Report of Solar Efficiency

& Facilities Update

Overview

• California Community Colleges Climate Change & Sustainability Policy

• Solar Projects Overview

• Solar Production

• Costs & Savings

• Sustainability Plans & Ideas

California Community Colleges Climate Change & Sustainability Policy

Climate Change & Sustainability Goals 2025 2030

1) Reduce greenhouse gas emission to ______ below 1990 levels. 30% 40%

2) Increase renewable energy consumption to _______. 25% 50%

3) _____ of fleet vehicles are zero-emission vehicles. 25% 50%

4) _____ of all new buildings and major renovations will be constructed as Zero Net Energy. 50% 100%

5) _______ of all new buildings and major renovations will achieve at least a Leadership in Energy and Environmental Design (LEED) “Silver” or equivalent rating.

50% 100%

6) Increase procurement of sustainable products and services by ________ of current levels. 20% 25%

7) Reduce municipal solid waste by ______ compared to current levels. 25% 50%

2019 CALGreen Code: Provide shade over 50% of all parking areas within 15 years

Solar Projects Overview

• 2013o District began research for solar project possibilities for Visalia & Tulare Campuses

o District signed an agreement with the Community College League of California (CCLC) for solar consulting services

• 2015o District released a RFQ/P for a design-build solar energy project

o Contract awarded to Borrego Solar Systems, Inc.

o Total Cost: $3M

o 0% interest, 17-year loan through the California Energy Commission

o $175,357/year

o September/November 2015 – Project installations complete & production began

Solar Project – Visalia Campus• Fixed-Tile Carport/Shade Solar Structure, 285 kW• Parking Lot 7, covers 104 general spaces and 3 ADA

spaces • Connection Date - November 6, 2015

Solar Production Summary - Visalia

2019 2020

http://s35356.mini.alsoenergy.com/Dashboard/AlsoEnergyDownload/2a566973506557724642304b772b71633d

Solar Project – Tulare Campus• Ground Mount, Single-Axis Tracking

Solar System, 633 kW • South of Building C, just north of M&O

Building and farm complex parking • Connection Date - September 9, 2015

Solar Production Summary - Tulare

2019 2020

http://s35693.mini.alsoenergy.com/Dashboard/AlsoEnergyDownload/2a5669735065572f4a416

Other Contract Terms

• Maintenance and Operations (Bi-Annual)

o Mechanical, Electrical, Rack System, Vegetation, Monitoringo $7,800.00/per year + 2% annually

o Module Cleaningo $6,137.00/per year + 2% annually

• Output Guarantee Agreement

o 25-year guarantee providing the District with 99% solar production

• True-Up Payment Analysis

o Conducted every 3-years

o 2018 true-up $47,314.02 (paid Spring 2019)

True-Up Payment Overview• 2018 True-Up Payment Analysis

o Visalia: Output/generation has met or exceeded cost savings guarantee per contracto $22,890.28

o Tulare: Output/generation has been lower than expectedo $(70,204.30)

o Total True-Up Paymento $47,314.02

• Corrective Actiono Borrego recommended an adjustment for the Tulare system equipment to be stowed at a 45-degree tilt

overnight versus the horizontal tilt the system has been utilizing since startupo Borrego believes the change in tilt will reduce soiling losses when the panels have dirt build up

• Next True-Up Payment Analysiso November 2021

Other Solar/Energy Savings

• California Solar Incentive Rebates – 5 Years (Southern California Edison)

FY 16 $118,374.73 FY 19 $137,637.60

FY 17 $113,623.93 FY 20 $137,637.60

FY 18 $180,914.28

Total = $688,188.14

• Direct Access – Constellation NewEnergy, Inc.o Third party electrical service provider, producing electricity at a discounted rate, locked in for multiple years through

California Direct Access Program

o FY 2020 Direct Access Estimated Savings

o $133,677.00

• SCE – Enersponse Programo Utility reduction request (HVAC temps/lighting)

o Average $7,000/year

Solar Project Cost/Savings Update

Year of Solar PV Operation

Benefit: Avoided

Electricity Costs

Benefit: California Solar

Program Incentives

Cost: Operations and Maintenance

Cost: Principal Payments on

CEC Loan

Annual Net General Fund

Benefit

Cumulative General Fund

Benefit

Year 12016

$276,872 $167,717 $(13,937) $(177,388) $253,264 $253,264

Year 2 2017

$287,233 $127,132 $(14,216) $(175,357) $224,792 $478,056

Year 32018

$265,907 $118,063 $(14,500) $(175,357) $194,113 $672,169

Year 42019

$270,560 $137,637 $(14,790) $(175,357) $218,050 $890,219

Year 52020

$277,283 $148,187 $(15,086) $(175,357) $235,027 $1,125,246

Sustainability Plans & Ideas • Current & Past Practice

o Continue to upgrade HVAC, lighting systems when doing district-wide remodelso Capital construction, implement California sustainability goals in the planning/design of the

Educational Support Services Building

• Energy Conservation & Energy Efficiency Services RFQo Compass Energy Solutionso Energy Audit started in September 2020o Firm to identify energy efficiency projects to maximize and assist with compliance with the California

Community College Sustainability Policy

• Future Plans & Ideaso Compliance with California Community College Sustainability Policyo Maximize district one-time funding and/or potential future bond funding to implement energy savings

projects resulting in general fund savingso Target Locations: Visalia and Hanford Campuses

COVID-19 Sanitation and Response Plan

• PPE distributiono Masks, gloves, sanitizer spray/microfiber cloths, disinfecting wipes, hand sanitizer

dispensers

• Awareness/wayfinding signage

• Disinfecting (using GenEon fogger)o Classrooms immediately following each session (orange/blue signage)

o Offices and public areas nightly and upon request

• Exposure mitigationo Building/area vacated for 2 days, 24-hour ‘flush’ of 100% outside air, disinfecting (fog) by

custodial staff 2x daily

GenEon Disinfectant

• What is hypochlorous acid?o Nature’s oldest disinfectant.

o Ingredient that gives bleach its microbial power.

o Same substance your white blood cells produce to fight off infections.

o Eliminates all bacteria, mycrobacteria, spores, fungi and viruses within seconds (COVID-19 within 3 minutes).

o 80-200x more effective than bleach and is 100% safe.

o “Rain” in the produce section at your local grocery store.

Indoor Air Quality

• Filtrationo Ultraviolet (UV) lighting installed in all air handlers

tied to chiller systems.

o iWave technology (bionic ionization) installed in all package units.

o Minimum MERV 13 in all buildings.

• Fresh Airo Energy management system (EMS) allows for

economizers to control fresh air intake.

UV Lighting

iWave

Project Updates

• Kern 738 Faculty Office Suite Modernizationo Dec 2019 – Aug 2020

BEFORE AFTER

• Kern 738 Faculty Office Suite Modernizationo Dec 2019 – Aug 2020

BEFORE AFTER

• San Joaquin & Yokut Classroom Modernizationo April – June 2020

BEFORE

• San Joaquin & Yokut Classroom Modernizationo April – June 2020

AFTER

• Moro Gym Acoustical Paneling Repairso June – July 2020

BEFORE AFTER

• Ponderosa & Sawtooth 326 Seating Upgradeso Aug 2020

BEFORE AFTER

• Moro Gym Restroom Modernizationso Aug 2020 – Jan 2021

BEFORE PROGRESS

• Sequoia Roofing Resealo June – Sept 2020

BEFORE AFTER

• Nursing Simulation Lab Remodelo June – Sept 2020

CONTROL ROOM VIEW INTO SIM LAB

• Mooney (South) Sidewalk Replacemento Nov 2020

BEFORE AFTER

• Baseball Field Fencing Replacemento Nov 2020

AFTER

• Cedar 424 Classroom Remodelo July – Dec 2020

PROGRESS AFTER

• Cedar 421 Classroom Remodelo July 2020 – Mar 2021

BEFORE PROGRESS

• Kern 738 Language Lab Remodelo Aug 2020 – Jan 2021

BEFORE PROGRESS

• Food Court Remodelo Nov 2020 – Apr 2021

PROGRESS

• Hanford Quad Expansiono Mar – June 2021

CONCEPTUAL SITE PLAN ENLARGED PLAN

• Track/Field Modernizationo June – July 2021

EXISTING

• Educational Support Serviceso We’re right on schedule…o Pre-construction prep:

o Building vacated Oct 2020.o Haz-mat abatement completed Dec

2020.o Primary electrical “stub out”

completed Dec 2020.

o DSA comments addressed and resubmitted 12/23/2020.

o DSA approval expected late Jan 2021.

o Formal bid 6-8 weeks in Feb/Mar 2021.

o Award in Apr 2021.o Construction June 2021 – Jan 2023.