59
Proper Placement of Concrete Decks

Proper Placement of Concrete Decks

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Proper Placement of Concrete Decks

Proper Placement of

Concrete Decks

Page 2: Proper Placement of Concrete Decks

Some Rules for Being a

Good Inspector

• Know the goal

• Enforce the specification

• Understand the contractor’s position

• Make sure the contractor understands

your position

Page 3: Proper Placement of Concrete Decks

Stiff Mixture

Page 4: Proper Placement of Concrete Decks

Wet mixture

Page 5: Proper Placement of Concrete Decks
Page 6: Proper Placement of Concrete Decks

• Know your technical limits—particularly on

bridge projects

• Develop a strategy for getting information

when you need it

• 3 major goals for any project:

1. Schedule

2. Budget

3. Quality

Some Rules for Being a

Good Inspector

Page 7: Proper Placement of Concrete Decks

Long after people forget the schedule and

budget, they will remember the quality.

This is your legacy and contribution to

our infrastructure.

Page 8: Proper Placement of Concrete Decks

Concrete Deck Construction

Three Parts to Deck Inspection:

1. Pre-placement Inspection

2. Placement Inspection

3. Post-placement Inspection

If the checklist below were followed on all

deck construction, we could have avoided

the vast majority of our deck problems.

Page 9: Proper Placement of Concrete Decks

Part 1: Pre-placement Inspection

Chairs: tipping, slippage, stacking,

consolidation

Forms: sturdy, clean

Reinforcement: size and type, clean

Shear Studs: spacing, height

Joints

Concrete Deck Construction

Page 10: Proper Placement of Concrete Decks

Deck Forms: Continuous Chairs

Page 11: Proper Placement of Concrete Decks

Are the bar size and spacing correct?

Typical transverse bar spacing is in the 5”- 7” range.

This deck is missing every other bar for a 14” spacing,

which should be a red flag that a problem exists.

Page 12: Proper Placement of Concrete Decks

Are the joints formed with

compressible material?

Use rigid foam or rubber rather

than timber

Page 13: Proper Placement of Concrete Decks

(Part 1)

Trucks

Screed set properly

o Vibrating unit

o Burlap drag

Backup vibrators

Clean lines for pump

Mobile mixer calibration

Concrete testing equipment

o Specs and calibration

Curing box with recording

thermometer

o Continuous temperature data

that can be printed

Concrete Deck Construction

Checklist

Page 14: Proper Placement of Concrete Decks

Is the concrete deposited using a chute?

(Aluminum chutes or lines are not permitted)

Page 15: Proper Placement of Concrete Decks

Is the screed set properly to provide

the specified crown and grade?

Check before placing concrete

Page 16: Proper Placement of Concrete Decks

Tachometer

Page 17: Proper Placement of Concrete Decks

(Part 1)

Aggregate Storage

Contingency Plan

o Equipment breakdown and inclement weather

Trial Batches

o Completed and results submitted and approved

Concrete Deck Construction

Checklist

Page 18: Proper Placement of Concrete Decks

(Part 2)

Forms are pre-warmed in cold weather

Aggregates kept from freezing

Ingredients cooled in hot weather

Use flaked or shaved ice

Monitor rate of evaporation

Concrete Deck Construction

Checklist

Page 19: Proper Placement of Concrete Decks

Part 2: Placement Inspection

Light availability

Certified Personnel

Formwork

Proper documentation

o Form TL-28a

Concrete protected against the elements

Concrete Deck Construction

Checklist

Page 20: Proper Placement of Concrete Decks

(Part 2)

Added water

Concrete delivery within time limit

Placement against fresh batch

Placement as close as possible to the final location

Even distribution

Concrete free from segregation

Concrete Deck Construction

Checklist

Page 21: Proper Placement of Concrete Decks

Place concrete as close as possible

to the final location in the structure

Chute outlet does not reach entire pour

Page 22: Proper Placement of Concrete Decks

(Part 2)

Avoid concrete contact with reinforcing bars

Dropping concrete

o Distance < 5’

o Drop chutes or tremie to direct the fall, no free fall

Avoid time delay

Concrete covered if delay

Moved by vibrators: NO

Concrete Deck Construction

Checklist

Page 23: Proper Placement of Concrete Decks

Is concrete moved by vibrators?

(Unacceptable Practice!)

Page 24: Proper Placement of Concrete Decks

(Part 2)

Vibrator inserted vertically and in grid pattern

Proper consolidation conducted even along the

edge and joints,

Over vibration may cause segregation

Concrete Deck Construction

Checklist

Page 25: Proper Placement of Concrete Decks

Are vibrators inserted in a grid pattern?

Page 26: Proper Placement of Concrete Decks

Consolidation

Page 27: Proper Placement of Concrete Decks

Is vibration causing segregation? (excessive mortar brought to the surface)

Excessive mortar at surface

Page 28: Proper Placement of Concrete Decks

Segregation

Page 29: Proper Placement of Concrete Decks

(Part 2)

Sufficient screed support

Sufficient concrete rolling in front of the rollers

Moderate amount of paste or mortar on the surface

of the concrete after screeding?

Concrete Deck Construction

Checklist

Page 30: Proper Placement of Concrete Decks

Is there enough concrete rolling in

front of the rollers?

Page 31: Proper Placement of Concrete Decks

Concrete in Front of the Rollers and the Auger

Page 32: Proper Placement of Concrete Decks

Is there only a moderate amount of paste or mortar

on the surface of the concrete after screeding?

Excessive mortar at surface

Page 33: Proper Placement of Concrete Decks

(Part 2)

Apply fog mist to concrete surface immediately after

screeding. Do not use a hose or pressure washer.

Do not spray water on the concrete before the screed

Only moderate hand finishing

Low areas

Wet burlap application

Specimen box immediately after casting

Concrete Deck Construction Checklist

Page 34: Proper Placement of Concrete Decks

Do NOT spray water on the

concrete surface before the screed

Page 35: Proper Placement of Concrete Decks

Fog Misting (Correct Procedure)

Page 36: Proper Placement of Concrete Decks

Water applied to

concrete surface

after screeding

should use a fog

mist. Do not use

hose nozzle.

Page 37: Proper Placement of Concrete Decks

Is any hand finishing

moderate?

Excessive hand finishing

Page 38: Proper Placement of Concrete Decks

Is the burlap wet and applied in a timely manner? (Surface drying! )

Page 39: Proper Placement of Concrete Decks

Is the burlap wet ? (but not dripping!)

Page 40: Proper Placement of Concrete Decks

Wet burlap

Page 41: Proper Placement of Concrete Decks

Proper Application of Wet Burlap?

Page 42: Proper Placement of Concrete Decks

Place Blankets Immediately After

Screeding

Page 43: Proper Placement of Concrete Decks

Proper Application of Wet Burlap

Page 44: Proper Placement of Concrete Decks

Burlap marks indicating timely

application of burlap.

Page 45: Proper Placement of Concrete Decks

Plastic Cover to Prevent Loss of

Moisture

Ties & Weights

help keep plastic

in place

Page 46: Proper Placement of Concrete Decks
Page 47: Proper Placement of Concrete Decks

Part 3: Post-placement Inspection

Daily checks on wet burlap

Freeze protection

Proper use of curing compound

Monitor concrete temperature

Checking joints

Alignment, formwork removed, workmanship

Low spots

Concrete Deck Construction

Checklist

Page 48: Proper Placement of Concrete Decks

Cold weather - Concrete Temperature

Page 49: Proper Placement of Concrete Decks

Cracks should be kept to less than .10mm. Cracks greater

than .20 mm (.01”) will allow intrusion of water & chlorides

& should be repaired either with epoxy or sealant

Page 50: Proper Placement of Concrete Decks

Cracks over .20 mm

should be repaired

Page 51: Proper Placement of Concrete Decks

Plastic shrinkage cracks – usually appear within the first

week or two

Page 52: Proper Placement of Concrete Decks

Plastic shrinkage cracks – usually appear within the first

week or two

Page 53: Proper Placement of Concrete Decks

Plastic shrinkage cracks – usually due to improper curing

and should be the responsibility of the contractor

Page 54: Proper Placement of Concrete Decks

Drying shrinkage cracks – may occur up to 6 months after

pour. Often transversely oriented and deep.

Page 55: Proper Placement of Concrete Decks

Checking for Low Spots:

Is the surface checked for low spots?

Page 56: Proper Placement of Concrete Decks

Checking for Low Spots:

Is the surface checked for low spots?

Page 57: Proper Placement of Concrete Decks

Checking for Low Spots:

Is the surface checked for low spots?

Page 58: Proper Placement of Concrete Decks

Conclusion

Proper attention to details will result in

quality construction. Structures built

with quality are safe, durable, and

cost effective.

Page 59: Proper Placement of Concrete Decks

Thank you.