Upload
michael-chaffey
View
122
Download
3
Tags:
Embed Size (px)
Citation preview
Pump Reliability Study:
Irving Paper
By: Michael Chaffey
Work Term 2
435 Bayside Dr.Saint John, NB
E2J 1B2December 19th, 2014
Gordon JinCo-operative EducationFaculty of Engineering and Applied ScienceMemorial University of NewfoundlandSt. John’s, NL A1B 3X5
Mr. Jin:
Throughout my work term, I was employed in the Reliability Department at Irving Paper, and was supervised by Mr. Reinier Hugenholtz, P. Eng. The department is responsible for all machine reliability in the mill on a day-to-day basis.
Irving Paper is continuously looking for ways to elevate their paper making process. An important way of accomplishing this goal is by improving the reliability of their equipment. One of the many components that make the mill operable are their pumps; keeping these pumps in service is fundamental in preventing downtime and reducing costs to the mill. The purpose of this report, entitled "Pump Reliability Study: Irving Paper," is to document and outline the steps that went into analyzing the reliability of the pumps at Irving Paper. This report is my second of four work reports required by the Division of Co-operative Education at the Memorial University of Newfoundland. This report was written entirely by me and has not received any previous academic credit at this or any other academic institution.
Please contact me with any questions you may have regarding this report.
Sincerely,
Michael Chaffey201102142
Pump Reliability Study: Irving Paper
Irving Paper Inc.Supervisor: Reinier Hugenholtz, P. Eng.
December 19th, 2014
Michael Chaffey201102142
Term 4 Mechanical EngineeringMemorial University of Newfoundland
EXECUTIVE SUMMARY
Previous to this project, Irving Paper’s reliability and maintenance personnel were
unclear on many aspects surrounding the pumps at their site. It was believed that a lot of
money was being spent on the maintenance of these pumps and that the mean time
between failures was not as long as it should have been. This report provides an analysis
and evaluation of the current state of pump reliability at Irving Paper along with the
associated maintenance costs.
Five pump tracking lists were created from data extracted from the mill’s computerized
maintenance management system. These lists were used to monitor the location and
details of the pumps across the mill. It was found that the mill has roughly 651 pumps
across the site. These pumps are located as follows:
Paper Machine #1 (170 Pumps) Paper Machine #2 (153 Pumps) Thermal Mechanical Pulping (223 Pumps) Other (105 Pumps)
An analysis of the pump spending in the mill concluded that, excluding labour, the mill
spends approximately $711,000 each year on pump rebuilds. The study also shows that
20% of the pumps account for roughly 90% of the pump rebuild costs over the last
5-¾ years. This indicates that the mill has some pumps that fail frequently. If these
pumps are dealt with, pump reliability could improve significantly, saving the mill money
on pump maintenance and by reducing downtime.
It is recommended that the mill allocates the time and resources to improve on some of
their existing processes:
Work Order Detail Enterprise One Swim Lanes Track Rebuilds
Root Cause Failure Analysis Track Rework Develop Improvement Process
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 i
TABLE OF CONTENTS
Page
Executive Summary..............................................................................................................i
Table of Contents................................................................................................................ii
List of Figures....................................................................................................................iii
List of Tables......................................................................................................................iii
1.0 INTRODUCTION.......................................................................................................1
1.1 Background...........................................................................................................1
1.2 Scope of Project....................................................................................................2
2.0 DATA MINING..........................................................................................................3
2.1 Pump Tracking......................................................................................................3
2.2 Work Order Cost Reports.....................................................................................4
3.0 GRAPHING................................................................................................................5
3.1 Pareto Costs By Area............................................................................................5
3.2 Annual Pump Repair Costs...................................................................................5
3.3 Top Ten Spreadsheets...........................................................................................7
3.4 Failure Timeline Graphs.......................................................................................9
4.0 ANALYSIS................................................................................................................10
4.1 Spreadsheets & Graphs.......................................................................................10
4.2 MC 5 Sunds Defibrator Pump.............................................................................11
5.0 CONCLUSION.........................................................................................................16
6.0 RECOMMENDATIONS..........................................................................................17
6.1 MC 5 Pump.........................................................................................................17
6.2 Changes to Procedures........................................................................................18
References..............................................................................................................................
Appendix A: ..........................................................................Pareto Charts by Mill Section
Appendix B: .....................................................................................Top Ten Pump Details
Appendix C: ..........................................................................................Mill Entity Number
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 ii
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 iii
LIST OF FIGURES
Figure 1. Maintenance Costs by YearFigure 2. Top Ten Pumps Mill WideFigure 3. Sample Failure Timeline GraphFigure 4. MC 5 Pump Failure Timeline GraphFigure 5. MC 5 Pump Seal Cross-SectionFigure 6. Seal Face CrackFigure 7. Seal Face GougeFigure 8. Existing Stuffing Box
LIST OF TABLES
Table 1. Annual Pump CostsTable 2. Top Ten Pumps Mill Wide
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 iii
1.0 INTRODUCTION
1.1 Background
Irving Paper Incorporated (IPI) is located on the East Side of Saint John in Southern New
Brunswick. The mill employs roughly 310 staff and hourly employees full time in
addition to numerous contractors employed on a daily basis. With two paper machines
and the recent upgrades of $226 million to Paper Machine #1 in 2006 (Mackenzie, 2014),
IPI remains a leading manufacturer of supercalendered SCB, SCA and SCA+ grade paper
in the world (JD Irving).
IPI produces roughly 420,000 tonnes of paper per year. This paper is used to print
magazines and flyers for many of the leading companies in the business: Time
Magazine, Entertainment Weekly, Sports Illustrated, People and Money Magazine.
Irving Paper uses many systems to maintain their paper making process. These systems
include but are not limited to: pumps, motors, tanks, agitators, rolls, hydraulics,
lubrication, electrical and various chemical processes. Each of these components play an
essential part in keeping production running and ensuring that the end product is of high
enough quality for their customers.
The mill is split up into different departments commonly referred to as ‘mill area’. These
areas consist of the Paper Machine #1 department (PM1), Paper Machine #2 department
(PM2), the pulping department; Thermo Mechanical Pulping (TMP), and the Thermal
Plant (TP) where the mill’s steam is made with the use of natural gas boilers.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 1
1.2 Scope of Project
The goal of this study was to determine ways in which IPI could reduce maintenance
costs and improve the overall reliability of their pump systems. First, information was
collected regarding both the number and location of all pumps in the mill. A review on
current pump-related spending was then conducted. By examining spending trends, the
most costly pumps were able to be identified and targeted for further investigation. This
information was used to make recommendations for improving the reliability of the mill’s
pumps. Summaries for each aspect of the project are seen below.
How many pumps does IPI have and where are they located:
Irving Paper staff had an idea of how many pumps they had in each area of the
mill but this number was only a vague estimation. It is a part of the scope of this
project to identify all pumps in the mill along with their locations.
How much is IPI spending on pump overhauls each year?
There was also uncertainty among the staff at IPI regarding the amount spent on
pump rebuilds. It was a common opinion from staff that an unnecessary amount
was being spent on these rebuilds. However, there were no reports made on
maintenance spending that were broken down into equipment classes or by mill
area. This project will gather such information on pump-related spending.
What are the predominant failure causes of the pumps?
At IPI, there are many different pump failures each year. Every time a pump
fails, it is sent out for a rebuild and there is rarely investigation into the cause of
the failure. A major part of this project was to examine these failures to
determine where improvements could be made. There is a small amount of data
on the CMMS (computerized maintenance management system) from which a
trend for common pump failures was created.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 2
2.0 DATA MINING
2.1 Pump Tracking
Lists of pumps were generated using JD Edwards OneWorld, the mill’s CMMS. The
equipment codes used in the pump entities are: 211; hydraulic and lubrication pumps,
255; vacuum pumps and 246; all other pumps. See Appendix C for a breakdown of the
entity number format used at IPI. Searches for codes were made and exported to excel
spreadsheets. The 651 pumps were divided into five sections, each having their own
tracking list:
Paper Machine #1 (170 Pumps) Paper machine #2 (153 Pumps) TMP (223 Pumps) Chemical Prep & Environmental (61 Pumps) Treatment Plant and Other (45 Pumps)
After the five initial lists of all pumps in the mill were created, the list for Paper Machine
#2 was expanded to include additional columns of pump detail:
Entity Number Entity Description Manufacturer Model
Type Size Speed Serial Number
Seal Type
This data was discovered through field surveying, searches through the company’s online
equipment files, through the hard copy equipment files and through the CMMS work
orders. Although this information was only found for the PM2 section (very time
consuming), it is recommended that this data is gathered for the other areas of the mill.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 3
2.2 Work Order Cost Reports
A meeting was held with David Angevine, Irving Paper’s site accountant, to obtain cost
records on pump rotating assembly overhauls. Work order cost reports were used to
gather this information, which show all spending and corresponding work orders based
on inputs of time period and mill department. These cost reports were generated for the
time period of Jan. 1st, 2009 to Sept. 27th, 2014. Cost reports were generated for each of
the following departments:
Paper Machine #1 (Department Code: 2021)
Paper Machine #2 (Department Code: 2022)
TMP 1 & 2 (Department Code: 2013)
TMP 3 (Department Code: 2016)
Environmental (Department Code: 2010)
Thermal Plant (Department Code: 2031)
Since these reports include all costs over the time period for all equipment in the
department, filtering was required to obtain only the data relevant to pump rebuilds. Any
work orders referring to the rotating assembly or a pump overhaul were kept and all other
work orders were removed from the list. This left only the necessary information related
to pump failures. Next, the “Labour,” “Hours” and “O/T Hours” columns were deleted,
leaving only the “Stores,” “Non-Stores” and “Service” columns. The remaining items
were sorted by pump entity and from here sub-totals were calculated. The sub-total
values for each pump were then sorted in descending order to give a list of the most
costly pumps in each section of the mill.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 4
3.0 GRAPHING
3.1 Pareto Costs By Area
Pareto charts were created for each of the three main sections of the mill: PM1, PM2 and
TMP. Once these Pareto charts were created, it was evident that the majority of the
failures were in a small number of the mill’s pumps (see Appendix A for lists sorted by
repair totals and the corresponding Pareto charts). As a result, a deeper investigation
into the failures of the ten most costly pumps in each section was done.
3.2 Annual Pump Repair Costs
In addition, work order cost reports were used to calculate annual total pump repair costs
in each section of the mill (Table 1). This information was collected for the years 2009-
2014. This data can be used to determine what sections of the mill are incurring the
highest costs; these areas can then be targeted for improvements to reduce spending.
Mill Area# Of
Pumps
Annual Pump Repair Costs2009 2010 2011 2012 2013
2014 (YTD)
PM1 170 $105,714 $208,974 $165,153 $236,355 $118,837 $135,824
PM2 153 $341,218 $179,009 $205,992 $222,286 $319,237 $185,954
TMP 223 $139,160 $229,429 $241,575 $217,375 $181,218 $223,294
Chem. &Envir.
61 $41,485 $91,606 $56,914 $43,826 $49,101 $54,596
TP & Other
44 $18,570 $32,238 $32,740 $52,978 $21,989 $41,159
Total: 641$646,14
7$741,25
7$702,37
4$772,82
0$690,38
2$640,82
7
Table 1. Annual Pump Costs
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 5
Using the data in Table 1, a graph displaying the total pump maintenance costs of the mill
by year was created; this graph can be seen in Figure 1. From 2009 to 2013, Irving Paper
spent an average of roughly $711,000 on pump maintenance each year.
Figure 1. Maintenance Costs by Year
By updating the bar graph in Figure 1 on a regular basis, mill staff will be able to monitor
their annual pump maintenance costs. Once modifications to the system are made, this is
where they will see the big picture and the cost outcomes of their improvements over
time. A potential budget could be set up and a category for a maintenance scorecard
could be created from this.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 6
3.3 Top Ten Spreadsheets
The ten most costly pumps in each section, as determined from the Work Order Cost
Reports, were looked up using the CMMS and any relevant data was taken from the work
orders and populated into spreadsheets entitled “Top Ten-Details” for each of the three
largest sections in the mill; PM1, PM2 and TMP. For the majority, the work order
descriptions were vague or non-existent; making reliability improvement much more
difficult than it should have been. These spreadsheets gave the reliability team failure
details on thirty of the mill’s “bad actor” pumps. From the thirty worst pumps, another
list was created that displayed the ten most costly pumps mill wide; this list can be seen
in Table 2 below (see Appendix B for details on these pumps).
Kobe Pumps
Vacuum PumpsHydraulic
Top Ten Pumps Mill Wide (1/1/09 to 9/27/14)
Order Entity #Entity
DescriptionManufacture
r# of
WOsRebuild Cost
1 PM224691 PM2 Kobe Pump #1 Kobe: Rotojet 9 $170,809
2 PM225504Vacuum Pump - Pickup Uhlebox
Nash 6 $139,723
3 PM224664 PM2 Kobe Pump #3 Kobe: Rotojet 9 $124,921
4 PM125521Couch High
Vacuum PumpNash 3 $102,781
5 PM1246139Trim Slitter Unit #2
PumpJet-X 8 $98,418
6 PM224627PM2 Vacuum Sump
Pump #2Byron Jackson 7 $89,446
7 GW624614HRU Recirculation
PumpAhlstrom 13 $86,401
8 GW624691MC Pump 5 -
Bleached TMP Tower
Sunds Defibrator
9 $82,703
9 PM1246138Trim Slitter Unit #1
PumpJet-X 13 $79,518
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 7
10 PM224663 PM2 Kobe Pump #2 Kobe: Rotojet 5 $79,303
Table 2. Top Ten Pumps Mill Wide
In Figure 2, the maintenance costs of the top ten pumps in the mill are shown as a Pareto
chart. The red series in front represents the costs incurred from 2013 up to September
27th of 2014 only. This indicates whether a pump has needed to be replaced or had
significant repairs completed recently and whether it continues to be a nuisance to the
mill.
Figure 2. Top Ten Pumps Mill Wide
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 8
Kobe Pumps Vacuum Pumps Hydraulic
By examining trends in spending over time, it can be determined whether repairs have
been successful in eliminating issues with a pump system. Being able to support your
efforts with statistical data can come in handy in any field of work.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 9
3.4 Failure Timeline Graphs
It was discussed that another point of interest for these failures is when they happened.
For instance, if changes were completed on a pump in 2013 and the failures continued
steadily after this point, it would be assumed that the issues with this particular pump
were not resolved. Had the number of failures decreased after this time, the reliability
team would likely shift their focus elsewhere, concluding that the reliability of this pump
had been improved.
The failure costs taken from the CMMS were plotted against a constant x-axis that
represents the total time period studied. Each failure cost appears above the timeline at
the time of failure. Thirty of these graphs were created: one for each of the ten worst
pumps in the PM1, PM2 and TMP areas (see the Top Ten Mill Wide Pumps in Appendix
B and an example of one of these graphs in Figure 3 below).
Figure 3. Sample Failure Timeline Graph
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 10
4.0 ANALYSIS
4.1 Spreadsheets and Graphs
It is seen from the “Maintenance Costs By Year Graph” in Figure 1 that, over the 5 full
years studied, approximately $711,000 was spent on pump rebuilds in the mill annually.
From the Pareto charts (Appendix A), it can be seen that a large number of these costs
occurred in a small number of pumps.
There are about 653 pumps in service in the mill. The total number of pumps and the
total amount spent on these pumps is enough information to calculate how close pump
reliability at the mill is to the ‘80/20 Rule’ (or the Pareto Principle). The 80/20 Rule is an
accepted standard for reliability in many different applications. This principle states that
approximately 80% of the costs will be spent on maintaining 20% of the equipment (in
this case, pumps) (Reh, 2014).
Out of the 651 pumps at Irving Paper, 20% is equivalent to about 130 pumps. When the
costs of the top 130 pumps are summed together, the total spending is roughly $645,000
each year. Thus, at Irving Paper:
90% of the costs have been spent on 20% of the mill’s pumps.
Irving Paper’s pump reliability comes up below the 80/20 Rule by about 10%. By
making adjustments to the pumps at the top of the list and getting closer to the 80/20
divide, the mill should be able to cut its annual pump maintenance costs considerably.
Based on this information, the reliability team decided to start their individual pump
analysis with the most costly pumps.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 11
4.2 MC 5 Sunds Defibrator Pump
Members of Irving Paper’s reliability team met with Dave Howe at Universal Sales
Limited (USL) in Saint John, NB to observe an air motor rebuild. While at USL, Mr.
Howe pointed out that IPI’s MC 5 Pump was there for a rebuild and that it was one that is
sent to them on a regular basis. The MC 5 Pump showed up at #8 on the list of highest
cost to maintain in the mill over the time period of this study. After looking at the work
order history and Failure Timeline Graph (see Figure 4 below) of this pump, it was seen
that lately it has had a seal failure roughly every six months.
Figure 4. MC 5 Pump Failure Timeline Graph
Each time the seal fails, the pump is taken out of service and sent to USL to have the
rotating assembly rebuilt or replaced, costing around $11,000 for parts and services each
failure. “A mechanical seal contains two rings with a high quality surface finish, one of
which is stationary whilst the other rotates with the pump shaft. Spring force and liquid
pressure hold the faces of the rings in contact with each other” (Sunds Defibrator, 1994).
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 12
The MC 5 Pump is a critical pump in the stock preparation process of the paper mill.
This pump is responsible for pumping all bleached stock from the bleached stock tower
to Paper Machine #1. If this pump fails, it will cease stock flow to the paper machine and
stop production until the failure has been resolved. There is no in-line spare and a pump
change would take hours to complete and cost the mill thousands of dollars in downtime.
By improving the reliability of this pump, rebuild costs due to seal failures could be
reduced, leading to significant financial savings.
It was pointed out by Dave Howe at USL that Irving Pulp & Paper (IPP- a sister mill to
Irving Paper) had a slightly larger Sunds Defibrator pump that had caused them similar
seal issues in the past. IPP’s pump is a 2025 model compared to Irving Paper’s 2015
model. The reliability group at IPI came up with a plan to modify the seal housing to
achieve a simpler design. This alteration involved shortening the stuffing box to allow
room for the installation of a new Chesterton 442 Split Mechanical Seal. “Eliminating
process leakage stops the problems created by it – premature bearing and equipment
failure, and the need to disassemble these large pumps to install new bearings and other
damaged components” (Chesterton, 2001).
Staff at Irving Paper first looked into the operating conditions of the pump and noticed
that there were discrepancies with the seal water setup and that the operation of the
associated vacuum pump seemed to need more monitoring. Figure 5 shows a cross-
section of the mechanical seal of the MC 5 pump.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 13
Figure 5. MC 5 Pump Seal Cross-Section
There were two seal water lines entering the stuffing box of the pump, each controlled by
a flowmeter. The flowmeter for the quench line was recommended by personnel to be set
at 2 litres/min but was set at 8 litres/min. The flowmeter for the flushing line was
recommended by personnel to be set at 8 litres/min and was set at 8 litres/min.
However, when the pump manual was consulted, it recommended the lines be set at 2-3
litres/min and 1-2 litres/min respectively. Discrepancies between recommended set points
and actual set points may be a contributing factor to seal failures, an issue warranting
further investigation.
When examining the drain line exiting the stuffing box running into the floor trench, it
was seen that there was hardly any water coming out. This indicates one of three
possibilities: the seal water lines were clogged and very little water was getting to the
seal, the water was leaking by the seal and mixing with the stock in the pump, or it was
entering the stuffing box and getting sucked out by the degassing pump.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 14
The seal water set up is crucial to cooling the stationary and rotating components of the
seal. If there is no seal water flow and these components are not kept cool, the seal will
fail and fill up with stock. See figures 6 and 7 for pictures of the seal face that has failed:
Figure 6. Seal Face Crack Figure 7. Seal Face Gouge
Notice the crack in the Figure 6; this crack shows that the seal likely experienced thermal
shock or was ran dry of its seal water. The gouge out of the face of the seal in Figure 7
shows that stock likely worked its way between the seal faces and caused a chunk of the
seal face to break off. After this failure took place, there would be no hope in stopping
the stock from passing through the seal and causing more problems.
IPI’s reliability team contacted staff at Irving Pulp & Paper to get some insight on the
changes they made. A meeting was set up on-site at USL to go over the modifications
with personnel from USL and IPP. The two pumps were set up side by side for the group
to examine; they were able to see that the two pumps were identical other than the seal
modifications and their size.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 15
The essence of the changes undergone was the shortening of the stuffing box and the
replacing of the existing mechanical seal with a 442 Split Seal. The benefit from this
transformation is that split mechanical seals are able to be removed and changed with the
pump in place; there is no need to go through the lengthy, costly and labour intensive
process of removing and disassembling the pump just to change a failed seal.
Figure 8. Existing Stuffing Box
In order to complete this change, the seal housing will have to be cut back to about half
its current size and the port for the degassing pump moved as far to the pump side of the
stuffing box as piping will permit. The slinger on the motor side of the stuffing box
could be replaced with a more modern and smaller V Ring to serve the same purpose;
both would protect the bearings from leaking seal water. Collaboration with A.W.
Chesterton and USL should be had to further discuss the details of this modification if so
desired.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 16
5.0 CONCLUSION
The goal of this study was to determine ways in which IPI could reduce maintenance
costs and improve the overall reliability of their pump systems. This was done by
identifying and locating all pumps in the mill and examining current pump-related
spending. It was found that there are roughly 650 pumps throughout the mill at Irving
Paper. Excluding labour, about $711,000 is spent each year on the overhaul of these
pumps alone and 90% of these costs were spent on 20% of the pumps.
For the time period studied (Jan. 1st, 2009 to Sept. 27th, 2014), the most costly pumps
were successfully identified and targeted for further investigation:
PM2 Kobe Pump #1 $170,809
Vacuum Pump- Pickup Uhlebox $139,723
PM2 Kobe Pump #3 $124,921
Couch High Vacuum Pump $102,781
Trim Slitter Unit #2 Pump $98,418
PM2 Vacuum Sump Pump #2 $89,446
HRU Recirculation Pump $86,401
MC Pump 5- Bleached TMP Tower $82,703
Trim Slitter Unit #1 Pump $79,518
PM2 Kobe Pump #2 $79,303
The main failure causes were seen to be seals and then bearings, respectively; this is an
extrapolation of the inconsistent work order data after having gone through the comments
and failure codes on many of the rebuild work orders.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 17
6.0 RECOMMENDATIONS
6.1 MC 5 Pump
Based on the analyses presented in this report, it is recommended that Irving Paper
further investigates the seal water supply and the associated vacuum system on the MC 5
Pump. The current operating conditions suggest that there is insufficient seal water
entering the stuffing box to cool the mechanical seal. It is assumed that this is likely from
partially clogged seal lines - the quality of the entire mill seal water system should be
checked.
By shortening the stuffing box and replacing the existing mechanical seal with a 442 Split
Seal or equivalent, seal failures will likely be reduced. Simplifying the sealing
arrangement of the MC 5 pump will be extremely beneficial to preventing failures of this
pump system. In addition to reducing pump failures, these changes will reduce the
difficulty and complication of future seal replacements; split mechanical seals are able to
be removed and changed with the pump in place. In other words, there is no need to go
through the lengthy, costly and labour intensive process of removing and sending the
pump to a rebuild shop for each failure. In order to complete these changes, the seal
housing would need to have major modifications completed and cooperation with A.W.
Chesterton and Universal Sales Limited would be ideal, since they have done this same
project at Irving Pulp & Paper within the last few years.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 18
6.2 Changes to Procedures
It is recommended that Irving Paper follows the Shewhart Plan→Do→Check→Act
cycle for continuous improvement (Tague, 2004). IPI should consider working on or
implementing the following points and processes:
Work Order Detail - The detail on the majority of work orders is very minimal and
an improvement would allow data collection to be done easier and with more
accuracy.
Track Rebuilds - USL receives little or no information when a pump is sent to
them; this definitely costs the mill when they are unsure of the failure cause and
complete an unnecessary full rebuild. Records from USL should be added to the
work order detail after they have been received.
Enterprise One Swim lanes - Already established E1 swim lanes should be
followed to ensure the appropriate individuals are aware when and why a pump is
sent out for a rebuild.
Root Cause Failure Analysis - Allocate resources to perform RCFA techniques
and resolve the cause of the failure rather than change out the same piece of
equipment multiple times per year without an investigation.
Track Rework - Monitor pumps that have had improvements done to them to see if
the problem has been resolved or if it is still ongoing.
Expand To Other Areas of Budget - An analysis like the one outlined in this report
could be expanded to other areas of the maintenance budget to better track costs.
By following the above recommendations, it is expected that pump reliability at Irving
Paper will substantially improve. Increasing reliability of the pump systems at IPI will
result in vast savings by reducing maintenance costs and downtime.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014 19
References
Medium Consistency Pump CMD Maintenance Instructions, Sunds Defibrator AB, Sundsvall, Sweden, 1994, pp. 25-28.
JD Irving. World first technology, brilliant results [Online]. Available: https://www.jdirving.com/jd-irving-products-services-forestry-products-irving-paper.aspx
G. Mackenzie, private communication, Nov. 2014.
F. J. Reh. (2014). Pareto’s Principle- The 80-20 Rule [Online]. Available: http://management.about.com/cs/generalmanagement/a/Pareto081202.htm
442 Split Mechanical Seal, Chesterton, Stoneham, MA, 2001.
N. R. Tague. The Quality Toolbox (2nd ed.), ASQ Quality Press, 2004, pages 390-392.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
APPENDIX A
PARETO CHARTS BY MILL SECTION
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
PM1 Pump Entities in Order of WO Cost(1/1/09 to 9/27/14)
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
PM2 Pump Entities in Order of WO Cost (1/1/09 to 9/27/14)
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
TMP Pump Entities in Order of WO Cost(1/1/09 to 9/27/14)
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
APPENDIX B
TOP TEN PUMP DETAILS
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
1PM2246
91PM2 Kobe Pump #1
Kobe: Rotojet 9 W/Os$170,8
09
Date W/O No. W/O DescriptionFailure Type
Total Comments
25-Jan-09 642679 REPLACE PUMP LEAKAGE $13,619
10-Apr-09 659060 REPLACE PUMPNORMAL
WEAR$23,011
10-Aug-10 757995 CHANGE PUMPABNORMAL WEAR
$13,979
9-May-11 813512REPLACE KOBE PUMP
LEAKAGE $15,994
23-Jul-12 900643 REPLACE PUMPNOT
FAILURE RELATED
$14,305
2-Nov-12 943462REPAIR DISCHARGE PIPE
LEAKAGE $30,430
26-May-14 1013557TCC REPIPE KOBE PUMPS
NOT FAILURE RELATED
$43,733
this work order is to cover the cost of having the suction and discharge piping on the kobe pumps replaced.
REPLACED VALVES WITH VALVES THAT WERE CUT OUT AND WORKED FINE. NEEDS FURTHER INVESTIGATION. NOW HAS 2" OIC SWING CHECK VALVES.
19-Aug-14 1075458CHANGE THIS PUMP-SEAL LEAKING
NOT FAILURE RELATED
$12,044
27-Jan-14 1013556 TCC BASE REPAIRNOT
FAILURE RELATED
$3,694
to cover cost of repair to exisiting base and regrout new sill plate.
existing base - sill plate hollwo underneath and grout falling apart. New base ordered. had to re-drill a few holes - drawing modified.base levelled and grouted.
vibration checked and results good
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
2PM2255
04
Vacuum Pump - Pickup
Uhlebox
Nash 6 W/Os$139,7
23
Date W/O No. W/O DescriptionFailure Type
Total Comments
27-Feb-09 644729PREP FOR VAC PUMP CHANGE
NOT FAILURE RELATED
$1,446
27-Jun-09 674880CHANGE OUT VAC PUMP
BEARING $25,438
7-Jul-09 651067REBUILD PM2 SPARE VAC PUMP
BEARING $34,115
3-Nov-09 674916REBUILD VAC PUMP
BEARING $30,254
11-Apr-14 1046361REPLACE VAC PUMP
LEAKAGE $43,280
Seal leak non drive end of 7L11 vacuum pump.
Water going into bearing housing. Please prep for change out
19-May-14 1054844COMPLETE VAC PUMP CHANGE
LEAKAGE $5,190
Need to complete the pump install.
Blanks need to be removed, pump re-alignment and recoupled.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
3PM22466
4PM2 Kobe Pump #3
Kobe: Rotojet 9 W/Os $124,921
Date W/O No. W/O Description Failure Type Total Comments
5-Mar-10 722736 REPLACE PUMPNORMAL
WEAR$18,139
8-Mar-11 834972 CHANGE OUT KOBE LEAKAGE $13,878
15-Jun-11 798302 REPLACE KOBE PUMP LEAKAGE $13,437
16-Sep-11 819838 CHANGE OUT KOBE LEAKAGE $10,909
9-Aug-12 905576 CHANGE BELT/PUMP BELT $15,108
22-Aug-12 915655 C/O PUMPNOT FAILURE
RELATED$6,897
22-Sep-12 922977 REPLACE PUMP LEAKAGE $29,999
12-Nov-12 913782PURCHASE NEW KOBE PUMP
NOT FAILURE RELATED
$6,260
4-Dec-12 907437 WELD REPAIRS LEAKAGE $10,294
4 PM1255 Couch NASH 3 W/Os $102,7
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
21High
Vacuum Pump
81
Date W/O No.W/O
DescriptionFailure Type Total Comments
1-Jan-09 511947CHANGE DRIVE END BEARING
BEARING $5,931
Vibration showing Outer race defect and looseness. shaft is visibly moving. Both bearings replaced, however the journals are badly worn and requires further repairs.
Time line completed and follow items for review. -Marc
25-Jul-11 827309
REPLACE GEARBOX-BEARING DEFECT
NOT FAILURE RELATED
(BEARING)
$91,816 Bearing defects on output shaft
of gearbox. Trend increasing. -Ken Squires
20-Dec-12 935445
ALIGN GEARBOX/MOTOR/PUMP
ALIGNMENT $5,034
Check gearbox alignment. Increasing vibration suspected to be caused by soft foot condition. Gearbox was replaced in March 2012. Check coupling gaps.
Do not just tighten down bolts on the gearbox as it may twist the gearbox housing creating problems with gearmesh alignment and vibration.
Have ACT come in to inject the pump base along with the alignment of the gearbox and motor.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
5PM12461
39
Trim Slitter Unit #2 Pump
JET-X 8 W/Os$98,41
8
Date W/O No. W/O DescriptionFailure Type
Total Comments
7-Dec-09 706238REPLACE INTENSIFIER
LEAKAGE
$1,740 The intensifier has a leak and
needs to be repaired.
12-Jun-09 672137TCC OF CYLINDER REPAIR
LEAKAGE
$1,690
5-May-10 736427PAPRIMA INTENSIFER CYLINDER RE
LEAKAGE
$3,023
2-Jun-10 742580PAPRIMA INTENSIFER CYLINDER RE
LEAKAGE
$2,804
30-Jun-11 822973 REBUILD PUMPLEAKAG
E$890
26-Sep-13 997830REBUILD HP CYLINDER SEALS
SEAL $3,138 rebuild HP cylinder. water
leaking into the oil system.
1-May-13 965519INTENSIFIER FAILURE
LEAKAGE
$2,791 intensifier failure error coming
up on unit. Test and rebuild cylinder if necessary.
20-Jan-14 1026457PAPRIMA INTENSIFER FAILURE
LEAKAGE
$82,342
Monday January 20th ,2014 intensifer failure.
SEE FAILURE REPORT FOR DETAILS. HEAD BOLTS ON INTENSIFIER FAILED.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
6PM2246
27
PM2 Vacuum Sump Pump
#2Byron Jackson 7 W/Os $89,446
Date W/O No. W/O DescriptionFailure Type
Total Comments
28-Jan-09 644164 REMOVE PUMP/REPAIR SHAFT $15,177
28-Apr-09 662714 INSTALL PUMP SHAFT $1,560
4-Oct-10 768571 REBUILD SUMP PUMP LEAKAGE $673
10-Nov-10 776782REBUILD PUMP ASSEMBLY
ABNORMAL WEAR
$20,607
26-Sep-12 916629 PULL PUMPNORMAL
WEAR$1,078
27-Sep-12 916802INSTALL VERT SUMP PUMP
LEAKAGE $45,487
8-Aug-13 986434REPLACE DISCHARGE VALVE
ABNORMAL WEAR
$4,864
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
7GW62461
4
HRU Recirculatio
n PumpAhlstrom 13 W/Os
$86,401
Date W/O No. W/O Description Failure Type Total Comments
10-Mar-09 653263 C/O SEALNOT FAILURE
RELATED$750
29-Oct-09 698165C/O PUMP & MECH SEAL
SEAL $8,309
THE SEAL HAS BEEN LEAKING TO LONG WE NEED TO CHANGE OUT THE PUMP ALSO
16-Mar-10 726294REPLACE PUMP & MECH SEAL
SEAL $7,787
used stock # 34330045 and changed it from a dynamic seal to a mechanical seal
4-Jun-10 743454CHANGE PUMP OUT
BEARING $7,389
6-Jul-10 751680TCC OF EMERGENCY SPARE PUMP
NOT FAILURE RELATED
$11,076
WE NEED A SPARE JUST FOR THE INSTALLATION. DAVE HOWE MADE ONE FOR US
19-Oct-10 771851 REPLACE SEALNOT FAILURE
RELATED$22,609
28-Jan-11 791498SEAL LEAKING - REPLACE
LEAKAGE $1,003
8-Mar-11 801277TCC OF REBUILD
SEAL $4,551
17-Mar-11 803051PURCHASE SEAL
SYSTEM IMPROVEMEN
TS$4,428
24-Aug-11 833460TCC RETROFIT PUMP FOR SPARE
NOT FAILURE RELATED
$7,022
28-Sep-11 840583 purchase partsSYSTEM
IMPROVEMENTS
$4,466
18-Jan-12 864763REBUILD SPARE AT USL
SEAL $2,636
new seal started to leak - replaced with spare and spare is at usl being repaired seal went to edmonton to be repaired
17-Dec-13 1017654REPLACE ROATING ASSEMBLY
ABNORMAL WEAR
$4,375 Seal leaking and rotating
assembly needs to be replaced
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
8GW62469
1
MC Pump 5 - Bleached
TMP Tower
Sunds Defibrator
9 W/Os$82,70
3
Date W/O No. W/O Description Failure Type Total Comments
22-Feb-11 798218SEAL LEAKING - CHANGE PUMP
SEAL $7,107 The seal is leaking badly
and needs to be changed.
11-Apr-11 808072 CHANGE SEAL SEAL $3,478 Seal is leaking stock.
12-May-11 814824TCC OF REBUILD PARTS FOR USL
NOT FAILURE RELATED
$14,717
these parts are being purchased for usl so they can rebuild our rotating assembly for mc5. The parts will be sold to USL to cover the costs. - MAY12/11 - KAB
6-Feb-12 868290 SEAL LEAKING - C/O PUMP
NOT FAILURE RELATED
$16,811
17-Dec-12 934059MECH SEAL LEAKING-C/O PUMP
SEAL $10,627
17-Apr-13 962615TCC OF REPAIRS FOR USL
NORMAL WEAR
$457
parts from usl parts list to rebuild spare rotating assembly IPI stock # 28122710
8-Aug-13 986462REPLACE ROTATING ASSEMBLY
HIGH VIBRATION
$9,440 HIGH VIBRATION.
CHANGE ROTATING ASSEMBLY
29-Jan-14 1023297CHANGE OUT PUMP
NOT FAILURE RELATED
$11,737 leaking lots of water
20-Jun-14 1061999REPLACE ROTATING ASSEMBLY
LEAKAGE $8,329 USL Changed out the
pump.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
9PM12461
38
Trim Slitter Unit #1 Pump
JET-X 13 W/Os$79,51
8
Date W/O No.W/O
DescriptionFailure Type
Total Comments
12-Jun-09 672136TCC OF CYLINDER REPAIR
LEAKAGE $1,150
23-Jun-09 674345REPLACE HEAT EXCHANGER
UNKNOWN
$335 Heat exchanger unit requires
replacement. Identified by Nick Lawson during rounds.
16-Jul-10 753862INSPECT REPAIR INTENSIFIER
LEAKAGE $11,990
7-Sep-10 763209OVERHAUL PAPRIMA
LEAKAGE $3,368
15-Mar-10 726141 Overhaul Pump LEAKAGE $813 O/H intensifier
31-Aug-11 834841REBUILD PAPRIMA UNIT
ABNORMAL WEAR
$6,100
16-Oct-11 836341CHANGE FOOT VALVES
NOT FAILURE RELATED
$2,204
6-Oct-12 918366CHANGE HIGH PRESSURE CYLINDER
NOT FAILURE RELATED
$9,473
15-Aug-12 908841REPLACE CYLINDER
LEAKAGE $8,284 Leaky Intensifier cylinder. Please
replace and identify cause of failure. Please replace filters at same time
18-Jun-12 896828 REPAIR PUMP LEAKAGE $5,627 cut failed on this pump. Looks like it
has an oil leak. Probably will need tp rebuild the inner-sub assembly.
5-Jun-12 894755MAKE NECESSARY REPAIRS
NOT FAILURE RELATED
$2,435
Make necessary repairs to "up stream" trim squirts at the Wire. Currently these units are not being used< but they will be needed on heavier weights after the June 27th shut.
Please ensure all nozzle assemblies are fully intact and all the hoses are in place prior to the shut on June 27th.
16-Dec-13 1016412CHANGE OUT FILTER SET
FILTER FAILURE
$15,167
10-Oct-13 1019558REPAIR PAPRIMA INTENSIFIER
ABNORMAL WEAR
$2,854 One of the filter housings are cracked
st#6028420 they are in stores but not yet recieved.
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
10 PM224663PM2 Kobe
Pump #2
Kobe: Rotojet
5 W/Os $79,303
Date W/O No. W/O DescriptionFailure Type
Total Comments
16-Feb-10 721107CHANGE OUT PUMP
BEARING
$18,213
6-Dec-12 958564INTERNAL SEAL LEAKING
LEAKAGE
$13,975
20-Jun-13 975682 REPLACE PUMP SEAL $30,260
13-Jul-14 1067812CHANGE OUT PUMP
NORMAL WEAR
$10,102
15-May-14 1054363CHANGE THIS PUMP
NOT FAILURE RELATE
D
$6,753 This Pump was Installed
on May 15th2014
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
APPENDIX C
MILL ENTITY NUMBER
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
Pump Reliability Study: Irving Paper Last Modified: December 18th, 2014
Mill Area CodeEach area in the mill is represented by its own two or three-digit code that states the equipment location in the mill. A few examples used in this report are:
PM1 – Paper Machine #1GW3 – Thermal Mechanical
Pulping (TMP) Line 3TP – Thermal Plant
Specific Number
Each piece of equipment in the same area and class has its own specific number. This number would start at 001 and continue for however many pieces of equipment there are in said area.
Equipment ClassEach piece of equipment in the mill has an equipment class number that describes the type of equipment it is. In this report, the following three equipment classes are studied:
211 – Hydraulic Pumps255 – Vacuum Pumps246 – All Other Pumps
PM1-246-120