.0 m), Headrace Channel (length 2,490m, width 1.9 m
× height 2.0m), Head Tank, Penstock (length 426m, 1.35m, Spillway pipe0.95 m),
Powerhouse
- Poring 2 : Headrace Channel (length 2,581m, width1.6m × height 1.9m), Head Tank, Penstock
(length 860m, 1.25m, Spillway pipe 1.25 m), Powerhouse
The following items are Key factor which will affect the method statement and schedule. The quantities
of main construction work have been estimated from the basic design drawings.
Table 6.1.2 Quantities of Main Work
Source: JICA Survey Team
Unit Excavation Earthfill ConcreteIntake m3 13,500 816 4,524 Waterway m3 83,179 6,535 5,880 Head Tank m3 3,110 160 593 Penstock m3 48,630 480 1,430 Powerhouse m3 13,700 150 1,100 Project Road m3 24,030 9,970 ----- Waterway m3 79,057 7,091 6,637 Head Tank m3 2,550 200 402 Penstock m3 136,180 460 2,570 Powerhouse m3 8,780 150 970 Project Road m3 43,324 12,346 -----
456,039 38,358 24,106 Total
Pori
ng-2
Pori
ng-1
Final Report
Preparatory Survey on North Sumatra Mini 6-2 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(1) Weather Condition
Yearly average temperature at project area is around 24℃. Yearly average rainfall is 3,448mm. The
amount of rainfall is quit high through a year. But the trend shows the rainfall from August to December
is more than other season.
(2) Construction Material
1) Cement
Normal Portland cement will be used. The supplier will be Padang cement. The cement will be
transported by ship to Sibolga from Padang port and transported to site by truck.
2) Aggregate
Aggregate will be purchased from the supplier in Tarutung. Considering the concrete schedule, we should
plan to stock the aggregate for the concrete volume which will be used in one week period.
3) Sand
Sand will be purchased from the supplier in Tarutung. Considering the concrete schedule, we should plan
to stock the sand for the concrete volume which will be used in one week period.
4) Re-bar
Re-bar will be purchased from the supplier in Medan. Re-bar will be supplied by in-land transportation
from Medan.
5) Rock material for masonry
Rock material will be taken from rock excavation by blasting. Also, rock material will be corrected from
river around site.
(3) Workable days
For the planning of construction method, following condition will be used considering Indonesian local
situation.
- Working hours : 8:00 ~ 17:00 (no night shift)
- Workable days:monthly average 20days(earth work), monthly average23days(concrete and
other works)
Fixed holidays are Sunday of every other week. (Hariraya holidays are excluded)
6.1.2 CONSTRUCTION SCHEDULE
Construction period for preparatory access road work is 6 months, and Main work is 36 months, by the
planning of method statement and quantities which is made from basic condition. Each commissioning
test at construction schedule were estimated for Poring-1 mini hydropower project at 27 months and
Poring-2 mini hydro project at 36 months including 4 month allowance. The construction schedule of
preparatory access road work and main work are shown below.
Final Report
Preparatory Survey on North Sumatra Mini 6-3 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 6.1.1 Preparatory Access Road Work
Access Road worksMobilization LS 1
Earth work (Excavation) cu.m 260,000Earth work (Earthfill) cu.m 92,000Pavemnt work (Gravel) sq.m 40,000Pavemnt work (Concrete) sq.m 30,000Drainage & culvert work LS 1
Demobilization LS 1
Mar.Nov. Dec.2016 2017
Unit QuantityAug. Sep. Oct. Jan. Feb.
F
inal Report
Preparatory Survey on N
orth Sumatra M
ini 6-4
N
ippon Koei C
o., Ltd.
Hydropow
er Project (P
PP
Infrastructure Project)
S
ource: JICA
Survey Team
Figu
re 6.1.2 M
ain W
ork S
ched
ule
Final Report
Preparatory Survey on North Sumatra Mini 6-5 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
6.1.3 PREPARATORY ACCESS ROAD WORK
In the road from Tarutung to project site, 24km of the road to project side should be improved. The
section to be improved is from Aek Nauli village to Siantar Naipospos village. Only motorbike can go
through the existing road. The improvement work makes the road wide enough for passing by
construction heavy equipment. And longitudinal slope should be refurbished below 14%. Earth work
volumes and each pavement quantities is indicated in the table below.
Concrete pavement work will be applied for the road surface which is more than 10% slope. Other section
surface will be aggregate pavement. The access road work will be planned to work to fulfil 6 month
construction schedule.
Table 6.1.3 Quantities of Access Road Work
Unit Quantity Excavation m3 260,000 Earth fill m3 91,000 Pavment (concrete)
m3 29,920
Pavement (Gravel)
m3 39,680
Source: JICA Survey Team
6.1.4 TEMPORARY FACILITY PLAN
(1) Concrete Plant
A batching plant with 30m3/h capacity will be planned at temporary facility yard. For the transportation of
concrete, truck mixer 5m3class:3nos, truck mixer 3m3:4nos, will be used. Aggregate and sand will be
purchased from Tarutung supplier.
Adding the batching plant, drum mixer 0.8m3class:2nos, and drum mixer 0.2m3class:4nos will be
prepared for supporting concrete work.
Source: JICA Survey Team
Figure 6.1.3 Concrete Pouring Schedule
0
50
100
150
200
250
300
0
5,000
10,000
15,000
20,000
25,000
30,000
No
v.'1
7
Dec
.'17
Jan.
'18
Feb
.'18
Mar
.'18
Ap
r.'1
8
May
'18
Jun.
'18
Jul.'
18
Aug
.'18
Sep
.'18
Oct
.'18
No
v.'1
8
Dec
.'18
Jan.
'19
Feb
.'19
Mar
.'19
Ap
r.'1
9
May
'19
Jun.
'19
Jul.'
19
Aug
.'19
Sep
.'19
Oct
.'19
No
v.'1
9
Dec
.'20
Pla
cing
vo
lime
per
day
(m3 /
day
)
Pla
cing
vo
lum
e (m
3 )
Maximum daily concrete placing volume
Average daily concrete placing volume
Accumulative concrete placing volume
Final Report
Preparatory Survey on North Sumatra Mini 6-6 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Re-bar Bending Yard
Re-bar stock yard and bending yard will be planned in temporary facility yard. All re-bar bending work
will be done in this yard and transport to each construction site.
(3) Site office and camp
Contractor’s site office and camp will be set up at temporary facility yard.
(4) Electric supply and water supply
Required electricity on site will be supplied by generator. Schedule for number of generator on site is
shown below. Water supply will be arranged at upstream of Intake and deliver to each construction site by
water truck.
Source: JICA Survey Team
Figure 6.1.4 Schedule for Number of Generator on Site
6.1.5 SPOIL BANK
Drainage during construction period should be cared adequately. Open drainage should be arranged at one
side on the spoil area when disposal work are going on. Thickness of spreading disposal material should
be 1m. Each layer should be compacted by Bulldozer. (6-8times)
If the edge of spoil bank slope is unstable, gabion mat or concrete wall should be constructed to make
stable and protect from drainage and heavy rain water. Spoil bank slope should be compacted using
backhoe bucket. After disposal work completed, drainage should be made on the spoil bank surface.
0
10
20
30
40
50
60
Nu
mb
er
15KVA
200kVA
Totalnum.
Max./month
200kVA 32 115KVA 802 54
Generator
Final Report
Preparatory Survey on North Sumatra Mini 6-7 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
6.1.6 PORING-1 MAIN CONSTRUCTION WORKS
(1) Project Road
1) Project road No, 1
Project road No, 1 is an access road from public access road to Intake. It is planned to enlarge the existing
small path. During construction period, it will be used as access to Intake and Headrace channel
construction. After construction is completed, it will be permanent access road to Intake. The
construction of Project road No, 1 will be started immediately after commencement of Poring-1 project,
the construction period is planned as 1.5months.
2) Project road No, 2
Project road No, 2 is an access road from public access road to Head Tank. During construction period, it
will be used as access to Head Tank and downstream of Headrace channel construction. After
construction is completed, it will be permanent access road to Head Tank. The construction of Project
road No, 2 will be started immediately after commencement of Poring-1 project, the construction period
is planned as 1.0months.
(2) Temporary Access Road for construction
1) Temporary Access Road No, 1
This is temporary access road from temporary facility yard to the middle point of Headrace Channel.
During construction period, it will be used as access road for excavation work and concrete work of
Headrace Cannel. The construction of Temporary Access Road No, 1 will be started immediately after
commencement of Poring-1 project, the construction period is planned as 2.0months.
2) Temporary Access Road No, 2-1,2-1,2-3
This is temporary access road from Siantar Nai-pospos village to 2 point of penstock and Powerhouse.
During construction period, it will be used as access road for excavation work and concrete work of
Penstock and Powerhouse. The construction of Temporary Access Road No, 2-1, 2-2, 2-3 will be started
immediately after commencement of Poring-1 project, the construction period is planned as 3.0months.
Final Report
Preparatory Survey on North Sumatra Mini 6-8 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 6.1.5 Layout of Project Road and Temporary Access Road
(3) Intake
1) Temporary work and excavation work
1st stage excavation work period is planned as 1.0month, and 2nd stage is 0.5month. The construction
period for diversion work is planned as 1.0month for 1st stage, and 0.5month for 2nd stage. The diversion
work should be done before excavation starting.
2) Concrete work construction period and organization
The construction work of Intake will not be a critical for the total schedule. So, the construction period
will be planned in 2018 dry season. Concrete work period is 3.5month in 1st stage, and 3month in 2nd
stage.
3) River diversion work
The construction of Intake weir and Intake will be done by 2 stage river diversion. Intake structure and left
side of Intake weir structure construction is on 1st stage. The remaining right side Intake weir structure will be
constructed on 2nd stage. Before starting excavation work of Intake and Intake Weir, River diversion work for
1st stage should be done. For excavating Intake and left side of Intake Weir area as 1st stage construction, sheet
pile wall will be constructed at middle of river. Sheet pile will be constructed from 5m upstream from Intake
weir to 5m downstream from counter dam. Upstream and downstream of the sheet pile will be connected and
filled by random material. After 1st stage concrete work is completed, up and downstream cofferdam should be
Final Report
Preparatory Survey on North Sumatra Mini 6-9 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
moved to the opposite side for 2nd stage construction work. Sheet pile will be embedded into Intake concrete
structure. The scale of diversion work has not been intended for flood conditions. Target discharge of
diversion work is estimated by the one year from construction period which is planned at maximum value
of the low flow analysis result (about Q=60m3/s). In addition, the construction status diagram is shown
in the below.
Source: JICA Survey Team
Figure 6.1.6 Figure 3.4.19 Flow Duration Curve at Poring-1 Intake Site
1st Stage River Diversion for Intake Weir 2nd Stage River Diversion for Intake Weir Source: JICA Survey Team
Figure 6.1.7 Layout of Project Road and Temporary Access Road
Final Report
Preparatory Survey on North Sumatra Mini 6-10 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
- Intake Diversion work 1st stage
The multiple-stage diversion method for the river water level by the sheet piles is determined in uniform
flow calculation water level to be added velocity head.
30.6422
2.437.641
237.641
22
gg
vWL
Source: JICA Survey Team
Figure 6.1.8 Typical Section of Diversion Work 1st Stage
- Intake Diversion work 2nd stage
Diversion work of 2nd stage is used the Intake and Sand flash. The water level of diversion work for
target discharge (Q = 60m3/s) is EL.646.92. In this case are became overflow of intake weir spillway.
Drainage capacity of the diversion work of 2nd stage is shown in the below.
- Drainage capacity of Sand flash only : Q = 25.30m3/s
- Do not overflow the Intake weir of spillway: Q = 53.3m3/s
Each facilities of discharge (sand land sand elimination gate, sediment ejection, water through the water
intake weir) are as shown in Figure 6.1.10. In addition, case of target discharge (60m3/s) will be shown in
the following formula.
Q4(Target discharge of diversion work) = Q1 (35.36) + Q2 (20.20) + Q3 (4.44) = 60m3/s.
Source: JICA Survey Team
Figure 6.1.9 Typical Section of Diversion Work 2nd Stage
Design Slope i=1/ 50.0Roughness Module n= 0.035Design Discharge Q=60m3/sWater Depth hw=1.76mVelocity V=4.20m/sMinimum Riverbed E.L 639.61Water Level E.L 641.37
Q1(Sand drain) Q2
(Sand trap basin)
Q3(Weir crerst)
Final Report
Preparatory Survey on North Sumatra Mini 6-11 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Source: JICA Survey Team
Figure 6.1.10 Drainage Capacity of Diversion Work 2nd Stage
(4) Headrace Channel
1) Temporary work and excavation work
For stating the excavation work of Headrace Channel, it is required to complete the construction of
Project road No, 1 and 2. The excavation of Headrace channel will be started at 2nd month from project
commencement. The period of Headrace Channel excavation is 7.3months.
2) Concrete work construction period and organization
Concrete work will be started after 6.5months from the commencement of excavation. Total working
period of concrete work is 14months. Only top slab concrete work is expected in last 2.5 months. For
the construction of Box type culvert, the construction of U-Type will be ahead and top slab work will be
followed. In this schedule, top slab work will be started after 3month from U-type culvert construction.
3) Headrace Channel construction cycle time
1Block is 6m. The period for U-type culvert construction of 1 block is 8days. (4days for basement, 4days
for wall) Top slab construction period for 1 block is 5days.
(5) Head Tank
1) Temporary work and excavation work
The excavation work of Head Tank will be carried out immediately after Project road No, 2completed. It
will be started after 1month from commencement of project, it will take 0.8month. The concrete work
for Head Tank will be delayed 3 month for prioritizing Headrace Channel and Penstock excavation work.
2) Concrete work construction period and organization
Concrete work start at 5th month from commencement of project. Construction period is 2.5month.
(m3/s)Q1 35.36Q2 20.20Q3 4.44Q4 60.00
Final Report
Preparatory Survey on North Sumatra Mini 6-12 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(6) Penstock
1) Temporary work and excavation work
For Penstock excavation work, it is required to complete Project road No, 2 and Temporary Access Road
No, 2-1, 2-1, 2-3. Penstock excavation work will start 4months after commencement of project. The
period of Penstock excavation is 6.0months.
2) Concrete work construction period and organization
Masonry work will start before concrete work, after 2 months from commencement of excavation work.
Masonry work will follow the section which the excavation work is completed. Construction period of
Masonry work is 5.5 months. Concrete work will start after 5 months from commencement of
excavation work. Construction period is 9.0 months.
3) Penstock construction cycle time
For Anchor block basement, 1st lift is 8 days, 2nd and 3rd lift is 6 days. Secondary concrete, after pipe
install, 1st, 2nd and 3rd lift id 6 days. For saddle support basement, 1st lift is 6days. 2nd lift is 4days.
Secondary concrete, after pipe install, is 3days.
(7) Powerhouse
1) Temporary work and excavation work
Temporary Access Road No, 2-3 will be used as access road to powerhouse at early stage. This temporary
access will be mainly used for hauling the excavated material from Penstock. After completing Poring2
Headrace channel excavation, access road along Poring2 Headrace channel will be an access road to
Powerhouse. Excavation work for powerhouse will be started after completion of Penstock excavation
and certain progress of Penstock pipe installation. (14.8months form commencement of project)
The period of excavation is 1.3months. The excavation equipment is Backhoe 1no, Bulldozer 1no, and
11tDump Truck 4nos.
2) Concrete work construction period and organization
Concrete work for Powerhouse will be started after completion of Intake concrete work. Concrete work
period is 2.0month in 1st stage, and 0.5month in 2nd stage (Secondary concrete).
3) Building work and M & E work
Following concrete work, 1.5month is scheduled for Building work including roof work and M&E work.
Then, after installation of Turbine and Generator, 1month is scheduled for Building finishing work.
4) Turbine and Generator
- Draft tube:Installation of Draft tube no1 will be started 19.5month after the commencement of
Pring1 project. Draft tube no2 will be started 0.5month after Draft tube No1.
- Turbine and Generator:Installation of Turbine No1 will be started 20.5month after the
commencement of Pring1 project. Turbine no2 will be started 0.5month after Turbine No1.
Final Report
Preparatory Survey on North Sumatra Mini 6-13 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Installation of Generator No1 will be started 20.8month after the commencement of Pring1
project. Generator no2 will be started 0.5month after Generator No1.
- Main transformer : Installation of main transformer will be started 20month after the
commencement of Pring1 project.
- Support and control equipment:Installation of support equipment for Turbine will be done
following Turbine installation. Support and control equipment of Generator will be started after
the completion of installation for Generator No1 & No2. There will be various sensitive works,
such setting up the cable, adjustment of equipment, detail cabling works, etc.
- Dry and wet test:Dry test is scheduled 23month after the commencement of Pring1 project and
the test period will be 0.5month. After dry test, Wet test will be carried out continuously. It will
also take 0.5month. Commercial operation will be started after the completion of Wet test
including full load test.
6.1.7 PORING-2 MAIN CONSTRUCTION WORKS
The commencement of Poring-2 project will be 8months after the commencement of Poring-1.
(1) Project road
1) Project road No, 3
Project road No, 3 is an access road from Siantar Nai-pospos Village to the middle point of Headrace
channel. During construction period, it will be used as access to Headrace channel construction. After
construction is completed, it will be permanent access road to Powerhouse No1 and Headrace channel
upstream. The construction of Project road No, 3 will be started immediately after commencement of
Poring-2 project, the construction period is planned as 1month.
2) Project road No, 4
Project road No, 4 is an access road from public access road to Powerhouse. During construction period,
it will be used as access to Penstock and Powerhouse for excavation and concrete works. After
construction is completed, it will be permanent access road to Powerhouse. The construction of Project
road No, 4 will be started immediately after commencement of Poring-2 project, the construction period
is planned as 4.5 months.
(2) Temporary Access Road for construction
1) Temporary Access Road 3-1, 3-2
This is temporary access road from Project road No, 4 to 2 point of Penstock. During construction period,
it will be used as access road for excavation work and concrete work of Penstock. The construction of
Temporary Access Road No, 3-1, 3-2 will be started 1month after commencement of Project road No, 4,
the construction period is planned as 2.0months.
Final Report
Preparatory Survey on North Sumatra Mini 6-14 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(3) Headrace Channel
1) Temporary work and excavation work
For stating the excavation work of Headrace Channel, it is required to complete the construction of
Project road No, 3. The excavation of Headrace channel will be started 1month after the commencement
of Project road No, 3. Temporary Access Road No, 2-3 is necessary for starting excavation. The period of
Headrace Channel excavation is 7.5months.
2) Concrete work construction period and organization
Concrete work will be started after 7months from the commencement of excavation. Total working period
of concrete work is 14.5months. Only top slab concrete work is expected in last 1.5 months. For the
construction of Box type culvert, the construction of U-Type will be ahead and top slab work will be
followed. In this schedule, top slab work will be started after 3month from U-type culvert construction.
3) Headrace Channel construction cycle time
1Block is 6m. The period for U-type culvert construction of 1 block is 8days. (4days for basement, 4days
for wall) Top slab construction period for 1 block is 5days.
(4) Head Tank
1) Temporary work and excavation work
The excavation work of Head Tank will be carried out 2.5month after starting excavation of Headrace
channel from Public access road. The period of excavation will be 0.5month. The concrete work for
Head Tank will be delayed 3 month for prioritizing Headrace Channel and Penstock excavation work.
2) Concrete work construction period and organization
Concrete work start at 6th month from commencement of Poring2 project. Construction period is
2.5month.
(5) Penstock
1) Temporary work and excavation work
For Penstock excavation work, it is required to complete Project road No, 4 and Temporary Access Road
No, 3-1, 3-2. Penstock excavation work will start 3months after commencement of Poring2 project.
The period of Penstock excavation is 8.0months.
2) Concrete work construction period and organization
Masonry work will start before concrete work, after 3 months from commencement of excavation work.
Masonry work will follow the section which the excavation work is completed. Construction period of
Masonry work is 7.0 months. Concrete work will start after 6 months from commencement of excavation
work. Construction period is 13 months.
Final Report
Preparatory Survey on North Sumatra Mini 6-15 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
3) Penstock construction cycle time
For Anchor block basement, 1st lift is 8 days, 2nd and 3rd lift is 6 days. Secondary concrete, after pipe
install, 1st, 2nd and 3rd lift id 6 days. For saddle support basement, 1st lift is 6days. 2nd lift is 4days.
Secondary concrete, after pipe install, is 3days.
(6) Powerhouse
1) Temporary work and excavation work
Project road No, 4 will be used as access road to powerhouse. Excavation work for powerhouse will be
started after completion of Penstock excavation and certain progress of Penstock pipe installation.
(16month form commencement of Poring2 project) The period of excavation is 2.0months.
2) Concrete work construction period and organization
Concrete work period is 2.0month in 1st stage, and 0.5month in 2nd stage (Secondary concrete).
3) Building work and M & E work
Following concrete work, 1.5month is scheduled for Building work including roof work and M&E work.
Then, after installation of Turbine and Generator, 1month is scheduled for Building finishing work.
4) Turbine and Generator
- Draft tube:Installation of Draft tube no1 will be started 21.5month after the commencement of
Pring2 project. Draft tube no2 will be started 0.5month after Draft tube No1.
- Turbine and Generator:Installation of Turbine No1 will be started 22.5month after the
commencement of Pring2 project. Turbine no2 will be started 0.5month after Turbine No1.
Installation of Generator No1 will be started 22.8month after the commencement of Pring2
project. Generator no2 will be started 0.5month after Generator No1.
- Main transformer:Installation of main transformer will be started 22.0 month after the
commencement of Pring2 project.
- Support and control equipment:Installation of support equipment for Turbine will be done
following Turbine installation. Support and control equipment of Generator will be started after
the completion of installation for Generator No1 & No2. There will be various sensitive works,
such setting up the cable, adjustment of equipment, detail cabling works, etc.
- Dry and wet test:Dry test is scheduled 24month after the commencement of Pring2 project and
the test period will be 0.5month. After dry test, Wet test will be carried out continuously. It will
also take 0.5month. Commercial operation will be started after the completion of Wet test
including full load test.
Final Report
Preparatory Survey on North Sumatra Mini 6-16 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(Blank Page)
Final Report
Preparatory Survey on North Sumatra Mini 7-1 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
CHAPTER 7 NATURAL AND SOCIAL ENVIRONMENTAL CONSIDERATION
7.1 PROJECT COMPONENTS WITH POTENTIAL IMPACTS ON THE ENVIRONMENT
The project comprises of two main components, i.e., Construction of the Poring-1 and Poring-2 Mini
Hydropower Plants (Component 1: Hydropower Plants) and Construction of the Poring-1 and Poring-2
Transmission Line (Component 2: Transmission Lines).
The facilities in Component 1: Hydropower Plants and Component 2: Transmission Lines are shown in
Table 7.1.1.
Table 7.1.1 Project Component Component 1: Hydropower Plants Facilities Area (ha)Poring-1 Intake Weir 0.55
Access Road (Existing road to intake weir including improvement of existing road and new road)
3.18
Access Road (Head tank to existing road) 0.59Headrace Channel and Project Road along Headrace Channel 5.26Head Tank 0.2Penstock 1.07Powerhouse 0.3Spoil Bank 1 2.16Spoil Bank 2 0.53Spoil Bank 3 1.10Spoil Bank 4 0.53Spoil Bank 5 0.18Spoil Bank 6 0.98Contractor’s Facility 3.5Subtotal 20.13
Poring-2 Access Road (Existing road to headrace channel) 0.2Access Road (Existing road to powerhouse) 3Headrace Channel 5.37Head Tank 0.12Penstock 2.53Powerhouse 0.3Spoil Bank 7 0.95Spoil Bank 8 0.51Spoil Bank 9 0.15Spoil Bank 10 0.56Spoil Bank 11 0.19Spoil Bank 12 3.81Spoil Bank 13 0.37Spoil Bank 14 0.92Spoil Bank 15 1.1Subtotal 20.08
Total 40.21
Final Report
Preparatory Survey on North Sumatra Mini 7-2 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Component 2: Transmission Lines Facilities Area (ha) Poring-1 33.8 km transmission line from powerhouse to
Tarutung Substation 0.149
(1 m² x 1,487 including poles and guy wire)Poring-2 36.7 km transmission line from powerhouse to
Tarutung Substation 0.162
(1 m² x 1,615 including poles and guy wire)Substation for Poring-1 and Poring-2 0.073
(13 m x 56 m)Total 0.384Source: JICA Survey Team
7.2 PRESENT CONDITIONS IN THE PROJECT AREA
7.2.1 NATURAL ENVIRONMENT
(1) Temperature
The project is located in the North Sumatra area, which has a tropical climate. The warm water
surrounding the island sets a fairly constant temperature with little seasonal variation. The average
maximum temperature ranges from 24°C to 26°C and the average minimum temperature ranges from
15°C to 16°C. There is no drastic seasonal difference; however, the rainy reason starts from May to July
and restarts from November to January. The dry season starts from February to April and restarts from
August to October. Maximum and minimum temperatures in North Sumatra between 2010 and 2014 are
shown in Figure 7.2.1 and Table 7.2.1.
Source: Meteorology, Climatology and Geophysics Agency (BMKG)
Figure 7.2.1 Maximum and Minimum Temperatures in North Sumatra
15.0
17.0
19.0
21.0
23.0
25.0
27.0
29.0
1 2 3 4 5 6 7 8 9 10 11 12
20102011201220132014Ave Max20102011201220132014Ave Min
℃ Month
Final Report
Preparatory Survey on North Sumatra Mini 7-3 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.1 Maximum and Minimum Temperatures in North Sumatra Year JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
2010 24.9 25.7 25.5 25.4 26.3 25.4 25.1 25.5 25.4 25.1 24.2 24.9
2011 26.0 26.3 26.4 26.4 26.6 26.1 25.7 25.7 25.6 25.5 25.4 25.6
2012 25.2 24.9 25.2 25.0 25.8 25.1 24.9 24.3 24.4 24.0 23.9 22.8
2013 25.6 24.4 24.9 24.8 25.0 25.3 24.9 25.1 25.4 24.6 24.6 24.0
2014 26.0 26.3 26.2 28.6 26.6 26.0 25.7 25.6 25.5 25.4 25.3 25.4
Ave. Max 25.5 25.5 25.6 26.0 26.1 25.6 25.3 25.2 25.3 24.9 24.7 24.5
2010 17.5 17.3 17.5 17.1 17.3 17.6 16.8 16.1 17.2 16.2 17.8 17.0
2011 15.3 15.5 15.6 15.5 15.6 15.4 15.2 15.1 15.6 15.6 15.6 15.2
2012 16.6 17.2 16.6 17.0 16.3 17.2 16.5 16.8 16.7 15.5 15.5 15.2
2013 17.0 17.2 15.7 15.6 16.4 16.5 16.2 16.8 16.8 17.4 17.6 15.2
2014 15.4 15.6 15.7 15.6 15.6 15.5 15.3 15.1 15.7 15.5 15.5 15.2
Ave. Min 16.4 16.6 16.2 16.2 16.2 16.4 16.0 16.0 16.4 16.0 16.4 15.6 Source: Meteorology, Climatology and Geophysics Agency (BMKG)
(2) Protected Area
In Indonesia, there are 50 national parks of which 11 national parks are located in Sumatra Island. There
are two national parks, i.e., Gunung Leuser (about 270 km north from the project area) and Batan Gadis
(about 135 km south from the project area), in the North Sumatra Province; however, they are located far
from the project area. It was confirmed that there is no protected area around and in the project area.
The location of the two national parks and the project area is shown in Figure 7.2.2.
Source: JICA Survey Team
Figure 7.2.2 National Park in Sumatra Island
(3) Fauna and Flora
The result of the field survey and hearing with local authorities and villagers on fauna and flora in the
project area is shown in Chapter 7.6.2.
Project Location
Final Report
Preparatory Survey on North Sumatra Mini 7-4 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(4) Land Usage
Most of the project area is located in the area categorized as production forest whose main function is to
yield forest produces. The proposed locations for constructing the facilities of the mini hydropower plants
of Poring-1 and Poring-2 are currently used for tree plantation such as rubber tree. There is no residential
area affected by the project. The proposed locations for constructing the transmission lines for the
Poring-1 Mini Hydropower Plant and Poring-2 Mini Hydropower Plant are partly in the production forest
area used for plantation such as rubber trees and the rest of the land is used as agricultural land. There is
no residential area affected by the construction of transmission lines. Land usage map around the project
area is shown in Figure 7.2.3.
Source: Forest Usage Map, Ministry of Forestry, 2014
Figure 7.2.3 Land Usage
Sumatra Island
Project Area
: Project Area
: Protected Forest
: Limited Production Forest
: Permanent Production Forest
Final Report
Preparatory Survey on North Sumatra Mini 7-5 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
7.2.2 SOCIAL ENVIRONMENT
(1) Population, Demography and Religion
There are two villages in Component 1. In these villages, all residents belong to the Toba Batak ethnic
group and speak Batak as their mother tongue. Most of the villagers are Christians with few Muslims.
There are 11 villages in Component 2. In these villages, the Toba Batak ethnic group is dominant ranging
from 80% in Siraja Hutagalung Village to 100% in the villages of Siantar Naipospos, Pardomuan Nauli,
Pansurbatu 1, Pansurbatu 2, and Hatatoruan 1. As minor ethnic groups, Nias, Jawa, Minan, Patang,
Madailing, and Aceh were identified. The Toba Batak is a dominant subgroup of the Batak ethnic group.
The Batak ethnic group is the third biggest ethnic group in Indonesia with about 8.4 million people spread
all over Indonesia. In North Sumatra Province, the Toba Batak is the major ethnic group.
Batak is the major language in all surveyed villages. Indonesian is fairly popular in Simonagkir Julu
Village (40%) which is the closest to Tarutung Substation and in the villages of Parbubu 1 (35%) and
Siraja Hutagalung (35%) which are located next to Simonagkir Julu Village. Otherwise, all surveyed
villages speak Batak. Christianity is dominant in all surveyed villages ranging from 82% to 100%.
Population, ethnicity, language, and religion in all surveyed villages are shown in Table 7.2.2.
Table 7.2.2 Population, Ethnicity, Language, and Religion Component 1: Hydropower Plants Village Population
(Female) Households Ethnicity Language Religion
Siantar Naipospos 1,083 (500) 217 Toba Batak (100%) Batak (100%) Christian (98.6%) Muslim (1.4%)
Pardomuan Nauli 732 (400) 154 Toba Batak (100%) Batak (100%) Christian (100%) Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Village Population Households Ethnicity Language Religion Siantar Naipospos 1,083 (495) 217 Toba Batak (100%) Batak (100%) Christian (98.6%)
Muslim (1.4%) Pardomuan Nauli 732 (385) 154 Toba Batak (100%) Batak (100%) Christian (100%) Pansurbatu 953 (420) 168 Toba Batak (99%)
Nias, Mandailing (angkola) (1%) Batak (99%) Indonesia (1%)
Christian (100%)
Pansurbatu 2 320 (120) 60 Toba Batak (100%) Batak (99%) Indonesia (1%)
Christian (100%)
Hutatoruan VIII (Aek Nasia)
485 (260) 114 Toba Batak (99%) Nias, Simalungun (1%)
Batak (99%) Indonesia (1%)
Christian (100%)
Aek Sian Simun 1,324 (675) 309 Toba Batak (99%) Nias, Simalungun (1%)
Batak (99%) Indonesia (1%)
Christian (99.9%) Muslim (0,1%)
Hutatoruan III* 520 (220) 75 Toba Batak (99%) Jawa (1%)
Batak (85%) Indonesia (15%)
Christian (99.9%) Muslim (0.1%)
Parbubu I 1,200 (750) 286 Toba Batak (95%) Nias, Jawa (5%)
Batak (65%) Indonesia (35%)
Christian (99,9%) Muslim (0.1%)
Hutatoruan I 1,771 (897) 434 Toba Batak (100%) Batak (95%) Indonesia (5%)
Christian (99%) Muslim (1%)
Siraja Hutagalung 2,265 (1,245) 617 Toba Batak (80%) Nias, Minang, Jawa (20%)
Batak (65%) Indonesia (35%)
Christian (82%) Muslim (18%)
Simorangkir Julu 1,133 (603) 279 Toba Batak (85%) Nias, Padang, Aceh, Jawa, Mandailing (15%)
Batak (60%) Indonesia (40%)
Christian (99%) Muslim (1%)
Source: Hearing with Acting Village Heads in July 2015
Final Report
Preparatory Survey on North Sumatra Mini 7-6 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(2) Economic Status
1) Income
Income in the two surveyed villages of Component 1 is very low. It is considered that villagers in these
two villages live in self-sufficiency. In other words, income is mainly or only generated from plantation.
Other necessities such as food and fire wood are grown in their land and purveyed by themselves without
cash. The average income of the affected households (AHHs) is relatively higher than that of the two
villages. However, it is still under the average income per capita per year of North Sumatra Province.
Most of the main income is generated from plantation of AHHs.
Average income per capita per year in the surveyed villages of Component 2 ranges from Rp2,019,672 to
Rp6,000,000. All villages are below the average income in North Sumatra Province. There is a tendency
that the closer the village to the center of Tarutung City, the higher the income. Main income in the
villages of Component 2 is generated from agricultural sector ranging from 70% in Sijara Hutagalung
Village to 93% in Siantar Naipospos Village and Pardomuan Nauli Village. Income from plantation is
dominant in the villages located in the mountainous area. On the other hand, the ratio of income from
lowland rice cultivation is high among the villages located in the flat land including the villages of
Hutatoruan III, Parbubu 1, Hutatoruan 1, Siaraja Hutagalung, and Simorangkir Julu. Income in the project
area is shown in Table 7.2.3. Main income source in the project area is shown in Table 7.2.4.
Table 7.2.3 Income Component 1: Hydropower Plants
Village Average Income per Capita per
Year (Rp) Average per Poorest Income
per Year (Rp) Average per Wealthiest Income per Year (Rp)
North Sumatra Province 38,050,000* 3,749,916* N/ASiantar Naipospos 2,404,432 1,200,000 19,200,000Pardomuan Nauli 2,019,672 960,000 9,600,000Affected Households (AHHs)1 5,234,575 1,200,000 19,600,000Source:*Central Bureau of Statistics in North Sumatra Province, 2014, Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Village Average Income per Capita
per Year (Rp) Average per Poorest Income
per Year (Rp) Average per Wealthiest Income per Year (Rp)
Siantar Naipospos 2,404,432 1,200,000 19,200,000Pardomuan Nauli 2,019,672 960,000 9,600,000Pansurbatu 2,115,424 1,500,000 9,000,000Pansurbatu 2 2,250,000 2,100,000 9,000,000Hutatoruan VIII (Aek Nasia) 3,384,742 2,400,000 9,000,000Aek Sian Simun 3,080,664 2,100,000 15,000,000Hutatoruan III* 2,596,153 1,500,000 12,000,000Parbubu I 4,290,000 2,400,000 39,000,000Hutatoruan I 6,000,000 1,800,000 30,000,000Siraja Hutagalung 4,903,311 2,400,000 45,000,000Simorangkir Julu 5,023,477 3,000,000 24,000,000AHHs2 N/A N/A N/A Source: Central Bureau of Statistics in North Sumatra Province, 2014, Hearing with Acting Village Heads in July 2015
1 As for Component 1, 43 households were identified as affected households in which 32 households were interviewed. The remaining 11 households could not be reached as they are living outside the project area, which is under land dispute 2 As for Component 2, 431 households were identified within the area of 3 m width x proposed transmission line length (about 32 km). Among the 431 households, 175 households were interviewed. The remaining 256 could not be reached mainly as they are living outside the project area
Final Report
Preparatory Survey on North Sumatra Mini 7-7 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.4 Main Income Source Component 1: Hydropower Plants (%)
Vil
lage
Agriculture
Smal
l-sc
ale
Tra
ding
(S
hops
, Sta
lls)
Tra
nspo
rtat
ion
(Mot
orcy
cle,
Tax
i)
Gov
ernm
ent S
ervi
ce
Fac
tory
Wor
k
Lab
orin
g
Oth
ers
Tota
l
Low
land
Ric
e C
ulti
vati
on
Upl
and
Ric
e C
ulti
vati
on
Low
land
Veg
etab
le
Cul
tiva
tion
Upl
and
Veg
etab
le
Cul
tiva
tion
Pla
ntat
ion
SN 93 2 0 0 5 86 2 2 0.5 0 0 2.3PN 93 2 0 0 20 71 2 2 0.5 0 0 2.5AHHs 87.5 0 0 0 0 87.5 6.25 0 0 0 0 6.25SN: Siantar Nipospos Village, PN: Pardomuan Nauli Village Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines (%)
Vil
lage
Agriculture
Smal
l-sc
ale
Tra
ding
(S
hops
, Sta
lls)
Tra
nspo
rtat
ion
(Mot
orcy
cle,
Tax
i)
Gov
ernm
ent S
ervi
ce
Fac
tory
Wor
k
Lab
orin
g
Han
dicr
aft3
Oth
ers
Tota
l
Low
land
Ric
e C
ulti
vati
on
Upl
and
Ric
e C
ulti
vati
on
Low
land
Veg
etab
leC
ulti
vati
on
Upl
and
Veg
etab
le
Cul
tiva
tion
Pla
ntat
ion
SN 93 2 0 0 5 86 2 2 0.5 0 0 0 2.3PN 93 2 0 0 20 71 2 2 0.5 0 0 0 2.5PB 84 38 0 0 10 36 3 1 5 0 4 2 1PB1 92 40 0 1 3 48 5 1 1 0 0 1 0PB2 90 40 0 2 3 45 1 1 3 0 0 5 0HT VIII 72.5 27.5 0 2 3 40 1 0.5 1 0 0 25 0ASS 85 42 0 5 0 38 2 1 5 0 0 7 0HTIII 80 60 0 2 3 15 4.5 0.5 10 0 0 5 0PRB I 70 55 0 0 3 12 2 3 10 0 0 15 0HT I 75 62 0 3 0 10 5 5 13 0 0 0 2SHG 72 65 0 0 2 5 5 1 20 0 0 5 0SMJ 80 60 0 0 3 17 1.5 1 2.5 0 0 5 0AHHs* - - - - - - - - - - - - - SN: Siantar Nipospos Village, PN: Pardomuan Nauli Village, PB:Pansurbatu Village, PB1:Pansurbatu 1 Village, PB2:Pansurbatu 2 Village, HT VIII: Hutatoruan VIII (Aek Nasia) Village, ASS: Aek Sia Simun Village, HT III: Hutatoruan III, PRB I: Parbubu I Village, HT I: Hutatoruan I Village, SHG: Siraja Hutagalung Village, SMJ: Simorangkir Julu Village Source: Hearing with Acting Village Heads in July 2015
2) Vulnerable
The minimum wage of North Sumatra Province in 2015 is set at Rp1,653,000 per month or
Rp198,360,000 per year. In Component 1, about half of the affected households in Siantar Naipospos
Village and most of the affected households in Pardomuan Nauli Village have fallen into the category of
vulnerable. As mentioned in the section on income, unlike city dwellers, villagers in the project area are
self-sufficient in food which does not require much money. Accordingly, justification of vulnerability in
each affected household needs to take not only income but also assets into account.
In Component 2, large numbers of affected households are under the category of vulnerable households
ranging from 33% to 92%. The number of vulnerable is small near Tarutung City.
3Some women make a traditional shawl; local name is ulos. They weave it in their home using a traditional technique.
Final Report
Preparatory Survey on North Sumatra Mini 7-8 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The number of vulnerable among the affected households is shown in Table 7.2.5.
Table 7.2.5 Vulnerable Households in Total Affected Households Component 1: Hydropower Plants
Village Vulnerable Households (in Total Interviewed Affected Households) Siantar Naipospos Village 11 (26 or 42%) Pardomuan Nauli Village 5 (6 or 83%)
Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Village Vulnerable Households (in 175 Interviewed Affected Households) Siantar Naipospos 29 (39 or 74%) Pardomuan Nauli 57 (62 or 92%) Pansurbatu 26 (32 or 81%) Pansurbatu 2 - Hutatoruan VIII (Aek Nasia) 10 (10 or 100%) Aek Sian Simun 2 (2 or 100%) Hutatoruan III* 3 (4 or 75%) Parbubu I 2 (2 or 100%) Hutatoruan I 1 (3 or 33%) Siraja Hutagalung 6 (11 or 55%) Simorangkir Julu 5 (10 or 50%) Source: Hearing with Acting Village Heads in July 2015
(3) Agriculture Production
1) Rice Production
In the two surveyed villages of Component 1, rice is planted in wet land and dry land. Rice paddy is fed
with irrigation using spring water or rain. The cropping season for rice paddy is once in a year starting
from October/November to January/February. In between crop season, the rice paddy is used for growing
vegetables. As for upland rice, the cropping season is also once in a year starting from July/August to
November/December. Upland rice is intercropped in the plantation area together with other vegetables.
The rate of irrigated/rainfed rice and upland rice is almost the same in Siantar Naipospos Village. On the
other hand, irrigated/rainfed is largely applied (84%) in Pardomuan Nauli Village.
In the surveyed villages in Component 2, the irrigated/rainfed paddy in total village land ranges from
0.3% in Siantar Naipospos Village to 64.6% in Siraja Hutagalung Village.
Rice production in the surveyed villages is shown in Table 7.2.6.
Final Report
Preparatory Survey on North Sumatra Mini 7-9 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.6 Rice Production Component 1: Hydropower Plants
Village Total Area
(ha) Rice Production Area in
Total Agricultural Land (%)
Rice Production Area
Irrigated/Rainfed Paddy Area (%)
Irrigated/ Rainfed Paddy
Yield (ton/ha/year)
Upland Rice Area (%)
Upland Rice Yield
(ton/ha/year)
Siantar Naipospos
3,968 0.6% (Total Agricultural Land is 23 ha)
0.3 5.6 0.3 3.1
Pardomuan Nauli
4,800 1.94% (Total Agricultural Land is 92 ha)
1.6 5.6 0.3 3.1
Source: Hearing with Acting Village Heads in April 2015
Component 2: Transmission Lines
District Village Total Area (ha)
Rice Production Area in Total Agricultural
Land (%)
Rice Production Area
Irrigated/Rainfed Paddy Area (%)
Irrigated/ Rainfed Paddy
Yield (ton/ha/year)
Upland Rice Area (%)
Upland Rice Yield
(ton/ha/year)
Adian Koting
Siantar Naipospos
3,968 0.6 0.3 (13 ha) 5.6 0.3 (10 ha) 3.1
Pardomuan Nauli
4,800 1.94 1.6 (77 ha) 5.6 0.3 (15 ha) 3.1
Pansurbatu 3,642 N/A 1.9% (139 ha)* *the ratio of irrigated/ rainfed paddy area in three villages, Pansurbatu, Pansurbatu 1, and Pansurbatu 2 (7,283 ha)
5.72** N/A
3.06**
Pansurbatu 2 2,427 N/A N/A
Tarutung Hutatoruan VIII (Aek Nasia)
350 N/A 6.85% (24 ha) 5.65** N/A 3.22**
Aek Sian Simun 456 N/A 5.26% (24 ha) N/A Hutatoruan III 44 N/A 11.36% (5 ha) N/A Parbubu I 475 N/A 15 % (71 ha) N/A Hutatoruan I 200 N/A 26 % (56 ha) N/A
Siatas Barita
Siraja Hutagalung
195 N/A 64.6 % (126 ha) 5.67** N/A 3.22**
Simorangkir Julu
300 N/A 11% (33 ha) N/A
* BPS (Central Bureau of Statistics) Kecamatan Adian Koting Dalam Angka 2014. **Data at District Level in BPS (Central Bureau of Statistics) Kecamatan Adian Koting Dalam Angka 2014. Source: Hearing with Acting Village Heads in July 2015, BPS (Central Bureau of Statistics) Kecamatan Adian Koting Dalam Angka 2014. Source: Hearing with Acting Village Heads in July 2015, BPS (Central Bureau of Statistics) Kecamatan Adian Koting Dalam Angka 2014.
2) Rice Sufficiency
In the two surveyed villages of Component 1, cultivated rice for domestic consumption can last for nine
months to three months. The AHHs can grow rice lasting from six months to nine months (44%) followed
by nine months to 12 months (38%), and for three months to six months (19%). Rice shortage can be
managed by buying at the market as the first choice followed by receiving governmental assistance and
offering labor in exchange of getting rice from other villagers.
In the surveyed villages of Component 2, ratio of rice sufficiency is high among the villages located in
flat land in which lowland rice cultivation is popular. In particular, about 80% of households can grow
rice lasting for nine months to 12 months in the villages of Siraja Hutagalung and Simorangkir Julu.
Similar to Component 1, rice shortage can be managed by buying at the market as the first choice
followed by receiving governmental assistance in the surveyed villages of Component 2.
Final Report
Preparatory Survey on North Sumatra Mini 7-10 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Rice sufficiency in the surveyed villages is shown in Table 7.2.7. Rice shortage management in the
surveyed villages is shown in Table 7.2.8.
Table 7.2.7 Rice Sufficiency Component 1 Hydropower Plants HHs with Rice All
Year (%) HHs with Rice for 9-12 Months (%)
HHs with Rice for 6-9 Months (%)
HHs with Rice for 3-6 Months (%)
Siantar Naipospos Village 0 2 45 53Pardomuan Nauli Village 0 4 60 36AHHs (32 HHs) 0 37.5 43.75 18.75Source: Hearing with Acting Village Heads in April 2015
Component 2 Transmission Lines HHs with Rice All
Year (%) HHs with Rice for 9-12 Months (%)
HHs with Rice for 6-9 Months (%)
HHs with Rice for 3-6 Months (%)
Siantar Naipospos 0 2 45 53Pardomuan Nauli 0 4 60 36Pansurbatu 0 15 75 10Pansurbatu 2 0 10 75 15Hutatoruan VIII (Aek Nasia) 0 3 72 25Aek Sian Simun 1 5 60 34Hutatoruan III 1 50 34 15Parbubu I 1 50 39 10Hutatoruan I 2 - - - Siraja Hutagalung 2 80 13 5
Simorangkir Julu 2 75 18 5AHHs 1.7 13 32 53Source: Hearing with Acting Village Heads in July 2015
Table 7.2.8 Rice Shortage Management (Ranking) Component 1: Hydropower Plants
Buy Trade/
ExchangeCharitable Donation
from Community Governmental/
International Aid Labor for Another
Household Siantar Naipospos Village 1 - - 2 3 Pardomuan Nauli Village 1 - - 2 3 AHHs 1 - - 2 - Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Buy Trade/
ExchangeCharitable Donation
from Community Governmental/
International Aid Labor for Another
Household Siantar Naipospos 1 - - 2 3 Pardomuan Nauli 1 - - 2 3 Pansurbatu 1 - - 2 - Pansurbatu 2 1 - - 2 - Hutatoruan VIII (Aek Nasia) 1 - - 2 - Aek Sian Simun 1 - - 2 - Hutatoruan III 1 - - 2 - Parbubu I 1 - - 2 - Hutatoruan I 1 - - 2 - Siraja Hutagalung 1 - - 2 - Simorangkir Julu 1 - - 2 - AHHs 1 - - 2 - Source: Hearing with Acting Village Heads in July 2015
3) Plantation
In the two surveyed villages of Component 1, except in the residential area, villagers use whole forest
land for commercial tree plantation as well as dry-field farming. Vegetables such as stink-bean, fruits
such as durian, mango, and upland rice are intercropped in the plantation area. Rubber and meranti trees
Final Report
Preparatory Survey on North Sumatra Mini 7-11 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
are the dominant species in Siantar Naipospos Village. On the other hand, rubber and benzoin trees are
the dominant species in Pardomuan Nauli Village.
Type of trees and the area for plantation in the surveyed villages in Component 1 are shown in Table
7.2.9. As for Component 2, there is no data available at the village level.
Table 7.2.9 Type of Trees and Area for Plantation (ha) Component 1: Hydropower Plants
Village Rubber Palm Hairy Fruit
Frankincense /Benzoin
Kyuhutan /Meranti
Others (with intercropping/mix cropping system) Coffee, Cacao, Coconut, Durian, Duku, Rambai,
House Mango, Stink-bean, Kiwi, Jackfruit Siantar Naipospos 200 1 2 2 100-200 100-200 Pardomuan Nauli 200 0.5 0.5 100 50 100-150 Source: Hearing with Acting Village Heads in April 2015
(4) Education
1) Literacy
In the two surveyed villages of Component 1, the villagers use Batak language for communication and
Indonesian language as the second language. The literacy rate (able to read and write at daily life level in
Indonesia) is 60% and the rate of speaking Indonesian is about 80%. Only 10% of the villagers including
AHHs are able to understand official documents written in Indonesian. Although the literacy rate is nearly
100% in most of the surveyed villages of Component 2, the ratio of understanding official document
written in Indonesian remains low at about 10%. As for the AHHs, the ratio of understating official
document written in Indonesian is slightly higher at 28.5%, but it still remains low. Accordingly, it is
necessary to give considerations such as assigning a staff who is bilingual in Indonesian and Batak
language whenever there is an occasion to communicate with the villagers.
Literacy rate of the surveyed villages is shown in Table 7.2.10.
Final Report
Preparatory Survey on North Sumatra Mini 7-12 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.10 Literacy Rate Component 1: Hydropower Plants
Village Literacy (able to read and
write at daily life level) (%)
Reading/Writing Understanding Official Document
Written in Indonesian (%) Speaking (%)
Siantar Naipospos Village 60 10 80 Pardomuan Nauli Village 60 10 80 AHHs 90.6 9.4 87.5 Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Village Literacy (able to read and
write at daily life level) (%)
Reading/Writing Understanding Official Document
Written in Indonesian (%) Speaking (%)
Siantar Naipospos 60 10 80 Pardomuan Nauli 60 10 80 Pansurbatu 95 10 40 Pansurbatu 2 95 5 40 Hutatoruan VIII (Aek Nasia) 95 10 40 Aek Sian Simun 95 10 40 Hutatoruan III 95 10 40 Parbubu I 95 10 40 Hutatoruan I 95 10 50 Siraja Hutagalung 97 12 50 Simorangkir Julu 95 12 50 AHHs N/A 28.5 92 Source: Hearing with Acting Village Heads in July 2015
2) School Enrolment
In the two surveyed villages of Component 1, about 40% of the villagers finished primary school
followed by 20% who finished middle school (junior high school), and about 10% who finished high
school.
In the surveyed villages of Component 2, the average ratio of total villagers who finished primary school,
middle school, and high school is about 76%, ranging from 69% in Hutatoruan I Village to 89% in
Hutatoruan III Village. There is no gap on education level between female and male in all surveyed
villages. In each village, there is at least one established primary school.
Education level in the surveyed villages is shown in Table 7.2.11 and education infrastructure in the
surveyed villages is shown in Table 7.2.12.
Final Report
Preparatory Survey on North Sumatra Mini 7-13 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.11 School Enrolment Component 1: Hydropower Plants
Technical School/ College/
University (Female)
Finished High
School (Female)
Finished Middle School
(Female)
Finished Primary School
(Female)
No Schooling (Female)
No Schooling Yet (0-5
years old)
Total Female
Total Population
Siantar Naipospos Village
30 (18) 3%
120 (55) 11%
230(110)21%
420(200)39%
155(52)14%
128 (60) 12%
495 45.71%
1,083
Pardomuan NauliVillage
20 (10) 3%
70 (45) 10%
135(90)18%
317(150)43%
90(45)12%
100 (45) 14%
385 53%
732
AHHs 0 0 0 1 4 0 5 32Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Technical School/ College/
University (Female)
Finished High
School (Female)
Finished Middle School
(Female)
Finished Primary School
(Female)
No Schooling (Female)
No Schooling Yet (0-5
years old)
Total Female
Total Population
Siantar Naipospos Village
30 (18) 3%
120 (55) 11%
230(110)21%
420(200)39%
155(52)14%
128 (60) 12%
495 45.71%
1,083
Pardomuan NauliVillage
20 (10) 3%
70 (45) 10%
135(90)18%
317(150)43%
90(45)12%
100 (45) 14%
385 53%
732
Pansurbatu 14 (8)
1.47%
200 (125)
20.99%
287(154)
30.11%
342(85)
35.89%
50(23)
5.25%
60 (25)
6.29%
420 44.07%
953
Pansurbatu 2 2 (1)
0.62%
18 (9)
5.62%
55(19)
17.19%
150(53)
46.89%
50(20)
15.62%
45 (18)
14.06%
120 37.5%
320
Hutatoruan VIII (Aek Nasia)
9 (5)
1.85%
50 (28)
10.31%
102(57)
21.03%
220(130)
45.36%
61(20)
12.58%
43 (20)
8.87%
260 53.60
485
Aek Sian Simun
18 (10)
1.36%
220 (120)
16.61%
350(169)
26.43%
502(270)
37.91%
129(60)
9.75%
105 (46)
7.94%
675 50.98%
1,324
Hutatoruan III 15 (7)
2.88%
100 (40)
19.23%
165(95)
31.73%
200(60)
38.47%
30(14)
5.77%
10 (4)
1.92%
220 42.3%
520
Parbubu I 25 (15)
2.08%
201 (140)
16.75%
370(236)
30.83%
294(170)
24.5%
205(129)
17.09%
105 (60)
8.75%
750 62.5%
1,200
Hutatoruan I 124 (77) 7%
363 (187)
20.50%
401(219)
22.64%
452(207)
25.52%
242(120)
13.67%
189 (87)
10.67%
897 50.64%
1,771
Siraja Hutagalung
110 (70)
4.86%
400 (265)
17.66%
793(450)
35.01%
501(300)
22.12%
311(100)
13.73%
150 (60)
6.62%
1,245 54.97%
2,265
Simorangkir Julu
100 (65)
8.82%
210 (120)
18.53%
300(140)
26.48%
350(188)
30.90%
93(35)
8.21%
80 (55)
7.06%
603 53.22%
1,133
Source: Hearing with Acting Village Heads in July 2015
Final Report
Preparatory Survey on North Sumatra Mini 7-14 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.12 Education Infrastructure Component 1: Hydropower Plants
Village Primary School Middle School High School Technical
School/College/University
Vocational
Siantar Naipospos 2 1 0 0 0 Pardomuan Nauli 2 1 0 0 0 Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Village Primary School Middle School High School Technical
School/College/University
Other
Siantar Naipospos 2 1 0 0 0 Pardomuan Nauli 2 1 0 0 0 Pansurbatu 0 1 0 0 0 Pansurbatu 2 0 0 0 0 0 Hutatoruan VIII (Aek Nasia) 1 0 0 0 1 (pre-school)*Aek Sian Simun 2 0 0 0 0 Hutatoruan III 1 0 0 0 0 Parbubu I 2 0 0 0 0 Hutatoruan I 1 1 0 0 1 (pre-school)*Siraja Hutagalung 1 0 0 0 0 Simorangkir Julu 2 0 1 0 1 (pre-school)** Pre-school for children between 4 to 5 years old Source: Hearing with Acting Village Heads in July 2015
(5) Infrastructure
1) Health
There is one branch of health center (poskesdes) in each village of Component 1. In the poskesdes, one
midwife is deployed on a full time basis in each village of Component 1. Once a month, infant and baby
care service is provided at the poskesdes as part of the government program. The closest health center is
located in Kolang District (about 20 km from both villages) and the other in Adian Koting District (about
30 km from both villages). There is a hospital in Tarutung City (about 67 km from both villages) which
can provide advanced medical care; however, villagers prefer to go to the health center in Kolang or
hospital in Sibolga City (67 km from both villages) rather than in Adian Koting or Tarutung because of
better accessibility.
In the surveyed villages of Component 2, there are health facilities such as clinic, health center, or
representative of health center except in the villages of Pansurbatu and Pansurbatu 2. Baby care is
provided in all the surveyed villages except in the villages of Pansurbatu, Pansurbatu 1, and Siraja
Hutagalung.
Distance to health infrastructure from surveyed villages is shown in Table 7.2.13.
Final Report
Preparatory Survey on North Sumatra Mini 7-15 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.13 Health Infrastructure (Distance to Village) Component 1: Hydropower Plants
Village Hospital Clinic Health CenterVillage Nurse/
Doctor
Representative of Health Center (Pos
Kesehatan Desa/Poskesdes)
Baby Care (Pos Yandu/Pos
Pelayanan Tepadu)
Siantar Naipospos
67 km to a hospital in Tarutung 67 km to a hospital to Sibolga
- 32 km to Adian Koting 20 km to Kolang District
In the village (1 km from the project area) In the village (2 km from the project area)
In the village (2 km from the project area)
In the village (2 km from the project area)
Pardomuan Nauli
67 km to a hospital in Tarutung 67 km to a hospital to Sibolga
- 30 km to Adian Koting 21 km to Kolang District
In the village (2 km from the project area)
In the village (100 m from the project area)
In the village (100 m from the project area)
Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Village Hospital Clinic Health Center Village Nurse/ Doctor
Representative of Health Center (Pos
Kesehatan Desa/Poskesdes)
Baby Care (Pos Yandu/Pos
Pelayanan Tepadu)
Siantar Naipospos
67 km - 32 km to Adian Koting 20 km to Kolang District
1 km in Limus 2 km in Lobu Haminjon
In the village In the village
Pardomuan Nauli
67 km - 30 km to Adian Koting 21 km to Kolang District
2 km In the village In the village
Pansurbatu 57 km to Tarutung City
- 31 km to Adian Koting District
- - -
Pansurbatu 2 57.5 km to Tarutung City
- 31 km to Adian Koting District
- - In the village
Hutatoruan VIII (Aek Nasia)
8 km to Tarutung City
In the village (It is called “Poliklinik Desa” or village Polyclinic)
8km to Tarutung District - - In the village
Aek Sian Simun
2.5 km to Tarutung City
- 2 km to Tarutung District - In the village In the village
Hutatoruan III
2.2 km to Tarutung City
- 2 km to Tarutung District - In the village In the village
Parbubu I 3 km to Tarutung City
In the village (Poliklinik )
2 km to Tarutung District - - In the village
Hutatoruan I 3.5 km to Tarutung City
In the village (Poliklinik Desa)
1 km to Tarutung District - - In the village
Siraja Hutagalung
6 km to Tarutung City
- In the village (Puskesmas Pembantu)
- In the village -
Simorangkir Julu
4 km to Tarutung City
- In the village - In the village In the village
Source: Hearing with Acting Village Heads in July 2015
2) Road
The distance from the surveyed villages of Component 1 to the main road to the center of Adian Koting,
which is the administrative district of these villages located in the direction of Tarutung City, is about 41
Final Report
Preparatory Survey on North Sumatra Mini 7-16 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
km. Accessibility to the major road is very bad. In particular, the condition of the road along the 10 km
section between Bagot Nahrmop, a subvillage of Pardomuan Nauli Village, and Aek Nauli Village, where
the road is located along the proposed transmission lines from the villages of Component 1 to Tarutung
City, is unpaved and partly too narrow and steep to pass through even by motorbike. Consequently, it has
been inhabited by vehicles accessing to the villages from the Tarutung area.
In the surveyed villages of Component 2, the distance to the center of the district is far at about 30 km
from the villages of Pansurbatu, Pansurbatu 1, and Pansurbatu 2; however, most of the road is paved and
in good condition. Other villages are relatively close to the center of the district ranging from 0 km from
Simorangkir Julu Village to 8 km from Hutatoruan Village.
Accessibility from the surveyed villages to the main road is shown in Table 7.2.14.
Table 7.2.14 Access from the Village to the Main Road Component 1: Hydropower Plants Village Distance Condition Accessibility Siantar Naipospos 41 km Unpaved All year long Pardomuan Nauli 41 km Unpaved All year long Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines District Village Distance4 Condition Accessibility Adian Koting Siantar Naipospos 41 km Unpaved All year long
Pardomuan Nauli 41 km Unpaved All year long Pansurbatu 31 km - Paved : 26 km
- Unpaved: 5 km All year long
Pansurbatu 2 31 km - Paved : 26 km - Unpaved: 5 km
All year long
Tarutung Hutatoruan VIII (Aek Nasia) 8 km - Paved : 5 km - Unpaved: 3 km
All year long
Aek Sian Simun 2 km Unpaved All year long Hutatoruan III 2 km Unpaved All year long Parbubu I 2 km Unpaved All year long Hutatoruan I 1 km Unpaved All year long
Siatas Barita Siraja Hutagalung 2 km Unpaved All year long Simorangkir Julu 0 km Unpaved All year long
Source: Hearing with Acting Village Heads in July 2015
3) Electrification Rate
There is no grid connection in the two surveyed villages of Component 1. In the villages, electricity is
used mainly for lighting. Major source for lighting is from oil lamp followed by kerosene oil generator.
Cost of oil varies depending on the duration of lighting usage. Some households share the cost of oil
generator with 2 to 15 households depending on the size of the generator.
Except in Siantar Naipospos Village and Pardomuan Nauli Village, all the surveyed villages in
Component 2 are connected to the grid ranging from 96% in Panturubatu 1 Village to 100% for the
remaining eight villages. Electrification rate in the surveyed villages is shown in Table 7.2.15.
4 Distance from each village to respective district office, i.e.: Adian Koting District, Tarutung District, or Siatas Barita District.
Final Report
Preparatory Survey on North Sumatra Mini 7-17 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.15 Electrification Rate Component 1: Hydropower Plants Village Connected to
the Grid (%) Battery (%) Oil Lamp Only
(%) Oil Generator (%)
Waterwheel (%)
Cost of Oil/Month
Siantar Naipospos 0 0 60 39.9 0.1 Rp540,000 (2 liters x Rp9,000)
Pardomuan Nauli 0 0 70 30 0 Rp540,000 (2 liters x Rp9,000)
Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines Village Connected to
the Grid (%) Battery (%) Oil Lamp Only
(%) Oil Generator (%)
Waterwheel (%)
Cost of Oil/Month
Siantar Naipospos 0 0 60 39.9 0.1 Rp540,000 (2 liters x Rp9,000)
Pardomuan Nauli 0 0 70 30 0 Rp540,000 (2 liters x Rp9,000)
Pansurbatu 100 0 0 0 0 0Pansurbatu 2 100 0 0 0 0 0Hutatoruan VIII (Aek Nasia)
100 0 0 0 0 0
Aek Sian Simun 100 0 0 0 0 0Hutatoruan III 100 0 0 0 0 0Parbubu I 100 0 0 0 0 0Hutatoruan I 100 0 0 0 0 0Siraja Hutagalung 100 0 0 0 0 0Simorangkir Julu 100 0 0 0 0 0Source: Hearing with Acting Village Heads in July 2015
4) Water Supply
Major source of water is from spring and few households use rain water in the two surveyed villages of
Component 1. The spring water taken from the mountains is available at the public space or directly
connected to the private compound via plastic hose. In Siantar Naipospos Villlage, there are nine public
water supply spaces including toilet. In Pardomuan Nauli Village, there are also nine public water supply
spaces including toilet. The water is used for cooking, bathing, drinking, and washing on a daily basis.
In 5 out of the 12 surveyed villages of Component 2, the source of water is spring water ranging from
97% in Siantar Naipospos to 100% in the villages of Pansurbatu, Pansurbatu 1, and Pansurbatu 2. On the
other hand, tap water is connected to the rest of the six villages ranging from 60% in Hutatoruan VIII to
100% in the villages of Hutatoruam III and Simorangkir Julu.
Source of water in the surveyed villages is shown in Table 7.2.16. The public water supply space is
shown in Figure 7.2.4.
Final Report
Preparatory Survey on North Sumatra Mini 7-18 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.16 Source of Water Component 1: Hydropower Plants Village Tap Water (%) Well (%) Spring (%) River/Stream (%) Rain (%) Siantar Naipospos 0 0 97 0 3Pardomuan Nauli 0 0 98 0 2Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines Village Tap Water (%) Well (%) Spring (%) River/Stream (%) Rain (%) Siantar Naipospos 0 0 97 0 3Pardomuan Nauli 0 0 98 0 2Pansurbatu 0 0 100 0 0Pansurbatu 2 0 0 100 0 0Hutatoruan VIII (Aek Nasia) 60 0 38 2 0Aek Sian Simun 80 20 0 0 0Hutatoruan III 100 0 0 0 0Parbubu I 70 30 0 0 0Hutatoruan I 90 10 0 0 0Siraja Hutagalung 90 10 0 0 0Simorangkir Julu 100 0 0 0 0Source: Hearing with Acting Village Heads in July 2015
Source: USU
Figure 7.2.4 Public Water Supply Space
5) Source of Cooking Energy
In the two surveyed villages of Component 1, wood is the main source of energy for cooking. Villagers
collect wood from the surrounding area of their plantation to help save cost of buying firewood.
In the surveyed villages of Component 2, wood is the main source of energy for cooking in the
mountainous villages such as Siantar Naipospos, Pardomuan Nauli, Pansurbatu, Pansurbatu 1, and
Pansurbatu 2. On the other hand, gas and electricity are the main sources of energy for cooking in the
villages of Aek Sian Simun, Hutatoruan III, Parububu 1, Hutatoruan I, Siraja Hutagalung, and
Simorangkir Julu.
Sources of energy for cooking in the surveyed villages are shown in Table 7.2.17.
Final Report
Preparatory Survey on North Sumatra Mini 7-19 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.17 Sources of Energy for Cooking Component 1: Hydropower Plants
Village Wood (%)Charcoal
(%) Gas (%)
Electricity (%)
Kerosene Stove (%)
Wood and Kerosene Stove (%)
Wood, Gas and Kerosene Stove (%)
Siantar Naipospos 94.5 0 0 0 4 1 0.5Pardomuan Nauli 94 0 0 0 5 1 0Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Village Wood (%)Charcoal
(%) Gas (%)
Electricity (%)
Kerosene Stove (%)
Wood and Kerosene Stove (%)
Wood, Gas and Kerosene Stove (%)
Siantar Naipospos 94.5 0 0 0 4 1 0.5Pardomuan Nauli 94 0 0 0 5 1 0Pansurbatu 50 0 5 10 25 5 5Pansurbatu 2 50 0 5 10 30 5 0Hutatoruan VIII (Aek Nasia)
35 0 5 10 35 15 0
Aek Sian Simun 0 0 55 40 5 0 0Hutatoruan III 0 0 55 44 1 0 0Parbubu I 0 0 50 30 10 10 0Hutatoruan I 0 0 50 30 20 0 0Siraja Hutagalung 0 0 55 40 5 0 0Simorangkir Julu 0 0 50 45 5 0 0Source: Hearing with Acting Village Heads in July 2015
6) Transportation
In the two surveyed villages of Component 1, motorbike is the main means of transport followed by
bicycle. There is a motorbike rental service between the two villages and Kolang District (20 km from the
two villages). The travel cost of one round trip is Rp100,000. There is no service to the direction of Adian
Koting District (40 km from the two villages) and Tarutung City (67 km from the two villages) due to bad
road condition. The high cost of transportation, far distance to the center of the districts, or bad road
condition confine the mobility of goods and villagers. Moreover, the lack of transport vehicles in the
villages has been an obstacle in transporting agricultural produce from the villages to the big markets
outside of the villages, thus, limiting business opportunities.
In all the surveyed villages of Component 2, motorbike is the main means of transport as well.
Means of transportation in the surveyed villages are shown in Table 7.2.18.
Final Report
Preparatory Survey on North Sumatra Mini 7-20 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.18 Means of Transportation Component 1: Hydropower Plants
Village Mini-Bus Private Car Motorbike Bicycle Siantar Naipospos 0 1 50-65 20Pardomuan Nauli 0 0 40-50 10Source: Hearing with Acting Village Heads in April 2015
Component 2: Transmission Lines
Village Mini-Bus Private Car Motorbike Bicycle Siantar Naipospos 0 1 50-65 20Pardomuan Nauli 0 0 40-50 10Pansurbatu 1 0 90-115 5-8Pansurbatu 2 1 0 40-42 2-3Hutatoruan VIII (Aek Nasia) 1 1 70-82 1-2Aek Sian Simun 2 1 230-245 1-3Hutatoruan III 1 1-2 50-55 1-2Parbubu I 2 1-2 200-210 4-6Hutatoruan I 2 1-3 300-320 1-4Siraja Hutagalung 5 1-5 450-490 1-5Simorangkir Julu 5 1-5 200-220 1-4Source: Hearing with Acting Village Heads in July 2015
(6) Public Health
1) Medical Treatment
In the two surveyed villages of Component 1, 60% of the villagers prefer to be given medical treatment at
home followed by treatment at a branch of health center or at the house of a licensed midwife/nurse in the
villages (40%).
In the surveyed villages of Component 2, the ratio of villagers who prefer to be given medical treatment
at home is quite high ranging from 35% in Siraja Hutagalung Village to 60% in Pardomuan Nauli
Village.
Places for medical treatment in the surveyed villages are shown in Table 7.2.19.
Final Report
Preparatory Survey on North Sumatra Mini 7-21 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.19 Places for Medical Treatment Component 1: Hydropower Plants
Village Treat at Home (%)
Village Health Center (%) Clinic(%)
Hospital(%)
Village Nurses (Bidan/Mantri)/ Representatives of Health Center in
Village (Pos Kesehatan Dosa/Poskesdes) (%)
Traditional Healer
(Datu) (%)
Siantar Naipospos 59 0 0 0 40 1Pardomuan Nauli Village
60 0 0 0 39 1
Source: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Village Treat at Home (%)
Village Health Center (%) Clinic(%)
Hospital(%)
Village Nurses (Bidan/Mantri)/Representatives of
Health Center in Village (Pos Kesehatan Dosa/Poskesdes) (%)
Traditional Healer
(Datu) (%)
Siantar Naipospos 59 0 0 0 40 1Pardomuan Nauli 60 0 0 0 39 1Pansurbatu 50 50 (go to “Puskesmas
Pembantu” in Pansurbatu 1 Village)
0 0 0 0
Pansurbatu 2 55 45 (go to “Puskesmas Pembantu” in Pansurbatu 1 Village)
0 0 0 0
Hutatoruan VIII (Aek Nasia)
45 35 (go to “Puskesmas Pembantu” in Pansurbatu 1 Village)
20 0 0 0
Aek Sian Simun 40 0 0 0 60 0Hutatoruan III 40 0 0 0 60 0Parbubu I 45 0 30 0 25 (go to “Poskesdes” in Aek Sian
Simun Village) 0
Hutatoruan I 50 0 50 0 0 0Siraja Hutagalung 35 35 0 0 30 0Simorangkir Julu 40 30 0 0 30 0Source: Hearing with Acting Village Heads in July 2015
2) Health Issues in the Community
In all the surveyed villages, the dominant health issues in the past 12 months are fever and influenza
followed by cough and gastritis. Number of cases and death within 12 months in the surveyed villages is
shown in Table 7.2.20.
Final Report
Preparatory Survey on North Sumatra Mini 7-22 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.2.20 Number of Cases and Deaths within 12 Months Component 1: Hydropower Plants
Vil
lage
Mal
aria
Den
gue
Dia
rrhe
a
Infa
nt
Mor
tali
ty
HIV
/AID
S
Hea
rt
Att
ack
Lun
g D
isea
ses
Hig
h B
lood
P
ress
ure
Fev
er a
nd
Infl
uenz
a
Rin
gwor
m
Tin
ea
Ver
sico
lor
Scab
ies
Cou
gh
Gas
trit
is
C D C D C D C D C D C D C D C D C D C D C D C D C D C DSN 0 0 0 0 5 0 0 0 0 0 7 0 1 0 1 0 30 0 2 0 1 0 1 0 21 0 20 0PN 0 0 0 0 3 0 1 0 1 0 1 0 3 0 4 0 20 0 2 0 2 0 1 0 25 0 13 0SN:Siantar Naipospos Village, PN:Pardomuan Nauli Village, C:Cases, D:DeathsSource: Hearing with Acting Village Heads in April 2015 Component 2: Transmission Lines
Vil
lage
Mal
aria
Den
gue
Dia
rrhe
a
Infa
nt M
orta
lity
HIV
/AID
S
Hea
rt A
ttac
k
Lun
g D
isea
ses
Hig
h B
lood
P
ress
ure
Fev
er a
nd
Infl
uenz
a
Rin
gwor
m
Tin
ea V
ersi
colo
r
Sca
bies
Cou
gh
Gas
trit
is
Eld
erly
Dis
ease
(a
dis
ease
of
old
age)
Cer
ebro
vasc
ular
A
ccid
ent (
CV
A)
Dia
bete
s
Kid
ney
Dis
ease
s
C D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C DSN 0 0 0 0 5 0 0 0 0 0 7 0 1 0 1 0 30 0 2 0 1 0 1 0 21 0 6 0 0 0 0 0 0 0 0 0PN 0 0 0 0 3 0 1 0 1 0 1 0 3 0 4 0 20 0 2 0 2 0 1 0 25 0 13 0 0 0 0 0 0 0 0 0PB 0 0 0 0 0 0 0 0 0 0 0 0 2 1 0 0 21 0 0 0 0 0 0 0 15 0 0 0 5 3 0 0 0 0 0 0PB2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 15 0 0 0 0 0 0 0 20 0 0 0 0 0 3 3 10 7 0 0HT VIII 0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 0 25 0 0 0 0 0 0 0 10 0 0 0 0 0 0 0 0 0 0 0ASS 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 15 0 0 0 0 0 0 0 12 0 0 0 0 0 0 0 0 0 0 0HT III 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 27 0 0 0 0 0 0 0 22 0 5 0 0 0 0 0 0 0 0 0PRB I 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 30 0 0 0 0 0 0 0 35 0 12 0 0 0 0 0 0 0 0 0HT I 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 20 0 5 0 0 0 0 0 0 0 0 0SHG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 45 0 0 0 0 0 0 0 25 0 22 0 2 0 0 0 0 0 1 1SMJ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 50 0 0 0 0 0 0 0 30 0 30 0 2 0 0 0 0 0 0 0SN:Siantar Nipospos Village, PN: Pardomuan Nauli Village, PB:Pansurbatu Village, PB2:Pansurbatu 2 Village, HT VIII: Hutatoruan VIII (Aek Nasia) Village, ASS: Aek Sian Simun Village, HT III: Hutatoruan III Village, PRB I: Parbubu I Village, HT I: Hutatoruan I Village, SHG: Siraja Hutagalung Village, SMJ: Simorangkir Julu Village, C:Cases, D:Deaths Source: Hearing with Acting Village Heads in July 2015
7.3 LEGAL AND INSTITUTIONAL FRAMEWORK
7.3.1 LEGISLATION ON NATURAL AND SOCIAL ENVIRONMENTAL CONSIDERATIONS
(1) Legislations Regarding Environmental Assessment
The statutory order in Indonesia is summarized in Table 7.3.1.
Final Report
Preparatory Survey on North Sumatra Mini 7-23 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.3.1 Summary of Statutory Order in Indonesia Priority Jurisdiction Category Translation in English
1 National Undang Undang Dasar (UUD) Constitution 2 Undang Undang (UU) Law 3 Peraturan Pemerintah (PP) Government Regulation 4 Peraturan Menteri (PERMEN)
PERMEN LH Ministerial Regulation Environmental Ministerial Regulation
5 Keputusan Menteri (KEPMEN) KEPMEN LH MENHUT-ll
Ministerial Decree Environmental Ministerial Decree Ministry of Forestry Decree
6 Keputusan Kepala Bappedal Decree of Head of Environment Impact Control Board 7 Regional Peraturan Daerah Provincial Government Regulation 8 Keputusan Guberner Decree of Governor - - Surat Edaran Circular Source: JICA Survey Team
Environmental assessment is carried out based on the Environmental Protection and Management Law
(2009) which defines the principle, purpose, and scope of environmental management. The regulation
entitled “Type of Business and Activities that Need to Prepare Environmental Impact Assessment Report
(AMDAL)”, which was enacted in 2012, presents the definitions of the projects that need to conduct
environmental impact assessment (EIA) for preparing an AMDAL and the projects that need to conduct
initial environmental examination (IEE) for preparing the environmental management and monitoring
plan (UKL-UPL). In order to obtain an environmental permit from the environmental authority, the
project owner needs to prepare AMDAL or UKL-UPL depending on the project definition and submit it
to the environmental authority such as the Ministry of Environment or Department of Environment in the
local government based on the scale of the project.
Procedure and format of UKL-UPL are stipulated in the Guideline to Develop Environmental Document
(2012). The list of main legislations regarding the project’s environmental assessment is shown in Table
7.3.2.
Table 7.3.2 Key Legislations Regarding Environmental Impact Assessment
No. Category Title Enacted Year Code
1
Environmental Assessment
Environment Protection and Management Law 2009 UU No.32
2 Law on Environmental Management 2010 Surat Edaran No.B-5362/Dep.l-l/LH
3 Environmental Management Plan and Environmental Monitoring Plan 2010 PERMEN THN No.13
4 Requirement of Consultant for Registration 2010 PERMEN LH No.7
5 Types of Business and Activities That Need to Prepare AMDAL 2012 PERMEN LH No.5
6 Guidelines to Develop Environmental Documents 2012 PERMEN LH No.16
7 Guidelines for Community Involvement 2012 PERMEN LH No.17
8 Environmental Permit 2012 PERMEN LH No.27
9 Regulation on Water Resources Management 2008 PP No.42
10 Environmental Standards on Air Quality 1999 PP No.41
11 Air Pollution Standard Index 1997 KEPMEN LH No.45
12 Environmental Standards on Water Quality 2001 PP No.82
13 Environmental Standards on Noise 1996 PERMEN LH No.48
Final Report
Preparatory Survey on North Sumatra Mini 7-24 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
14 Environmental Standards on Vibration 1996 PERMEN LH No.49
15 Environmental Standards on Odor Level 1996 KEPMEN No.50
16 Natural Environment
Regulation on River 2011 PP No.38
17 Law on Water Resources 2004 UU No.7
18 Law on the Conservation of Natural Biological Resources and Its Ecosystem 1990 UU No.5
19 Conservation of Flora and Fauna 1999 PP No.7
20 Law on Forestry 1999 UU No.41
21 Cultural Heritages
Law on Cultural Heritages 1992 UU No.5
22 Procedures at the Time of Historical/Cultural Discovery during Construction Phase 1993 PP No.10
Source: JICA Survey Team
(2) Environmental Assessment Procedures for the Project
The project is required to obtain an environmental permit, which is one of the required materials to
acquire a construction permit (IMB).
The process to obtain the environmental permit is as follows: According to the Regulation No. 5 (Types
of Business and Activities That Need to Prepare Environmental Impact Assessment Report) (Perman LH
05 Tahun, 2012), the project does not apply to the conditions stipulated in K3.1.C (transmission line
construction of more than 150 kV) or K.3.2.C (dam height of more than 15 m, reservoir size of more than
200 ha, and electricity generation capacity of more than 50 MW). Accordingly, the project is not required
to develop AMDAL but will only prepare UKL-UPL. The prepared UKL-UPL shall be submitted to the
environmental department in North Tapanuli District in order to obtain a recommendation letter. Together
with the recommendation letter, the project owner shall submit UKL-UPL to the District Head in North
Tapanuli District to obtain an environmental permit. The required content of UKL-UPL is stipulated in
Regulation No.16 (Guidelines to Develop Environmental Documents) (2012). It is considered that the
requirement of preparing UKL-UPL is much similar to that of the initial environmental examination
(IEE). The summary of the contents of UKL-UPL is shown in Table 7.3.3.
Table 7.3.3 Contents of UKL-UPL Chapter Required Contents of UKL-UPL A.
1. 2.
Project Owner’s Profile (Project’s) Owner’s name Address, phone number, fax, email
B 1. 2. 3. 4.
Project Plan and Activity Project name Location of the project/activity Scale of the project/activity Outline of the project/activity in each phase (pre-construction/construction/operation)
C. 1. 2. 3. 4.
Environmental Impact Assessment, its Mitigation Plan and Environmental Monitoring Plan Environmental Impact Environmental Mitigation Plan Environmental Monitoring Plan Institutional Arrangement for the Monitoring Plan
D. Necessary Permission to Obtain (in case of PPLH) E. Statement on the Commitment of Carrying Out the UKL-UPL by the Project Owner F. Bibliography of the UKL-UPL G. Appendices
Source: Guideline to Develop Environmental Document, PERMEN LH No.16 2012
Final Report
Preparatory Survey on North Sumatra Mini 7-25 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
The state of environmental procedure and further requirements on environmental permit in each project’s
component are summarized in Table 7.3.4. As for the small hydropower plants and related facilities of
Poring-1 and Poring-2, UKL-UPL have been certified and environmental permit have been obtained since
April 2013. The certified UKL-UPL will expire after three years from the certification date in case of no
commencement of construction activity before the expiry date. As for the transmission lines of Poring-1
and Poring-2, the UKL-UPL shall be developed and environmental permit shall be obtained.
Table 7.3.4 State of Environmental Procedure and Further Requirements Component Present State Further Requirements
UKL-UPL Environmental Permit
Poring-1 Mini Hydropower Plant and its Related Facilities
Certified on 10 April 2013
Issued on 16 April 2013
Poring-1 Mini Hydropower Plant and its Related Facilities
Poring-2 Mini Hydropower Plants and its Related Facilities
Certified on 10 April 2013
Issued on 16 April 2013
Poring-2 Mini Hydropower Plants and its Related Facilities
Transmission Line for Poring-1 Mini Hydropower Plant
Submitted in September and it has been under review
Not obtained Transmission line for Poring-1 Mini Hydropower Plant
Transmission Line for Poring-2 Mini Hydropower Plant
Submitted in September 2015 and it has been under review
Not obtained Transmission line for Poring-2 Mini Hydropower Plant
Source: JICA Study Team
(3) Land Acquisition Procedure
As for the private investment project, the project owner shall obtain location permit (Izim Lokasi) from
North Tapanuli District government. With the permit, the project owner starts acquiring land for the
project. In the case of this project, the project area consists of two types of land, i.e., forest land and
agricultural land. The land acquisition procedure in each land category is as follows:
1) Forest Land
The whole area of Component 1 and a part of Component 2 are located in the production forest under the
management of the Ministry of Forestry. Accordingly, it needs to obtain permission from the Ministry of
Forestry due to conversion of land category from forest land to private land to be used for investment.
Project owner shall make a request for land conversion to the Department of Forestry in North Tapanuli
District government. After endorsement by the Department of Forestry in North Tapanuli District
government, the request will be processed to the Ministry of Forestry with the recommendation letter
issued by the Governor of North Sumatra. Then, the permission is obtained after the Ministry of Forestry
approved the request.
2) Agricultural Land
There is no legal procedure on land acquisition for the case of private investment project. The content of
sales contract, compensation method, and any other land affairs for the affected land shall be developed
based on the agreement between the project owner and affected households.
Final Report
Preparatory Survey on North Sumatra Mini 7-26 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(4) Environmental and Social Considerations by JICA
The project is required to comply with the JICA Guidelines for Environmental and Social Considerations
(the Guidelines). Based on the Guidelines, the project was classified as a Category B project. It is
stipulated that “generally, the proposed projects are site-specific, few if any are irreversible; and in most
cases, normal mitigation measures can be designed more readily”5 . As for Category B project,
environmental and social consideration studies require the IEE level, including mitigation measures to
avoid, minimize, or compensate for adverse impact, monitoring plan, and institutional arrangement. It
also needs to analyze alternatives covering the “without project” situations. Consultations with local
stakeholders on the result of the environmental and social considerations shall be conducted for all
Category A projects and for Category B projects as needed.
7.3.2 INSTITUTIONAL FRAMEWORK
The North Tapanuli District government is the key governmental administrative body in relation to the
project’s environmental and social consideration. The governmental administrative bodies relevant to the
study are shown in Table 7.3.5.
Table 7.3.5 Governmental Administrative Bodies Relevant to the Project Institution Role
Natural Environment Dept. of the North Tapanuli District Government
Reviews the submitted UKL-UPL and issues recommendation letter after approval of the UKL-UPL
Head/Vice Head of the North Tapanuli District Government
Issues environmental permit after receipt of the recommendation letter from the Natural Environmental Office of the North Tapanuli District government
Natural Environment Dept. of the North Sumatra Province Government
Gives advice to the Natural Environment Department of the North Tapanuli District government, as necessary
Dept. of Mining and Energy of the North Tapanuli District Government
Reviews the submitted UKL-UPL and gives comments to the Natural Environment Department of the North Tapanuli District government during review period of the UKL-UPL
Dept. of Integrated Permitted Service of the North Tapanuli District Government
Reviews the submitted UKL-UPL and gives comments to the Natural Environment Department of North Tapanuli District government during review period of the UKL-UPL
Dept. of Land Affairs of the North Tapanuli District Government
Reviews the submitted UKL-UPL and gives comments to the Natural Environment Department of the North Tapanuli District government during review period of the UKL-UPL
Dept. of Forestry of the North Tapanuli District Government
Reviews the application of request for forest conversion and issues recommendation letter (approval letter) to the Governor of North Sumatra Province
Governor of North Sumatra Province
Issues recommendation letter to the Ministry of Forestry for obtaining permission of forest conversion
Ministry of Forestry Reviews the application of forest conversion request and issues permit of the conversion Reviews the application of IPPKH (permit of land development) submitted by the project owner (private investment) and issues the IPPKH
Source: JICA Survey Team
5 2.2 Categorization, JICA Guidelines for Environmental and Social Considerations, 2010
Final Report
Preparatory Survey on North Sumatra Mini 7-27 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
7.4 ALTERNATIVES
(1) Poring-1 Mini Hydropower Plant
Two alternatives were considered for the location of intake weir. For both alternatives, no impact is
anticipated on the upstream cultivation area due to the rise of the water level as a result of constructing
the intake weir. As for the required land area, almost the same area needs to be acquired for the two
alternatives. Even the conditions of the two alternatives are almost the same, Alternative 2 is selected.
Because Alternative 2 contributes in the increase in access to the Poring River through the construction of
access road, which is to be used not only by the construction vehicles but also by the villagers. Opening
the new access road to the Poring River gives an opportunity for creating a new fishing site and
compensates the decrease of fishing opportunity due to diversion of water from the Poring River to the
headrace channel of Poring-1 after constructing the Poring-1 Intake Weir. The comparison table of
alternatives is shown in Table 7.4.1.
Table 7.4.1 Alternatives
Alternatives Impact to Upstream
Cultivation Area Land Acquisition Evaluation
Alternative 1 No impact: no cultivation area to be impacted due to the water level rise
Length of headrace channel: 2.91 km No need to construct access road
Alternative 2 is selected Reason: Although almost the same area needs to be acquired for Alternative 1 and Alternative 2, Alternative 2 contributes in the increase in access for the villagers to the Poring River through the construction of the access road.
Alternative 2 No impact: no cultivation area to be impacted due to the water level rise
Length of headrace channel: 2.5 km About 0.45 km of access road to the intake needs to be constructed
Source: JICA Survey Team
(2) Poring-2 Mini Hydropower Plant
After confirming that the headrace channel of Poring-2 would affect the public graveyard, primary school,
and church, an alternative location for the headrace channel was considered to avoid these public facilities.
Consequently, the headrace channel was moved about 20 m toward the mountain side from the original
plan in order to avoid any effects on these facilities from land acquisition due to the construction of the
headrace channel. The original plan and alternative plan are shown in Figure 7.4.1.
Source: JICA Survey Team
Figure 7.4.1 Original Layout and Alternative Layout for Headrace Channel
Headrace Chanel
Public Road
Public Road (read line) Headrace Chanel (blue line)
Final Report
Preparatory Survey on North Sumatra Mini 7-28 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(3) Transmission Lines of the Poring-1 Mini Hydropower Plant and Poring-2 Mini Hydropower Plant
Two alternative transmission line routes were considered. Alternative 1 was aligned along the existing
public road from the Tarutung Substation to the Poring-1 Mini Hydropower Plant. Alternative 2 was
aligned avoiding existing public road and traverses mainly agricultural land from the Tarutung Substation
up to the point in Aek Nauli Village, where there is no distribution line pole constructed along the road.
The rest of the 14 km line route was aligned along the existing public road from the point in Aek Nauli
Village until the Poring-1 Mini Hydropower Plant. The length of the transmission line of Alternative 1 is
shorter than that of Alternative 2. However, in the case of Alternative 1, there are many structures such as
distribution line poles or shops already constructed along the road and it is difficult not to affect these
structures in many areas. Alternative 2 also affects the agricultural land. However, Alternative 2 was
selected because it will not affect structures; thus, no resettlement will occur.
7.5 SCOPING
Based on the findings from the field reconnaissance, hearings with the authorities concerned as well as
collected information from relevant institutions, the positive/negative impacts resulting from the project
in the construction phase and operation phase were estimated. In the course of the scoping process, the
UKL-UPLs6 of the Component 1 (Mini Hydropower Plants) were reviewed and reflected on the scoping.
The scoping on the Component 1 (Mini Hydropower Plants) and the Component 2 (Transmission Lines)
are shown in Table 7.5.1 and Table 7.5.2, respectively.
Table 7.5.1 Anticipated Impact on Component 1 (Hydropower Plants)
No. Impacts Rating
Brief Description Pre-/Const
ruction Operation
1. Anti-Pollution 1.1 Air Pollution C - Construction: Air pollution such as exhaust fumes from earthmoving equipment as
well as construction vehicle associated with the facilities of hydropower plant construction is anticipated Operation: No activity that will cause air pollution is anticipated.
1.2 Water Pollution B U Construction: Temporary water pollution due to concrete mixing, aggregate collection and excavation is anticipated. In addition, temporary water pollution from contractor’s/employee’s camp/office is anticipated. Operation: Anticipated impact is unknown at this stage after diverting the river water to headrace channels. Water quality analysis needs to be conducted to assess the impact on the water quality.
1.3 Waste B - Construction: Construction waste soil will be generated mainly from the powerhouse construction site. Vegetable debris will be generated at the time of land clearance for the land of powerhouse, headrace channel, intake weir, and access road. Also, waste such as kitchen scraps and human waste will be generated from worker’s camps and construction office. Operation: No activity that will cause waste is anticipated.
1.4 Soil Contamination - - Construction: No soil contamination is predicted. Operation: No soil contamination is predicted.
6 UKL-UPL (environmental management and monitoring plan) for the Poring-1 Mini Hydropower Plant and Poring-2 Mini
Hydropower Plant were already prepared by the project owner (JDG Poring for the Poring-1 Mini Hydropower Plant and JDG
Cianten for the Poring-2 Mini Hydropower Plant) and certified by the North Sumatra District Government in 2013.
Final Report
Preparatory Survey on North Sumatra Mini 7-29 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
No. Impacts Rating
Brief Description Pre-/Const
ruction Operation
1.5 Noise and Vibration
C C Construction: Noise and vibration resulting from construction activities are anticipated. Operation: Noise from the powerhouse will affect residents along the powerhouse area.
1.6 Ground Subsidence
- - Construction/Operation: No activity that will cause ground subsidence is anticipated.
1.7 Offensive Odor - - Construction/Operation: No activity that will cause offensive odor is anticipated. 1.8 Bottom Sediment - - Construction/Operation: No activity that will affect bottom sediment is anticipated.2. Natural Environment 2.1 Protected Area - - Construction/Operation: The project area is not located in a protected area. 2.2 Flora, Fauna, and
Biodiversity U U Construction/Operation: Some impacts on existing habitats will be anticipated due
to changing land use patterns. It is necessary to confirm with relevant administrative body if the habitat of endangered species is located within the project area.
2.3 Hydrological Situation
- U Construction: No activity that will affect hydrological situation is anticipated. Operation: Change in the hydrological situation of the section where the water from the Poring River is diverted to the headrace channel is expected. Maintenance flow for this section shall be estimated.
2.4 Topography and Geographical Features
B - Construction: Topography and geographical features will be affected due to constructing powerhouse, headrace channel, intake weir, and access road Operation: No activity that will affect topography and geographical features is anticipated.
3. Social Environment 3.1 Involuntary
Resettlement B - Construction: No resettlement is needed since the location of all facilities avoided
the residential area. However, due to constructing the facilities and access road, about 40 ha of land will be acquired. Operation: No activity that will cause involuntary resettlement is anticipated.
3.2 Vulnerable (poor households, female- headed households)
U - Construction: Vulnerability on affected people needs to be confirmed in conducting hearings with relevant administrative bodies and affected people. Operation: No activity that will affect the vulnerable group is anticipated.
3.3 Indigenous and Ethnic Minority
C - Construction: Villagers in the project area belong to the Toba Batak ethnic group. Low rate of understanding of Indonesian language by the villagers will affect communication between villagers and project owner/contractor. Operation: No activity that will affect indigenous and ethnic minority is anticipated.
3.4 Local Economy, Employment, and Livelihood
B+ B+ Construction: Positive impact such as creation of local employment is predicted. Operation: Positive impact such as creation of local employment is predicted.
3.5 Land Use and Utilization of Local Resources
C - Construction: Due to the project, 40 ha of land will be converted from plantation/agricultural land. Operation: No activity that will impact on land use or change of local resources is predicted.
3.6 Water Usage or Water Rights of Common
U U Construction/Operation: User of the Poring River among locals in the project area need to be surveyed for estimating the impact from the project.
3.7 Existing Social Infrastructures and Services
A+ - Construction: In order to improve accessibility of construction vehicles to the project area, the main road from Tarutung to the villages will be upgraded. It will help the accessibility of the villagers to Tarutung area. Operation: No activity that will affect existing social infrastructures and services is anticipated.
3.8 Social Institutions and Local Decision-making
- - Construction/Operation: No activity that will affect social institutions and local decision-making is anticipated.
3.9 Misdistribution of Benefit and Damage
- - Construction/Operation: No activity that will cause misdistribution of benefit and damage is anticipated.
3.10 Local Conflict of Interest
- - Construction/Operation: No activity that will cause local conflict of interest is anticipated.
3.11 Cultural Heritage - - Construction/Operation: No cultural heritage is confirmed within the project 3.12 Landscape C - Construction: Construction of the facilities such as powerhouse and intake weir will
change the scenery. Operation: No activity that will affect landscape is anticipated.
3.13 Gender C - Construction: Unfair involvement due to gender bias in the process of land acquisition will cause unfair distribution of compensation.
Final Report
Preparatory Survey on North Sumatra Mini 7-30 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
No. Impacts Rating
Brief Description Pre-/Const
ruction Operation
Operation: No activity that will cause gender issues is anticipated. 3.14 Children’s Rights - - Construction/Operation: No activity that will affect children’s rights is anticipated.3.15 Communicable
Diseases such as HIV/AIDS
C - Construction: Inflow of construction workers from construction worker’s camp to local communities will raise risks of communicable diseases. Operation: No activities raising the risk of communicable diseases in the local communities are anticipated.
3.16 Working Environment (includes work safety)
B - Construction: Inappropriate management of working environment will raise the risk of accident and decease. Operation: No activities raising the risk of working environment is anticipated.
4. Others 4.1 Accidents C - Construction: The effect of construction vehicles to the local community is
anticipated. Operation: No activities that will cause accidents are anticipated.
4.2 Global Warming - B+ Construction: CO2 emission from construction vehicles is not significant. Operation: Since the hydropower plant uses renewable energy, it will contribute to reduce CO2 emission.
Rating: A: Serious impact is anticipated, B: Some impact is anticipated, C: Small impact is anticipated, +Positive impact is anticipated, U: Extent of impact is unknown and examination is needed, Impact may become clear as study progresses, -: No impact is anticipated Source: JICA Survey Team
Table 7.5.2 Anticipated Impact on Component 2 (Transmission Lines)
-No. Impacts Rating
Brief Description of Result Pre-/Const ruction
Operation
1. Anti-Pollution 1.1 Air Pollution C - Construction: Air pollution such as exhaust fumes from earthmoving equipment as
well as construction vehicle associated with the tower construction is anticipated. Operation: No activity that will cause air pollution is anticipated.
1.2 Water Pollution B - Construction: Temporary water pollution due to concrete mixing at substation and excavation for digging hole to bury transmission pole is anticipated. In addition, temporary water pollution from contractor’s/employee’s camp/office is anticipated. Operation: No activity that will cause water pollution is anticipated.
1.3 Waste C - Construction: Soil will be excavated for burying construction pole and installing transformer at substation; however, the soil will be backfilled and no waste soil will be generated. Waste such as kitchen scraps and human waste will be generated from the worker’s camps and construction office. Operation: No activity that will cause waste is anticipated.
1.4 Soil Contamination - C Construction: No soil contamination is predicted. Operation: Inappropriate management of transformer will cause oil leakage. Consequently, it will contaminate the soil.
1.5 Noise and Vibration
C - Construction: Noise and vibration resulting from construction activities are anticipated. The main cause of noise and vibration are generated at the time of digging hole for burying transmission pole. Operation: No activity that will cause noise and vibration.
1.6 Ground Subsidence
- - Construction/Operation: No activity that will cause ground subsidence is anticipated.
1.7 Offensive Odor - - Construction/Operation: No activity that will cause offensive odor is anticipated. 1.8 Bottom Sediment - - Construction/Operation: No activity that will affect bottom sediment is anticipated.2. Natural Environment 2.1 Protected Area - - Construction/Operation: The project area is not located in a protected area. 2.2 Flora, Fauna, and
Biodiversity U - Construction: Mammal survey and bird survey along the transmission line route as
well as hearing with relevant administrative body will be conducted in order to grasp the present condition of the natural environment and assess the impact from the project. Operation: No activity that will cause negative impact on flora, fauna and biodiversity is anticipated.
2.3 Hydrological Situation
- - Construction/Operation: No activity that will cause negative impact on hydrological situation is anticipated.
2.4 Topography and C - Construction: Topography and geographical features will be affected due to the
Final Report
Preparatory Survey on North Sumatra Mini 7-31 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
-No. Impacts Rating
Brief Description of Result Pre-/Const ruction
Operation
Geographical Features
construction of transmission poles. Operation: No activity that will cause negative impact on topography and geographical features is anticipated.
3. Social Environment 3.1 Involuntary
Resettlement B - Construction: No resettlement is needed since the transmission line route avoided
the residential area. However, due to constructing transmission poles and substation, about 0.4 ha of land will be acquired. Operation: No activity that will cause involuntary resettlement is anticipated.
3.2 Vulnerable (poor households, female- headed households)
U - Construction: Vulnerability on affected people needs to be confirmed in conducting hearings with relevant administrative bodies and affected people. Operation: No activity that will affect the vulnerable is anticipated.
3.3 Indigenous and Ethnic Minority
U - Construction: Villagers in the project area belong to the Toba Batak ethnic group. Low rate of understanding of the Indonesian language by the villagers will affect the communication between villagers and the project owner/contractor. Operation: No activity that will affect indigenous and ethnic minority is anticipated.
3.4 Local Economy, Employment, and Livelihood
B+ B+ Construction/Operation: Positive impact such as creation of local employment is predicted.
3.5 Land Use and Utilization of Local Resources
C - Construction: Due to the construction of transmission poles, 0.4 ha of land will be converted from forest/agricultural land. Operation: No activity that will impact on land use or change of local resources is predicted.
3.6 Water Usage or Water Rights of Common
- - Construction/Operation: No activity that will give negative impact on water usage or water rights of commons is predicted.
3.7 Existing Social Infrastructures and Services
A+ - Construction: In order to improve accessibility for construction vehicles to the project area, the main road from Tarutung to the villages will be upgraded. It will help villagers to have access to Tarutung area. Operation: No activity that will affect existing social infrastructures and services is anticipated.
3.8 Social Institutions and Local Decision-making
- - Construction/Operation: No activity that will affect social institutions and local decision-making is anticipated.
3.9 Misdistribution of Benefit and Damage
- - Construction/Operation: No activity that will cause misdistribution of benefit and damage is anticipated.
3.10 Local Conflict of Interest
- - Construction/Operation: No activity that will cause local conflict of interest is anticipated.
3.11 Cultural Heritage - - Construction/Operation: No cultural heritage is confirmed within the project area.3.12 Landscape C - Construction: Construction of distribution poles will change the scenery.
Operation: No activity that will affect landscape is anticipated. 3.13 Gender C - Construction: Fair involvement in the process of land acquisition will be disturbed
due to gender bias, however, judging on the basis of current social status and women’s role, no gender concern is anticipated. Operation: No activity that will cause gender issues is anticipated.
3.14 Children’s Rights - - Construction/Operation: No activity that will affect children’s rights is anticipated.3.15 Communicable
Diseases such as HIV/AIDS
C - Construction: Inflow of construction workers from construction worker’s camp to local communities will raise the risks of communicable diseases. Operation: No activities raising the risk of communicable diseases in the local communities are anticipated.
3.16 Working Environment (includes work safety)
B - Construction: Inappropriate management of working environment will raise the risk of accident and decease. Operation: No activities raising the risk of working environment is anticipated.
4. Others 4.1 Accidents C - Construction: The effect of construction vehicles to the local community is
anticipated. Operation: No activities that will cause accidents are anticipated.
4.2 Global Warming - - Construction/Operation: No activities that will cause accidents is anticipatedRating: A: Serious impact is anticipated, B: Some impact is anticipated, C: Small impact is anticipated, +: Positive impact is anticipated, U: Extent of impact is unknown and examination is needed,impact may become clear as study progresses, -: No impact is anticipated Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 7-32 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
7.6 INITIAL ENVIRONMENTAL EXAMINATION (IEE)
7.6.1 TERMS OF REFERENCE (TOR) OF THE IEE
Based on the scoping, the TOR for the Component 1 and Component 2 is developed as shown in Table
7.6.1.
Table 7.6.1 TOR of the IEE Component 1: Hydropower Plants
No. Impacts Items for Study Methodology
1. Pollution Control 1.1 Air Pollution 1. Confirm the present condition in the
project area 2. Impacts during construction phase
1.Collect existing information from relevant authorities 2.Confirm content, method, period, location, area of construction works and access road for construction vehicles
1.2 Water Pollution 1. Confirm the present condition in the project area 2. Impacts during construction phase 3. Impact after diverting river water to the headrace channels
1.Collect existing information from relevant authorities 2.Confirm content, method, period, location, area of construction works and access road for construction vehicles 3.Conduct water quality analysis in the project area of the Poring River in order to estimate the impact from the diversion of water
1.3 Waste 1. Confirm present condition in the project area 2. Impacts during construction phase
1.Collect existing information from relevant authorities 2.Confirm content, method, period, location, area of construction works and location of construction worker’s camp/office
1.4 Noise and Vibration 1. Confirm present condition in the project area 2. Impact during construction phase
1.Collect existing information from relevant authorities 2. Confirm content, method, period, location, and area of construction works
2. Natural Environment
:2.1 Flora, Fauna, and Biodiversity
1. Collect present condition in the project area 2. Impacts during construction phase
1. Conduct field reconnaissance and hearing with villagers 2. Confirm content, method, period, location, area of construction works and location of construction worker’s camp/office
2.2 Hydrological Situation
1. Collect present condition in the project area and estimate maintenance flow for the Poring-1 and Poring-2 Hydropower Plants 2. Impacts during operation phase
1. Conduct water quality survey and fish survey in the Poring River in order to grasp the present condition at the upstream, intersection of the proposed intake weir and powerhouse, and downstream of the Poring-1 and the Poring-2 Hydropower Plants. Then, estimate the environmental maintenance flow for the Poring-1 and Poring-2 Hydropower Plants. 2.Confirm content, method, period, location, area of construction works and location of construction worker’s camp/office
2.3 Topography and Geological Features
1.Collect present condition in the project area 2.Impact during construction phase
1.Conduct field reconnaissance and hearing with relevant authorities 2.Confirm content, method, period, location, area of construction works and access road for construction vehicles
3. Social Environment
3.1 Involuntary Resettlement
1.Confirm present condition in the project area
1. Hearing with relevant authorities, collect information on similar project, conduct census, loss inventory survey and socioeconomic survey on affected households
3.2 Vulnerable (poor households, female-headed households)
1.Confirm present condition in the project area
1. Hearing with relevant authorities, collect information on similar project, conduct census, loss inventory survey and socioeconomic survey on affected households
Final Report
Preparatory Survey on North Sumatra Mini 7-33 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
3.3 Indigenous and Ethnic Minority
1.Confirm present condition in the project area
1.Hearing with relevant authorities, collect information on similar project, conduct census, loss inventory survey and socioeconomic survey on affected households
3.4 Land Use or Water Rights of Common
1.Confirm present condition in the project area
1.Hearing with relevant authorities and conduct field reconnaissance
3.5 Water Use and Utilization of Local Resources
1.Collect information in the project area 1.Hearing with relevant authorities and local community in the project area
3.6 Landscape 1.Collect information in the project area2.Impacts during construction and operation phases
1.Hearing with relevant authorities and conduct field reconnaissance 2.Confirm location of the proposed facilities
3.7 Gender 1.Confirm present condition in the project area
1.Hearing with relevant authorities, collect information on similar project, conduct census, loss inventory survey and socioeconomic survey on affected households
3.8 Communicable Diseases such as HIV/AIDS
1.Impact during construction phase 1.Confirm location of construction worker’s camps/office
3.9 Working Environment (includes work safety)
1.Confirm legislations on working environment in Indonesia
1.Confirm information on similar project
4. Others 4.1 Accidents 1.Impact during construction phase 1.Confirm access road for construction vehicles and
conditions around the area 4.2 Global Warming 1.Impact during operation phase 1.Calculate the amount of CO2 to be reduced by
constructing the hydropower plant 4.3 Stakeholder
Meeting (SHM) 1.Organize SHM in compliance with the requirement of JICA and the Government of Indonesia
1.Individual meetings and focused group meetings to be organized at the project site during the conduct of census, loss inventory survey and socioeconomic survey 2. SHM at the village/district level to be organized after drafting the IEE report
Component 2: Transmission Lines
No. Impacts Items for Study Methodology
1. Pollution Control 1.1 Air Pollution 1.Confirm present condition in the
project area 2.Impacts during construction phase
1.Collect existing information from relevant authorities 2.Confirm content, method, period, location, area of construction works and access road for construction vehicles
1.2 Water Pollution 1.Confirm present condition in the project area 2.Impacts during construction phase
1.Collect existing information from relevant authorities 2.Confirm content, method, period, location, area of construction works and access road for construction vehicles
1.3 Waste 1.Confirm present condition in the project area 2.Impacts during construction phase
1.Collect existing information from relevant authorities 2.Confirm content, method, period, location, area of construction works and location of construction worker’s camp/office
1.4 Noise and Vibration 1.Confirm present condition in the project area 2.Impact during construction phase
1.Collect existing information from relevant authorities 2.Confirm content, method, period, location, and area of construction works
2. Natural Environment 2.1 Flora, Fauna, and
Biodiversity 1.Collect information on flora, fauna and biodiversity in the project area 2.Confirm present condition in the project area 3.Impacts during construction and operation phases
1.Collect existing information from relevant authorities 2.Conduct plant, mammal and bird survey along the transmission line route 3.Confirm content, method, period, location, area of construction works and access road for construction vehicles
2.2 Topography and Geological Features
1.Collect present condition in the project area 2.Impact during construction phase
1.Conduct field reconnaissance and hearing with relevant authorities 2.Confirm content, method, period, location, area of construction works and access road for construction vehicles
3. Social Environment
Final Report
Preparatory Survey on North Sumatra Mini 7-34 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
3.1 Involuntary Resettlement
1.Confirm present condition in the project area
1.Hearing with relevant authorities, collect information on similar project, conduct census, loss inventory survey and socioeconomic survey on affected households
3.2 Vulnerable (poor households, female-headed households)
1.Confirm present condition in the project area
1.Hearing with relevant authorities, collect information on similar project, conduct census, loss inventory survey and socioeconomic survey on affected households
3.3 Landscape 1.Impact during construction phase 1.Confirm content, method , period, location, and area of construction works
3.4 Gender 1.Confirm present condition in the project area
1.Hearing with relevant authorities, collect information on similar project, conduct census, loss inventory survey and socioeconomic survey on affected households
3.5 Communicable Diseases such as HIV/AIDS
1.Impact during construction phase
1.Confirm location of construction worker’s camps/office
3.6 Working Environment (includes work safety)
1.Confirm legislations on working environment in Indonesia
1.Confirm information on similar project
4. Others 4.1 Accidents 1.Impact during construction 1.Confirm access road for construction vehicles and
conditions around the area 4.2 Stakeholder
Meeting (SHM) 1.Organize SHM in compliance with the requirement of JICA and the Government of Indonesia
1.Individual meetings and focused group meetings to be organized at the project site during conducting census, loss inventory survey, and socioeconomic survey 2. SHM at the village/district level to be organized after drafting IEE report
Source: JICA Survey Team
7.6.2 RESULTS OF THE IEE
The IEE was conducted by examining available data, hearing with stakeholders, carrying out site
reconnaissance, conducting site survey, and laboratory analysis. Overall result is described under (1)
summary of the IEE result. Then, the surveys which were specifically conducted in order to assess the
unknown impact at the time of scoping are described in the following sections in (2) Natural Environment
and (3) Social Environment.
(1) Summary of the IEE Result
According to the result of the IEE, predicted impacts of the Component 1 and Component 2 projects were
mostly the same as those identified by the scoping. Consequently, it is concluded that no significant
negative impact was predicted and the predicted impacts could be avoided or minimized by applying
countermeasures.
As for Component 1, the main negative impacts will be temporary and site-specific pollution such as air
pollution, water pollution, waste generation, and noise and vibration due to construction activities during
the construction phase. In addition, fishes and fishery will be affected due to the diversion of water from
the Poring River to the headrace channels in about 5 km section between the Poring-1 Intake Weir and the
Poring-2 Powerhouse during the operation phase.
Similar to Component 1, the main negative impacts of Component 2 will be temporary and site-specific
pollution such as air pollution, water pollution, waste generation, and noise and vibration due to
construction activities during the construction phase.
Final Report
Preparatory Survey on North Sumatra Mini 7-35 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Efforts were made to avoid any resettlement due to the construction of project facilities for both
Component 1 and Component 2. Consequently, there will be no resettlement resulting from the
construction of the project facilities.
The following is the summary of the result. The comparative table on the scoping result and the IEE result
is shown in Table 7.6.2. Based on the result, materials for appraisal were prepared.
Table 7.6.2 IEE Results Component 1: Hydropower Plants
No Impacts Rating Rating Brief Description PCo/C O PCo/C O
1. Anti-Pollution 1.1 Air Pollution C - C - Construction: Air pollution such as exhaust fumes from earthmoving equipment
as well as construction vehicles associated with the facilities of hydropower plant construction is anticipated. Considering the scale of construction activities, the impact is temporary and site specific, thus not significant. Operation: No activity that will cause air pollution is anticipated.
1.2 Water Pollution B U B - Construction: Temporary water pollution due to concrete mixing, aggregate collection and excavation is anticipated. In addition, temporary water pollution from contractor’s employee’s camp/office is anticipated. Operation: Since there is no direct discharge of wastewater to the section where the water would be decreased due to the diversion of water, negative impact of the diversion on water quality is not significant (see details in the following section (2) Natural Environment).
1.3 Waste B - B - Construction: Construction waste soil will be generated mainly from the powerhouse construction site. Vegetable debris will be generated at the time of land clearance for the land of powerhouse, headrace channel, intake weir, and access road. Also, waste such as kitchen scraps and human waste will be generated from worker’s camps and construction office. Operation: No activity that will cause waste is anticipated.
1.4 Soil Contamination
- - - - Construction: No soil contamination is predicted. Operation: No soil contamination is predicted.
1.5 Noise and Vibration
C C C - Construction: Noise and vibration resulting from construction activities are anticipated. Disturbance from noise and vibration is to be predicted particularly at the construction site of headrace channel near the residential area. Operation: Some noise is predicted near the powerhouse. However, negative impact is not anticipated since it is located far from the residential area.
1.6 Ground Subsidence
- - - - Construction/Operation: No activity that will cause ground subsidence is anticipated.
1.7 Offensive Odor - - - - Construction/Operation: No activity that will cause offensive odor is anticipated.
1.8 Bottom Sediment - - - - Construction/Operation: No activity that will affect bottom sediment is anticipated.
2. Natural Environment 2.1 Protected Area - - - - Construction/Operation: The project area is not located in a protected area. 2.2 Flora, Fauna and
Biodiversity U U C B Construction: No endangered species were confirmed. Some impacts on existing
habitats will be anticipated due to changing land use patterns; however, the impacts are site-specific. Operation: The decrease of water due to diversion of river water from the Poring River to the headrace channels affects the population and sizes of fish species. (see details in the following section (2) Natural Environment).
2.3 Hydrological Situation
- U - B Construction: No activity that will affect hydrological situation is anticipated. Operation: Change in the hydrological situation in the section where the water from the Poring River is diverted to the headrace channel will affect the population and size of fish species.
2.4 Topography and Geographical Features
B - B - Construction: Topography and geographical features will be affected due to the construction of powerhouse, headrace channel, intake weir, and access road. Operation: No activity that will affect topography and geographical features is anticipated.
3. Social Environment 3.1 Involuntary B - B - Construction: No resettlement is needed since the location of all facilities
Final Report
Preparatory Survey on North Sumatra Mini 7-36 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Resettlement avoided the residential area. However, due to construction of the facilities and access road, about 40 ha of land will be acquired. Operation: No activity that will cause involuntary resettlement is anticipated.
3.2 Vulnerable (poor households, female-headed households)
U - B - Construction: Land acquisition for the construction of project facilities will decrease the income generated from the land. Operation: No activity that will affect the vulnerable is anticipated.
3.3 Indigenous and Ethnic Minority
C - C - Construction: The Toba Batak is a major ethnic group and Batak is their native language in the project area. Although the literacy ratio is high ranging from 60% to 97%, the ratio of understanding the official document in Indonesian remains low at around 30%. Consideration shall be given for communication. Operation: No activity that will affect indigenous and ethnic minority is anticipated.
3.4 Local Economy, Employment, Livelihood
B+ - B+ A+ Construction: Positive impact such as creation of local employment is predicted.Operation: No activity that will affect local economy, employment and livelihood is anticipated. Upgraded road which has been constructed during the construction phase for accessing the construction site will enhance the vital mobilization of people and goods and contribute to the economic development in the project area.
3.5 Land Use and Utilization of Local Resources
C - C C Construction: Due to the project, 40 ha of land will be converted from plantation/agricultural land. Operation: Due to the diversion of water from the Poring River to the headrace channels, the fish in the diversion section will decrease in number and size which will affect the villager’s fishing opportunities.
3.6 Water Usage or Water Rights of Common
U U C C Construction: There is no building infrastructure such as irrigation or water supply in the section where the water is to be diverted to the headrace channel from the Poring River. Moreover, there are no activities such as tourism or boat transportation in the section. However, construction activities in and along the Poring River will affect the villager’s fishing opportunity. Operation: In the section where the water is to be diverted from the Poring River to the headrace channel, the number and size of fish are predicted to be smaller. Consequently, it will affect the villager’s fishing opportunities.
3.7 Existing Social Infrastructures and Services
A+ - A+ - Construction: In order to improve accessibility of construction vehicles to the project area, the main road from the villages to the direction of Tarutung will be upgraded. It will help the villagers’ accessibility to Tarutung area. Operation: There is no activity that will affect existing social infrastructures and services.
3.8 Social Institutions and Local Decision-making
- - - - Construction/Operation: No activity that will affect social institutions and local decision-making is anticipated.
3.9 Misdistribution of Benefit and Damage
- - - - Construction/Operation: No activity that will cause misdistribution of benefit and damage is anticipated.
3.10 Local Conflict of Interest
- - - - Construction/Operation: No activity that will cause local conflict of interest is anticipated.
3.11 Cultural Heritage - - - - Construction/Operation: No cultural heritage is confirmed within the project. 3.12 Landscape C - C - Construction: Construction of the facilities such as power house and intake weir
will change the scenery. However, the project is located in a remote area where there are no touristic activities; the impact on the landscape is not significant. Operation: No activity that will affect landscape is anticipated.
3.13 Gender C - - - Construction: No unfair custom for women on landownership or social participation is confirmed in the villages of the project area. Accordingly, no activity that will cause gender issues is anticipated. Operation: No activity that will cause gender issues is anticipated.
3.14 Children’s Rights - - - - Construction/Operation: No activity that will affect children’s rights is anticipated.
3.15 Communicable Diseases such as HIV/AIDS
C - C - Construction: Inflow of construction workers from construction worker’s camp to local communities will raise the risks of communicable diseases. Operation: No activities raising the risk of communicable diseases in the local communities are anticipated.
3.16 Working Environment (includes work safety)
B - B - Construction: Inappropriate management of working environment will raise the risk of accident and decease. Operation: No activities raising the risk of working environment is anticipated.
Final Report
Preparatory Survey on North Sumatra Mini 7-37 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
4. Others 4.1 Accidents C - C C Construction: The effect of construction vehicles to the local community is
anticipated. Operation: There is a risk for villagers to fall down into the open headrace channel.
4.2 Global Warming - B+ - B+ Construction: CO2 emission from construction vehicles is not significant. Operation: Since the hydropower plant uses renewable energy, it will contribute to reduce CO2 emission.
Component 2: Transmission Lines
No. Impacts Rating Rating based
on IEE Result
Brief Description of Result
PCo/C O PCo/C O
1. Pollution Control 1.1 Air Pollution C - C - Construction: Air pollution such as exhaust fumes from earthmoving equipment
as well as construction vehicle associated with the tower construction is anticipated. Considering the scale of the construction activities, the impact is temporary and site specific, thus not significant. Operation: No activity that will cause air pollution is anticipated.
1.2 Water Pollution C - C - Construction: Temporary water pollution due to concrete mixing at the substation and excavation for digging hole to bury transmission pole is anticipated. In addition, temporary water pollution from contractor’s employee’s camp/office is anticipated. Considering the scale of construction activities, the impact is temporary and site specific, thus not significant. Operation: No activity that will cause water pollution is anticipated.
1.3 Waste C - C - Construction: Soil will be excavated for burying construction pole and installing transformer at the substation; however, the soil will be backfilled and no waste soil will be generated. Waste such as kitchen scraps and human waste will be generated from the worker’s camps and construction office. Considering the scale of construction activities, the impact is not significant. Operation: No activity that will cause waste is anticipated.
1.4 Soil Contamination
- - - C Construction: No soil contamination is predicted. Operation: Inappropriate management of transformer will cause oil leakage. Consequently, it will contaminate soil.
1.5 Noise and Vibration
C - C - Construction: Noise and vibration resulting from construction activities are anticipated. The main cause of noise and vibration will be generated at the time of digging hole for burying transmission pole. Considering the scale of construction activities, the impact is not significant. Operation: No activity that will cause noise and vibration is anticipated.
1.6 Ground Subsidence
- - - - Construction/Operation: No activity that will cause ground subsidence is anticipated.
1.7 Offensive Odor - - - - Construction/Operation: No activity that will cause offensive odor is anticipated.
1.8 Bottom Sediment - - - - Construction/Operation: No activity that will affect bottom sediment is anticipated.
2. Natural Environment 2.1 Protected Area - - - - The project area is not located in a protected area. 2.2 Flora, Fauna and
Biodiversity U - C - Construction: After conducting mammal survey and bird survey along the
transmission line route as well as carrying out hearing with relevant administrative bodies, no primary forest was confirmed in the project area. Low biodiversity value was observed in the project area because the area has been disturbed and the habitats have been degraded in previous years due to human encroachment in the area. Along the proposed line route, two species categorized as vulnerable, one species categorized as endangered species, and one species categorized as critically endangered under IUCN Red List were found. The upgrade of the access road would cause illegal logging. 14 mammal species (4 endangered, 7 vulnerable, 3 near threatened) listed in IUCN Red List were found. Impact for birds are not significant since the birds are small in size and the TL will be constructed at a height which the birds do not migrate. These are not endemic to the project area. Considering the scale of construction, in which the transmission line route will not change the shape of the land entirely and the construction activities will be site specific and temporary, the impact would not be significant.
Final Report
Preparatory Survey on North Sumatra Mini 7-38 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Operation: No activity that will cause negative impact on flora, fauna and biodiversity is anticipated.
2.3 Hydrological Situation
- - - - Construction/Operation: No activity that will cause negative impact on hydrological situation is anticipated.
2.4 Topography and Geographical Features
C - C - Construction: Topography and geographical features will be affected due to the construction of transmission poles. Considering the scale of construction activities, the impact is temporary and site specific, thus not significant Operation: No activity that will cause negative impact on topography and geographical features is anticipated.
3.1 Involuntary Resettlement
C - C - Construction: No resettlement is needed since the transmission line route avoided the residential area. However, due to the construction of transmission poles and substation, about 0.4 ha of land will be acquired. Operation: No activity that will cause involuntary resettlement is anticipated.
3.2 Vulnerable (poor households, female-headed households)
U - C - Construction: The average income in most of the project area is under the minimum income set in North Sumatra Province. However, the impact to the affected households is not significant (only 1 m² will be affected due to the construction of a pole at a time) Operation: No activity that will affect the vulnerable is anticipated.
3.3 Indigenous and Ethnic Minority
U - C - Construction: The Toba Batak is the major ethnic group and the Batak language is their native language in the project area. Although the literacy ratio is high ranging from 60% to 97%, the ratio of those who can understand official documents in Indonesian remains low at around 30%. Consideration shall be given for communication. Operation: No activity that will affect indigenous and ethnic minority is anticipated.
3.4 Local Economy, Employment, Livelihood
C+ - C+ A+ Construction: Positive impact such as creation of local employment is predicted. Operation: No activity that will affect local economy, employment, and livelihood is anticipated. Upgraded road which is constructed during the construction phase for accessing construction site will enhance the mobilization of people and goods and contribute in the economic development of the project area.
3.5 Land Use and Utilization of Local Resources
C - C - Construction: Due to the construction of transmission poles, 0.4 ha of land will be converted from forest/agricultural land. The acquired area is sparse, thus the impact on each affected area is not significant. Operation: No activity that will impact on land use or change the local resources is predicted.
3.6 Water Usage or Water Rights of Common
- - - - Construction/ Operation: No activity that will cause negative impact on water usage or water rights of commons is predicted.
3.7 Existing Social Infrastructures and Services
A+ - A+ - Construction: In order to improve accessibility of construction vehicles to the project area, the main road from Tarutung will be upgraded. It will help villagers to have access to Tarutung area. Operation: No activity that will affect existing social infrastructures and services is anticipated.
3.8 Social Institutions and Local Decision-making
- - - - Construction/Operation: No activity that will affect social institutions and local decision-making is anticipated.
3.9 Misdistribution of Benefit and Damage
- - - - Construction/Operation: No activity that will cause misdistribution of benefit and damage is anticipated.
3.10 Local Conflict of Interest
- - - - Construction/Operation: No activity that will cause local conflict of interest is anticipated.
3.11 Cultural Heritage - - - - Construction: No cultural heritage is confirmed within the project area. Operation: No activity that will affect cultural heritage is anticipated
3.12 Landscape C - C - Construction: Construction of distribution poles will change the scenery. However, the transmission line will be located either along the side of the public road or remote location from the residential area; thus, the predicted impact is not significant. Operation: No activity that will affect the landscape is anticipated.
3.13 Gender C - - - Construction: Fair involvement in the process of land acquisition will be disturbed due to gender bias; however, judging on the basis of current social status and women’s role, no gender concern is anticipated. Operation: No activity that will cause gender issues is anticipated.
Final Report
Preparatory Survey on North Sumatra Mini 7-39 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
3.14 Children’s Rights - - - - Construction/Operation: No activity that will affect children’s rights is anticipated.
3.15 Communicable Diseases such as HIV/AIDS
C - C - Construction: Inflow of construction workers from the construction worker’s camp to local communities will raise the risks of communicable diseases. However, considering the scale of construction activities, the impact is temporary and site-specific, thus not significant Operation: No activities that will raise the risk of communicable diseases in the local communities are anticipated.
3.16 Working Environment (includes work safety)
C - C - Construction: Inappropriate management of working environment will raise the risk of accident and death. Operation: No activities that will raise the risk of accident and decease in the working environment are anticipated.
4.1 Accidents C - C - Construction: The effect of construction vehicles to the local community is anticipated. Operation: No activities that will cause accidents are anticipated.
4.2 Global Warming - - - - Construction/Operation: No activities that will cause accidents are anticipatedSource: JICA Survey Team
(2) Natural Environment
1) Flora
Component 1 (Hydropower Plants): According to the UKL-UPL (Environmental Management and
Monitoring Plan) prepared by the North Sumatra University (USU) and certified by the North Tapanuli
District Government in 2013, 71 species were found in the proposed project construction area (Location
I) or residential area (Location II) in Component 1. No threatened species, comprising of critical species
(CR), endangered species (EN), and vulnerable species (VU) under the IUCN Red List or Attachment to
the Presidential Decree No.7 1999 on Conservation of Flora and Fauna, were found in Location I.
Component 2 (Transmission Lines): The sampling survey was conducted during the wet season (April
2015) and dry season (September 2015). Survey methods are: 1) direct sampling at eight locations along
the proposed transmission lines, 2) observations, 3) identification of unknown plants at the laboratory of
Plant Ecology, Department of Ecology, North Sumatra University, and 4) interviews with local people.
As for the land cover vegetation along the transmission line route, it was found that it was dominated by
shrubs, fields, and settlements; and there is a primary forest. About 154 species of plants are scattered
along the path of observation. Based on the literature review, two species of plants that are listed in the
Attachment to the Presidential Decree No.7 1999 on Conservation of Flora and Fauna, and two species
categorized as vulnerable, one species categorized as endangered, and one species categorized as
critically endangered under the IUCN Red List were found.
These identified plants are not endemic plants in the project area. These plants are widely distributed in
various forest areas in Indonesia as well as in the tropical forests. With the efforts to avoid these identified
species by rerouting the transmission line, the impact on the flora in the project area of Component 2 can
be minimized. Accordingly, predicted impact on the flora is not significant.
2) Fauna
Component 1 (Hydropower Plants): According to the certified UKL-UPL prepared by USU 2013, 15
mammals and 7 aves were identified in the area of Component 1. Six out of 15 mammals identified
through hearing with villagers that are categorized as threatened species (CR: critically endangered, VU:
Final Report
Preparatory Survey on North Sumatra Mini 7-40 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
vulnerable, EN: endangered) in IUCN Red List or 12 mammals fall into the protected list in Decree No.7.
After carrying out hearing with villages in the area of Component 1 in April 2015, it was confirmed that
these species were used to be in the project area; however, they have not been witnessed in the last ten
years. Accordingly, it would be assumed that no threatened species are confirmed in the Component 1
area, however, is better to prepare mitigation measures such as prohibit hunting by the construction
workers in the project area.
Component 2 (Transmission Lines): The sampling survey was conducted during the wet season (April
2015) and dry season (September 2015). Survey methods are: 1) observations, 2) identification of
unknown mammals at the laboratory of Plant Ecology, Dept. of Ecology, North Sumatra University and
3) interviews with local people.
As for mammals, 53 species were found along the proposed transmission line routes in which 12 species
are listed in the Attachment to the Presidential Decree No.7 1999 on Conservation of Flora and Fauna.
Among the 12 species, only three species are actually observed at the field, two species could not be
specified due to insufficient data, and information on seven species were collected from public interviews.
On the other hand, 14 mammals under the UNCN Red List were found comprising four endangered
species, eight vulnerable species, and three nearly threatened species. Only six species were actually
observed at the field, two species could not be specified due to insufficient data, and information on six
species were collected from public interviews.
Some of the habitat of identified species will be permanently disturbed due to cutting of trees for the
construction of the transmission lines and temporarily due to the construction activities. However, the
scale of impact due to the conversion of about 0.4 ha of forest/agricultural land to project land for burying
transmission line pole with 1 m² land in each pole along the 30 km of linger area and cutting of trees of 5
m width along the transmission line route will not change the shape of the land entirely; and the
construction activities will be site specific and temporary; therefore, it is considered that the project will
not affect/impact significantly on the survival of living things in the project area.
3) Impact Resulting from the Water Diversion from the Poring River to the Headrace Channel
Due to the diversion of water from the Poring River to the headrace channel of the Poring-1 and Poring-2
mini hydropower plants, the river discharge in the 5 km section from the Poring-1 Intake Weir to the
Poring-2 Mini Hydropower Plant will be decreased. Since there is no specific regulation on the
maintenance flow of hydropower plants in Indonesia, the electric generation guideline (Ministry of Land,
Infrastructure, Transport and Tourism, Japan, 1988) will be applied to set the maintenance flow for the
Poring-1 and Poring-2 mini hydropower plants. Based on the guideline, the maintenance flow for the
project is to be set at about 0.31 m3/s (see Chapter 4.2.1). In this section, the impact resulting from the
water diversion will be discussed.
In order to assess the impact resulting from the diversion of water from the Poring River to the headrace
channel, the following items were studied by conducting field survey and hearings with the local people
and authorities, and carrying out literature review. The studied items and the results of the study are
Final Report
Preparatory Survey on North Sumatra Mini 7-41 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
summarized in Table 7.6.3.
Table 7.6.3 Summary of the Survey Result No Items Point to be assessed Method of Study Result 1 Fish and
Fishery Conservation concern, importance of habitat in the project area
- Identify fish species from the Poring River during the dry season and wet season using appropriate fishing methods and working with local fisherman
Two fish species were found in the project area of the Poring River. Both are not endemic to the region and not listed in the IUCN Red List. Abundance of fishes is very low due to geographic feature of the project area and over fishing by local people.
Socioeconomic importance to local community and fisheries in the downstream of the project site
- Interview with village heads and local people by conducting focused-group discussions
There is no commercial fishing. There is no fishing point after the downstream of the project site due to difficult accessibility. Fishing is a hobby and for domestic consumption.
2 Water Quality Water quality and wastewater discharge amount
- Confirm the location of wastewater discharge to the project area of the Poring River - Analyze the water quality at the laboratory
There is no location of discharged domestic or industrial wastewater directly into the project area of the Poring River. The result of water quality analysis in the dry and wet season satisfies the water quality standards.
3 Water Supply Water level decrease to water supply facility
- Confirm the location of water supply facility within the project area
There is no water supply facility located in the project area of the Poring River
4 Irrigation Water level decrease to irrigation system
- Confirm the location of irrigation facility within the project area
There is no irrigation facility located in the project area of the Poring River
5 Underground Water
Water level decrease to water supply facility
- Confirm the location of the facility using underground water within the project area
There is no water supply facility using underground water in the project area
6 Boat Transportation
Water level decrease to boat transportation
- Confirm the location of boat transportation within the project area
There is no boat transportation in the project area of the Poring River
7 Tourism Water level decrease to aesthetics and touristic activities
- Confirm the location of tourism site or facility within the project area
There is no location or facility used for tourism in the project area of the Poring River
Source: JICA Survey Team
Based on the study, it is concluded that the negative impacts on the items from No.3 to No.7 are not
anticipated. Accordingly, the result of the impact on the fish and fishery and water quality are discussed
in this section.
a. Fish and Fishery
- Fish Species
The fish species survey was conducted at the six sites during the two seasons, the wet season (from 26 to
28 of May 2015) and the dry season (from 10 to 14 of August 2015). The location of the six sampling
sites is shown in Table 7.6.4. The result of the collected fish species is shown in Table 7.6.5.
Final Report
Preparatory Survey on North Sumatra Mini 7-42 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.6.4 Location of Fish Species Survey Location Description
Lubuk* Sihopar Intake Weir Poring-1 Lubuk NIpis Intake Weir Poring-1
Lubuk Pandan Power House Poring-1 Lubuk Bangal Intake Weir Poring-2**
Lubuk Sitorngom Power House Poring-2 Lubuk Batnunbolon One of the fishing points of villagers
*Lubuk means a fishing point in the local language (Toba Batak language) **The survey was conducted based on the old layout with Poring-2 Intake Weir. However, after the review of the facility layout, Poring-2 Intake Weir is decided not to be constructed. Source: USU
Table 7.6.5 Result of Identified Fish Species Wet Season
Location
Condition of Site Fish Species
pH Temperature
(°C) DO (mg/L)
Conductivity(S)
Velocity (m/s)
Local Name Scientific Name Number of Catch
Lubuk Sihopar 7.5 23 7.3 20 1.2 Ikan Garing Neolissochilus sumatranus 3
Lubuk NIpis 7.6 25 7.2 22 0.6 - - 0
Lubuk Pandan 7.2 27 7,2 20 0.9 Ikan Garing Neolissochilus sumatranus 1
Lubuk Bangal 7.4 26 7.2 20 1.0 Ikan Garing Neolissochilus sumatranus 6
Lubuk Sitorngom 7.3 26 7.3 21 1.2 Ikan Garing Neolissochilus sumatranus 3
Ikan Garing Tar tambra 1
Lubuk Batnunbolon 7.3 29 7.2 23 2.0-3.5 Ikan Garing Neolissochilus sumatranus 12
Source: USU Dry Season
Location
Condition of Site Fish Species
pH Temperature
(°C) DO (mg/L)
Conductivity(S)
Velocity (m/s)
Local Name Scientific Name Number of Catch
Lubuk Sihopar 7.3 22 7.4 21 1.0 Ikan Garing Neolissochilus sumatranus 2
Ikan Garing Tar tambra 4
Lubuk NIpis 7.4 23 7.3 21 0.8 - - 0Lubuk Pandan 7.3 22 7.3 21 1.2 - - 0Lubuk Bangal 7.4 22 7.5 22 1.2 Ikan Garing Neolissochilus sumatranus 1
Ikan Garing Tar tambra 3
Lubuk Sitorngom 7.7 22 7.3 21 1.5 Ikan Garing Tar tambra 3
Lubuk Batnunbolon 7.4 23 6.9 22 2.7 - - 0Source: USU
The result of the fish species survey at five locations around the intake weir and powerhouse of the
Poring-1 and Poring-2 mini hydropower plants during the rainy season showed that the number of catch
was relatively low with a total of 26 fishes. Furthermore, the weight of each fish was quite small ranging
from 16.6 g to 143.1 g and only two fishes exceeded 100 g. The survey result at the same location during
the dry season indicated that the number of catch is lower (13 fishes) than that during the rainy season and
the size of fish is also smaller ranging from 9.3 g to 68.3 g. This fact shows that the abundance of fish in
the Poring River is low. In particular, it is remarked that even under the present condition, the population
and size of fishes become small during the dry season when the discharge is low.
Final Report
Preparatory Survey on North Sumatra Mini 7-43 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
In the survey, two fish species were identified, namely, Tor tambra7 and Neolissochilus sumatranus. Both
species are not listed as vulnerable or endangered in the IUCN Red List and they are not ascent type of fish.
There is no specific study on the required maintenance flow for these identified fish species; however, these
types of fish are categorized as fish species living in fast flowing water. There are several studies reporting that
this type of fish is identified with water discharge of more than 25 L/s (or 0.025 m3/s), with dissolved oxygen
(DO) of 6-8 ppm, and an optimum discharge for breeding fish of 50-100 L/s (or 0.05 – 0.1 m3/s).8
Considering the fact that the maintenance flow rate is set at 0.31 m3/s, the discharge of water from the Poring-1
and Poring-2 mini hydropower plants would satisfy the optimum discharge for breeding the fish species.
However, because of the undulating topography of the Poring River and the presence of many boulders in the
river, the water route is changed in a complex way. It is predicted that the set maintenance flow of 0.31 m3/s
(or about 97% of drought water discharge) would partly make the water flow significantly lower.
Consequently, the population and size of the fish species in the section wherein the water discharge will
decrease due to the diversion would be affected.
- Fishery and Local Community
The information on the villagers who practice fishing in the Poring River was obtained from the
information office of the chief secretary of the village and also from some local community leaders. The
names of fishermen were also obtained from the village of Siantar Naipospos and Pardomuan Nauli. The
total number of interviewed persons is 24 comprising 21 persons from Siantar Naipospos Village and
three persons from Pardomuan Nauli. Interviewees were chosen randomly.
Based on the interviews and information from the villagers in the two surveyed villages, it was confirmed
that none of them catch fish in the river for commercial purpose. Basically, they catch fish for domestic
consumption and if they catch a large number of fish, it will be sold to other villagers. Some of the
villagers mentioned that they catch fish just for entertainment or hobby after work. Summary of the catch
in the Poring River obtained from the interview is shown in Table 7.6.6.
The methods of fishing are with net, hook and lines. Villagers go for fishing not all the time or everyday,
but 2 to 3 times in a week or once in a week.
After the construction of the Poring-1 Mini Hydropower Plant and the Poring-2 Mini Hydropower Plant,
the number of fishes as well as the size of fishes are predicted to be smaller. Accordingly, it would cause:
1) losing one of the sources of protein for domestic consumption, 2) spending extra money to buy fish for
domestic consumption, 3) losing additional income opportunity for selling extra catch to neighbors, and
4) losing location for recreation after work. 7 Tor tambra is categorized as DD (Data Deficient) in the IUCN Red List 8 Haryono, Tjakrawidjaja, A.H. 2009. Bioekologi ikan tambra sebagai dasar dalam proses domestikasi dan reproduksinya. Proses domestikasi dan reproduksi ikan tambra yang telah langka langka menuju domestikasinya:17-36. LIPI Kiat, Ng Chi. 2004. The king of the river mahseer in Malayan and the region. Inter Sea Fishery, Malaysia. Kottelat, M., A.J. Whitten, S.N. Kartikasari & S. Wirjoatmodjo. 1993. Freshwater Fishes of Western Indonesia and Sulawesi. Periplus Editions Limited. 1-291+84 plates Weber, M. & L.F. de Beaufort. 1913-1916. The Fishes of the Indo-Australian Archipelago I-XI. E.J. Brill Ltd., Leiden.
Final Report
Preparatory Survey on North Sumatra Mini 7-44 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
According to the hearings in the focused group meeting, all participants agreed to support the project if
the project would consider measures for community development as compensation for the loss of fish
catch. Main requests for community development are: 1) improve access road from the village to Adian
Koting District (towards Tarutung direction), 2) electrification in the village, and 3) improve domestic
water supply facilities in the village.
Table 7.6.6 Type of Fish, Volume of Catch, and Economic Value Type of Fish
Method of Catch Volume of
Catch, kg/timeEconomic Value
kg/Rp (US$) Frequency of Fishing
Local Name Scientific Name Ikan Garing Neolissochilus sumatrana Net/hook and lines 0.25 kg to 4 kg 50,000 (3.7) to
60,000 (4.5) 2-3 times a week, Once a week
Ikan Jurung/ Ihan Batak
Tor Tambroides Hook and lines 1 kg to 2 kg 50,000 (3.7) to 60,000 (4.5)
2-3 times a week, Once a week
Ikan Dundung Anguilla bicolour Hook and lines/net 0.1 kg to 2 kg 50,000 to 60,000 2-3 times a week, Once a week
Ihan Lappung N/A Hook and lines 0.1 kg to 2 kg 50,000 (3.7) 2-3 times a week, Once a week
Ihan Lelan Osteochilus vittatus C.V Hook and lines 0.5 kg to 2 kg 50,000 (3.7) Once a week Source: JICA Survey Team
- Conclusion
Considering the fact that the set maintenance flow rate of 0.31 m3/s, it will satisfy the required discharge
for breeding the fish species. The topography of the Poring River does not enable fish species
(particularly large size of fish) to migrate from one area to another area for feeding and this will likely
reduce the population and size of the fish. The identified fish species are not endemic to the region and
they are considered to be popular in the upstream and downstream of the project site, where geography of
the area is very similar to the project area. Consequently, it is considered that the impact due to the
diversion of water from the intake weir of the Poring-1 Mini Hydropower Plant to the Poring-2
Powerhouse would not be significant on the fish species in the local area or population of fish.
The mitigation measures against the loss of fishing site and loss of fish catch shall be considered taking
into account the villagers’ requests. Since the losses involve not the fishermen engaged in commercial
basis particularly but the whole community members living near the affected section in the Poring River,
it is recommended to provide a means of assistance for community development in exchange of
compensating the losses. Some of the requests such as improving the access road to Tarutung is already
incorporated in the project framework. In addition to this, alternative means to supplement protein such as
constructing fish culture or introducing effective method for breeding livestock shall be developed during
the operation phase. Using the corporate social responsibility (CSR) scheme is one of the realistic options.
b. Water Quality
Water quality sampling was conducted at the nine sites during the two seasons, i.e., wet season (from 25
to 27 April 2015) and dry season (from 10 to 13 August 2015). The location of the nine sampling sites is
shown in Table 7.6.7. The result of water sampling is shown in Table 7.6.8.
Final Report
Preparatory Survey on North Sumatra Mini 7-45 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.6.7 Location of the Water Sampling Location Description
Site 1 Poring-1 Intake Weir Site 2 Poring-1 Powerhouse Site 3 Poring-2* Intake Weir Site 4 Poring-2 Powerhouse Site 5 Public Bathroom in Dusum Limus Site 6 Aek Pandolungan (tributary) in Dusum Lobu Site 7 Aek Pandolungan (tributary) in Dusum Lobu Haminjon Site 8 Pancuran (public water supply space) in Dusun Lobu Haminjon Site 9 Public bathroom in Dusum Lobu Haminjon
*The survey was conducted based on the old layout with Poring-2 Intake Weir. However, after the review of the facility layout, Poring-2 Intake Weir is decided not to be constructed Source: USU
Table 7.6.8 Results of the Water Sampling Wet Season
Parameters Unit of
Measurement National Standard*
Site 1 Site 2 Site 3 Site 4 Site 5 Site 6 Site 7 Site 8 Site 9
Physical Temp. C ± 3 28.0 28.0 28.5 29.0 27.0 27.0 28.4 28.3 29.0 Odor - - No
odorNo
odorNo
odorNo
odorNo
odorNo
odorNo
odor No
odor No
odorTDS mg/l 1,000 231.7 228.5 267.5 299.4 146.8 142.3 205.8 226.7 TSS mg/l 50 34.9 32.6 31.5 30.8 32.5 34.7 33.6 31.4 32.8 pH - 6-9 7.2 6.6 7.1 7.3 6.3 7.2 6.7 6.4 6.4 Color PtCo - 4.2 <3.10 4.8 4.1 <3.10 <3.10 <3.10 <3.10 3.88 Turbidity NTU - 0.8 0.4 0.6 0.4 0.3 0.3 0.6 0.9 0.4 Conductivity s - 20 20 21 22 21 20 22 21 20 Chemical Iron (Fe) mg/l 1 <0.08 <0.08 <0.08 0.10 <0.08 <0.08 <0.08 <0.08 <0.08Fluoride (F) mg/l 1.5 0.08 0.05 0.05 0.09 0.08 0.12 0.09 0.12 0.06 Cadmium (Cd) mg/l 0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01DO mg/l >4 7.3 7.2 7.4 7.2 7.1 7.4 7.3 7.2 7.3 Alkalinity (CaCO3) mg/l - 36.52 31.44 41.62 49.55 32.17 38.56 44.56 52.76 45.91Chloride (Cl) mg/l - 24.51 19.67 32.75 28.61 17.62 22.45 28.39 37.11 22.63Chromium VI (Cr6+)
mg/l 0.05 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04
Manganese (Mn) mg/l - 0.10 0.09 0.07 0.12 0.05 0.06 0.05 0.06 0.18 Ammonia (NH3-N) mg/l - 0.28 0.25 0.27 0.26 0.20 0.18 0.17 0.18 0.14 Nitrate (NO3-N) mg/l 10 8.37 7.56 7.63 8.25 4.23 3.69 4.56 4.14 8.20 Nitrite (NO2-N) mg/l 0.06 0.03 0.02 <0.01 0.03 <0.01 <0.01 <0.01 <0.01 0.03 Zinc (Zn) mg/l 0.05 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02Sulfate (SO4) mg/l - 27.51 26.34 33.26 37.11 28.66 20.10 16.23 27.12 16.66Lead (Pb) mg/l 0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03MBAS mg/l 0.2 0.09 0.09 0.05 0.08 0.08 0.03 0.08 0.03 0.15 Phenol mg/l 0.001 <0.006 <0.006 <0.006 <0.006 <0.006 <0.006 <0.006 <0.006 <0.006Organic (KMnO4) mg/l - 3.11 3.05 4.26 5.17 3.20 2.76 3.86 4.19 2.24 Total Phosphate (PO4)
mg/l - 0.10 0.07 0.10 0.07 0.06 0.04 0.03 0.04 0.03
Microbiological Total Coliform Jml/100 ml 5,000 286 254 325 417 188 115 205.8 266.9 295 Faecal Coliform Jml/100 ml 1,000 104 97 177 227 89 63 112 161 116 *Management of Water Quality and Water Pollution Control Class II, PPRI No.82, 2001 Source: USU Dry Season
Parameters Unit of
Measurement National Standard*
Site 1 Site 2 Site 3 Site 4 Site 5 Site 6 Site 7 Site 8 Site 9
Physical Temp. C ± 3 22.0 22.0 22.0 22.0 24 23 22 22 24 Odor - - No
odorNo
odorNo
odorNo
odorNo
odorNo
odorNo
odor No
odor No
odor
Final Report
Preparatory Survey on North Sumatra Mini 7-46 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
TDS mg/l 1,000 0.09 0.09 0.09 0.09 0.10 0.09 0.09 0.09 0.10TSS mg/l 50 35.2 33.9 30.4 29.8 30.1 32.2 34.0 32.8 33.0pH - 6-9 7.3 7.3 7.4 7.4 7.1 7.4 7.4 6.8 6.7 Color PtCo - 4.3 <3.10 4.5 3.9 <3.10 <3.10 0.7 0.10 3.90Turbidity NTU - 0.10 0.6 0.5 0.3 0.4 0.4 21 22 0.4 Conductivity s - 21 21 22 21 21 21 22 Chemical Iron (Fe) mg/l 1 <0.08 <0.08 <0.08 0.10 <0.08 <0.08 <0.08 <0.08 <0.08Fluoride (F) mg/l 1.5 0.09 0.06 0.06 0.10 0.09 0.13 0.08 0.10 0.05Cadmium (Cd) mg/l 0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01DO mg/l >4 7.4 7.3 7.5 7.3 7.2 7.3 7.4 7.3 7.1 Alkalinity (CaCO3) mg/l - 35.42 32.90 42.20 50.13 33.09 39.08 45.60 53.42 46.10Chloride (Cl) mg/l - 25.05 20.07 31.78 29.09 18.20 23.10 29.89 38.09 23.56Chromium VI (Cr6+)
mg/l 0.05 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04
Manganese (Mn) mg/l - 0.11 0.10 0.09 0.15 0.06 0.07 0.06 0.07 0.20Ammonia (NH3-N) mg/l - 0.30 0.27 0.30 0.28 0.21 0.19 0.18 0.19 0.16Nitrate (NO3-N) mg/l 10 8.42 7.62 7.68 8.31 3.90 2.25 4.56 4.19 9.09Nitrite (NO2-N) mg/l 0.06 0.03 0.03 <0.01 0.04 <0.01 <0.01 <0.01 <0.01 0.04Zinc (Zn) mg/l 0.05 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02Sulfate (SO4) mg/l - 28.20 27.10 34.40 36.21 28.70 20.19 17.08 28.16 17.12Lead (Pb) mg/l 0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03MBAS mg/l 0.2 0.10 0.10 0.06 0.009 0.09 0.04 0.09 0.04 0.18Phenol mg/l 0.001 <0.006 <0.006 <0.006 <0.006 <0.006 <0.006 <0.006 <0.006 <0.006Organic (KMnO4) mg/l - 3.15 3.11 4.34 5.28 3.34 2.80 3.90 4.21 2.35Total Phosphate (PO4)
mg/l - 0.09 0.08 0.15 0.09 0.07 0.05 0.04 0.05 0.04
Microbiological Total Coliform Jml/100 ml 5,000 290 262 332 423 190 123 204.2 256.9 303 Faecal Coliform Jml/100 ml 1,000 106 95 179 230 90 68 115 168 120 *Management of Water Quality and Water Pollution Control Class II, PPRI No.82, 2001 Source: USU
The result of water sampling in the wet season and dry season shows that the present water quality of the
Poring River around the proposed location of the Poring-1 and Poring-2 mini hydropower plants satisfied
all parameters of the national standards. In the same manner, the water quality at the wastewater
discharge points or tributaries also satisfied all parameters of the national standards.
There was no location in which the pipe of domestic wastewater is directly connected to the Poring River
in the section between the proposed Poring-1 Intake Weir and the proposed Poring-2 Powerhouse. There
is only one discharge point of domestic wastewater identified at Site 6 where the public water supply
place is located near a tributary of the Poring River. After conducting the discharge measurement at this
point, 0.018 m3/s of domestic wastewater was poured via the tributary of the Poring River. However, the
domestic wastewater would be diluted with the water from the identified 15 tributaries upstream of Site 6.
Accordingly, it is considered that the impact on water quality would be insignificant.
Consequently, although the discharge of the Poring River decreases significantly during the operation
phase, negative impact from the decrease in water discharge would be insignificant on the water quality
of the Poring River in the section between the Poring-1 Intake Weir and the Poring-2 Powerhouse
because there is almost no source of wastewater discharge into the Poring River.
Final Report
Preparatory Survey on North Sumatra Mini 7-47 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(3) Social Environment
1) Scale of impact
In Component 1, two villages with 52 households will be affected. There will be no resettlement;
however, about 22 ha of land will be permanently acquired and about 17.5 ha of land will be temporarily
occupied. As for Component 2, 11 villages with 145 households will be affected. In order to construct
transmission line poles, about 0.4 ha of land will be acquired permanently. The scale of impact of
Component 1 and Component 2 is summarized in Table 7.6.9.
Table 7.6.9 Summary of Affected Area, Households and Assets Component 1: Hydropower Plants
Item Unit Poring-1 Poring-2 Affected Village Number 2 2 Affected Land (Permanently) ha 11.15 11.52 Affected Land (Temporary) ha 8.98 8.56 Affected HHs Number 22 33
Type of Land to be Affected9
Agricultural Land (%) 0 0 Plantation Land (%) 95.58 90.97 Residential Land (%) 0 0.42
Others (%)10 4.42 (bush area, forest, crops, etc.) 8.61 (bush area, forest, crops, etc.)Affected Assets Trees Number 8,682 6,868 Crops except paddy (Permanently)
Number 2,080 1,820
Crops except paddy (Temporary)
Number 0 0
Paddy (Permanently) ha 0.5 0.5 Paddy (Temporary) ha 0 0 Source: Hearing with Acting Village Heads in April 2015 and September 2015 Component 2: Transmission Lines
Item Unit Poring-1 and Poring-2* Affected Village Number 11 Affected Land (Permanently) ha 0.311 Affected HHs Number 145
Type of Land to be Affected State Land (Production Forest Land) (%) 33
Non-state Land (%) 57 Affected Assets11 Land ha 0.31 Tress Number 1,613 Crops (except rice) Number 686 Rice ha 0.035 *The precise project area of the Poring-1 Transmission Line and the Poring-2 Transmission Line will be identified after conducting the detailed measurement survey. Source: Hearing with Acting Village Heads in July 2015
2) Summary of Land Acquisition Plan (LAP)
In compliance with the requirement of the JICA Guidelines, land acquisition plans (LAP) for the Poring-1
9 As aforementioned in Chapter 2.1 (2) (land used by the local community), the project area is categorized as production forest (state land) under the management of the Ministry of Forest. However, it is used by local community. The term “type of land to be affected” means the type of land actually used by the local community. 10 It is difficult to distinguish the area for agriculture, plantation, and others since the land is for multiple uses such as plantation of woods and fruit trees for domestic consumption and/or vegetable garden. Here, agricultural land means paddy; plantation land means the land mainly used for commercial trees; and others means forest land used for domestic consumption. 11 The figure includes the area of state land and non-state land.
Final Report
Preparatory Survey on North Sumatra Mini 7-48 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Mini Hydropower Plant, Poring-2 Mini Hydropower Plant, Poring-1 Transmission Line, and Poring-2
Transmission Line were prepared separately.
The following is the summary of the LAP.
a. Policy Gap between the Government of Indonesia and JICA
There is no specific requirement set for land acquisition or resettlement for the private investment Project.
Accordingly, the acquisition or resettlement of the Project will be proceeded in complying with JICA
Guidelines for Environmental and Social considerations and making reference with similar private investment
Projects in Indonesia.
b. Cut-off-date of Eligibility
The cut-off-date of eligibility refers to the date prior to which the occupation or use of the Project area makes
residents/users of the same eligible to be categorized as PAPs and be eligible to Project entitlements. The
cut-off date coincides with the date of the census of affected persons within the Project area boundaries, which
will be conducted at the time of a population census.
In the Project, cut-off-date for titleholders of proposed land is as follows;
- Component 1: Poring 1 and Poring 2 Small Hydropower Plant: 24, April 2015 to 02 May 2015, and 8
September 2015 to 15 September 2015 (Additional survey based on the updated layout: 10 additional
households were identified)
Component 2: Transmission lines for the Poring 1 and Poring 2 Mini Hydropower Plants: Since there is no
boundary of each transmission lines measured, it would be at the time of detailed measurement survey in a
detailed design phase.
c. 4.2 Entitlement Matrix
Based on the hearing from acting village heads in Siantar Naipospos and Pardomuan Nauli as well as the
affected households, an entitlement matrix is developed as shown in Table 7.6.10
Final Report
Preparatory Survey on North Sumatra Mini 7-49 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.6.10 Entitlement Matrix
No. Type of Loss Entitled Persons Entitlement Implementation Issues/Guidelines
1. Fixed Assets 1.1 Loss of land for agriculture in the
land for the Project Those who use the land
Cash compensation at replacement cost based on the market price of Project area or price of similar project nearby
Compensation amount is calculated in consulting with and referring market price of Project area or price set for similar project near the project area at detailed measurement survey
1.2 Loss of private structure in the land for the Project
Those who own the structure
Cash compensation based at replacement cost on the current market price of that area
Compensation amount is calculated in consulting with and referring market price of Project area
1.3 Loss of public structure in the land for the Project
Those who own the structure
Rebuild and upgrade the structure
Compensation amount is calculated in consulting with and referring market price of Project area
1.4 Loss of standing crops/tress in the land for constructing the Project
To be assisted as a part of loss of income sources
2 Loss of Income Source 2.1 Loss of income from standing
crops/tress in the land for constructing the Project
Those who cultivating crops/trees
Trees: Cash Compensation based on the rate set by Dept. of Agriculture and Plantation in North Tapanuli Regency Crops: Cash compensation based on the current market price of Project area
Trees: Compensation amount is calculated based on the compensation price list in Department of Agriculture and Plantation in North Tapanuli Regency) at Detailed Measurement Survey Crops: Compensation amount is calculated in consulting with and referring market price of Project area or price set for similar project near the project area at detailed measurement survey
2.2 Loss of income from standing crops/tress in the land which is to be occupied temporary for constructing Project
Those who cultivating crops/trees
Crops: Cash Compensation of one crop season (s) in the occupied period Trees: Cash compensation based on the rate set by Department of Agriculture and Plantation in North Tapanuli Regency
Crops: Compensation amount is calculated in consulting with and referring market price (farm gate price) of Project area at detailed measurement survey Trees: Compensation amount is calculated based on the compensation price list in Department of Agriculture and Plantation in North Tapanuli Regency) at Detailed Measurement Survey
Source: JICA Survey Team
d. Livelihood Restoration Plan
Although there will be no resettlement in the Project, 11.15 ha of land where is used for commercial plantation
as well as vegetable garden for domestic consumption to be used for constructing facilities of the Project.
In addition to provide cash and assistances in order to compensate the loss of income for the PAPs, it is
recommended to provide means for an alternative sustainable livelihood. Taking account of the assistance
requests by PAHs (i.e. infrastructure development for the project affected community, priority employment
etc), skill improvement in the agricultural field would be effective for restoring and improving PAH’s living
standard for long term. Detailed livelihood restoration plan shall be prepared through the livelihood restoration
committee established during detailed design phase.
The livelihood restoration for the PAHs should be continued in an operation phase as well. Accordingly, the
requested assistances from the acting village heads and PAHs, which could not be realized at the time of
construction phase, can be implemented in an operation phase by using the Corporate Social Responsibility
scheme (CSR).
Final Report
Preparatory Survey on North Sumatra Mini 7-50 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
7.7 ENVIRONMENTAL MANAGEMENT
7.7.1 INSTITUTIONAL ARRANGEMENT
(1) Pre-construction/Construction Phase
JDG Poring/JDG Cianten will establish the project offices. A staff shall be assigned for implementing the LAP
requirement and environmental monitoring. The roles and responsibilities for each institution concerned in the
pre-construction/construction phase are shown in Table 7.7.1.
Table 7.7.1 Roles and Responsibilities of Institutions Concerned in the Pre-construction /
Construction Phase Institution Roles and Responsibilities Key Parties
Project Office (Poring-1 Mini Hydropower Plant under JDG Poring / Poring-2 Mini Hydropower Plant under JDG Cianten)
- Establish the Environmental and Social Team* - Submit environmental monitoring report to the
Department of Environment, North Tapanuli Regency (every six months) and JICA (every three months)
Project Office
Environmental and Social Team in Poring-1 Mini Hydropower Plant Project Office / Poring-2 Mini Hydropower Plant Project Office)
- Enhance smooth implementation of land acquisition between the project office and PAHs
- Prepare environmental monitoring report
Environmental and Social Team
Environmental and Social Officer in the Construction Contractor Office
- Implement mitigation activities based on the environmental management and monitoring plan
Construction Contractor
Department of Environment, North Tapanuli Regency
- Supervise environmental management activities including land acquisition implemented by the project office
Department of Environment, North Tapanuli Regency
Livelihood Restoration Committee (Grievance Committee)
- Enhance harmonious consensus on compensation and assistances between PAPs/affected community and the project office
- Ensure the implementation of LAP - Act in the Grievance Committee (see Chapter 5
Grievance Redress System)
- Village head (Chair) - All concerned village
authorities - Representatives from PAHs- Representatives of the
project office *Environmental and Social Team is in-charge of LAP implementation as well as UPL-UKL/Environmental Management and Monitoring Source: JICA Survey Team
(2) Operation Phase
The tasks on environmental monitoring will be taken by the Operation and Maintenance Department in
Poring-1 Mini Hydropower Plant (JDG Poring) and Poring-2 Mini Hydropower Plant (JDG Cianten). The
LAP shall be finished by the end of the construction. However, it is highly recommended to give social
considerations to the communities in the project area continuously during the operation phase.
Community development committee which used to be the livelihood restoration committee previously
will be established with the assistance of JDG Poring/JDG Cianten. In consultation with the committee,
JDG Poring will develop a community development plan in the framework of CSR. Details such as
management method shall be finalized at the commencement of the project operation. Proposed roles and
responsibilities of relevant institutions for the CSR activity during the operation phase are shown in Table
7.7.2.
Final Report
Preparatory Survey on North Sumatra Mini 7-51 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.7.2 Proposed Roles and Responsibilities for CSR Activity during
the Operation Phase Institution Roles and Responsibilities Key Parties
Poring-1 Mini Hydropower Plant in JDG Poring Poring-2 Mini Hydropower Plant in JDG Cianten
- Establish an Environmental Team - Submit an environmental monitoring
report to the Department of Environment, North Tapanuli Regency every six months
- Develop a plan for CSR and secure budget for the CSR
Poring-1 Mini Hydropower Plant
Environmental and Social Team in Poring-1 Mini Hydropower Plant / Poring-2 Mini Hydropower Plant
- Implement CSR activities Environmental and Social Team
Community Development Committee
- Cooperate with JDG Poring/JDG Cianten for smooth implementation of the CSR
- Village head (Chair) - All concerned village authorities - Representatives from local community - Representatives of Poring-1 Mini
Hydropower Plant Source: JICA Survey Team
7.7.2 MITIGATION MEASURES AND MONITORING PLAN
Based on the result of IEE, mitigation measure and its monitoring plan are developed for each predicted
impact as shown in Table 7.7.3.
Table 7.7.3 Mitigation Measures and Monitoring Plan Mitigation Measures Component 1: Hydropower Plants Pre-construction/Construction Phase Potential Impact
Proposed Mitigation Measures Institutional
ResponsibilityImplementation
Schedule Cost
Anti-Pollution Air Pollution ①Apply preventive maintenance system, optimizing
construction schedule to minimize time that vehicles are in operation.
②Apply dust control measures such as water spraying on the unpaved road.
Contractor During construction
-
Water Pollution ①Apply sediment traps, silt traps, develop fuel handling procedure, and proper sewage
②Monitor the water quality at discharge point of wastewater
Contractor During construction
①Under civil work cost
②Under Environmental Management and Environmental Monitoring Cost
Waste ①Secure sites for disposing of construction wastes,
vegetable debris, and installing garbage bins
Contractor During construction
Under civil work cost
Noise and Vibration
①Limit the construction work only at daytime near the
residential area.
②Apply periodical inspection of the equipment
Contractor During construction
-
Natural Environment Flora, Fauna and Biodiversity
①Instruct all personnel employed by the Contractor not to intrude into the forest land for hunting, trading of wildlife or collecting timber.
Contractor During construction
(instruction can be provided at the time of safety
Final Report
Preparatory Survey on North Sumatra Mini 7-52 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
②Prohibit introduction of species by all personnel employed by the Contractor
awareness program)
Topography and Geographical Features
①Avoid unnecessary excavation and digging works Contractor During construction
-
Social Environment Involuntary Resettlement
①Apply appropriate compensation and assistance such as priority employment for the PAHs, community infrastructure improvement for the project affected community
EST* Before commencement of construction activities
Under Environmental Management and Environmental Monitoring Cost
Vulnerable (poor households)
①Apply proper compensation EST Before commencement of construction activities
Indigenous and Ethnic Minority
①Assign a staff who is bilingual in Indonesian and Batak language whenever there is an occasion to communicate with villagers
EST During pre-construction/ construction
Land Use and Utilization of Local Resources
①Apply proper compensation EST Before commencement of construction activities
Landscape ①Avoid leaving borrow pit and cut area
②Reinstate the damage with vegetation coverage
Contractor During construction
Under civil work cost
Water Usage or Water Rights of Common
①Apply appropriate assistance such as priority employment for the PAHs, community infrastructure improvement for the project affected community
EST During pre-construction/ construction
Under civil work cost /Environmental Management and Environmental Monitoring Cost
Communicable Diseases such as HIV/AIDS
①Develop a health awareness program
②Employ local people as much as possible
Contractor During construction
Under Environmental Management and Environmental Monitoring Cost
Working Environment (includes work safety)
①Develop a safety awareness program
②Apply safe working practice
Contractor During construction
Others Accidents ①Prepare road safety measurement plan Contractor During
construction Under Environmental Management and Environmental Monitoring Cost (Included under the cost of working environment)
* EST: Environmental and Social Team at the Project Office of Poring-1 Mini Hydropower Plant/Poring-2 Mini Hydropower Plant Operation Phase (implemented by JDG Poring/JDG Cianten)
Potential Impact Proposed Mitigation Measures
Implementation Schedule
Cost
Natural Environment Flora, Fauna and Biodiversity
①Apply appropriate assistance such as priority employment for the PAHs, community infrastructure improvement for the project affected community
During operation Under the budget of CSR
Hydrological Situation
①Apply appropriate assistance such as priority employment for the PAHs, community infrastructure improvement for the project affected community
During operation
Final Report
Preparatory Survey on North Sumatra Mini 7-53 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Social Environment Land Use and Utilization of Local Resources
①Apply appropriate assistance such as priority employment for the PAHs, community infrastructure improvement for the project affected community
During operation Under the budget of CSR
Water Usage or Water Rights of Common
①Apply appropriate assistance such as priority employment for
the PAHs, community infrastructure improvement for the project affected community
During operation
Others Accidents ①Apply warning signs along the headrace channel During operation Under operation
and maintenance cost
Component 2: Transmission Lines Pre-construction/Construction Phase Potential Impact Proposed Mitigation Measures Institutional
ResponsibilityImplementation
Schedule Cost
Anti-Pollution Air Pollution ①Apply preventive maintenance system, optimizing
construction schedule to minimize time that vehicles are in operation.
②Apply dust control measures such as water spraying on the unpaved load.
Contractor During construction
-
Water Pollution ①Apply sediment traps and silt traps, develop fuel handling procedure, and proper sewage
②Monitor the water quality at discharge point of wastewater
Contractor During construction
①Under civil work cost
②Under Environmental Management and Environmental Monitoring Cost
Waste ①Secure sites for disposing of construction wastes,
vegetable debris, and installing garbage bins
Contractor During construction
Under civil work cost
Noise and Vibration
①Limit the construction work only at daytime near the residential area.
②Apply periodical inspection of the equipment.
Contractor During construction
-
Natural Environment Flora, Fauna and Biodiversity
①Instruct all personnel employed by the Contractor not to intrude into the forest land for hunting, trading of wildlife or collecting timber.
②Prohibit species introduction by all personnel
employed by the Contractor
Contractor During construction
(instruction can be provided at the time of safety awareness program)
Topography and Geographical Features
①Avoid unnecessary excavation and digging works Contractor During construction
-
Social Environment Involuntary Resettlement
①Apply appropriate compensation and assistances such as priority employment for the PAHs, community infrastructure improvement for the project affected community
EST Before commencement of construction
Under Environmental Management and Environmental Monitoring Cost
Vulnerable (poor households)
①Apply proper compensation EST Before commencement of construction
Indigenous and Ethnic Minority
①Assign a staff who is bilingual in Indonesian and Batak language whenever there is an occasion to communicate with the villagers
EST During pre-construction/ construction
Land Use and Utilization of Local Resource
①Apply proper compensation EST Before commencement of construction
Final Report
Preparatory Survey on North Sumatra Mini 7-54 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Landscape ①Avoid leaving borrow pit and cut area
②Reinstate the damage with vegetation coverage
Contractor During construction
Under civil work cost
Communicable Diseases such as HIV/AIDS
①Develop a health awareness program
②Employ local people as much as possible
Contractor During construction
Under Environmental Management and Environmental Monitoring Cost
Working Environment (includes work safety)
①Develop a safety awareness program
②Apply safe working practice
Contractor During construction
Accidents ①Prepare road safety measurement plan Contractor During construction
Under Environmental Management and Environmental Monitoring Cost (Included under the cost of working environment)
* EST: Environmental and Social Team at the Project Office of Poring-1 Mini Hydropower Plant/Poring-2 Mini Hydropower Plant Operation Phase (implemented by JDG Poring/JDG Cianten)
Potential Impact Proposed Mitigation Measures Implementation Schedule Cost Soil Contamination ①Develop operation and maintenance program During operation Under operation and
maintenance cost Monitoring Plan Component 1: Hydropower Plants Pre-construction/Construction Phase
Potential Impact Parameter to be Monitored
Measurement and Frequency
Institutional Responsibility
Implementation Schedule
Cost
Anti-Pollution Air Pollution ①Vehicle Inspection Checklist
②Site Inspection (Construction Site)
①Daily, Visual Inspection
②Daily during Dry Season
EST* During construction
Under Environmental Management and Environmental Monitoring Cost
Water Pollution ①Site Inspection (Construction Site and Worker’s Camp)
②Review the Result of Water Sampling (Construction Site and Worker’s Camp)
①Monthly
②Monthly
EST During construction
Waste ①Site Inspection (Construction Site and Worker’s Camp)
①Monthly EST During construction
Noise and Vibration
①②Site Inspection
(Construction Site)
①②Monthly EST During construction
Natural Environment Flora, Fauna and Biodiversity
①②Site Inspection
(Construction Site and Worker’s Camp)
①②Monthly EST During construction
Under Environmental Management and Environmental Monitoring CostTopography and
Geographical Features
①Site Inspection (Construction Site)
①Monthly EST During construction
Social Environment Involuntary Resettlement
①Site Inspection
(Construction Site)
①Monthly (weekly
during disbursement of compensation)
EST Before commencement of construction activities
Under Environmental Management and Environmental Monitoring CostVulnerable (poor
households) ①Site Inspection ①Monthly EST Before
commencement
Final Report
Preparatory Survey on North Sumatra Mini 7-55 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
(Construction Site) (weekly during disbursement of compensation)
of construction activities
Indigenous and Ethnic Minority
①Site Inspection (Construction Site)
①Monthly EST During pre-construction/ construction
Land Use and Utilization of Local Resources
①Site Inspection (Construction Site)
①Monthly EST Before commencement of construction activities
Landscape ①②Site Inspection (Construction Site)
①②Monthly EST During construction
Water Usage or Water Rights of Common
①Site Inspection (Construction Site)
①Monthly (weekly during disbursement of compensation)
EST During pre-construction/ construction
Communicable Diseases such as HIV/AIDS
①Number of Trainings
②Site Inspection (Construction Site)
①Every six months
②Every six months
EST During construction
Working Environment (includes work safety)
①Number of Trainings
②Site Inspection
(Construction Site)
①Every six months
②Monthly
EST During construction
Others Accident ①Number of Trainings ①Every six months EST During
construction Under Environmental Management and Environmental Monitoring Cost
* EST: Environmental and Social Team at the Project Office of Poring-1 Mini Hydropower Plant/Poring-2 Mini Hydropower Plant Operation Phase (implemented by JDG Poring/JDG Cianten) Potential Impact
Parameter to be MonitoredMeasurement and Frequency Implementation
Schedule Cost
Natural Environment Flora, Fauna and Biodiversity
①Check annual CSR plan developed by JDG Poring/JDG Cianten
①Annually During operation Under the budget of CSR
Hydrological Situation
①Check annual CSR plan
developed by JDG Poring/JDG Cianten
①Annually During operation
Social Environment Land Use and Utilization of Local Resources
①Check annual CSR plan developed by JDG Poring/JDG Cianten
①Annually During operation Under the budget of CSR
Water Usage or Water Rights of Common
①Check annual CSR plan
developed by JDG Poring/JDG Cianten
①Annually During operation
Others Accidents ①Site Inspection ①Every 6 Months During operation Under operation
and maintenance cost
Final Report
Preparatory Survey on North Sumatra Mini 7-56 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Component 2: Transmission Lines Pre-construction/Construction Phase Potential Impact
Parameter to be Monitored Measurement and Frequency
Institutional Responsibility
Implementation Schedule
Cost
Anti-Pollution Air Pollution ①Vehicle Inspection Checklist
②Site Inspection (Construction
Site)
①Daily, Visual Inspection
②Daily during Dry Season
EST* During construction
Under Environmental Management and Environmental Monitoring Cost
Water Pollution ①Site Inspection (Construction Site and Worker’s Camp)
①Monthly EST During construction
Waste ①Site Inspection (Construction
Site and Worker’s Camp)
①Monthly EST During construction
Noise and Vibration
①②Site Inspection
(Construction Site)
①②Monthly EST During construction
Natural Environment Flora, Fauna and Biodiversity
①②Site Inspection
(Construction Site and Worker’s Camp)
①②Monthly EST During construction
Under Environmental Management and Environmental Monitoring CostTopography
and Geographical Features
①Site Inspection (Construction Site)
①Monthly EST During construction
Social Environment Involuntary Resettlement
①Site Inspection (Construction Site)
①Monthly (weekly during disbursement of compensation)
EST Before commencement of construction
Under Environmental Management and Environmental Monitoring Cost
Vulnerable (poor households)
①Site Inspection (Construction Site)
①Monthly (weekly during disbursement of compensation)
EST Before commencement of construction
Indigenous and Ethnic Minority
①Site Inspection (Construction Site)
①Monthly EST During pre-construction/ construction
Land Use and Utilization of Local Resources
①Site Inspection (Construction Site)
①Monthly EST Before commencement of construction
Landscape ①②Site Inspection (Construction Site)
①②Monthly EST During construction
Communicable Diseases such as HIV/AIDS
①Number of Trainings
②Site Inspection (Construction
Site)
①Every six months
②Monthly
EST During construction
Working Environment (includes work safety)
①Number of Trainings
②Site Inspection (Construction Site)
①Every six months
②Monthly
EST During construction
Others Accidents ①Number of Trainings ①Every six months EST During
construction Under Environmental Management and Environmental Monitoring Cost
* EST: Environmental and Social Team at the Project Office of Poring-1 Mini Hydropower Plant/Poring-2 Mini Hydropower Plant
Final Report
Preparatory Survey on North Sumatra Mini 7-57 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Operation Phase (implemented by JDG Poring/JDG Cianten) Potential Impact
Parameter to be Monitored Measurement and
Frequency Implementation Schedule Cost
Pollution Control Soil Contamination
①Site Inspection ①Daily During operation Under operation and maintenance cost
Source: JICA Survey Team
7.7.3 IMPLEMENTATION SCHEDULE
(1) Pre-construction Phase
1) Establishment of Livelihood Restoration Committee
A livelihood restoration committee shall be established in order to deal with issues such as compensation
and assistance. It will enhance harmonious consensus on compensation and assistance between the
project-affected persons (PAPs)/affected community and the project office.
The livelihood restoration committee will act as grievance redress committee as well. Any complaints
from the affected community and PAPs related to the construction and construction activities of the
Poring-1 Mini Hydropower Plant shall be dealt in the committee.
2) Detailed Measurement Survey (DMS)
After obtaining IPPKH (Forest Area Usage License), a DMS must be undertaken in order to a) finalize
the affected land and its users (PAPs) and b) finalize the affected structure and its owner in collaboration
with PAPS and local authorities.
3) Socialization to Finalize Compensation and Assistance
After confirming the affected land and its users, entitlement of compensation and assistance to PAPs and
affected community shall be finalized by conducing socialization through livelihood restoration
committee and consultation with PAPs. It is necessary to have the opportunity of socialization and
consultation as many times as possible for achieving consensus among stakeholders.
4) Finalization of the Draft LAP
With the outcome of the DMS, accurate scope of impacts (name and quantities of affected assets) will be
identified and detailed compensation rates and rehabilitation measures will be prepared. With the
information incorporated, the draft LAP shall be finalized.
5) Signing of Compensation Contracts and Payment of Compensation to PAPs
The final step in the land acquisition implementation process is the signing of compensation contracts and
delivery of payments to PAPs. This step should be completed prior to the commencement of construction
activities.
(2) Construction Phase
Most of the tasks in the LAP will be completed during the pre-construction phase. When conducting
monitoring activities based on IEE during the construction phase, AHHs who need any support resulting
Final Report
Preparatory Survey on North Sumatra Mini 7-58 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
from the land acquisition will be assisted.
(3) Operation Phase
Environmental monitoring activities will be undertaken by the operation and maintenance department
under Poring-1 Mini Hydropower Plant/Poring-2 Mini Hydropower Plant. The LAP shall end at the
completion of construction. Activity on social considerations will be implemented continuously under the
scheme of CSR.
Implementation schedule is summarized in Figure 7.7.1.
- Component 1: Hydropower Plants
- Component 2: Transmission Lines
Source: JICA Survey Team
Figure 7.7.1 Implementation Schedule
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4
Establish Livelihood RestorationCommittee (Grievance Redress ▼Detailed Measurement Survey
Socialization on finalize compensationand assistance
Finalize Land Acquisiiton Plan
Compensation and Land Acquisition
Environmental Monitoring by EST
Enviornmental Monitoirng by Operation andMaintenance Department(CSR Activities by EST)
Operation Phase
2019
Construction Phase
Pre-Construction Phase
Year (per calendar year)2015 2017 20182016
Road Upgrade (5months) Main Works (22
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4
Establish Livelihood Restoration Committee(Grievance Redress Committee) ▼Detailed Measurement Survey
Socialization on finalize compensation andassistance
Finalize Land Acquisition Plan
Compensation and Land Acquisition
Environmental Monitoring by EST
Environmental Monitoring by Operationand Maintenance Department(CSR Activities by EST)
Operation Phase
2019
Construction Phase
Pre-Construction Phase
Year (per calendar year)2015 2017 20182016
Main Works (22 months)
Final Report
Preparatory Survey on North Sumatra Mini 7-59 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
7.8 STAKEHOLDER MEETING
Throughout the IEE process, formal and informal consultations were undertaken with key stakeholders,
including central and local government officials and persons and communities in the project area. The
primary objective of the stakeholder consultation is to provide information on the project such as purpose
of the project, layout of the project, schedule and method of construction and the likely environmental
and social impacts of the project construction and operation. In addition, environmental and social
information on the project area throughout the meetings and public concerns about the project are to be
collected. In particular, since the project will entail land acquisition, a series of public consultation
meeting (PCM) has been conducted for PHS in the project area.
The summary of focused group meeting on fish and fishery is shown in Table 7.8.1. The outcomes of the
PCM are shown in Table 7.8.2. Information obtained from administrative bodies as well as opinions
collected from the individual and public consultation meetings are reflected on the LAP development
process.
Table 7.8.1 Summary of Focused Group Meeting No Requested Assistance for Community Development Responses
1 Enhance rural development for the progress of villager’s living standards
Community infrastructure will be improved as a part of assistance
2 Give the priority for local people to be a worker of this project in the construction and operational phases
Local people, in particular PAHs will be prioritized to be employed as much as possible in a construction and operation phase
2 Improve the domestic water supply for villagers in two affected village, and improving the condition of public bathing and public toilet.
Improving domestic water supply and public bating and public toilet will be one of the option for community infrastructure improvement
3 Improve the infrastructure such as improvement of public road, bridges (between Limus sub-village in Siantar Naipospos Village and electrification
Improvement of public road will be realized as a part of project.
4 Improve crop yields of frankincense/benzoin Providing skill improvement as a part of livelihood restoration plan for the PAHs
Opinion (comment, recommendation etc)
1
This project help this village to make improvement for social and public facilities and make it equal for each sub village, it is better to avoid social jealousy among villagers who lives in each sub village in the village.
Information on the project will be disseminated transparently
2 Make some training for housewives in order to make economic business to assist the economic life of the family
Providing skill improvement as a part of livelihood restoration plan for the PAHs
3 Start this project as soon as possible and not make survey only.
After obtaining financial assurance, the project will be realized ASAP
4 This project is the positive impact for this village. -
5 If there is affected agricultural land for this project, it has to be fair for compensation process.
Information on the project will be disseminated transparently
6 Help for the procurement of additional teachers to school in our village
It will be considered as a one of option for the affected community development in an operation phase
Source: JICA Survey Team
Final Report
Preparatory Survey on North Sumatra Mini 7-60 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Table 7.8.2 Summary of Public Consultation Meetings Date Location Target No. of Attendees Remarks/Requests Responses 17 Sept. 2015 Time 9:00-11:30
Office Hall in Carmat Tarutung Office
Officials -Tatutun Subdistrict -Villages --Hutatorian Vlll --Aek Sian Simun - -Hutatoruan lll - -Parbubu 1 - -Hutatoruan 1, -PAHs
- 71 participants:
- 48 PAHs - 7 Villagers - 16 Officials
- PAHs agreed and supported these projects, they requested information about the compensation on land and plants/agriculture.
- The company must think about the
safety of the people around the transmission lines.
- Precise identification of PAHs will be needed for the final database of affected land and plants/agriculture
- Compensation process will be implemented by using “pago-pago (compensation to be set in the negotiation in the Toba Batak)”
- Price of compensation will be based on the market price of the land. The price of plants from government is just a basis for negotiation and it will be finalized through the negotiation.
- Compensation given to PAHs will be either by cash or bank transfer.
- Priority of employment at the site has to be given to the local people in the project area, especially for the member of PAHs whose age is older than 16 years olds (the age after finishing compulsory education)
- CSR activities will be provided to the villages according to the capability of the company
- Safety measures at construction
sites will be duly applied
18 Sept. 2015 Time 11:00 – 13:30
HKBP Church in Lobu Haminjon Subvillage (Siantar Naipospos Village)
Officials - Adian Koting Subdistrict - Villages -- Siantar Naipospos
- 64 participants for Poring-1 and Poring-2 Mini Hydropower Plants:
- 31 PAHs - 28 Villagers- 5 Officials
- 15 PAHs for transmission lines
- Support these projects as long as these projects do not make people worse off.
- This project has to give priority to the villagers as workers, especially for the PAHs.
- This project has to give advantage to the villagers in Siantar Naipospos Village.
- Worry if the headrace is near the settlement area.
- Villagers in Siantar Naipospos are
asking for electrification because they do not have electricity until today.
- Compensation processes need to be transparent and directly negotiate to the project owner on land and plant/agriculture.
- The final survey for PAHs has to be very detailed.
- If the company needs a partner for
business, the company has to give priority to local entrepreneurship
- Priority of employment at the site has to be given to the local people in the project area, especially for the member of PAHs whose age is older than 16 years olds (the age after finishing compulsory education)
- Layout of the headrace near the settlement area will designed dully considering the safety of settlement area
- Electrification will be difficult since it need approval from PLN, however, infrastructure in the affected community will be improved by the project
- This project can help improve some infrastructure by CSR program in an operation phase as well
- Compensation process will be implemented by using “pago-pago (compensation to be set in the negotiation in the Toba Batak)”
- Detailed measurement survey will be conducted in further phase (detailed desing phase)
- Priority of employment at the site
has to be given to the local people in the project area, especially for
Final Report
Preparatory Survey on North Sumatra Mini 7-61 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Date Location Target No. of Attendees Remarks/Requests Responses first.
- Anticipate any negative impact to the community and increase its positive impact.
the member of PAHs whose age is older than 16 years olds (the age after finishing compulsory education)
18 Sept. 2013 Time 14:00 – 16:30
HKBP Church in Torhonas Subvillage (Pardomuan Nauli Village)
Officials - Adian Koting Subdistrict -- Pardomuan Nauli
- 6 participants for Poring-1 and Poring-2 Mini Hydropower Plants: All of them are PAHs.
- 78 participants for transmission line:
- 55 PAHs - 17 Villagers- 6 Officials
- Support this project to be started as soon as possible.
- The land is an inheritance from one
generation to another, but no land certificate is available. They asked this situation to the project owner.
- This project should give priority to
local labor from the village if the development activities are in this village.
- Compensation processes have to
involve the PAHs and negotiate directly to the project owner on the land and plant/agriculture, and no fees for the PAHs.
- After the measurement, if the land
owned by the community is left with very little area, then the public suggested that the company has to buy it wholly because it would not be beneficial for them to use it for agriculture if the remaining land is very small.
- The company has to improve some
infrastructure and developed the village by CSR program.
- If the status of the land is a
production forest (government land) or limited production forest (government land), the company has to pay the government for rental fee, and the local people who cultivated the land for compensation. The compensation rate will be set through the “pago-pago” processes.
- Priority of employment at the site has to be given to the local people in the project area, especially for the member of PAHs whose age is older than 16 years olds (the age after finishing compulsory education)
- Compensation process will be implemented by using “pago-pago (compensation to be set in the negotiation in the Toba Batak)”
- During the estimation of the compensation, this issue will be take for granted
- Affected community infrastructure will be improved as a part of assistance for affected community in a construction phase as well as operation phase by CSR program
19 Sept 2015 Time 11:00- 13:30
HKBP Church in Pansurbatu Village
Officials - Adian Koting Subdistrict Villages -- Pansurbatu -- Pansurbatu 2
56 participants: - 30 PAHs - 19 Villagers - 7 Officials
- Participants asked about the status of the land (government land) since there are no land certificates.
- There are some worries if they will
agree to give their land to this company; the company that will manage the land in the future is a mine company and not for micro power plants.
- Participants asked for a transparent
compensation process, and to directly negotiate with the project owner on land and plant/agriculture.
- Identification of PAHs should be made for the final compensation process and there are no fees or cutting the number of payments; they asked to directly give the money to the PAHs by cash or bank transfer.
- The company will not make people lose their rights for .using the land (government land)
- The land will be used only for mini hydropower plant
- Compensation process will be
implemented by using “pago-pago (compensation to be set in the negotiation in the Toba Batak)”
- Identification of PAHs will be finalized in conducting detailed measurement survey in a further phase and there will be no fee to be asked for. The compensation money will be paid by cash or bank transfer.
Final Report
Preparatory Survey on North Sumatra Mini 7-62 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
Date Location Target No. of Attendees Remarks/Requests Responses
- Safety of transmission line was asked.
- Participants demanded honesty regarding the negative and positive effects of the project, as well as honesty in the compensation process.
- There are no negative impacts for
people if they work under the transmission lines, because it is 33 kV. (low voltage)
- Information on the project will be disseminated transparently
Pending - Siatal Barita Subdistrict Villages -Siraja Hutagalung - Simorangkir Julu
- After obtaining the official letter from Bupati (North Tapanuli District Office), PCM has to be organized.
Source: JICA Survey Team
7.9 ESTIMATION OF REDUCTION OF GREENHOUSE GAS
Hydropower generation utilizes hydraulics potential energy for power generation without producing
greenhouse gas (GHG) and is considered as renewable energy. Development and introduction of a new
hydropower station into the power system which includes thermal power generation using fossil fuels can
directly contribute to reduce the GHG emission reduction. In this analysis, GHG reduction by Poring-1
and Poring-2 mini hydropower development is estimated.
The method to estimate the GHG reduction is introduced in “Methodological Tool: Tool to calculate the
emission factor for an electricity system” prepared within the framework convention on climate change
by the United Nations. The method is adopted as the method to calculate the GHG emission reduction for
clean development mechanism also known as CDM.
According to the method, the GHG emission reduction by a hydropower plant is calculated by the
following equation:
ERy = BEy – PEy - LEy
BEy = EGBL,y * EF CO2, grid, y
Where, ERy : GHG emission reduction in year y (t CO2/year)
BEy : GHG emission by substituted power plant in year y (Baseline emission) (t CO2)
PEy : GHG emission by the hydropower plant in year y (t CO2)
LEy : Leakage GHG emission of the hydropower plant in year y (t CO2)
EGBL,y : Annual electrical energy supplied to the grid by the hydropower plant (MWh)
EF CO2, grid, y : Combined margin grid emission factor in year y (t CO2/MWh)
The emission factor is obtained by the weighted average of build margin and operation margin. The
Indonesian National Commission on CDM released the grid emission factor of Sumatra Island until year
2012, and the value is 0.686 (t CO2/MWh). The leakage GHG and GHG emission by the hydropower
plant is negligibly small, and therefore assumed to be zero.
The annual electrical energy productions of Poring-1 and Poring-2 mini hydropower stations are 69.1
GWh/year and 75.3 GWh/year, respectively. Total loss of energy from the power plant to the receiving
Final Report
Preparatory Survey on North Sumatra Mini 7-63 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
point of Tarutung Substation is estimated at 13.7%. Therefore, the annual power generation amounts
supplied to the grid by Poring-1 and Poring -2 mini hydropower stations are estimated to be 59.6
GWh/year and 65.0 GWh/year, respectively. Accordingly, the GHG emission reduction for the above
annual power generation is estimated as follows:
Poring-1 Mini Hydropower Station : 40,885.6 t CO2/year
Poring-2 Mini Hydropower Station : 44,590.0 t CO2/year
7.10 CONCLUSIONS AND RECOMMENDATIONS
7.10.1 CONCLUSIONS
After conducting the IEE by examining the available data, hearing with stakeholders, carrying out site
reconnaissance, conducting site survey and laboratory analysis, it is concluded that no significant negative
impact was predicted and the predicted impacts could be avoided or minimized by applying
countermeasures.
As for Component 1 (Hydropower Plants), the main negative impacts will be temporary and site-specific
pollution such as air pollution, water pollution, waste generation, and noise and vibration due to
construction activities during the construction phase. In addition, fish resources and fishery will be
affected due to the diversion of water from the Poring River to the headrace channels for about 5 km
section from the Poring-1 Intake Weir to the Poring-2 Powerhouse during the operation phase.
Similar to Component 1, the main negative impacts of Component 2 (Transmission Lines) will be
temporary and site-specific pollution such as air pollution, water pollution, waste generation, and noise
and vibration due to construction activities during the construction phase.
Effort was made to avoid any resettlement due to the construction of the project facilities for both
Component 1 and Component 2. Consequently, there will be no resettlement resulting from constructing
the project facilities.
7.10.2 RECOMMENDATIONS
The following are the procedures to be taken in the further project phases:
Obtain approval for UKL-UPL: The UKL-UPL on transmission lines of Poring-1 and Poring-2
which is now under review at Bupati needs to be approved.
Organize public consultation meeting (PCM): The PCM at Siatal Barita Subdistrict is now pending.
After obtaining an official letter from Bupati (North Tabanuli District Office), the PCM shall be
organized to explain the result of IEE as well as the LAP to affected community and PAPs.
Establish a livelihood restoration committee: A livelihood restoration committee shall be established
in the affected community in order to deal with issues such as compensation and assistances.
Finalize the land acquisition plan (LAP): The information on the affected land and its users and
affected structure and its users identified after DMS shall be incorporated into the draft LAP for
Final Report
Preparatory Survey on North Sumatra Mini 7-64 Nippon Koei Co., Ltd. Hydropower Project (PPP Infrastructure Project)
finalization.
Organize socialization: It is necessary to have opportunity of socialization and consultation as many
times as possible for achieving consensus among stakeholders on compensation, assistances or any
issues related to the construction before the construction phase.
Enhance community development: It is recommended that social considerations will be continuously
given to the affected community during the operation phase by using the CSR scheme.