Pwd Final Report

Embed Size (px)

Citation preview

  • 7/29/2019 Pwd Final Report

    1/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 1

    Chapter 1: Introduction

    1.1 BACKGROUND

    Kazi Nazrul Islam Avenue, also known as VIP road is one of the major arterial roadsof Kolkata providing critical connectivity to the Netaji Subhas Chandra Bose

    International Airport as well as to an increasing no. Residential colonies and

    institutions. It starts at Ultadanga in the city core and near the airport, having total

    length about 8km. It also acts the main link roads for the traffic entering the city as

    well as NH2 or via NH6 (via Belghoria Expressway) as well as NH34, NH35 from

    northern side of Kolkata, thereby catering to the significant quantum of through traffic

    using this road.

    Over the years, massive ribbon development comprising of residential, commercialand institutional activities along this corridor has started generating a huge volume of

    local traffic and significant cross traffic along this corridor thereby resulting in the

    massive congestion and vehicle-vehicle and vehicle pedestrian conflict at several busy

    crossings. The conflict between through traffic and cross traffic at several busy

    interactions has also seriously impeded the smooth and speedy movement of traffic

    thereby hindering urban mobility and also endangers the safety of the urban residents.

    To address this impediment to traffic movement, provide security to the residents andcater to the growing travel demand as well as substantial ribbon like urban

    development along the road, a grade separation in the form of an elevated corridor is

    considered to be the only viable solution for smooth flow of traffic through the

    provision of two tiers of the carriageway, the upper tier as elevated corridor to cater to

    the through traffic and the other, i.e. the lower tier which will be existing carriagewaywith the necessary improvement to cater to the local traffic with the provision of

    service roads and facilities for non-motorized traffic and footpaths for pedestrians in

    the line with the requirements of the National Urban Transport Policy (NUTP) of the

    Ministry of Urban Development, Govt. of India. Additionally to facilitate smooth and

    safe pedestrian crossings particularly at Keshtopur, Baguihati and Jora Mandir,

    pedestrian underpasses at these locations have been proposed.

    1.2 OBJECTIVE AND NEED FOR THE PROJECT

  • 7/29/2019 Pwd Final Report

    2/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 2

    The need for an efficient transportation system and network to ensure uninterruptedmobility in and around the city and from/to its only airport has been felt for quite

    some time. Over the last decade due to massive ribbon development comprising of

    residential, commercial and institutional activities along the Kazi Nazrul IslamAvenue (KNIM) which is the main artery to the city airport has started generating a

    huge volume of local traffic and significant cross traffic along this corridor thereby

    resulting in massive congestion and vehicle-vehicle and vehicle-pedestrian conflict at

    several busy crossing. The conflict between through traffic and cross traffic at several

    busy intersections has also seriously impeded the smooth and speedy movement of

    traffic thereby hindering urban mobility.

    To cater to this growing travel demand while addressing the impediment due to theribbon development along the road, a grade separation in the form of an elevated

    corridor is considered to be the only viable solution for smooth urban mobility along

    VIP Road.

    The proposed elevated corridor will form part of the major linkage between thesouthern part of the Kolkata Metropolitan Area (KMA), central business district of

    Kolkata, north eastern part of KMA where the international airport of the city is

    located and the north 24 paraganas district. The decadal population growth rate in

    north 24 paraganas district is 22.62 percent, which is an indication of huge growth in

    population in the north eastern fringe of the city of Kolkata. This growth in population

    has resulted in enormous growth in traffic both through as well as cross, leading tomassive traffic congestion along stretches of the Kazi Nazrul Islam avenue thereby

    increasing travel time to the citys only airport and also creating huge traffic snags for

    the movement of the local residents. The airport traffic also endangers the movement

    of pedestrians and non-motorized vehicles lying on the stretch.

    In order to overcome traffic congestion and enhance urban mobility along KaziNazrul Islam Avenue (VIP Road) and providing safe movement for the local

    pedestrians and minimise the increasing conflict of local and through traffic, it has

    been proposed to build the elevated corridor that would segregate the local trafficfrom through traffic and eliminate the conflict at the major locations of Keshtopur,

    Baguihati and Jora Mandir and also facilitate smooth and safe pedestrian crossings

    through pedestrian underpasses in line with the provisions of the NUTP.

    1.3 DESCRIPTION OF THE PROJECT CORRIDOR

    The total length of the corridor over which the elevated road has been proposed is 2kms. It will follow the existing alignment of the Kazi Nazrul Islam Avenue or VIP

    Road along its central verge with minor geometric correction if found necessary. Thelocation of the proposed elevated corridor is shown in the enclosed index map.

  • 7/29/2019 Pwd Final Report

    3/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 3

    The project area being a very critical urban corridor is maintained by the PWD Roads,Govt. of West Bengal under its jurisdiction. The project corridor is of significant

    importance as it connects the citys only airport, serves as gateway to Kolkata from

    other districts within or outside KMA and also other states and also caters to anincreasing volume of urban population. Massive ribbon development can be observed

    along the corridor resulting vehicle-vehicle and vehicle-pedestrian conflict at several

    locations most prominent among which is Kestopur, Baguihati and Jora Mandir.

    Development along the corridor is of mixed nature thereby generating mixed traffic.

    These include major commercial areas of Keshtopur clubbed with residential and

    institutions such as schools colleges etc. Between Keshtopur and Baguihati prominent

    showrooms of leading car manufacturers can be seen. College more, Baguihati and

    Jora Mandir has also undergone massive mixed use development with a number of

    hospitals, banks, commercial establishments, institutions, a large market and huge

    residential localities. The land adjacent to the road at Baguihati is used as parking lot

    and terminal for busses originating from Baguihati to various locations in KMA.

    Besides, PWD mechanical workshops and stack yard is located adjacent to the project

    stretch. The Baghjola canal crosses the project corridor at Keshtopur via a skewed

    bridge with sluice gates. There are a no. of cross roads at Keshtopur, college more,

    Baguihati and Jora Mandir which carry considerable cross traffic that are of mixed

    nature out of which a large no. of pedestrian traffic can be observed. Traffic along the

    project corridor is of mixed nature varying from heavy traffic like busses, trucks etc.

    to medium and light commercial vehicles to auto rickshaws, two wheelers and non-

    motorized traffic comprising of rickshaws , bicycles and pedestrian traffic.

  • 7/29/2019 Pwd Final Report

    4/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 4

    INDEX MAP

  • 7/29/2019 Pwd Final Report

    5/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 5

    Chapter 2: Environmental and social impact study

    2.1 INTRODUCTION

    In order to identify the environmental issues related to the activities for construction of a road

    with two separate ramps between Keshtopur and Jora Mandir on Kazi Nazrul Islam Avenue

    (KNIA) also known as VIP Road an environmental social assessment were carried out on thebasis of secondary data. Environmental assessment includes the study of present

    environmental set-up in and around the project influence area.

    2.2 STUDY OBJECTIVES

    The objectives of the environmental assessment are to enable early determination and

    evaluation of potential impacts on ambient environment due to project related activities

    during construction and operation phases and thereafter examination of level of study

    required in the succeeding period. The Environmental assessment would also help to design

    the project in an environmentally sustainable and socially acceptable mode by incorporatingenvironmental regulations and suggestion made by the possible funding institutions.

    2.3 ENVIRONMENTAL IMPACT ASSESSMENT REQUIREMENT OF THE PROJECT

    Regional Environmental Settings

    Anticipated Environmental Impacts and Mitigation Measures

    Environmental Impactsconstruction phase On Air Quality On noise level On water quality On soil On Ecology

    Causes of Impacts on Air Quality

    Land clearing

  • 7/29/2019 Pwd Final Report

    6/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 6

    Construction of pavementsNoise pollution will be caused by

    Operation of construction equipments such as earth moving and material handlingequipments.

    Cause of Impacts on Water Quality

    Water quality may deteriorate from runoff and waste generated from constructionactivities.

    Impact on Soil

    Contamination of soil is expected due to deposition of construction materials andwaste products as well as fuel and lubricant spillage from vehicles.

    Impacts on Ecology

    Unforeseen accidents could result in personal injuries and damage to private orpublic property.

    Environmental Impactsoperational phaseDuring operational phase the environmental impacts are likely to be mostly positive.

    However there could be some adverse impacts due to inadequateoperations/maintenance/control. Increase in air pollution is expected during the operation

    phase since traffic volume is predicted to be high. It is essential that appropriate traffic safety

    measures are included in project design.

    Road safety and Traffic Management during Construction

    Contractor in consultation with PWD, (Road) will have to prepare a trafficmanagement plan for approval of the State Police. The plan will include:

    Measures to be taken to prevent traffic congestion. Provision of temporary safe access to school/residence that will be blocked due to

    construction.

  • 7/29/2019 Pwd Final Report

    7/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 7

    Measures to be taken for safe passage of traffic including temporary diversions andseparation of motor vehicle traffic from non-motorised and pedestrian traffic where

    necessary.

    Measures to be taken to ensure safety to traffic passing through the construction areaincluding signs, marking flags, lights and flagmen as may be required.

    2.4 SOCIAL IMPACTS

    The following sections discuss the social impacts of the proposed project and also focus on

    the various conclusions and recommendations in order to eliminate adverse effects on thesocial environment of the study area.

    Social Impact Assessment

    Baseline situation of certain well-defined pockets have been studied while discussing the

    social setting of the immediate project area. These pockets include following:

    Ultadanga Multi-Point Crossing VIP Road (along the Keshtopur Canal) Lake Town Bangur Avenue DumDum Park Areas adjacent to proposed elevated corridor like Keshtopur, Baguihati and Jora

    Mandir.

    Ultadanga Multi Point CrossingThe Ultadanga Intersection is adjacent to HUDCO more. Different kinds of shops are seen in

    this place .A footbridge has been constructed at this multi point crossing to facilitate

    movement of pedestrian traffic. Heavy traffic movement marks this densely built-up area.

    Noise pollution and air pollution levels are high. This is basically a commercial location. The

    social nature of this area is truly cosmopolitan.

  • 7/29/2019 Pwd Final Report

    8/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 8

    VIP Road and GolaghataHigh-rise multi-storied apartments, factory warehouses, vehicle showrooms, commercial

    establishments, stationery shops, resorts, restaurants, vacant spaces etc. are noticed along VIP

    Road. The Keshtopur Canal runs parallel to the VIP Road. This is the single major road

    leading to the Netaji Subhash International and Domestic Air Terminal Dum Dum . Vehicular

    traffic level is considerably high. A large population that provides a range of domestic and

    professional services in capacity of domestic helps, drivers, cooks, maids, shop assistants,

    garage boys, telephone booth operators, photocopier operators, attendants etc. also lives in

    this area. Water bodies are also seen along the VIP Road. Large advertisements are noticed

    along the roadside. These are lit up during the evening.

    Lake TownHigh-rise multi-storied apartments, factory warehouses, vehicle showrooms, commercial

    establishments, stationery shops, resorts, restaurants, vacant spaces etc. are noticed in Lake

    Town. A large population that provides a range of professional services also seen in Lake

    Town. There is a footbridge constructed across the VIP Road connecting Lake Town with

    Salt Lake City.

    Bangur AvenueHigh-rise multi-storied apartments, factory warehouses, vehicle showrooms, commercial

    establishments, stationery shops, resorts, restaurants, vacant spaces etc. are noticed in Bangur

    Avenue. Well-to-do section of the society live in the affluent apartments here.

    Dum Dum ParkThis area is also similar to Bangur Avenue in its characteristics and social fabric with high

    rise multi storied residential apartments and commercial establishments, restaurants.

  • 7/29/2019 Pwd Final Report

    9/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 9

    Chapter 3: Engineering Surveys & Investigation

    A detailed ground reconnaissance of the project road was undertaken after the study of maps

    and preliminary data collected. Separate teams were deployed along the roadway section to

    conduct surveys and investigation, the summary of which is enlisted in succeeding sections.

    3.1 TOPOGRAPHIC SURVEY

    EQUIPMENTS Electronic total station with angular accuracy of 1 sec Auto Level having accuracy of 2.5 mm/km Other items like measuring tapes, ranging rods, etc. as required. STANDARD CODES USED IRC:SP 19-2001 IRC:SP 13 SURVEY PROCEDURE Location of Temporary Bench Marks(TBM) Fixation of Temporary Bench Mark(TBM) Levels

    All leveling are carried out from the GTS BM located at Baguihati Central Godown,

    Baguihati, under Alipore Sub-Division having value of 3.943 with Auto Level

    having accuracy 2.5 mm/km.

  • 7/29/2019 Pwd Final Report

    10/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 10

    Details of TBM points have been furnished in the table below:

    TBM

    No.

    Chainage

    (km)

    Northing

    (N)

    Easting

    (E)

    Elevation

    (Z)

    Side Offset from

    center

    Line(m)

    TBM-1 3.168 10830.91 11295.66 3.781 Right 19.55

    TBM-2 3.219 10884.15 11307.08 3.840 Right 20.53

    TBM-3 4.280 11456.34 12172.67 3.710 Left 16.00

    TBM-4 4.355 11493.59 12236.90 3.531 Left 13.13

    TBM-5 4.603 11618.95 12454.90 3.531 Right 15.52

    TBM-6 4.654 11646.43 12498.06 3.326 Right 14.90

    Taking detail Survey Readings Ground Features Take Off Survey Coding Guidelines for Typical Feature Surveys Long Sections Cross Sections Cross Section at Culverts Temporary(TEMP) Stations

    Survey Controls The entire topographic survey has been carried out by Total Station having

    facility of transferring data to computer.

    All transverse stations were recorded with X,Y and Z co-ordinates and werechecked to eliminate any error.

    The TBMs were connected for X and Y co-ordinates by Total Stations withclosing at intervals.

    Levels of all Temporary BMs were obtained by Auto Levels only. Levels wereclosed to eliminate any error. However, subsequent leveling from TBMs for

    contouring purpose(detailing) have been carried out by Total Station.

  • 7/29/2019 Pwd Final Report

    11/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 11

    Ground Verification Digital Terrain Modeling (DTM)

    3.2 ROAD AND PAVEMENT INVESTIGATIONS

    Road Inventory Survey Pavement Investigation

    Pavement Condition Survey

    a) Pavement Condition Surveyi. Pavement

    Cracking(narrow and wide) Ravelling(% of pavement area affected) Potholing(% of pavement area affected) Edge Break(length in meters) Rut depth(in mm)

    ii. ShoulderShoulders are unpaved and their condition

    is indicated along with pavement condition

    b) Subgrade Characteristics and StrengthAfter dividing the road into homogeneous segments with

    respect to pavement condition and strength, soil classificationand mechanical characteristics of subgrade soil along the

    existing road alignment have been carried out by digging pits

    @ 1 pit per km in a staggered manner on both sides of the

    road. The tests include :

    In-situ density and moisture content of sample of eachpit

    Grain Size Analysis Atterberg Limits Modified Proctor Test Laboratory CBR

  • 7/29/2019 Pwd Final Report

    12/33

  • 7/29/2019 Pwd Final Report

    13/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 13

    Chapter 4: Construction Programme

    4 .1 CONSTRUCTION EQUIPMENT:

    The project is basically a decongestion and capacity augmentation project by constructing

    one elevated corridor along with construction of service road, footpath cum drain and

    widening of main carriageway including two numbers culverts. All necessary equipments/

    machineries for fully mechanized construction will be necessary for timely implementation of

    the project. The list of equipments given below in the table includes the machineries related

    to the earthworks, base/ sub-base works, concrete works, structural works and other

    miscellaneous works.

    4.2 CON STRUCTION PROGRAM M E AND M ETHODO LOGY:

    The construction methodology envisages composite super structure with steel pier in the

    viaduct portion. The main purpose of adopting this type of construction is to minimize the

    disruption in traffic flow during construction period and also to reduce the tenure of

    construction period. During construction, central portion of selected stretches of VIP road

    shall have to be barricaded. The steel column and & girders will be fabricated at workshop

    and transported to site by trailer. The size of single piece will guide the location of splicing.

    The girders will be launched on piers and the deck slab will be cast by taking temporary

    support from the girders. After completion of decking, crash barrier, expansion joint, railing

    and all the appurtenances will be fixed and wearing course will be laid. The embankment

    portion of the flyover will be constructed by R.E wall.

    The total duration of project construction period has been considered as 20 months.

  • 7/29/2019 Pwd Final Report

    14/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 14

    List of Equipments:

    Type of Equipment Output of Machine Remarks

    Air Compressor 1250 sqm/hr Surface cleaning

    Batching and mixing plant 15-20 cum/hr Concrete MixBatching and mixing

    plant(30cum)

    30 cum/hr Concrete Mix

    Concrete Mixer(0.4/0.28 cum) 2.5 cum/hr Concrete Mix

    Concrete Pump 25 cum/hr Concrete Mix

    Crane-35T 35 Tonne For lifting

    Crane-3T 3 Tonne For lifting

    Crane-80T 80 Tonne For lifting

    Dozer D-50-A 15 150 cum/hr Clearing

    Dozer D-80-A12 180 cum/hr Clearing

    Front-end Loader 25 cum/hr Aggregate Loading

    Generator 300 KVA 300 kva Hot Mix Plant

    Generator 100 KVA 100 kva WMM Plant

    Hot Mix Plant(60-90 TPH) 60-90 cum/hr Asphalt Mix

    Hydraulic Excavator 60 cum/hr Excavation

    Mastic Cooker 1 tonne/hr Mastic asphalt

    Mechanical Broom 1250 sqm/hr Surface cleaning

    Motor Grader(3.35 m blade) 50 cum/hr GSB Spreading

    Motor Grader(3.35 m blade) 200 cum/hr Soil Spreading

    Paver Finisher(with sensorcontrol)

    30 cum/hr Asphalt Mix Laying

    Piling rig with Bentonitepump

    2 to3 RM/hr Boring

    Pressure distributor(Bitumen) 1750 sqm/hr Tack coat/ Prime coat

    Pressure distributor(Emulsion) 1750 sqm/hr Tack coat/ Prime coat

    Road Marking Machine 100 sqm/hr Road Marking

    Roller(Ordinary) 70 cum/hr Earth/ Soil

    Roller(Pneumatic tyred) 25 cum/hr Asphalt works

    Roller(Tandem) 30 cum/hr Asphalt works

    Roller(Vibratory) 100 cum/hr Earth/ Soil

    Tipper/ Trucks 5.5 cum All kinds of material

    Transit Mixer 3 cum/hr Transportation of concrete

    mix

    Transit Mixer 4.5 cum/hr Transportation of concrete

    mix

    Wet Mix Plant(60 TPH) 60 Tonne/hr WMM

  • 7/29/2019 Pwd Final Report

    15/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 15

    Chapter 5: Cost Estimation and Rate Analysis

    5.1 GENERAL

    The methodologies adopted for estimating the cost of the proposed elevated corridor and its

    ancillary works which may be divided be divided in three board items of works as follows:

    Proposed elevated corridor Improvement of existing road and Proposed pedestal subway

    For each item of work the cost estimate has been arrived based on following steps:

    Analysis of unit rates of various items of work. Estimation of quantities for site clearance & utility relocation. Estimation of quantity for earthwork and road components e.g. pavement, cross

    drainage structures, bridges etc. and other ancillaries as per relevant IRC/IS and

    MoRTH specifications. Consideration of allowances for contingencies.

    5.2 ANALYSIS OF RATES:

    The rates of various item of works associated with the proposed project has been arrived

    based on public works (roads ),directorate ,schedule of rates ,2008 government of West

    Bengal with latest addendum and corrigendum issued on 1st

    July ,2010. Considering cost of

    materials, machinery and labour with additional percentages to concider Over head Chargesand Contractors profit. The said schedule of Rates follows the guidelines furnished in

    MoRT&Hs Standard Data Book (first revision 2003).

    Rates of item of works which are not covered in schedule of rates, 2008 of public works

    (roads) directorate, the rates have been taken from PWD, NH Schedule of Rates,2007-2008

    Govt. of West Bengal. Moreover the rates of structural steel & bolt including fabrication &

    erection have been analyzed considering the present market rate.

    The contractors profit has been considered on all items at uniform rate of 10%. The profit

    has been considered applicable on material, machinery, labour cost and overhead charges, asper the MoRTH Standard Data Book.

  • 7/29/2019 Pwd Final Report

    16/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 16

    5.3 COST ESTIMATE:

    The cost estimate of the project has been delivered based on the rates for various items of

    work taken from schedule of different departments.

    The estimated cost of the project amounts Rs. 208,03,88,745 (Rupees Two Hundred EightCrores Three Lakhs Eight Eighty Thousand Seven Hundred Forty Five only).

    The abstract of the estimated cost of the project is provided in the table below:

    SL NO. ITEM OF WORK AMOUNT(Rs.) REMARKS

    A. Proposed Elevated Corridor

    Foundation 18,18,98,118 Substructure 32,63,14,822 Superstructure 107,40,15,814 Approach ramp 2,15,93,387 Miscellaneous 34,49,971

    Subtotal ( Proposed Elevated

    Corridor)

    160,72,72,112

    B. Improvement of existing road

    1. Road works 144810723

    2. Side drain 80854994

    3. CD structure 15396854

    4. Miscellaneous works 20079056

    Sub total ( Improvement of existing

    road)

    261141627

    C. Proposed pedestrian subway

    Subway at Kestopur 17403694 Subway at Baguiati 18743098 Subway at Jora

    mandir

    17144904

    Sub Total( Proposed pedestriansubway)

    53291696

  • 7/29/2019 Pwd Final Report

    17/33

  • 7/29/2019 Pwd Final Report

    18/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 18

    Chapter 6:Subgrade Soil Investigation

    SUBGRADE SOIL INVESTIGATION

    In order to access the existing pavement composition including subgrade soil properties test

    pits of size 1.00m*1.00m were excavated at the pavement shoulder interface down to the

    subgrade level.

    The following tests are performed on the soil sample:

    A field dry density using sand replacement method was carried out at the subgrade levelas per IS:2720(Part 28).

    On the soil sample collected from the top 300mm of subgrade classification and thefollowing laboratory tests were performed:

    Field moisture content(as per IS:2720(Part 2)- 1973) Grain size analysis(as per IS:2720(Part 4)- 1985)Grain size analysis express quantitatively the proportions by mass of the various size of

    particles present in the soil.

  • 7/29/2019 Pwd Final Report

    19/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 19

    Atterberg Limits(as per IS:2720(Part 5)- 1985) Plastic limit: The plastic limit of fine-grained soil is the water content of the soil

    below which it ceases to be plastic. It begins to crumble when rolled into threads

    of 3mm dia.

    Liquid Limit: The liquid limit is the water content at which it will takes 25 blowsto close the groove over a distance of 13 mm.

    Plasticity Index: The plasticity index (PI) is a measure of the plasticity of a soil.The plasticity index is the size of the range of water contents where the soil

    exhibits plastic properties. The PI is the difference between the liquid limit and the

    plastic limit (PI = LL-PL). Soils with a high PI tend to be clay, those with a lower

    PI tend to be silt, and those with a PI of 0 (non-plastic) tend to have little or no silt

    or clay.

    Modified Proctor Test or Heavy Compaction Test

  • 7/29/2019 Pwd Final Report

    20/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 20

    Soil at known water content is placed in a specified rammer in to a mould of given

    dimensions, subjected to a compactive effort of controlled magnitude and the resulting unit

    weight determination. The procedure is repeated for varying Water Content and Dry Unit

    Weight.

    California Bearing Ratio Test4 days soaked(as per IS:2720(Part 16)- 1985)

    The Ratio of the force per unit area to penetrate a soil mass with circular plunger of 50 mm

    diameter @ 1.25 mm/min to that required for corresponding penetration of a standard

    material.

    CBR = [PT / PS] x 100

    PT = Corrected unit (or total) test load corresponding to the chosen penetration from the loadpenetration curve (fig. 2 of chapter IS: 2720 (Part 16)-1979 Method of test for soils: Part 16

    Laboratory Determination of CBR (first revision) in Compendium of Indian Standards on

    Soil Engineering Part 1)

  • 7/29/2019 Pwd Final Report

    21/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 21

    PS = unit (or total) standard load for the same depth of penetration as for PS taken from table

    below.

    CBR Apparatus

  • 7/29/2019 Pwd Final Report

    22/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 22

    Chapter 7:Geotechnical Investigation

    In order to obtain information on the physical properties of soil and rock around a site to

    design earthworks and foundations for proposed structures and for repair of distress to

    earthworks and structures caused by subsurface conditions.

    Description Of Field Work

    Some soil core samples were collected and these samples were taken to the laboratoryfor tests to obtain various properties of sub soil formation.

    Laboratory Testing

    The following laboratory tests were carried out on disturbed and undisturbed soil samples

    for identification and classification purposes and to obtain the strength and other properties of

    the formation.

    Grain Size Analysis Natural Moisture Content Atterbergs Limits Specific Gravity:

    This is the ratio of the mass of unit volume of soil at a stated temperature to the mass of the

    same volume of gas free distilled water at a stated temperature.

  • 7/29/2019 Pwd Final Report

    23/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 23

    Triaxial Test:A cylindrical specimen of soil encased in an impervious membrane is subjected to a constant

    confining pressure and then loaded axially @ 1.25 mm per minute to failure without change

    in total water content in the specimen.

    The test is limited to specimen in the form of the right cylinder of nominal diameter 38 mm

    and height equal to twice the nominal diameter. The ratio of diameter of the specimen to

    maximum size of particle in the soil should not be less than 5.

    Triaxial Apparatus

    One Dimensional Consolidation Test:A test in which the specimen is laterally confined in a ring and is compressed between porous

    plates in fully saturated condition. The gradual reduction in volume of soil mass on

    application of compressive stress is due to expulsion of water from the pores. The height of

    the ring shall not be less than 20mm. with diameter to height ratio of about 3. Further the

    specimen height shall be not less than 10 times the maximum particle size.

    Consolidation Apparatus

  • 7/29/2019 Pwd Final Report

    24/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 24

    Chapter 8: Substructure - Piling

    8.1 Pile

    In this project all the piles were 1000 mm in diameter, 20-25m in length, concrete and

    cast-in-situ. These were basically friction piles. For the construction of the pile it should not

    take more than 8 hours.

    The steps are

    Survey Casing punching/driving Boring/drilling Cage lowering Tremmie lowering Flushing Concreting

    First the surveyor will give the point for the drilling following the centreline of

    formwork. After that a temporary casing is driven but the erection has to be straight so

    from the centre two perpendicular lines of 2m is taken together with that spirit level is

    used for the straightening of the casing. Constant length of the diagonal is maintained

    during the driving of the casing.Boring is done with the help of Hydraulic Rotary piling rig. Temporary steel casing of

    required length will be driven. After reaching the founding level the bore will be

    thoroughly flushed with fresh bentonite solution. Reinforcement cages will be

    prefabricated in suitable length of about 10m. These will be lap welded at site and

    lowered in to the bore with the help of mobile crane. On placing the reinforcement

    cage, tremmie pipe elements will be assembled and lowered inside the cage. The bore

    will be then concreted by tremmie method with a minimum slump of 150mm.

    8. 2 Pile cap

    After the approval of the pile report, green flag is given to the construction of the pile

    cap. The concreting of the pile is done up to the ground level bit it is cut down to cut off level

    to get the sound concrete. The reinforcement from the pile is extended further and enters in to

    the cap. The reinforcement of the pile cap is made and then concreting. This kind of work is

    given to the subcontractor. But before the pile cap a floor of pain concrete (PCC) is done.

    Dewatering is also done to expel water from the pit before the concreting.

  • 7/29/2019 Pwd Final Report

    25/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 25

    Chapter 9: Pavement Analysis and Design

    GEOMETRIC DESIGN:

    The project corridor lies in plain terrain and passing through highly urbanized areas. As such,

    the geometric standards relevant to plain terrain as per IRC: 73-1980 and IRC: 86-1983 have

    been adopted.

    DESIGN SPEED:

    Design speed is the single most important factor that affects the geometric design. It directly

    affects the sight distance, horizontal curve, and the length of vertical curves. Since the speed

    of vehicles vary with driver, terrain etc, a design speed is adopted for all the geometric

    design.

    Design speed is defined as the highest continuous speed at which individual vehicles can

    travel with safety on the highway when weather conditions are conducive.

    HORIZONTAL ALLIGNMENT:

    Horizontal alignment is one of the most important features influencing the efficiency and

    safety of a highway. Horizontal alignment design involves the understanding on the design

    aspects such as design speed and the effect of horizontal curve on the vehicles. The horizontalcurve design elements include design of super elevation, extra widening at horizontal curves,

    design of transition curve, and set back distance.

    HORIZONTAL CURVES:

    The presence of horizontal curve imparts centrifugal force which is a reactive force acting

    outward on a vehicle negotiating it. Centrifugal force depends on speed and radius of the

    horizontal curve and is counteracted to a certain extent by transverse friction between the tyre

  • 7/29/2019 Pwd Final Report

    26/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 26

    and pavement surface. On a curved road, this force tends to cause the vehicle to overrun or to

    slide outward from the centre of road curvature. For proper design of the curve, an

    understanding of the forces acting on a vehicle taking a horizontal curve is necessary.

    Various forces acting on the vehicle are illustrated in the figure 1.

    Figure 1: Effect of horizontal curve

    They are the centrifugal force (P) acting outward, weight of the vehicle (W) acting downward,

    and the reaction of the ground on the wheels (Ra and Rb)The centrifugal force and the weight is

    assumed to be from the centre of gravity which is at h units above the ground. Let the wheel base

    be assumed as b units. The centrifugal force in kg/m2 is given by

    where is the weight of the vehicle in kg, is the speed of the vehicle in m/sec , g is the

    acceleration due to gravity in m/sec2

    and is the radius of the curve in

    VERTICAL ALLIGNMENT:

    The vertical alignment of a road consists of gradients (straight lines in a vertical plane) and

    vertical curves. The vertical alignment is usually drawn as a profile, which is a graph with

    elevation as vertical axis and the horizontal distance along the centre line of the road as the

    the horizontal axis.

    GRADIENT:

    Gradient is the rate of rise or fall along the length of the road with respect to the horizontal.

    While aligning a highway, the gradient is decided for designing the vertical curve.

  • 7/29/2019 Pwd Final Report

    27/33

  • 7/29/2019 Pwd Final Report

    28/33

  • 7/29/2019 Pwd Final Report

    29/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 29

    DESIGN TRAFFIC

    The method considers traffic in terms of the cumulative number of standard axles (8160 kg)

    to be carried by the pavement during the design life. This requires the following information:

    1. Initial traffic in terms of CVPD

    2. Traffic growth rate during the design life

    3. Design life in number of years

    4. Vehicle damage factor (VDF)

    5. Distribution of commercial traffic over the carriage way.

    PAVEMENT THICKNESS DESIGN CHARTS

    For the design of pavements to carry traffic in the range of 1 to 10 msa, use chart 1 and for

    traffic in the range 10 to 150 msa, use chart 2 of IRC:37 2001. The design curves relate

    pavement thickness to the cumulative number of standard axles to be carried over the design

    life for different sub-grade CBR values ranging from 2 % to 10 %. The design charts will

    give the total thickness of the pavement for the above inputs. The total thickness consists of

    granular sub-base, granular base and bituminous surfacing. The individual layers are

    designed based on the the recommendations given below and the subsequent tables.

    PAVEMENT COMPOSITION

    Sub-base

    Sub-base materials comprise natural sand, gravel, laterite, brick metal, crushed stone or

    combinations thereof meeting the prescribed grading and physical requirements. The sub-base material should have a minimum CBR of 20 % and 30 % for traffic upto 2 msa and

    traffic exceeding 2 msa respectively. Sub-base usually consist of granular or WBM and the

    thickness should not be less than 150 mm for design traffic less than 10 msa and 200 mm for

    design traffic of 1:0 msa and above.

    Base

    The recommended designs are for unbounded granular bases which comprise conventional

    water bound macadam (WBM) or wet mix macadam (WMM) or equivalent confirming to

  • 7/29/2019 Pwd Final Report

    30/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 30

    MOST specifications. The materials should be of good quality with minimum thickness of

    225 mm for traffic up to 2 msa an 150 mm for traffic exceeding 2 msa.

    Bituminous surfacing

    The surfacing consists of a wearing course or a binder course plus wearing course. The most

    commonly used wearing courses are surface dressing, open graded premix carpet, mix seal

    surfacing, semi-dense bituminous concrete and bituminous concrete. For binder course,

    MOST specifies, it is desirable to use bituminous macadam (BM) for traffic upto o 5 msa and

    dense bituminous macadam (DBM) for traffic more than 5 msa.

  • 7/29/2019 Pwd Final Report

    31/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 31

    Chapter 10: Institutional Framework

    FRAMEWORK FOR IMPLEMENTATIONThe project is to be implemented with the intention of decongesting and improving

    urban mobility of the Kolkata city. The project would be developed on a public

    funded format with partial resources from the state government budget. Construction

    should take a period of 18 months.

    AUTHORITY FOR APPROVALS/ CLEARANCESThe project would require approvals from the following departments as part of theproject implementation

    a) Public Works departmentb) Utilities agencies such as Electricity Boards/ Telephone exchangec) State Pollution control Boardd) Any other approvals, as may be required during implementation

    Project Risk Assessment Funding Risk

    Construction Risks Cost Overrun Risk Approvals Risk Operation & Maintenance Risks

    Present levels of service and proposed improvement1) Present scenario

    Kazi Nazrul Islam Avenue (KNIA) or the VIP acts as the main arterial road to

    access Kolkata city from Netaji Subhas Chandra Bose International Airport and

    National Highways No. 34,35,2 and 6. The existing traffic scenario seriously

    impedes smooth urban mobility due to following reasons:-

    No separate provision exists for the segregation of through traffic and localtraffic generated from the various cross roads that exist along the project

    road.

    No separate service road exists for segregation of local slow moving trafficfrom fast moving traffic.

    Non existence of adequate pedestrian facilities for smooth passage in themain crossing especially at Kestopur, Baguihati and Jora Mandir.

    Unauthorized and haphazard road side parking and scattered movement ofthe pedestrian.

  • 7/29/2019 Pwd Final Report

    32/33

    Summer Vocational Training 2012

    4 Lane Elevated Corridor From Keshtopur To Jora Mandir On Kazi Nazrul

    Islam Avenue [VIP Road] Page 32

    2) Proposed DevelopmentsTo address the problem of congestion, provide adequate facilities for pedestrian

    and facilitate uninterrupted mobility the following measures have been proposed.

    (A) Standardize the road cross section of the proposed corridor foraugmentation of the road capacity to cater future vehicular and pedestriantraffic.

    Enhance capacity of the corridor by providing standard 6 lanedivided carriageway.

    Segregating the local traffic from through traffic and alsomotorized from non-motorized traffic.

    Pedestrian facilities need to be planned to minimize thepedestrian conflicts with vehicular traffic.

    Parking area needs to be identified especially near the schooland college areas and necessary parking lane has to be

    provided.

    (B) Proposing Vertical segregation of the through traffic and cross traffic inthe congested stretch and busy intersection to eliminate the conflict among

    them.

    By providing 4-lane elevated flyover from Kestopur to Jora Mandir via

    Baguihati crossing are proposed for through traffic along proposed

    corridor. Flyover length will be 1658.5m

    (C) Provision for separate Pedestrian subwayProvision for pedestrian subways has been planned at Kestopur, Jora

    Mandir and Baguihati with an aim to facilitate smooth and safe pedestrian

    crossing and eliminate pedestrian vehicle conflict.

    Salient features of pedestrian subways:

    a) Location : At Kestopur- Ch. 3.346 KmAt Baguiati- Ch. 4+212 Km

    At Jora Mandir Ch. 4+607 Km

    b) Vertical clear height : 2.75 mc)

    Width of subway : 6.50 m

    (D) Road Side Drainage :Longitudinal PCC drain have been provided on the both side of the road

    and connected with the existing CD structure for the smooth passage of

    storm water.

    Major improvements envisaged are as follows:

    Reduced travel time (proposed design speed of 70 km/hr) Smooth well maintained pot hole free riding surface Efficient traffic management system including signals, sign boards

    and road delineators

    Proposed illuminated carriageway

  • 7/29/2019 Pwd Final Report

    33/33

    Summer Vocational Training 2012

    Uninterrupted movement for pedestrians Overall safety Improved mobility