Celanese Methanol Plant Clear Lake, Texas $160,000,000 Contract Value Worley Parsons 15 Month Duration 1,860,300 Workhours 148,000 LF of Piping –Spools 11,126 Pipe Welds -187,383 Weld Dia. Inches 1,022 Hydrostatic Test Packages Greenfield Project Turner Increased craft manpower from 300 to 900 over a 7-week period 110 pipe welders on the project Turner fabricated all piping with pipe sizes ranging up to 72” diameter Turner provided commissioning and start-up assistance Zero Lost Time Accidents Project Quick Facts

Project Quick Facts - Turner · PDF file148,000 LF of Piping –Spools 11,126 Pipe Welds -187,383 Weld Dia. Inches 1,022 Hydrostatic Test Packages • Greenfield Project

  • Upload
    vanlien

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Project Quick Facts - Turner  · PDF file148,000 LF of Piping –Spools 11,126 Pipe Welds -187,383 Weld Dia. Inches 1,022 Hydrostatic Test Packages • Greenfield Project

CelaneseMethanol Plant Clear Lake, Texas$160,000,000 Contract Value

Worley Parsons

15 Month Duration

1,860,300 Workhours

148,000 LF of Piping –Spools

11,126 Pipe Welds -187,383 Weld Dia. Inches

1,022 Hydrostatic Test Packages

• Greenfield Project

• Turner Increased craft manpower from 300 to 900 over a 7-week period

• 110 pipe welders on the project

• Turner fabricated all piping with pipe sizes ranging up to 72” diameter

• Turner provided commissioning and start-up assistance

Zero Lost Time Accidents