Project_Status_Deck.pptx

Embed Size (px)

Citation preview

  • 7/28/2019 Project_Status_Deck.pptx

    1/6

    PROJECT STATUS

    SUMMARY

  • 7/28/2019 Project_Status_Deck.pptx

    2/6

    Insert Date Presentation Title Goes Here

    Sample Project Status/Schedule Summaries

    In addition to managing a project plan in Microsoft Project, you may also wish to depict

    the schedule or project status in a more summarized version for Steering Committee

    meetings, team meetings, project kickoffs, weekly status reports, etc. These can be

    tailored to a specific projects needs:

    Sample 1: Executive View

    Sample 2: Basic Status Dashboard A Sample 3: Basic Status Dashboard B

    Sample 4: Excel (Week by Week View)

    2

  • 7/28/2019 Project_Status_Deck.pptx

    3/6

    Insert Date Presentation Title Goes Here

    Project Status Summary Sample 1

    Green Yellow RedOn track; will complete as planned Planned delivery at risk Will miss planned deliveryOriginally planned or completed activityKey Milestone Legend:

    1. Kickoff Project2. Project Phase - TBD

    3. Project Phase - TBD

    Recent Accomplishments

    TBD

    TBD

    TBD

    Upcoming Key Activities

    TBD

    TBD

    Scope:

    TBD

    TBD

    TBD

    Summary

    Project Description: TBD

    Actual/Estimated

    Key Milestones

    3

    Nov29

    Planned

    2

    Oct20

    Sept25

    Sept25

    1

    1

    Sep 2011 Oct 2011 Nov 2011 Dec 2011 Jan 2012 Feb 2012 Mar 2012 Apr 2012

    4. Project Phase - TBD5. Project Phase - TBD

    6. Deployment Date - TBD

    Aug 2011

    6

    Mar30

    4 5

    Jan29

    Mar15

    6

    May1

    3

    Dec16

    2

    Nov1

    4 5

    Mar30

    Apr15

    Key Risks and Issues

    TBD

    TBD

    Required Decisions & Guidance

    TBD

    TBD

    Gray 3

  • 7/28/2019 Project_Status_Deck.pptx

    4/6

    Insert Date Presentation Title Goes Here

    Project Status Summary Sample 2

    Summary of Recent Status: TBD

    Activities Completed:

    TBD TBD

    TBD

    Activities In Progress:

    TBD

    TBD

    TBD

    Issues/Risks:

    TBD

    TBD

    TBD

    Deliverable Owner/Signoff Status Planned/Revised Completion Date Comments

    Key Deliverables/Milestones:

    Project Name: Current Phase:

    Project Start: Planned/Revised End:

    Baseline Budget: % Budget Spent:

    Overall Project Status As of:

    4

  • 7/28/2019 Project_Status_Deck.pptx

    5/6

    Insert Date Presentation Title Goes Here

    Project Status Summary Sample 3

    Activities Completed through Next Steps

    Phase /Workstream TBD

    TBD

    TBD

    TBD

    Phase /Workstream TBD TBD

    TBD

    TBD

    Phase /Workstream TBD

    TBD

    TBD

    TBD

    TBD

    Phase /Workstream TBD

    TBD

    TBD

    TBD

    Risks/Key Decisions Required Budget

    TBD

    TBD

    TBD

    TBD

    Overall Project Status As of:

    5

  • 7/28/2019 Project_Status_Deck.pptx

    6/6

    Insert Date Presentation Title Goes Here

    Project Status Summary Sample 4

    Activity by User Type Owner Notes Status10/21

    10/28

    11/4

    11/11

    11/18

    11/25

    12/2

    12/9

    12/16

    12/23

    12/30

    1/6

    1/13

    1/20

    1/27

    2/3

    2/10

    2/17

    2/24

    Complete UAT Tom In Progress

    Confirm list of HR users Tom Confi rm totals and types In Progress

    Distribute 1st Comm Tom/Mary Not Started

    Provide update at HRO meeting Tom Confirm date w/ Alfredo Not Started 11/17

    Produce & Finalize Training Tom Coordinate with? Not Started

    Publish to iLearn Mary Coordinate with? Not Started

    Update ITS Materials Tom Coordinate with? Not Started

    Distribute 2nd Comm Tom Confirm distro list Not Started

    Conduct ILT for Power Users? TBD TBD/confirm who? Not Started

    Confirm Support Model Tom Not Started

    Distribute Final Comm TBD Confirm distro list Not Started Final

    Close-Out Deployment to HR Users TBD Track issues /nex t s teps Not S tarted

    Support Operational ITS Not Started

    2011Project # 1 - Phase A

    Human Resources Users

    2012

    6