May 22, 2008 TPTF Quality Center Update Eileen Hall Ken Kasparian

Quality Center Update

Embed Size (px)

DESCRIPTION

Quality Center Update. Eileen Hall Ken Kasparian. Nodal Quality is of Increasing Concern. Areas of Concern Limited testing in lower environments Late detection of defects increasing defect resolution time Increased number of releases requires support for multiple versions of software (2+) - PowerPoint PPT Presentation

Citation preview

Page 1: Quality Center Update

May 22, 2008TPTF

Quality Center Update

Eileen HallKen Kasparian

Page 2: Quality Center Update

22

Nodal Quality is of Increasing Concern

• Areas of Concern

– Limited testing in lower environments

– Late detection of defects increasing defect resolution time

– Increased number of releases requires support for multiple versions of software (2+)

– Defects not uniformly prioritized from a program perspective

– Currently do not have integrated test environment

– Final builds of critical components have not been integrated

• Mitigation Measures

– Provide for adequate test cycles in revised schedule

– Minimize number of releases/builds

– Program level participation in defect prioritization

– Accelerate build out of integrated test environment

Page 3: Quality Center Update

33

Nodal FAT Active Defects by Severity by Project

Problems areas include:

NMMS has 30 Severity 1 and Severity 2 defects

MMS has 14 Severity 2 defects

OS UI has 10 Severity 2 defects

EIP has 9 Severity 1 and Severity 2 defects

Note – Includes New, Open, Reopen, Fixed and Test

The number of Severity 1 and Severity 2 defects is increasing.

Page 4: Quality Center Update

44

Nodal Active Defects by Severity Trend

• Severity 3 trend is remaining relatively constant (784 currently outstanding)• Severity 2 defects are increasing due to defect reclassification to reflect must-fix defects

Sev 2

Sev 3

Sev 1

Page 5: Quality Center Update

55

Average Days to Fix FAT Severity (1, 2, 3) Defect by Vendor

Defect turnaround time is one key indicator of vendor performance.

Page 6: Quality Center Update

66

Nodal % Reopened Defects by Vendor

ABB, AREVA, and Siemens are fixing their products with a low reopen rate, a good indication that these vendors are sufficiently testing their releases/defect bundles prior to delivery.

Increased focus on more robust dev/pre-FAT testing for vendors with high reopen rate.

Key indicator of vendor performance (indicates what percentage of fixes delivered by a vendor failed retest).

Page 7: Quality Center Update

77

Severity 1, 2, and 3 defects found in the Early Delivery Systems (EDS)

Majority of EMS defects are detected in EDS.

1 Data Loss/Critical Error2 Loss of functionality w /o w o..3 Loss of functionality w ith w ..

Defect Summary Graph

Project

CR

R

EM

S

MM

S

MM

S M

M

OS

UI

Num

ber

of D

efe

cts

65

60

55

50

45

40

35

30

25

20

15

10

5

0

4

60

3

10

3

Page 8: Quality Center Update

88

Quality Strategy Moving Forward

• Ensure adequate testing time in the appropriate environment.• Minimize number of releases/builds.• Prioritize defects according to program impact.• Complete integration test environment.