ISO 9906:2012 Rotodynamic pumps -- Hydraulic performance acceptance tests -- Grades 1, 2 and 3 Pump Testing Requirement

Pump Testing Requirement

Embed Size (px)

DESCRIPTION

Pump Testing Requirement

Citation preview

ISO 9906:2012Rotodynamic pumps -- Hydraulic

performance acceptance tests -- Grades 1, 2 and 3

Pump Testing Requirement

• ISO 9906:2012 specifies hydraulic performance tests for customers' acceptance of rotodynamic pumps (centrifugal, mixed flow and axial pumps). It is intended to be used for pump acceptance testing at pump test facilities, such as manufacturers' pump test facilities or laboratories. ISO 9906:2012 can be applied to pumps of any size and to any pumped liquids which behave as clean, cold water.

• It specifies three levels of acceptance:

• grades 1B, 1E and 1U with tighter tolerance;

• grades 2B and 2U with broader tolerance;

• grade 3B with even broader tolerance.

• It applies either to a pump itself without any fittings or to a combination of a pump associated with all or part of its upstream and/or downstream fittings.

Pump Testing Requirement

Main Objective

Confirm pump performance parameters:

• Capacity

• Head

• Power

• Efficiency

• NPSH

Pump Testing Requirement

Others

Confirm pump performance parameters:

• Temperature rise

• Noise

• Dimension

• Material

• Protection coating

Pump Testing Requirement

Pump Testing Requirement

Consideration

Confirm pump performance parameters:

• Water Temperature

• Speed

• Power

• Efficiency

• NPSH

Pump Testing Requirement

Arrangement

Pump Testing Requirement

Item

No.

Particulars Unit 1 2 3

1. Quantity of water delivered against

Total Head by each pump

m3/hr

2. Total Dynamic Head m

3. Water Power (base on item 1 & 2) kW

4. Maximum Power input for Motor kW

5. Overall Efficiency of Pump and Motor %

6. Pump Speed rpm

7. NPSH m

Pump Testing Requirement

Computation

Flow meter 1

Item

No.

Particulars Unit 1 2 3

1. Quantity of water delivered against

Total Head by each pump

m3/hr

2. Total Dynamic Head m

3. Water Power (base on item 1 & 2) kW

4. Maximum Power input for Motor kW

5. Overall Efficiency of Pump and Motor %

6. Pump Speed rpm

7. NPSH m

Pump Testing Requirement

1

Pump Testing Requirement

Computation

Pressure

gauge P2

2

Pressure

gauge P1

= P2 – P1 + (V22 – V12/2g)

Item

No.

Particulars Unit 1 2 3

1. Quantity of water delivered against

Total Head by each pump

m3/hr

2. Total Dynamic Head m

3. Water Power (base on item 1 & 2) kW

4. Maximum Power input for Motor kW

5. Overall Efficiency of Pump and Motor %

6. Pump Speed rpm

7. NPSH m

Pump Testing Requirement

1

2

Pump Testing Requirement

Computation

kW, (after power

factor)

3

Speed

Water Power = x x 9.811 2

4

5

Item

No.

Particulars Unit 1 2 3

1. Quantity of water delivered against

Total Head by each pump

m3/hr

2. Total Dynamic Head m

3. Water Power (base on item 1 & 2) kW

4. Maximum Power input for Motor kW

5. Overall Efficiency of Pump and Motor %

6. Pump Speed rpm

7. NPSH m

Pump Testing Requirement

1

2

4

3

5

4

3

X 100