48
Relion ® Protection and Control 630 series Commissioning Manual

RE_630_comm_756801 _ENa

Embed Size (px)

Citation preview

Page 1: RE_630_comm_756801 _ENa

Relion® Protection and Control

630 seriesCommissioning Manual

Page 2: RE_630_comm_756801 _ENa
Page 3: RE_630_comm_756801 _ENa

Document ID: 1MRS756801Issued: 15.09.2009

Revision: AProduct version: 1.0

© Copyright 2009 ABB. All rights reserved

Page 4: RE_630_comm_756801 _ENa

CopyrightThis document and parts thereof must not be reproduced or copied without writtenpermission from ABB, and the contents thereof must not be imparted to a thirdparty, nor used for any unauthorized purpose.

The software or hardware described in this document is furnished under a licenseand may be used, copied, or disclosed only in accordance with the terms of suchlicense.

TrademarksABB and Relion are registered trademarks of ABB Group. All other brand orproduct names mentioned in this document may be trademarks or registeredtrademarks of their respective holders.

WarrantyPlease inquire about the terms of warranty from your nearest ABB representative.

ABB Oy

Distribution Automation

P.O. Box 699

FI-65101 Vaasa, Finland

Telephone: +358 10 2211

Facsimile: +358 10 22 41094

http://www.abb.com/substationautomation

Page 5: RE_630_comm_756801 _ENa

ConformityThis product complies with the directive of the Council of the EuropeanCommunities on the approximation of the laws of the Member States relating toelectromagnetic compatibility (EMC Directive 2004/108/EC) and concerningelectrical equipment for use within specified voltage limits (Low-voltage directive2006/95/EC). This conformity is the result of tests conducted by ABB inaccordance with the product standards EN 50263 and EN 60255-26 for the EMCdirective, and with the product standards EN 60255-6 and EN 60255-27 for the lowvoltage directive. The IED is designed in accordance with the internationalstandards of the IEC 60255 series.

Page 6: RE_630_comm_756801 _ENa

DisclaimerThe data, examples and diagrams in this manual are included solely for the conceptor product description and are not to be deemed as a statement of guaranteedproperties. All persons responsible for applying the equipment addressed in thismanual must satisfy themselves that each intended application is suitable andacceptable, including that any applicable safety or other operational requirementsare complied with. In particular, any risks in applications where a system failure and/or product failure would create a risk for harm to property or persons (including butnot limited to personal injuries or death) shall be the sole responsibility of theperson or entity applying the equipment, and those so responsible are herebyrequested to ensure that all measures are taken to exclude or mitigate such risks.

This document has been carefully checked by ABB but deviations cannot becompletely ruled out. In case any errors are detected, the reader is kindly requestedto notify the manufacturer. Other than under explicit contractual commitments, inno event shall ABB be responsible or liable for any loss or damage resulting fromthe use of this manual or the application of the equipment.

Page 7: RE_630_comm_756801 _ENa

Safety information

Dangerous voltages can occur on the connectors, even though theauxiliary voltage has been disconnected.

Non-observance can result in death, personal injury or substantialproperty damage.

Only a competent electrician is allowed to carry out the electricalinstallation.

National and local electrical safety regulations must always befollowed.

The frame of the IED has to be carefully earthed.

The IED contains components which are sensitive to electrostaticdischarge. Unnecessary touching of electronic components musttherefore be avoided.

Whenever changes are made in the IED, measures should be takento avoid inadvertent tripping.

Page 8: RE_630_comm_756801 _ENa
Page 9: RE_630_comm_756801 _ENa

Table of contents

Section 1 Introduction.......................................................................3This manual........................................................................................3Intended audience..............................................................................3Product documentation.......................................................................4

Product documentation set............................................................4Document revision history.............................................................5Related documentation..................................................................6

Symbols and conventions...................................................................6Safety indication symbols..............................................................6Manual conventions.......................................................................6Functions, codes and symbols......................................................7

Section 2 Starting up......................................................................11Factory and site acceptance testing.................................................11Commissioning checklist..................................................................11Checking the power supply..............................................................12Energizing the IED............................................................................12

Check the IED operation.............................................................12IED start-up sequence.................................................................12

Setting up communication between PCM600 and the IED...............13Writing an application configuration to the IED.................................17Checking CT circuits.........................................................................17Checking VT circuits.........................................................................18Checking the RTXP test switch .......................................................18Checking transducer circuits............................................................19Checking binary input and output circuits.........................................19

Binary input circuits.....................................................................19Binary output circuits...................................................................20

Checking optical connections...........................................................20

Section 3 Establishing connection and verifying the IEC 61850station communication....................................................21Setting the station communication....................................................21Verifying the communication............................................................21

Section 4 Testing IED operation.....................................................23Preparing the IED to verify settings..................................................23Activating test mode.........................................................................24Preparing the connection to the test equipment...............................25Connecting test equipment to the IED..............................................25

Table of contents

630 series 1Commissioning Manual

Page 10: RE_630_comm_756801 _ENa

Releasing the function to be tested..................................................26Verifying analog primary and secondary measurement...................27Testing protection functionality.........................................................28

Section 5 Troubleshooting .............................................................29Fault tracing......................................................................................29

Identifying hardware errors..........................................................29Identifying runtime errors.............................................................29Identifying communication errors.................................................29

Checking the communication link operation...........................30Checking the time synchronization.........................................30

Running the display test..............................................................30Indication messages.........................................................................31

Internal faults...............................................................................31Warnings.....................................................................................32Additional indications...................................................................32

Correction procedures......................................................................32Resetting the configuration..........................................................32Changing and setting the password............................................33Identifying IED application problems...........................................33

Inspecting the wiring...............................................................33

Section 6 Glossary.........................................................................37

Table of contents

2 630 seriesCommissioning Manual

Page 11: RE_630_comm_756801 _ENa

Section 1 Introduction

1.1 This manual

The commissioning manual contains instructions on how to commission the IED.The manual can also be used by system engineers and maintenance personnel forassistance during the testing phase. The manual provides procedures for checkingof external circuitry and energizing the IED, parameter setting and configuration aswell as verifying settings by secondary injection. The manual describes the processof testing an IED in a substation which is not in service. The chapters are organizedin chronological order in which the IED should be commissioned.

1.2 Intended audience

This manual addresses the personnel responsible for commissioning, maintenanceand taking the IED in and out of normal service.

The commissioning personnel must have a basic knowledge of handling electronicequipment. The commissioning and maintenance personnel must be wellexperienced in using protection equipment, test equipment, protection functionsand the configured functional logics in the IED.

1MRS756801 A Section 1Introduction

630 series 3Commissioning Manual

Page 12: RE_630_comm_756801 _ENa

1.3 Product documentation

1.3.1 Product documentation set

Pla

nnin

g &

pur

chas

e

Eng

inee

ring

Inst

allin

g

Com

mis

sion

ing

Ope

ratio

n

Mai

nten

ance

Dec

omm

issi

onin

gde

inst

allin

g&

dis

posa

l

Application manual

Operation manual

Installation manual

Service manual

Engineering manual

Commissioning manual

Communication protocolmanual

Technical manual

Pla

nnin

g &

pur

chas

e

Eng

inee

ring

Inst

allin

g

Com

mis

sion

ing

Ope

ratio

n

Mai

nten

ance

Dec

omm

issi

onin

gde

inst

allin

g&

dis

posa

l

Pla

nnin

g &

pur

chas

e

Eng

inee

ring

Inst

allin

g

Com

mis

sion

ing

Ope

ratio

n

Mai

nten

ance

Dec

omm

issi

onin

gde

inst

allin

g&

dis

posa

l

Application manualApplication manual

Operation manualOperation manual

Installation manualInstallation manual

Service manualService manual

Engineering manualEngineering manual

Commissioning manualCommissioning manual

Communication protocolmanualCommunication protocolmanual

Technical manualTechnical manual

en07000220.vsd

IEC07000220 V1 EN

Figure 1: The intended use of manuals in different lifecycles

The engineering manual contains instructions on how to engineer the IEDs usingthe different tools in PCM600. The manual provides instructions on how to set up aPCM600 project and insert IEDs to the project structure. The manual alsorecommends a sequence for engineering of protection and control functions, LHMIfunctions as well as communication engineering for IEC 61850 and DNP3.

The installation manual contains instructions on how to install the IED. Themanual provides procedures for mechanical and electrical installation. The chaptersare organized in chronological order in which the IED should be installed.

The commissioning manual contains instructions on how to commission the IED.The manual can also be used by system engineers and maintenance personnel forassistance during the testing phase. The manual provides procedures for checkingof external circuitry and energizing the IED, parameter setting and configuration aswell as verifying settings by secondary injection. The manual describes the process

Section 1 1MRS756801 AIntroduction

4 630 seriesCommissioning Manual

Page 13: RE_630_comm_756801 _ENa

of testing an IED in a substation which is not in service. The chapters are organizedin chronological order in which the IED should be commissioned.

The operation manual contains instructions on how to operate the IED once it hasbeen commissioned. The manual provides instructions for monitoring, controllingand setting the IED. The manual also describes how to identify disturbances andhow to view calculated and measured power grid data to determine the cause of afault.

The service manual contains instructions on how to service and maintain the IED.The manual also provides procedures for de-energizing, de-commissioning anddisposal of the IED.

The application manual contains descriptions of preconfigurations. The manual canbe used as a reference for configuring control, protection, measurement, recordingand LED functions. The manual can also be used when creating configurationsaccording to specific application requirements.

The technical manual contains application and functionality descriptions and listsfunction blocks, logic diagrams, input and output signals, setting parameters andtechnical data sorted per function. The manual can be used as a technical referenceduring the engineering phase, installation and commissioning phase, and duringnormal service.

The communication protocol manual describes a communication protocolsupported by the IED. The manual concentrates on vendor-specific implementations.

The point list manual describes the outlook and properties of the data pointsspecific to the IED. The manual should be used in conjunction with thecorresponding communication protocol manual.

The service manual is not available yet.

1.3.2 Document revision historyDocument revision/date Product series version HistoryA/2009.09.15 1.0 First release

Download the latest documents from the ABB web site http://www.abb.com/substationautomation.

1MRS756801 A Section 1Introduction

630 series 5Commissioning Manual

Page 14: RE_630_comm_756801 _ENa

1.3.3 Related documentationProduct series- and product-specific manuals can be downloaded from the ABBweb site http://www.abb.com/substationautomation .

1.4 Symbols and conventions

1.4.1 Safety indication symbols

The electrical warning icon indicates the presence of a hazardwhich could result in electrical shock.

The warning icon indicates the presence of a hazard which couldresult in personal injury.

The caution icon indicates important information or warning relatedto the concept discussed in the text. It might indicate the presenceof a hazard which could result in corruption of software or damageto equipment or property.

The information icon alerts the reader to important facts andconditions.

The tip icon indicates advice on, for example, how to design yourproject or how to use a certain function.

Although warning hazards are related to personal injury, it should be understoodthat operation of damaged equipment could, under certain operational conditions,result in degraded process performance leading to personal injury or death.Therefore, comply fully with all warning and caution notices.

1.4.2 Manual conventionsConventions used in IED manuals. A particular convention may not be used in thismanual.

• Abbreviations and acronyms in this manual are spelled out in Glossary.Glossary also contains definitions of important terms.

• Push button navigation in the LHMI menu structure is presented by using thepush button icons, for example:

Section 1 1MRS756801 AIntroduction

6 630 seriesCommissioning Manual

Page 15: RE_630_comm_756801 _ENa

To navigate between the options, use and .• HMI menu paths are presented in bold, for example:

Select Main menu/Settings.• LHMI messages are shown in Courier font, for example:

To save the changes in non-volatile memory, select Yes and press .• Parameter names are shown in italics, for example:

The function can be enabled and disabled with the Operation setting.• The ^ character in front of an input or output signal name in the function block

symbol given for a function, indicates that the user can set an own signal namein PCM600.

• The * character after an input or output signal name in the function blocksymbol given for a function, indicates that the signal must be connected toanother function block in the application configuration to achieve a validapplication configuration.

1.4.3 Functions, codes and symbolsTable 1: Functions included in 630 series IEDs

Functionality IEC 61850 IEC 60617 ANSIProtection

Three-phase non-directional overcurrent,low stage

PHLPTOC 3I> 51P-1

Three-phase non-directional overcurrent,high stage

PHHPTOC 3I>> 51P-2

Three-phase non-directional overcurrent,instantaneous stage

PHIPTOC 3I>>> 50P/51P

Three-phase directional overcurrent, lowstage

DPHLPDOC 3I> → 67-1

Three-phase directional overcurrent, highstage

DPHHPDOC 3I>> → 67-2

Non-directional earth-fault, low stage EFLPTOC I0> 51N-1

Non-directional earth-fault, high stage EFHPTOC I0>> 51N-2

Non-directional earth-fault, instantaneousstage

EFIPTOC I0>>> 50N/51N

Directional earth-fault, low stage DEFLPDEF I0> → 67N-1

Directional earth-fault, high stage DEFHPDEF I0>> → 67N-2

Transient/intermittent earth-fault INTRPTEF I0> → IEF 67NIEF

Stabilised restricted earth-fault LREFPNDF dI0Lo> 87NL

High-impedance–based restricted earth-fault

HREFPDIF dI0Hi> 87NH

Negative-sequence overcurrent NSPTOC I2> 46

Phase reversal PREVPTOC I2>> 46R

Three-phase thermal overload for feeder T1PTTR 3Ith>F 49F

Table continues on next page

1MRS756801 A Section 1Introduction

630 series 7Commissioning Manual

Page 16: RE_630_comm_756801 _ENa

Functionality IEC 61850 IEC 60617 ANSIThree-phase thermal overload fortransformers

T2PTTR 3Ith>T 49T

Three-phase thermal overload for motors MPTTR 3Ith>M 49M

Loss-of-load supervision LOFLPTUC 3I< 37

Motor stall protection JAMPTOC Ist> 51LR

Emergency start ESMGAPC ESTART ESTART

Motor start-up supervision STTPMSU Is2t n< 49,66,48,51LR

Negative phase-sequence timeovercurrent protection

MNSPTOC I2>M 46M

Three-phase overvoltage PHPTOV 3U> 59

Three-phase undervoltage PHPTUV 3U< 27

Positive-sequence overvoltage PSPTOV U1> 47O+

Positive-sequence undervoltage PSPTUV U1< 47U+

Negative-sequence overvoltage NSPTOV U2> 47O-

Residual overvoltage ROVPTOV U0> 59G

Frequency gradient DAPFRC df/dt> 81R

Overfrequency DAPTOF f> 81O

Underfrequency DAPTUF f< 81U

Load shedding LSHDPFRQ UFLS/R 81LSH

Transformer differential protection for two-winding transformers

TR2PTDF 3dI>T 87T

Fault locator SCEFRFLO FLOC 21FL

Distance protection DSTPDIS Z< 21, 21P, 21N

Automatic switch-onto-fault logic CVRSOF SOTF SOTF

Phase discontinuity PDNSPTOC I2/I1> 46PD

Three-phase current inrush detection INRPHAR 3I2f> 68

Circuit-breaker failure CCBRBRF 3I>/I0>BF 51BF/51NBF

Autoreclosing DARREC O → I 79

Tripping logic TRPPTRC I → O 94/86

Protection-related functions

Local acceleration logic DSTPLAL LAL LAL

Communication logic for residualovercurrent

RESCPSCH CLN 85N

Scheme communication logic DSOCPSCH CL 85

Current reversal and WEI logic CRWPSCH CLCRW 85CRW

Current reversal and WEI logic forresidual overcurrent

RCRWPSCH CLCRWN 85NCRW

Control

Bay control QCCBAY CBAY CBAY

Interlocking interface SCILO 3 3

Circuit-breaker/disconnector control GNRLCSWI I ↔ O CB/DC I ↔ O CB/DC

Table continues on next page

Section 1 1MRS756801 AIntroduction

8 630 seriesCommissioning Manual

Page 17: RE_630_comm_756801 _ENa

Functionality IEC 61850 IEC 60617 ANSICircuit breaker DAXCBR I ↔ O CB I ↔ O CB

Disconnector DAXSWI I ↔ O DC I ↔ O DC

Local/remote switch interface LOCREM R/L R/L

Synchrocheck SYNCRSYN SYNC 25

Supervision and monitoring

Circuit-breaker condition monitoring SSCBR CBCM CBCM

Fuse failure supervision SEQRFUF FUSEF 60

Current-circuit supervision CCRDIF MCS 3I MCS 3I

Trip-circuit supervision TCSSCBR TCS TCM

Generic measured values MVGGIO

Measured value limit supervision MVEXP

Station battery supervision SPVNZBAT U<> U<>

Tap position indication TPOSSLTC TPOSM 84M

Energy monitoring EPDMMTR E E

Measurement

Three-phase current CMMXU 3I 3I

Three-phase voltage, phase-to-earthvoltages (RMS)

VPHMMXU 3Upe 3Upe

Three-phase voltage, phase-to-phasevoltages (RMS)

VPPMMXU 3Upp 3Upp

Residual current RESCMMXU I0 I0

Residual voltage RESVMMXU U0 Vn

Sequence current CSMSQI I1,I2 I1,I2

Sequence voltage VSMSQI U1,U2 V1,V2

Power monitoring with P, Q, S, powerfactor, frequency

PWRMMXU PQf PQf

Metering

Pulse counter for energy metering PCGGIO

Disturbance recorder function

Disturbance recorder DRRDRE DREC DREC

Analog channels 1-10 (samples) A1RADR ACH1 ACH1

Analog channel 11-20 (samples) A2RADR ACH2 ACH2

Analog channel 21-30 (samples) A3RADR ACH3 ACH3

Analog channel 31-40 (calc. val.) A4RADR ACH4 ACH4

Binary channel 1-16 B1RBDR BCH1 BCH1

Binary channel 17-32 B2RBDR BCH2 BCH2

Binary channel 33-48 B3RBDR BCH3 BCH3

Binary channel 49-64 B4RBDR BCH4 BCH4

1MRS756801 A Section 1Introduction

630 series 9Commissioning Manual

Page 18: RE_630_comm_756801 _ENa

10

Page 19: RE_630_comm_756801 _ENa

Section 2 Starting up

2.1 Factory and site acceptance testing

Testing the proper IED operation is carried out at different occasions, for example:

• Acceptance testing• Commissioning testing• Maintenance testing

This manual describes the workflow and the steps to carry out the commissioningtesting.

Factory acceptance testing (FAT) is typically done to verify that the IED andconfiguration meets the requirements by the utility or industry. This test is the mostcomplex and in depth, as it is done to familiarize the user to a new protection or toverify a new configuration. The complexity of this testing depends on several factors.

• New IED type• New configuration• Pre-configured• Modified existing configuration

Site acceptance testing (SAT or commissioning testing) is typically done to verifythat the new installed IED is correctly set and connected to the power system. SATrequires that the acceptance testing has been performed and that the applicationconfiguration is verified.

Maintenance testing is a periodical verification that the IED is healthy and hascorrect settings depending on changes in the power system. There are also othertypes of maintenance testing.

2.2 Commissioning checklist

Before starting up commissioning at site, check that the following items are available.

• Single line diagram• Protection block diagram• Circuit diagram• Setting list and configuration• Crossed Ethernet cable (CAT 5)• Three-phase test equipment

1MRS756801 A Section 2Starting up

630 series 11Commissioning Manual

Page 20: RE_630_comm_756801 _ENa

• PC with PCM600 installed along with the connectivity packagescorresponding to the IED used

• Administration rights on the PC to set up IP addresses• Product documentation (engineering manual, installation manual,

commissioning manual, operation manual, technical manual andcommunication protocol manual)

2.3 Checking the power supply

Check that the auxiliary supply voltage remains within the permissible inputvoltage range under all operating conditions. Check that the polarity is correct.

2.4 Energizing the IED

2.4.1 Check the IED operationCheck all connections to external circuitry to ensure that the installation was madecorrectly, before energizing the IED and carrying out the commissioning procedures.

Energize the power supply of the IED to start it up. This could be done in numberof ways, from energizing a whole cubicle to energizing a single IED. The IED timemust be set. The self-supervision function in the Main menu/Monitoring/IEDstatusorMain menu/Monitoring/Internal events menu in LHMI should also bechecked to verify that the IED operates properly.

2.4.2 IED start-up sequenceThe following sequence is expected when the IED is energized.

• The green Ready LED starts instantly flashing and the ABB logo is shown onthe LCD.

• After approximately 30 seconds "Starting" is shown on the LCD.• Within 90 seconds the main menu is shown on the LCD and the green Ready

LED shows a steady light, which indicates a successful start-up.

The start-up times depend on the size of the applicationconfiguration. Application configuration with less functionalitymeans shorter start-up times.

If the green Ready LED continues to flash after start-up, the IED has detected aninternal error. Navigate via Main menu/Monitoring/IED status to investigate thefault.

Section 2 1MRS756801 AStarting up

12 630 seriesCommissioning Manual

Page 21: RE_630_comm_756801 _ENa

2.5 Setting up communication between PCM600 andthe IED

The communication between the IED and PCM600 is independent of the usedcommunication protocol within the substation or to the NCC.

The communication media is always Ethernet and the used protocol is TCP/IP.

Each IED has an Ethernet interface connector on the front and on the rear side. TheEthernet connector can be used for communication with PCM600.

When an Ethernet based station protocol is used, PCM600 communication can usethe same Ethernet port and IP address.

For the connection of PCM600 to the IED two basic variants have to be considered.

• Direct point to point link between PCM600 and the IED front port.• Indirect link via a station LAN or from remote via a network.

The physical connection and the IP address must be configured in both cases toenable communication.

The communication procedures are in both cases the same.

1. If needed, set the IP address for the IEDs.2. Set up the PC or workstation for a direct link (point to point), or3. Connect the PC or workstation to the LAN/WAN network.4. Configure the IED IP addresses in the PCM600 project for each IED to match

the IP addresses of the physical IEDs.

Setting up IP addressesThe IP address and the corresponding mask can be set via the LHMI for eachavailable Ethernet interface in the IED. Each Ethernet interface has a defaultfactory IP address when the complete IED is delivered. This is not given when anadditional Ethernet interface is installed or an interface is replaced.

• The default IP address for the IED front port is 192.168.0.254 and thecorresponding subnetwork mask is 255.255.255.0, which can be set via theLHMI path Main menu/Configuration/Communication/TCP-IPconfiguration/Front port

• The default IP address for the IED rear port is 192.168.2.10 and thecorresponding subnetwork mask is 255.255.0.0, which can be set via theLHMI path Main menu/Configuration/Communication/TCP-IPconfiguration/LAN1

The front and rear port IP addresses cannot belong to the samesubnet or communication will fail. It is recommended to change the

1MRS756801 A Section 2Starting up

630 series 13Commissioning Manual

Page 22: RE_630_comm_756801 _ENa

IP address of the front port, if the front and rear port are set to thesame subnet.

Setting up the PC or workstation for point to point access to IEDsfront portA special cable is requested to connect two physical Ethernet interfaces togetherwithout a hub, router, bridge or switch in between. The Tx and Rx signal wiresmust be crossed in the cable to connect Tx with Rx on the other side and viceversa. These cables are known as null-modem cable or cross-wired cable. Theminimum length should be about 2 m. The connector type is RJ-45, see Figure 2.

IEC09000096-1-en.vsd

PCM600

Tx Tx

Rx Rx

RJ-45IED

IEC09000096 V1 EN

Figure 2: Point to point link between IED and PCM600 using a null-modemcable

The following description is an example valid for standard PCs using MicrosoftWindows operating system. The example is taken from a Laptop with one Ethernetinterface.

Administrator rights are requested to change the PC communicationsetup. Some PCs have the feature to automatically detect that Txsignals from the IED are received on the Tx pin on the PC. Thusstraight (standard) Ethernet cable can be used.

The IEDs DHCP server for the front port assigns an IP address for the computer.The computer must be configured to obtain its IP address automatically asdescribed in the following procedure.

1. Select Network Connections in the PC, see Figure 3.

Section 2 1MRS756801 AStarting up

14 630 seriesCommissioning Manual

Page 23: RE_630_comm_756801 _ENa

IEC09000355-1-en.vsdIEC09000355 V1 EN

Figure 3: Select: Network connections

2. Select Properties in the status window, see Figure 4.

IEC09000356-1-en.vsdIEC09000356 V1 EN

Figure 4: Right-click Local Area Connection and select Properties

3. Select the TCP/IP protocol from the list of configured components using thisconnection and click Properties, see Figure 5.

1MRS756801 A Section 2Starting up

630 series 15Commissioning Manual

Page 24: RE_630_comm_756801 _ENa

IEC09000357-1-en.vsdIEC09000357 V1 EN

Figure 5: Select the TCP/IP protocol and open Properties

4. Select Obtain an IP address automatically, see Figure 6.

IEC09000358-1-en.vsdIEC09000358 V1 EN

Figure 6: Select: Obtain an IP address automatically

5. Close all open windows and start PCM600.

Setting up the PC to access the IED via a networkThis task depends on the used LAN/WAN network. PC and IED must belong to thesame subnetwork.

Section 2 1MRS756801 AStarting up

16 630 seriesCommissioning Manual

Page 25: RE_630_comm_756801 _ENa

2.6 Writing an application configuration to the IED

Ensure that the IED includes the correct application configurationaccording to project specifications.

The application configuration is created using PCM600 and then written to theIED. Establish a connection between PCM600 and the IED when an applicationconfiguration must be written to IED.

When writing an application configuration to the IED, the IED is automatically setin configuration mode. When the IED is set in configuration mode, all functionsare blocked. The red Trip LED on the IED flashes, and the green Ready LED is litwhile the IED is in the configuration mode. When the writing procedure iscompleted, the IED is automatically set into normal mode.

Be sure to set the correct technical key in IED and PCM600 toprevent writing an application configuration to the wrong IED.

See the engineering manual for information on how to create ormodify an application configuration and how to write to IED.

Set setting parameters through the LHMI. See the operation manualfor information on how to change a setting from the LHMI.

2.7 Checking CT circuits

The CTs must be connected in accordance with the terminal diagram provided withthe IED, both with regards to phases and polarity. The following tests arerecommended for every primary CT or CT core connected to the IED.

• Primary injection test to verify the current ratio of the CT, the correct wiringup to the protection IED and correct phase sequence connection (that is L1,L2, L3.)

• Polarity check to prove that the predicted direction of secondary current flowis correct for a given direction of primary current flow. This is an essential testfor the proper operation of the directional function, protection or measurementin the IED.

• CT secondary loop resistance measurement to confirm that the currenttransformer secondary loop dc resistance is within specification and that thereare no high resistance joints in the CT winding or wiring.

1MRS756801 A Section 2Starting up

630 series 17Commissioning Manual

Page 26: RE_630_comm_756801 _ENa

• CT excitation test to ensure that the correct core in the CT is connected to theIED. Normally only a few points along the excitation curve are checked toensure that there are no wiring errors in the system, for example due to amistake in connecting the CT's measurement core to the IED.

• Earthing check of the individual CT secondary circuits to verify that each three-phase set of main CTs is properly connected to the station earth and only atone electrical point.

• Insulation resistance check.

Both primary and secondary sides must be disconnected from theline and IED when plotting the excitation characteristics.

2.8 Checking VT circuits

Check that the wiring is in strict accordance with the supplied connection diagram.

Do not continue before any errors are corrected.

Test the circuitry.

• Polarity check• VT circuit voltage measurement (primary injection test)• Earthing check• Phase relationship• Insulation resistance check

The polarity check verifies the integrity of circuits and the phase relationships. Thepolarity should be measured as close to the IED as possible to ensure that most ofthe wiring is also checked.

The primary injection test verifies the VT ratio and the wiring all the way throughfrom the primary system to the IED. Injection must be performed for each phase-to-neutral circuit and each phase-to-phase pair. In each case voltages in all phases andneutral are measured.

2.9 Checking the RTXP test switch

The RTXP test switch is designed to provide the means of safe testing of the IED.This is achieved by the electromechanical design of the test switch and test plughandle, when the test plug handle is inserted it first blocks the trip and alarm

Section 2 1MRS756801 AStarting up

18 630 seriesCommissioning Manual

Page 27: RE_630_comm_756801 _ENa

circuits then it short circuit CT secondary circuit and opens VT secondary circuitsmaking the IED available for secondary injection.

When pulled out the test handle is mechanically stopped in half withdrawnposition, in this position the current and voltage enter the protection, but the alarmand trip circuits are still isolated.

Not until the test handle is completely removed the trip and alarm circuits arerestored for operation.

Verify by pulling in all cables that the contact sockets have beencrimped correctly and that they are fully inserted. This should neverbe done with current circuits in service.

Current circuit

1. Verify that the contact are of current circuit type.2. Verify that the short circuit jumpers are located in the correct slots.

Voltage circuit

1. Verify that the contact are of voltage circuit type.2. Check that no short circuit jumpers are located in the slots dedicated for voltage.

Trip and alarm circuits

1. Check that the correct type of contacts are used.

2.10 Checking transducer circuits

Verify from the manufacturer that the total circuit resistance is under specifiedvalues from the instrument (transducer) manufacturer.

2.11 Checking binary input and output circuits

2.11.1 Binary input circuitsPreferably, disconnect the binary input connector from the binary input cards.Check all connected signals so that both input level and polarity are in accordancewith the IEDs specifications.

1MRS756801 A Section 2Starting up

630 series 19Commissioning Manual

Page 28: RE_630_comm_756801 _ENa

2.11.2 Binary output circuitsPreferably, disconnect the binary output connector from the binary output cards.Check all connected signals so that both load and voltage are in accordance withthe IED specifications.

2.12 Checking optical connections

Check that the Tx and Rx optical connections are correct.

An IED equipped with optical connections requires a minimumdepth of 180 mm. The allowed minimum bending radius has to bechecked from the optical cable manufacturer.

Section 2 1MRS756801 AStarting up

20 630 seriesCommissioning Manual

Page 29: RE_630_comm_756801 _ENa

Section 3 Establishing connection and verifying theIEC 61850 station communication

3.1 Setting the station communication

To enable IEC 61850 station communication:

• The IEC 61850-8-1 station communication functionality must be on in theLHMI. Navigate to Main menu/Configuration/Communication/IEC61850-8-1/General and set parameter Operation to On.

• To enable GOOSE communication the Operation parameter for thecorresponding GOOSE function blocks (GOOSEBINRCV andGOOSEINTLKRCV) must be set to On in the application configuration.

3.2 Verifying the communication

Connect your PC to the nearby switch and ping the connected IED and theSubstation Master PC to verify that the communication is working (up to thetransport layer). If it is possible to see all of them, then they can see each other.

The best way to verify the communication up to the application layer is to

• use a protocol analyzer, for example an Ethereal that is connected to thesubstation bus, and

• monitor the communication

1MRS756801 A Section 3Establishing connection and verifying the IEC 61850 station communication

630 series 21Commissioning Manual

Page 30: RE_630_comm_756801 _ENa

22

Page 31: RE_630_comm_756801 _ENa

Section 4 Testing IED operation

4.1 Preparing the IED to verify settings

If a test switch is included, start preparation by making the necessary connectionsto the test switch. This means connecting the test equipment according to a specificand designated IED terminal diagram.

Put the IED into test mode to facilitate the test of individual functions and preventunwanted operation caused by other functions. The test switch should then beconnected to the IED.

Verify that analog input signals from the Technical reference manual module aremeasured and recorded correctly by injecting currents and voltages required by thespecific IED.

To make testing even more effective PCM600 should be used. PCM600 includesthe Signal monitoring tool, which is useful to read of the individual currents andvoltages, their amplitudes and phase angles. In addition PCM600 contains theDisturbance handling tool. The content of reports generated by the Disturbancehandling tool can be configured which makes the work more efficient. Forexample, the tool may be configured to only show time tagged events and toexclude analog information and so on.

The disturbance report settings must be checked to ensure that indications are correct.

Functions to test, signal and parameter names can be found in the technical manual.The correct initiation of the disturbance recorder is made on start and/or release ortrip from a function. Also check that the wanted recordings of analogue (real andcalculated) and binary signals are achieved.

Parameters can be entered into different setting groups. Make sureto test functions for the same parameter setting group. If needed thetests must be repeated for all different setting groups used. Thedifference between testing the first parameter setting group and theremaining is that there is no need for testing the connections.

Observe during testing that the right method for testing must be used thatcorresponds to the actual parameters set in the activated parameter setting group.

In LHMI the directional earth fault protection low stage DPHLPDOC parametergroup 4 is active indicated by the * next to #4 and the test of the DPHLPDOC mustbe performed according to the value given for the setting Pol quantity, defaultsetting value Cross pol.

1MRS756801 A Section 4Testing IED operation

630 series 23Commissioning Manual

Page 32: RE_630_comm_756801 _ENa

Set and configure the function(s) before the testing can start. Most functions arehighly flexible in that it permits a choice of functional and tripping modes. Thevarious modes are checked at the factory as part of the design verification. Incertain cases only modes with a high probability of coming into operation need tobe checked when commissioned to verify the configuration and settings.

Requirements for testing the function.

• Calculated settings• Valid configuration diagram for the IED• Valid terminal diagram for the IED• Technical manual• Three-phase test equipment

Content of the technical manual.

• Application and functionality summaries• Function blocks• Logic diagrams• Input and output signals• A list of setting parameters• Technical data for the function

The test equipment should be able to provide a three-phase supply of currents (andfor some START functions also voltage). The magnitude and angle of currents(and voltages) should be possible to vary. Check that the IED is prepared for testbefore starting the test session. Consider the logic diagram of the function whenperforming the test.

The response from a test can be viewed in different ways.

• Binary output signals• Service values in LHMI (logical signal or phasors)• A PC with PCM600 (configuration software) in debug mode

4.2 Activating test mode

The IED shall be put into test mode before testing. Test mode blocks all functionsin the IED and the individual functions to be tested can be unblocked to preventunwanted operation caused by other functions. In this way, it is possible to testslower back-up measuring functions without the interference from faster measuringfunctions. Test mode is indicated when the yellow Start LED flashes.

Procedure

Section 4 1MRS756801 ATesting IED operation

24 630 seriesCommissioning Manual

Page 33: RE_630_comm_756801 _ENa

1. Browse to Main menu/Tests/IED test mode2. Set parameter TestMode to On and save the changes.

As a consequence the yellow Start LED will start flashing as a reminder andremains flashing until the test mode is switched off.

4.3 Preparing the connection to the test equipment

The IED can be equipped with a test switch of type RTXP8, RTXP18 or RTXP24.The test switch and its associated test plug handle (RTXH8, RTXH18 or RTXH24)are a part of the COMBITEST system, which provide secure and convenienttesting of the IED.

When using the COMBITEST, preparations for testing are automatically carriedout in the proper sequence, that is for example, blocking of tripping circuits, shortcircuiting of CT’s, opening of voltage circuits, making IED terminals available forsecondary injection). Terminals 1 and 8, 1 and 18 as well as 1 and 12 of the testswitches RTXP8, RTXP18 and RTXP24 respectively are not disconnected as theysupply DC power to the protection IED.

The RTXH test-plug handle leads may be connected to any type of test equipmentor instrument. When a number of protection IEDs of the same type are tested, thetest-plug handle only needs to be moved from the test switch of one protection IEDto the test switch of the other, without altering previous connections.

Use COMBITEST test system to prevent unwanted tripping when the handle iswithdrawn, since latches on the handle secure it in the half withdrawn position. Inthis position, all voltages and currents are restored and any reenergizing transientsare given a chance to decay before the trip circuits are restored. When the latchesare released, the handle can be completely withdrawn from the test switch,restoring the trip circuits to the protection IED.

If a test switch is not used, take measures according to provided circuit diagrams.

Never disconnect the secondary connection of a current transformercircuit without short-circuiting the transformer's secondarywinding. Operating a current transformer with the secondarywinding open will cause a massive potential build up that maydamage the transformer and injure humans.

4.4 Connecting test equipment to the IED

Connect the test equipment according to the IED specific connection diagram.

1MRS756801 A Section 4Testing IED operation

630 series 25Commissioning Manual

Page 34: RE_630_comm_756801 _ENa

Pay attention to the current polarity. Make sure that the connection of input andoutput current terminals and the connection of the residual current conductor iscorrect. Check that the input and output logical signals in the logic diagram for thefunction under test are connected to the corresponding binary inputs and outputs ofthe IED under test.

4.5 Releasing the function to be tested

Release or unblock the function to be tested. This is done to ensure that only thefunction or the chain of functions to be tested are in operation and that otherfunctions are prevented from operating. The user can release the tested function(s)by setting the corresponding Blocked parameter under Function test modes to No inLHMI.

When testing a function in this blocking feature, remember that not only the actualfunction must be activated, but the whole sequence of interconnected functions(from measuring inputs to binary output contacts), including logic and so on.Before starting a new test mode session the user should scroll through everyfunction to ensure that only the function to be tested (and the interconnected ones)have the parameters Blocked and eventually EvDisable are set to No and Yesrespectively. Remember that a function is also blocked if the BLOCK input signalon the corresponding function block is active, which depends on the configuration.Ensure that the logical status of the BLOCK input signal is equal to 0 for thefunction to be tested. Event function blocks can also individually be blocked toensure that no events are reported to a remote station during the test. This is doneby setting the parameter EvDisable to Yes.

Any function is blocked if the corresponding setting in LHMI underMain menu/Tests/Function test modes menu remains On, that isthe parameter Blocked is set to Yes and the parameter TestModeunder the Main menu/Tests/IED test mode remains active. Allfunctions that were blocked or released from a previous test modesession, that is the parameter Test mode is set to On, are reset whena new test mode session is started.

Procedure

1. Browse to the Function test modes menu.The Function test modes menu is located in LHMI under Main menu/Tests/Function test modes.

2. Browse to the function instance that should be released.3. Set parameter Blocked for the selected function to Yes.

Section 4 1MRS756801 ATesting IED operation

26 630 seriesCommissioning Manual

Page 35: RE_630_comm_756801 _ENa

4.6 Verifying analog primary and secondarymeasurement

Verify that the connections are correct and that measuring and scaling is correctly.This is done by injecting current and voltage to the IED.

Apply input signals as needed according to the actual hardware andthe application configuration made in PCM600.

Procedure

1. Inject a symmetrical three-phase voltage and current at rated value.2. Compare the injected value with the measured values.

The voltage and current phasor menu in LHMI is located under Main menu/Measurements.

3. Compare the frequency reading with the set frequency and the direction of thepower.The frequency and active power are located under Main menu/Tests/Function status/Monitoring/PWRMMXU()PQf:1/Outputs. Then navigateto the bottom of the list to find the frequency.

4. Inject an unsymmetrical three phase voltage and current, to verify that phasesare correctly connected.

If some setting deviates check the analog input settings under

Main menu/Configuration/Analog inputs

Measured values such as current (phase and residual)and voltages (phase-to-earth,phase-to-phase and residual)as well as active, reactive and apparent power, powerfactor phase angles as well as positive and negative sequence currents and voltagesare available in LHMI under Main menu/Monitoring/I/O status/Monitoring.

Navigate to the measurement function that contains the quantity to be checked.

Table 2:

CMMXU IA; IB and IC amplitude range and angle

RESCMMXU I0 amplitude range and angle

CSMSQI I1 and I2 amplitude range and angle

VPHMMXU UA; UB and UC i.e. phase-to-neutral

amplitude range and angle

VPPMMXU UAB; UBC and UCA i.e. phase-to-phase

amplitude range and angle

Table continues on next page

1MRS756801 A Section 4Testing IED operation

630 series 27Commissioning Manual

Page 36: RE_630_comm_756801 _ENa

RESVMMXU U0 amplitude range and angle

VSMSQI U1 and U2 amplitude range and angle

PWRMMXU S; P; Q; PF; Ilag; Ilead and f amplitude range and angle

Also the Signal monitoring tool in PCM600 can be used to read measured values.In many cases it is more convenient to use PCM600 since, among many things,reports on measured values can be exported from the Signal monitoring tool toother tools (for example MS Excel) further analysis.

4.7 Testing protection functionality

Each protection function must be tested individually by secondary injection.

• Verify operating levels (trip) and timers.• Verify alarm and blocking signals.• Use the disturbance handling tool in PCM600 to evaluate that the protection

function has received the correct data and responded correctly (signaling andtiming).

• Use the event viewer tool in PCM600 to check that only expected events haveoccurred.

Section 4 1MRS756801 ATesting IED operation

28 630 seriesCommissioning Manual

Page 37: RE_630_comm_756801 _ENa

Section 5 Troubleshooting

5.1 Fault tracing

5.1.1 Identifying hardware errors

1. Check the module with an error.• Check the general IED status in Main menu/Monitoring/IED status

for a faulty hardware module.• Check the history of changes in internal event list in Main menu/

Monitoring/Internal events.2. Inspect the IED visually.

• Inspect the IED visually to find any physical error causes.• If you can find some obvious physical damage, contact ABB for repair

or replacement actions.3. Check whether the error is external or internal.

• Check that the error is not caused by external origins.• Remove the wiring from the IED and test the input and output operation

with an external test device.• If the problem remains, contact ABB for repair or replacement actions.

5.1.2 Identifying runtime errors

1. Check the error origin from IED's internal event list Main menu/Monitoring/Internal events.

2. Reboot the IED and recheck the supervision events to see if the fault hascleared.

3. In case of persistent faults, contact ABB for corrective actions.

5.1.3 Identifying communication errorsCommunication errors are normally communication interruptions orsynchronization message errors due to communication link breakdown.

• Check the IEC61850 and DNP3 communication status in internal event list inMain menu/Monitoring/Internal events.

• In case of persistent faults originating from IED's internal faults such ascomponent breakdown, contact ABB for repair or replacement actions.

1MRS756801 A Section 5Troubleshooting

630 series 29Commissioning Manual

Page 38: RE_630_comm_756801 _ENa

5.1.3.1 Checking the communication link operation

There are several different communication links on the product. First check that allcommunication ports that are used for communication are turned on.

1. Check the front communication port RJ-45.1.1. Check that the uplink LED is lit with a steady green light.

The uplink LED is located on the LHMI above the RJ-45communication port on the left. The port is used for direct electricalcommunication to a PC connected via a crossed-over Ethernet cable.

1.2. Check the communication status of the front port via the LHMI in Mainmenu/Monitoring/Ethernet/Front port.Check that the LINKUP value is 1, that is, the communication isworking. When the value is 0, there is no communication link.

2. Check the communication status of the rear port X0 via the LHMI in Mainmenu/Monitoring/Ethernet/LAN1.The X0 communication port on the rear side of the IED is for electricalcommunication to a PC connected via a crossed-over Ethernet cable. Thiscommunication port is an alternative to the front communication port.• Check that the LINKUP value is 1, that is, the communication is

working. When the value is 0, there is no communication link.3. Check the communication status of the rear port X1 via the LHMI in Main

menu/Monitoring/Ethernet/LAN1.The X1 communication port on the rear side of the IED is for optical Ethernetvia LC connector or electrical via RJ-45 connector of the IEC 61850-8-1station bus communication.• Check that the LINKUP value is 1, that is, the communication is

working. When the value is 0, there is no communication link.

5.1.3.2 Checking the time synchronization

• Select Main menu/Monitoring/IED status and check the status of the timesynchronization on Time Synch.The Time synch value is Ready when the synchronization is in order. Note thatthe time synchronization source has to be activated. Otherwise the value isalways Ready.

5.1.4 Running the display testTo run the display test, either use the push buttons or start the test via the menu.

• Select Main menu/Test/LED test.• Press or simultaneously and .

Section 5 1MRS756801 ATroubleshooting

30 630 seriesCommissioning Manual

Page 39: RE_630_comm_756801 _ENa

All the LEDs are tested by turning them on simultaneously. The LCD shows aset of patterns so that all the pixels are activated. After the test, the displayreturns to normal state.

5.2 Indication messages

5.2.1 Internal faultsWhen the Ready LED indicates an internal fault by flashing, the messageassociated with the fault is found in the internal event list in the LHMI menu Mainmenu/Monitoring/Internal events. The message includes the date, time,description and signal state for the fault. The internal event list is not updateddynamically. The list is updated by leaving the Internal events menu and thenselecting it again. The current status of the internal fault signals can also bechecked via the LHMI in Main menu/Monitoring/IED status.

Different actions are taken depending on the severity of the fault. After the fault isfound to be permanent, the IED stays in internal fault mode. The IED continues toperform internal tests during the fault situation.

When a fault appears, the fault indication message is to be recorded and statedwhen ordering service.

Table 3: Internal fault indications

Fault indication Additional informationInternal FaultReal Time Clock Error

Hardware error with the real time clock.

Internal FaultRuntime Exec. Error

One or more of the application threadsare not working properly.

Internal FaultSW Watchdog Error

This signal will be activated when theterminal has been under too heavy loadfor at least 5 minutes.

Internal FaultRuntime App Error

One or more of the application threadsare not in an expected state.

Internal FaultFile System Error

A file system error has occurred.

Internal FaultTRM-Error

A TRM card error has occurred. Theinstance number is displayed at the endof the fault indication.

Internal FaultBIO-Error

A BIO card error has occurred. Theinstance number is displayed at the endof the fault indication.

Internal FaultCOM-Error

A COM card error has occurred. Theinstance number is displayed at the endof the fault indication.

Internal FaultPSM-Error

A PSM card error has occurred. Theinstance number is displayed at the endof the fault indication.

1MRS756801 A Section 5Troubleshooting

630 series 31Commissioning Manual

Page 40: RE_630_comm_756801 _ENa

5.2.2 WarningsThe warning message associated with the fault is found in the internal event list inthe LHMI menu Main menu/Monitoring/Internal events. The message includesthe date, time, description and signal state for the fault. The current status of theinternal fault signals can also be checked via the LHMI in Main menu/Monitoring/IED status.

When a fault appears, the fault indication message is to be recorded and statedwhen ordering service.

Table 4: Warning indications

Warning indication Additional informationWarningIEC 61850 Error

IEC 61850 has not succeeded in someactions such as reading the configurationfile, startup etc.

WarningDNP3 Error

Error in DNP3 communication.

5.2.3 Additional indicationsThe additional indication messages do not activate internal fault or warning.

The messages are listed in the LHMI menu under the event list. The signal statusdata is found under the IED status and in the internal event list.

Table 5: Additional indications

Warning indication Additional informationTime Synch Error Source of the time synchronization is lost

or time system has made a time reset.

BATTERY1 Error BATTERY1 Error status.

BATTERY2 Error BATTERY2 Error status.

Settings Changed Settings have been changed.

Setting Groups Changed Setting group has been changed.

5.3 Correction procedures

5.3.1 Resetting the configurationThe configuration is reset with PCM600.

For more information, see PCM600 documentation.

Section 5 1MRS756801 ATroubleshooting

32 630 seriesCommissioning Manual

Page 41: RE_630_comm_756801 _ENa

5.3.2 Changing and setting the passwordThe password can only be set with PCM600.

For more information, see PCM600 documentation.

5.3.3 Identifying IED application problemsNavigate to the appropriate menu in the LHMI to identify possible problems.

• Check that the function is on.• Check that the correct setting group (1 to 4) is activated.• Check the blocking.• Check the mode.• Check the measurement value.• Check the connection to trip and disturbance recorder functions.• Check the channel settings.

5.3.3.1 Inspecting the wiring

The physical inspection of wiring connections often reveals the wrong connectionfor phase currents or voltages. However, even though the phase current or voltageconnections to IED terminals might be correct, wrong polarity of one or moremeasurement transformers can cause problems.

• Check the current or voltage measurements and their phase information fromMain menu/Measurements.

• Check that the phase information and phase shift between phases is correct.• Correct the wiring if needed.

• Change the parameter Negation in Configuration/Analog inputs/3-phase analog group/SMAI_20_n:1 (n= the number of the SMAI used).

Changing the Negation parameter is not recommendedwithout special skills.

• In PCM600, change the parameter CTStarPointn (n= the number on thecurrent input) under the parameter settings for each current input.

• Check the actual state of the connected binary inputs.• In LHMI, select Main menu/Monitoring/I/O status/Binary input

modules. Then navigate to the board with the actual binary input to bechecked.

• With PCM600, right-click the product and select Signal Monitoring.Then navigate to the actual I/O board and to the binary input in question.The activated input signal is indicated with a yellow-lit diode.

1MRS756801 A Section 5Troubleshooting

630 series 33Commissioning Manual

Page 42: RE_630_comm_756801 _ENa

• Measure output contacts using the voltage drop method of applying at least theminimum contact load given for the output relays in the technical data, forexample 100 mA at 24 V AC/DC.

Output relays, especially power output relays, are designed forbreaking high currents. Due to this, layers of high resistancemay appear on the surface of the contacts. Do not determineproper functionality of connectivity or contact resistance bymeasuring with a regular hand-held ohm meter.

A1

2

3

4

V

GUID-BBAEAF55-8D01-4711-A71D-BBC76B60BA3D V1 EN

Figure 7: Testing output contacts using the voltage drop method

1 Contact current

2 Contact voltage drop

3 Load

4 Supply voltage

Section 5 1MRS756801 ATroubleshooting

34 630 seriesCommissioning Manual

Page 43: RE_630_comm_756801 _ENa

V1

2

A

GUID-31DF5495-91F1-4A4B-8FD5-50625038961E V1 EN

Figure 8: Testing a trip contact

1 Trip contact under test

2 Current limiting resistor

• To check the status of the output circuits driving the output relay via theLHMI, select Main menu/Monitoring/I/O status/Binary output modulesand then navigate to the board with the actual binary output to be checked.

• Test and change the relay state manually.1. To set the IED to test mode, select Main menu/Test/IED test mode/

TestMode and set the parameter to On.2. To operate or force the output relay to operate, select Main menu/Test/

Forcing/Binary output values and then navigate to the board with theactual binary output relay to be operated/forced.

3. Select the BOn_PO to be operated/forced and use and or tooperate the actual output relay.In PCM600, only the result of these operations can be checked by right-clicking the product and selecting Signal Monitoring tool and then

1MRS756801 A Section 5Troubleshooting

630 series 35Commissioning Manual

Page 44: RE_630_comm_756801 _ENa

navigating to the actual I/O-board and the binary input in question. Theactivated output signal is indicated with a yellow-lit diode. EachBOn_PO is represented by two signals. The first signal in LHMI is theactual value 1 or 0 of the output, and in PCM600 a lit or dimmed diode.The second signal is the status Normal or Forced. Forced status is onlyachieved when the BO is set to Forced or operated on the LHMI.

Set the parameter TestMode to Off after completing thesetests. The Start LED will stop flashing when the relay isno longer in test mode.

An initially high contact resistance will not cause problems as it will be reducedquickly by the electrical cleaning effect of fritting and thermal destruction oflayers, bringing the contact resistance back to the mOhm range. As a result,practically the full voltage is available at the load.

Section 5 1MRS756801 ATroubleshooting

36 630 seriesCommissioning Manual

Page 45: RE_630_comm_756801 _ENa

Section 6 Glossary

ANSI American National Standards InstituteCAT 5 A twisted pair cable type designed for high signal integrityCT Current transformerDC Direct currentDHCP Dynamic Host Configuration ProtocolDNP3 A distributed network protocol originally developed by

Westronic. The DNP3 Users Group has the ownership ofthe protocol and assumes responsibility for its evolution.

EMC Electromagnetic compatibilityEthernet A standard for connecting a family of frame-based

computer networking technologies into a LANFAT Factory acceptance testingGOOSE Generic Object Oriented Substation EventHMI Human-machine interfaceI/O Input/outputIEC International Electrotechnical CommissionIEC 61850 International standard for substation communication and

modellingIEC 61850-8-1 A communication protocol based on the IEC 61850

standard series and a standard for substation modellingIED Intelligent electronic deviceIP Internet protocolIP address A set of four numbers between 0 and 255, separated by

periods. Each server connected to the Internet is assigneda unique IP address that specifies the location for the TCP/IP protocol.

LAN Local area networkLC Connector type for glass fibre cableLCD Liquid crystal displayLED Light-emitting diodeLHMI Local human-machine interfaceNCC Network control center

1MRS756801 A Section 6Glossary

630 series 37Commissioning Manual

Page 46: RE_630_comm_756801 _ENa

PC Personal computer; PolycarbonatePCM600 Protection and Control IED ManagerRJ-45 Galvanic connector typeRMS Root-mean-square (value)Rx Receive/ReceivedSAT Site acceptance testingSOTF Switch on to faultTCP/IP Transmission Control Protocol/Internet ProtocolTCS Trip-circuit supervisionTx Transmit/TransmittedVT Voltage transformerWAN Wide area networkWEI Weak-end infeed logic

Section 6 1MRS756801 AGlossary

38 630 seriesCommissioning Manual

Page 47: RE_630_comm_756801 _ENa

39

Page 48: RE_630_comm_756801 _ENa

Contact us

ABB OyDistribution AutomationP.O. Box 699FI-65101 VAASA, FinlandPhone +358 10 22 11Fax +358 10 22 41094

www.abb.com/substationautomation

1MR

S75

6801

Cop

yrig

ht 2

009

AB

B. A

ll rig

hts

rese

rved

.