Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Contract No.: AID-522-16-TO-00003
April 28, 2017
This publication was produced for review by the United States Agency for International Development. It
was prepared by Banyan Global for the Empleando Futuros Project.
EMPLEANDO FUTUROS
Q2 QUARTERLY REPORT
JANUARY 2017 – MARCH 2017
EMPLEANDO FUTUROS
Q2 QUARTERLY REPORT
JANUARY 2017 – MARCH 2017
Contract No.: AID-522-16-TO-00003
Submitted to: Ana Rubi
Contracting Officer’s Representative
USAID Honduras
DISCLAIMER
The authors’ views expressed in this publication do not necessarily reflect the views of the United States
Agency for International Development (USAID) or the United States Government.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 i
PROJECT OVERVIEW
Project Name Empleando Futuros
Contract Number AID-522-16-TO-00003
Activity Start Date June 30, 2016
Activity End Date June 30, 2021
Prime Implementer Banyan Global
Subcontractor Education Development Center
Geographic Coverage Tegucigalpa, San Pedro Sula, Tela, Choloma, La Ceiba
Reporting Period Life of Project
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 ii
CONTENTS Contents. ........................................................................................................................................ ii
Acronyms and Abbreviations ..................................................................................................... iv
1. Executive Summary ...............................................................................................................6
Introduction .................................................................................................................. 6
Summary of Results and Key Achievements ............................................................... 6
Problems Encountered and Lessons Learned ............................................................... 7
2. Activity Implementation ........................................................................................................8
Submission of Deliverables .......................................................................................... 8
Progress Narrative ........................................................................................................ 8
2.2.1 Result 1 ........................................................................................................................... 8
2.2.2 Result 2 ......................................................................................................................... 10
2.2.3 Result 3 ......................................................................................................................... 12
Status of Activity Level Logic Models ....................................................................... 13
Implementation Challenges and Opportunities .......................................................... 13
3. Collaboration and Knowledge-Sharing ..............................................................................15
Linkages with other USAID Activities ...................................................................... 15
Collaboration & Knowledge-Sharing with Partner Entities in Host Government and
other Donor Agencies ............................................................................................................ 15
Key Highlights of Collaboration ................................................................................ 16
Collaboration Challenges ........................................................................................... 16
4. Integration of Cross-Cutting Issues ....................................................................................17
Gender ........................................................................................................................ 17
Safety and Security ..................................................................................................... 17
5. Management & Administrative Issues ...............................................................................19
Achievements, Constraints and Critical Issues ........................................................... 19
Personnel .................................................................................................................... 20
Adaptation of the Activity .......................................................................................... 21
Modifications and Amendments ................................................................................. 21
6. Assessments, Evaluations and Lessons Learned ...............................................................22
Major Assessments ..................................................................................................... 23
Internal Evaluations .................................................................................................... 23
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 iii
Lessons Learned ......................................................................................................... 23
Actions and Way Forward .......................................................................................... 23
7. Planned Activites for Quarter 3 ..........................................................................................24
8. Financial Information ..........................................................................................................27
Cash Flow Chart ......................................................................................................... 27
Budget Details and Notes ........................................................................................... 27
Sub-Award Details ..................................................................................................... 27
9. Branding, Communication and Disemmination ................................................................28
Key Communication Activities .................................................................................. 28
9.1.2 Launch Events of Empleando Futuros Project ........................................................ 28
9.1.3 Youth Recruitment Campaign ................................................................................... 28
Branding ..................................................................................................................... 29
9.2.1 Material for Launch Event ......................................................................................... 29
10. Sustainability and Exit Strategy .........................................................................................31
ANNEXES.. ..................................................................................................................................32
ANNEX 1: RFA TIMELINE AND PROCESS .....................................................................33
ANNEX 2: EMPLEANDO FUTUROS POWERPOINT PRESENTATION .......................35
ANNEX 3: PICTURES & EVENTS ......................................................................................38
ANNEX 4: SUCCESS STORIES ..........................................................................................40
ANNEX 5: MEETING REPORT ...........................................................................................44
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 iv
ACRONYMS AND ABBREVIATIONS AMDC Alcaldía Municipal del Distrito Central (Central District City Hall)
CBT Community-based Training
CLB Competencias Laborales Básicas (Basic Labor Competencies)
COP Chief of Party
COR Contracting Officer’s Representative
COSUDE Cooperación Suiza de Desarrollo (Swiss Development Cooperation)
DO1 Development Objective One
EDC Education Development Center
EF Empleando Futuros
FUNADEH Fundación Nacional para el Desarrollo de Honduras (National Foundation for the
Development of Honduras)
GBV Gender Based Violence
GIS Gender Inclusion Strategy
GIZ Deutsche Gesellschaft fur Internationale Zusammenarbeit (German Society for
International Cooperation)
IDB International Development Bank
INFOP Instituto Nacional de Formación Profesional
JAG Jobs for America’s Graduates
LMA Labor Market Assessment
MEL Monitoring Evaluation and Learning
MESCLA Monitoring and Evaluation Support for Collaborative Learning and Adapting
METAS (GOALS) Mejorando la Educación para Trabajar, Aprender, y Superarse
NGO Non-Governmental Organization
PIRS Performance Indicator Review Sheets
R1 Result 1
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 v
R2 Result 2
R3 Result 3
RFA Request for Application
RSM Risk and Strategic Management
RTN Registro Tributario Nacional (National Tax Registry)
SENA Servicio Nacional de Aprendizaje (National Learning Service)
USAID United States Agency for International Development
VAT Value Added Tax
WFD Activity Workforce Development Activity
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 6
1. EXECUTIVE SUMMARY
INTRODUCTION
On June 30, 2016, USAID/Honduras and Banyan Global signed a five-year Task Order to
acquire professional and technical services for the implementation of the USAID/Honduras’
Workforce Development Activity (WFD Activity), part of USAID/Honduras’ Country
Development Cooperation Strategy under Development Objective 1 (DO1), Sub-Intermediate
Result 1.1.2 - “Quality services that protect against violence increased.” Through the WFD
Activity, USAID/Honduras’ broader objective aims to increase citizen security for vulnerable
populations in urban, high-crime areas in Honduras by supporting workforce development that
will increase income-generating opportunities for youth who are at-risk of being perpetrators of
violence. The activity will strengthen comprehensive workforce readiness services, including job
linkage and self-employment, to benefit at-risk youth, including those who qualify for secondary
and tertiary services.
The following report covers project activities from January 1 - March 31, 2017 as the project
transitioned from start-up into implementation.
SUMMARY OF RESULTS AND KEY ACHIEVEMENTS
Key highlights and achievements in Quarter 2 included the following:
• Hiring/on-boarding 20 program and administrative staff in Tegucigalpa and San Pedro Sula,
including a full-time Gender Specialist and a full-time Security Coordinator.
• Opening a regional office in San Pedro Sula to support activities in San Pedro Sula,
Choloma, Tela and La Ceiba.
• Completion of the Monitoring, Evaluation and Learning Plan along with 17 Project Indicator
Reference Sheets, pending final USAID approval.
• Submission of the Gender Inclusion Strategy. Pending final USAID approval, the project will
integrate these activities with the goal of greater gender equality.
• Approval of the project Grant’s Manual and the release of the first Request for Proposal for
implementers of Phase 1 of Result 1 training.
• Revision of base program manuals, Life Skills and Basic Labor Competencies - key
components of Result 1 training.
• Submission of a revised budget and costed work plan.
• Finalizing and obtaining permission to initiate the four-focus area Instituto Nacional de
Formación Profesional (INFOP) intervention plan as well as achieving increased interest in
collaboration from donors and their implementing organizations.
• Completion of the competitive process to hire a firm to conduct the Labor Market
Assessment, pending final USAID approval.
• Conducting one national and two regional project launch events with over 500 attendees,
including regional and national level press coverage that generated over $80,000 of earned
media value.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 7
All program deliverables have been met on time and the project is scheduled to begin training
youth under Result 1, as well as INFOP leaders and associates, in June 2017.
PROBLEMS ENCOUNTERED AND LESSONS LEARNED
The most significant problem encountered during the quarter was due to the slow pace and
confusing state of approvals for tax exemption requirements by the Honduran government.
Changes in tax exemption rules and processes at the end of 2016, accompanied by changes in
government offices caused delays and additional staff time and resources dedicated to resolving
these issues as part of the project’s start-up activities.
Additionally, two staff members who had been hired as consultants and were slotted for full-time
positions left the project in January. This resulted in some short-term staff shortages before
replacements were hired. Despite these challenges, the project has met all its deliverables on
time.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 8
2. ACTIVITY IMPLEMENTATION
SUBMISSION OF DELIVERABLES
As of April 28, 2017, Empleando Futuros has submitted the following deliverables.
Deliverable Submission Date
Branding and Marking Plan September 28, 2016
Gender Analysis September 28, 2016
Gender Inclusion Strategy February 24, 2017
Monitoring and Evaluation Plan December 20, 2016
Security Plan July 28, 2016
Life of Project Work Plan July 30, 2016
PROGRESS NARRATIVE
The following three sections detail progress for the three project results.
2.2.1 RESULT 1
During the second quarter, Result 1 activities focused on development of its methodological
concepts and materials; definition of an at-risk youth recruitment and registration strategy; and
refinement of the roles, responsibilities, and methods of collaboration for and among members of
the technical team.
Key to these activities is the project’s Place-Based Strategy that not only focuses recruitment on
youth from high-violence communities, but also locates the first phase of training (Life Skills,
Cognitive Behavioral Therapy, and Basic Labor Competencies) within these communities.
Result 1
At least 7,500 at-risk youth will have benefited from comprehensive workforce development
services with improved job placement and self-employment rates; and,
At least 50 percent of youth who received services from the WFD Activity will have obtained
new or improved employment, including self-employment.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 9
Below is a short description of who will conduct the trainings and where the major training
components will take place:
Phase 1 – Local partner organizations will recruit and select youth, recruit program mentors, and
provide a space for training activities.
Phase 2 – Specialized organizations, through sub-contracts, will implement Life Skills, Cognitive
Behavioral Therapy and Basic Labor Competencies training to recruited youth. Trainings will be
conducted at professional vocational training centers in the at-risk communities. Empleando
Futuros staff will also lead a Capstone (vocational and socio-labor orientation) course at these
centers.
Phase 3 – Through a sub-grant mechanism, a select number of organizations will lead program
follow-on and job-insertion activities, including internships or practical experiences,
entrepreneurship activities, and other interactions designed to ensure that youth transition from
training into employment.
Activities and results of this quarter include:
• Youth recruitment and selection, and training methodologies and tools: The project
developed a guide for community-based training organizations on promoting the program;
recruiting, selecting, and registering youth; and linking youth to other programs, vocational
professional training, and jobs.
• Facilitator and Mentor Bank. Based on the interest and need to hire and train mentors and
facilitators from the focus communities, the project published Terms of Reference for these
positions and has conducted a preliminary screening of candidates. These candidates will be
contracted by the community organizations and groups implementing the Life Skills and
Basic Labor Competencies training. The project also conducted a “learning workshop” with
key stakeholders to develop a Mentoring Guide.
• Development and revision of Phase 1 training materials. Based on the experiences of
Project METAS (Mejorando la Educación para Trabajar, Aprender, y Superarse) and with the
authorization of the Education Development Center (EDC), the Empleando Futuros project
staff has revised the Life Skills and Basic Labor Competencies materials.
• Basic Labor Competencies (CLB) program development. The project has defined the
Terms of Reference to contract one or both organizations that EDC has authorized to lead
CLB. Actions anticipated in those sub-contracts include: (1) administration of the program;
(2) coordination of the training and evaluation; and (3) provision of certification indicating
the level of progress or learning for each participant. Under Result 2, Empleando Futuros will
begin discussions with INFOP in the following quarter with the goal that INFOP, or their
delegate, offers a national level certification course.
• Job Insertion Methodology. The project has developed a table of contents for a job
insertion training strategy and a methodological outline for its Job Orientation and Insertion
approach. The strategy will be completed by May 2017 with the detailed methodology
completed by September 2017, before the first youth begin insertion activities.
• Prioritizing Vocational Training Areas. Although the labor market assessment will soon
begin, project staff have completed a review of the labor market demand through two
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 10
mechanisms: (1) review of studies conducted by FHI360, Catholic Relief Services and
Honduras 2020; and (2) face-to-face consultations with private sector representatives,
including industrial groups, the pharmaceutical industry, and manufacturing industry.
Vocational areas identified as being in the highest demand include machine operators and
mechanics for the manufacturing industry; pharmaceutical agents; commercial salespeople,
and cashiers for the service industry; hotel service staff; air conditioning repair and
maintenance operators; and baristas, bartenders, cooks, and waiters in the tourism and food
service industries.
▪ Agreements with Business Sectors. Working through chambers of commerce and business
associations, the project held meetings with representatives of different business sectors with
three goals: (1) present Empleando Futuros and its methodologies for recruiting and training
youth; and (2) learn more about labor demands by sector; and (3) create opportunities to sign
agreements with sector leaders to better link curricula to demand and for internship and job
placement.
▪ JAG. Empleando Futuros and USAID staff continued conversations with the U.S.-based Jobs
for America’s Graduates (JAG) organization with the goal of conducting a three-part
exchange program that will strengthen the ability of Empleando Futuros’ implementers and
private sector collaborators to build lasting linkages and improve market-driven training. The
first exchange with JAG members visiting Honduras is expected to take place in
August/September 2017.
▪ Other Activities Related to Result 1. The Empleando Futuros team has also completed the
following: (1) support for the development for the Phase 1 RFA; (2) an inventory of the types
of training offered by the Professional Vocational Centers with the goal of evaluating the
occupations offered and the capacity of these centers; and (3) coordination with other USAID
projects so they may refer youth to Empleando Futuros.
2.2.2 RESULT 2
Following the completion of the INFOP study in the previous quarter, activities between January
and March focused on fine-tuning the action plan, revising the activity budget, coordinating with
other members of the donor community, and developing the required commitments among
donors and INFOP to complete the plan and achieve the goal of INFOP becoming more
responsive to the needs of the Honduran job market.
In January, Ana Murillo was selected as the Result 2 Coordinator, and she officially started in
that role in early March. Even before her official start, Ms. Murillo conducted several meetings
with the project leaders and consultants to gain familiarity of the activities and centralize
decision-making.
Result 2
INFOP will have strengthened their institutional capacity to provide quality services and to
effectively align services with the needs of the private sector.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 11
Based on the assessment noted above, Empleando Futuros has developed a comprehensive plan
with four focus areas to achieve the goal of a more market-driven INFOP. They include:
• Focus Area 1 – Leadership for Workforce Development Change. This includes leadership
training and personal coaching for two groups of individuals. Group 1 consists of 27 high-
level INFOP leaders as well as key members of the Honduran government, representatives of
major donor organizations, private sector leaders, and representatives of INFOP vocational
training partners and collaborators. Group 2 will consist of 20 next-level INFOP technical
managers and select trainers. Each leadership training group will conduct a personal skills
and aptitudes assessment, participate in group leadership training workshops, develop a
personal leadership plan and receive personalized coaching, and participate in a visit to
Colombia’s Servicio Nacional de Aprendizaje (SENA), the leading government-led
vocational institution in Latin America. The goal of the leadership training is for the
participants to learn to work together better and develop the skills needed to make the
required organizational and technical changes within the INFOP system to become more
market-oriented and meet the workforce skill needs of Honduras’ private sector. The
leadership training will be certified by a local university to give it greater value and
legitimacy.
• Focus Area 2 – Training of Trainers. This focus area will include six groups of 20 INFOP
trainers/facilitators each who will develop consistent methodologies and practices for
designing and implementing INFOP courses. This should yield a clear and consistent
“INFOP way” of training youth.
• Focus Area 3 – Curriculum Design and Pedagogical Support for Market-driven Training.
The project will assist INFOP to create an office dedicated to identifying labor trends,
prospects, and needs and to developing on-line training courses and materials.
• Focus Area 4 – Monitoring, Evaluation and Learning (MEL). The goal of this focus area is to
build resolve and capacity within INFOP to create and fully fund an effective MEL unit that
tracks the outcomes of INFOP-led or supported training as it relates to job insertion and
retention, and uses this information to adjust training offers and the design of specific
courses.
USAID and Empleando Futuros staff have identified that cooperation from other INFOP donors
is necessary to reach these objectives. USAID/Honduras estimates that there is currently over
$185 million of combined donor investment in workforce development activities in the country.
Therefore, Empleando Futuros is participating with USAID/Honduras in a donor’s working
group to maximize the impact of these investments and avoid duplication. Empleando Futuros
staff has participated in group meetings and met individually with leadership of donor groups
such as the U.S. Department of Labor, the World Bank, the Inter-American Development Bank,
COSUDE (Swiss Development Cooperation), GIZ (German Society for International
Cooperation), EuroLabor – European Union, the Organization of Ibero-American States, and
others as part of this effort.
In the next quarter, members of the donor community plan to make commitments on how they
and their programs can support the four focus areas described above. There is also agreement
that each donor will include their major activities within INFOP’s master plan and timetable
developed by Empleando Futuros.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 12
For activities under this result to be successful, the INFOP Executive Director, top leadership, its
Board of Directors, and the Office of the President need to commit to change and to dedicate the
necessary resources. As this is a particularly difficult challenge during an election year,
Empleando Futuros has developed three different scenarios based on the level of commitment
obtained from INFOP and the Honduran government. Each scenario has the same overarching
goal while the level of U.S. government investment and specific targets will vary.
USAID/Honduras has given provisional approval for Scenario 1 (the highest level of
engagement), pending the degree of commitment demonstrated by the INFOP in the coming
months.
Planned Activities for Next Quarter
• Invite 27 leaders and secure their participation for training – April
• Prepare training materials for leadership course – April/May
• Produce a methodological guide for coaching participants in leadership training – May
• Contract university to lead program leadership program certification – May
• Present and validate action plan with INFOP – May
• Sign memorandum of understanding letter with INFOP and other donor organizations – June
• Kick off leadership training with two-day training – June
2.2.3 RESULT 3
Information gathering activities continued for Result 3 with the intention to start training for
tertiary prevention beneficiaries in Quarter 4. In addition, a full-time R3 staff member will be
hired in Quarter 3. Among the activities conducted during the quarter were visits to centers
working with youth who have been in conflict with the law. In February, the Chief of Party
(COP) visited the government-run Jalteva juvenile detention center located approximately 90
minutes from Tegucigalpa. Orphan Helpers, an international non-governmental organization
(NGO) that works with current and former incarcerated youth, led the visit. In March, a
delegation from Empleando Futuros, including the Banyan Global president, visited Unidos por
la Vida (United for Life) NGO located in San Pedro Sula. Unidos por la Vida works with
Fundación Nacional para el Desarrollo de Honduras (FUNADEH) on a USAID-funded program
that is working to rehabilitate and find employment for former gang members. Project staff
Result 3
At least 400 youth identified as in need of tertiary prevention services will have received
services leading to improved rates of legal income generation; and
There will be increased evidence and knowledge about effective strategies in providing
comprehensive workforce development services to youth in conflict with the law and/or ex-
gang members.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 13
members also met with members of the Programa Nacional de Prevención (National Prevention
Program) that works with former gang members and formerly incarcerated youth throughout the
country.
STATUS OF ACTIVITY LEVEL LOGIC MODELS
Below is the logic model that demonstrates the process a beneficiary will go through in the
Empleando Futuros project. The six stages include: Life Skills, Cognitive Behavioral Therapy,
Basic Labor Competencies, Professional Training, Labor Insertion Orientation, and Job
Placement.
IMPLEMENTATION CHALLENGES AND OPPORTUNITIES
There are two challenges and opportunities related to Result 1. First, the model depends upon
youth being trained inside or near their communities of residence. Those communities, by nature,
are violence-ridden, making it challenging to conduct training and to find organizations that are
qualified to host training. Empleando Futuros has designed the training components so that
organizations that might have limited administrative capacity can host training and recruit youth
(i.e., they are not required to implement the technical aspects of the program or manage large
budgets). These organizations are important to the model because of their ability to recruit and
retain at-risk youth, and for their legitimacy and credibility within the target population. The
challenges include finding these organizations and then providing them with the support needed
to ensure their success. At the same time, this presents an opportunity to build capacities of
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 14
small, local organizations and involve youth in the program who might not otherwise have an
opportunity to participate.
A second challenge/opportunity is ensuring that all the training components come together in a
timely manner. Considering that the length of professional vocational training varies depending
on the level of technical complexity, it is a challenge to design a constant pipeline of youth based
on universal program end dates. Again, Empleando Futuros will be working closely with all
members of the training chain to ensure that the different components fit together. The
opportunity side of this challenge is to develop highly qualified organizations in the communities
and in the vocational centers with new skills and approaches to working with at-risk youth.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 15
3. COLLABORATION AND
KNOWLEDGE-SHARING
LINKAGES WITH OTHER USAID ACTIVITIES
Empleando Futuros prioritizes collaboration with other USAID projects as part of its strategy.
The project has met numerous times with EDC/METAS to discuss adapting and transitioning
their MEL system that tracks youth-related outcomes. Empleando Futuros will be working
closely with EDC staff to complete this transition during the next quarter. Empleando Futuros
staff attended the METAS closing ceremony in February and used several lessons learned from
the project launch events in March. Youth from METAS were also invited to participate in key
roles of the program launch. Project staff have been building on community and private contacts
established through METAS and have also applied and adapted lessons learned from METAS to
revise program manuals for Life Skills and Basic Labor Competencies. Finally, the project
nominated two Community Heroes that were active in METAS and who will cooperate with
Empleando Futuros for the USAID/Honduras awards.
Empleando Futuros staff, together with Honduras Convive, have also participated in a round of
community-based meetings in three of the highest risk communities in San Pedro Sula. Through
these meetings, project staff strengthened connections to community leaders and listened to
challenges of the communities that can be addressed through the project.
Empleando Futuros staff have had numerous meetings with staff from FUNADEH and ProPonte
Mas to discuss referral systems and coordination of activities at the community level. These
conversations will continue in the next quarter with the goal of having signed agreements
outlining how the referral systems will work. With ProPonte Mas, the conversations also
included discussions of MEL systems and approaches to gender inclusion, resulting in better-
informed decisions by the project.
COLLABORATION & KNOWLEDGE-SHARING WITH PARTNER
ENTITIES IN HOST GOVERNMENT AND OTHER DONOR
AGENCIES
These activities are highlighted in the Result 2 section of the report which focused on work with
INFOP and with the international donor community. The infographic below illustrates the impact
of other projects including A Ganar, Proyecto Metas and Proponte Más on the design of the
Empleando Futuros project. This graphic was presented at the regional Workforce Development
Workshop in Guatemala.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 16
KEY HIGHLIGHTS OF COLLABORATION
As noted in the section on Result 2, USAID and Empleando Futuros have brought the
international donor community together to coordinate activities and resources being dedicated to
support INFOP. Donors are meeting at least twice a month to discuss collaborative plans and
future activities.
COLLABORATION CHALLENGES
Some organizations expect Empleando Futuros to simply follow the path established by METAS
or other workforce development programs without challenging conventional thought or building
on lessons learned. Other organizations may have had expectations of designated funding for
their programs without considering new ways of conducting workforce training. One
organization stated, “Just give me the 7,500 youth, we can train them all in one year.” These
perceptions have led to some challenges and the need to clearly explain how Empleando Futuros
has been designed and why. Cooperation with USAID/Honduras has been important to
communicate expectations within these communities.
The collaboration work with INFOP faces additional challenges due to differing donor
timetables. One key INFOP donor project is scheduled to end in 2017 while the International
Development Bank (IDB) does not plan to enter this space until 2018 or later. Complicating the
matter further are the uncertainties that come with the upcoming 2017 Honduran presidential
elections.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 17
4. INTEGRATION OF CROSS-
CUTTING ISSUES
GENDER
In line with Empleando Futuros’ commitment to ensure that gender and other vulnerable
populations are considered in programming design and activities, this past quarter a decision was
made to hire a full-time gender specialist for the project. Interviews were conducted in January,
and in March Liena Isaula began as the full-time project Gender Specialist. Since her hire, Ms.
Isaula has been working closely with the Banyan Global Gender Specialist in Washington, D.C.
as well as with all technical staff, including the Chief of Party.
Following the Empleando Futuros gender analysis that was submitted in 2016, consultant Mary
Ellen Duke traveled to Honduras in late January/early February to consult with project staff in
preparation for the Gender Inclusion Strategy (GIS). A draft GIS was submitted on February 24.
An updated draft will be submitted for final approval in the next quarter. The GIS provided a
costed (both financial and human resource) estimation and action plan for all key gender
activities.
Gender considerations and language were also woven into the Request for Applications (RFA)
for Empleando Futuros grants. While not a requirement for award, the RFA highlighted that
previous experience or willingness to engage on gender-related topics or if gender-based
violence (GBV) prevention training would be desired. The project has committed to providing
gender training and guidance to all sub-grantees.
In addition, with support from the Gender Specialist, the Empleando Futuros team is reviewing
and revising program manuals, intake documents, and other materials to ensure that language is
inclusive and that exercises, graphics, and other information in those documents do not reinforce
traditional or negative stereotypes. The Basic Labor Competencies revision is now complete
while the review of the Life Skills Manual will be finished early next quarter.
SAFETY AND SECURITY
In March, Banyan Global hired a full-time Security Specialist, Mauricio Chacón, to oversee
safety and security issues for staff and implementing partners. Mr. Chacón is based in the San
Pedro Sula office but he travels frequently to Tegucigalpa and other program sites. In
coordination with other senior administrative staff, he will oversee the project’s drivers and
vehicle fleet and ensure that all visits to communities follow established safety protocols. He will
also lead training sessions for staff and implementing partners on topics related to work in at-risk
communities. Immediately upon being hired, Mr. Chacón led introductory safety training
sessions with staff and conducted security screening visits to communities scheduled to be
visited by Banyan Global’s president during her visit to Honduras in March.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 18
Banyan Global also completed the contracting process to hire Risk and Strategic Management
(RSM) Corporation to conduct a thorough safety and security assessment of the project’s offices
as well as the communities where project staff is working. The assessment is currently being
conducted. Its findings will be used to develop protocols and training modules for dealing with
common safety threats such as gang interactions, what to do in the case of violence nearby, and
how to assess if and when it is safe to enter a community. The safety assessment will include
meetings with police, community leaders, other USAID programs, United Nations, and others.
The assessment will also focus on gender aspects related to security to ensure that the
perspectives of women are taken into account.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 19
5. MANAGEMENT &
ADMINISTRATIVE ISSUES
ACHIEVEMENTS, CONSTRAINTS AND CRITICAL ISSUES
Empleando Futuros completed the last major start-up activities during this quarter, including:
• Opening an office in San Pedro Sula.
• Hiring 20 new staff members for both offices. All full-time persons who had worked as
consultants in 2016 transitioned to full-time staff in January 2017.
• Completing the Registro Tributario Nacional (RTN) process for both Banyan Global and
Empleando Futuros Project (necessary for VAT devolution process with the Ministry of
Finance).
• Obtaining certification for tax exemptions. The registration process in the new Franchises
module ETAX is pending, due to the Honduran government process of re-organizing tax
offices, which has resulted in delays. Banyan Global is working closely with USAID to
monitor and resolve these issues.
• Obtaining approval for the Grants Manual and releasing the first RFA. (See Annex 1 for RFA
timeline and process).
• Opening local bank accounts.
• With the hiring of new staff and the transition of consultants to locally hired staff, several
new administrative policies and guidelines have been established for sound office
management.
Constraints and critical issues include:
• The tax registration process in the new franchise module ETAX is pending, due to Honduran
government process of re-organizing tax offices which has resulted in delays. Banyan Global
is working closely with USAID to monitor and resolve these issues.
• Banyan Global resolved an outstanding human resource issue with a former consultant that
entailed a claim for acquired benefits per Honduran Law. The agreement has been
documented through the Ministry of Labor.
• The project continues to experience some challenges, including the sometimes-excessive
bureaucratic requirements of the Honduran government to process the tax exemptions
certification and operational permission given by Alcaldía Municipal del Distrito Central
(AMDC). Most notably, the Honduran government has changed the rules for obtaining tax
exemptions, which resulted in significant time needed this quarter to obtain the registration in
the new modules of the Tax Exemption Certification and to be able to generate Purchase
Orders exempted (expected to be resolved in the next quarter).
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 20
PERSONNEL
Twenty new staff members joined the Empleando Futuros team during the past quarter. New
staff hires/starts during this period included:1
January:
• Carlomagno Amaya – Workforce Development Specialist-Result 1 Leader2 Tegucigalpa.
• Joseth Garcia – Receptionist/Administrative Assistant Tegucigalpa.
• Francia Nazar – Finance Manager Tegucigalpa.
• Reyna Gomez – Executive Assistant and Procurement Specialist Tegucigalpa.
February:
• Ana Gabriela Banegas – Northern Region Operations Manager San Pedro Sula.3
• Francis Caballero – Communication Specialist Tegucigalpa.
• Nadia Castillo – Grants Specialist San Pedro Sula.
• Hector Fajardo – Vocational Training Specialist San Pedro Sula.
• Maria Candelaria Martínez – Basic Labor Competencies Specialist San Pedro Sula.
• Luis Armando Tinoco – Life Skills & Mentoring Specialist San Pedro Sula.
• Haydee Lopez – Recruitment/Selection Specialist San Pedro Sula.
• Julia Vindel – Recruitment/Selection Specialist Tegucigalpa.
• Mariem Anariba – Finance and Administrative Manager Tegucigalpa.
• Wendy Perdomo – Office Cleaner and Messenger Tegucigalpa.
March:
• Karla Portillo – Monitoring and Evaluation Assistant San Pedro Sula.
• Ana Francisca Murillo – INFOP Specialist - Result 2 Tegucigalpa.
• Liena Isaula – Gender Specialist.
• Mauricio Chacón – Security Specialist San Pedro Sula.
• Senia Salgado – Administrative and Procurement Assistant San Pedro Sula.
• Julissa Ustariz – Program Operations Manager Consultant Tegucigalpa.
Pending Hires for Next Quarter:
• Finance Specialist San Pedro Sula
• Result 3 Specialist
• Drivers for San Pedro Sula and Tegucigalpa
• Office Cleaner and Messenger San Pedro Sula
• Interns San Pedro Sula and Tegucigalpa
1 A complete organizational chart is included in Annex 2. 2 Except for the Security Specialist who is based in San Pedro Sula, all other staff listed without a geographic
indicator are based in Tegucigalpa but have national responsibilities. 3 Staff listed for San Pedro Sula support activities throughout the Northern Region including Choloma, Tela and La
Ceiba.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 21
ADAPTATION OF THE ACTIVITY
There are no adaptations to report at this time.
MODIFICATIONS AND AMENDMENTS
There are no modifications or amendments to report at this time.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 22
6. ASSESSMENTS, EVALUATIONS
AND LESSONS LEARNED Monitoring, Evaluation and Learning
Obtaining a robust monitoring, evaluation and learning agenda is a top priority for the
Empleando Futuros project. To this end, project staff and USAID staff worked collaboratively to
develop a monitoring and evaluation plan as well as a set of 17 PIRS (Performance Indicator
Reference Sheets) to guide the plan. The PIRS focus on four areas including general or
overarching indicators, and indicators specifically for the three project Results. Currently Banyan
Global is awaiting final approval of the PIRS by USAID.
The guiding principles for the development of the PIRS focused on developing indicators that are
measurable, realistic, achievable, and impactful. Project and USAID staff invested great effort to
carefully define terms such as “program completion”, “measuring improvements by youth”,
“measuring improvements by organizations”, “measuring protective factors”, and “job insertion”
to align with these guiding principles. As part of process, the project engaged the services of
expert consultant Gary Woller, who spent one week in March meeting with project staff and
stakeholders. Dr. Woller suggested improvements on the plan and the PIRS and provided expert
advice on the MEL tracking system and development of intake and tracking forms.
After carefully considering other systems, Banyan Global has moved into advanced discussions
with EDC to adapt and transfer the METAS electronic MEL tracking system for Empleando
Futuros. In addition to being cost-effective, this process will enable Empleando Futuros to house
and maintain records for the over 40,000 youth captured by the METAS tracking system. The
system transfer is scheduled to take place in Quarter 3.
Regional Sharing and Learning on Workforce Development
During the last week of March, the COP, the MEL Specialist, the USAID project Contracting
Officer’s Representative (COR), and the USAID/Honduras Education Office MEL Specialist
participated in the regional Workforce Development Workshop in Guatemala City, Guatemala.
Other participants included USAID and project staff from Nicaragua, El Salvador, and
Guatemala plus USAID and Mathematica staff from Washington, DC. At the workshops,
participants shared project details, discussed commonalities and differences, and searched for
common indicators that can be shared with USAID and the U.S. Congress. The project
presentation conducted by the Empleando Futuros staff was extremely well received. (See Annex
3 for a copy of the PowerPoint presentation, in Spanish).
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 23
MAJOR ASSESSMENTS
Impact Evaluation
Throughout the quarter, Empleando Futuros staff met numerous times with the DEXIS staff from
the Monitoring and Evaluation Support for Collaborative Learning and Adapting (MESCLA)
program to coordinate activities for the upcoming impact evaluation. This has resulted in
DEXIS, and their partner the University of Notre Dame, agreeing to pilot a new instrument that
will enable Empleando Futuros’ staff and partners to classify at-risk youth 18 years and over into
either primary, secondary or tertiary prevention categories. Testing of the instrument will begin
in April 2017 and is expected to be ready before Empleando Futuros registers its first youth in
June 2017.
INTERNAL EVALUATIONS
No internal evaluations were conducted this quarter.
LESSONS LEARNED
Project staff participated in the AGanar Impact Evaluation presentations at USAID in mid-
February. Lessons from this evaluation such as the importance of focusing on the quality of jobs,
the value of comprehensive training including life skills, and the importance of classifying youth
by risk level at the start of training will be applied to Empleando Futuros where possible.
ACTIONS AND WAY FORWARD
A Labor Market Assessment (LMA) designed to focus specifically on job opportunities for at-
risk youth in the five target municipalities is scheduled to begin in April 2017. The LMA will
target at least 300 businesses and should be completed by no later than October 2017. This study
will provide the project with important insight regarding private sector demand for workforce
skills.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 24
7. PLANNED ACTIVITES FOR
QUARTER 3
Result 1 Activities Completion
Date
1. Conduct at least four informational workshops for community
organizations interested in applying for grants under Results 1-Phase 1
activities.
April 2017
2. Define the methodology to review and evaluate the validity of current
vocational training courses being offered vs. the demands of the market.
April 2017
3. Contract the organizations that will lead Life Skills, community-based
training (CBT), and CLB training (combination of limited competition
and open competition).
May 20217
4. Finalize agreements with other USAID organizations and lead
orientation sessions on youth referral systems.
May 2017
5. Develop and publish RFP for vocational training activities. May 2017
6. Create and maintain a database of vocational training curricula. May 2017
7. Train mentors and facilitators in or for target municipalities. May 2017
8. Publish Life Skills and CLB training materials for youth and facilitators. May 2017
9. Award grants to community organizations for Result 1-Phase 1
recruitment/selection activities.
May-June
2017
10. Conduct registration training and evaluation workshops for grantees. June 2017
11. Initiate youth training activities through grantees. June 2017
12. Guide and support grantees in the first stages of training. June 2017
13. Sign at least five agreements with private sector organizations to
collaborate with/support the project.
June 2017
14. Finalize the strategy and methodology for Phase 3, Youth Mentorship
and Job Insertion.
June 2017
15. Publish RFA to recruit organizations to lead mentorship and job
insertion activities.
June 2017
16. Conduct workshops to develop course outlines for at least five new
vocational courses based on demand.
June 2017
17. Finalize memorandum of understanding with JAG to start the proposed
exchanges.
June 2017
Result 2 Activities
1. Invite and secure participation of INFOP representatives for capacity-
focused/leadership training.
April 2017
2. Prepare training materials for INFOP leadership course. May 2017
3. Produce a methodological guide for coaching participants in leadership
training.
May 2017
4. Contract university to lead program leadership program certification. May 2017
5. Present and validate action plan with INFOP. May 2017
6. Sign memorandum of understanding letter with INFOP and other donor June 2017
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 25
organizations.
7. Kick off 2-day leadership training. June 2017
Result 3 Activities
1. Complete the recruitment process and hire R3 Specialist. May 2017
2. Prepare RFA for first round of youth recruitment and training activities. June 2017
MEL Activities
1. Submit intake forms and obtain approval of MEL plan and PIRS. April 2017
2. Train community organizations on use of intake forms. June 2017
3. Adapt METAS tracking system for Empleando Futuros. June 2017
Gender-Inclusion Activities
1. Visit by Banyan Global gender experts and conduct staff training. April 2017
2. Submit revised Gender Inclusion Strategy. April 2017
3. Attend New Masculinities training provided by ProPonte Mas. April 2017
4. Revise R1 and R2 manuals and materials with stronger gender
integration.
May 2017
5. Conduct monthly gender inclusion training with staff in Tegucigalpa
and San Pedro Sula.
May 2017 and
ongoing
6. Conduct initial gender inclusion training workshops with selected R1
organizations.
June 2017
Safety Activities
1. Submit Threat Analysis and Risk Assessment conducted by Risk and
Strategic Management (RSM).
May 2017
2. Finalize project protocols suggested in security assessment. June 2017
3. Hold monthly safety training for staff. May/June
2017
4. Hold safety training for implementers. May/June
2017
Labor Market Assessment
1. Finalize LMA work plan/schedule. May 2017
2. Complete LMA inception report submitted. June 2017
Consultants and International Travel
1. Julissa Ustariz to continue activities as Program Operations Manager
consultant in Tegucigalpa.
April-
June2017
2. Christine Seisun (Banyan Global staff) and Mary Ellen Duke
(consultant) to work on Gender Inclusion Strategy and conduct staff
trainings.
April 2017
3. Susan Ross (EDC Project Director) to identify technical support
priorities and establish relationships with potential local stakeholders.
April 2017
4. Jorge Restrepo to continue providing Result 2 support. May and June
2017
5. Linsey Jaco (Banyan Global) to support subcontracting efforts and sub-
grant review, selection and agreements.
May 2017
Administrative Activities
1. Anticipated completion of tax registration process. May 2017
2. Procure project vehicles. June 2017
3. Submit request for budget realignment request. May 2017
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 26
4. Submit Milestone Schedule. May 2017
5. Submit revised Branding and Marking Plan (will include social media
and photo policy).
June 2017
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 27
8. FINANCIAL INFORMATION
CASH FLOW CHART
Obligations, Actual Expenditure, Pipeline Projection
The following table indicates cash flow status as of the end of FY17.
Obligation to Date
(as of March 2017)
Actual Expenditures
(June 2016-March 2017)
Projections
FY17Q3 & FY17Q4
Balance through
FY17 End
BUDGET DETAILS AND NOTES
Empleando Futuros has been in ongoing discussions with USAID regarding necessary changes to
the original budget due to increased salary costs resulting from a larger specialized in-country
staff and adjustments to anticipated training costs for Result 1 and Result 3. A request for budget
realignment that includes revised budget notes and justification notes is anticipated to be
submitted in May 2017.
Ongoing discussions with USAID regarding the contractual milestone schedule are anticipated to
culminate in a request for approval submission in May 2017.
Empleando Futuros’ costed work plan is currently under review by USAID after submission on
March 24, 2017.
SUB-AWARD DETAILS
EDC and RSM are the only active subcontracts in FY17 Q2.
EDC continues to support the project with three field staff integrated with the Empleando
Futuros staff in Tegucigalpa. A fourth EDC member is anticipated to start on the project at the
end of Q3. Upon further definition of Result 1-3 activities and necessary budget adjustments, the
EDC subcontract scope and budget required modifications. Empleando Futuros submitted a
revised scope and budget ceiling to EDC in the beginning of FY17 Q3 which is currently still
under review by EDC. An amendment to the subcontract is anticipated in FY17 Q3.
RSM initiated activities on the Threat Analysis and Risk Assessment with a kick-off meeting
with Empleando Futuros staff and with necessary deployment preparation for the in-country
assessment.
The majority of the sub-award activity, which includes the Labor Market Assessment, grants to
community organizations, and subcontracts to various institutions anticipated to provide CLB,
Life Skills, CBT and vocational training, will begin in FY17 Q3.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 28
9. BRANDING, COMMUNICATION
AND DISEMMINATION
KEY COMMUNICATION ACTIVITIES
9.1.2 LAUNCH EVENTS OF EMPLEANDO FUTUROS PROJECT
The project conducted three major launch events in March covering the project’s major
geographic areas and key media markets. In total, 543 people attended the three events: 178 in
Tegucigalpa; 117 in La Ceiba; and 158 in the city of San Pedro Sula, including media. Several
key stakeholders attended the event, including representatives of the Honduran government,
private enterprise, nongovernmental organizations, youth, international cooperation agencies,
USAID staff, and education sector representatives. These launches generated a broad interest in
our project among the people who attended. The events’ strategic communications in different
media markets also helped generate interest in the project. (See Annex 4)
The launch events had three major objectives: (1) announce the program to the public and key
stakeholders; (2) generate opportunities to meet key stakeholders; and (3) demonstrate the value
of hiring at-risk youth to both the public and especially the private sectors. To accomplish these
objectives, the events included meaningful participation of youth, governmental officials and
private sector representatives. In all three events, the USAID Mission Director, a high ranking
governmental official, a business representative, and the Banyan Global president spoke about
the importance of the project. In Tegucigalpa, a group of youth developed and shared a skit
where, dressed as chefs, they expressed the importance of the project and demonstrated the
principal competencies that youth need to possess to be a successful employee. Also in
Tegucigalpa, the launch event included a panel discussion where a representatives of the private
sector, INFOP, and USAID, as well as two at-risk youth, participated. In addition, Keysi
Sánchez, a youth beneficiary of Proyecto METAS, was the Master of Ceremonies for the
Tegucigalpa launch.
In La Ceiba and San Pedro Sula, the panel discussion was replaced with youth-focused
workshops. In one workshop, youth participants learned how to create a better resume and job
interview techniques. In the second workshop, youth learned how to apply for Empleando
Futuros and received advice on choosing a career.
The local media played an important role in the launch events, generating over 10 articles in
national and local newspapers, both digital and printed; several television and radio stories were
broadcast from the major outlets. Together, this generated an earned media value of $87,447.
9.1.3 YOUTH RECRUITMENT CAMPAIGN
To meet the goal of 7,500 youth trained, Empleando Futuros estimates that 12,000 youth need to
register with the project due to attrition and other reasons. Therefore, a public campaign to
recruit youth will be vital to achieving these targets. Based on interviews with youth and with
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 29
youth development experts, the project determined that to demonstrate the value and purpose of
Empleando Futuros, campaign materials should focus on key words such as scholarship (becas)
and employment (empleo). Below are examples of the banners and photographs designed by
Empleando Futuros staff and will be distributed through INFOP and other vocational centers.
BRANDING
9.2.1 MATERIAL FOR LAUNCH EVENT
The project created branded materials for the launch events to increase name recognition of
Empleando Futuros and USAID’s leadership of its activities. All of these materials followed
USAID branding and marking guidelines. Below are some examples of the launch materials.
Agenda with
USAID and
Empleando Futuros
branding, given out
at the launch events
Bag with USAID
and Empleando
Futuros branding,
given out at the
launch events
Shirt with
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 30
Folder with
Empleando Futuros
branding, given out
at the launch events
Shirts with
USAID and
Empleando Futuros
branding, for
Empleando Futuros
staff.
Polo Shirt with
USAID and
Empleando Futuros
branding, for
Empleando Futuros
staff.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 31
10. SUSTAINABILITY AND EXIT
STRATEGY While the majority of the project’s sustainability and exit strategy activities will take place in
Years Four and Five, Empleando Futuros is taking proactive steps in Year One to ensure
sustainability is built into its strategy from the start. This includes moving from discussing
Empleando Futuros as a project with communities and potential implementers to discussing it as
a process and model that can be transferred to local organizations working in close collaboration
with government institutions. It also includes documenting the model’s steps and costs so that
donors and stakeholders understand the different program components and the level of economic
and human resource commitment needed to succeed.
The MEL and the upcoming Impact Evaluation are designed to look at the value and
effectiveness of the different program components individually and as a whole. Likewise, the
MEL system will collect data that will enable an evaluation of program achievements, by
component, and allow the project to make adjustments to its youth and private sector
engagement strategies over time.
Finally, the work with INFOP and the donor community could likely be the project’s greatest
sustainable impact. If INFOP makes the fundamental changes and adjustments being proposed –
such as designing and delivering more market-driven training - they could become a leader of
private-sector focused skills training for Honduran youth.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 32
ANNEXES
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 33
ANNEX 1: RFA TIMELINE AND
PROCESS
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 34
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 35
ANNEX 2: EMPLEANDO FUTUROS
POWERPOINT PRESENTATION
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 36
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 37
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 38
ANNEX 3: PICTURES & EVENTS Launch Event in Tegucigalpa, Honduras
Discussion Panel - “Empleando Futuros for a Safer Honduras.” From left to right: Louis Alexander - Moderator of the panel;
Michael Maxey - USAID representative; Mey Hung – Private Sector Representative (Walmart); Edgardo Valenzuela – INFOP
Representative; two youth, Laura and Guido.
Speakers, from left to right: Meaghan Smith - Banyan Global
President; Carlos Madero - Minister of Labor; James Watson
– USAID Mission Director; and Paul Teeple - COP
Empleando Futuros.
A play was held to show the importance of youth in the
Empleando Futuros Project.
“The Recipe for the Future” was the name given to part of the
play where two young chefs, showed the “necessary
ingredients” to be part of Empleando Futuros Project.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 39
Launch Events in San Pedro Sula and La Ceiba
Empleando Futuros staff and youth with USAID and Banyan Global staff.
Special Speakers, from left to right: Tatiana Paz – Private
Sector Representative; Meaghan Smith - Banyan Global
President; Armando Calidonio – San Pedro Sula Mayor; James
Watson – USAID Mission Director; and Paul Teeple -
Empleando Futuros COP.
Interview with Empleando Futuros COP, Paul Teeple. Press
played an important role in the launch.
Workshops for youth were held, where they learned how to
choose a career, create a resume and prepare for a job interview.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 40
ANNEX 4: SUCCESS STORIES
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 41
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 42
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 43
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 44
ANNEX 5: MEETING REPORT
City Date and Place Meeting Purpose/Agreement
Tegucigalpa January 12, 2017
Davivienda
Meeting with
Antonio Barahona
- Empleando Futuros project was
presented.
- Areas were identified where personnel
are required: customer service, commercial
experts, accounting (commercial banking)
and financial education.
- Empleando Futuros will send a proposal
of a MOU to initiate cooperation between
both organizations (this would include
training and job placement).
Tegucigalpa January 12, 2017
INTUR
Meeting with Olga
Frech (Corporate
Social
Responsibility
Coordinator)
INTUR
- Informed about Empleando Futuros, the
opportunities of the new project and the
possible participation of the: Institute,
Corporation and Foundation.
- Investigated the feasibility of the
participation of INTUR in the Participatory
Occupational Analysis.
- Once approved, invite to the Participatory
Occupational Analysis meeting.
Tegucigalpa January 12, 2017
MENDELS
Meeting with Elvira
Villanueva-
(Human Resources
Mendels)
- Informed about Empleando Futuros, the
implications of the new project and the
possible participation as: Institute, Group
and Foundation.
- Investigated the feasibility of the
participation of Mendels in the
Participatory Occupational Analysis.
- Once approved, invite to the Participatory
Occupational Analysis meeting.
Tegucigalpa January 13, 2017
PDA World Vision
Meeting with the
technical team of
World Vision
- Shared information about Empleando
Futuros.
- Gain information on the capacity of the
facilities and the areas of influence.
Tegucigalpa January 16, 2017
Training Center San
Juan Bosco
Meeting with the
project coordinator
of the Training
Center San Juan
- Shared information about Emplando
Futuros.
- Gain information about the center's offer
of services and its capacity of services to
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 45
Bosco young people.
Tegucigalpa January 16, 2017
Empleando Futuros
Office
Meeting with the
technical team of
Dión Group
- Shared information about Empleando
Futuros.
- Gain information about the center's offer
of services and its capacity of services to
young people, including mobile
workshops.
Tegucigalpa January 17, 2017
Honduran Red Cross
Share information
about Empleando
Futuros with
different
organizations
within the
community (San
Francisco)
CDA(Centro de
Alcances),
ACJ(Asociación
Cristiana de
Jóvenes), Virgen de
La Paz,
ACOES(Asociación
de Colaboracióon y
Esfuerzo)
- Introduced Empleando Futuros to
organizations, especially the work and role
the community will be representing.
- All organizations reported on the
technical training they currently teach and
agreed to participate from Phase 1
(Recruitment and Selection) and Technical
Training.
- It was also agreed, that they will be
informed of the timeline to participate in
the recruitment and selection process.
Tegucigalpa January 17, 2017
CDA (Centro de
Alcance) Campo Cielo
Meeting with the
technical team of
RETE ONG.
- Shared information about Empleando
Futuros.
- Gain information about RETE's offer of
services and its youth services capacity.
Tegucigalpa January 18, 2017
UNITEC
Meeting with
Corporate Social
Responsibility-
Nadia Mazzoni
(Corporate Social
Responsibility)
- Presented Empleando Futuros and the
different components of Result 1.
- UNITEC reported that different Formal
Professional Centers could be adapted to
be provided as vocational training options
for young people.
La Ceiba January 19, 2017
Vocational Center in
La Ceiba
Meeting with
director – Reyna
Zorto
- Shared information about Empleando
Futuros and the diagnosis of the referred
vocational training centers.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 46
La Ceiba
January 19, 2017
Peace and Justice
Project
Meeting with
director – Belinda
Rodriguez
- Shared information about Empleando
Futuros and the activities carried out by the
organization in the city.
La Ceiba January 19, 2017
CEPROSAF
Meeting with team
members of the
local organization
who carried out
activities – Leticia
de Foot, Arnaldo
Soliz
- Presented Empleando Futuros and
examine activities carried out by the
organization in the communities of La
Ceiba and Tela.
La Ceiba January 19, 2017
Honduran Red Cross
Meeting with Red
Cross member –
Rosario Arias
- Presentation of the project and the review
of the work of the organization in the
communities of the city and similar
projects that they have worked on.
La Ceiba January 19, 2017
Proponte Más
Meeting with
Regional Director
in La Ceiba – Tesla
Quevedo
-Youth referring for secondary and tertiary
prevention services.
Tegucigalpa January 20, 2017
Lintegrity
Meeting with
Executive Director
Victor Ordoñez
- Informed about Empleando Futuros and
the different phases of training for the
youth.
- Learn the work through skills for life and
education in values that Lintegrity teaches.
La Ceiba January 20, 2017
INFOP
Meeting with
Deputy Director –
Osman Martinez
- The diagnosis of the educational offer of
the actions carried out by the institute in
the city of La Ceiba.
Tegucigalpa January 25, 2017
Casa Alianza
Meeting with the
Executive Director
of Casa Alianza
Jose Guadalupe
Ruela
- Socialization of the project Empleando
Futuros.
- Share information about the center's offer
of services and its capacity of services to
young people.
Tegucigalpa January 26, 2017
Empleando Futuros
Meeting with
Eduardo Posadas
from UTH (Flor
Ferrufino)
- Presented Empleando Futuros as well as
the different components of Result 1.
- UTH reported that the different diplomas
and technical training that could be adapted
to be offered as vocational training options
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 47
for young people, especially in the area of
technology and Tourism.
Tegucigalpa January 26, 2017
Hotel School Los
Sauces
Meeting with Flor
Ferrufino, Director
of Operations Los
Sauces
- Presented Empleando Futuros and
different components of Result 1.
- Los Sauces reported that they have a
boarding school for people in the rural area
- Bachelor in Hospitality (3 years), are
women between the ages of 15-20, who
receive this training for the duration of 1
year.
- The Sauces would be willing to work
with Empleando Futuros, as long as they
are provided women in this age range (in
shorter courses).
Tegucigalpa January 26, 2017
TERRA Group
Meeting with Sr.
Francisco
Hernández, CSR
- Presented Empleando Futuros.
- Terra Group reported that they should
inform both the Foundation and the
department about this project, but it was
necessary to know more details, such as: if
they could obtain funds as a Foundation
participate in the process, the participation
levels of the companies (professional
internship opportunities and / or jobs).
Tegucigalpa January 27, 2017
INFOP
Meeting with the
Director
- Presented Empleando Fututros.
- Explained different options of technical
training that this center offers. It is working
at its maximum capacity of 100%
Tegucigalpa January 27, 2017
University Center
Ilama/Ilama
Meeting with
Teresa Galeano, -
Training Officer
- Presented Empleando Futuros.
- They informed us of the technical offers
they have available and the flexibility to
adapt the curricula to what the project will
demand.
Tegucigalpa January 27, 2017
CADERH
Meeting with
Martha Ivonne,
Lourdes Maradiaga
- Presented Empleando Futuros.
- CADERH had a lot of questions and
explained how they visualized themselves
as a network to the project.
Tegucigalpa January 31, 2017
DIUNSA/ Empleando
Futuros Offices
Meeting with
Coordinator of
Corporate Social
Responsibility -
Elisa Pineda
- Presented Empleando Futuros.
- They visualized that as Foundation
Diunsa they could participate in both the
first phase (community), in the vocational
training and in job intermediation.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 48
Tegucigalpa February 01, 2017/
CRS Offices
Meeting with the
technical team of
Coorporate Social
Responsability.
- Share information about Empleando
Futuros.
- Learn information regarding the services
offered at the center and their capacity of
service to the youth.
Tela January 20, 2017
Municipal Hall
Meeting with
Mayor of Tela –
Mario Fuentes
- Diagnosis of the support actions that will
be taking place at the institute in the city of
Tela
Tela January 20, 2017
Free Butterflies
Meeting with
women
organization –
Calixta
Martinez/Founder
- The meeting was held in the community
of Tornabe, as this community has been
prioritized to carry out a pilot process.
Tela January 24, 2017
PNUD
Meeting with
regional
coordinator of
Security Citizen –
Fanny Gallo
- To learn about the actions that are being
carried out in the different municipalities
of Tela, Ceiba, Choloma and San Pedro
Sula.
Tela January 24, 2017
UNAH Tela
Meeting with Dean
and well-being
coordinator –
Santiago Ruiz and
Juana Fernandez
- Presented Empleando Futuros and the
participation in phase two in the vocational
training.
Tela January 26, 2017
Municipal Prevention
Council
Former meeting
with Mayor of Tela
and local
government such as
national police,
education and
health services -
Mario Fuentes
- Presented Empleando Futuros to the
partners.
Choloma February 8, 2017
Mario Ugarte
Technical Vocational
Center
Meeting with
Director – Miguel
Barahona
- Diagnosis of the training offers of the
vocational training centers in the technical
formation.
San Pedro
Sula
February 9, 2017
SOLFAHSA
Meeting with Board
of Directors of
small businesses
pharmacy – Jose
- Preparation of alliances with the
pharmaceutical sector in the preparation of
pharmaceutical agents.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 49
Antonio
Tegucigalpa February 9, 2017
CRS / CRS Offices
Meeting with Youth
Program Manager-
Luis Amilcar
Sevilla
- It was mentioned that CRS is considering
to participate as bidders when the RFA is
published. Before the consultation of
whether it can be applied in a consortium /
network / group of organizations, they said
that it is possible.
- Empleando Futuros consulted on whether
it is possible that the project team, can
receive a 1 day training by CRS (Catholic
Relief Services). They explained that it is
possible and asked us to take them into
account when CRS does a workshop and it
could be done in a day / workshop only
with them. It was answered that the
Empleando Futuros team would analyze
the case.
Tegucigalpa February 13, 2017
Offices of Empleando
Futuros
Meeting with the
technical team of
CADERH-USAID-
Empleando Futuros
- Discussed the future working method
with the project.
Tegucigalpa February 14, 2017
Offices College of
Psychologists
College of
Psychologists
- An explanation on the different stages of
Cognitive Behavioral Therapy was given
to the Empleando Futuros team.
- It was explained that there are few
programs that include this type of
intervention.
- It was also informed that they have
experience and material to do this type of
work.
Tegucigalpa February 14, 2017
FUNDAUNAH
UNAH
Meeting with Dean
Nabil Kawas
(Faculty of
Science), Luisa
Nieto (Assistant of
Strategic Planning)
- Empleando Futuros Team explained the
different stages of Result 1 training and
how the UNAH, through the Foundation,
could participate in vocational training in
all 5 cities.
- Information meetings were scheduled for
the university centers in the four cities.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 50
Tegucigalpa February 14, 2017
National Program of
Prevention Offices
Meeting with the
technical team of
National Program
of Prevention
- Presented Empleando Futuros with the
PNP staff and community leaders of the
San Miguel district of Tegucigalpa.
San Pedro
Sula February 14, 2017
Instituto Politécnico
Centroamericano
(IPC)
Meeting with
Executive Director
– Carlos Turcios
- Explanation of their academic offer and
technical pedagogical spaces.
San Pedro
Sula February 15, 2017
Centro Técnico
Sampedrano
Meeting with
Director – Omar
Zacapa
- Get to know their availability to be part
of the project and their technical and
vocational offer.
Choloma February 15, 2017
Chamber of
Commerce and
Industry of Choloma
Meeting with
Executive Director
and Business
Service coordinator
– Armando Leclair
and Alejandra
Mejia
- Explored articulating actions with the
association job board members for future
actions with the private sector in support of
the Participatory Occupational Analysis.
Tegucigalpa February 15, 2017
INFOP
Meeting with
INFOP youth
- Discussed recruitment and selection
campaign with INFOP youth.
Tela February 16, 2017
Chamber of
Commerce and
Industry of Tela
Meeting with
President and
Executive Director
– Mario Bautista
and Karen Aguilar
- Explored joint actions with the
Association of members for future actions
with the private sector and support in the
Participatory Occupational Analysis.
San Pedro
Sula February 16, 17, 21, 22
and March 1, 2017
- Centro Técnico
Honduras Corea
- Centro Técnico de
Chamelecón
- Diagnosis of the training offer in non-
formal training in the area of electricity in
the city.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 51
- Instituto Técnico
de Electricidad y
Electrónica(ITEE)
- Escuela Técnica
Automotriz del
Norte(ESTANOR)
- Universidad
Pedagógica
nacional Francisco
Morazán
- Centro Técnico
Hondureño Alemán
(CTHA)
San Pedro
Sula,
Choloma,
Tela and La
Ceiba
February 27 and 28,
2017 March 1, 3, 8 and
9, 2017
- Instituto
Millenium
- Children
International
- UNITEC
- New Hope
- Instituto Virgen
de Suyapa
- Centro Casa de
Visitación e
Instituto Cristo Rey
- Centro San Juan
Bosco
- Técnico Bet EL
- Instituto Técnico
Triunfo de la Cruz
- Instituto Técnico
Rafael Pineda
Ponce
- Diagnosis of the academic training offer
in non-formal training in different areas.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 52
- INFOP
La Ceiba February 17, 2017
Chamber of
Commerce and
Industry of Atlántida
Meeting with
Executive Director
and Vocal II – Jimi
Benitez and Denis
Maradiaga
- Explored articulating actions with the
association members for future actions
with the private sector and the support in
the Participatory Occupational Analysis
and in relation to the actions related to the
vocational center of La Ceiba.
San Pedro
Sula February 20, 2017
RETE
Meeting with
Northern
Coordinator – Erika
Cuevas
- Shared information about resumes for
facilitators.
San Pedro
Sula
February 21, 2017
AVANTE
Meeting with
Psychologist –
Sandra Galindo and
Mauricio Vasquez
- Gained information about activities
carried out by AVANTE for the services of
the Cognitive Behavioral Therapy
component.
San Pedro
Sula February 21, 2017
Chamber of
Commerce and
Industry of Cortés
Meeting with
Human Resources
Coordinator and
Job Board
- Articulated actions with the members for
future actions’ employment pool of the
with the private sector.
Choloma February 27, 2017
Millenium
Meeting with
Director – Ronald
Peralta
- Identified possible partners for the
implementation of community
organizations.
Choloma February 27, 2017
MOMUCLAA
Meeting with
women’s
organizations in
Lopez Arellano
- Presented program and opportunity to
look for organizations.
Tela February 28, 2017
UN Volunteers
Meeting with
PNUD Consultant –
Elvin Zepeda
- Searched for facilitators.
Tela February 28, 2017
Youth Council of the
City of Tela
Oath of the Youth
Council
- Searched for recruitment of young
beneficiaries.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 53
Tegucigalpa February 20-24, 2017
Organizational
Community Offices in
Tegucigalpa
- Visión Mundial,
PDA, La Travesía.
- RETE.
- Cruz Roja
Hondureña.
- Asociación
Compartir.
- Meeting with representatives of
organizations to coordinate nomination of
aspiring facilitators and mentors of
communities.
- Summon applicants and provide guidance
with an aspiring group.
Tegucigalpa March 2, 2017
Empleando Futuros
Offices Tegucigalpa
EDC, Expert on
technology,
Mahomar Munir
- Planned the design of the software.
San Pedro
Sula,
Choloma /La
Ceiba
March 3, 8 and 9, 2017
Morales Outreach
Center and Red Cross
in Chamelecon
Ceden Outreach
Center in Choloma
Elementary School
Marco Antonio Ponce
in las Mercedes, La
Ceiba
- Outreach Center
Coordinator -Jessy
Castro
- Red Cross
Volunteer - Odalma
Henriquez
- Thelma
Clavasquin
- Presented the program and its actions
towards training of youth and the
postulation of facilitators.
Tegucigalpa March 6-10, 2017
Facilities of
Community
Organizations
- Meetings with
aspiring groups
within the
communities: La
Travesía
- National Violence
Prevention Program
office
- San Francisco
- Campo Cielo
- Villanueva
- Shared information about upcoming RFA
with the communities, the requirements of
the process of selection of mentor and
community facilitator.
- Received resumes.
Tegucigalpa March 8, 2017
Grupo INTUR
Olga Frech, Human
Resources
Department and
representatives in
charge of training
- INTUR presented a proposal to be able to
train about 3 to 4 thousand young people in
training "model restaurant", a kitchen -
laboratory with an investment of $
79,670.00; from 3 to 5 months training
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 54
program (500-700 hours)
San Pedro
Sula March 9, 2017
Clarión Hotel
Workshop
Exchange of Good
Mentoring Practices
- Workshop to exchange experiences and
lessons learned with organizations that
work or wish to work with mentoring.
Tegucigalpa March 10 to 27, 2017
UNITEC
Representatives of
UNITEC
- Studied possibility to certify the program
of Professional Formation.
Tegucigalpa March 14, 2017
Plan Honduras/Child
Fund
Conversation with
representatives of:
Plan Honduras
Child Fund
- Project information, scope and
intervention of communities was provided.
San Pedro
Sula March 14, 2017
Together For Life
Meeting with
Director – Rene
Corea
- Diagnosis of the training offer with
tertiary prevention work.
Tegucigalpa March 16, 2017
Hyatt Place Hotel
Meeting between
Banyan
Global/Empleando
Futuros
representatives and
Private Sector
Leader: INTUR,
Mendels, and
Chamber of
Commerce
- Shared project information and learned
about the human resource needs of leading
employers.
Tegucigalpa March 16, 2017
INFOP
Meeting with Mr.
Vicente Domínguez
/ Director INFOP
La Travesía,
technical training
center, with Banyan
Global authorities,
Ms. Meghan Smith
and Mr. Louis
Alexander.
- Tour of the facilities and presentation of
the instructors.
- Learn about youth who attend INFOP and
that are part of the area benefited and on
demand for technical training.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 55
San Pedro
Sula March 17, 2017
Copantl Hotel
Meeting between
Banyan
Global/Empleando
Futuros
representatives and
Private Sector
Leaders from
COHEP, Larach y
Compañía,
GILDAN
- Shared project information and learn
about the human resource needs of leading
employers.
Tegucigalpa March 24, 2017
Empleando Futuros
Office
Meeting with Lic
Félix Alonso
Executive Secretary
and Lic. Lorena
Reyes / Education
Area of the
National Violence
Program
- Defined joint actions to work on
Outcome 1 (support, coordination,
recommendation of facilitators).
- Reference of Result 3, community visits
and elements for analysis of letter of
understanding.
Tegucigalpa March 20-31, 2017 Meetings with
technical team for
the pre-selection
and evaluation of
applicants for
facilitators and
mentors
- Reviewing applicants' resumes to
facilitators and mentors:
> 142 postulants
> 51 pre-selected from the selected
communities
Tegucigalpa March 29, 2017
Honduran Support
Group for the Deaf
Meeting with
director- Marlen
Martínez
- Presented Empleando Futuros.
- They reported companies such as BAC,
TIGO, PROMERICA, which currently
provide job opportunities to people with
disabilities.
- There is a labor inclusion table to which
they will invite the project so that it can
participate and from there to be able to
identify the feasibility of a possible
collaboration.
Tegucigalpa March 29, 2017
Empleando Futuros
Offices
Presentation day
with Life Skills and
Work Readiness
Training facilitators
- Meeting to define the induction day for
the formation of the database of facilitators
of HPV and CLB programs.
Tegucigalpa March 30, 2017 Selection day for
specialist in
- Meeting to define the terms in which the
impact assessment of Empleando Futuros.
Empleando Futuros FY17 Quarter 2 Report, January 2017 – March 2017 56
Empleando Futuros
Offices
professional
technical training
Tegucigalpa March 31, 2017
Empleando Futuros
Offices
Meeting with the
Dexis-Mescla team
- Meeting to define the terms of impact
assessment of the Empleando Futuros.
Tegucigalpa March 31, 2017
Intercontinental Hotel
Josué Moreno,
Training
- They knew about the project during the
launch event.
- They are interested in providing
opportunities for professional practices (for
this must be a formal agreement).
- Employment opportunities are few, due
to low turnover in some areas. What is
most demanded is the part time hiring for
events.
- They were open to be involved in the
Participatory Occupational Analysis, as
long as they are held inside the hotel and
are short.
- Start drafting the MOU, so we can start
with the collaboration between both
organizations.
Tegucigalpa March 31, 2017
Euro Labor
Technical team of
Euro Labor (Result
2)
- Seek an approach with the Project
"Institutional Strengthening of Decent
Employment and Opportunities for Youth
in Honduras", part of the result 2 of Euro
Labor that comes to support our Project.