Quality Center Update. Eileen Hall Ken Kasparian. Nodal Quality is of Increasing Concern. Areas of Concern Limited testing in lower environments Late detection of defects increasing defect resolution time Increased number of releases requires support for multiple versions of software (2+) - PowerPoint PPT Presentation
Citation preview
May 22, 2008TPTF
Quality Center Update
Eileen HallKen Kasparian
22
Nodal Quality is of Increasing Concern
• Areas of Concern
– Limited testing in lower environments
– Late detection of defects increasing defect resolution time
– Increased number of releases requires support for multiple versions of software (2+)
– Defects not uniformly prioritized from a program perspective
– Currently do not have integrated test environment
– Final builds of critical components have not been integrated
• Mitigation Measures
– Provide for adequate test cycles in revised schedule
– Minimize number of releases/builds
– Program level participation in defect prioritization
– Accelerate build out of integrated test environment
33
Nodal FAT Active Defects by Severity by Project
Problems areas include:
NMMS has 30 Severity 1 and Severity 2 defects
MMS has 14 Severity 2 defects
OS UI has 10 Severity 2 defects
EIP has 9 Severity 1 and Severity 2 defects
Note – Includes New, Open, Reopen, Fixed and Test
The number of Severity 1 and Severity 2 defects is increasing.
44
Nodal Active Defects by Severity Trend
• Severity 3 trend is remaining relatively constant (784 currently outstanding)• Severity 2 defects are increasing due to defect reclassification to reflect must-fix defects
Sev 2
Sev 3
Sev 1
55
Average Days to Fix FAT Severity (1, 2, 3) Defect by Vendor
Defect turnaround time is one key indicator of vendor performance.
66
Nodal % Reopened Defects by Vendor
ABB, AREVA, and Siemens are fixing their products with a low reopen rate, a good indication that these vendors are sufficiently testing their releases/defect bundles prior to delivery.
Increased focus on more robust dev/pre-FAT testing for vendors with high reopen rate.
Key indicator of vendor performance (indicates what percentage of fixes delivered by a vendor failed retest).
77
Severity 1, 2, and 3 defects found in the Early Delivery Systems (EDS)
Majority of EMS defects are detected in EDS.
1 Data Loss/Critical Error2 Loss of functionality w /o w o..3 Loss of functionality w ith w ..
Defect Summary Graph
Project
CR
R
EM
S
MM
S
MM
S M
M
OS
UI
Num
ber
of D
efe
cts
65
60
55
50
45
40
35
30
25
20
15
10
5
0
4
60
3
10
3
88
Quality Strategy Moving Forward
• Ensure adequate testing time in the appropriate environment.• Minimize number of releases/builds.• Prioritize defects according to program impact.• Complete integration test environment.