13
.)1 ReportNo: Meeting Date: 18-287 November 14, 2018 Alameda-Contra Costa Transit District STAFF RE PORT TO: FROM: SUBJECT: AC Transit Boardof Directors Michael A. Hursh, General Manager East Bay Bus Rapid Transit Project Progress Report BRIEFING ITEM RECOMMENDED ACTON(S) Consider receiving the monthly construction progress report on the East Bay Bus Rapid Transit IBRT) Project for the month of October 2018. BUDGETARY/FISCAL IMPACT Refer to Attachment 1, Slide No. 3 on Project Management and Construction Budgets for the construction contract and professionalservices contracts supporting the BRT Construction and the Funding-Expenditure chart. BACKGROUND/RATIONALE This report is an update on four main areas of the BRT program: design services, construction management, infrastructure and station platform construction, and community outreach/contract compliance. Bid Package 3 Infrastructure and Station Platform Project Construction ConstructionProgress (CP): Milestone lactivities in Segment A (42nd Ave to San Leandro Transit Center) have progressed to interim condition status, except in Zone 9. This means the outside area improvements (curb ramps, sidewalks, drainage, signals, communication conduit and road rehab) and median improvements(median curbs, station platforms and roadway reconstruction) are complete. The electricalcontractor Mike Brown Electric(MBE) is energizing and activatingthe new signalsystem throughoutthe segment. Atotal of 18 BRT platforms(six in SanLeandro andtwelve in Oakland) comprising 15 BRT stations are in interim condition status and being evaluated for bus docking and alignment issues. Milestone 2 activities in Segment B(20th Street at Broadway to 42nd Avenue) continue in Zones 3 through 6 from 2nd Avenue at Lake Merritt to Derby Avenue in the Fruitvale District. Construction activities include building outside area improvements such as curb ramps, sidewalks, drainage, concrete bus pads, road rehabilitation, foundations for the new signaland lighting system, and installation communications conduit. The contractor is also working in Zone 2 along llth Street between Harrison and Madison to relocate an East Bay Municipal Utility District (EBMUD) waterline 1 of 13

RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

.)1 ReportNo:Meeting Date:

18-287

November 14, 2018Alameda-Contra Costa Transit District

STAFF RE PORTTO:

FROM:

SUBJECT:

AC Transit Board of Directors

Michael A. Hursh, General Manager

East Bay Bus Rapid Transit Project Progress Report

BRIEFING ITEM

RECOMMENDED ACTON(S)

Consider receiving the monthly construction progress report on the East Bay Bus Rapid TransitIBRT) Project for the month of October 2018.

BUDGETARY/FISCAL IMPACT

Refer to Attachment 1, Slide No. 3 on Project Management and Construction Budgets for theconstruction contract and professional services contracts supporting the BRT Construction andthe Funding-Expenditure chart.

BACKGROUND/RATIONALE

This report is an update on four main areas of the BRT program: design services, constructionmanagement, infrastructure and station platform construction, and communityoutreach/contract compliance.

Bid Package 3 Infrastructure and Station Platform Project Construction

Construction Progress (CP):

Milestone lactivities in Segment A (42nd Ave to San Leandro Transit Center) have progressed tointerim condition status, except in Zone 9. This means the outside area improvements (curbramps, sidewalks, drainage, signals, communication conduit and road rehab) and medianimprovements(median curbs, station platforms and roadway reconstruction) are complete. Theelectricalcontractor Mike Brown Electric(MBE) is energizing and activatingthe new signalsystemthroughoutthe segment. Atotal of 18 BRT platforms(six in San Leandro and twelve in Oakland)comprising 15 BRT stations are in interim condition status and being evaluated for bus dockingand alignment issues.

Milestone 2 activities in Segment B(20th Street at Broadway to 42nd Avenue) continue in Zones3 through 6 from 2nd Avenue at Lake Merritt to Derby Avenue in the Fruitvale District.Construction activities include building outside area improvements such as curb ramps,sidewalks, drainage, concrete bus pads, road rehabilitation, foundations for the new signalandlighting system, and installation communications conduit. The contractor is also working in Zone2 along llth Street between Harrison and Madison to relocate an East Bay Municipal UtilityDistrict (EBMUD) waterline

1 of 13

Page 2: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

Report No. 18-287Page 2 of4

Milestone 3 activities(milling, curb to curb paving, canopy installations, signing and striping, etc.)have started in Segment A. The pavement milling operations started at 42nd Avenue headingsouth towards San Leandro. The curb to curb paving of rubberized asphalt willfollow the millingoperations with approximately ten days lag. Installing appropriate roadway signage and stripingis the last step during this interim phase

Looking ahead, the contractor expects to continue curb to curb paving activities in Segment A,outside area improvements in Segment B and to start canopy installation in San Leandro.

Construction Management(CM);The current CM (WSP) team has more field inspectors and office engineers than the previousteam, which has enabled more observations and oversight of the construction work andimproved documentation. A proactive process of tracking individualWork Areas(WA) along withreview of the contractor's recovery schedule has helped to better measure the physicalprogressof the construction. This approach willhelp AC Transit better manage OCJones and their progresstoward meeting project deliverables. The CM team continues to work with third party Utilityproviders on relocations, maintaining traffic controls work site safety, and enforcing qualitycontrol. WSP continues to work with the BRT Systems Activation Group comprised of District Staffand OCJ technicalsubcontractors to implement the communications elements of the project(e.g.

fiber optic network, security cameras, ticket vending machines and centralized management ofelectronic systems). The District's remaining administrative priority is to assist OCJ to secure Citypermits to start major infrastructure improvements on Broadway(Zone 1), Chinatown(Zone 2),and Fruitvale (Zone 7).

Northern Layover:The Northern Layover location is an on-street facility on San Pablo Avenue between West GrandAvenue and 21st Street. The Traffic Memorandum required by the City of Oakland has been

approved by the City and is being reviewed by Caltrans. Discussions with Caltrans regarding theplacement of an Operator Restroom Facility are ongoing. The District will finish the CEQA/NEPAanalysis before starting the construction in early 2019.

San Leandro Transit Center

The San Leandro Transit Center Project is separately funded by a Congestion Mitigation and AirQuality Improvement grant for key capital investments by AC Transit in coordination with BARTand the City of San Leandro. The project will reconfigure the bus transit center within the SanLeandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT)southern terminus, other AC Transit routes, and other transit services. Construction is expectedto start in early 20]-9 and be complete by July 2019.

Community Outreach and Public Engagement

The Outreach Team continues its daily stakeholder engagement efforts along the BRT corridor,including in-person visits with residents and businesses, email and phone requests foropportunities to present updates, and participation in community festivals and events.

2 of 13

Page 3: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

Report No. 18-287Page 3 of4

The outreach team's day-to-day focus remains on 1) ensuring businesses/stakeholders know inadvance about the upcoming start of construction; 2) daily monitoring of active work areas toensure construction impacts are minimized and issues addressed as quickly as possible; and 3)troubleshooting issues reported by corridor stakeholders.

During the month of September and the first two weeks of October, the outreach team loggedthe following interactions:

In addition to the daily activities associated with monitoring construction progress andtroubleshooting issues on the corridor, the team continues its efforts to share information withthe generalpublic on the status of the project, its many benefits and key features. This includesattending community events and meetings. Below is the list of events attended andpresentations made in the month of October:

Project Labor Agreement/Construction Careers Policy

The project's local hire utilization percentage has been hovering around 34% for the past fewmonths. Although short of the 50% goal, AC Transit continues to make progress. The Districtmonitors the contractor and its subcontractors' routinely submitted good faith efforts to hirelocal residents to the extent practicable. The region has seen a massive growth in constructionprojects, limiting the supply of local workers, and as a result, contractors on this project havebegun including off-site local hire credit requests, which are now being incorporated into thecurrent percentage

Outreach Team Interactions September2018

October1-15,2018

TotaINumber oflnteraction Activities logged 121 91

Number ofindividualstakeholders interacted withjunduplicated)

79 57

Total Complaints 8 8

.Access 6 lBusiness is slow 0 l

Parking l 4

trash l 0

Construction Debris 0 lA/iter Service Disruption 0 l

l0/03/18 Unity CounciIFruitvale Business Improvement District "Property OwnersMeetin g"

l0/06/18 Oakland Black Cowboy Parade & Festivall0/09/18 Allen Temple Arms l& lIResident CounciIMeeting

lO/13/18 The Oakland Mayor's Commission on Aging: Community Presentation &Listening Session

lO/18/18 Beat 32X Neighborhood Crime Prevention Council(NCPC)l0/24/18 Alameda County Department of Public Health

3 of 13

Page 4: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

Report No. 18-287Page 4 of4

ADVANTAGES/DISADVANTAGES

This report is a monthly construction update and there are no associated advantages ordisadvantages.

ALTERNATIVESANALYSIS

There is no analysis of alternatives required for this report

PRIOR RELEVANT BOARD ACTION/POLICIES

There are no relevant Board actions related to this report

AmACHMENTS

1. BRT Progress Presentation

Approved by:

Reviewed by:

Ramakrishna Pochiraju, Executive Director of Planning and Engineering

Denise C. Standridge, General CounselClaudia Allen, Chief FinancialOfficerBeverly Greene, Executive Director of External Affairs, Marketing &Communications

Claudia Burros, Director of Legislative Affairs and Community RelationsDavid Wilkins, BRT Program DirectorSteven Jones, BRT Outreach ManagerWilliam Toms, Director of Project Controls and Systems AnalysisPhillip Halley, Contracts Compliance Administrator

Prepared by:

Project Labor Agreement/ Construction Career Policy (PLA/CCP) Outreach:l0/03/18 AC Transit Roots Community Health Clinic Job Fairl0/08/18 Beyond Emancipation Readiness Training

l0/09/18 Merritt College Job & Resource Fair

4 of 13

Page 5: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

C00:

E

$

n

a>

a>Ea)>0

B0E0ameg0D>00

5 of 13

Page 6: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

n

QC0

00

0C

/

C

QBF

-Ea)C

e

0C

B0C

&CB0CB00

B

C

a,$ e5'E

:3

>

0

E

CdB

I''A

{

emQ

..I>

C

Ca)E) LJ

R00

a)CQN

qg

%

p€s.8 33

av") i

CEaJ

aCQN>

RQ'=

b

0

{'U I

00 RaC0N

a>0C0N

a)

B

naJ

0NQZb

I

e90N

LO Qa)

l-x

£t,.u+

a)>

'cR0

£0N

C0Ln

0

e-+

J L-

a.} +-l

a)0

0Nc.a3

[

£0

a} .J

oa£''la

N0 C

g0C0

C

6 of 13

Page 7: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

H>n<a)Qe0H=C0

P

\.Q8eg0\.

'GCGCB(.a0g'<'BQ':+'qeE(.a

g'<

'De'+0>

.

BB'DGea©c.0

€QaeE(.a

Cg0D>-

0a

8H8

LQS

0 $

g $

g $

0g

g

hi

gi

gi

0$

g

g

7 of 13

Page 8: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

8 of 13

Page 9: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

a)=

m

\

\

\

\

\

\

\

\

\

\

£'DC=

:b:

3+3Bg3Q.

X

3mC

Cc:3a)Ca)

C06B6F

C3a)

C3

gQ.

03g

a>0

00LO

suo1111W

9 of 13

Page 10: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

0

gQ

.

e

iQ.

0

. D

10 of 13

Page 11: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

]

gVf

e0nCa>a>Cea)>=0a>00

l

t

+

0CC

C0

>

a)C

CC; 'a

a)C

CIJ

>

=C3EE000M

CE

C(.a

0

0EC0

0F C

mC0

c)0

©ng=01=l

a

'=B0

CaJE

EC3

C3C

mQ

.E£

C

Q.

Dg

EC3E

E

CF''' L.

a)'c)

+-)

C

C0C

C©0

Q.

aJG0

30 C

E aJ

[-

QO

0000

00000

0

0000

\\0 0

''-.\0

0

11 of 13

Page 12: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

30=C0Q.

0F-

30=a;Ca)

Bn

H0t.a30=0F-

©<0a>a>C0H=C0Ca>Ea)a>0a>0

ll=C0NBBa>

£0Ba

ga)

g0C3C

e30=a)Ca)0

'"""-l"-

r'\l30 C

D

a)0a)

g=

a)cuCcu>

. .

tO02,

. D

$ @l CP

a)0'e

cu

ncu cu cu cu

-+-J

-+-J

-b-U -b-U

12 of 13

Page 13: RE PORT - AC Transit · 2018. 11. 8. · Leandro BART Station to better accommodate the East Bay Bus Rapid Transit Project (BRT) southern terminus, other AC Transit routes, and other

0bl.... IJ

0Ca>na>aQCa>

n.0nNnnnmam

=0gg

D0q'

r---l

Za0BR0

B

0

=0Pg

Qg0B

0ZC0

C0C0=£0

B>C0Be0Q.

Z01-nED

0£a)£

k00B

=00

a)Q.

P£0

'u£0

3

. D

n

13 of 13