7/28/2019 Project_Status_Deck.pptx
1/6
PROJECT STATUS
SUMMARY
7/28/2019 Project_Status_Deck.pptx
2/6
Insert Date Presentation Title Goes Here
Sample Project Status/Schedule Summaries
In addition to managing a project plan in Microsoft Project, you may also wish to depict
the schedule or project status in a more summarized version for Steering Committee
meetings, team meetings, project kickoffs, weekly status reports, etc. These can be
tailored to a specific projects needs:
Sample 1: Executive View
Sample 2: Basic Status Dashboard A Sample 3: Basic Status Dashboard B
Sample 4: Excel (Week by Week View)
2
7/28/2019 Project_Status_Deck.pptx
3/6
Insert Date Presentation Title Goes Here
Project Status Summary Sample 1
Green Yellow RedOn track; will complete as planned Planned delivery at risk Will miss planned deliveryOriginally planned or completed activityKey Milestone Legend:
1. Kickoff Project2. Project Phase - TBD
3. Project Phase - TBD
Recent Accomplishments
TBD
TBD
TBD
Upcoming Key Activities
TBD
TBD
Scope:
TBD
TBD
TBD
Summary
Project Description: TBD
Actual/Estimated
Key Milestones
3
Nov29
Planned
2
Oct20
Sept25
Sept25
1
1
Sep 2011 Oct 2011 Nov 2011 Dec 2011 Jan 2012 Feb 2012 Mar 2012 Apr 2012
4. Project Phase - TBD5. Project Phase - TBD
6. Deployment Date - TBD
Aug 2011
6
Mar30
4 5
Jan29
Mar15
6
May1
3
Dec16
2
Nov1
4 5
Mar30
Apr15
Key Risks and Issues
TBD
TBD
Required Decisions & Guidance
TBD
TBD
Gray 3
7/28/2019 Project_Status_Deck.pptx
4/6
Insert Date Presentation Title Goes Here
Project Status Summary Sample 2
Summary of Recent Status: TBD
Activities Completed:
TBD TBD
TBD
Activities In Progress:
TBD
TBD
TBD
Issues/Risks:
TBD
TBD
TBD
Deliverable Owner/Signoff Status Planned/Revised Completion Date Comments
Key Deliverables/Milestones:
Project Name: Current Phase:
Project Start: Planned/Revised End:
Baseline Budget: % Budget Spent:
Overall Project Status As of:
4
7/28/2019 Project_Status_Deck.pptx
5/6
Insert Date Presentation Title Goes Here
Project Status Summary Sample 3
Activities Completed through Next Steps
Phase /Workstream TBD
TBD
TBD
TBD
Phase /Workstream TBD TBD
TBD
TBD
Phase /Workstream TBD
TBD
TBD
TBD
TBD
Phase /Workstream TBD
TBD
TBD
TBD
Risks/Key Decisions Required Budget
TBD
TBD
TBD
TBD
Overall Project Status As of:
5
7/28/2019 Project_Status_Deck.pptx
6/6
Insert Date Presentation Title Goes Here
Project Status Summary Sample 4
Activity by User Type Owner Notes Status10/21
10/28
11/4
11/11
11/18
11/25
12/2
12/9
12/16
12/23
12/30
1/6
1/13
1/20
1/27
2/3
2/10
2/17
2/24
Complete UAT Tom In Progress
Confirm list of HR users Tom Confi rm totals and types In Progress
Distribute 1st Comm Tom/Mary Not Started
Provide update at HRO meeting Tom Confirm date w/ Alfredo Not Started 11/17
Produce & Finalize Training Tom Coordinate with? Not Started
Publish to iLearn Mary Coordinate with? Not Started
Update ITS Materials Tom Coordinate with? Not Started
Distribute 2nd Comm Tom Confirm distro list Not Started
Conduct ILT for Power Users? TBD TBD/confirm who? Not Started
Confirm Support Model Tom Not Started
Distribute Final Comm TBD Confirm distro list Not Started Final
Close-Out Deployment to HR Users TBD Track issues /nex t s teps Not S tarted
Support Operational ITS Not Started
2011Project # 1 - Phase A
Human Resources Users
2012
6