By: Tamer Farid Rev. 6 G1201 Adams Challenge Event Description [Contract] Key Date Effective Date of Agreement 5-Nov-14 Start of Cutting Project Steel 15-Dec-14 Mobilization of Sleeper / Riser Installation Marine Spread 14-Aug-15 Completion of Full Deck Main Structure + Full Jacket Fabrication 7-Sep-15 Mobilization of Pipeline / Platform Installation Marine Spread 8-Sep-15 Installation of Jacket at the Worksite 10-Oct-15 Completion of Installation of All Pipelines 21-Nov-15 Installation of the Rashid-C Deck at the Work Site 24-Nov-15 Pre-Commissioning of All Pipelines 26-Dec-15 Mechanical Completion of All Facilities 26-Dec-15 Handover of All Project Documentation 4-Feb-16 DSV Adams Challenge Sleepers Installation SMART Flange Preparation Risers Installation Bowstring Installation Production Spools Metrology, Closing Spools, Jacket Grouting, Crossing Completion, Susea Protection Frames & Bowstring Removal Pre-commissioning Support DSV Oceanic Installer Subsea FCG of 14" & 20" Replacement Pipelines Metrology, Fixed & Closing Spools Installation G1201 Rashid C Jacket & Boat Landing Installation Pipelines Installation (30", 20" & 14") Pipelines Installation (18", 10" & 12") Deck Installation Pre-Commissioning 30", 20" & 14" 18", 12" & 10" Feb-16 Mar-16 Jan-16 May-15 Dec-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Jacket Topsides Piles Risers Tie-in Spools Installation Aids Pre-Engineering Survey Geophysical & ROV Jacket Face Surveys Bowstring Installation (4 nos.) Concrete Sleepers Installation 102 Km of Pipelines; 30", 20", 18", 14", 12" & 10" In-line Barred Tees (6 nos.) Risers (8 nos.) + Riser Clamps (29 nos.) Free Span Corrections Tie-in / Closing Spools Production Spools Smart Flanges (8 nos.) Valve Assemblies Subsea Protection Frames (6 nos.) FCG & Hydrotest of all Pipeline Systems. De-watering & Nitrogen Purging of 10" Gas Lift Pipeine System. As-Built Survey ROV & CP Potential Surveys Pre-Commissioning Fabrication (Dubai Dry Docks) DSV Preparatory Works Scope of Work DSV Works Pipelying (G1201)

Rashid C_Synopsis_R6

Embed Size (px)

Citation preview

By: Tamer Farid Rev. 6

G1201Adams Challenge

Event Description [Contract] Key Date

Effective Date of Agreement 5-Nov-14

Start of Cutting Project Steel 15-Dec-14

Mobilization of Sleeper / Riser Installation Marine Spread 14-Aug-15

Completion of Full Deck Main Structure + Full Jacket Fabrication 7-Sep-15

Mobilization of Pipeline / Platform Installation Marine Spread 8-Sep-15

Installation of Jacket at the Worksite 10-Oct-15

Completion of Installation of All Pipelines 21-Nov-15

Installation of the Rashid-C Deck at the Work Site 24-Nov-15

Pre-Commissioning of All Pipelines 26-Dec-15

Mechanical Completion of All Facilities 26-Dec-15

Handover of All Project Documentation 4-Feb-16

DSV Adams Challenge

Sleepers Installation

SMART Flange Preparation

Risers Installation

Bowstring Installation

Production Spools

Metrology, Closing Spools, Jacket Grouting, Crossing

Completion, Susea Protection Frames & Bowstring Removal

Pre-commissioning Support

DSV Oceanic Installer

Subsea FCG of 14" & 20" Replacement Pipelines

Metrology, Fixed & Closing Spools Installation

G1201

Rashid C Jacket & Boat Landing Installation

Pipelines Installation (30", 20" & 14")

Pipelines Installation (18", 10" & 12")

Deck Installation

Pre-Commissioning

30", 20" & 14"

18", 12" & 10"

Feb-16 Mar-16Jan-16May-15 Dec-15Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15

Jacket

Topsides

Piles

Risers

Tie-in Spools

Installation AidsPre-Engineering

Survey

Geophysical & ROV Jacket Face

Surveys

Bowstring Installation (4 nos.)

Concrete Sleepers Installation102 Km of Pipelines; 30", 20", 18", 14",

12" & 10"In-line Barred Tees (6 nos.)

Risers (8 nos.) + Riser Clamps (29 nos.)

Free Span Corrections

Tie-in / Closing Spools

Production Spools

Smart Flanges (8 nos.)

Valve Assemblies

Subsea Protection Frames (6 nos.)FCG & Hydrotest of all Pipeline

Systems.De-watering & Nitrogen Purging of 10"

Gas Lift Pipeine System.As-Built Survey ROV & CP Potential Surveys

Pre-Commissioning

Fabrication

(Dubai Dry Docks)

DSV Preparatory

Works

Scope of Work

DSV Works

Pipelying

(G1201)