DESIGN & CONSTRUCT

NEW ORBITAL HIGHWAY AND TRUCK ROUTE (P023)

Contract 3: Orbital Highway Mesaieed to Salwa Road

PROJECT ID: IA 12/13 C 062 ST

26 October 2015

Page 2: Qatar Petroleum Procedure

Date: 25/10/2015 Page 1 of 37

QP Pipe Protection Procedures

Removal of QP Pipeline bund wall

Page 3: Qatar Petroleum Procedure

Date: 25/10/2015 Page 2 of 37

QP Pipe Protection Procedures

Page 4: Qatar Petroleum Procedure

Date: 25/10/2015 Page 3 of 37

QP Pipe Protection Procedures

Trench Excavation close to pipeline

Excavation of hard rock material

Page 5: Qatar Petroleum Procedure

Date: 25/10/2015 Page 4 of 37

QP Pipe Protection Procedures

Page 6: Qatar Petroleum Procedure

Date: 25/10/2015 Page 5 of 37

QP Pipe Protection Procedures

Excavation and installation of support pedestal

Page 7: Qatar Petroleum Procedure

Date: 25/10/2015 Page 6 of 37

QP Pipe Protection Procedures

Trimming of excavation in preparation for foundation installation

Page 8: Qatar Petroleum Procedure

Date: 25/10/2015 Page 7 of 37

QP Pipe Protection Procedures

Excavated formation/foundation level

Page 9: Qatar Petroleum Procedure

Date: 25/10/2015 Page 8 of 37

QP Pipe Protection Procedures

Steel plates will be set prior to installation of arch segment

Page 10: Qatar Petroleum Procedure

Date: 25/10/2015 Page 9 of 37

QP Pipe Protection Procedures

Restricted zone during element lifting

Page 11: Qatar Petroleum Procedure

Date: 25/10/2015 Page 10 of 37

QP Pipe Protection Procedures

Arch Elements transported on flatbed trailer

Page 12: Qatar Petroleum Procedure

Date: 25/10/2015 Page 11 of 37

QP Pipe Protection Procedures

Off-Loading Arch elements using Lifting beam

Page 13: Qatar Petroleum Procedure

Date: 25/10/2015 Page 12 of 37

QP Pipe Protection Procedures

Storage of Arch Elements on Firm Ground and Proper Dunnage

Page 14: Qatar Petroleum Procedure

Date: 25/10/2015 Page 13 of 37

QP Pipe Protection Procedures

Marks on footing keyway

Page 15: Qatar Petroleum Procedure

Date: 25/10/2015 Page 14 of 37

QP Pipe Protection Procedures

Marks on unit side face for fast alignment

Page 16: Qatar Petroleum Procedure

Date: 25/10/2015 Page 15 of 37

QP Pipe Protection Procedures

Turning of Arch element with Side Brackets

Page 17: Qatar Petroleum Procedure

Date: 25/10/2015 Page 16 of 37

QP Pipe Protection Procedures

Installation of steel bracket on the segment

Page 18: Qatar Petroleum Procedure

Date: 25/10/2015 Page 17 of 37

QP Pipe Protection Procedures

First arch unit staggered by half width

Page 19: Qatar Petroleum Procedure

Date: 25/10/2015 Page 18 of 37

QP Pipe Protection Procedures

Total Station Survey Check of Crown Alignment

Page 20: Qatar Petroleum Procedure

Date: 25/10/2015 Page 19 of 37

QP Pipe Protection Procedures

Element in Footing Keyway (Unit position adjustment using hardwood wedges)

Page 21: Qatar Petroleum Procedure

Date: 25/10/2015 Page 20 of 37

QP Pipe Protection Procedures

STEP 4

RELEASE CRANE B. CRANE A CONTINUES PLACING UNIT

Erection Sequence of the Elements (units)

Page 22: Qatar Petroleum Procedure

Date: 25/10/2015 Page 21 of 37

QP Pipe Protection Procedures

Grouting Foundation Keyway

Page 23: Qatar Petroleum Procedure

Date: 25/10/2015 Page 22 of 37

QP Pipe Protection Procedures

Fig. A. Backfill Material zones Fig. B. Backfill material grain size

Page 24: Qatar Petroleum Procedure

Date: 25/10/2015 Page 23 of 37

QP Pipe Protection Procedures

Up to existing slope or final grade

Or minimum one span

Max

Backfill placement levels - Max. Differential height < 0.50 m

Page 25: Qatar Petroleum Procedure

Date: 25/10/2015 Page 24 of 37

QP Pipe Protection Procedures

Crown Beam Reinforcement Prepared According to Approved Drawings

Page 26: Qatar Petroleum Procedure

Date: 25/10/2015 Page 25 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 27: Qatar Petroleum Procedure

Date: 25/10/2015 Page 26 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 28: Qatar Petroleum Procedure

Date: 25/10/2015 Page 27 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 29: Qatar Petroleum Procedure

Date: 25/10/2015 Page 28 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 30: Qatar Petroleum Procedure

Date: 25/10/2015 Page 29 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 31: Qatar Petroleum Procedure

Date: 25/10/2015 Page 30 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 32: Qatar Petroleum Procedure

Date: 25/10/2015 Page 31 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 33: Qatar Petroleum Procedure

Date: 25/10/2015 Page 32 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 34: Qatar Petroleum Procedure

Date: 25/10/2015 Page 33 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 35: Qatar Petroleum Procedure

Date: 25/10/2015 Page 34 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 36: Qatar Petroleum Procedure

Date: 25/10/2015 Page 35 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Page 37: Qatar Petroleum Procedure

Date: 25/10/2015 Page 36 of 37

QP Pipe Protection Procedures

Minimum fill cover before heavy plant can cross the arch

Page 38: Qatar Petroleum Procedure

Date: 25/10/2015 Page 37 of 37

QP Pipe Protection Procedures

Table 1 — Earthworks Compaction criteria