PROJECT RISKS (OIL & GAS DOWNSTREAM) A CLIENT’S PERSPECTIVE
Tan, Hooi-Hong - Project Manager
1
Use this area for cover image (height 6.5cm, width 8cm)
SHELL AT A GLANCE
Producing 2% of the world’s oil….
And 3% of the world’s gas
3.3 million barrels oil equivalent
produced daily
…around 48% of which is natural
gas
$20.5 billion income $30 billion Capex
Employing 93,000 people
Operating in 90+ countries
In 2010
2
CONFIDENTIAL
WHAT KEEPS US AWAKE AT NIGHT ?
1. HSE incidence
Process Safety - Lost of Primary Containment
Construction Safety - Fatality or Lost Time Incidence. Damage to Assets.
2. Quality issues from Vendors and EPC Contractor leading to ...
Process Safety incidents during and/or after start up.
Operability problems - not meeting investment premise on plant capacity
and/or availability after start up.
3
CONFIDENTIAL
HSSE: PROCESS SAFETY
Definition of Process Safety:
Shell Group Definition: Asset Integrity – Process Safety Management Standard (AI-PSM)
Process Safety: The management of hazards that can give rise to major accidents
involving the release of potentially dangerous materials, release of energy (such as
fire or explosion) or both. (Definition taken from the Baker Report)
Asset integrity: The ability of an asset to perform it’s intended function effectively
while safeguarding life and environment
GOAL: Keep the hydrocarbons in the pipeline!
4
CONFIDENTIAL
LEARNING FROM INCIDENTS IN THE INDUSTRY: YTD 2011
5
• Mont Belvieu, USA – explosion and fire at Enterprise Products petroleum plant due to pipeline failure.
• Fushun, China – more than 30 people were hurt in an explosion at a PetroChina Co.’s refinery complex.
• Pembroke, UK – four people were killed in an explosion and fire at Chevron oil refinery.
• Nairobi, Kenya – third party fatality and multiple injuries occurred as a result of explosion at Shell Kirinyaga Road Service Station, which is Shell NOV (non-operated venture).
• Gibraltar, UK – explosion of oil and water tank due to welding injured 14 people.
• Mexico City, Mexico – two were people killed in an explosion and fire at Pemex oil refinery.
• Nairobi, Kenya – more than 100 people killed in an explosion of pipeline operated by Kenya Pipeline Company.
Included for awareness and learning
Copyright of SEPL CONFIDENTIAL
SAFETY PERFORMANCE: YTD 2011
7
Long-term trend data illustrates improvements in safety performance. However, performance is showing signs of leveling-off in 2011, with LTIF and TRCF deteriorating slightly compared to 2010
TRCF LTIF FAR
TRCF and LTIF per million working hours; FAR per 100 million working hours
0
1
2
3
4
'02 '03 '04 '05 '06 '07 '08 '09 '10 '110
2
4
6
8
TRC
F/LT
IF
FAR
1.06 FAR (YTD 2011)
1.23 TRCF (Jan-Aug 2011)
0.35 LTIF (Jan-Aug 2011)
(Shell Operated Ventures, includes cases confirmed and under review)
CONFIDENTIAL
PROJECT RISKS (OIL & GAS DOWNSTREAM) – A CLIENT’S PERSPECTIVE
For this ECRI conference, I would like to focus on three aspects
that impact Project HSE and Quality risks.
1. Vendors’ Quality
2. EPC Contractor Factor
3. Contracting Models
8
CONFIDENTIAL
PROJECT RISKS – VENDORS’ QUALITY
Risks to Quality arising from :
Business model (not transparent to EPC and Client) for Engineering,
Procurement and Fabrication. Especially after mergers and acquisitions.
Complicated supply chain interfaces arising from using many sub-vendors and
Affiliates.
QA/QC gaps between engineering and fabrication (incl. sub-vendors)
Extensive out-sourcing and use of Low cost centers for engineering and
fabrication.
Issues
QA/QC and fabrication processes that are not aligned.
Underestimation of effort to manage interfaces and supply chain resulting in delivery
schedule and quality risks not recognised and/or appropriately assessed and mitigated.
Lack of awareness/concern wrt impact of poor quality on Process Safety and schedule.
Most vendors are not set up to manage integration complexities esp. package units
Examples : CV, Package units (compressor etc….) 9
Platform's DG trips
Vibration issues - rotating
GRVE, GRP
Pinhole Leaks
Vibration issues - static
Specialised contractor services
GTG's
Valves leaks
Cleaning (eng, plan/prep)
Seals failures
Simops/ PTW/MOC
Instrument functions
Rotating Equipments
Tightness
Preservation/Maintanence & Cleanliness
PAS, Process Cntrl
Operations line-up
Unexpected trips
Mechanical integrity
Engineering, Design
Safeguarding related
Vendor (package, equipment)
0 20 40 60 80 100 120 140 160 180comm. start-up
Vendor Quality Trends Overview from a Mega Project.(Jan 2010 – August 2011)
10
0
5
10
15
20
25
30
Oth
ers
Flo
wse
rve
NO
OR
TEN
ER
IKSE
N GE
AA
LBO
RG
EN
GIN
EER
ING
A/S
Ho
ney
wel
l
AB
B
Nat
ion
al O
ilwel
l Var
co (
NO
V)
FS E
LLIO
T
MA
NTU
RB
O
Siem
ens
Wea
ther
ford PSI
Cam
ero
n
Wei
r
Joh
n Z
ink
Po
np
ow
er
Sulz
er (
Ind
ia)
Au
dco
Ind
ia
Total number of incidents per vendor
Vendor Quality Trends Overview from a Mega Project - Vendor flaws during CSU
CONFIDENTIAL
PROJECT RISKS – EPC CONTRACTOR FACTOR
HSE management - No noticeable step change in performance.
Bias towards Construction HSE and light on Process Safety
Emphasis on “hard” HSE aspect (physical barriers - PPE, Procedures etc), and less on “soft”
aspect (communication, behaviour based approach skills to effect work culture change) in
HSE management
Its like starting all over again from project to project even with same EPC contractor.
Resource Skillpool management
Where do the HSE and QA/QC stand in relation to other “Core” EPC skillpool (e.g.
Construction Management , Engineering) in the EPC organisation?
Competency and Experience of HSE, E,P,C, Projects Control and Commissioning & SU staff :
Is there a structured Training scheme for EPC staff ?
Is there a structured competency assessment for EPC staff ?.
EPC staff competency assessment & screening process
Client’s process vs EPC contractor’s. Note : EPC contractor is an extension of Client.
Many risks are introduced with poor and/or unqualified staffing esp. in critical positions.
12
CONFIDENTIAL
PROJECT RISKS – EPC CONTRACTOR FACTOR
Project Team set up and Leadership.
Leadership
Are the PM, SM equipped/competent to manage soft issues ?
Cost and Schedule driven Mindset still persist ?
Roles and Responsibilities for EPC Team.
Are R&R made for all team members.? Maybe only for senior team members. ?
Are the R&R formalised. ?
Team dynamics
Are there due considerations given for culture, diversity etc.?
Poorly assembled team becomes ineffective/dysfuntional
Are there meaningful team building ? Or is it just “going through the motion” attitude ?.
Weak Leadership and ineffective/dysfunctional Team increases risks to HSE, Cost,
Schedule and Quality dramatically.
13
CONFIDENTIAL
COMPONENTS FOR TEAM DEVELOPMENT
Project Objective & Vision : • Project objectives developed
• Objectives clearly communicated to and understood by team members
Team Composition : • All functions that can influence project outcomes adequately represented on team
• Challenges of diversity and experience
Roles and Responsibilities : • Roles, responsibilities, and expectations clearly defined, agreed and aligned
Implementation Processes and Governance • Work process and governance in place for developing and executing projects
• Process understood by project team
14
CONFIDENTIAL
PROJECT RISKS – EPC CONTRACTOR FACTOR IMPACT ON OPERABILITY
Risk Management approach – LS sub-contracting mind set prevalent.
Risks are often transferred, instead of managed (assessed and mitigated).
Business model – To lower fixed cost
Preference for No Risk or very low risk contracts compromises accountability
mindset.
High Agency staff to Permanent staff ratio
Outsourcing /High dependence on Low cost centers for engineering.
Over simplistic approach toward oversight needed to secure quality in engineering and
adherence to schedule. Over promise (Cost benefit) and under deliver in quality and
schedule. More support needed than assumed.
Impact of poor engineering on Total installed cost - feed back loop ?
Reward is skewed to Cost and Schedule (incentives). Quality is compromised.
HSE and Operability risks increased arising from “workarounds” during construction to
secure schedule.
15
CONFIDENTIAL
PROJECT RISKS – EPC FACTOR IMPACT ON OPERABILITY
Retention of Lessons learned - Similar risks appearing again and again.
EPC contractors are not around to experience poor operability performance
and hence unlikely to have the feedback loop on LL.
What is the process to instill corporate memory for LL. ?
LL process too cumbersome and not always conducive to effect structural
changes ?
16
CONFIDENTIAL
ADJUSTED OPERABILITY
17
Pro
du
ctio
n
(Per
cen
t o
f N
amep
late
Cap
acit
y)
Better
Worse
Company
0
10
20
30
40
50
60
70
80
90
100
110
120
A B C D E F G H I J K L M N P Q R
Production Rates Adjusted for Non-Technical Losses
Adjusted Production
Mining
Chemicals
Refining
CONFIDENTIAL
PROJECT RISKS – CONTRACTING MODELS
Contracting Models influence and impact project outcomes in
HSE, Cost, Schedule and Quality (Operability).
1. Poorly designed Contracts, (with or without incentive scheme) drives
wrong behaviour. Example : Reward for achievement of Mechanical
Completion milestones without linkage to quality etc. Separate
incentives for senior managers ?
2. Lump Sum, Reimbursable etc, - Does it determine, EPC resource
allocation and Leadership ?
3. Does it drive the right behaviour for risks management. LS vs
Reimbursable
4. Does it promote and secure HSE, and Quality?
18
CONFIDENTIAL
MEGAPROJECT PERFORMANCE BY CONTRACT TYPES
19
Perc
enta
ge o
f Pro
ject
s In
Gro
up
Contract Type
0%
20%
40%
60%
80%
100%
EPC-LS EPC/EPCm Reimbursable Alliances Mixed
Success
Failure
CONFIDENTIAL
PERFORMANCE BY CONTRACT TYPE
20
-10%
10%
30%
50%
70%
EPC-LS EPC/EPCmReimbursable
Alliances Mixed
Cost Growth Schedule Slip Production Failures
Pe
rce
nta
ge
Contract Type
0%
CONFIDENTIAL
PROJECT RISKS – MITIGATIONS
Vendor Quality :
Broad base Enterprise Frame Agreements (EFA) for key Services, Bulks &
Equipment vendors based on risk assessment against quality, cost and schedule
performance ?
EFA with KPI for quality, cost and delivery. Benchmarking.
Utilise Client and EPC resources for inspection and expediting instead of 3rd
Parties .
EPC Contractor Factor :
Resource Skillpool management
Prescribe similar Client internal competency requirements for EPC resources. ?
Mandate HSE personnel for Project to be permanent staff instead of Agency staff.
Roles and Responsibilities and Alignment with Client
Mandate clear Roles and Responsibilities in EPC team as well as between Client and EPC
contractor.
21
CONFIDENTIAL
PROJECT RISKS – MITIGATIONS
Leadership and Team Building
Invest in a structured Team building and alignment programme ?.
Emphasise leadership and ownership at all levels. HSE and Quality standards are set here !
Risk Management Approach
Risks must not be transferred to the least able Party (IC). EPC contractor must be willing and
to assist IC – leadership and ownership !
EPC Contractor Business model
Selling services as against selling labour hours to deliver Projects of highest HSE standard
that meets Quality specified, within Cost and Schedule.
Use of Low Cost Centers :
Minimise Home Office/Back Office (LCC) interfaces ?. Allocate defined scope (e.g. by
discipline) to strengthen ownership.?
Support the LCC with the right level of Home Office resources at the LCC, not remotely.
Flawless Start Up and Sustained Operation post SU.
Engineer and build facilities that will start up flawlessly. Avoid mechanical completion driven
mentality.
22
CONFIDENTIAL
PROJECT RISKS – MITIGATIONS
Contracting Models.
Needs to promote the following :
1. Accountability for HSE, and Quality above Cost and Schedule.
Fees at risk for non performance of HSE and Quality. ?
Co-payment Incentive scheme for Quality. ?
2. Strive for collaborative working relationship between Client and EPC Contractor. Not always a given !
23
INDUSTRY EXPERIENCE- DELIVERY OF MAJOR PROJECTS
Characteristics of Major Projects that “Fail”:
Early promises
Schedule driven
No independent assurance of cost & schedule
Poor Front End Loading – Meeting Decision Gates Deadlines
“Largest ever” (delivery, installation, ops problems)
Too many firsts (>5) – too complex to handle
Insufficiently resourced
Poor (team) integration
Wrong contracting strategy (EPC, one off alliances)
HOW TO BE SUCCESSFUL
Characteristics of Major Projects that “Succeed”:
1. Avoid “the illusion of optimization” in early Assess & Select
2. Drive clarity on targets – “Tell me what you really, really want”
3. Front End Loading in line with project phase and complexity
4. Stability in concept & scope
5. Avoid to be schedule driven (in the definition phase); “Schedule driven
Mega projects are bound to fail”
6. Break the project up into distinct scope elements (major projects in
themselves) managed by separate project managers & contractors
7. Strong Owners (& Contractors) Team - Good Relations & Integrated Team
8. Repeat and standardize
9. Do not underestimate (Non Technical) Risks
10.Avoid “over-promising” in early phase
CONFIDENTIAL
PROJECT RISKS
Is there a compelling case to differentiate
EPC services to deliver Top Quartile Projects
(Cost & Schedule) meeting the GOAL ZERO
for HSE for facilities that meet Client’s
Investment Premise for safe and sustained
operation consistently ?
26
Copyright of SEPL CONFIDENTIAL
Now is NOT the time to be doing projects badly. Besides Luck and Devine interventions, the only factor between our performance now and Top Quartile project performance, is our collective Competence and Commitment to fundamentally change how we deliver Quality and HSE.
Project Risks – A Client’s Perspective.