Upload
colin-mccoy
View
212
Download
0
Embed Size (px)
Citation preview
OPTIMIZING GENERATION
Remarks of R.P. SinghCMD, SJVN Limited
17th INDIA POWER FORUM
14th November, 2014
Power Scenario in India & Neighboring Countries
All India Installed Capacity (As on 30th September, 2014)
Sector Installed Capacity (MW) % Share
Thermal 1,76,778 69.6
Hydro 40799 16.05
Nuclear 4,780 1.85
RES 31692 12.5
Total 254049
Source:- CEA Report
Power Scenario in India & Neighboring Countries
Estimated Demand & Generation Projection in India by 2050
Year Peak Demand Requirement (GW)
Installed Capacity Requirement (GW)
2016-17 200 271
2021-22 283 372
2026-27 401 528
2031-32 542 712
2036-37 644 882
2046-47 844 1258
2050 896 1388
Source:- Dessert Power India 20250 Report
Power Scenario in India & Neighboring Countries(- Contd-)
Status of Hydro Power Development in India (As on 30th September,2014 )
Status Capacity (MW)
Hydro Potential Available 148701
Under Operation 40799*
Under Construction 13207
Potential yet to explore 96100
% of Potential harnessed ( Operation + construction)
34 %
• Including Small/Mini Hydro PlantsSource:- CEA Report
Power Scenario in India & Neighboring Countries(- Contd-)
% Share of sectors in All India Hydro Power Installed Capacity (As on 30.09.2014)
Sector Installed Capacity (MW) % Share
Central 10623 26.03
State 27482 67.36
Private 2694 6.61
Total 40799
Source:- CEA Report
Power Scenario in India & Neighboring Countries(- Contd-)Status of Hydro Power Development in India - Opportunities
StatusCapacity (MW) > 25 MW
Arunachal Pradesh
Uttarakhand
Himachal Pradesh
Sikkim Karnataka Maharashtra
Hydro Potential
50064 17998 18540 4248 6459 3314
Under Operation
405 3426 8439 669 3585 2487
Under Construction
2854 1640 3085 2622 0 0
Yet to explore
46805 12932 7016 957 2874 827
% of potential explored
6.5 28 62 55 55 75
Source:- CEA Report
Kerala
3378
1881
100
1396
59
Power Scenario in India & Neighboring Countries(- Contd-)
Hydro Power Opportunities in Neighboring Countries:-
Status Capacity (MW)
Bhutan Nepal
Hydro Potential 30000(Technically feasible 23760 )
80000
Under Operation 1488 718
Under Construction 10064 4323
Yet to Explore 12208 74959
% of Potential explored 48 6
Challenges for Hydro Power Sector Land Acquision
Environmental Issues
Market Challenges:- Bidding process for hydro projects, difficulty in financing due to long gestation period
Technical Challenges: Natural Disasters of flood and landslides along with unexpected cavities, underground water springs (hot/cold) and a relatively fragile rock as Himalayas are young fold mountains.
Lack of Infrastructure:- Lack of communication facilities, Sub stations & Power Evacuation Network.
Clearance of DPR and approval of Investment decision
Long gestation period
Challenges for Hydro Power Sector-Contd-
Major slippage reasons for Hydro Projects
Delay in Preparation of DPR & MOU Signing
Delay in MOEF Clearances
Delay in Investment decision/Funds tie up constraints
Delay in Award of Works
Geological Surprises
Natural Calamity
R &R Issues
Court cases
Measures to Optimize the Hydro Power Generation
Optimization in Operation of Hydro Power Plants Hydro Plants need to operate at Overload Capacity available within design limit during high
flow season and/or during peak hrs.
Use of advance technologies e.g. Robotic based HVOF Coatings on underwater parts , Periodic Reservoir Flushing and specific arrangements at Dam to counter high silt in the river.
Use of latest Control schemes/up gradation of control system of old plants to achieve fast response characteristics e.g. FGMO/RGMO Mode of operation, SPS Schemes for improving grid security etc.
Result:-
Extra MU Extra MW Less Maintenance time Reduced cost of Maintenance Increased Plant Availability
2011-12 2012-13 2013-14 2014-15(up to 11th Nov)
5000
5500
6000
6500
7000
7500
8000
7610
6778
7192
5841
Gross Energy Generation (MU)
• The design energy generation capacity is 6,612 MU in a 90% dependable year
Measures to Optimize the Hydro Power Generation-Contd-
Nathpa Jhakri Hydro Power Station (1500 MW)
2011-12 2012-13 2013-14 2014-15(up to 11th
Nov)
60.00%
70.00%
80.00%
90.00%
100.00%
110.00%104.26% 105.15% 105.75%
108.29%
PAF ( NAPAF 90%)
Highest in the country
Measures to Optimize the Hydro Power Development
Regulatory Framework for Hydro Power Sector:-
• Revival of Mega Power Policy to allow the benefit of Excise Duty/Custom Duty on Equipments as well as Construction material (Steel, Cement etc) for the Hydro plants of Unit size more than 50-100 MW
• Possibility of Single Window clearance for all approvals required to set up a Hydro Power Plant.
• A Central Agency/ Govt. of India may be given the responsibility for preparation of DPR and obtaining all other statuary clearances before the allotment of project to developer for execution.
• Statuary clearance from the Environment, Forest and Wildlife point of view may be accorded on a speedy basis.
• Speedy approval of investment decision after the project has been allotted to the developer.
Improving Infrastructure of the Region Prior to Execution of Project:Roads, Rail Connectivity, Upgrading of the existing sub-stations, Basic Infrastructure for PAPs
Measures to Optimize the Hydro Power Development (Contd.)
Planning for Integrated River basin development approach:-
Project allocation procedure in line with integrated river basin development , Cascade /Tandem Projects should be allotted to same developer.
Development of Benefit sharing mechanism with PAPs for benefit of all stakeholders:- Provisions for the PAPs to establish an ownership in the project by offering suitable equity
participation at par as on the date of COD. Power evacuation Infrastructure:- Dedicated Transmission network may be created for Evacuation of Power from the North East
Region. Building Pooling substations in locations having concentration of hydro resources to reduce
project cost. Introduction of Hydro Power Purchase obligation in line with renewable sector.
Differential Tariff Structure consisting of Peak & Off-Peak Tariff
Introduction of incentive scheme for Operational Hydro Power Plants -- Black start up capability -- reactive power regulation -- measures to ensure grid security like SPS & FGMO/RGMO mode .
THANK YOU