Reconciliation Paper 2d0111209 Public

  • Upload
    ken-ngo

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    1/20

    Report for the Danish TelecommunicationAuthority

    2011/2012 upgraded cost model

    draft version

    Reconciliation paper for the calculation of

    actual operator costs

    14 December 2011

    Ref: 19176-452

    .

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    2/20

    Ref: 19176-452 .

    Contents

    1

    Introduction 1

    2 Model calibration 33 Model reconciliation 53.1 Unit capital costs of equipment 73.2 Asset price trends 83.3 Asset lifetimes 93.4 Top-down capex 103.5 Top-down opex 114 Cost optimisation 125 Updates to calibration and reconciliation of the cost model 145.1 Updates related to calibration 145.2 Updates related to reconciliation 15

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    3/20

    2011/2012 upgraded cost model draft version

    Ref: 19176-452 .

    Copyright 2011. Analysys Mason Limited has produced the information contained herein

    for the Danish Telecommunication Authority. The ownership, use and disclosure of this

    information are subject to the Commercial Terms contained in the contract betweenAnalysys Mason Limited and the Danish Telecommunication Authority.

    Analysys Mason Limited

    St Giles Court

    24 Castle Street

    Cambridge CB3 0AJ

    UK

    Tel: +44 (0)845 600 5244

    Fax: +44 (0)1223 460866

    [email protected]

    www.analysysmason.com

    Registered in England No. 5177472

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    4/20

    2011/2012 upgraded cost model draft version | 1

    Ref: 19176-452 .

    1 Introduction

    In early 2011 the Danish Telecommunication Authority contracted Analysys Mason Limited

    (Analysys Mason) to undertake a significant upgrade of the original mobile long -run average

    incremental cost (LRAIC) model (hereinafter referred to as the original mobile LRAIC model or

    the v4 model) used by the Danish Telecommunication Authority to set the prices for mobile

    termination in Denmark between June 2008 and November 2011.

    The mobile LRAIC model was originally constructed in 2007/2008 and version four of the model

    was released for consultation in June 2008. The Danish Telecommunication Authority has since

    updated the original mobile LRAIC model on an annual basis. The most recent upgrade of the cost

    model (hereinafter referred to as the upgraded cost model or the 5.0vD model) was completed

    in November 2011.1

    On 14 December 2011 the Danish Telecommunication Authority issued thedraft version of the upgraded cost model to the Danish mobile operators for consultation.

    The upgraded cost model contains calculations of the network drivers and deployments, and

    reasonably reflects the level of the Danish operators actual network deployments over the period

    to the end of 2010. It also includes a network costing calculation for a generic operator.2]

    The 5.0vD model used the inputs and calculations from the Danish Telecommunication

    Authoritys 2011 pricing decisions on the market for voice call termination on individual mobile

    networks (Market 7) as a starting point.3

    At the same time, the Danish Telecommunication

    Authority received top-down information from the four mobile operators in Denmark (TDC,Telenor, Telia and Hi3G) covering their actual network and expenditures to the end of 2010.

    This document describes the calibration and reconciliation of the actual operator calculations for

    TDC, Telenor, Telia and Hi3G for the years 20072010:

    calibration has been undertaken to ensure the network design algorithm was capable of

    reflecting the actual network deployment of the mobile operators

    reconciliation was undertaken to examine the expenditure levels, identify differences and

    resolve discrepancies between top-down and bottom-up costing approaches (where cost

    information existed for both bottom-up and top-down models).

    1http://www.itst.dk/tele-og-internetregulering/smp-regulering/engrospriser/lraic-1/lraic-priser/mobil/2011.

    2 This calculation is described in Section 4.2 of the model documentation.

    3Available at http://www.itst.dk/tele-og-internetregulering/smp-regulering/engrospriser/lraic-1/lraic-priser.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    5/20

    2011/2012 upgraded cost model draft version | 2

    Ref: 19176-452 .

    For details of the calibration and reconciliation of the model undertaken for the years prior to

    2007, please refer to the reconciliation paper4

    released with the v4 model on 16 June 2008. As far

    as possible, the calibration and reconciliation exercises undertaken to arrive at the 5.0vD model

    have only been designed to affect the years after 2006.

    This document includes references to confidential information. In the public release of this

    document, confidential information has been replaced by the scissor symbol ().

    In order to undertake the reconciliation, the 5.0vD model is calculated using different settings to

    those used when calculating the proposed cost result. Figure 1.1 below outlines how certain

    parameters must be set up. These are selectable from the CTRL worksheet in the 5.0vD model.

    Parameter For reconciliation For the proposed cost result5

    3G coverage cell effective radii

    implemented

    Linked operator number Linked operator number

    Cost of working capital Reconciled costing (no working

    capital)

    Including working capital allowance

    Include 3G licence fees? No Yes

    Cost optimisation

    (Sheet)

    Reconciled Optimised

    Figure 1.1: Parameter set-up configurations for reconciliation and for the production of a cost result[Source: Analysys Mason]

    The 5.0vD model is set up with a different choice of parameters since the working capital

    allowance does not appear in the actual operational expenditure (opex) of the mobile operators,

    and also because reconciliation of the 3G licence fees is unnecessary.

    The remainder of this document is laid out as follows:

    Section 2 describes the model calibration process

    Section 3 describes the model reconciliation process

    Section 4 describes the cost optimisation applied to

    Section 5 describes key changes to the reconciliation since the original mobile LRAIC model

    reconciliation.

    4The public version of the previous reconciliation paper was released on 16 June 2008 http://www.itst.dk/tele-og-internetregulering/smp-regulering/engrospriser/filarkiv-engrospriser/lraic/lraic-processer/lraic-mobil/endelig-model-og-prisafgorelser/Reconciliation%20paper%20Public_160608.pdf

    5Full details are given in Section 3.5 of the model documentation.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    6/20

    2011/2012 upgraded cost model draft version | 3

    Ref: 19176-452 .

    2 Model calibration

    All four mobile network operators in Denmark supplied a reasonably detailed set of network

    deployment data with which to calibrate network deployments in the bottom-up calculations

    within the upgraded cost model. In addition, all the network deployment data from the original

    calibration is still available and so was also used.

    In some cases, the data was available over a range of time periodswith the majority of data having at

    least 2006 and 2010 data points. This helps to provide a further cross-check on the suitability of the

    model algorithms in reflecting the dynamic effects occurring in the mobile networks.

    Item TDC Telenor Telia Hi3G

    Sites

    Base transceiver station (BTS)

    NodeB

    Transceiver (TRX)

    Backhaul links

    Base station controller (BSC) or

    radio network controller (RNC)

    Mobile switching centre (MSC)

    Backbone

    BSC/RNC or MSC ports

    Home location register (HLR)

    Switching sites

    Figure 2.1: Scope of top-down network deployment data provided by the mobile operators for years20062010 [Source: Operator data]

    Note that exact calibration (i.e. no divergence from supplied operator data in all years) was not

    undertaken. This is because such an exercise would be unduly complicated, would result in a

    vastly expanded model for very little increase in understanding, and it would only affect the model

    results negligibly.

    It is also worth noting that the calibration of the upgraded cost model was undertaken to minimise

    changes to modelled years before 2007, and so to not significantly affect the calibration of the

    original mobile LRAIC model. The 5.0vD model reflects the status of network deployment

    reasonably accurately for each mobile network operator as of 2010, as shown below in Figure 2.2.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    7/20

    2011/2012 upgraded cost model draft version | 4

    Ref: 19176-452 .

    TDC Telenor Telia Hi3G

    Top-

    down

    data

    Bottom-

    up model

    Top-

    down

    data

    Bottom-

    up model

    Top-

    down

    data

    Bottom-

    up model

    Top-

    down

    data

    Bottom-

    up model

    Sites

    BTS

    NodeB

    TRX

    BSC

    RNC

    2G MSC

    3G MSC-S

    MGW

    Figure 2.2: Asset calibration for the modelled year 2010 [Source: 5.0vD model, operator data]

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    8/20

    2011/2012 upgraded cost model draft version | 5

    Ref: 19176-452 .

    3 Model reconciliation

    Reconciliation of the bottom-up calculations within the upgraded cost model, as distinct from

    calibration, is the process of comparing bottom-up expenditures of the model with top-down(actual) expenditures submitted by the mobile operators. This reconciliation process can take into

    account the breadth of expenditure information in the upgraded cost model:

    unit capital prices of equipment

    price trends

    asset lifetimes

    top-down capital expenditures (capex)

    top-down opex

    WACC.

    The range of information provided in response to the data request issued to the Danish mobile

    operators in June 2011 is presented below in Figure 3.1.6

    Item TDC Telenor Telia Hi3G

    Unit capital prices

    Price trends

    Asset lifetimes

    Capex Yes Yes Yes Yes

    Opex Yes Yes Yes Yes

    Figure 3.1: Provision of reconciliation data [Source: Analysys Mason]

    Accordingly, Analysys Masons approach to reconciling the cost model utilised different methods

    in each of these areas, as described below:

    Unit capital prices

    of equipment

    The existing unit capital prices were in most cases kept unchanged from the

    original mobile LRAIC model. The costs of equipment supplied by were

    used as the basis of a check on the assumed capital prices for the period

    20072010. The two exceptions were the costs of owned site acquisition and

    third-party site acquisition. In the original mobile LRAIC model, for some

    (but not all) operators the costs of these two types of site were set to be equal.

    In the 5.0vD model, the cost of owned site acquisition has now been set

    higher than that for third-party site acquisition in all cases.

    Where new assets have been added to the 5.0vD model, the equipment

    prices submitted by and international benchmarks (e.g. the unit costs

    in PTSs (the Swedish regulator) mobile LRIC model)7

    have been used as

    the basis of the directequipment price for all operators.

    6During the development of the original mobile LRAIC model, operators provided top-down data up to the end of2006. As part of the development of the 5.0vD model, data was requested for the period 20072011. This data was

    then used in conjunction with the data prior to 2006, in order to extend the reconciliation from 2006 to 2010.7

    http://www.pts.se/sv/Bransch/Telefoni/SMP---Prisreglering/Kalkylarbete-mobilnat/Gallande-prisreglering/.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    9/20

    2011/2012 upgraded cost model draft version | 6

    Ref: 19176-452 .

    Where operators, or benchmarks, have not provided necessary equipment

    prices, Analysys Mason has developed its own estimates. In most cases,

    these estimates were cross-checked (in aggregate) with the resulting top-

    down cost data to ensure validity for the Danish context.

    In addition to direct equipment prices, mobile operators undertake a wide

    range of indirect capital investments incremental upgrades, tools,

    facilities, ancillary equipment, civil works, etc. These indirect costs do

    not have a standard list price per unit, and therefore are usually only

    identifiable from detailed asset register manipulation, business

    plan/budgets or through top-down comparison. We have left the indirect

    mark-ups used for the assets unchanged from the v4 model. For the new

    assets (Ethernet backhaul, high-speed packet access (HSPA) upgrades

    etc.), we have primarily used the cost model recently developed by PTS

    in Sweden as a benchmark. None of these assets has a mark-up for

    indirect costs in the PTS model and no data was provided by operators to

    allow estimation of indirect mark-ups for these assets. Therefore, in the

    5.0vD model, the indirect mark-ups are assumed to be zero.

    We note that no operators provided unit prices for the operating costs of

    assets.

    sset price trends The information on asset price trends supplied by operators concerned

    capital equipment prices. To validate the existing annual price trends in

    the model, the information provided by the mobile operators along with

    Analysys Masons estimates from other public mobile long-run

    incremental cost (LRIC) models were compared.

    Following this, a top-down comparison of capex and opex was

    undertaken, applying cost trends between 20062010 to ensure that the

    2006 unit prices had reach appropriate levels by 2010, based on the

    information provided by.

    sset lifetimes The model uses economic lifetimes to drive the replacement of networkassets. The economic lifetimes in the original mobile LRAIC model were

    based upon a number of information points:

    typical mortgage durations in Denmark

    economic lifetimes applied by the mobile cost model

    Analysys Masons estimates of the economic lifetime of network

    elements in the absence of replacement, driven by accounting rules,

    technology upgrade or service enhancement.

    Although the model contains accounting lifetimes for reference, boththe reconciliation and the proposed cost result use economic lifetimes.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    10/20

    2011/2012 upgraded cost model draft version | 7

    Ref: 19176-452 .

    In this way, assets are only replaced after their estimated useful life,

    rather than after their average accounting lifetime.

    For the 5.0vD model, no existing assets had their lifetimes revised. For

    the new assets added to the model, economic lifetimes consistent with

    similar existing assets were used.

    Top-down capex We have been able to compare capex calculated by the model directly (in

    nominal terms) with the data provided by all four operators. This was

    performed at an aggregate and sub-category level in order to compare the

    capital investments associated with each operators business.

    Top-down opex Due to the lack of bottom-up information on opex per network element

    from the mobile operators, we have checked the total opex levels in the

    model for each operator according to reconciliation with the categorisedtop-down data.

    Each of these areas is discussed in greater detail below.

    3.1 Unit capital costs of equipmentThe capital equipment cost for each network element was initially set in the reconciliation of the

    original mobile LRAIC model, with values derived according to:

    direct equipment prices from the price list information submitted by the mobile operators the identification of additional indirect capital investments from the top-down accounting

    information.

    However, the 5.0vD model contains a number of entirely new assets in the asset list. To derive unit

    costs for the entirely new assets, a similar process was undertaken as in generating the original

    asset costs. Both the directequipment prices from and international benchmarks (e.g. prices in

    PTSs mobile LRIC model)8

    were used as the basis for equipment prices.

    Figure 3.2below shows those assets in the upgraded cost model that have either been modified or

    are entirely new. A color-coding system is used to illustrate the sources of information used tocalculate them.

    Figure 3.2: Direct equipment prices [Source: 5.0vD model]

    8http://www.pts.se/sv/Bransch/Telefoni/SMP---Prisreglering/Kalkylarbete-mobilnat/Gallande-prisreglering/.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    11/20

    2011/2012 upgraded cost model draft version | 8

    Ref: 19176-452 .

    The colour-coding system used in Figure 3.2 is explained below.

    Colour Description Figure 3.3: Colour

    scheme used in costbase inputs [Source:

    Analysys Mason]

    Calculated from the bottom-up costs supplied by the

    operator9

    Based on bottom-up costs supplied by another operator

    Derived from international benchmarks

    Derived from actual top-down expenditures

    Unit cost not required for that case

    3.2 Asset price trendsIn reconciling the asset price trends in the upgraded cost model, it was decided to consider the

    trends after 2006 in two separate parts, namely the trends from 20062010 and the trends in the

    long term. We describe these considerations separately below.

    3.2.1Price trends between 20062010The price trends in the upgraded cost model are designed to capture real-world reductions (or

    increases) in the costs of network equipment. supplied unit capital cost information for

    2008-2010. Therefore, it was possible to derive a compound annual growth rate (CAGR) between

    the modelled 2006 asset costs and the 2010 asset costs provided by (in 2006 real terms DKK).

    These CAGR values are shown below in Figure 3.4, compared with the cost trends assumed in the

    v4 model for 2006-2010.

    20062010 v4 model

    capex cost trends

    CAGR Figure 3.4: Comparisonof the 20062010capex cost trends toCAGRs derived usings modelled 2006

    costs ands 2010data [Source: 5.0vDmodel, operator data]

    Sites 1%

    BTS -6% to -5%

    TRX -8%

    Carriers -7%

    BSC -6%

    RNC -5%

    As can be seen above, the operator data indicated several instances where a more aggressive

    decrease in unit costs had been experienced than was forecast in the v4 model. In addition to this

    bottom-up mapping of unit costs, a top-down reconciliation with each operator was also

    undertaken. In this exercise, capex and opex trends were adjusted to generate appropriate levels of

    annual expenditures in the period 2007-2010, as discussed further in Sections 3.4 and 3.5below.

    In order to minimise changes to the modelled expenditures prior to 2006, as far as possible only

    price trends from 2006 onwards were adjusted.

    9Some of the bottom-up costs have also been blended with benchmarks from other models, where available.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    12/20

    2011/2012 upgraded cost model draft version | 9

    Ref: 19176-452 .

    3.2.2Long-term cost trendsBoth submitted information on the price trends applying to capital equipment. This data was

    used in combination with the long-term price trends from the v4 model to inform an updated long-

    term trend, as shown in Figure 3.5.

    Real-term long-term,

    from the v4 model

    (19932010)

    real-term averagecosts changes (2001

    2007)

    real-term averagecosts changes (2008

    2010)

    Bottom-up, real-term

    long-term, forecast

    (2010 and after)

    Sites 1.1% 0.75%

    Towers 2.1% 2.1%

    BTS 5.7% to 5% 8.0%

    NodeB 2.1% 5.5%

    TRX 7.8% 7.0%

    Channel kit (CK) 6.1% 5.5%

    BSC 6.1% 8.5%

    RNC 5.1% 7.0%

    Figure 3.5: Comparison of real annual average price trends [Source: 5.0vD model, operator data]

    In comparing the data on price trends submitted by the operators to that in the bottom-up model, it

    can be observed that:

    The historical price trends from the v4 model are generally less negative than both trends,

    with the difference to being highlighted in the original reconciliation, whilst the datawas not available at the time. This difference may be one of the reasons for necessity of the

    larger cost trends observed from 2007 to 2011.

    The price trends in the upgraded cost model are likely to apply identically to all mobile

    operators. This is because it is assumed that all Danish mobile operators are under the

    influence of the same real-term changes in equipment (hardware, software, etc.) and local

    (wage, site acquisition, etc.) costs.

    The basis for revising a long-term trend in the model using the data provided was to use the

    average of the original value and the values derived from data provided by . The values used in

    the 5.0vD model are shown in the grey column in Figure 3.5 above.

    3.3 Asset lifetimesEach operator submitted accounting lifetimes for network assets. Analysys Masons manipulations

    to arrive at average accounting lifetimes were provided to the mobile operators as part of the

    development of the original mobile LRAIC model. Economic asset lifetimes were also originally

    calculated for each network element. This economic lifetime was assessed as the replacement

    lifetime of assets in a steady-state environment, i.e. one in which services, network asset releasesand equipment replacements are predictable and stable in the long term. They were based on

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    13/20

    2011/2012 upgraded cost model draft version | 10

    Ref: 19176-452 .

    characteristics of the Danish market (e.g. typical mortgage durations) and the economic lifetimes

    used by Ofcom (UK) and PTS (Sweden).

    Additionally, in the original mobile LRAIC model, economic lifetimes were limited to a maximum

    of 20 years to reflect a conservative view of long-lived assets. This principle has been maintained

    in the 5.0vD model.

    When determining the lifetimes for the new assets added to the 5.0vD model, values from existing

    equivalent assets have been used, or benchmarks from other mobile cost models where this was

    not possible.

    3.4 Top-down capexAll four operators submitted categorised top-down capex. These actual data points were used to

    assess the degree to which the direct bottom-up equipment prices managed to capture the levels ofexpenditure actually accumulated by the mobile businesses.

    The majority of new data received from operators was given in the format as outlined in the

    operator data request. These categories where mapped to the existing broad capex categories, as

    shown in Figure 3.6, so as to expand the previous reconciliations to 2010.

    Data request TDC Telenor Telia Hi3G

    Radio network

    Last-mile backhaul

    BSCs/RNCs

    Transmission, excl.

    backbone

    Switching

    Backbone

    transmission

    Other core

    infrastructure

    Indirect network

    costs

    Non-network costs

    Business

    overheads

    Figure 3.6: Broad capex categories; note that the number of categories provided varies by operator[Source: Analysys Mason]

    The aggregated direct bottom-up equipment prices, including both direct and indirect costs, have

    been reconciled against the actual top-down expenditures given by operators. The cumulative

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    14/20

    2011/2012 upgraded cost model draft version | 11

    Ref: 19176-452 .

    capex was compared as this removes possible timing effects from the expenditures. Figure 3.7

    below shows a comparison of the modelled cumulative capex versus the actual cumulative capex

    for each operator.

    TDC Telenor Telia10

    Hi3G

    Top-

    down

    Bottom-

    up

    Top-

    down

    Bottom-

    up

    Top-

    down

    Bottom-

    up

    Top-

    down

    Bottom-

    up

    Cumulative capex

    to end 2006

    % difference

    Cumulative capex

    to end 2010

    % difference

    Figure 3.7: Cumulative capex comparison for modelled direct and indirect expenditures (nominal DKKmillion) [Source: 5.0vD model, operator data]

    3.5 Top-down opexGiven the limited availability of bottom-up unit opex applicable to the Danish mobile network

    operators, the level of opex in the upgraded cost model has been set according to the available top-

    down data. A comparison of total opex for the four mobile operators for both 2006 and 2010 is

    shown below in Figure 3.8.

    TDC Telenor Telia Hi3G

    Top-

    down

    Bottom-

    up

    Top-

    down

    Bottom-

    up

    Top-

    down

    Bottom-

    up

    Top-

    down

    Bottom-

    up

    Total opex, 2006

    % difference

    Total opex, 2010

    % difference

    Figure 3.8: Comparison of total opex (nominal 2006 DKK million) [Source: 5.0vD model, operatordata]

    As is the case with capex, there have been no revisions made to the indirect opex mark-ups.

    Similarly, there have been no indirect mark-ups derived for the new assets, due to lack of available

    data. Instead, the direct cost is assumed to capture all associated operating costs for the asset.

    10In the development of the original mobile LRAIC model, did not provide a full-time series of in-year investments

    for its historical investments. As an alternative, the present value of capex was calculated instead for the purposesof reconciliation instead.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    15/20

    2011/2012 upgraded cost model draft version | 12

    Ref: 19176-452 .

    4 Cost optimisation

    In this section we revisit the cost optimisation previously applied to . We have compared the

    costs calculated across in order to ascertain where network and costing differences exist. Figure

    4.1 shows the components of total cumulative economic costs (sum of capex and opex over

    time) calculated with the unit costs applicable to each mobile operator. In this comparison it is

    important to observe that the inventory of assets being considered in each case is identical; the

    only difference is the unit capex and opex assumed.

    Figure 4.1: Network costs under different unit cost situations [Source: 5.0vD model]

    We note that this comparison still raises questions about theexpenditure allocation provided by

    , since:

    The last-mile access backhaul layer of the network exhibits a significant and material

    difference when compared to costs calculated according to the cost bases of the other operators

    The proportion of capex, and hence termination costs, contributed by the appears high

    compared to Analysys Masons experience of this part of the cost base in similar cost models, and

    is significantly higher than for the other Danish mobile operators.

    fully reconciled expenditures are calculated using the following unit prices:

    unit capex (1992) = direct capex (1992) plusindirect costs

    unit opex (1992) = unit capex (1992).

    Based on our comparison between the mobile operators, we consider that costs in the 5.0vD

    model should still be reduced by an indirect cost multiplier and a unit opex multiplier. This level

    of unit costs for can therefore be considered fully optimal for the purpose of wholesale mobile

    termination regulation in the Danish context.

    We note that Figure 4.1 also shows a significant change in the economic cost within other core

    infrastructure and backbone transmission when using the cost base of Operator 1 (). The

    reason for the difference in backbone transmission is that the unit opex for the National site-site

    circuit switched backbone distance (SDH STM1) is almost an order of magnitude higher for

    than the other operators. We have reduced this level in the 5.0vD model, producing closer

    agreement for this category, as shown below in Figure 4.1. This is also accounted for in the opex

    reconciliation in Figure 3.8, and does not significantly affect the opex reconciliation for.

    Figure 4.2: Network costs under different unit cost situations, with revisedunit costs [Source:5.0vD model]

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    16/20

    2011/2012 upgraded cost model draft version | 13

    Ref: 19176-452 .

    The reason for the difference in other core infrastructure is primarily the higher costs assumed in

    the cost base for the voicemail server and the billing system, compared with the other

    operators. We have not revised these inputs in the calculation in the model, although this can

    be investigated further.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    17/20

    2011/2012 upgraded cost model draft version | 14

    Ref: 19176-452 .

    5 Updates to calibration and reconciliation of the cost model

    This section describes some of the key changes to the 5.0vD model as a result of the calibration

    and reconciliation of the actual operator calculations for TDC, Telenor, Telia and Hi3G for the

    years 20072010.

    Section 5.1 describes updates made related to the calibration of modelled assets

    Section 5.2 describes updates made related to the reconciliation of modelled expenditures.

    5.1 Updates related to calibrationChoice of 3G cell

    radii used forcalibration

    In the original reconciliation, the effective cell radii implemented for 3G

    coverage was assumed to be Draft v2 voice, outdoor. When either calculatinga cost result, or undertaking calibration/reconciliation, this input is now set to

    Linked operator number.

    The reason for using Draft v2 voice, outdoor radii in the v4 model was that

    urban indoor cell radii, as used in the cost result at the time, caused a rapid

    deployment of sites, with the look-ahead effect in the model leading to 3G costs

    being incurred in 2006 and 2007. In addition, 3G coverage was too limited in

    order to adequately calibrate the 3G coverage inputs by operator in the model.

    In 2011, following four more years of evolution in the 3G networks inDenmark, these 3G coverage inputs can now be more accurately calibrated.

    This means that it can now be considered reasonable to use these radii

    during calibration/reconciliation, thus aligning the 3G methodology with

    that used for 2G.

    Updated traffic

    measures

    The various proportions of daily traffic in the busy hour were updated with

    more recent data for each operator. Although this affects the model results

    prior to 2007, none of the parameters had changed significantly, meaning

    that any differences to the calibration prior to 2006 were not substantial.

    In addition, operator information was used to populate the 5.0vD model

    busy-hour parameters for both Release 99 and HSPA.

    Updated site splits The split of sites by owned tower, third-party tower and third-party rooftop sites

    was updated for 2010 and 2011 using operator data. The number of 2G/3G

    indoor sites and repeaters in tunnels were also updated for each operator.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    18/20

    2011/2012 upgraded cost model draft version | 15

    Ref: 19176-452 .

    Updated BSC/RNC

    capacities

    To update the BSC and RNC capacities in a similar fashion as described by

    operators in their data submissions, a BSC and RNC upgrade path was

    defined. This functionality is intended to represent the fact that both BSCs

    and RNCs are available in a range of step-wise capacities, with operators

    tending to deploy a mixture of capacities. Therefore, the capacity used in themodel each year becomes a weighted average of the capacity options.

    Updated other

    asset capacities

    In addition to updating the BSC and RNC capacities, other assets capacities

    were revised only where necessary. Examples of such revision are the HLR

    capacity for and the capacity of the SMS centre (SMSC) throughput for.

    Updated some

    utilisation factors

    During the calibration, some of the operators utilisation factors were

    updated. This was mostly related to 3G assets. Where utilisation factors

    varied over time, such as that for the BSC, they were updated for the years

    2007-2010.

    Other updates In addition to the above, various smaller updates were made:

    To capture a roll-out of HSPA across the network, the minimum speed

    deployment for high-speed downlink packet access (HSDPA) for each

    geotype was calibrated with operator data. Minimum speeds were

    usually set so that the urban geotypes had equal speeds to, or faster than,

    the suburban geotypes, which in turn had equal speeds to, or faster than,

    the rural geotypes. The HSUPA grade deployed was then that

    corresponding to the ladder of HSDPA speed deployed.

    The percentage of pre-existing 2G sites available for 3G upgrade was

    adjusted to match the data submitted by the mobile operators.

    Call attempts per successful call and average call durations were checked

    against the new operator information and adjusted where appropriate.

    5.2 Updates related to reconciliationChoice of 3G cell

    radii used for

    reconciliation

    This change, as described above, is also used to reconcile expenditures.

    Used economic

    lifetimes rather

    than accounting

    lifetimes for

    reconciliation

    We believe this is reasonable since we are modelling replacement capex in

    the upgraded cost model, which should reflect the lifetimes of assets

    enduring in the network, rather than when they are fully depreciated.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    19/20

    2011/2012 upgraded cost model draft version | 16

    Ref: 19176-452 .

    Revised unit capex

    for existing assets

    In response tos data submission that the type of sites being purchased

    change in value over time, site assets were further split down by geotype to

    allow for their unit costs to vary by geotype. For the 5.0vD model, the unit

    cost of a site is assumed to be the same in all four geotypes, which is

    consistent with the v4 model.

    The unit capex for owned sites and third-party sites has also been updated so

    that the former has a higher unit cost than the latter for all operators (in the

    original v4 model, these were set as equal for some operators).

    Following the investigations in Section 4,sunit opex for the National

    site-site circuit switched backbone distance (SDH STM1) asset was

    reduced to a level closer to that of the other operators.

    Added unit costs for

    new assets

    New assets were added to the upgraded cost model including HSPA,

    Ethernet backhaul, and an Ethernet backbone. The unit costs for these newassets were calculated using a blend of benchmarking from other cost

    models and cost data submitted by.

    Revised 20062010

    capex trends

    The cost trends between 2006 and 2010 were revised, as described in

    Section 3.2.1. To capture operator unit cost changes over this time,

    significant negative cost trends had to be applied to many assets.

    While the cost trends are more negative than usual, it is felt that in this

    instance they are appropriate as they are only applied for a small number of

    years. They are also indicated as appropriate in order to get closer top-down

    reconciliation with actual opex. The long-term trend is more conservative

    than these short-term reductions. In addition, both the mobile cost models

    developed by Ofcom (in the UK) and ARCEP (in France) have precedents

    for large negative trends in this time period.

    Revised long-term

    capex trends

    The long-term capex trends were revised as is detailed in Section 3.2.2,

    using operator data from, as well as international benchmarks.

    Revised 20062010

    opex trends

    The opex cost trends between 2006 and 2010 were revised during the top-

    down opex reconciliation to capture annual operator opex over this period.

    To achieve similar opex charges as seen in operator data, significant

    negative cost trends had to be applied to some of the asset classes, though as

    with the capex trends this is felt to be reasonable over the short time period.

    As is the case for capex, there are also precedents for negative price trends

    (in real terms) from the models developed by both Ofcom and ARCEP.

    Revised long-term

    opex trends

    The majority of long-term opex trends remained as in the original

    calibration. New cost trends were added for new assets according to

    benchmarks, or to be consistent with existing assets in the same asset class.

  • 7/27/2019 Reconciliation Paper 2d0111209 Public

    20/20

    2011/2012 upgraded cost model draft version | 17

    Adjustments to

    operator data

    Data supplied by operators was adjusted prior to calibration to ensure the

    accuracy of the comparison. The key adjustments are listed below:

    sindirect network capex in 2010 was assumed to be the same

    as in 2009, as otherwise there was a significantly inflated capex in

    2010

    s network transmission opex in 2010 was assumed to be the

    same as in 2006 to take into account having internalised

    transmission costs

    interconnect, handsets and depreciation and amortisation opex

    values were excluded froms reconciliation data

    the 2009 and 2010 business overheads capex for was assumed

    to be the same as in 2008, to remove effects of

    non-network costs were excluded from s opex to better

    correspond to its previous submission; capitalised indirect network

    costs were included in the capex reconciliation.