Project Plan Revised

Embed Size (px)

Citation preview

  • 7/27/2019 Project Plan Revised

    1/23

    IT Project Plan Workbook

    Page 1 10/15/2013

    PROJECT

    PLAN WORKBOOK

    Sections

    I. Project Profile

    II. Requirements Decision Making Model

    III. Project Plan

    IV. Project Plan Schedule

    V. Project Implementation Plan

    VI. Project Test Plan

    VII. Project Plan Recommendation Document

    VIII. Project Plan Group Review

    IX. Post Project Summary

  • 7/27/2019 Project Plan Revised

    2/23

    IT Project Plan Workbook

    Page 2 Revised: 10/15/2013

    PROFILE

    PREPARED BY: DATE:

    ProfilesI. User ProfileUsers Growth

    5 Doctors 4 New Doctors

    1 Office manager 4 Nurses

    1 Billing Manager 4 Interns

    10 Nurses

    5 Receptionists

    5 X-Ray Technicians

    10 Medical Assistants

    4 Office Supervisors4 Billing Clerks

    II. Usage/Applications ProfileWindows 98Novell 4.5

    SCO Unix

    Billing Management Application

    III. Geographic ProfileRosevilleSacramento

    Elk Grove

    Rancho CordovaFolsom

    IV. Hardware Profile

  • 7/27/2019 Project Plan Revised

    3/23

    IT Project Plan Workbook

    Page 3 Revised: 10/15/2013

    V. Special Requirements Profile

    REQUIREMENTS

    DECISION MAKING MODEL

    1. LIST REQUIREMENTS

    2. CLASSIFY REQUIREMENTS

    A. MUSTS

    B. WANTS

    3. SCORE REQUIREMENTS

    A. SCORE MUSTS

    B. SCORE WANTS

    4. DETERMINE RISK EVALUATION

    A. WHAT COULD GO WRONG IF MUST IS NOT MET?B. WHAT COULD GO WRONG IF IT IS NOT MET?

    5. DEFINITION OF TERMS

    REQUIREMENT: A GENERAL NEED OR CONDITION THAT MUST

    BE MET BY THE SYSTEM OR PRODUCT FOR IT

    TO BE ACCEPTABLE BY YOUR DEPARTMENT.

    MUST : THE REQUIREMENT IS MANDATORY FOR THE

    SYSTEM OR PRODUCT TO BE ACCEPTABLE.

    WANT : THE REQUIREMENT IS DESIRABLE BUT NOT

    MANDATORY FOR THE SYSTEM OR PRODUCT

    TO BE ACCEPTABLE.

    RISK DETERMINE THE IMPACT IF THE MUST OR IT T

    EVALUATION REQUIREMENT IS NOT MET BY THE PROJECT.

  • 7/27/2019 Project Plan Revised

    4/23

    IT Project Plan Workbook

    Page 4 Revised: 10/15/2013

    MUST REQUIREMENTS

    Please write all your MUST requirements in the first column. Score each requirement

    on a scale of 1 to 10. With 10 having the highest priority and 1 having the lowest priority.

    (1) Determine the level of importance for each requirement.

    (2) Then evaluate each score by the priority it has for your project.

    If you encounter two requirements which have equal importance and priority, then

    perform a risk evaluation. Ascertain the level of impact if this requirement was not met

    by the project and assign a risk evaluation score based on the same 1-10 scale.

    MUST REQUIREMENTS PRIORITY

    SCORE

    RISK

    EVALUATION

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    8.

    9.

    10.

    11.

    12.

    13.

    14.

  • 7/27/2019 Project Plan Revised

    5/23

    IT Project Plan Workbook

    Page 5 Revised: 10/15/2013

    15.

  • 7/27/2019 Project Plan Revised

    6/23

    IT Project Plan Workbook

    Page 6 Revised: 10/15/2013

    WANT REQUIREMENTS

    Please write all your WANT requirements in the first column. Score each requirement

    on a scale of 1 to 10. With 10 having the highest priority and 1 having the lowest priority.

    (1) Determine the level of importance for each requirement.

    (2) Then evaluate each score by the priority it has for your project.

    If you encounter two requirements which have equal importance and priority, then

    perform a risk evaluation. Ascertain the level of impact if this requirement was not met

    by the project and assign a risk evaluation score based on the same 1-10 scale.

    WANT REQUIREMENT PRIORITY

    SCORE

    RISK

    EVALUATION

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    8.

    9.

    10.

    11.

    12.

    13.

    14.

    15.

  • 7/27/2019 Project Plan Revised

    7/23

    IT Project Plan Workbook

    Page 7 Revised: 10/15/2013

    PROJECT PLAN

    PREPARED

    BY:

    DATE:

    I. ObjectivesA. System Objectives

    B. Infrastructure Objectives

    II. Project Scope

  • 7/27/2019 Project Plan Revised

    8/23

    IT Project Plan Workbook

    Page 8 Revised: 10/15/2013

    III. Organization

    A. Staffing Plan

    B. Customer Staffing Plan

    IV. Project Approach

    A. Project Assumptions

    B. Project Risks

  • 7/27/2019 Project Plan Revised

    9/23

    IT Project Plan Workbook

    Page 9 Revised: 10/15/2013

    PROJECT PLAN

    PROJECT

    PLAN:

    DATE:

    VI. BudgetA. Estimated Resources

    B. Cost for Each Phase

    C. Estimated Cost for Project

  • 7/27/2019 Project Plan Revised

    10/23

    IT Project Plan Workbook

    Page 10 Revised: 10/15/2013

    D. Facility Requirements

    VII. Schedule

    A. Phases of Work

    B. Estimated Phase Start and End Dates

    C. Time Line Schedule

  • 7/27/2019 Project Plan Revised

    11/23

    IT Project Plan Workbook

    Page 11 Revised: 10/15/2013

    PROJECT CHARTER

    PROJECT TITLE:

    A. PROJECT DESCRIPTIONThe purpose of this project is to investigate the reasons for the problem and propose asolution.

    B. PROJECT MANAGER ASSIGNED AND AUTHORITY LEVELList the person who has been given authority to lead the project. Define the level ofauthority granted such as: does he or she determine budget, schedule and staffing, etc.?

    C. OBJECTIVESThe project is to be completed no later than ____________. The budget is limited to no

    more than __________. The project will reduce expenditures by at least ______%. We

    expect that no more than _______ complaints will occur throughout the project from

    customers as we interrupt their day-to-day work.

    D. BUSINESS CASEWhy is the project being done? This project is being completed in order to prevent

    ___________________. We expect that improved customer satisfaction will increaserevenue to the company in the _____ year due to a decrease in ____________. We

    hope that the project will generate ideas on improving customer satisfaction while

    fixing this problem.

    E. PRODUCT DESCRIPTION/DELIVERABLESWhat are the specific deliverables wanted and what will be the end result of the project?1. A report that outlines what can be changed, how much each change will cost and the

    expected decrease in time it takes to ________ resulting from each change. The

    report will be presented to these departments: ____________, ______________,and _____________.

    2. A list of interactions with our customers necessary to complete the changes.3. A work breakdown structure, due within _____ weeks, that outlines the plan for

    accomplishing the project and a list of potential risks expected completing the

    project.

  • 7/27/2019 Project Plan Revised

    12/23

    IT Project Plan Workbook

    Page 12 Revised: 10/15/2013

    PROJECT CHARTERPREPARED BY: DATE:

    Project Title:A. PROJECT DESCRIPTION

    B. PROJECT MANAGER ASSIGNED AND AUTHORITY LEVEL

    C. PROJECT OBJECTIVES

    D. BUSINESS CASE

    E. PRODUCT DESCRIPTION/DEL IVERABLES

    F. SIGNED AND APPROVED BY:

    SENIOR MANAGEMENT:

  • 7/27/2019 Project Plan Revised

    13/23

    IT Project Plan Workbook

    Page 13 Revised: 10/15/2013

    PROJECT PLANSCHEDULE

    Description:

    Project Schedule:

    Activity Start Date Completion Date Status

  • 7/27/2019 Project Plan Revised

    14/23

    IT Project Plan Workbook

    Page 14 Revised: 10/15/2013

    PROJECT

    IMPLEMENTATION

    PLAN

    I. Implementation Plan Overview/Strategy

    II. Implementation Plan Task List

    Task

    #Implementation Plan

    Task Description

    Resource

    Required

    days

    Responsible

    PersonStart

    Date

    mm/dd/y

    y

    End

    Date

    mm/dd/yy

  • 7/27/2019 Project Plan Revised

    15/23

    IT Project Plan Workbook

    Page 15 Revised: 10/15/2013

    CONTINGENCY

    DE-INSTALLATION

    PLAN

    III. Contingency De-Installation Plan Overview/Strategy

    IV. Contingency De-Installation Plan Task List

    Tas

    k #Contingency/De-Installation Plan

    Task Description

    Resource

    Required

    days

    Responsible

    PersonStart

    Date

    mm/dd/yy

    End

    Date

    mm/dd/yy

  • 7/27/2019 Project Plan Revised

    16/23

    IT Project Plan Workbook

    Page 16 Revised: 10/15/2013

    PROJECT

    TEST PLANUAT Unit

    Type of Testing:

    PROJECT NAME: TEST CYCLE NO:

    PROGRAM NAME:

    PREPARED BY: DATE:

    TESTED BY: DATE:

    Test

    Case NoTest Conditions Test Procedures Expected Results Date

    Tested

    mm/dd

    Pass/

    Fail

    P/F

  • 7/27/2019 Project Plan Revised

    17/23

    IT Project Plan Workbook

    Page 17 Revised: 10/15/2013

    PROJECT PLAN

    RECOMMENDATION DOCUMENT

    PREPARED BY: DATE:

    Definition SectionI. Statement of Opportunity

    II. Scope of Requirements

    A. High Level RequirementsB. Affected/Unaffected Products, Services, or Operations

    III. Solution CriteriaA. Summary of Solution CriteriaB. Detailed Evaluation

    VI. Recommendation

  • 7/27/2019 Project Plan Revised

    18/23

    IT Project Plan Workbook

    Page 18 Revised: 10/15/2013

    II. Requirements Scope

    A. High Level Requirements

    ReqmtNo.

    Requirement Statement[Statement must be clearly defined, complete, and

    verifiable]

    Validation Method[Description of what must occur to demonstrate

    that the requirement has been met]

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    1920

  • 7/27/2019 Project Plan Revised

    19/23

    IT Project Plan Workbook

    Page 19 Revised: 10/15/2013

    B. Affected/Unaffected Products, Services, Operations, and Organizations

    Category A/U * Description (If Affected (A)

    Functions/Processes:

    User Departments:

    Subsystems:

    * A/U: EnterAfor Affected andUfor Unaffected.

  • 7/27/2019 Project Plan Revised

    20/23

    IT Project Plan Workbook

    Page 20 Revised: 10/15/2013

    III. Solution Criteria

    Solution:

    Description:

    Advantages:

    Disadvantages:

    Preliminary Estimate: [of cost and effort required]

  • 7/27/2019 Project Plan Revised

    21/23

    IT Project Plan Workbook

    Page 21 Revised: 10/15/2013

    VI. Recommendation

    [Describe in detail the preferred solution for meeting the customer's requirementsincluding a preliminary estimate for cost, resources, and schedule.]

  • 7/27/2019 Project Plan Revised

    22/23

    IT Project Plan Workbook

    Page 22 Revised: 10/15/2013

    PROJECT PLAN

    GROUP REVIEW

    Project Name:

    Date of Review:

    Role Participants Name Comments/Recommendations

    Facilitator

    Recorder

    Reviewer 1

    Reviewer 2

    Reviewer 3

    Reviewer 4

    Reviewer 5

  • 7/27/2019 Project Plan Revised

    23/23

    IT Project Plan Workbook

    PROJECT PLAN

    POST PROJECT SUMMARY

    PREPARED BY: DATE:

    Comments/Recommendations

    I.

    II.

    III.

    IV.

    V.