Upload
phungnga
View
219
Download
2
Embed Size (px)
Citation preview
PRE FEASIBILITY REPORT
for
PROPOSED EXPANSION OF DISTILLERY
of
M/s. SHREE GANESH KHAND UDYOG
SAHKARI MANDLI LTD.
Shri Harisinhji Mahida Bhavan, At & Po: Vataria,
Tal: Valia, Dist: Bharuch, Gujarat-393001
CONTENTS
1.0 EXECUTIVE SUMMARY
1.1 Company Profile
Shree Ganesh Khand Udyog Sahkari Mandli Limited was founded in the year 1985 in
Gujarat, India. The Company is a manufacturer and exporter of diverse range of
Agricultural and other products. All the affairs of the company are managed under the
guidance of Mr. Banesinh S. Dodia, the managing director. It is under his headship,
they have achieved the newer heights of success. Here are the few highlights of the
company.
Specialization
The enterprise is a co-operative Sugar Factory registered under the Co-operative Sugar
Societies Act-1961 (Regd. No. SE-42, dt.22-04-1985). The plants installed in our
production unit have the capacity of 4200 TCD owing to the same, around 3800 to 4000
MT of Sugarcanes is crushed per day with capacity utilization of around 120%. We have
also achieved an average sugar recovery of 10.52% during season 2007-08.
Infrastructure
The state-of-the-art infrastructure is backed with technologically advanced tools and
machineries that assist in the quality and quantity production of our products.
Moreover, the robust infrastructural base has also been an essential element of
smooth functioning of the business.
Sr.
No.
Description Page No.
1. Executive Summary 3
2. Introduction of the Project/Background information 6
3. Project Description 8
4. Site Analysis 16
5. Planning Brief 17
6. Proposed Infrastructure 18
7. Rehabilitation and resettlement (R & R) Plan 19
8. Project Schedule & Cost Estimates 19
9. Analysis of Proposal (Final Recommendations) 19
2
Quality Assurance
Our prime motto is to serve quality products and for the same, various stringent quality
tests are conducted under the supervision of our quality control executives. The quality
checks are conducted in our well-equipped laboratories that are arranged in our plants
of Distillery & Sugar.
1.2 Project Details
1.2.1 Products along with Production Capacity
NAME OF PRODUCTS EXISTING*
(MT/Month)
TOTAL AFTER EXPANSION
(MT/Month)
Products
V.P. Sugar 14,500 14,500
Rectified Spirit 33 KLPD 66 KLPD
Absolute Alcohol 30 KLPD 60 KLPD
By-Products
Molasses 6,000 7,500
Bagasse 45,000 45,000
Filter Cake 4,500 4,500
* CTE No. 39960 dated Dec. 27, 2010 obtained. CCA Inward application no. 96471
dated June 25, 2015 applied.
1.2.2 Raw Material Requirement
LIST OF RAW MATERIALS EXISTING*
(MT/Month)
TOTAL AFTER EXPANSION
(MT/Month)
SUGAR
Sugar Cane 1,35,000 1,35,000
Lime 216 216
Sulphur 61 61
Phosphoric Acid 8.1 8.1
DISTILLERY
3
Molasses 3,750 MT/Month 7,500 MT/Month
* CTE No. 39960 dated Dec. 27, 2010 obtained. CCA Inward application no. 96471
dated June 25, 2015 applied.
1.3 Water Requirement, Waste Water Generation and Treatment
Total water requirement is 1820 KL/Day at present which is met through Bore well. The
wastewater generation is 1215 KL/Day at present. Total water requirement will be
2010 KL/Day after proposed expansion which is met through Bore well. The wastewater
generation will be 890 KL/Day after proposed expansion. The effluent from sugar
factory is sent to ETP consists of primary, secondary & tertiary treatment facility to
treat the effluent and treated effluent is reused as per requirement of factory for
cooling, washing, irrigation purposes, etc. Entire qty. of wastewater from distillery is
utilized in bio-composting and the same shall be followed after proposed expansion.
1.4 Air Pollution Source and Control Management
Sr.
No.
Stack
Attached to
Stack Height
in meter
Air Pollution Control
System
Parameter Permissible Limit
1.
Boiler 1 & 2
(20 MT/Hr)
40 Multi Cyclone
Separator with
Scrubber (Wet)
Particulate Matter ≤ 150 Mg/Nm3
SO2 ≤ 100 ppm
NOX ≤ 50 ppm
2. Boiler 3
(35 MT/Hr) 40
Particulate Matter ≤ 150 Mg/Nm3
SO2 ≤ 100 ppm
NOX ≤ 50 ppm
3. Boiler 4
(15 MT/Hr) 40
Particulate Matter ≤ 150 Mg/Nm3
SO2 ≤ 100 ppm
NOX ≤ 50 ppmler
4.
Boiler 5
(Proposed)
(2.5 MT/Hr)
30
Particulate Matter ≤ 150 Mg/Nm3
SO2 ≤ 100 ppm
NOX ≤ 50 ppmler
There shall be no process emission from the manufacturing process as well as any other ancillary
process.
4
1.5 Hazardous Waste Management
Sr.
No.
Type of Hazardous
Waste
Category Existing Total after
Proposed
Expansion
Mode of Disposal
1. Used Oil 5.1 202 Lit/
Month
202 Lit/ Month Collection, storage,
transportation and final
disposal by sale to registered
re processors or use as
lubricant.
2. Discarded Bags /
Liners / Drums
33.1 4648
Nos./Month
4648
Nos./Month
Collection, storage,
transportation & sale to
authorized traders.
3. Bio-Compost - 2000
MT/Month
3300 MT/Month Used as manure
4. ETP Sludge 35.3 - 15 MT/Month
1.6 Green Belt
Company has developed an effective green belt within the factory and on periphery of
the factory. Total Plot Area is 4,86,264 m2 out of which 1,45,879 m
2 is Green Belt Area.
In addition to this, majority of the vacant land shall be planted with trees, shrubs and
grasses.
1.7 Power & Fuel Requirements
Power required from DGVCL is 75 KW.
SR.
NO.
NAME OF FUEL QUANTITY (MT/HR)
EXISTING ADDITIONAL TOTAL
1. Bagasse 40 15 55
2. Biomass (Briquette) -- 0.5 0.5
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of the project and project proponent. In case of mining project, a
copy of mining lease/letter of intent should be given.
5
Identification of the project
Shree Ganesh Khand Udyog Sahkari Mandli Limited, Proposes expansion of distillery at
Shri Harisinhji Mahida Bhavan, At & Po: Vataria, Tal: Valia, Dist: Bharuch, Gujarat-
393001
Identification of the project proponent
SR.
NO.
NAME OF DIRECTOR ADDRESS
1. SHREE SURJITSINH.A.MANGROLA
(CHAIRMAN)
AT & PO.LUNA,
DIST : BHARUCH
MOBILE NO.-9099700006
2. SHREE MOHANBHAI BECHARBHAI PATEL
(VICE-CHAIRMAN)
AT & PO : NAGAL,
DIST : BHARUCH
MOBILE NO.- 9825325351
3. SHREE MOTISINH GANPATSINH MATIYEDA
AT & PO : VALIA,
DIST : BHARUCH
MOBILE NO.-9099300123
4. SHREE VIJAYSINH BHIMSINH VASAVA
PO : MIRAPOR ,
DIST : BHARUCH
MOBILE NO.-9913210082
5. SHREE DINESHBHAI CHHANABHAI PATEL
(CHAUDHARY)
PO : AMBAVADI,
DIST : BHARUCH
MOBILE NO.-9979130121
6. SHREE JAYENDRASINH MOTISINH KATHAVADIYA
AT & PO : KATHWADA
DIST : BHARUCH
MOBILE NO.-9925396961
7. SHREE ARVINDSINH CHHATRASINH VARACHHIYA
AT & PO : KANTVA,
DIST : BHARUCH
MOBILE NO.-9925239403
8. SHREE IBRAHIM GULAM MOHMED MANJRA AT & PO : DIVA,
DIST : BHARUCH
MOBILE NO.-9825178826
9. SHREE PIYUSHKUMAR CHANDRAVADAN PATEL
AT : VAGHVAN,
DIST : BHARUCH
MOBILE NO.-9825729510
10. SHREE MAHENDRASINH RANDHIRSINH PILUDARIYA
AT & PO : DHAROLI,
DIST : BHARUCH
MOBILE NO.-9925239402
11. SHREE NAVINBHAI PARAGBHAI PATEL
AT & PO : SAMLOD,
DIST : BHARUCH
6
MOBILE NO.-9925239401
12. SHREE HIRALAL KANCHANLAL MODI
AT & PO : ANKLESHWAR
DIST : BHARUCH
MOBILE NO.-9879933777
13. SHREE KARSHANBHAI.G.PATEL
AT & PO : PARDI IDRISH ,
DIST : BHARUCH
MOBILE NO.-9825317404
14. SHREE MANHARLAL.M.PATEL AT & POST : CHALTHAN ,
DIST : BHARUCH
MOBILE NO.-9825113049
15. SHREE BANESINH.S.DODIA
(MANGING DIRECTOR)
AT & POST : VATARIA ,
DIST : BHARUCH
MOBILE NO.-9925192007
16. DIRECTOR OF SUGAR GANDINAGAR
PHONE: 079-23220771
17. JOINT DIRECTOR (AGRI.) VADODARA
18. DIRECTOR
GANDHINAGAR
PHONE: 079-23222293
2.2 Brief description of nature of the Project
Proposed expansion of Distillery
2.3 Need for the project and its importance to the country and or region
The demand for products intended to be manufacture is increasing in the country by
expanding this unit M/s Shree Ganesh Khand Udyog Sahkari Mandli Limited will be able
to meet the demand of the product locally. This will also generate direct and indirect
employment opportunity for various levels of people.
2.4 Demands-Supply Gap
Based on our informal survey of the market with our current customers and various
traders, we have found that there is a big potential for the range of the products we
are planning.
7
2.5 Imports vs. Indigenous production
Based on the current cost of indigenous raw materials and the non availability of some
materials, we will have to import some of the key raw materials as they are not
available indigenously. This will make us very competitive against imported finished
products and we will export of our finished products to the international markets.
2.6 Export possibility
Depending on the international demand of products we shall explore the possibility of
exporting the products.
2.7 Domestic/Export Markets
Major portion of the product will be used for domestic market and some portion of the
product may be exported depending on the international market.
2.8 Employment Generation (Direct and Indirect) due to project.
M/s Shree Ganesh Khand Udyog Sahkari Mandli Limited will give direct employment to
local people based on qualification and requirement. In addition to direct employment,
indirect employment shall generate ancillary business to some extent for the local
population.
3.0 Project Description
3.1 Type of Project including interlinked and interdependent projects, if any.
Proposed Expansion of Distillery Unit
Category: A-5(g)
No interlinked project has been submitted.
8
3.2 Location (map showing general location, specific location and project boundary &
project site layout) with coordinates.
Map showing general location
(Courtesy: Environmental Information Center, New Delhi)
12
3.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
It is expansion within existing premises. No alternate site considered.
Major factors involved in the selection of site are listed below:
• Minor site clearance activities shall be carried out to clear shrubs and weed.
• The project site is located on level ground, which does not require any major land filling
for area grading work.
• Proximity to Raw Material suppliers.
• Site is very well connected by road and railway.
• Availability of Power, Water, etc.
Modern infrastructure support and amenities at par in other global markets, including:
� Efficient transport facilities.
� Environment-friendly zone.
� Uninterrupted power supply.
3.4 Size or Magnitude of Operation
Please refer Section-1.2.1, Page No. 1 to 2.
3.5 Project Description with process details (a schematic diagram/flow chart showing the
project layout, components of the project, etc. should be given)
Please refer Please refer Form-I, Annexure-III.
3.6 Raw Material required along with estimated quantity, likely source, marketing area of
final product/s, mode of transport of raw material and Finished product.
For raw material required along with quantity; Please refer Section-1.2.2, Page No. 2.
3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be
briefly outlined.
After proposed expansion, every effort will put to recycle/reuse the water.
13
3.8 Availability of water its source, energy/power requirement and source should be
given.
Water Source
Total water requirement shall meet through bore well.
Power & Fuel Requirement
Power required from DGVCL is 75 KW.
Bagasse: 55 MT/Day
(40 MT/Day Existing + 15 MT/Day Additional)
Biomass (Briquette): 0.5 MT/Day
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
management/disposal.
Please refer Please refer Form-I, Annexure-V & VI.
3.10 Schematic representations of the feasibility drawing which give information of EIA
purpose.
RECONNAISSANCE SURVEY OF EXISTING PLANT ANNUAL REPORT
MARKET ASSESSMENT
FINANCIAL REPORT
PROJECT REPORT
INTRODUCTION
MONITORING OF AIR, WATER & SOIL QUALITY & NOISE
LEVELS. DATA ON METEOROLOGY SOCIO-ECONOMIC STATUS
& BASIC AMENITIES. SITE VISITS BY AND INTERVIEWS WITH
LOCALS
BASELINE
ENVIRONMENTAL
STATUS
ENVIRONMENTAL INFORMATION CENTRE
CENTRAL GROUND WATER BOARD
GUJARAT POLLUTION CONTROL BOARD (GPCB)
PUBLIC HEALTH ENGINEERING DEPT.
AGRICULTURE DEPARTMENT
FOREST DEPARTMENT
IRRIGATION DEPARTMENT
EMPLOYMENT EXCHANGE
HEALTH CENTER
CENSUS DEPT.
INDIAN METEOROLOGICAL DEPT.
SOCIOECONOMIC
STATUS &
INFRASTRUCTURE
PROPOSED
PLANT
FACILITY DESCRIPTION
IMPACTS
METHODOLOGY OF
IMPACT
ASSESSMENT
IDENTIFICATION & ASSESSMENT OF IMPACTS
EVALUATION OF IMPACTS BY MATRIX METHOD
SOURCE OF INFORMATION OVERVIEW OF
E. I. A. STUDIES
ACTIVITIES
ENVIRONMENTAL
MANAGEMENT PLAN
DESCRIPTION OF EFFLUENT TREATMENT PLAN, AIR
POLLUTION CONTROL, HAZARDOUS WASTE MANAGEMENT,
GREEN BELT DEVELOPMENT MONITORING PROGRAM
RISK ANALYSIS
STUDIES &
DISASTER
MANAGEMENT PLAN
SAFETY, HEALTH & ENVIRONMENTAL POLICY, GUIDELINES BY
DIRECTOR GENERAL OF FACTORY SAFETY, MINISTRY OF LABOR. CONSEQUENCE ANALYSIS
PREPARATION OF DISASTER MANAGEMENT PLAN
14
4.0 Site Analysis
4.1 Connectivity
• Site is very well connected by road
• Availability of water, power facilities
4.2 Land Form, Land Use and Land Ownership
It will be incorporated in EIA Studies.
4.3 Topography (along with map)
We will be incorporated topography in EIA Studies.
4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including
area under CRZ)), shortest distances from the periphery of the project to periphery of the
forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from
HFL of the river), CRZ. In case of the notified industrial area, a copy of the Gazette
notification should be given.
It will be incorporated in EIA Studies.
4.5 Existing Infrastructure
Existing Infrastructures facilities are listed below:
Site is very well connected by road
Proximity to sugar cane growers
Availability of sufficient land free form cultivation
Availability of power evacuation facilities
4.6 Soil Classification
It will be incorporated in EIA Studies.
15
4.7 Climatic data from secondary sources
Primary source: our own weather station & Secondary Sources: Indian Meteorological
Department, Ahmedabad.
4.8 Social infrastructure available
Depending on the growth of the company the required social infrastructure will be
provided.
5.0 Planning Brief
5.1 Planning Concept (type of industries, facilities, transportation, etc) Town and Country
planning/Development authority classification.
Type of Industry: Proposed expansion of distillery
5.2 Population Projection
It will be incorporated in EIA Studies.
5.3 Land use planning (breakup along with green belt etc.)
Total Area – 175400 m2
Plant Area – 27025 m2
Open Area – 40000 m2
Green Belt Area – 65000 m2
5.4 Assessment of Infrastructure Demand (Physical & Social)
It will be incorporated in EIA Studies.
5.5 Amenities/Facilities
It will be incorporated in EIA Studies.
16
6.0 Proposed Infrastructure
6.1 Processing Zone – 100000 m2
6.2 Non- Processing Zone – 386264 m2
6.3 Green Belt
Company has developed an effective green belt within the factory and on periphery of the
factory. Total Plot Area is 4,86,264 m2 out of which 1,45,879 m
2 is Green Belt Area. In
addition to this, majority of the vacant land shall be planted with trees, shrubs and grasses.
6.4 Social Infrastructure
Depending on the growth of the company the required social infrastructure will be
provided.
6.5 Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways etc)
Major factors involved in the selection of site are listed below:
• Site is very well connected by road
• Proximity to sugar cane growers
• Availability of sufficient land free from cultivation
• Availability of power facilities
• Availability of water
6.6 Drinking water Management (Source & Supply of water)
Total water requirement shall meet through bore well.
6.7 Sewerage System
Sewage pipes would be laid in entire sugar factory for the removal and disposal of mainly
non-harmful liquid wastes from the offices, canteen and domestic waste coming from
different sections. These liquid wastes would be sent to septic tank & soak pit.
6.8 Solid Waste Management
Please refer Section 1.5 (Page No. 3).
17
7.0 Rehabilitation and Resettlement (R & R) Plan
7.1 Policy to be adopted (central/state) in respect of the project affected including home
oustees, land oustees and landless laborers (a brief outline to be given)
There is no habitation on the proposed expansion project activity area and it is barren land,
so R & R policy is not applicable to this project.
There shall not be displacement of any population in project area. Any major activity that
may lead to resettlement of the people is considered as permanent impact. Hence, there is
no permanent impact on this account. The increasing industrial activity will boost the
commercial and economical status of the locality up to some extent.
8. Project Schedule & Cost Estimates
8.1 Likely date of start of construction and likely date of completion (Time schedule for
the project to be given).
We shall start construction after getting environmental clearance and consent to establish.
We shall start production upon making application for CCA.
8.2 Estimated Project cost along with analysis in terms of economic viability of the
project.
Total Project Cost for proposed project activity is Rs. 2.97 Crores.
9. Analysis of Proposal (Final Recommendations)
9.1 Financial and social benefits with special emphasis on the benefit to be local people
including tribal population, if any, in the area.
• Employment would be as per prevailing norms of state government for skilled and
unskilled people for the proposed expansion project.
• Social Welfare shall be done.
• Cordial relation with the industry shall be established and representation shall be made
to villagers for help for creation of facilities related to health, education, etc.