Report to the Strategic Development Committee
Ronald Reagan Washington National Airport Capital Construction Program
January 2017
Secure National Hall
Secure National Hall
Project Cost Summary
Total Expenditures $ 10,366,610
Total Budget $ 237,524,197
Total Forecast $ 237,524,197
Secure National Hall
Schedule Activities
Design Development
Secure National Hall Design Package 90% Design 23 Dec 2016
Blast Assessment – Draft Report 23 Dec 2016
Construction
Notice to Proceed Spring 2017
Completion Fall 2020
Secure National Hall
Construction Phasing
• Construction phasing workshops are on-going with the Construction Manager
at Risk (CMAR) Contractor, Design Consultant, and MWAA stakeholders to
develop the construction sequence for the Secure National Hall Project.
• Maintenance of Traffic (MOT) Coordination plans for the Departures and
Arrivals’ roadways are being developed in anticipation of the construction of
the Exterior Work of the new Security Screening Checkpoints.
• Internal Phasing (National Hall, Public Circulation Areas, ticketing level, and
Metro Bridges) is being developed for the interior construction.
• Collaboration with A/E, CMAR Contractor, Airlines and various MWAA
stakeholders to identify and mitigate impacts to operations, airlines and
travelling public is underway.
• MOT/Internal Phasing planning is ongoing to maintain target completion of
Fall 2020.
New North Concourse
New North Concourse
Project Cost Summary
Total Expenditures $ 6,726,806
Total Budget $ 380,898,607
Total Forecast $ 380,898,607
New North Concourse Schedule Activities
Design Development
Demolition of Hangars 11 & 12; Corporate Office Building
(Package #2A) – 100% Design
16 Dec 2016
Apron Paving, Utilities and Hydrant Fueling
(Package #2B) – 60% Design
21 Nov 2016
Concourse Construction
(Package #3) – 30% Design
20 Jan 2017
Construction Procurement
Lot K and Airfield Area A Reconfiguration (Package #1) On-Going
Construction
Notice To Proceed (Package #1) January 2017
Completion Summer 2021
Enabling Projects
• Transportation Network Company (TNC) Lot
– TNC Lot temporarily shifted to Crystal City
– Hangars 11/12 Parking shifted to former TNC Lot
• COB Relocation
– Tenant Space Completion: March 23
– Employee Relocation: March 24 – April 6
• Parking Changes (Supporting Lot K Construction)
– Close Hangars 11/12 Parking: Completed
– Close Lot K Parking: Week of January 9
• Others
– Central Utility Plant Modification Construction Award: February 17
Turner Outreach Program
• Training and Apprenticeship Programs - Partnering with Community
Hub for Opportunities in Construction Employment (C.H.O.I.C.E), a
pre-apprenticeship program to be hosted late January 2017/early
February 2017.
• LDBE Subcontracting and Training Programs - Turner School of
Construction Management in conjunction with Georgetown
University and Project 500 - Classes to commence February
28. Outreach will begin the week of January 20.
• LDBE Mentor/Protégé Program – Quarterly meeting scheduled for
February 2017 with MWAA Office of Supplier Diversity. Draft
agenda to be submitted.
• Career Outreach Program - Recruitment of summer college interns
to begin first quarter of 2017.
• Veterans Program - Ongoing
• Community Hotline/Project Website - Ongoing
Regional Construction Outlook
8.09.0
10.011.012.013.014.015.016.0
Ja
n-0
6
Jul-0
6
Ja
n-0
7
Jul-0
7
Ja
n-0
8
Jul-0
8
Ja
n-0
9
Jul-0
9
Ja
n-1
0
Jul-1
0
Ja
n-1
1
Jul-1
1
Ja
n-1
2
Jul-1
2
Ja
n-1
3
Jul-1
3
Ja
n-1
4
Jul-1
4
Ja
n-1
5
Jul-1
5
Ja
n-1
6
Jul-1
6
DC Construction Employment, (in 10,000s)
• Construction activity was near
10-year high for 2016.
• Forecasts are showing an
increase in construction
projects in the DC/MD/VA
region for the next several
years.
• Market remains busy with
backlog of projects.