Repairing Spalled Reinforced Concrete using PatchPins METHOD STATEMENT Specification Notes The following criteria are to be used unless specified otherwise: A. Pilot hole diameter to be 6.5mm B. Pilot hole depth to be 2” C. Pin spacing and position can be varied according to site conditions D. Pins are to be installed approx. 2” from the edge of the patched area E. Intermediate pins should be at 6” – 8” centers. Extra pins may be used at the discretion of the engineer / site manager. F. There should be a minimum of two pins per patch. G. The outer end of installed pins must be below the face of the concrete patch. To ensure this occurs pins may be bent as required. The above specification notes are for general guidance only and Helifix reserves the right to amend details/notes as necessary. 1. Remove all loose concrete from the area to be patched. Hammer tap the area to establish if any hollows are present and break back to sound concrete. Remove any dust and debris with a stiff wire brush. Clean and treat any exposed steel rebar with a suitable coating, e.g. epoxy or zinc paint. For drilling pilot hole ................................SDS rotary hammer drill 650w/700w For installing PatchPin................PatchPin support tool with SDS rotary hammer drill 650w/700w set on hammer only RECOMMENDED TOOLING RT23 If your application differs from this repair detail or you require specific advice on your particular project, call Helifix toll free on 888-992-9989. Our Technical Department can provide you with a full support service including: Advice, assistance and recommendations on all structural repair matters Devising and preparing complete repair proposals for specific situations GENERAL NOTES 1 2 3 4 2. Drill pilot holes, vertically or at an angle of up to 45°, to the correct diameter and spacing into the concrete (using an SDS rotary hammer drill). 3. Fit the PatchPin support tool over the drill bit and insert the PatchPin into the tool. Install the PatchPin into the pilot hole with the SDS rotary hammer drill set to hammer only. Ensure that the outer end of the pin is below the face of the concrete patch – the pin can be bent, if required. 4. Apply the patching mortar, as required, in accordance with the manufacturers instructions. Fill all gaps and make good the surface. www.helifix.com A division of HALFEN USA Inc. P.O. Box 547 Converse, TX 78109 [email protected] Toll Free: 888-992-9989 Fax: 877-683-4910

Repairing Spalled Reinforced Concrete using PatchPins · Repairing Spalled Reinforced Concrete using PatchPins METHOD STATEMENT Specification Notes The following criteria are to be

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Repairing Spalled Reinforced Concrete using PatchPins · Repairing Spalled Reinforced Concrete using PatchPins METHOD STATEMENT Specification Notes The following criteria are to be

Repairing Spalled Reinforced Concrete using PatchPins

METHOD STATEMENT

Specification Notes

The following criteria are to be used unless specified otherwise:

A. Pilot hole diameter to be 6.5mm

B. Pilot hole depth to be 2”

C. Pin spacing and position can be varied according to site conditions

D. Pins are to be installed approx. 2” from the edge of the patched area

E. Intermediate pins should be at 6” – 8” centers. Extra pins may be used atthe discretion of the engineer / site manager.

F. There should be a minimum of two pins per patch.

G. The outer end of installed pins must be below the face of the concretepatch. To ensure this occurs pins may be bent as required.

The above specification notes are for general guidance only and Helifix reservesthe right to amend details/notes as necessary.

1. Remove all loose concrete from the area to be patched. Hammer tapthe area to establish if any hollows are present and break back tosound concrete. Remove any dust and debris with a sti� wire brush.Clean and treat any exposed steel rebar with a suitable coating, e.g.epoxy or zinc paint.

For drilling pilot hole ................................SDS rotary hammer drill 650w/700wFor installing PatchPin................PatchPin support tool with SDS rotary hammer

drill 650w/700w set on hammer only

RECOMMENDED TOOLING

RT23

If your application di�ers from this repair detail or you requirespeci�c advice on your particular project, call Heli�x toll free on888-992-9989. Our Technical Department can provide you with afull support service including:

Advice, assistance and recommendations on all structuralrepair mattersDevising and preparing complete repair proposals for speci�csituations

GENERAL NOTES

1

2

3

4

2. Drill pilot holes, vertically or at an angle of up to 45°, to the correctdiameter and spacing into the concrete (using an SDS rotary hammerdrill).

3. Fit the PatchPin support tool over the drill bit and insert the PatchPininto the tool. Install the PatchPin into the pilot hole with the SDSrotary hammer drill set to hammer only. Ensure that the outer end ofthe pin is below the face of the concrete patch – the pin can be bent,if required.

4. Apply the patching mortar, as required, in accordance with themanufacturers instructions. Fill all gaps and make good the surface.