Region al Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment of the milestones and targets (Art. 20 (4) of CPR) As amended after expert meeting on October 24, 2013 Veronica Gaffey & Jan Marek Ziółkowski Evaluation & European Semester Unit DG for Regional and Urban Policy 1 Cohesion Policy

Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Embed Size (px)

Citation preview

Page 1: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Regional PolicyRegional Policy

Draft Implementing Act

Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment of the milestones and targets (Art. 20 (4) of CPR)

As amended after expert meeting on October 24, 2013

Veronica Gaffey & Jan Marek ZiółkowskiEvaluation & European Semester Unit

DG for Regional and Urban Policy1

Cohesion Policy

Page 2: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

We have received comments from 16 Member States.

• Nearly 80% of comments concerned the draft Implementing Act.

• Among them, the main issues of concern were performance framework for complex priorities, indicators, milestones and targets, criteria for assessing their achievement, excluded resources and reserve, examples.

2

Page 3: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

Complex priorities (HU, LV and UK)

3

• For priorities which concern more than one Fund (ESF, ERDF or CF) or more than one category of region, indicators, their milestones and targets, and actual values have to be broken down by Fund or category of region.

• The representativeness of output indicators and achievement of milestones and targets are assessed independently for each Fund and each category of region within such a priority.

• The reserve is allocated and suspension of payments and financial corrections may be applied independently for each Fund and each category of region within such a priority.

• Examples (including example of priority with more than one TO, to be included in the Guidance on Performance Framework.

Page 4: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

Financial indicator (CZ, GR, LT and LV)

Comments Reply

Text on realistic and achievable milestone unclear (which years are concerned), moreover the automatic decommitment will be applied at the level of Fund or category of region for each programme.

The text has been revised; now it makes reference to the "total value of milestones set for the financial indicators under performance frameworks related to any ESI Fund or category of region" giving more flexibility (i.e. milestone for a particular financial indicator may be lower than N+3)

4

Page 5: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

Output indicators and key implementation steps (BG, CZ, DE, DK, HU, LV, PL, RO, UK)

Comments Reply

The ESF exception to use partially implemented operations for reporting against milestones and targets should apply as well to the ERDF and CF.

No legal base for ERDF/CF.

Many long-term interventions will not be completed by 2018, so key implementation steps will be widely used to supplement or complement output indicators.

Agree, option to do so has been foreseen in the Implementing Act

What is meant by “fully implemented operations”?A definition has been included in the Implementing Act.

Key implementation steps expressed as 0-1 not justified.

Agree, this option has been excluded.

Are key implementation steps used for targets or not?

They should not be used for targets.

5

Page 6: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

Milestones and targets (BE, DE and LU)

Comments Reply

Targets should be calculated without the reserve taken into account to limit the number of amendments.

Disagree, only if we assume all or majority of priorities fail to achieve their milestones.

Regular update Milestones and targets may be updated in line with Annex II of CPR.

6

Page 7: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

Criteria for assessing achievement (AT, BE, HU, LU, PL)

7

Comments Reply

Criteria for achieving milestone or target too strict compared to criteria for failing ('majority' instead of 'all'; 80% or 75% instead of 85%)

Disagree, different assessments at stake.

Weighted average should be used to assess attainment of milestone.

Disagree, too complicated and does not work if more than one indicator refers to the same allocation.

A financial indicator included in the performance framework should not be taken into account for assessing the attainment of milestone.

Disagree, it is an obligatory element of the performance framework.

Page 8: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

Excluded resources and reserve (CZ, EE, LT and PL)

Comments Reply

Can different priorities or objectives within the priority have different percentage of performance reserve to be allocated?

"The performance reserve shall constitute between [5 and 7] per cent of allocation to each priority within a programme with exception of priorities dedicated to technical assistance."

Will it be possible to re-allocate a part of reserve from unsuccessful priority to technical assistance?

No, TA priorities and programmes are not covered by the performance framework.

Will it be possible to allocate less than full reserve to underperforming, but important priorities or allocate the reserve conditionally?

No, the CPR gives no such possibility.

8

Page 9: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

Excluded resources and reserve (CZ, EE, LT and PL)

Comments Reply

Youth Employment Initiative

Covered by the performance framework, but excluded from the calculation of the reserve, so YEI takes no part in re-allocation of reserve. However, in the case of serious failure, a suspension of payments or financial correction are possible.

Technical Assistance

Taken into account to calculate the amount of reserve for a programme, but there will be no reserve for TA priorities, nor performance framework. Therefore, the TA priorities take no part in re-allocation of reserve and no suspension of payments or financial correction are possible (no serious failure).

9

Page 10: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Cohesion PolicyCohesion Policy

Examples and guidance (BG, CZ, DK, EE, FI, HU, LT, LV, PL, UK)

Several MS asked for guidance or examples in the following areas:• Documentation (what is to be included; any

formal requirements);• Priorities using financial instruments• Complex priorities• Consistency between programmes• Key implementation stepsThey will be provided in the updated Guidance document.

10

Page 11: Regional Policy Draft Implementing Act Consistent approach to determine the milestones and targets in the performance framework and to assess the attainment

Regional PolicyRegional Policy

Reference documents

FICHE NO 24 A – IMPLEMENTING ACT ON THE ARRANGEMENTS TO

ENSURE A CONSISTENT APPROACH FOR DETERMINING MILESTONES

AND TARGETS IN THE PERFORMANCE FRAMEWORK

FOR EACH PRIORITY AND FOR ASSESSING THE ATTAINMENT OF THE

MILESTONES AND TARGETS