    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJPAGE

    2 of 19

    REVISION

    0BRZ

    CHANGE RECORD

    REVISION

    NUMBER

    ITEM

    NUMBER

    DESCRIPTION OF CHANGE

    A   ALL Issued for IDC

    B Issued for Approval (IFA)

    C Re- IFA

    0 Approved for construction

  • 8/18/2019 Ras Gas Work pack

    4/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) and

    associated pipe workbetween the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJPAGE

    3 of 19

    REVISION

    0BRZ

    TABLE OF CONTENTS

    1.0  SUMMARY ......................................................................................................................... 5 

    1.1  Justification ......................................................................................................................... 5 

    1.2  Corresponding eMOC Number ........................................................................................... 5 

    1.3  Outline Scope of Work ........................................................................................................ 5 

    1.3.1  Disciplines ........................................................................................................................... 5 

    1.4  Equipment / System Affected / Impacts to Operations ....................................................... 6 

    1.5  Related Workpacks ............................................................................................................. 6 

    1.6  Shutdown Content .............................................................................................................. 6 

    1.7  Engineering Queries ........................................................................................................... 6 

    1.8 

    Special Requirements ......................................................................................................... 7 

    1.9  Isolations ............................................................................................................................. 8 

    1.9.1  Workpack Isolations ............................................................................................................ 8 

    1.10  Work excludes from this workpack ..................................................................................... 8 

    2.0  SCOPE OF WORK ............................................................................................................. 9 

    2.1  Offshore Construction ......................................................................................................... 9 

    2.1.1 Pipe Activities………………………………………………………………………………………9 

    2.2  Tie ins ................................................................................................................................. 9 

    2.2.1 Pipe Tie-ins ………………………………………………………………………………………..9 

    3.0  DRAWING & DOCUMENTS ............................................................................................. 10 

    R f &

  • 8/18/2019 Ras Gas Work pack

    5/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) and

    associated pipe workbetween the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJPAGE

    4 of 19

    REVISION

    0BRZ

    5.3 Safety Checklist……………………………………………………………………..…………..12 

    5.4 Accident / Incident Reporting………………………………………………………..…………12 

    5.5 Special Requirements………………………………………………………………..…………13 

    5.6 Habitats………………………………………………………………………………..………….13 

    5.7 Scaffolding………………………………………………………………………………..………13 

    6.0 MATERIALS…………………………………………………………………...…………………14 

    6.1 Key/Critical items of equipment……………………………………………..…………………14 

    6.2 MTO by Workpack………………………………………………………………..……………..14 

    6.3 Equipment & Consumables……………………………………………………..……………...14 

    6.4 Materials Queries………………………………………………..……………………………....14 

    7.0 CONSTRUCTION METHOD STATEMENT……..……………………………………………15 

    7.1 

    Subcontractor / Vendor Assistance .................................................................................. 15 

    8.0 

    JOBCARDS ...................................................................................................................... 15 

    9.0  INSPECTION AND TEST CETIFICATION REQUIREMENTS ......................................... 15 

    9.1  Completion / Handover Certificates .................................................................................. 15 

    9.2  Inspection & Test Summary Requirements Matrix ........................................................... 16 

    9.3  Test Packs ........................................................................................................................ 16 

    10.0 

    TECHNICAL QUERIES .................................................................................................... 17 

    11.0 AS BUILDING…………………………………………………………………………………….20 

    12.0 ATTACHMENTS…………………………………………………………………………………21 

  • 8/18/2019 Ras Gas Work pack

    6/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) and

    associated pipe workbetween the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    5 of 19

    REVISION

    0BRZ

    1.0 SUMMARY

    1.1 Justification

    The existing potable water system on the RGA LQ will be tied into and combined with the new

    potable water system on the ALQ. This will provide greater capacity and flexibility.

    1.2 Corresponding eMOC Number

    This will be supplied by RG eMOC initiator in a later revision.

    1.3 Outline Scope of Work

    1. Install all new required pipe supports (pipe supports are detailed in the pipe support

    workpack).

    2. Under the guidance of RG Operations& PMT conduct all required shutdowns (QT-Y-9402Potable water Press. Set), isolations and LOTOs (5 valves total, see section 1.9.1).

    3. Depressurise as required.

    4. Remove blind at TP-PI-07A

    5. Install tie in tee piece (including new isolation valve HV393 NC in closed position).

    6. Carry out any required testing

    7. Under the guidance of RG Operations & PMT remove all isolations and LOTOs.

    8. RG Operations to bring QT-Y-9402 Potable Water Press Set back into service.

    9. Install piping (new line QT-WPT-840-4”-DBS1) between tie in location TP-PI-07B and ALQ

    closure spool location

  • 8/18/2019 Ras Gas Work pack

    7/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) and

    associated pipe workbetween the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    6 of 19

    REVISION

    0BRZ

    The tie in TP-PI-07 will require the potable water press set to be shut down. This will restrict

    the potable water supply. Review the best time to execute this work with Operations

    (potentially night shift work).

    HHI piping engineering & construct ion to consider installation of the new pipe spools. There

    is limited crane access in this area.

    1.3.1 Disciplines

    Disciplines Included In Work Scope: 

    Piping Structural Electrical Instruments Rigging Scaffolding Vendor Other

     Pipe

    supports  1 

    1.4 Equipment / System Affected / Impacts to Operations

    The potable water maker and associated systems will require to be shut down during thispiping modification. To be assessed with, and confirmed by, RGA Operations.

    This work scope will be planned so that potable water supply will still be available from

    the water stored in the storage tanks.

    1.5 Related Workpacks

    There are no workpacks related to this scope of work.

    1.6 Shutdown Content

    The potable water maker and associated systems will require to be shut down during this

  • 8/18/2019 Ras Gas Work pack

    8/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) and

    associated pipe workbetween the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    7 of 19

    REVISION

    0BRZ

    HHI DCC DCC TBC

     All Engineering Queries are to be accompanied by a standard HHI engineering Query

    Form.

    1.8 Special Requirements

    The below table highlights activities for the attention of RasGas Operations.

     Activity Yes No

    Hot Work Yes 

    Stress Relieving No

    Lifting  Yes  

    Blocked Access/Egress Yes

    Scaffolding  Yes

    Use of Existing Facilities  Yes

    External Working Hours / Shift Pattern No

    SIMOPS No

    Overboard Work No

    HYDM Test No

    Pressure Testing using N2 No 

    Radiographic test No

     

  • 8/18/2019 Ras Gas Work pack

    9/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) and

    associated pipe workbetween the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    8 of 19

    REVISION

    0BRZ

    1.9 Isolations

    Isolation information will be updated in later revisions.

    1.9.1 Workpack Isolations

    The following lines and/or equipment require isolation in accordance with the above prior

    to work commencing under this workpack

    Isolation

    Number

    SystemLine and/or

    Equipment No.Scope

    Description

    P&ID

    1 Existing Potable

    Water

    Valve BBFS8 HV0031 Close valve and

    LOTO

    4950-QT-PR-4104

    2 Existing Potable

    Water

    Valve BBFS8 HV0035 Close valve and

    LOTO

    4950-QT-PR-4104

    3 Existing Potable

    Water

    Valve BBFS8 HV0039 Close valve and

    LOTO

    4950-QT-PR-4104

    4 Existing Potable

    Water

    QT-P-9401A, Valve

    HV0112

    Close valve and

    LOTO

    4950-QT-PR-4104

    5 Existing Potable

    Water

    QT-P-9401A, Valve

    HV0113

    Close valve and

    LOTO

    4950-QT-PR-4104

    6 Existing Potable

    Water

    BBFS8 HV393NC Close valve and

    LOTO

    4950-QT-PR-4104

    Refer to Attachment No. 03) for P&ID mark-up of isolations to facilitate tie-ins.to be

    completed for 1st issue.

  • 8/18/2019 Ras Gas Work pack

    10/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) and

    associated pipe workbetween the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    9 of 19

    REVISION

    0BRZ

    2.0 SCOPE OF WORK

    2.1 Offshore Construct ion

    HHI will provide a scope of work detailing all construction activities required during the

    execution of this workpack.

    2.1.1 Piping Act ivi ties

    1. Install all required scaffolding required for this workpack (see the construction method

    statement for details).

    2. Install all new required pipe supports (locations to be confirmed by HHI piping post

    piping-survey). (Note: If the installation of supports requires Hot Work then installation

    of appropriate welding habitat (pressurised or non-pressurised) shall be done prior to

    starting the work.)

    3. Make all required isolations and LOTOs required to install the tie in spool (see section1.9.1).

    4. Make tie in. Remove LOTOs.

    5. Install new piping from ALQ to tie in location.

    6. Isolate and LOTO new valve BBFS8 HV393NC

    7. Make tie in at TP-PI-07B

    8. Remove isolations.

    2.2 Tie ins

    2 2 1 Pi i Ti i

  • 8/18/2019 Ras Gas Work pack

    11/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    10 of 19

    REVISION

    0BRZ

    3.0 DRAWING & DOCUMENTS

    3.1 Reference Drawing & Documents

    Included in this section are the following reference document types (as required) :

    Tie-in Register

    Marked up Drawings

    Isometric Drawings

    3.1.1 Tie-in Register

    Document No. Title Rev

    BRZ-QT-L-PN-0001TIR COMBINED ALQ & RGA A

    3.1.2 Marked up drawings

    Drawing No. Title Rev

    49450-QT-PR-4104 QUARTERS PLATFORM PIPING &

    INSTRUMENTATION DIAGRAM POTABLE

    WATER MAKER. 

    7D

    49450-QT-PR-4108 QUARTERS PLATFORM PIPING &

    INSTRUMENTATION DIAGRAM WASHDOWN

    SYSTEM

    9D

    49450-QT-PR-4104  P&ID marked up to show isolation points. 

  • 8/18/2019 Ras Gas Work pack

    12/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    11 of 19

    REVISION

    0BRZ

    Note all pip ing destruct and construct Isometrics are to be included and attached in

    this workpack.

    4.0 PROCEDURES / SPECIFICATIONS / REFERENCES

    The following RasGas documents will be adhered to during the execution of this workpack.

    TO BE INCLUDED IN LATER REVISIONS.

  • 8/18/2019 Ras Gas Work pack

    13/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    12 of 19

    REVISION

    0BRZ

    5.0 SAFETY

    Refer to JSA attachment 7.

    5.1 General

     All construction activities shall comply with the RasGas Safety Management System.

    5.2 Permit to Work System

    The RasGas Permit To Work system has been designed to assist CONTRACTOR and

    operating personnel working on RasGas offshore installations to carry out work in

    accordance with safe working practices.

    The PTW system includes regulations, procedures, documentation and guidance notes

    laying down the conditions of work and precautions which must be taken by HHI during

    the execution of any work to ensure safety of both personnel and plant. The permit to

    work system has been designed as both a working and reference document.

    The permits issued for work in this workpack will be discussed at the permit meeting prior

    to the commencement of the work.

     All permits must be applied for by HHI PTW trained personnel a minimum of 24 hours in

    advance of commencing the work.

    5.3 Safety Checklist

    The following activities will be carried out :

    a. Discuss work scope permits with the production / discipline supervisors 

    b Tool box talk with foreman / charge-hand

  • 8/18/2019 Ras Gas Work pack

    14/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    13 of 19

    REVISION

    0BRZ

    RasGas will be informed of all hot work requirements after the site verification study.

    5.6 Habitats

    Consultation is required with RasGas operations before establishing temporary habitatrequirements prior to construction work commencing. HHI is to supply and install the

    necessary material for the habitats.

    5.7 Scaffolding

    HHI will ensure Scaffolding erected for installation activities does not inhibit F&G

    detection or deluge system.

    Plans for Scaffolding will be submitted by HHI to RasGasOperations30 days in advance

    of any planned erection.

  • 8/18/2019 Ras Gas Work pack

    15/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    14 of 19

    REVISION

    0BRZ

    6.1 Key/Crit ical items of equipment

    POS for Key/Critical items of equipment identified by workpack and by tie-in, will be

    included in the 1st revision of each workpack.

    Item PO Number Vendor Supplied by

    BULK ITEM XXX XXX HHI Offshore

    VALVE XXX XXX HHI Offshore

    6.2 Workpack MTO4” Bolt/Nut & gasket. See attached isometric drawing.

    6.3 Equipment & Consumables

    Construction Information to be included in later revisions.

    6.4 Materials Queries

    Refer all materials queries to HHI Materials Coordination focal point

    Name e-mail Telephone Number

    TBC

    Material for this work scope is held at HHI onshore materials storage facility, in Ulsan andwill be shipped directly to the platform after being checked and confirmed by HHI

    Brownfield Engineer.

    •  All materials are to be checked on arrival to the platform to ensure that there has

  • 8/18/2019 Ras Gas Work pack

    16/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    15 of 19

    REVISION

    0BRZ

     All required work to complete this workpack will be executed under the RG PTW system. All PTW will

    be completed and submitted to RG Operations the day before the planned work.

    HHI will only perform LOTO and Isolations under the guidance of RG Operations & RG PMT.

     All bolts will be hot bolted before proceeding with tie-in work.

    Testing will be as per the line list.

    Prefabrication of pipe spools will be maximized.

    This work will be completed in stages as per the level 3 schedule. This workpack can only be

    completed after the ALQ installation.

     Any pipe work that is pre-installed before the ALQ installation will have a cap end installed to protect

    the pipe.

    Scaffolding will be set up so all workers have a safe working platform.

    This work will be conducted by the following team: 1 supervisor, 5 pipefitters & 1 safety.

    7.1 Subcontractor / Vendor Assistance

    No need any subcontractor / Vendor because HHI will perform.

    8.0 JOBCARDS

    CONSTRUCTION INFORMATION TO BE INCLUDED IN LATER REVISIONS.

  • 8/18/2019 Ras Gas Work pack

    17/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    16 of 19

    REVISION

    0BRZ

    9.2 Inspection & Test Summary Requirements Matrix

    The following Discipline Inspection and Test Summary’s are applicable to this workpack

    Discipline Platform System Ref. MC-1 Ref.

    Electrical / Mechanical

    Note: Discipline, Inspection and Test Summary’s detail minimum certification

    Examples of additional certification.

    Calibration, NDT, Leak Testing, Coating, Load Testing or Bolt Tensioning

    Punch list.

    Discipline punch lists are included within each ITS. Record outstanding items according

    to original work scope at handover stage

    9.3 Test Packs

  • 8/18/2019 Ras Gas Work pack

    18/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    17 of 19

    REVISION

    0BRZ

    10.0 TECHNICAL QUERIES

  • 8/18/2019 Ras Gas Work pack

    19/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    18 of 19

    REVISION

    0BRZ

    11.0  AS BUILDING

    HHI will follow the BARZAN Project as-building procedure.

    The contractor shall be responsible for preparing redline as built mark-ups for any agreed

    deviation to the AFC design during installation, pre-commissioning and commissioning. 

    During installation, all design changes must be marked-up / as-built on the relevant

    drawings and collated onto the designated RasGas workpack set of documents. Upon

    completion of mechanical completion / commissioning / system hand-over, all drawings

    must be stamped “As-Built”, signed and dated (including those drawings that have no

    changes). Contractor to prepare field sketch for any obstruction / clashing occur as per project design

    document and shall obtain RasGas PMT Operations approval prior to start with the work.

  • 8/18/2019 Ras Gas Work pack

    20/30

     

    DOCUMENT TITLE Potable Water System Tie-

    in(TP-PI-07A&B) andassociated pipe work

    between the RGA LQ and ALQ module

    DOCUMENT Number

    BRZ-QT-WP-PN-0002

    PROJ

    PAGE

    19 of 19REVISION

    0BRZ

    12.0  ATTACHMENTS

    1) 49450-QT-PR-4104 QT Platform piping & instrumentation potable water maker.

    2) 49450-QT-PR-4108 QT Platform piping & instrumentation wash down system.

    3) 49450-QT-PR-4104 P & ID Isolation Mark Up.

    4) Isometrics to be attached in a subsequent revision.

    5) Model shots and Photographs.

    6) Model shot for interconnecting line between ALQ and QT.

    7) JSA-PN-0002

  • 8/18/2019 Ras Gas Work pack

    21/30

  • 8/18/2019 Ras Gas Work pack

    22/30

  • 8/18/2019 Ras Gas Work pack

    23/30

    1

  • 8/18/2019 Ras Gas Work pack

    24/30

     

    N

    2 2

    SEE SHT

    SHT 1

    E 67294

    N 61991

    EL +29992

    59

    4 NPD

    4X4 NPD

    6

     

    6

    4

    5

    1

    EL +29541

    4 N

    PD

    5

    8

    230

    STEM W 4 5 .0 S

    5

     

    7

    5

     

    5

    CONN TO

    QT-T-9401A/ A1

    4 FFF E 150#

    E 66708

    N 63124

    EL +29541

    4

    8

    8

    5

    6

     

    8

    8

    4X4 NPD

     

    8

    7

    INSUL:

    N

    E 60655

    N 61804

    EL +2 9 9 9 2

    INSUL:

     0’ 0

    TP-PI-07

     

    5

    9

    CONN TO

    QT-Y-9402/ II

    4 F FFE 150#

    E 60655

    N 6 2 3 5 0

    EL +29992

    QT-WPT-388-DBS1-N

    QTPA0112

      U

    QT-WPT-388-4 -DBS1-N

    49450-QT-PR-4104

    QT-WPT-388-DBS1 0.5000 25. 00 8.6200

    48.90

    0.000 DBS1

    N O PA I N T 4 N

    0.0

    ANALY

    NONE

    2 2

    R ASGAS OFFSHOR E EXPANSION PR OJ EC T

    PDS Model Number:

    PAINT

    N O TES: -

    I

    F

    N

    m

    e

     

    %

    CHECK ISOMETRIC

    RasGas Company Limi ted

    CONSULTANT/CONTRACTOR :

    HEAVY INDUSTRIES CO., LTD.

    402025-00546

    N

     

    FABRICATION MATERIALS

      U

    T SIZE

    NO COMPONENT DESCRIPTION (Inch) ITEM CODE QTY

    SEE ISO

    QT-388

    E 60655

    F4 G7 B8

    TP-PI-07

    QT-WPT-840-4 -DBS1-N

  • 8/18/2019 Ras Gas Work pack

    25/30

      U  U  U

    1 PIPE D1784 SL-PE S/80 4 1PPP0180 7.8 M

      U

    2 TEE STR D1784 SW S/80 4X4 3TSP0180 1

      U

    3 ELBOW 90D D1784 SW S/80 4 3ELP0180 5

      U

    4 FLG WN D1784 FF 150 -S/80 4 2FWP0018 7

      U

    5 FLG BLD D1784 FF 150 4 2FBP0010 1

      U

      U

      ERECTION MATERIALS

      U

    T SIZE

    NO COMPONENT DESCRIPTION (Inch) ITEM CODE QTY

      U

      U

      U

    6 PIPE PE S-80 CPVC, D1784 CL 23447-B 4 PIPPPP5 1.8 M

      U

    7 GSKT GARLOCK-3400 FULL FACE 150#-1/16 4 5GF05J34 6

      U

    8 STUD B/N/PW A193B7M/A1942HM XYLAN, 110.0MM BOLT 5/8 6BN0270P 48

      LENGTH

     9 VALVE BALL FB CPVC FF 150# TAG NO:BBFS8 4 7VBBFS8X 1

      U

      PIPE SUPPORTS

      U

    0 PC02-4 4 PSL 2

      U

    1 REST 4 PSL 1

      U

    2 IS01 4 4 PSL 1

      U

      PIECE MARKS

      U

     SP 1 SP2 SP3 SP4

      U  U

      CUT PIPE LENGTH

      U

    PIECE LENGTH NPD REMARKS PIECE LENGTH NPD REMARKS

      NO (MM) (IN) NO (MM) (IN)

      U

      169 4 206 4

      1250 4 387 4

      164 4 1474 4

      1722 4 327 4

      3605 4 150 4

    N 61975

    EL +29992

    *UNDEFI NED*

    SP

    <

     

    >

     

    N

    P

    D

    *UNDEFI NED*

    2

    4

    3

    2

    4X4 NPD

    *UNDEFI NED*

    <

     

    >

     

    *UNDEFI NED*

    2

    7

    9

    4 G7 B8

    380

    9

    F4 G7 B8

    *UNDEFI NED*

    SP2

    3

    5

    2

    S10

    3-074

    <

     

    >

     

    *UNDEFI NED*

    1

    3

    2

    3

    3

    *UNDEFI NED*

    <

    4

    >

     

    *UNDEFI NED*

    5

     

    3

    *UNDEFI NED*

    <

     

    *UNDEFI NED*

    2

    3

    EL +29695

    *UNDEFI NED*

    1

    1

    1

    4

    S10

    3-071

    <

    6

    >

     

    *UNDEFI NED*

    1

    6

     

    7

    3

    67

    *UNDEFI NED*

    9

    2

    9

    S11

    3-093

    <

    7

    >

     

    *UNDEFI NED*

    1

    7

    2

    9

    F4

    F4 G7 B8

    *UNDEFI NED*

    3

    3

    3

    SP3

    <

    8

    >

     

    *UNDEFI NED*

    66

    SP4

    3

    *UNDEFI NED*

    6

    4

    3

    S12

    3-166

    <

    9

    >

     

    4

     

    N

    P

    D

    *UNDEFI NED*

    3

    6

    7

    8

    F4 G7 B8

    SEE ISO

    QT-WPT-840-1

    E 53382

    N 60055

    EL +29695

    *UNDEFI NED*

    <

    1

     

    >

     

    *UNDEFI NED*

    2

    2

    3

    F4 G7 B8

    5

    Q

    T

     

    A

    D

    W

    T

    R

    H

    D

    2

    D

    QT05-WPT-840-1

    DBS1

    QT05

    QT-WPT-840-4 -DBS1-N

    N

    D

    N

    M

    O

    N

    LINE NO.

    PACKAGE No.

    P&ID REF.

    PWHT

    PAINT SYSTEM No.

    INSULATION

    SPOOL DATA

    PROJECT

    TYPE

    THK

    NOTE

    GAD REF.

    RT MT

    UT PT

    E

    T

    A

    C

    T

    N

     

    D

    A

    T

    1. ORIGIN POINTS

    CODE

    SUB BLOCK.

    ASME B31.3

    SPEC I S O D W G N O .

    R E V N o

    ULSAN KOREA

    (Q525)

    OFFSHORE & ENGINEERING DIVISION

    /N

    1

    2

    3

    4

    5

    6

    7

    8

    9

    SPOOL NO

    SHT NO

    STAGE NO REV

    DESIGNED

    [A](E 0 mm) &

    [4](N 0 mm)

    CHECKED

    FOR FABRICATION

      RZ N

    BRZ-ALQ-D-PN-

    BRZ-ALQ-D-PN-

    5 Attachment Model shot and Photograph

  • 8/18/2019 Ras Gas Work pack

    26/30

  • 8/18/2019 Ras Gas Work pack

    27/30

    6 Model shot for interconnecting line between ALQ and QT

    QT05-WPT-840-1

     Appendix –JSA Form

  • 8/18/2019 Ras Gas Work pack

    28/30

     Appendix JSA Form

    Job Safety Analysis forPotable water tie ins TI-PI-07A/B 

     ActivityWorkOrder

    FunctionLocation

    Piping tie-ins andassociatedpipework 

     At minimum, the following PPE is required for task

    •  Approved and inspected Hard Hat

    •  Safety Glasses with side shields

    •  Long sleeves coverall

    •  Approved gloves to be worn at all times (no

    cotton gloves)•  Approved Safety foot wear

    **Mandatory control measures for all steps

    Reviewed by Signature Date

    Notes:

    1. Job start meeting is to be held on the RGA Complex. At this meetingthe Workmethod and JSA will be reviewed and signed by all personnelinvolved in the taskany additional hazards identified will beadded to this

    JSA and the summary sheet.2. Emergency procedure and Rescue plan will be discussed at the Job

    Startmeeting.3. Work to be completed under PTW-Conditions.PTW must be on site and

    signed by all personnel involved in task.

    4. This is a living document and as such may be subject to review at anytime asidentified changes in conditions / work scope may dictate.Where a change has been identified, this will be managed in line with

    HHIProcedures, Instructions, Specifications and Standards and will beexecuted/interfacedin accordance with other SHE&S Systems.

    Amendments to the JSA may be added (written) / removed at thework sitewhen agreement has been reached by all concerned parties. 5.

    This shall beupdated in JSA summary sheet, if available

    JSA No: 0136 JSA

    Title:

  • 8/18/2019 Ras Gas Work pack

    29/30

    System: Train:

    Task description:

    UncontrolledRisk

    ResidualRisk

    STEP ACTIVITY HAZARD H M L CONTROL MEASURES H M L1.  Scaffolding  A.  Working at height 

    B.  Pinch points  L 

    A.  Working at height procedure, safe working 

    platform 

    B.  Correct PPE (gloves) L 

    2  Installation of  new 

    piping 

    A.  Working at height 

    B.  Erecting scaffold platform 

    on grating. 

    C.  Use of  manual tools 

    A.  Working at height procedure 

    B.  Personnel tied off  at all times; even when lower 

    than handrail. 

    C.  Correct PPE (gloves) 

    Tie‐ins

     A.  Pressurized

     lines

      L  A.  RG LOTO and Isolation procedure  L 

     Approved Signature Print Title: Date

    Performing Party Signature Print Title: Date