Upload
pradipta-sain
View
271
Download
0
Embed Size (px)
Citation preview
7/29/2019 Pwd Final Report
1/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 1
Chapter 1: Introduction
1.1 BACKGROUND
Kazi Nazrul Islam Avenue, also known as VIP road is one of the major arterial roadsof Kolkata providing critical connectivity to the Netaji Subhas Chandra Bose
International Airport as well as to an increasing no. Residential colonies and
institutions. It starts at Ultadanga in the city core and near the airport, having total
length about 8km. It also acts the main link roads for the traffic entering the city as
well as NH2 or via NH6 (via Belghoria Expressway) as well as NH34, NH35 from
northern side of Kolkata, thereby catering to the significant quantum of through traffic
using this road.
Over the years, massive ribbon development comprising of residential, commercialand institutional activities along this corridor has started generating a huge volume of
local traffic and significant cross traffic along this corridor thereby resulting in the
massive congestion and vehicle-vehicle and vehicle pedestrian conflict at several busy
crossings. The conflict between through traffic and cross traffic at several busy
interactions has also seriously impeded the smooth and speedy movement of traffic
thereby hindering urban mobility and also endangers the safety of the urban residents.
To address this impediment to traffic movement, provide security to the residents andcater to the growing travel demand as well as substantial ribbon like urban
development along the road, a grade separation in the form of an elevated corridor is
considered to be the only viable solution for smooth flow of traffic through the
provision of two tiers of the carriageway, the upper tier as elevated corridor to cater to
the through traffic and the other, i.e. the lower tier which will be existing carriagewaywith the necessary improvement to cater to the local traffic with the provision of
service roads and facilities for non-motorized traffic and footpaths for pedestrians in
the line with the requirements of the National Urban Transport Policy (NUTP) of the
Ministry of Urban Development, Govt. of India. Additionally to facilitate smooth and
safe pedestrian crossings particularly at Keshtopur, Baguihati and Jora Mandir,
pedestrian underpasses at these locations have been proposed.
1.2 OBJECTIVE AND NEED FOR THE PROJECT
7/29/2019 Pwd Final Report
2/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 2
The need for an efficient transportation system and network to ensure uninterruptedmobility in and around the city and from/to its only airport has been felt for quite
some time. Over the last decade due to massive ribbon development comprising of
residential, commercial and institutional activities along the Kazi Nazrul IslamAvenue (KNIM) which is the main artery to the city airport has started generating a
huge volume of local traffic and significant cross traffic along this corridor thereby
resulting in massive congestion and vehicle-vehicle and vehicle-pedestrian conflict at
several busy crossing. The conflict between through traffic and cross traffic at several
busy intersections has also seriously impeded the smooth and speedy movement of
traffic thereby hindering urban mobility.
To cater to this growing travel demand while addressing the impediment due to theribbon development along the road, a grade separation in the form of an elevated
corridor is considered to be the only viable solution for smooth urban mobility along
VIP Road.
The proposed elevated corridor will form part of the major linkage between thesouthern part of the Kolkata Metropolitan Area (KMA), central business district of
Kolkata, north eastern part of KMA where the international airport of the city is
located and the north 24 paraganas district. The decadal population growth rate in
north 24 paraganas district is 22.62 percent, which is an indication of huge growth in
population in the north eastern fringe of the city of Kolkata. This growth in population
has resulted in enormous growth in traffic both through as well as cross, leading tomassive traffic congestion along stretches of the Kazi Nazrul Islam avenue thereby
increasing travel time to the citys only airport and also creating huge traffic snags for
the movement of the local residents. The airport traffic also endangers the movement
of pedestrians and non-motorized vehicles lying on the stretch.
In order to overcome traffic congestion and enhance urban mobility along KaziNazrul Islam Avenue (VIP Road) and providing safe movement for the local
pedestrians and minimise the increasing conflict of local and through traffic, it has
been proposed to build the elevated corridor that would segregate the local trafficfrom through traffic and eliminate the conflict at the major locations of Keshtopur,
Baguihati and Jora Mandir and also facilitate smooth and safe pedestrian crossings
through pedestrian underpasses in line with the provisions of the NUTP.
1.3 DESCRIPTION OF THE PROJECT CORRIDOR
The total length of the corridor over which the elevated road has been proposed is 2kms. It will follow the existing alignment of the Kazi Nazrul Islam Avenue or VIP
Road along its central verge with minor geometric correction if found necessary. Thelocation of the proposed elevated corridor is shown in the enclosed index map.
7/29/2019 Pwd Final Report
3/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 3
The project area being a very critical urban corridor is maintained by the PWD Roads,Govt. of West Bengal under its jurisdiction. The project corridor is of significant
importance as it connects the citys only airport, serves as gateway to Kolkata from
other districts within or outside KMA and also other states and also caters to anincreasing volume of urban population. Massive ribbon development can be observed
along the corridor resulting vehicle-vehicle and vehicle-pedestrian conflict at several
locations most prominent among which is Kestopur, Baguihati and Jora Mandir.
Development along the corridor is of mixed nature thereby generating mixed traffic.
These include major commercial areas of Keshtopur clubbed with residential and
institutions such as schools colleges etc. Between Keshtopur and Baguihati prominent
showrooms of leading car manufacturers can be seen. College more, Baguihati and
Jora Mandir has also undergone massive mixed use development with a number of
hospitals, banks, commercial establishments, institutions, a large market and huge
residential localities. The land adjacent to the road at Baguihati is used as parking lot
and terminal for busses originating from Baguihati to various locations in KMA.
Besides, PWD mechanical workshops and stack yard is located adjacent to the project
stretch. The Baghjola canal crosses the project corridor at Keshtopur via a skewed
bridge with sluice gates. There are a no. of cross roads at Keshtopur, college more,
Baguihati and Jora Mandir which carry considerable cross traffic that are of mixed
nature out of which a large no. of pedestrian traffic can be observed. Traffic along the
project corridor is of mixed nature varying from heavy traffic like busses, trucks etc.
to medium and light commercial vehicles to auto rickshaws, two wheelers and non-
motorized traffic comprising of rickshaws , bicycles and pedestrian traffic.
7/29/2019 Pwd Final Report
4/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 4
INDEX MAP
7/29/2019 Pwd Final Report
5/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 5
Chapter 2: Environmental and social impact study
2.1 INTRODUCTION
In order to identify the environmental issues related to the activities for construction of a road
with two separate ramps between Keshtopur and Jora Mandir on Kazi Nazrul Islam Avenue
(KNIA) also known as VIP Road an environmental social assessment were carried out on thebasis of secondary data. Environmental assessment includes the study of present
environmental set-up in and around the project influence area.
2.2 STUDY OBJECTIVES
The objectives of the environmental assessment are to enable early determination and
evaluation of potential impacts on ambient environment due to project related activities
during construction and operation phases and thereafter examination of level of study
required in the succeeding period. The Environmental assessment would also help to design
the project in an environmentally sustainable and socially acceptable mode by incorporatingenvironmental regulations and suggestion made by the possible funding institutions.
2.3 ENVIRONMENTAL IMPACT ASSESSMENT REQUIREMENT OF THE PROJECT
Regional Environmental Settings
Anticipated Environmental Impacts and Mitigation Measures
Environmental Impactsconstruction phase On Air Quality On noise level On water quality On soil On Ecology
Causes of Impacts on Air Quality
Land clearing
7/29/2019 Pwd Final Report
6/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 6
Construction of pavementsNoise pollution will be caused by
Operation of construction equipments such as earth moving and material handlingequipments.
Cause of Impacts on Water Quality
Water quality may deteriorate from runoff and waste generated from constructionactivities.
Impact on Soil
Contamination of soil is expected due to deposition of construction materials andwaste products as well as fuel and lubricant spillage from vehicles.
Impacts on Ecology
Unforeseen accidents could result in personal injuries and damage to private orpublic property.
Environmental Impactsoperational phaseDuring operational phase the environmental impacts are likely to be mostly positive.
However there could be some adverse impacts due to inadequateoperations/maintenance/control. Increase in air pollution is expected during the operation
phase since traffic volume is predicted to be high. It is essential that appropriate traffic safety
measures are included in project design.
Road safety and Traffic Management during Construction
Contractor in consultation with PWD, (Road) will have to prepare a trafficmanagement plan for approval of the State Police. The plan will include:
Measures to be taken to prevent traffic congestion. Provision of temporary safe access to school/residence that will be blocked due to
construction.
7/29/2019 Pwd Final Report
7/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 7
Measures to be taken for safe passage of traffic including temporary diversions andseparation of motor vehicle traffic from non-motorised and pedestrian traffic where
necessary.
Measures to be taken to ensure safety to traffic passing through the construction areaincluding signs, marking flags, lights and flagmen as may be required.
2.4 SOCIAL IMPACTS
The following sections discuss the social impacts of the proposed project and also focus on
the various conclusions and recommendations in order to eliminate adverse effects on thesocial environment of the study area.
Social Impact Assessment
Baseline situation of certain well-defined pockets have been studied while discussing the
social setting of the immediate project area. These pockets include following:
Ultadanga Multi-Point Crossing VIP Road (along the Keshtopur Canal) Lake Town Bangur Avenue DumDum Park Areas adjacent to proposed elevated corridor like Keshtopur, Baguihati and Jora
Mandir.
Ultadanga Multi Point CrossingThe Ultadanga Intersection is adjacent to HUDCO more. Different kinds of shops are seen in
this place .A footbridge has been constructed at this multi point crossing to facilitate
movement of pedestrian traffic. Heavy traffic movement marks this densely built-up area.
Noise pollution and air pollution levels are high. This is basically a commercial location. The
social nature of this area is truly cosmopolitan.
7/29/2019 Pwd Final Report
8/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 8
VIP Road and GolaghataHigh-rise multi-storied apartments, factory warehouses, vehicle showrooms, commercial
establishments, stationery shops, resorts, restaurants, vacant spaces etc. are noticed along VIP
Road. The Keshtopur Canal runs parallel to the VIP Road. This is the single major road
leading to the Netaji Subhash International and Domestic Air Terminal Dum Dum . Vehicular
traffic level is considerably high. A large population that provides a range of domestic and
professional services in capacity of domestic helps, drivers, cooks, maids, shop assistants,
garage boys, telephone booth operators, photocopier operators, attendants etc. also lives in
this area. Water bodies are also seen along the VIP Road. Large advertisements are noticed
along the roadside. These are lit up during the evening.
Lake TownHigh-rise multi-storied apartments, factory warehouses, vehicle showrooms, commercial
establishments, stationery shops, resorts, restaurants, vacant spaces etc. are noticed in Lake
Town. A large population that provides a range of professional services also seen in Lake
Town. There is a footbridge constructed across the VIP Road connecting Lake Town with
Salt Lake City.
Bangur AvenueHigh-rise multi-storied apartments, factory warehouses, vehicle showrooms, commercial
establishments, stationery shops, resorts, restaurants, vacant spaces etc. are noticed in Bangur
Avenue. Well-to-do section of the society live in the affluent apartments here.
Dum Dum ParkThis area is also similar to Bangur Avenue in its characteristics and social fabric with high
rise multi storied residential apartments and commercial establishments, restaurants.
7/29/2019 Pwd Final Report
9/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 9
Chapter 3: Engineering Surveys & Investigation
A detailed ground reconnaissance of the project road was undertaken after the study of maps
and preliminary data collected. Separate teams were deployed along the roadway section to
conduct surveys and investigation, the summary of which is enlisted in succeeding sections.
3.1 TOPOGRAPHIC SURVEY
EQUIPMENTS Electronic total station with angular accuracy of 1 sec Auto Level having accuracy of 2.5 mm/km Other items like measuring tapes, ranging rods, etc. as required. STANDARD CODES USED IRC:SP 19-2001 IRC:SP 13 SURVEY PROCEDURE Location of Temporary Bench Marks(TBM) Fixation of Temporary Bench Mark(TBM) Levels
All leveling are carried out from the GTS BM located at Baguihati Central Godown,
Baguihati, under Alipore Sub-Division having value of 3.943 with Auto Level
having accuracy 2.5 mm/km.
7/29/2019 Pwd Final Report
10/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 10
Details of TBM points have been furnished in the table below:
TBM
No.
Chainage
(km)
Northing
(N)
Easting
(E)
Elevation
(Z)
Side Offset from
center
Line(m)
TBM-1 3.168 10830.91 11295.66 3.781 Right 19.55
TBM-2 3.219 10884.15 11307.08 3.840 Right 20.53
TBM-3 4.280 11456.34 12172.67 3.710 Left 16.00
TBM-4 4.355 11493.59 12236.90 3.531 Left 13.13
TBM-5 4.603 11618.95 12454.90 3.531 Right 15.52
TBM-6 4.654 11646.43 12498.06 3.326 Right 14.90
Taking detail Survey Readings Ground Features Take Off Survey Coding Guidelines for Typical Feature Surveys Long Sections Cross Sections Cross Section at Culverts Temporary(TEMP) Stations
Survey Controls The entire topographic survey has been carried out by Total Station having
facility of transferring data to computer.
All transverse stations were recorded with X,Y and Z co-ordinates and werechecked to eliminate any error.
The TBMs were connected for X and Y co-ordinates by Total Stations withclosing at intervals.
Levels of all Temporary BMs were obtained by Auto Levels only. Levels wereclosed to eliminate any error. However, subsequent leveling from TBMs for
contouring purpose(detailing) have been carried out by Total Station.
7/29/2019 Pwd Final Report
11/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 11
Ground Verification Digital Terrain Modeling (DTM)
3.2 ROAD AND PAVEMENT INVESTIGATIONS
Road Inventory Survey Pavement Investigation
Pavement Condition Survey
a) Pavement Condition Surveyi. Pavement
Cracking(narrow and wide) Ravelling(% of pavement area affected) Potholing(% of pavement area affected) Edge Break(length in meters) Rut depth(in mm)
ii. ShoulderShoulders are unpaved and their condition
is indicated along with pavement condition
b) Subgrade Characteristics and StrengthAfter dividing the road into homogeneous segments with
respect to pavement condition and strength, soil classificationand mechanical characteristics of subgrade soil along the
existing road alignment have been carried out by digging pits
@ 1 pit per km in a staggered manner on both sides of the
road. The tests include :
In-situ density and moisture content of sample of eachpit
Grain Size Analysis Atterberg Limits Modified Proctor Test Laboratory CBR
7/29/2019 Pwd Final Report
12/33
7/29/2019 Pwd Final Report
13/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 13
Chapter 4: Construction Programme
4 .1 CONSTRUCTION EQUIPMENT:
The project is basically a decongestion and capacity augmentation project by constructing
one elevated corridor along with construction of service road, footpath cum drain and
widening of main carriageway including two numbers culverts. All necessary equipments/
machineries for fully mechanized construction will be necessary for timely implementation of
the project. The list of equipments given below in the table includes the machineries related
to the earthworks, base/ sub-base works, concrete works, structural works and other
miscellaneous works.
4.2 CON STRUCTION PROGRAM M E AND M ETHODO LOGY:
The construction methodology envisages composite super structure with steel pier in the
viaduct portion. The main purpose of adopting this type of construction is to minimize the
disruption in traffic flow during construction period and also to reduce the tenure of
construction period. During construction, central portion of selected stretches of VIP road
shall have to be barricaded. The steel column and & girders will be fabricated at workshop
and transported to site by trailer. The size of single piece will guide the location of splicing.
The girders will be launched on piers and the deck slab will be cast by taking temporary
support from the girders. After completion of decking, crash barrier, expansion joint, railing
and all the appurtenances will be fixed and wearing course will be laid. The embankment
portion of the flyover will be constructed by R.E wall.
The total duration of project construction period has been considered as 20 months.
7/29/2019 Pwd Final Report
14/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 14
List of Equipments:
Type of Equipment Output of Machine Remarks
Air Compressor 1250 sqm/hr Surface cleaning
Batching and mixing plant 15-20 cum/hr Concrete MixBatching and mixing
plant(30cum)
30 cum/hr Concrete Mix
Concrete Mixer(0.4/0.28 cum) 2.5 cum/hr Concrete Mix
Concrete Pump 25 cum/hr Concrete Mix
Crane-35T 35 Tonne For lifting
Crane-3T 3 Tonne For lifting
Crane-80T 80 Tonne For lifting
Dozer D-50-A 15 150 cum/hr Clearing
Dozer D-80-A12 180 cum/hr Clearing
Front-end Loader 25 cum/hr Aggregate Loading
Generator 300 KVA 300 kva Hot Mix Plant
Generator 100 KVA 100 kva WMM Plant
Hot Mix Plant(60-90 TPH) 60-90 cum/hr Asphalt Mix
Hydraulic Excavator 60 cum/hr Excavation
Mastic Cooker 1 tonne/hr Mastic asphalt
Mechanical Broom 1250 sqm/hr Surface cleaning
Motor Grader(3.35 m blade) 50 cum/hr GSB Spreading
Motor Grader(3.35 m blade) 200 cum/hr Soil Spreading
Paver Finisher(with sensorcontrol)
30 cum/hr Asphalt Mix Laying
Piling rig with Bentonitepump
2 to3 RM/hr Boring
Pressure distributor(Bitumen) 1750 sqm/hr Tack coat/ Prime coat
Pressure distributor(Emulsion) 1750 sqm/hr Tack coat/ Prime coat
Road Marking Machine 100 sqm/hr Road Marking
Roller(Ordinary) 70 cum/hr Earth/ Soil
Roller(Pneumatic tyred) 25 cum/hr Asphalt works
Roller(Tandem) 30 cum/hr Asphalt works
Roller(Vibratory) 100 cum/hr Earth/ Soil
Tipper/ Trucks 5.5 cum All kinds of material
Transit Mixer 3 cum/hr Transportation of concrete
mix
Transit Mixer 4.5 cum/hr Transportation of concrete
mix
Wet Mix Plant(60 TPH) 60 Tonne/hr WMM
7/29/2019 Pwd Final Report
15/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 15
Chapter 5: Cost Estimation and Rate Analysis
5.1 GENERAL
The methodologies adopted for estimating the cost of the proposed elevated corridor and its
ancillary works which may be divided be divided in three board items of works as follows:
Proposed elevated corridor Improvement of existing road and Proposed pedestal subway
For each item of work the cost estimate has been arrived based on following steps:
Analysis of unit rates of various items of work. Estimation of quantities for site clearance & utility relocation. Estimation of quantity for earthwork and road components e.g. pavement, cross
drainage structures, bridges etc. and other ancillaries as per relevant IRC/IS and
MoRTH specifications. Consideration of allowances for contingencies.
5.2 ANALYSIS OF RATES:
The rates of various item of works associated with the proposed project has been arrived
based on public works (roads ),directorate ,schedule of rates ,2008 government of West
Bengal with latest addendum and corrigendum issued on 1st
July ,2010. Considering cost of
materials, machinery and labour with additional percentages to concider Over head Chargesand Contractors profit. The said schedule of Rates follows the guidelines furnished in
MoRT&Hs Standard Data Book (first revision 2003).
Rates of item of works which are not covered in schedule of rates, 2008 of public works
(roads) directorate, the rates have been taken from PWD, NH Schedule of Rates,2007-2008
Govt. of West Bengal. Moreover the rates of structural steel & bolt including fabrication &
erection have been analyzed considering the present market rate.
The contractors profit has been considered on all items at uniform rate of 10%. The profit
has been considered applicable on material, machinery, labour cost and overhead charges, asper the MoRTH Standard Data Book.
7/29/2019 Pwd Final Report
16/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 16
5.3 COST ESTIMATE:
The cost estimate of the project has been delivered based on the rates for various items of
work taken from schedule of different departments.
The estimated cost of the project amounts Rs. 208,03,88,745 (Rupees Two Hundred EightCrores Three Lakhs Eight Eighty Thousand Seven Hundred Forty Five only).
The abstract of the estimated cost of the project is provided in the table below:
SL NO. ITEM OF WORK AMOUNT(Rs.) REMARKS
A. Proposed Elevated Corridor
Foundation 18,18,98,118 Substructure 32,63,14,822 Superstructure 107,40,15,814 Approach ramp 2,15,93,387 Miscellaneous 34,49,971
Subtotal ( Proposed Elevated
Corridor)
160,72,72,112
B. Improvement of existing road
1. Road works 144810723
2. Side drain 80854994
3. CD structure 15396854
4. Miscellaneous works 20079056
Sub total ( Improvement of existing
road)
261141627
C. Proposed pedestrian subway
Subway at Kestopur 17403694 Subway at Baguiati 18743098 Subway at Jora
mandir
17144904
Sub Total( Proposed pedestriansubway)
53291696
7/29/2019 Pwd Final Report
17/33
7/29/2019 Pwd Final Report
18/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 18
Chapter 6:Subgrade Soil Investigation
SUBGRADE SOIL INVESTIGATION
In order to access the existing pavement composition including subgrade soil properties test
pits of size 1.00m*1.00m were excavated at the pavement shoulder interface down to the
subgrade level.
The following tests are performed on the soil sample:
A field dry density using sand replacement method was carried out at the subgrade levelas per IS:2720(Part 28).
On the soil sample collected from the top 300mm of subgrade classification and thefollowing laboratory tests were performed:
Field moisture content(as per IS:2720(Part 2)- 1973) Grain size analysis(as per IS:2720(Part 4)- 1985)Grain size analysis express quantitatively the proportions by mass of the various size of
particles present in the soil.
7/29/2019 Pwd Final Report
19/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 19
Atterberg Limits(as per IS:2720(Part 5)- 1985) Plastic limit: The plastic limit of fine-grained soil is the water content of the soil
below which it ceases to be plastic. It begins to crumble when rolled into threads
of 3mm dia.
Liquid Limit: The liquid limit is the water content at which it will takes 25 blowsto close the groove over a distance of 13 mm.
Plasticity Index: The plasticity index (PI) is a measure of the plasticity of a soil.The plasticity index is the size of the range of water contents where the soil
exhibits plastic properties. The PI is the difference between the liquid limit and the
plastic limit (PI = LL-PL). Soils with a high PI tend to be clay, those with a lower
PI tend to be silt, and those with a PI of 0 (non-plastic) tend to have little or no silt
or clay.
Modified Proctor Test or Heavy Compaction Test
7/29/2019 Pwd Final Report
20/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 20
Soil at known water content is placed in a specified rammer in to a mould of given
dimensions, subjected to a compactive effort of controlled magnitude and the resulting unit
weight determination. The procedure is repeated for varying Water Content and Dry Unit
Weight.
California Bearing Ratio Test4 days soaked(as per IS:2720(Part 16)- 1985)
The Ratio of the force per unit area to penetrate a soil mass with circular plunger of 50 mm
diameter @ 1.25 mm/min to that required for corresponding penetration of a standard
material.
CBR = [PT / PS] x 100
PT = Corrected unit (or total) test load corresponding to the chosen penetration from the loadpenetration curve (fig. 2 of chapter IS: 2720 (Part 16)-1979 Method of test for soils: Part 16
Laboratory Determination of CBR (first revision) in Compendium of Indian Standards on
Soil Engineering Part 1)
7/29/2019 Pwd Final Report
21/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 21
PS = unit (or total) standard load for the same depth of penetration as for PS taken from table
below.
CBR Apparatus
7/29/2019 Pwd Final Report
22/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 22
Chapter 7:Geotechnical Investigation
In order to obtain information on the physical properties of soil and rock around a site to
design earthworks and foundations for proposed structures and for repair of distress to
earthworks and structures caused by subsurface conditions.
Description Of Field Work
Some soil core samples were collected and these samples were taken to the laboratoryfor tests to obtain various properties of sub soil formation.
Laboratory Testing
The following laboratory tests were carried out on disturbed and undisturbed soil samples
for identification and classification purposes and to obtain the strength and other properties of
the formation.
Grain Size Analysis Natural Moisture Content Atterbergs Limits Specific Gravity:
This is the ratio of the mass of unit volume of soil at a stated temperature to the mass of the
same volume of gas free distilled water at a stated temperature.
7/29/2019 Pwd Final Report
23/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 23
Triaxial Test:A cylindrical specimen of soil encased in an impervious membrane is subjected to a constant
confining pressure and then loaded axially @ 1.25 mm per minute to failure without change
in total water content in the specimen.
The test is limited to specimen in the form of the right cylinder of nominal diameter 38 mm
and height equal to twice the nominal diameter. The ratio of diameter of the specimen to
maximum size of particle in the soil should not be less than 5.
Triaxial Apparatus
One Dimensional Consolidation Test:A test in which the specimen is laterally confined in a ring and is compressed between porous
plates in fully saturated condition. The gradual reduction in volume of soil mass on
application of compressive stress is due to expulsion of water from the pores. The height of
the ring shall not be less than 20mm. with diameter to height ratio of about 3. Further the
specimen height shall be not less than 10 times the maximum particle size.
Consolidation Apparatus
7/29/2019 Pwd Final Report
24/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 24
Chapter 8: Substructure - Piling
8.1 Pile
In this project all the piles were 1000 mm in diameter, 20-25m in length, concrete and
cast-in-situ. These were basically friction piles. For the construction of the pile it should not
take more than 8 hours.
The steps are
Survey Casing punching/driving Boring/drilling Cage lowering Tremmie lowering Flushing Concreting
First the surveyor will give the point for the drilling following the centreline of
formwork. After that a temporary casing is driven but the erection has to be straight so
from the centre two perpendicular lines of 2m is taken together with that spirit level is
used for the straightening of the casing. Constant length of the diagonal is maintained
during the driving of the casing.Boring is done with the help of Hydraulic Rotary piling rig. Temporary steel casing of
required length will be driven. After reaching the founding level the bore will be
thoroughly flushed with fresh bentonite solution. Reinforcement cages will be
prefabricated in suitable length of about 10m. These will be lap welded at site and
lowered in to the bore with the help of mobile crane. On placing the reinforcement
cage, tremmie pipe elements will be assembled and lowered inside the cage. The bore
will be then concreted by tremmie method with a minimum slump of 150mm.
8. 2 Pile cap
After the approval of the pile report, green flag is given to the construction of the pile
cap. The concreting of the pile is done up to the ground level bit it is cut down to cut off level
to get the sound concrete. The reinforcement from the pile is extended further and enters in to
the cap. The reinforcement of the pile cap is made and then concreting. This kind of work is
given to the subcontractor. But before the pile cap a floor of pain concrete (PCC) is done.
Dewatering is also done to expel water from the pit before the concreting.
7/29/2019 Pwd Final Report
25/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 25
Chapter 9: Pavement Analysis and Design
GEOMETRIC DESIGN:
The project corridor lies in plain terrain and passing through highly urbanized areas. As such,
the geometric standards relevant to plain terrain as per IRC: 73-1980 and IRC: 86-1983 have
been adopted.
DESIGN SPEED:
Design speed is the single most important factor that affects the geometric design. It directly
affects the sight distance, horizontal curve, and the length of vertical curves. Since the speed
of vehicles vary with driver, terrain etc, a design speed is adopted for all the geometric
design.
Design speed is defined as the highest continuous speed at which individual vehicles can
travel with safety on the highway when weather conditions are conducive.
HORIZONTAL ALLIGNMENT:
Horizontal alignment is one of the most important features influencing the efficiency and
safety of a highway. Horizontal alignment design involves the understanding on the design
aspects such as design speed and the effect of horizontal curve on the vehicles. The horizontalcurve design elements include design of super elevation, extra widening at horizontal curves,
design of transition curve, and set back distance.
HORIZONTAL CURVES:
The presence of horizontal curve imparts centrifugal force which is a reactive force acting
outward on a vehicle negotiating it. Centrifugal force depends on speed and radius of the
horizontal curve and is counteracted to a certain extent by transverse friction between the tyre
7/29/2019 Pwd Final Report
26/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 26
and pavement surface. On a curved road, this force tends to cause the vehicle to overrun or to
slide outward from the centre of road curvature. For proper design of the curve, an
understanding of the forces acting on a vehicle taking a horizontal curve is necessary.
Various forces acting on the vehicle are illustrated in the figure 1.
Figure 1: Effect of horizontal curve
They are the centrifugal force (P) acting outward, weight of the vehicle (W) acting downward,
and the reaction of the ground on the wheels (Ra and Rb)The centrifugal force and the weight is
assumed to be from the centre of gravity which is at h units above the ground. Let the wheel base
be assumed as b units. The centrifugal force in kg/m2 is given by
where is the weight of the vehicle in kg, is the speed of the vehicle in m/sec , g is the
acceleration due to gravity in m/sec2
and is the radius of the curve in
VERTICAL ALLIGNMENT:
The vertical alignment of a road consists of gradients (straight lines in a vertical plane) and
vertical curves. The vertical alignment is usually drawn as a profile, which is a graph with
elevation as vertical axis and the horizontal distance along the centre line of the road as the
the horizontal axis.
GRADIENT:
Gradient is the rate of rise or fall along the length of the road with respect to the horizontal.
While aligning a highway, the gradient is decided for designing the vertical curve.
7/29/2019 Pwd Final Report
27/33
7/29/2019 Pwd Final Report
28/33
7/29/2019 Pwd Final Report
29/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 29
DESIGN TRAFFIC
The method considers traffic in terms of the cumulative number of standard axles (8160 kg)
to be carried by the pavement during the design life. This requires the following information:
1. Initial traffic in terms of CVPD
2. Traffic growth rate during the design life
3. Design life in number of years
4. Vehicle damage factor (VDF)
5. Distribution of commercial traffic over the carriage way.
PAVEMENT THICKNESS DESIGN CHARTS
For the design of pavements to carry traffic in the range of 1 to 10 msa, use chart 1 and for
traffic in the range 10 to 150 msa, use chart 2 of IRC:37 2001. The design curves relate
pavement thickness to the cumulative number of standard axles to be carried over the design
life for different sub-grade CBR values ranging from 2 % to 10 %. The design charts will
give the total thickness of the pavement for the above inputs. The total thickness consists of
granular sub-base, granular base and bituminous surfacing. The individual layers are
designed based on the the recommendations given below and the subsequent tables.
PAVEMENT COMPOSITION
Sub-base
Sub-base materials comprise natural sand, gravel, laterite, brick metal, crushed stone or
combinations thereof meeting the prescribed grading and physical requirements. The sub-base material should have a minimum CBR of 20 % and 30 % for traffic upto 2 msa and
traffic exceeding 2 msa respectively. Sub-base usually consist of granular or WBM and the
thickness should not be less than 150 mm for design traffic less than 10 msa and 200 mm for
design traffic of 1:0 msa and above.
Base
The recommended designs are for unbounded granular bases which comprise conventional
water bound macadam (WBM) or wet mix macadam (WMM) or equivalent confirming to
7/29/2019 Pwd Final Report
30/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 30
MOST specifications. The materials should be of good quality with minimum thickness of
225 mm for traffic up to 2 msa an 150 mm for traffic exceeding 2 msa.
Bituminous surfacing
The surfacing consists of a wearing course or a binder course plus wearing course. The most
commonly used wearing courses are surface dressing, open graded premix carpet, mix seal
surfacing, semi-dense bituminous concrete and bituminous concrete. For binder course,
MOST specifies, it is desirable to use bituminous macadam (BM) for traffic upto o 5 msa and
dense bituminous macadam (DBM) for traffic more than 5 msa.
7/29/2019 Pwd Final Report
31/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 31
Chapter 10: Institutional Framework
FRAMEWORK FOR IMPLEMENTATIONThe project is to be implemented with the intention of decongesting and improving
urban mobility of the Kolkata city. The project would be developed on a public
funded format with partial resources from the state government budget. Construction
should take a period of 18 months.
AUTHORITY FOR APPROVALS/ CLEARANCESThe project would require approvals from the following departments as part of theproject implementation
a) Public Works departmentb) Utilities agencies such as Electricity Boards/ Telephone exchangec) State Pollution control Boardd) Any other approvals, as may be required during implementation
Project Risk Assessment Funding Risk
Construction Risks Cost Overrun Risk Approvals Risk Operation & Maintenance Risks
Present levels of service and proposed improvement1) Present scenario
Kazi Nazrul Islam Avenue (KNIA) or the VIP acts as the main arterial road to
access Kolkata city from Netaji Subhas Chandra Bose International Airport and
National Highways No. 34,35,2 and 6. The existing traffic scenario seriously
impedes smooth urban mobility due to following reasons:-
No separate provision exists for the segregation of through traffic and localtraffic generated from the various cross roads that exist along the project
road.
No separate service road exists for segregation of local slow moving trafficfrom fast moving traffic.
Non existence of adequate pedestrian facilities for smooth passage in themain crossing especially at Kestopur, Baguihati and Jora Mandir.
Unauthorized and haphazard road side parking and scattered movement ofthe pedestrian.
7/29/2019 Pwd Final Report
32/33
Summer Vocational Training 2012
4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul
Islam Avenue [VIP Road] Page 32
2) Proposed DevelopmentsTo address the problem of congestion, provide adequate facilities for pedestrian
and facilitate uninterrupted mobility the following measures have been proposed.
(A) Standardize the road cross section of the proposed corridor foraugmentation of the road capacity to cater future vehicular and pedestriantraffic.
Enhance capacity of the corridor by providing standard 6 lanedivided carriageway.
Segregating the local traffic from through traffic and alsomotorized from non-motorized traffic.
Pedestrian facilities need to be planned to minimize thepedestrian conflicts with vehicular traffic.
Parking area needs to be identified especially near the schooland college areas and necessary parking lane has to be
provided.
(B) Proposing Vertical segregation of the through traffic and cross traffic inthe congested stretch and busy intersection to eliminate the conflict among
them.
By providing 4-lane elevated flyover from Kestopur to Jora Mandir via
Baguihati crossing are proposed for through traffic along proposed
corridor. Flyover length will be 1658.5m
(C) Provision for separate Pedestrian subwayProvision for pedestrian subways has been planned at Kestopur, Jora
Mandir and Baguihati with an aim to facilitate smooth and safe pedestrian
crossing and eliminate pedestrian vehicle conflict.
Salient features of pedestrian subways:
a) Location : At Kestopur- Ch. 3.346 KmAt Baguiati- Ch. 4+212 Km
At Jora Mandir Ch. 4+607 Km
b) Vertical clear height : 2.75 mc)
Width of subway : 6.50 m
(D) Road Side Drainage :Longitudinal PCC drain have been provided on the both side of the road
and connected with the existing CD structure for the smooth passage of
storm water.
Major improvements envisaged are as follows:
Reduced travel time (proposed design speed of 70 km/hr) Smooth well maintained pot hole free riding surface Efficient traffic management system including signals, sign boards
and road delineators
Proposed illuminated carriageway
7/29/2019 Pwd Final Report
33/33
Summer Vocational Training 2012
Uninterrupted movement for pedestrians Overall safety Improved mobility