0 Projek Menaiktaraf Bayan Lepas Expressway Dari Batu Maung ke Jambatan Pulau Pinang

Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

Embed Size (px)

Citation preview

Page 1: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

0

Projek Menaiktaraf Bayan Lepas Expressway

Dari Batu Maung ke Jambatan Pulau Pinang

Page 2: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

PROJECT ORGANIZATION CHART

Page 3: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

2

Employer JKSB

Design and Build Contractor UEMB

Consulting Engineer (C & S) RB Perunding Sdn. Bhd.

Consulting Engineer (M & E) RAZ Associates

Contract Sum

RM 359,713,908.80 (Based on Tender Sum Analysis –

19th April 2013)[ RM 15,000,000.00 Provisional Sum for underground utilities relocation at Sungai Tiram]

Effective Date Of Contract TBA

Original Completion Date of Construction TBA

Construction Period Twenty Four (24) Months

CONTRACT INFORMATION

Page 4: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

3

Completion Date of Defect Liability Period TBA

Defect Liability Period Twenty Four (24) Months

Liquidate And Ascertained Damages 0.0535%/day

Performance Bond TBA

Contractors All Risk Insurance

a) Policy No. : CCX03374565/64/01/YYY

b) Expiry Date : 14th May 2017

Workmen’s Compensation Insurance

a) Policy No. : LWX/03374566/64/01/YYY

b) Expiry Date : 30th April 2017

CONTRACT INFORMATION (CONT’)

Page 5: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

4

The scope of works comprise of construction and completion of

a) 1 No. of Dual Two Elevated Structureb) 1 No. Roundabout at Southbay Junctionc) Road Wideningd) Drainagee) Walkwayf) Pedestriang) Relocation of Utilities and Servicesh) Street Lightingi) Landscapingj) Pavementk) Road Marking and Furniturel) Traffic Sign

PROJECT SCOPE OF WORKS

Page 6: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

PROJECT LAYOUT PLAN

Page 7: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

6

SUMMARY OF PROGRESS

Activities Completed at Site Actual Start Actual Finish

1. Mapping and Detection of Utilities Works 2-Jan-13 15-Jan-13

2. Total of 26 Boreholes Soil Investigation(Confirming Design)

25-Jan-13 19-Feb-13

3. Dilapidation Survey Works 27-Dec-12 15-Mar-13

4. Signboard Installation Works 12-Mar-13 25-Mar-13

5. Total of 26 Boreholes Soil Investigation(Alternative Design)

13-Apr-13 10-May-13

6. Removal of Trees at Median (CH 1800 – CH 5000)

6-May-13 21-May-13

7. Temporary Road Widening (CH 1800 – CH 5000) 21-May-13 22-Jun-13

8. Installation of Temporary Street Lighting Works(CH 1800 – CH 5000)

9-July-13 7-Aug-13

Page 8: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

7

SUMMARY OF PROGRESS (Cont’)

Activities In Progress Total Quantity

Quantity Completed (As of 22nd

Aug 2013)

Actual Start

1. Total of 77 Boreholes Soil Investigation(Alternative Design)

77 35 12-June-13

2. Bored Piling Works 98 - 19-Aug-13 (Test Pile at

Pier P18)

Page 9: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

8

SUMMARY OF PROGRESS (Cont’)

Activities In Progress

1. Casting Yard a) Site Clearance completed on 12th August 2013.b) Construction of Hoarding in progress.c) Construction of Internal Road in progress.

2. Batching Plant a) Site Clearing & Platform Preparation completed on 19-July-2013.b) Plant positioning pegging at site and piling works completed on 29-July-2013.c) Civil works-construct plant foundation, Toilet, Lab in progress.

3. Installation of Temporary Cofferdam Caisson in progress.

4. Remove Existing Median in progress. Total length to remove = 3200mTotal length completed remove = 2100m (As of 22nd August 2013)

Page 10: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

9

SUMMARY OF PROGRESS (Cont’)

Activities In Progress

5. Protection / Relocation of Services at CH000 – CH525Trial hole (11kV and 33kV) completed on 22-Aug-13 morning. The result will be compiled and submit to TNB for confirmation of cable type.

6. Protection / Relocation of Services at CH5000 – CH6175Trial hole (33kV) in progress. The result will be compiled and submit to TNB for confirmation of cable type.

Page 11: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

10

PROGRESS CLAIM

CLAIM AND PAYMENT STATUS

ICP No. 1 RM 2,533,231.00 (For Period Ending May 2013)

ICP No. 2 RM 4,220,263.17 (For Period Ending June 2013)

ICP No. 3 RM 5,123,283.49 (For Period Ending July 2013)

Total Billing to Date : RM 11,876,777.66

Latest Certification : -

Latest Payment Received : -

Page 12: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

11

Status

Preliminary Drawings Submitted

DESIGN DEVELOPMENT STATUS

Page 13: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

12

Summary of Method Statement for Erection

Note: The information as of 21st August 2013

Method Statement submission and approval

Nos. Remarks

Method Statement issued to RBP 9

Method Statement Accepted / Info by RBP 9

Method Statement Under Review by RBP 0

Method Statement UEMB to resubmit to RBP 0

Method Statement Submitted to JKSB 9

Method Statement Close Out / Info by JKSB 0

Method Statement Pending Close Out by JKSB 3Soil Investigation

Bored Pile Cast In Situ Construction

Bored Pile Testing using O-Cell Test

Method Statement Pending Close Out by UEMB 6

Temporary Widening Existing Road

Temporary Street Lighting Pole

Hacking of Parapet (Temporary works)

Temporary Cofferdam – Caisson

Toe Grouting of Bore Pile In-Situ

Sonic Logging of Bored Pile In-Situ

Page 14: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

13

NO.SAFETY, HEALTH &

ENVIRONMENT ACTIVITIESNUMBERS/FREQUENCY PARTIES INVOLVED

1 Safety Meeting Nil Nil

2 Tool Box Meeting 14 Sub Contractors

3 Safety Induction 9 Sub Contractors

4 Safety Training (e.g. fire drill) Nil Nil

5 HSE Improvement Notice Nil Nil

6 HSE Violation Notice 1 Sub Contractors

7 Housekeeping 24/ Daily Sub Contractor

8 Accident/ Incident Nil Nil

9 Penalty Issued Nil Nil

10 Stop Work Order Nil Nil

HSE MONTHLY BRIEF REPORT FOR JULY 2013

Page 15: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

14

NO. ACCIDENT/INCIDENT PREVIOUS MONTH THIS MONTH

1 Fatality Nil Nil

2 Injuries Nil Nil

3 Occupational Disease Nil Nil

4Accident / Incident Involving

Machinery Nil Nil

5 Damage Loss of Property Nil Nil

6 Near Misses Nil Nil

TOTAL Nil Nil

SUMMARY OF SAFETY AND HEALTH ISSUES FOR JULY 2013

Page 16: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

15

UEMC Statistic of Safety Incident / Accident for the Month of July 2013

0 0 0 0 0 0 0 0 0 0 0 00

1

2

3

4

5

Jan '13 Feb '13 March '13 April '13 May '13 June '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec'13

QU

AN

TIT

Y

MONTH

Note : No accident/incident reported.

Page 17: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

16

UEMC Statistic of Environment Incident / Accident for the Month of July 2013

0 0 0 0 0 0 0 0 0 0 0 00

1

2

3

4

5

Jan '13 Feb '13 March '13 April '13 May '13 June '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec'13

QU

AN

TIT

Y

MONTH

Note : No accident/incident reported.

Page 18: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

17

Manpower Statistic

Item Description Quantity

1 Total Accident / Incident for the Month 0

2 Total Manpower 97

3 Total Man Days worked 2,328

4 Total Man Hours Worked 23,280

5 Man Hours worked (WLTI) from June 2013 to July 2013 38,640

6 Man Hours worked from June 2013 to July 2013 38,640

7 Number of Lost Time Injury (LTI) from Jan 2013 – June 2013 0

UEMC Safety & Health Performance – July 2013

0

50

100

Jan Mar May Jul Sep Nov

Total Manpower for Year 2013

Manpower

Page 19: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

18

ISSUES TO HIGHLIGHT

Status

Letter of Award Pending Issuance

Preliminary Drawings Pending Approval

Land Acquisition Pending from JKSB

Page 20: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

19

PROGRESS PHOTOGRAPH

Soil Investigation Works in progress

Page 21: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

20

Soil Investigation Works in progress

PROGRESS PHOTOGRAPH

Page 22: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

21

PROGRESS PHOTOGRAPH

Installation Temporary Cofferdam Caisson Works in progress

Page 23: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

22

Temporary Cofferdam Caisson Works completed at P23

PROGRESS PHOTOGRAPH

Page 24: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

23

PROGRESS PHOTOGRAPH

1st Drilling for Bored Piling Works in progress

Page 25: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

24

Bored Piling Works in progressSilos for Bored Piling Works

PROGRESS PHOTOGRAPH

Page 26: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

25

Construction of Hoarding at Casting Yard in progress

PROGRESS PHOTOGRAPH

Page 27: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

26

Cabin for site office casting yard Civil works – construction of plant foundation, EMS, Toilet, Lab and

Batching Plant in progress

PROGRESS PHOTOGRAPH

Page 28: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

27

PROGRESS PHOTOGRAPH

Remove Existing Median in progress

Page 29: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

28

Trial Hole for TNB cable at CH000 – CH525

PROGRESS PHOTOGRAPH

Page 30: Projek Menaiktaraf Bayan Lepas Expressway Dari Batu · PDF fileDari Batu Maung ke Jambatan Pulau Pinang. PROJECT ORGANIZATION CHART. 2 Employer JKSB Design and Build Contractor UEMB

29

THANK YOU