64
Public Hearings November 4, 6, 10 & 12, 2014

Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Public HearingsNovember 4, 6, 10 & 12, 2014

Page 2: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 2

Randy LindstromTransmission Planning Supervisor

Nebraska Public Power District

Page 3: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

SPP is a FERC Approved Regional Transmission Organization

Monitor the Regional Grid to Maintain Reliability Process Requests for Generator Interconnections and

Transmission Service Across the Region Operate Integrated Market Planning Coordinator For The Nine State SPP Region NPPD is a Member of SPP

Page 4: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District
Page 5: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Three Year study process to assess long-term and near-term needs of SPP Transmission System

Objective is to develop a cost-effective, flexible, and robust transmission network that provides efficient, reliable access to diverse generation resources

Promotes transmission investment that meets reliability, economic and public policy needs

ITP20-Year & ITP10-Year Plans are developed every three years and the ITP Near-Term Plan is developed every year

5

Page 6: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Transmission expansion plan focused on the year 2022 Economic and reliability analyses utilized to define the

required projects Two large scale projects in Nebraska were approved by

SPP Board Of Directors in January 2012 Hoskins – Neligh 345/115 kV Project (Under

Construction) Gentleman – Holt 345 kV R-Project (Public Hearing) The Needs and Benefits of these projects were to improve

reliability, reduce congestion, and enable renewables

6

Page 7: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District
Page 8: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

During the Summer of 2012, NPPD experienced severe hot and dry weather conditions across the entire system

Resulted in extreme system peak load levels NPPD set all-time record summer peak load levels

which were nearly 400 MW greater than 2011 North Central Nebraska area (Zone 5) experienced

unprecedented loads due to irrigation demand There were load delivery issues in Zone 5 due to

limited transmission capacity

Page 9: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

North Central Nebraska area (Zone 5) consists of high concentration of electric irrigation load

115 kV Transmission ring connected to stronger sources via limited capacity, high impedance lines

During contingency events of these source lines, or connections within the ring, thermal overloads and voltage depressions can occur

These issues jeopardize the future ability to reliably serve the local area loads during peak loading conditions

Page 10: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

In 2013, SPP Board of Directors directed this study in response to potential high incremental load additions in the SPP region

Oil and Gas development in New Mexico, Texas and Oklahoma and irrigation load growth in Nebraska

These new loads had not been accounted for in previous ITP studies

Cost effective transmission plan was developed to address reliability needs over a 10-year period under updated loads

High Priority Incremental Load Study was approved by SPP in 2014 and the Thedford 345/115 kV Project was included

Page 11: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District
Page 12: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

New Thedford 345 kV Substation and new Thedford345/115 kV 417 MVA Transformer

Ties into existing Thedford 115 kV Substation to provide a new high capacity feed on the west side of Zone 5

Thedford project is needed to address thermal overloads and voltage violations during contingency events in Zone 5

Thedford plan focused on maximizing the reliability benefits of the R-Project facility additions

Page 13: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

220 miles of new 345 kV transmission line and new 345 kV interconnections at Thedford and Holt County

Provides significant reliability benefits by addressing the worst case GGS area stability issues and the future Zone 5 load delivery issues

Provides congestion relief by increasing west – east transfer capability across the NPPD transmission system

Provides transmission capacity to allow interconnection of new renewable generation projects

Provides a new bulk transmission path to address thermal and voltage issues identified along the Gentleman – Grand Island transmission corridor

14

Page 14: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

R-Project needed to improve the Reliability of the Nebraska transmission system for future load delivery service

R-Project needed to Reduce Congestion on the existing Nebraska transmission system to improve future generation delivery service

R-Project needed to provide new transmission capacity to enable future Renewable generation interconnection and delivery service

The Nebraska Power Review Board approved NPPD’s application for authority to construct this project on October 10, 2014

Page 15: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 17

Aaron AmesDepartment Manager/Analyst

POWER Engineers, Inc.

Page 16: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 18

Routing and Siting Phases• Study area determination• Corridor determination• Route identification, analysis and selection• Working with affected landowners to resolve localized routing

issues related to a specific parcel• Public Input• Public meeting at each phase• Information given and received

Page 17: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Locations DatesInvitations

SentAttendance

Stud

y A

rea Tryon, Hershey, Halsey,

Mullen, Chambers &Ainsworth

1/19/2014 through

1/22/20133,695 581

Cor

rido

rs Thedford, Sutherland,Stapleton, Bartlett, Dunning & Burwell

9/9/2013 through

9/17/20131,641 369

Alte

rnat

e R

oute

s Stapleton, Sutherland, Thedford, Bartlett,Dunning & Burwell

4/29/14 through 5/7/2014

542 398

Add

ition

al

Lan

dow

ner

Mee

tings

Stapleton & Brewster8/13/2014 through

8/14/201477 63

11/12/2014 19

Page 18: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 20

Preliminary Study Area Determination Data Acquisition Field Reconnaissance Final Study Area Determination

Page 19: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 21

Reviewed the Study Area and Project • Agency scoping meetingsObtained agency input and data from US Fish and Wildlife Service,

Nebraska Game and Parks Commission, Nebraska Department of Roads, US Army Corps of Engineers, Nebraska Historical Society

• Public outreach meeting and community leader briefings• Study Area Public Meetings• Public comment and dataObtained comment and feedback, provided project information

Page 20: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 22

Page 21: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 23

Summary of Results from Study Area Public Meeting• Minimize impacts to residences• Minimize impacts to farm and ranch operations• Acquired data on new and planned center pivots, residence

locations, cemeteries, and land use

Page 22: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 24

Detailed Data Acquisition• High resolution aerial photography of Study Area • Field verification of information Initial public commentPublic data sources

• Identification of potential river crossings Determination of Initial Corridors Review Meeting and Determination of Final Corridor

Page 23: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 25

Determined Routing Criteria Key Criteria

• Proximity to homes• Proximity to Towns and Villages• Existing Access• Center pivot conflicts• Shelterbelts• Field bisections• Wetlands/Jurisdictional waters• Length• Cost• Heavy Angles

Conducted Analysis of Data based on the Criteria

Page 24: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 26

Proximity to Occupied ResidencesNumber less than 300 ft.Number over 300 ft. & less than 500 ft.Number over 500 ft. & less than 0.25 mile

Proximity to Towns/VillagesNumber less than or equal to 0.25 mileNumber over 0.25 mile & less than or equal to 0.5 mileNumber over 0.5 mile & less than 1 mile

Proximity to Other AmenitiesNumber of churches within 500 ft.Number of schools within 0.25 mileNumber of cemeteries within 500 ft.Public use airports (landing strip > 3200 ft.) within 1.5 milesPublic use airports (landing strip < 3200 ft.) within 1.25 milesPrivate FAA registered airports within 1.25 milesPrivate non-FAA registered airports within 0.5 mile

Land Use CriteriaWellheads within ROW of apparent centerlineNumber of other buildings within ROWProximity to platted developmentLength adjacent to platted development (ft.)Irrigated cropland crossed (acres in ROW)Pasture/rangeland crossed (acres in ROW)Dry land crops crossed (acres in ROW)Number of center pivot conflictsCultivated field bisections

Other Land UseNumber of parcels crossed by ROW Number of land owners affected by ROW

Page 25: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 27

Environmental CriteriaThreatened and endangered plant habitat within ROW (acres)Wetland/jurisdictional water crossed (acres)Recorded Conservation easements crossed (ft.)Trees within ROW (acres)Shelterbelt within ROW (acres)Number of known cultural resources within 500 ft. (recorded only)Number of river crossingsNumber of named stream crossingsPreliminary whooping crane stop over habitat (acres within 1 mile of route centerline)Tern and plover habitat (acres within 0.25 mile of route centerline)Sandhills Scenic Byway crossed (#)Sandhills Scenic Byway paralleled (miles)

Engineering and ConstructionDistance of floodplain crossing (ft.)Miles of Sandhills CrossedNumber of heavy angles (greater than 30 degrees)Length (miles)Cost (millions of dollars)

Subtransmission line (69 and 34.5 kV) relocation (ft.)Number of railroads crossedLength of railroads paralleled (ft.)Number state highways crossedNumber US highways crossedInterstate highway crossingNumber major pipelines crossedLength of major pipelines paralleled (within ROW)Number of existing 345 kV transmission line crossingsNumber of existing 230 kV transmission line crossingsNumber of existing 115 kV transmission line crossingsNumber of existing Subtransmission line (69 and 34.5 kV) crossingsLength of existing transmission parallel <500’ (ft.)Number of communication towers within 0.25 mileExisting access for construction and operation (miles)

Page 26: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 28

Corridor Selection• Selected corridors to minimize conflictsAvoidance of population density Minimizing impacts to agricultural land and center pivotsAvoidance of residencesRiver CrossingsAvoidance of wetlands

• Selected corridors that would provide for routing flexibility• Selected corridors that would provide substation siting

opportunities• Mapped corridors

Page 27: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 29

Page 28: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 30

Agency Scoping Conducted Second Public Outreach Meeting and

Briefings of Community Leaders Conducted Corridor Public Meetings Conducted Detailed Data Acquisition Conducted Additional Field Verification of

Information

Page 29: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 31

Input data collected into a Geographic Information System (GIS)

Determined Potential Route Links Screened Potential Route Links Determined Potential Routes Evaluated and Screened Potential Routes

Page 30: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 32

Route Screening Route alternatives developed Project team reviewed and further evaluated

alternatives

Page 31: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 33

Page 32: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Conducted Third Set of Public Outreach and Community Leader Meetings

Conducted Alternative Route Public Meetings Obtained Public Comment Specific to Route

Alternatives

Routing and Siting

11/12/2014 34

Page 33: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

• Additional Landowner meetings held• Invitations sent to potentially affected landowners• Comments specific to alternative routes were taken

1811/12/2014 35

Page 34: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 36

Reviewed over 2,200 Public Comments Final Route Evaluation Final Proposed Route Selection

Page 35: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 37

Page 36: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 38

Page 37: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 39

Page 38: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 40

Page 39: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 41

Page 40: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 42

Page 41: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 43

Page 42: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

11/12/2014 44

Page 43: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Compared to the Preferred Route Shown at the April/May Open Houses, the Proposed Route Results In:• Avoiding private airstrip• Fewer homes• Better access• Less shelterbelts• Avoiding new Wetland Reserve Program Property• Results in added length, angles and cost

Make Localized Adjustments as Needed to Proposed Route• Resolution of specific landowner issues related to land use

11/12/2014 45

Page 44: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Clint Endsley, PEProject Engineer

POWER Engineers, Inc.

Page 45: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

47

Page 46: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Avoid hill tops Locate on leeward wind side

Page 47: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

49

TUBULAR STEEL POLE

HORIZONTAL LATTICE TOWER

Page 48: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District
Page 49: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

51

TUBULAR STEEL POLE

HORIZONTAL LATTICE TOWER

Page 50: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District
Page 51: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

53

Schedule

Page 52: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

54

Page 53: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District
Page 54: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

56

Page 55: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Process of Succession Stabilization Vegetative Cover Periods of Varying Dominant

Plant Communities Native Plant Community Returns

Input from Stakeholders Landowners Sandhills Experts (Dr.

Stubbendieck, Restoration Contractors)

Local Agencies (UNL, NRCS, NRD, NDOR)

Page 56: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Al BeiermannLand Management Manager

Nebraska Public Power District

Page 57: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Stage 1: Preliminary activities• Survey• Engineering• Environmental• Appraisal

Stage 2: Acquisition of easements and substation sites

Stage 3: Construction and Maintenance activities

59

Page 58: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Survey activities• Collect information for design purposes• Develop legal description of easements

Engineering activities• Soil sampling

Environmental studies• Wetland area• Historical sites

Appraisal work Right of Entry Agreement

• Opportunity to determine best structure locations Restoration compensation

60

Page 59: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Landowner Contacts• Description of transmission line and easement• Landowner input welcome

Easement Rights• Landowner rightsContinue existing operationsRestrictions for trees, buildings, altering grade of land, etc.NPPD review of future plans

• NPPD RightsConstruct, operate, maintain line

Substation Facilities61

Page 60: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Good Faith Negotiations

Compensation Methodology

• Establish baseline land market values

Land classifications (based on land use)

Establish values for all land classifications

Obtain Independent Real Estate Appraiser

62

Page 61: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Assumptions: • Easement Area (1-mile x 200’ wide) = 24.24 acres• Land Value ($1,000/acre x 24.24 acres) = $24,240• Transmission Structures = 4 (four)

Special conditions compensation Substation Sites – purchase fee title

SinglePole

Lattice Tower

Easement Area Payment(80% of $24,240)

$19,392 $19,392

Structure Payment• Single Pole – 4 @ $500 ea. (equal to ½ acre value) • Lattice Tower – 4 @ $1,000 ea. (equal to 1 acre value)

$2,000$4,000

Total Easement Payment $21,392 $23,392

63

Page 62: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Landowner Rights• Good faith negotiations • NPPD Goal – voluntary easement acquisition

Negotiation Process Requirements• Accept or reject offer• Representation by an attorney• Eminent domain processAppointment of three individuals to serve as AppraisersAward paid to Clerk of County CourtBoth parties have right to appeal

64

Page 63: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Construction Activity• Compensation for damages

Tree Removal• Protect line integrity• Reduce future maintenance activities• Dispose of material

Future Maintenance Activity• Compensation for damages

Thirty-Day Comment Period

65

Page 64: Public Hearings November 4, 6, 10 & 12, 2014November 4, 6, 10 & 12,2014. 11/12/2014 2 Randy Lindstrom Transmission Planning Supervisor Nebraska Public Power District

Tom Kent, Vice President and Chief Operating

Officer