109
PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL SUBMITTAL SPECIFICATIONS HEADQUARTERS AIR ARMAMENT CENTER EGLIN AIR FORCE BASE, FLORIDA REPLACE HALON SYSTEMS, FSD-2 BLDG 13A, 374, & 1358 EGLIN A.F.B., FLORIDA 25 JUNE 2010 DIRECTORATE OF CIVIL ENGINEERING (96 CEG/CEPDW) PETERSON ENGINEERING, INC. 75 SOUTH "F" STREET PENSACOLA, FL 32502 (850) 434-0513 (850) 434-9674 FAX [email protected] JOB NO. 08067

PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN

FINAL SUBMITTAL

SPECIFICATIONS

HEADQUARTERS AIR ARMAMENT CENTER EGLIN AIR FORCE BASE, FLORIDA REPLACE HALON SYSTEMS, FSD-2 BLDG 13A, 374, & 1358 EGLIN A.F.B., FLORIDA 25 JUNE 2010 DIRECTORATE OF CIVIL ENGINEERING (96 CEG/CEPDW) PETERSON ENGINEERING, INC. 75 SOUTH "F" STREET PENSACOLA, FL 32502 (850) 434-0513 (850) 434-9674 FAX

[email protected] JOB NO. 08067

Page 2: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

REPLACE HALON SYSTEMS, FSD-2 BLDG 13A, 374, & 1358 FTFA 94-1196 EGLIN AFB, FL SPECIFICATIONS

TABLE OF CONTENTS SECTION NO. TITLE PAGE NO=S 01010 STATEMENT OF WORK 01010-1 - 01010-3 01011 GENERAL CONDITIONS 01011-1 - 01011-10 01340 SHOP DRAWINGS, PRODUCT DATA,

AND SAMPLES 01340-1 - 01340-3 01400 QUALITY CONTROL 01400-1 - 01400-3 01500 ENVIRONMENTAL PROTECTION 01500-1 - 01500-4 01540 AFFIRMATIVE PROCUREMENT 01540-1 – 01540-14 02050 DEMOLITION AND REMOVAL 02050-1 - 02050-2 02222 EXCAVATION AND BACKFILL 02222-1 - 02222-9 02602 EXTERIOR WATER LINES 02602-1 - 02602-6 15010 MECHANICAL GENERAL REQUIREMENTS 15010-1 - 15010-11 15325 WET PIPE SPRINKLER SYSTEM 15325-1 - 15325-6 15329 GASEOUS CLEAN-AGENT FIRE SUPPRESSION SYSTEM 15329-1 – 15329-19 16050 BASIC ELECTRICAL MATERIALS

AND METHODS 16050-1 - 16050-5

16402 INTERIOR DISTRIBUTION SYSTEM 16402-1 - 16402-11

END OF TABLE OF CONTENTS

Page 3: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01010-1

SECTION 01010 STATEMENT OF WORK PART 1 GENERAL 1.1 GENERAL INTENTION: It is the declared and acknowledged

intention and meaning to remove the Halon 1301 Fire Suppression Systems in the following buildings. An overhead wet pipe system and gaseous system shall be installed for:

Building Number 13A 18A 374 9621 1358 12723

1.2 GENERAL DESCRIPTION: In general, the work will consist of

the following:

a. Removal of the halon cylinders and piping. Halon to be shipped to office Government storage site off-base.

b. Rework the existing halon control panels will be

removed.

c. Provide overhead and/or sidewall wet pipe sprinkler protection to these respective areas. Hazard to be ordinary hazard group 1.

d. Where areas are shielded (either copper or steel), the

integrity of those spaces shall be maintained. New penetrations shall be RF tested.

e. All new sprinkler systems flow and tamper switches

shall be connected to the building fire alarm.

f. Work in all facilities will be accomplished in approved phases or by sprinkler zones per an approved schedule. The contractor will complete work in one zone prior to moving to next zone to work. All materials require for work in a zone shall be on site before starting any work in that zone. The buildings are high security and contractor will be greatly restricted in accessing these facilities. The Contractor shall provide

Page 4: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01010-2

escorts.

g. The contractor shall remove the existing suspended ceilings as required to install the sprinkler piping above the ceiling. The contractor shall reinstall the suspended ceiling after completion of work. Any ceiling tile or grid damaged shall be replaced.

h. The contractor shall be responsible for all work

related to connecting to and interface with the existing fire alarm and controls. This includes any programming or replacement of E-Prom or other components as required providing complete working systems.

i. The existing fire alarm panels in Building 374 shall

remain. j. All areas of Buildings 374 and 13A are “secured

facilities”. The Contractor is responsible for employing security personnel to supply escort services for the duration of this project. Security escorts must be provided in sufficient numbers to escort Contractor employees at all times (maximum of 6 employees per security guard) and in all work areas of the facility. One security escort shall monitor each work group where all personnel can be observed by escort. Additional escorts shall be provided to escort individual workers who travel throughout the building for errands, personal hygiene, or any other purposes. In summary, all workers shall be monitored by a security escort at all times. The security firm supplying escort services must be licensed/bonded and its personnel meet government required clearance criteria (i.e., cleared to “Secret” level). Personnel providing escort services must be identified in appropriate submittals to the Contracting Officer.

1.3 LOCATION: The work is located at Eglin Air Force Base, FL.

The exact location of the facility will be indicated by the Contracting Officer.

1.4 SITE INSPECTION: Prospective bidders are expected to visit

the areas of work and verify all conditions and dimensions.

Page 5: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01010-3

All areas of work require the site visit to be escorted. 1.5 RECORD DRAWINGS: The contractor shall maintain at the job

site a set of full size contract drawings, marking them in red to show all variations between the construction actually provided and that indicated or specified in the contract documents, including buried or concealed construction. Where a choice of materials or method is permitted herein or where variations in scope or character of work from that of the original contract are authorized, the drawings shall be marked to define the construction actually provided. The representations of such changes shall conform to standard drafting practice and shall include such supplementary notes, legends, and details as necessary to clearly portray the as-built construction. On completion of the work, the set of marked-up drawings shall be delivered to the Contracting Officer, and shall be subject to his approval before acceptance. The set shall be protected and be in good clean condition when submitted.

PART 2 PRODUCTS (Not Used) PART 3 EXECUTION (Not Used)

END OF SECTION

Page 6: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-1

SECTION 01011 GENERAL CONDITIONS (Rev-1) PART 1 GENERAL 1.1 GENERAL A. The work to be performed under this Contract shall consist of

furnishing all supervision, tools, equipment, materials, supplies, manufactured articles, all transportation, services, including fuel, power, water, essential communications, for the performance of all work. Materials and services not expressly shown or called for in the Contract Documents which are necessary for the complete and proper construction of the work shall be performed, furnished and installed by the Contractor.

B. The Contractor shall perform all work required in accordance

with the Contract Documents and subject to the terms and conditions of the Contract, complete and ready to use.

1.2 MATERIALS A. All materials, products or devices incorporated in this

project shall be new and unused, and shall be the products of reliable manufacturers who, unless otherwise specified, are regularly engaged in the manufacture of such material or devices.

1.3 STORM PROTECTION A. Should warnings of wind of gale force or stronger be issued,

the contractor shall take every practicable precaution to minimize danger to persons, to the work, and to adjacent property. These precautions shall include closing all openings, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

1.4 INTERFERENCE WITH STATION OPERATIONS A. Permission to interrupt any station utility, communication,

operational or traffic service or pattern shall be requested in writing at least 10 working days prior to the date of the desired interruption. The contractor shall receive approval in writing from the Contracting Officer before the requested interruption may be put into effect.

1.5 CHEMICAL LATRINE A. The Contractor shall provide, at no additional cost to the

Page 7: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-2

government, a minimum of one chemical latrine, and additional latrines at one per 12 workmen. The latrine(s) will be at the job site for the duration of the contract performance period. The latrine(s) shall be serviced as often as required for sanitary conditions but in no case shall servicing be less than twice per week. Servicing shall comply with all applicable federal, state and local laws, ordinances and regulations. The latrine waste shall be disposed of legally off government lands. The latrine will not be required at bldg 374.

1.6 PUBLICATIONS A. Publications referred to in this specification may include

reference dates that do not reflect the current status of the publication. Unless otherwise stated in the specification (this will be accomplished by stating "Compliance is required with this publication versus any future versions") the current publication is the applicable publication. Where the specification further refers to deviations from these publications, these deviations will be applied to the current publication.

1.7 WORK CLEARANCE A. The contractor shall be responsible for obtaining and having

filled out form AF 103, Base Civil Engineering Work Clearance Request. No site work shall be done until this form is completed.

1.8 SAFETY A. The contractor shall perform all excavation according to

Occupational Safety and Health Administration 1926 Subpart P. B. The contractor shall follow all applicable portions of the US

Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1.

C. CODE OF FEDERAL REGULATIONS (CFR)

29 CFR 1910.147, Control of Hazardous Energy (Lock Out/Tag Out)

1.9 SCHEDULING A. The contractor shall submit a schedule of proposed work to the

Contracting Officer. The schedule shall show the proposed activities, including locations where work is planned, and planned affect on the utilities and traffic flow. All work sequencing and phasing is subject to the approval of the Contracting Officer. Mission requirements will take priority

Page 8: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-3

over contract work. 1.10 REFERENCES A. The publications listed throughout the specifications form a

part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

1.11 CONFORMANCE WITH AGENCY REQUIREMENTS A. Where materials or equipment are specified to conform to

requirements of the Underwriters' Laboratories, Inc., or other agency, institute, codes, councils or regulatory bodies, the contractor shall submit proof of such conformance. The label or listing of the specified agency will be acceptable evidence. In lieu of the label or listing, the contractor may submit a written certificate from any approved, nationally recognized testing organization adequately equipped and competent to perform such services, stating that the items have been tested and that the units conform to the requirements, including methods of testing, of the specified agency. Where equipment is specified to conform to requirements of the ASME Boiler and Pressure Vessel Code, the design, fabrication, and installation shall conform to the code in every respect and bear the ASME Stamp.

1.12 CAPACITIES A. Capacities of all equipment and material shall be not less

than those indicated, nor exceed maximum values which are stated in the specifications or shown on the drawings.

1.13 SUBMITTAL OF MATERIALS AND EQUIPMENT A. Within 14 days after notice to proceed and before purchasing

any materials or equipment, the contractor shall submit to the Contracting Officer for approval, in five bound copies, a list of materials he proposes for the work. Items to be submitted include, but are not limited to, the items listed in each individual section. Partial submittals will not be acceptable and will be returned without review. Submittals shall include the manufacturer's names, trade name, catalog model or number, nameplate data, size, layout dimensions, capacity, project specification and paragraph reference, applicable Federal, Military, industry, and technical society publication references, and other information necessary to establish contract compliance of each item the contractor proposes to furnish.

1. Shop Drawings. Drawings shall be a minimum of 8.5 inches

by 11 inches in size, except as specified otherwise.

Page 9: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-4

2. Manufacturer's Data. Submittals for each manufactured item shall be manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves, and catalog cuts.

3. Cataloged Products. Materials and equipment shall be

cataloged products of manufacturers regularly engaged in production of such materials or equipment and shall be manufacturer's latest design that complies with the specification requirements. Materials and equipment shall duplicate items that have been in satisfactory commercial or industrial use at least 2 years prior to bid opening. Where two or more items of the same class of equipment are required, these items shall be products of a single manufacturer.

4. Submittal Organization. The submittal shall be organized

in the same order as the specification sections. The cut sheets shall be marked with equipment number which is shown on the drawings or name for something general such as piping. The submittal sheets shall document the piece of equipment meets the proformance requirements of the contract documents. Note: Unmarked submittals will be rejected without review.

5. Samples. The samples shall be such as to illustrate the

functional and aesthetic characteristics of the product.

6. Submittal Approval. The approval of a submittal does not relieve the product from meeting all requirements of the contract documents. The contractor must note on the submittal any exceptions or else the product can be rejected at any stage of the project and the contractor must remove the product and provide one meeting the requirements of the contract documents at no cost to the Government.

1.14 NAMEPLATES A. Each major item of equipment shall have the manufacturer's

name, address, serial and model numbers, and date of manufacture, on a plate securely attached to the item.

1.15 VERIFICATION OF DIMENSIONS A. The contractor shall visit the premises to thoroughly

familiarize himself with all details of the work and working conditions and verify all dimensions in the field, and shall advise the Contracting Officer of any discrepancy before performing any work. The contractor shall be specifically responsible for the coordination and proper relation of his work to other structures and to the work of all other trades.

Page 10: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-5

1.16 DRAWINGS A. Because of the scale of the drawings, it is not possible to

indicate all offsets, fittings, and accessories that are required. The contractor shall carefully investigate the site and finish conditions affecting his work and he shall furnish fittings, offsets, transitions, unions, etc., as may be required to meet such conditions at no additional cost to the Government.

1.17 CUTTING AND REPAIRING A. The work shall be carefully laid out in advance and no

excessive cutting of construction will be permitted. Damage to building, piping, wiring, or equipment as a result of cutting for installation shall be repaired by mechanics skilled in the trade involved at no additional expense to the Government.

1.18 MANUFACTURER'S RECOMMENDATIONS A. Where installation procedures or any part thereof are required

to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations shall be furnished to the Contracting Officer prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.

1.19 PAINTING A. At the completion of all work, all equipment on this project

shall be checked for damage, and any factory finished paint that has been damaged shall be repaired to match the adjacent areas. Any metal item that has been provided which has not been painted or otherwise protected shall be painted with primer and final coatings as recommended by the paint manufacturer for the particular application.

1.20 DELIVERY AND STORAGE A. Equipment and materials shall be carefully handled, properly

stored, and adequately protected to prevent damage before and during installation, in accordance with the manufacturer's recommendations and as approved by the Contracting Officer. Damaged or defective items shall be replaced. Equipment will not be delivered to the job site unless it can be stored inside the building or in an enclosed area such as a trailer.

1.21 LOCKOUT OF ENERGY SOURCES A. Provide appropriate lockout devices for energy isolating

Page 11: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-6

valves and for machines or other equipment to prevent unexpected start-up or release of stored electrical, mechanical, hydraulic, pneumatic, thermal, chemical, or other energy in accordance with 29 CFR 1910.147. Lockout devices for valves shall provide a means of attachment to which, or through which, a lock can be affixed or shall have a locking mechanism built into it so that the valve cannot be moved from the lockout position until the lock is removed.

1.22 CONTRACTOR PREPARED AS-BUILT DRAWINGS

A. General: The Government will furnish the Contractor on CD ROM one electronic set of solicitation drawing files and any amendments for use in preparation of as-built drawings by the Contractor. Copies of the drawings will be the responsibility of the Contractor. The as-built drawings shall be a record of the construction as installed and completed by the Contractor. They shall include all deviations, modifications, or changes from the contract drawings, however minor, that were incorporated in the work, all additional work not appearing on the contract drawings, and all changes which are made after final inspection of the contract work. In the event the Contractor accomplishes additional work which changes the as-built condition of the facility after submission of the as-built drawings, the Contractor shall furnish revised and/or additional drawings as required to depict as-built conditions. The requirements for these additional drawings will be the same as for the as-built drawings included in the original submittal.

B. Red line as-built drawings: The Contractor shall have on his

staff, personnel to mark up a set of paper copy construction drawings to show the as-built conditions. These as-built marked copies shall be kept current and available on the job site at all times. All changes from the contract plans which are made in the work or additional information which might be uncovered in the course of construction shall be accurately and neatly recorded, as the events occur, by means of details and notes. The Contractor shall call attention to entries by redlining areas affected. The red line as-built will be jointly inspected for accuracy and completeness by the Contracting Officer's representative and a responsible representative of the Contractor prior to submittal of each request for payment. The Contracting Officer's approval of the current status of the as-built drawings shall be a prerequisite to the Contracting

Page 12: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-7

Officer's approval of request for progress payment and request for final payment under the contract. The drawings shall show the following information, but not be limited thereto: (1) The location and description of any utility lines or

other installations of any kind or description known to exist within the construction area. The location includes dimensions to permanent features.

(2) The location and dimensions of any changes within the

building or structures. (3) Correct grade or alignment of roads, structures or

utilities if any changes were made from contract plans. (4) Changes in details of design or additional information

obtained from working drawings specified to be prepared and/or furnished by the Contractor including but not limited to fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment foundations, etc.(

(5) All changes or modifications which result from the

final inspection.

(6) Options: Where contract drawings or specifications allow options, only the option selected for construction shall be shown on the as-built drawings.

(7) Extensions of Design: Shop Drawings such as structural

fabrication and erection drawings and fire alarm systems that will require extensive redrafting effort in order to create a electronic set will not be required to be incorporated into the electronic set. They will be included as an Appendix to the paper copy set.

C. Submittal of as-built drawings for review and approval: The Contractor shall participate in monthly review meetings with the Contracting Officer's Representative to show the progress made the preceding month and make all required changes. At time of final construction inspection, the Contractor shall submit one copy of the red lined as-built drawings to the Contracting Officer's Representative for

Page 13: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-8

review and approval. The as-built drawings shall be certified as to their correctness by the signature of an authorized representative of the Contractor. Upon Government approval of the Contractor's redlined copy of the as-built drawings, the Contractor shall prepare and provide two electronic sets of as-built drawings by incorporating the red line marked up notations on the construction drawings into the electronic set of solicitation drawings and amendments. In addition to the electronic sets of as-built drawings which shall be submitted on a CD-ROM, the Contractor shall also submit a full size set of as-built drawings on mylar. Submittals are to be to the Contracting Officer's Representative not later than ten (10) calendar days after project completion date.

D. Final Drawing Format.

(1) The solicitation drawing files and any amendments

thereto will be furnished to the Contractor in electronic format. The solicitation drawing files have been prepared in MicroStation and/or AutoCAD format. The drawing file indicates the format which the drawing was developed. The As Built drawings shall reflect all changes made during construction as indicated by the red line marked up notations on the construction drawings. Revisions/redrafting shall match the font styles,sizes, and formats; line weights/thicknesses and styles/types; and all other drafting elements used on the solicitation drawing/amendments. All elements must be incorporated into each as-built drawing file; the use of reference files shall not be permitted. In addition, the Contractor will include the building number issued by Eglin AFB in the title block of the Final As-Built Drawings.

(2) As-built drawings will be submitted in a version of

AutoCAD that is coordinated with 96 CEG drafting section at the time of submission. The as-built DWG files shall have no reference files attached as all shall be bound into the file to make one AutoCAD DWG file, which also shall be purged and created with standard AutoCAD pen table. Scaled drawings should provide a bar scale and shall be in feet not meters. Contractor shall provide 1 hard copy of as-built drawings on Mylar on an Arch D sheet size and 2 CD’s in AutoCAD and PDF. Final As-Built

Page 14: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-9

drawings will include the assigned building number in the title block.

a. AutoCAD drawings shall have correct geometry:

1. Segmented lines and arcs are to be made continuous and free of self overlapping sections, thus decreasing files size and increasing efficiency within the AutoCAD platform.

2. All AutoCAD data shall be free of topological errors such as slivers, undershoots, overshoots dangles, overlaps, intersections, etc.

3. Area features such as building footprints, parking lots, roadways, and airfield pavements shall be true polyline polygons. Adjacent polygons will not have gaps or overlaps.

b. AutoCAD drawings shall be checked for correct spatial projection to one of the following: 1. North American Datum 1983 Florida State Plane North FIPS 0903 Feet (AutoCAD Code FL83-NF) 2. Universal Transverse Mercator 1984, Zone 16 North (AutoCAD Code UTM84-16N) c. Any Building Information Models (BIM) developed for a project will be supplied in a Model Archive as part of the final as-built submittal consisting of two sets of files: 1. The first set shall be a collection of individual Models as received from the Model Element Author(s). 2. The second set of files will consist of the aggregate of those individual Models in a format suitable for archiving and viewing. The aggregate model will also be submitted in a DWG file format.

(3) All revisions made to the solicitation drawings and/or

amendment drawings to reflect changes made during construction shall be flagged in a numbered triangle and shall have the revision block completed as follows. The entry in the description column of the revision block shall read "AS-BUILT". The date of the revision and one approving initial from a responsible person within the Contractor's Firm shall also be included in the revision

Page 15: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01011-10

block. Above the drawing title block the drawing will be labeled in bold letters "AS-BUILT".The Contractor shall also furnish a revised index of drawings to match the actual design drawings. The drawing title blocks shall be in a uniform format to match the requirements as specified in the Design Manual.

(4) The two electronic sets of as-built drawing files shall

be submitted in AutoCAD format and two electronic sets of as built drawings shall be submitted in pdf.

(5) The hard copy reproducible set of as-built drawings

shall be submitted unbound on mylar. The drawings shall be full size.

E. Payment: No separate payment will be made for the as-built drawings required under this contract, and all costs in connection there-with will be considered a subsidiary obligation of the Contract. PART 2 PRODUCTS (Not Used) PART 3 EXECUTION (Not Used) END OF SECTION

Page 16: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01340-1

SECTION 01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.1 GENERAL A. The contractor shall submit the certain items, information and

tests for approval. All submittals shall be submitted with AF Form 3000, Material Approval Form. Shop drawings and certificates shall be submitted prior to fabrication and commencement of work insofar as possible. All items requiring approval shall be submitted within 14 days after the Notice to Proceed date of the contract. Submit all related items of a section or items that are dependent on each other at the same time for coordination. In lieu of the Underwriter's inspection label, the contractor may submit a certified test report from any nationally recognized testing agency acceptable to the Contracting Officer and adequately equipped and competent to perform such services. Unless otherwise specified, costs of all items requiring approval shall be at the contractor's expense. Where tests by an independent testing laboratory are required, the original copies of test reports shall be sent by the testing laboratory directly to the Contracting Officer.

B. The items to be submitted have been summarized for convenience

on the attached Air Force Form 66. Additional submittals may be required if stated in specifications.

Page 17: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01400-1

SECTION 01400 QUALITY CONTROL PART 1 GENERAL 1.1 REVIEW AT PLACE OF MANUFACTURE A. Unless otherwise specified, all products, materials, and

equipment may be subject to review by the Contracting Officer at the place of manufacture.

B. The presence of the Contracting Officer at the place of

manufacture, however, shall not relieve the Contractor of the responsibility for furnishing products, materials, and equipment which comply with all requirements of the Contract Documents. Compliance is a duty of the Contractor, and said duty shall not be avoided by any act on the part of the Contracting Officer.

1.2 SAMPLING AND TESTING A. Unless otherwise specified, all sampling and testing shall be

in accordance with the methods prescribed in the current standards of the ASTM or any other standard referenced, as applicable to the class and nature of the article or materials considered; however, the Contracting Officer reserves the right to use any generally-accepted system of sampling and testing which will insure that the quality of the workmanship is in full accord with the Contract Documents.

1.3 SITE INVESTIGATION AND CONTROL A. The Contractor shall verify all dimensions in the field and

shall check field conditions continuously during construction. The Contractor shall be solely responsible for any inaccuracies built into the work due to their failure to comply with this requirement.

B. The Contractor shall inspect the work site conditions and

shall report in writing to the Contracting Officer any conditions which will prevent proper completion of the work. Failure to report any such conditions shall constitute acceptance of all work site conditions, and any required removal, repair, or replacement caused by unsuitable conditions shall be performed by the Contractor at no cost to the Government.

1.4 REVIEW AND TESTING A. The Contractor shall allow the Contracting Officer ample time

and opportunity for review and testing of materials to be used in the work. The Contractor shall advise the Contracting

Page 18: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01400-2

Officer within 5 days upon placing orders for materials so that arrangements may be made, if desired, for review before shipment from the place of manufacture. The Contractor shall at all times furnish the Contracting Officer, facilities including labor, and allow proper time for reviewing and testing materials, equipment, and workmanship. The Contractor must anticipate that possible delays may occur in the execution of their work due to the necessity of materials and equipment being reviewed and accepted for use.

B. The Government will bear the costs of all tests, reviews, or

investigations undertaken by the order of the Contracting Officer for the purpose of determining conformance with the Contract Documents if such tests, reviews, or investigations are not specifically required by the Contract Documents, and if conformance is ascertained thereby. Whenever non conformance is determined by the Contracting Officer as a result of such tests, reviews, or investigations, the Contractor shall bear the full costs of any additional tests and investigations, which are ordered by the Contracting Officer to ascertain subsequent conformance with the Contract Documents.

1.5 RIGHT OF REJECTION A. The Contracting Officer, shall have the right, at all times

and places, to reject any articles or materials to be furnished hereunder which, in any respect, fail to meet the requirements of the Contract Documents, regardless of whether the defects in such articles or materials are detected at the point of manufacture or after completion of the work at the site. If the Contracting Officer, through an oversight or otherwise, has accepted materials or work which is defective or which is contrary to the Contract Documents, such materials, no matter in what stage or condition of manufacture, delivery, or erection, may be subsequently rejected by the Contracting Officer.

B. The Contractor shall promptly remove rejected articles or

materials from the site of the work after notification of rejection. All costs of removal and replacement of rejected articles or materials as specified herein shall be borne by the Contractor.

1.6 WEATHER CONDITIONS A. Work that may be affected by inclement weather shall be

suspended until proper conditions prevail. In the event of impending storms, the Contractor shall take necessary precautions to protect all work, materials and equipment from exposure.

Page 19: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01400-3

1.7 FIRE PROTECTION A. The Contractor shall take all necessary precautions to prevent

fires at or adjacent to the work, including its own equipment and trailers. Fire extinguisher stations shall be provided throughout the work area to meet OSHA regulations. Additional fire extinguishers shall be provided if required by Contracting Officer. The Contractor shall obtain a Hot Work Permit from the Fire Department for all welding, cutting or other work involving an open flame or producing sparks.

PART 2 PRODUCTS (Not Used) PART 3 EXECUTION (Not Used) END OF SECTION

Page 20: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01500-1

SECTION 01500 ENVIRONMENTAL PROTECTION PART 1 GENERAL 1.1 SCOPE A. This section covers environmental protection in general.

Specific environmental requirements are included in other appropriate sections of the specifications. Additional general environmental requirements are included in the General Provisions of the contract. The provisions of this section are in addition to the aforementioned requirements. Where the general provisions of this section conflict with specific requirements elsewhere, the specific requirements shall control.

1.2 GENERAL A. The contractor shall comply with all applicable local, state,

federal, and Air Force environmental regulations. These items include, but are not limited to, the following:

1. Vehicles and other powered equipment will meet all

applicable air quality regulations for emissions. Equipment shall be mechanically sound and have all seals, grease rings, and other containment systems in place to prevent leakage. Drip pans shall be maintained such that overflow and spills do not occur. Associated waste shall be handled in accordance with all applicable regulations. There shall be no activities for equipment maintenance including oil changes, filter replacements, or hydraulic equipment repair performed on base without prior approval by the Contracting Officer.

2. All solid waste shall be collected and disposed of on a

daily basis. There shall be no accumulation of solid waste unless properly containerized or put within a fenced area to prevent material being blown about by the wind. No liquids shall be put into base dumpsters. This includes paints, oils, chemicals, compressed gas, or pesticides, and other similar materials. Dried paint cans will be allowed in dumpsters only if such can contain no lead, chromium or cadmium, or other hazardous materials.

3. All hazardous wastes such as sandblast media, chlorinated

solvents, paint, paint thinners, cleaners, and fuels will be labeled and an inventory management system will be initiated to ensure timely removal and proper disposal. No on-base disposal will be allowed.

Page 21: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01500-2

a. All drums must be labeled with a hazardous waste label. The label shall include the proper DOT shipping name, UN or NA, EPA waste number, generator information, and accumulation start date. The label shall be placed on the side of the drum.

b. All drums used to store hazardous waste shall be

nonleaking and safe to handle. Drums that are rusty, dented, or leaking will be overpacked. Drums and/or overpacks shall be provided by the Contractor. All drums shall be DOT approved containers.

c. Storage of drums will be approved by the Hazardous

Waste Branch of the Environmental Management Directorate (AFDTC/EMP) prior to the generation of hazardous waste. The Contractor shall document inspection of drums for leaks on a daily basis or if not working in the area daily, then a weekly inspection will suffice. A drum shall be disposed within 90 days of the first drop in the container. A copy of the inspection checklist will be forwarded to EMP every Friday.

d. Hazardous waste drums shall be stored at an

approved accumulation site. A sign identifying the site as an accumulation site with two points of contact will be placed in a highly visible position.

e. Hazardous Waste transportation and disposal shall

be coordinated through EMP. The transporters and disposal facilities will be approved by the EMP prior to their use. Manifests will be signed only by the EMP.

4. Hazardous Materials. The Contractor shall submit to the

Contracting Officer a list of all hazardous materials to be brought onto Eglin AFB property prior to the onset of any work. The list shall include all paints, solvents, POL products, pesticides, etc to be used during the duration of the contract. All newly identified requirements for hazardous materials shall be coordinated with and approved by the Compliance Division of the Environmental Management Directorate (EMC) prior to bringing the material on Eglin property.

5. Fuel storage will be limited to 500 gallons and shall be

contained in a government approved portable tank. Siting of the tanks shall be approved by the Contracting Officer.

Page 22: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01500-3

6. Storage of oils, greases, chemicals, or other liquids shall require a fully contained facility for spill prevention and security. A minimum of 40 pounds of absorbent material per 44 gallons of chemical/oil/grease will be on hand for spill control.

7. All spills shall immediately be called to 911 and then

called to the Eglin Consolidated Command Post (882-3278). Information as to spill location, type of material, and estimated time when the spill occurred shall be provided. The Contractor shall ensure appropriate personnel protective equipment (PPE) is available to take care of spill cleanup and handling of residues of materials under their control.

8. Spray painting is not allowed inside buildings.

9. Contractor sites (i.e. trailer and storage sites) shall

be properly maintained at all times. Repair of all damage due to improper erosion control shall be the responsibility of the Contractor. Release of the site by the Contractor will be accompanied by a final Contractor site review, at which time site deficiencies will be noted. The Contractor shall have 14 calendar days (beyond the contract completion date if necessary) to correct all deficiencies. The contract completion date will not be changed due to any of the required site review actions.

10. Asbestos: If the Contractor encounters unforeseen site

conditions including, but not limited to suspected asbestos containing materials during the performance of this contract, the Contractor shall cease operations in the suspect area, immediately evacuate all personnel, and notify the Contracting Officer and the construction inspector. Samples will be taken and analyzed by the Government.

11. The Release of ODCs is Prohibited: All refrigerants will

be recycled or recovered in accordance with EPA standards. The recycle/recovery equipment must be certified by an approved equipment testing organization to meet the standards in FR 82.158 (b) or (d), equipment pursuant to FR 82.36 (a), or equipment manufactured before Nov 15, 1993, that meets the standards in 82.158 (c), (e), or (g). In addition the equipment operator or technician must meet the certification requirements for Universal Technician as required by EPA Regulation 40 CFR, Part 82, Subpart F.

12. Banned Ozone Depleting Chemicals: All equipment using

Page 23: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01500-4

any Class 1 ozone depleting chemicals (ODCs) for a fire suppressant, refrigerant or solvent is banned from acquisition or use unless it has a Air Force waiver. This includes, but is not limited to systems using Class 1 ODCs such as halon 1211, halon 1301, R-11 (trichloromonofluoromethane), R-12 (dichlorodifluoromethane), R-113 (trichlorotrifluoroethane), R-114 (dichloroodifluoromethane), R-115 (chloropentafluorethane), and all azeotropic mixtures containing controlled chemicals such as CFC 500, 501, 502, and 504.

13. Ground Contamination: If suspected contamination is

encountered during excavation activities (often indicated by unusual colors or odors), the Contractor shall contact the Contracting Officer immediately.

14. Environmental Training: Specific Contractor personnel

may be required to attend Hazard Communications (HazCom) Training and Hazard Waste Seminars held bi-annually at Eglin AFB at no expense to the Contractor. If the Contractor has a HazCom Program in place and can provide proof of such program, then the HazCom Training can be waived. Proof of an existing HazCom Program shall be provided to the environmental management representative at the pre-construction meeting and updated annually.

1.3 SUBMITTALS A. The contractor shall submit a list of all hazardous materials

as indicated in paragraph 1.2.A.4. PART 2 PRODUCTS (Not Used) PART 3 EXECUTION (Not Used) END OF SECTION

Page 24: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-1

SECTION 01540

AFFIRMATIVE PROCUREMENT PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. The publications shall be the most current issue.

AIR FORCE CENTER FOR ENVIRONMENTAL EXCELLENCE (AFCEE)

AF APP Air Force Affirmative Procurement

Plan

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA) CPG 1 Comprehensive Procurement Guidelines

ETL 00-1 EPA Guideline Items in Construction

and Other Civil Engineering Specifications

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 247 Comprehensive Procurement Guideline

for Products Containing Recovered Material

48 CFR FAR 23.402 Code of Federal Acquistion

Regulations, Subpart 23.4 - Use of Recovered Materials

5 USC 102 Government Organization and

Employees, Part I - The Agencies Generally, Chapter 1 - Organization, Section 102. Military Departments

5 USC 105 Government Organization and

Employees, Part I - The Agencies Generally, Chapter 1 - Organization, Section 105. Executive Agency

42 USC 6903 The Public Health and Welfare,

Chapter 82 - Solid Waste Disposal, Sec. 6903. Definitions

Page 25: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-2

42 USC 13102 The Public Health and Welfare,

Chapter 133 - Pollution Prevention, Sec. 13102. Definitions

RCRA Sec. 6002 The Resource Conservation and

Recovery Act (RCRA) (42 USC 6962)

OFFICE OF THE FEDERAL ENVIRONMENTAL EXECUTIVE (OFEE) EO 13101 Greening the Government through Waste

Prevention, Recycling, and Federal Acquisition

OFFICE OF FEDERAL PROCUREMENT POLICY

OFPP 92-4 Policy Letter 92-4, Procurement of

Environmentally Sound and Energy-Efficient Products and Services

1.2 RELATED SPECIFICATION SECTIONS: Section 01010 - GENERAL REQUIREMENTS

1.3 AFFIRMATIVE PROCUREMENT AND POLLUTION PREVENTION

a. Affirmative Procurement is a mandatory component of the Air Force pollution prevention program. The AF Installation Pollution Prevention Program Guide includes this goal for Affirmative Procurement: "100% of all products purchased each year in each of U.S. EPA's 'Guideline Item' categories shall contain recycled materials meeting U.S. EPA's Guideline Criteria."

b. Currently, reporting of affirmative procurement

purchases is limited to contracts having a total value greater than $100,000 which includes the purchase of any amount of U.S. EPA-designated items.

c. This document contains guidelines for implementing the

RCRA, EO, DOD, and Air Force requirements. 1.4 INTENT

a. The intent of this section is to increase the awareness of all contractors as to the availability of products manufactured from or that contain recycled materials, thereby increasing the use of these products in the construction of this project.

Page 26: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-3

b. The various sections of the specifications contain

references to products to be used in the construction of this project. The listed product may or may not be manufactured from or contain recycled materials. Therefore all contractor(s), subcontractors, equipment suppliers and material suppliers are responsible for compliance with this specification, particularly paragraph 1.9 and those items/products listed in paragraph 2.1. Recycled products shall be used wherever possible subject to the exemptions as per paragraph 1.9.

c. Substitution of recycled materials or recycled products

for specified products are subject to the provisions of paragraph 1.5 Submittals.

1.5 SUBMITTALS The following shall be submitted in accordance with Section 01330, SUBMITTAL PROCEDURES:

SD-03 Product Data

Product Sources and Information

Submit manufacturer's material specifications, installation instructions, physical characteristics

SD-07 Certificates

Product Sources and Information

Certify that products meet or exceed the specified requirements.

1.6 RECYCLED OR RECOVERED PRODUCTS Those construction materials identified in paragraph 2.1 at the end of this section.

1.7 QUALITY ASSURANCE 1.7.1 Manufacturer Companies specializing in the manufacture of products that comply with the requirements of this section with a minimum of three (3) years documented experience.

Page 27: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-4

1.8 DEFINITIONS

a. AFFIRMATIVE PROCUREMENT: The purchase of environmentally preferable products manufactured from recycled and reclaimed materials.

b. ACQUISITION: The acquiring by contract with appropriated

funds for supplies or services (including construction) by and for the use of the Federal Government through purchase or lease, whether the supplies or services are already in existence or must be created, developed, demonstrated, and evaluated. Acquisition begins at the point when agency needs are established and includes the description of requirements to satisfy agency needs, solicitation and selection of sources, award of contracts, contract financing, contract performance, contract administration, and those technical and management functions directly related to the process of fulfilling agency needs by contract.

c. CONTRACTOR (S): The prime contractor, subcontractors,

material suppliers, and equipment suppliers who provide the products that will be used in the construction of this project.

d. ENVIRONMENTALLY PREFERABLE: Products or services having

a lesser or reduced effect on human health and the environment when compared to competing products or services, serving the same purpose. This comparison may consider raw materials acquisition, production, manufacturing, packing, distribution, reuse, operation, maintenance, or product or service disposal. (EO 13101)

e. EPA DESIGNATED ITEM: An item that is or can be made with

recovered material; that is listed by the Environmental Protection Agency (EPA) in a procurement guideline (40 CFR 247); and for which EPA has advised purchasing recommendations in a related Recovered materials Advisory Notice (RMAN). (48 CFR FAR 23.402)

f. EXECUTIVE AGENCY OR AGENCY: An executive agency as

defined in 5 USC 105. For the purpose of this order, military departments, as defined in 5 USC 102 are covered under the auspices of the Department of Defense.

g. POLLUTION PREVENTION: Source reduction as defined in the

Pollution Prevention Act of 1990 (42 USC 13102), and other practices that reduce or eliminate the creation of pollutants through (a) increased efficiency in the use

Page 28: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-5

of raw materials, energy, water, or other resources; or (b) protection of natural resources by conservation.

h. PRODUCT: Materials and equipment that will be used in

the construction of this project.

i. POSTCONSUMER MATERIAL: A material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. "Postconsumer material" is a part of the broader category of "recovered material".

j. PROCUREMENT: The purchase and providing of products to

be used in the construction of this project.

k. RECOVERED MATERIALS: Waste materials and by-products which have been recovered or diverted from solid waste, but such term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process. (EO 13101, 42 USC 6903 (19) and 48 CFR FAR 23.402)

l. RECYCLABILITY: The ability of a product or material to

be recovered from or otherwise diverted from the solid waste stream for the purpose of recycling. (EO 13101)

m. RECYCLING: The series of activities, including

collection, separation, and processing by which products or other materials are recovered from the solid waste steam for use in form of raw materials in the manufacture of new products other than fuel for producing heat or power by combustion. (EO 13101)

n. RECYCLED MATERIAL: A material utilized in place of raw

or virgin material in product manufacturing consisting of materials derived from postconsumer waste, industrial scrap, material derived from agricultural wastes, and other items, all of which can be used in new product manufacturer. (CPG 1, ETL 00-1 & OFPP 92-4)

o. RECYCLED PRODUCT: A recycled product is one made

completely or partially from waste materials or by-products recovered or diverted from the solid waste stream.

p. SOLID WASTE: Garbage, refuse, sludges and other

discarded materials including those from industrial, commercial, and agricultural operations, and from community activities. This excludes solids or dissolved

Page 29: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-6

materials in domestic sewage or other significant pollutants in water resources, such as silt, dissolved or suspended solids in industrial waste water effluents, dissolved materials in irrigation return flow, etc. (CPG 1 and ETL 00-1)

q. SPECIFICATION (S): A clear and accurate description of

the technical requirements for materials, products, or services including the minimum requirement for materials' quality and construction and any equipment necessary for an acceptable product. In general, specifications are in the form of written descriptions, drawings, prints, commercial designations, industry standards, and other descriptive references.

r. UNREASONABLE PRICE: If the cost of the recycled content

product exceeds the cost of a non-recycled item, the Air Force considers the cost to be unreasonable. (AF APP)

s. VERIFICATION: Procedures used by procuring agencies to

confirm both vendor estimates and certifications of the percentages of recovered materials contained in the products supplied to them or to be used in the performance of a contract. (CPG 1 and ETL 00-1)

t. WASTE PREVENTION: Any change in the design,

manufacturing, purchase, or use of materials or products (including packaging) to reduce their amount or toxicity before they are discarded. Waste prevention also refers to the reuse of products or materials.

u. WASTE REDUCTION: Preventing or decreasing the amount of

waste being generated through waste prevention, recycling, or purchasing recycled and environmentally preferable products.

1.9 EXEMPTIONS U.S. EPA recommends minimum content levels for those items listed at paragraph 1.10. The minimum content levels can be found at www.epa.gov/cpg. These levels are mandatory unless one of the following exemptions applies. RCRA Sec. 6002 provides the following exemptions from the requirement to purchase EPA-designated items:

a. The product is not available from a sufficient number of

sources to maintain a satisfactory level of competition (i.e., available from two or more sources).

Page 30: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-7

b. The product is not available within a reasonable period of time.

c. The product does not meet the performance standards in

applicable specifications or fails to meet reasonable performance standards of the procuring agency.

d. The product is not available at a reasonable price. For

Air Force purposes, "unreasonable price" is defined as follows: If the price of the recycled-content product exceeds the cost of a non-recycled item, then the price is considered unreasonable.

1.10 U.S. EPA-DESIGNATED ITEMS The 54 U.S. EPA-designated items are listed below. Not all of these materials may be required in the construction of this project. Please refer to the drawings and specifications.

1.10.1 Paper Products Item 1: All paper and paper products, excluding building and

construction paper grades. 1.10.2 Vehicular Products Item 2: Lubricating oils containing re-refined oil, including

engine lubricating oils, hydraulic fluids, and gear oils, but excluding marine and aviation oils.

Item 3: Tires, excluding airplane tires. Item 4: Reclaimed engine coolants, excluding coolants used in

non-vehicular applications. 1.10.3 Construction Products Item 5: Building insulation products. Item 6: Structural fiberboard products for applications other

than building insulation. Item 7: Laminated paperboard products for applications other

than building insulation. Item 8: Cement and concrete, including products such as pipe

and block, containing fly ash.

Page 31: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-8

Item 9: Cement and concrete, including concrete products such as pipe and block, containing ground-granulated blast furnace (GGBF) slag.

Item 10: Carpet made of polyester fiber for use in low- and

medium-wear applications. Item 11: Floor tiles containing recovered rubber or plastic. Item 12: Patio blocks containing recovered rubber or plastic. Item 25: Shower and restroom dividers/partitions containing

recovered steel or plastic. Item 26: Reprocessed and consolidated latex paint for specific

uses. Item 37: Carpet cushion. Item 38: Flowable fill. Item 39: Railroad grade crossing surfaces. 1.10.4 Transportation Products Item 13: Traffic barricades used in controlling or restricting

vehicular traffic. Item 14: Traffic cones used in controlling or restricting

vehicular traffic. Item 27: Parking stops. Item 28: Channelizers used as temporary traffic control

devices. Item 29: Delineators used as temporary traffic control devices. Item 30: Flexible delineators used as temporary traffic control

devices. 1.10.5 Park And Recreation Products Item 15: Playground surfaces containing recovered rubber or

plastic. Item 16: Running tracks containing recovered rubber or plastic. Item 31: Plastic fencing.

Page 32: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-9

Item 40: Park benches and picnic tables. Item 41: Playground equipment. 1.10.6 Landscaping Products Item 17: Hydraulic mulch products containing recovered paper or

recovered wood. Item 18: Compost made from yard trimmings, leaves, and/or grass

clippings. Item 32: Garden and soaker hoses containing recovered rubber or

plastic. Item 33: Lawn and garden edging containing recovered rubber or

plastic. Item 42: Food waste compost. Item 43: Plastic lumber landscaping timbers and posts. 1.10.7 Non-Paper Office Products Item 19: Office recycling containers. Item 20: Office waste receptacles. Item 16: Plastic desktop accessories. Item 22: Toner cartridges. Item 23: Binders. Item 24: Plastic trash bags. Item 34: Printer ribbons (re-inked ribbons or re-inking

equipment/service for ribbons). Item 35: Plastic envelops. Item 44: Solid plastic binders. Item 45: Plastic clipboards. Item 46: Plastic file folders. Item 47: Plastic clip portfolios.

Page 33: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-10

Item 48: Plastic presentation folders. 1.10.8 Miscellaneous Products Item 36: Pallets. Item 49: Sorbents. Item 50: Industrial drums. Item 51: Awards and plaques. Item 52: Mats. Item 53: Signage, including supports and posts. Item 54: Manual grade strapping. 1.11 APPLICABILITY

a. These requirements apply to all contractors employed in the construction of this project.

b. Please direct all questions regarding the plan to the

contracting officer or designated representative. PART 2 PRODUCTS 2.1 PARTIAL LIST OF PRODUCT SOURCES AND INFORMATION 2.1.1 General Data

a. Comprehensive Procurement Guidelines, epa.gov/cpg

b. Environmental Building News, www.ebuild.com/

c. Certified Forest Products Council, www.cerifiedwood.org/

d. Wiley Series in Sustainable Design, www.wiley.com//

e. The Carpet and Rug Institute, www.carpet-rug.com//

f. Information, McGraw-Hill, [email protected]/

g. Florida Directory of Recycled Product Vendors, www.2.dep.state.fl.us/waste/programs/rbac/downloads/rbac_dir.pd

Page 34: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-11

h. Oikos Green Building Source, News, searchable products data base, library, www.oikos.com/

i. Green Design Network, News, publications, databases,

www.greendesign.net

j. Green Works Recycled Content7 Product Guide, detailed vendors directory, www.metrokc.gov/greenworks/recycontent.htm>

2.1.2 Division 03, Concrete

a. GranCem, granulated blast-furnace slag, www.grancem.com/

b. Syndesis, cement-based, pre-cast product workable with wood tools, www.syndesisinc.com/

2.1.3 Division 04, Masonry

a. Heble Building Systems, autoclaved aerated concrete blocks, www.heble.com/

b. Ytong Florida Ltd., autoclaved aerated concrete blocks,

www.ytong-usa.com/ 2.1.4 Division 06, Wood & Plastics

a. Avonite, solid surfacing, www.avonite.com/

b. Chemical Specialties, wood treatment, www.treatedwood.com/

c. Homasote Company, structural fiberboard,

www.homasote.com/

d. Isobar, fiberboard composed of straw fibers and non-toxic resins, www.isoboard.com/

e. Trashiest Mac Millan, engineered wood products,

www.homasote.com/ 2.1.5 Division 07, Thermal & Moisture Protection

a. Duro-Last Roofing, recycled PVC walkway pads, 1-800-2480280

b. Johns Manville, Insulation products, www.jm.com/

Page 35: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-12

c. Majestic Skylines, rubber-based slate-look roofing for steep roofs, www.majesticskylines.com/

d. Owens-Corning, insulation products,

www.owenscorning.com/ 2.1.6 Division 08, Doors & Windows

a. Marvin Window & Door, windows, some meeting "Energy Star Label", www.marvin.com/

b. Pella, energy efficient windows, www.pella.com/

2.1.7 Division 09, Finishes

a. Armstrong World Industries, Inc.-Flooring Systems, www.armstrong-floors.com/

b. Armstrong World Industries, Inc.-Ceiling Systems,

www.ceilings.com/

c. Benjamin Moore & Co., VOC free acrylic interior latex paint, www.benjaminmoore.com/

d. CanFibre Group Ltd., all-green medium-density

fiberboard, www.canfibre.com/

e. Chemrex Inc., low-e interior paint, www.chemrex.com/

f. Collins & Aikman Floor coverings, carpet with 100% post-consumer backing, www.powerbond.com/

g. DesignTex, Inc., polyester panel fabric made from 100%

PET fiber, www.dtex.com/

h. Dodge-Regupol, Inc., 100% recycled rubber-flooring, www.regupol.com/

i. Eco-sensitive modular tile, vinyl tile with 100%

recycled carpet-backing, www.powerbond.com/

j. Environmental Stone Products, stone manufactured from 100% recycled glass, www.environmentalstone.com/

k. Glidden: residential interior latex paints 100% free of

VOC, www.icipaintstores.com/

l. Homasote Inc., sound barrier, www.homasote.com/

Page 36: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-13

m. Isobar Enterprises, Inc. panel made from wheat straw and non-toxic resins, 1-503-2427345

n. Marley-Flexco Co., flooring made from 95% recycled truck

and bus tires, www.marleyflexco.com/

o. The Mat Factory, Inc., interlocking roll-up tiles made from 100% postconsumer tire rubber and PVC plastic from electric cable covers, 1-949-6453122

p. Permafirm Pad Co., carpet pads made from almost 100%

recycled content, 1-800-3446977

q. Sherwin Williams, VOC compliant paints and enamels, www.sherwin.com/

r. SierraPine Limited, formaldehyde-free particleboard and

medium density fiberboard containing recycled/recovered wood fiber, www.sierrapine.com/

s. Summittville Tiles, impervious porcelain tiles using

feldspar tailings, www.summitville.com/

t. Tectum, natural-fiber acoustical ceiling and wall panels, www.tectum.com/

u. Tiles with natural fibers, tiles made of a bio-alloy

material and natural fibers, www.maderatile.com/

v. USG Interiors, Inc., synthetic gypsum board, www.usg.com/

w. Decorative Architectural Tiles, floor, counter & wall

tile made from 100 % postconsumer glass, 1-808-8857812

x. Forbo, linoleum-flooring utilizing renewable resources, www.forbo.com/

2.1.8 Division 10, Specialties

a. The Access Store, modular ramping system made from 100% recycled rubber, www.accessstore.com/

b. BP Solar, photovoltaic modules and systems,

www.bp.com/bpsolar/index

c. Mecho Shade Systems, interior shadecloths, www.mechoshade.com/

Page 37: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

01540-14

d. R Control, structural insulated panel (SIP), www.mechoshade.com/

2.1.9 Division 12, Furnishings

a. Guilford of Maine, fabric from 100% recycled materials, www.terratex.com/

b. Phenix Biocomposites, tabletops made from soy based

products free of petrochemicals, 1-800-3248187

c. Safe Solutions, LLC, furniture manufactured from waste wood, 1-970-247-3333

2.1.10 Division 16, Electrical

a. Advance Transformer Company, linear reactor ballast, www.advancetransformer.com/

b. Artemide Inc., energy efficient cold-cathode lighting,

www.artemide.com/

c. Edison Price Lighting, track mounted metal-halide PAR 30 &38 lamps, 1-212-5216995

d. Leviton Manufacturing Corporation, Inc., occupancy

sensors, www.leviton.com/

e. Phillips Lighting, energy efficient compact fluorescent lamps, www.phillips.com/lighting

f. Osram Sylvania, mercury-free lamps and energy efficient

fluorescent lamps, www.osramsylvania.com/

g. Sensor Switch, lighting control occupancy sensors, www.sensorswitch.com/

h. Venture Lighting, pulse-start high performance lamp and

ballast system, www.venturelighting.com/ PART 3 EXECUTION Not used.

END OF SECTION

Page 38: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02050-1

SECTION 02050 DEMOLITION AND REMOVAL PART 1 GENERAL 1.1 SCOPE A. This section covers demolition and removal, complete. 1.2 APPLICABLE PUBLICATIONS A. The publications listed below form a part of this

specification to the extent referenced. The publications are referred to in the text by the basic designation only.

1. Code of Federal Regulations (CFR).

40 CFR 260-268, Hazardous Waste Management.

2. Florida Administrative Code (FAC).

Rule 62-730, Hazardous Waste.

1.3 REQUIREMENTS A. The work includes demolition or removal of all construction

indicated or specified. Do not begin demolition until authorization is received from the Contracting Officer. Remove rubbish and debris from the station daily. Store materials that cannot be removed daily in areas specified by the Contracting Officer. Contractor shall dispose of all hazardous waste in accordance with all applicable Federal and State laws including but not limited to 40 CFR 260-268 and FAC Rule 62.730.

1.4 OPERATION OF AREA DURING CONSTRUCTION A. During working hours and after hours, all construction

equipment and materials shall be parked and stored to cause minimum disruption to normal operations at the site.

PART 2 PRODUCTS (Not Used) PART 3 EXECUTION 3.1 PROTECTION OF EXISTING WORK A. Utilities: Preserve in operating condition, unless otherwise

noted, and protect active utilities traversing project site. Existing utility locations shall be determined by contractor before commencement of work. Where removal of existing

Page 39: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02050-2

utilities is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary service or connections for electrical and mechanical utilities.

B. Structures: All existing building surfaces, equipment and

furnishings not to be removed shall be protected by the contractor from damage during work under this contract. Damage to such items due to work under this contract shall be promptly repaired by the contractor at his own expense. Contractor shall provide all required covers, shoring, bracing, and supports.

C. Dust Control: Take appropriate action to check the spread of

dust to occupied building areas and to avoid the creation of a nuisance in the surrounding area. Do not use water if it results in hazardous or objectionable conditions, such as ice, flooding, or pollution. Comply with all dust regulations imposed by local air pollution agencies.

3.2 REMOVAL OF EXISTING MATERIALS/EQUIPMENT A. Where noted or indicated on the drawings, or specified herein,

portions of existing mechanical and electrical materials and equipment shall be removed. All materials indicated to be removed by the contractor and not required to be reinstalled, including scrap, shall become the property of the contractor, (except where indicated on the drawings) and shall be promptly removed from Eglin reservation and legally disposed of at the contractor's expense. Reference the contract drawings for additional information on disposition of particular equipment. Existing items required to be removed temporarily in order to properly install new work shall be replaced upon completion of new work. Temporary bracing, supports and shoring shall be installed to protect and support existing work and equipment as required to complete the project.

3.3 GENERAL A. Where new work adjoins existing, the new work shall abut or

tie into the existing construction in accordance with standard building construction practices.

3.4 PATCHING AND REPAIRING A. Existing finishes and structures indicated to remain that are

damaged during construction shall be patched and finished to match adjacent surfaces unless otherwise specified herein.

END OF SECTION

Page 40: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-1

SECTION 02222 EXCAVATION AND BACKFILL PART 1 GENERAL 1.1 SCOPE A. Furnish labor, materials, equipment, and incidentals necessary

to perform all excavation, backfill, fill, grading and slope protection required to complete the additions to the existing water systems. The work shall include: pits and pipe, all bedding, backfilling, fill and required borrow; grading and disposal of surplus and unsuitable materials; and all related work such as sheeting, bracing and dewatering operations.

1.2 QUALITY ASSURANCE A. Codes and Standards: Excavation and backfill for utility

systems shall be performed in compliance with applicable codes, standards and requirements of governing authorities having jurisdiction in the area.

1.3 JOB CONDITIONS A. The Contractor shall locate, protect, shore, brace, support

and maintain all underground pipes, conduits, drains and other underground construction and utilities uncovered or otherwise affected by the construction work performed. All replacement of such underground construction, utilities or parts thereof shall be made with new materials conforming to the requirements of these specifications or, if not specified, as approved by the contracting officer at no cost to the Government.

1.4 REFERENCES A. ASTM D 1556 - Density and Unit Weight of Soil in Place by the

Sand-Cone Method B. ASTM D 1557 - Laboratory Compaction Characteristics of Soil

Using Modified Effort (56,000 Ft-lbf/cu. ft.) C. ASTM D 2922 - Density of Soil and Soil-Aggretate in Place by

Nuclear Methods

Page 41: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-2

1.5 SUBMITTALS A. The Contractor shall submit information and samples to the

Contracting Officer for review as specified herein in accordance with Section 15010, "Mechanical General Requirements". The information shall include:

1. A detailed description of dewatering method chosen and

sequence of dewatering operations.

2. List of materials and equipment to be used.

3. Drawings of the sheeting system and design computations shall be submitted to the Contracting Officer; however, the review of these Drawings shall in no way relieve the Contractor of the responsibility to provide a safe and satisfactory sheeting and shoring system. Sheeting and shoring shall be designed by the Contractor, and the proposed design shall be sealed by a Professional Engineer registered in the State of Florida. If the Contracting Officer is of the opinion that at any point sufficient or proper supports have not been provided, he may request additional supports put in at the Contractor's expense.

PART 2 PRODUCTS 2.1 MATERIALS A. Pipe Bedding: Sand for bedding shall be a dry screened sand.

Sand shall be graded sand with 100 percent passing 1 3/8-inch sieve and not more than 5 percent passing a No. 200 sieve. All pipe bedding material shall be new. Existing pipe bedding material may not be used.

B. Backfill: Backfill material shall not be expansive nor have

high organic content, shall be free of debris, lumps and clods. Not more than 10% of weight shall be finer than 74 micron (No. 200) U. S. Standard Sieve. Broken concrete shall not be used. Fill material containing limerock shall have sufficient sand to fill the voids in the limerock. No stones or rocks larger than 3-inches in diameter will be permitted in any backfill. Backfill material placed within 1-foot of piping and appurtenances or in the upper 6-inches of all backfill and fills shall not contain any stones or rocks

Page 42: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-3

larger than 1-inch in diameter. Existing backfill material may be used, only if it meets the above mentioned requirements.

PART 3 EXECUTION 3.1 GENERAL A. All excavation, backfill and grading necessary to complete the

work specified herein shall be made by the Contractor and the cost thereof shall be included in the contract price. Material shall be furnished as required from off-site sources and hauled to the site. The Contractor shall take all necessary precautions to maintain the work area in a safe and workable condition.

B. The Contractor shall remove and replace, where required, all

existing shrubbery, trees, grass, sprinklers, fences, signs, mail boxes, guard rails, structures, roadways, sidewalks, curbs and similar items in the way and shall make all excavation necessary for the work. Where pavement or sidewalks are cut, they shall be cut by means of a mechanical pavement saw to form true and straight edges which shall in general be either parallel or at right angles with the road or sidewalk. The cost of removing and replacing any plantings shall be included in the bid and no additional payment will be made for this work. In order to protect himself from being held liable for any existing damaged pavement, including detour routes, the Contractor is advised to notify the Contracting Officer in writing where such defective pavement exists prior to proceeding with any work in the vicinity.

C. All cleared materials shall be promptly removed from the work

area and disposed of off base by the Contractor, at no additional cost to the Government. Accumulation of debris or stockpiling along the route of the work will not be allowed.

3.2 EXCAVATION A. The Contractor shall perform all excavation of every

description and of whatever substances encountered to the dimensions, grades and depths specified herein.

B. Trenches for piping shall be excavated to a width within the

limits of the top of the pipe and the trench bottom so as to

Page 43: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-4

provide a clearance on each side of the pipe barrel, measured to the face of the excavation or sheeting if used, of 8 inches to 12 inches. All pipe trenches shall be excavated to a level where suitable material is reached and to a minimum of 8 inches below the outside bottom of the pipe barrel. Excavation depths in other types of materials and conditions shall be made as hereinafter specified.

C. In areas where trench widths are not limited by right-of-way and/or easement widths, property line restrictions, existing adjacent improvements including pavements, structures and other utilities, and maintenance of traffic, the trench sides may be sloped to a stable angle of repose of the excavated material but only from a point one foot above the crown of the pipe.

D. Barriers shall be placed at each end of all excavations and at

such places as may be necessary along excavations to warn all pedestrian and vehicular traffic of such excavations. Lights shall also be placed along excavations from sunset each day to sunrise of the next day until such excavation is entirely refilled, compacted, and surface restored. All excavations shall be barricaded in such a manner as to prevent persons from falling or walking into any excavation. Safe and suitable ladders that project 2-feet above the top of the trench shall be provided for all trenches greater than 4-feet in depth. Excavation for appurtenances shall be sufficient to provide a clearance between their outer surfaces and the face of the excavation of sheeting, if used, of not less than 12-inches.

E. Excavated unsuitable material shall be removed from the site

and disposed of by the Contractor. Materials removed from the trenches shall be stored in such a manner that will not interfere unduly with traffic on public roadways and sidewalks. In congested areas, such materials that cannot be stored adjacent to the trench or used immediately as backfill shall be removed to other convenient places of storage acceptable to the Contracting Officer at the Contractor's expense. Excavated material that is suitable for use as backfill shall be used in areas where sufficient material is not available from the excavation. Suitable material in excess of backfill requirements shall be the property of the Contractor and shall be hauled away by the Contractor with no additional cost to the Government; all costs for hauling,

Page 44: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-5

loading and unloading shall be included in the bid price. 3.3 SHEETING AND BRACING A. The term sheeting shall represent any type of shoring used to

support the sides of the excavation. For trench excavation 5 feet deep or less, sheeting and shoring shall be installed where necessary to control trench width, protect the workmen and the general public, and prevent damage to this or adjacent work, or structures. When a trench excavation is in excess of 5 feet deep, the Contractor shall comply with the provisions of the State of Florida "Trench Safety Act" and compliance with OSHA requirements. Method(s) of compliance used shall protect the workmen and the general public, prevent damage to this or adjacent work, structures, utilities, pavements, sidewalks, curbs, gutters and similar improvements both public and private, and to provide for proper maintenance of traffic. The trench width may vary to accomplish this and to comply with the Trench Safety Act, but only from a point 1 foot above the top of the pipe.

B. Where wood sheeting or certain designs of steel sheeting are

used or when removal of sheeting system can disturb the bedding, pipe or alignment of pipe, the sheeting shall be cut off at a level of 2 feet above the top of the installed pipe and that portion below the level shall be left in place. The Contractor shall not receive additional compensation over and above the Contract price for any sheeting that is required to be left in place. If interlocking steel sheeting is used, it may be removed providing removal can be accomplished without disturbing the bedding, pipe or alignment of the pipe. Any damage to the pipe bedding, pipe or alignment of the constructed utility caused by the removal of sheeting shall be cause for rejection of the affected portion of the work.

C. The Contractor shall be responsible for the adequacy of all

sheeting used and for all damage resulting from sheeting and bracing failure or from placing, maintaining and removing it.

3.4 REMOVAL OF WATER A. General: It is a basic requirement of the Contract Documents

that excavation shall be free from water before pipes are repaired.

Page 45: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-6

B. The Contractor shall provide pumps, and other appurtenant equipment necessary to remove and maintain water at such a level as to maintain a dry construction site. The Contractor shall continue dewatering operations until backfilling has progressed to a sufficient depth over the pipe to prevent flotation or movement of the pipe in the trench or so that it is above the water table. If at any point during the dewatering operation it is determined that fine material is being removed from the excavation sidewalls, the dewatering operation shall be stopped and the method modified or an alternative method employed. If any of the subgrade or underlying material is disturbed by movement of groundwater, surface water, or any other reason, it shall be replaced at no additional cost to the Government with crushed stone or gravel. The Contractor shall use dewatering systems that include automatic starting devices, and standby pumps that will ensure continuous dewatering in the event of a break down of one or more pumps.

C. Disposal: The Contractor shall be responsible to dispose of

water from the dewatering operation in accordance with the Contract Documents and shall obtain all necessary permits and conform to all local regulations and codes. Water from dewatering operation may be disposed at locations directed by the Contracting Officer with the proper installation of separation screens and operation of the dewatering system in accordance with all local regulations and codes. The Contractor shall submit his dewatering method and point(s) of discharge to the Contracting Officer for review at least ten days prior to any dewatering activities. The Contractor shall provide maintenance of canal(s) and drainage ditches to which he discharges. The cost of maintaining drainage ditches and canal(s) shall be included in the bid price. The Contractor shall remove siltation and haul, and dispose of this material at his expense and all costs for hauling, loading and unloading shall be included in this bid price. Water from the trenches and excavation shall be disposed of in such a manner as will not cause injury to public health, to property, to the work completed or in progress, to the surface of the streets, to interfere with the use of the same by the public, or will not cause pollution of any waterway or stream. The Contractor shall submit his proposed methods of handling trench water and locations at which the water will be disposed of to the Contracting Officer for review at least ten days prior to any related work and shall receive written acceptance before

Page 46: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-7

starting the excavation. 3.5 TRENCH STABILIZATION A. No claim for extras, or additional payment will be considered

for cost incurred in the stabilization of trench bottoms which are rendered soft or unstable as a result of construction methods, such as improper or inadequate sheeting, dewatering or other causes. In no event shall pipes or other utilities be installed when such conditions exist and the Contractor shall correct such conditions so as to provide proper bedding or foundations for the proposed installation at no additional cost to the Government before placing the pipes.

3.6 PIPE BEDDING A. Pipe trenches shall be excavated subject to the requirements

of the specification. The resulting excavation shall be backfilled with the specific pipe bedding material, up to the level of the centerline of the proposed pipe barrel. This backfill shall be tamped and compacted to provide a proper bedding for the pipe and shall then be shaped to receive the pipe. Bedding shall be provided under the branch of all fittings to furnish adequate support and bearing under the fitting. Any excavation below the levels required for installation of the pipe bedding shall be backfilled with acceptable bedding material, tamped, compacted and shaped to provide proper support for the proposed pipe, at no additional cost to the Government.

3.7 BACKFILL A. Pipelines: Backfilling of trenches will not be allowed until

the work has been reviewed by the Contracting Officer, and the Contracting Officer indicates that backfilling may proceed. Any work covered up or concealed without the knowledge or consent of the Contracting Officer may be required to be uncovered or exposed at no cost to the Government.

B. Pipeline trenches shall be backfilled with a select backfill

material to a level 12-inches above the top of the pipe. Such material shall be placed in 6-inch layers, each compacted to the densities specified in "compaction and densities". Only hand operated mechanical compacting equipment shall be used within six inches of the installed pipe. After the select

Page 47: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-8

backfill has been placed as specified above, and after all excess water has completely drained from the trench, backfilling of the remainder of the trench may proceed. The remainder of the backfill shall be placed in horizontal layers, the depth of which shall not exceed the ability of the compaction equipment employed, and in no event shall exceed a depth of 12-inches. Each layer shall be moistened, tamped, puddled, rolled or compacted to the densities specified. The backfill up to the centerline of the pipe shall be placed as soon as practical after the repair of the pipe. On parts of the line where ground water level may be high enough to float the pipe, the placing of the backfill and the rate of pumping the trench shall be so controlled as to prevent the pipe from floating or moving from the line and grade established.

3.8 COMPACTION AND DENSITIES A. Compaction Requirements: Compaction of backfill shall be 98%

of the maximum density where the trench is located under structures or paved areas, and 95% of the maximum density elsewhere. Methods of control and testing of backfill construction are:

1. Maximum density of the material in trenches shall be

determined by ASTM D 1557, Method D.

2. Field density of the backfill material in place shall be determined by ASTM D 1556 or D 2922.

B. Testing: A minimum of two tests of the field density of the

backfill shall be conducted at each point of repair to establish compliance with the compaction requirements of these specifications. The Contractor shall coordinate and provide the tests. Trench backfill which does not comply with the specified densities, as indicated by such tests, shall be reworked and re compacted until the required compaction is secured at no additional cost to the Government. The costs for retesting such work shall be paid for by the Contractor.

3.9 ADDITIONAL EXCAVATION AND BACKFILL A. Where organic material, such as roots, muck, or other

vegetable matter, or other material which will result in unsatisfactory foundation conditions is encountered below the level of the proposed bedding material, additional excavation

Page 48: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02222-9

shall be performed to a depth of 3' below pipeline or where acceptable foundation bearing surface is found. Additional specified sheeting shall be installed if necessary to maintain trenches. The resulting excavation shall be backfilled with fill material as specified and placed in 12-inch layers, tamped and compacted up to the level of the bottom of the specified pipe bedding material. Sufficient compaction of this material shall be performed to protect the proposed pipe against settlement. Minimum compaction requirements shall be as specified. Construction shall then proceed in accordance with the provisions Pipe Bedding. The excavation of all additional material below the outside bottom of the pipe and corresponding sheeting, dewatering and other work, as required, shall be completed at the Contractor's expense.

END OF SECTION

Page 49: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02602-1

SECTION 02602 EXTERIOR WATER LINES PART 1 GENERAL 1.1 SECTION INCLUDES (SUBMITTALS REQUIRED FOR EACH ITEM)

A. Valves. B. Piping.

C. Fittings. 1.2 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

1. AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

ASTM A 53, Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless

2. AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA B300, Hypochlorites

AWWA B301, Liquid Chlorine

AWWA C104, Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water

AWWA C110, Ductile-Iron and Gray-Iron Fittings, 3 In. Through 48 In., for Water and Other Liquids

AWWA C111, Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings

AWWA C153, Ductile-Iron Compact Fittings, 3 In. Through 6 In. for Water and Other Liquids

AWWA C500, Gate Valves for Water and Sewage Systems

AWWA C502, Dry-Barrel Fire Hydrants

Page 50: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02602-2

AWWA C509, Resilient-Seated Gate Valves for Water and Sewage Systems

AWWA C600, Installation of Ductile-Iron Water Mains and Their Appurtenances

AWWA C606, Grooved and Shouldered Joints

3. DUCTILE IRON PIPE RESEARCH ASSOCIATION (DIPRA)

DIPRA-01, Thrust Restraint Design for Ductile Iron Pipe

4. NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 24, Installation of Private Fire Service Mains and Their Appurtenances

5. FEDERAL SPECIFICATIONS (FS)

TT-E-489, Enamel, Alkyd, Gloss, Low Voc Content

TT-P-645b, Primer, Coating, Latex Base, Interior, White (for Gypsum Wallboard, or Plater)

6. FEDERAL STANDARD

NO. 595a, Colors

1.3 GENERAL

A. Piping for water distribution lines shall be ductile iron.

1. The Contractor shall have a copy of the

manufacturer's recommendations for each material or procedure to be utilized available at the construction site at all times.

2. Excavation, Trenching, and Backfilling for Water

Lines. Shall be in accordance with the applicable

Page 51: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02602-3

provisions of Section 02222 Excavation and Backfilling, except as modified herein.

1.4 SUBMITTALS

A. The following shall be submitted in accordance with Section 15010 Mechanical General Requirements.

1. Water distribution piping, fittings, joints, and

coupling.

2. Valves and valve boxes. 1.5 HANDLING

A. Pipe and accessories shall be handled so as to insure delivery to the trench in sound, undamaged condition. Particular care shall be taken not to injure the coating or lining. If the coating or lining of any pipe or fitting is damaged, repair shall be made by the Contractor at his expense to original condition as approved by the Contracting Officer. No other pipe or material of any kind shall be placed inside a pipe or fitting after the coating has been applied. Pipe shall be carried into position and not dragged. Use of pinch bars and tongs for aligning or turning pipe will be permitted only on the bare ends of the pipe. The interior of pipe and accessories shall be thoroughly cleaned of foreign matter before being lowered into the trench and shall be kept clean during laying operations by plugging or other approved method. Before installation, the pipe shall be inspected for defects. Material found to be defective before or after laying shall be replaced with sound material without additional expense to the Government. Rubber gaskets that are not to be installed immediately shall be stored in a cool and dark place.

PART 2 PRODUCTS 2.1 DUCTILE-IRON PIPE

A. Shall conform to AWWA C151, working pressure not less than 150 psi, unless otherwise shown or specified. Pipe

Page 52: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02602-4

shall be cement-mortar lined in accordance with AWWA C104. Linings shall be standard.

1. Ductile-Iron Pipe. Fittings shall be suitable for

150 psi pressure rating, unless otherwise specified. Fittings for mechanical joint pipe shall conform to AWWA C110.Fittings shall be cement-mortar lined (standard thickness) in accordance with AWWA C104.

2.2 JOINTS

A. Ductile-Iron Pipe. Mechanical joints shall be of the stuffing box type and shall conform to AWWA C111. All joints shall be restrained.

B. Rubber gaskets and lubricant shall conform to the

applicable requirements of AWWA C111. 2.3 GATE VALVES

A. Shall be designed for a working pressure of not less than 150 psi. Valve connections shall be mechanical joint as required for the piping in which they are installed. Valve shall have a clear waterway equal to the full nominal diameter of the valve, and shall be opened by turning counter clockwise. The operating nut shall be 2" x 2". The valves shall be resilient seated. The valve stem shall be sealed with "O" rings. Valves shall be iron body, bronze mounted, and shall conform to AWWA C509.

2.4 INDICATOR POST

A. The post indicator shall attach to gate valve and have lockable handle. The sleeve shall be adjustable for different depths. It shall be painted red. The indicator post shall meet the requirements of UL 789 "Indicator posts for fire- protection service@ .

2.5 MISCELLANEOUS ITEMS

A. Disinfection materials shall conform to the following:

Page 53: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02602-5

1. Chlorine, Liquid: AWWA B301.

2. Hypochlorite, Calcium and Sodium: AWWA B300.

PART 3 EXECUTION 3.1 INSTALLATION

A. Pipe shall be cut in a neat and workmanlike manner without damage to the pipe. Cutting shall be done with a mechanical wheel-type cutter. Squeeze type mechanical cutters shall not be used for ductile iron. Transit pipe will be snap broken not cut if encountered.

B. Joint Deflection - Ductile-Iron Pipe. The maximum

allowable deflection shall be as given in AWWA C600.

C. Pipe and related accessories shall be carefully lowered into the trench by means of derrick, ropes, belt slings, or other similar equipment. Under no circumstances shall any of the water-line materials be dropped or dumped into the trench. Care shall be taken to avoid abrasion of the pipe coating. Except where necessary in making connections with other lines, pipe shall be laid with the bells facing in the direction of laying. The full length of each section of pipe shall rest solidly upon the pipe bed, with recesses excavated to accommodate bells, couplings, and joints. Pipe that has the grade or joint disturbed after laying shall be taken up and relayed. Pipe shall not be laid in water or when trench conditions are unsuitable for the work. Water shall be kept out of the trench until joints are complete. When work is not in progress, open ends of pipe, fittings, and valves shall be securely closed so that no trench water, earth, or other substance will enter the pipes or fittings. Where any part of the coating or lining is damaged, the repair shall be made by the Contractor at his expense equal to the original material. The Contractor shall provide thrust blocks as indicated on the drawings.

3.2 HYDROSTATIC TESTS

Page 54: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02602-6

A. Where any section of a water line is provided with new

concrete thrust blocking for valve, the hydrostatic tests shall not be made until at least 5 days after installation of the concrete thrust blocking, unless otherwise approved.

1. Pressure Test. After the pipe is laid, the joints

completed, valves installed, and the trench partially backfilled leaving the joints exposed for examination, the newly laid piping or any valved section of piping shall, unless otherwise specified, be subjected for 1 hour to a hydro-static pressure test of system pressure. Each valve shall be opened and closed several times during the test. Exposed pipe, joints, fittings, and valves shall be carefully examined during the partially open trench test. Joints showing visible leakage shall be replaced or remade as necessary. Cracked or defective pipe, joints, couplings, and valves, discovered in consequence of this pressure test shall be removed and replaced with sound material, and the test shall be repeated until the test results are satisfactory.

3.3 STERILIZATION

A. Sterilization. The valve assembly with the field fabricated piping shall be flushed with water then capped and filled with a 500 MG/L chlorine solution. The solution shall be flowed through the valves and be retained in the assembly for 60 minutes. The assembly shall be drained and then flushed with potable water till the residual chlorine reading of the discharge water matches those of the supply water. The initial solution used for sterilization shall be drained then disposed of into a sanitary sewer. The sterilization should be completed on the job site no more than 30 minutes before installation. The ends of the existing cut pipe shall be swabbed with a 5 percent hypochlorite solution.

B. If the pit becomes flooded during the valve replacement,

the Contractor shall be required to do a complete

Page 55: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

02602-7

sanitization of the affected water system as required by the Contracting Officer.

3.4 CLEANUP

A. Upon completion of the installation of water lines, and appurtenances, all debris and surplus materials resulting from the work shall be removed.

END OF SECTION

Page 56: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-1

SECTION 15010 Rev 1 MECHANICAL GENERAL REQUIREMENTS

1.1 APPLICATION: A. This section applies to all sections of Division 15,

"Mechanical" of this project. 1.2 REFERENCES: A. The publications listed throughout the specifications form a

part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

CODE OF FEDERAL REGULATIONS (CFR)

29 CFR 1910.147, Control of Hazardous Energy (Lock Out/Tag Out)

1.3 GENERAL: A. The contract drawings indicate the extent and general

arrangement of the work. The contractor shall be responsible for installing the proposed systems as indicated, without violation of applicable codes, standards, or specification requirements. The contractor is also responsible for coordinating the installation and operation of these systems with the other sections of this specification to provide a complete and operable system. Items shall be arranged such that they fit the space as indicated and shall allow adequate and approved clearance for entry, servicing and maintenance. Detailed drawings of any proposed departures due to actual field conditions shall be submitted to the Contracting Officer for approval. All work shall conform to the requirements of the referenced publications and as specified herein.

1.4 CONFORMANCE WITH AGENCY REQUIREMENTS: A. Where materials or equipment are specified to conform to

requirements of the Underwriters' Laboratories, Inc., or other agency, institute, codes, councils or regulatory bodies, the contractor shall submit proof of such conformance. The label or listing of the specified agency will be acceptable evidence. In lieu of the label or listing, the contractor may submit a written certificate from any approved, nationally recognized testing organization adequately equipped and competent to perform such services, stating that the items have been tested and that the units conform to the requirements, including methods of testing, of the specified agency. Where equipment is specified to conform to

Page 57: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-2

requirements of the ASME Boiler and Pressure Vessel Code, the design, fabrication, and installation shall conform to the code in every respect and bear the ASME Stamp.

1.5 CAPACITIES: A. Capacities of all equipment and material shall be not less

than those indicated, nor exceed maximum values which are stated in the specifications or shown on the drawings.

1.6 EQUIPMENT INSTALLATION: A. Necessary supports shall be provided for equipment and systems

components as required. Vibration isolation shall be provided on any piece of equipment which would otherwise cause vibrations or noise to be detected by building occupants. Concrete pads shall be provided for all outdoor equipment installed. The pads shall extend past the units a minimum of 6" on each side.

1.7 ELECTRICAL WORK: A. Electric-motor-driven equipment specified herein shall be

provided complete with motors and controls. Electric equipment and wiring shall be in accordance with Division 16, "Electrical". Electrical characteristics shall be as indicated. Each motor shall be of sufficient capacity to drive the equipment at the specified capacity without exceeding the nameplate rating of motor when operating at proper electrical system voltage. Manual or automatic control and protective or signal devices required for the operation herein specified and any control wiring required for controls and devices, but not shown on the electrical plans, shall be provided under this section as required.

1.8 SUBMITTAL OF MATERIALS AND EQUIPMENT FOR APPROVAL:

A Within 14 days after notice to proceed and before purchasing

any materials or equipment, the contractor shall submit to the Contracting Officer for approval, in five bound copies, materials he proposes for the work. The submittal shall also meet the requirements of Section 01340. Items to be submitted include, but are not limited to, the items listed in each individual section. Partial submittals will not be acceptable and will be returned without review. Submittals shall include the manufacturer's names, trade name, catalog model or number, nameplate data, size, layout dimensions, capacity, project specification and paragraph reference, applicable Federal, Military, industry, and technical society publication references, and other information necessary to establish contract compliance of each item the contractor proposes to furnish. The manufacturer of the equipment shall submit a

Page 58: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-3

letter on company letterhead stating the equipment provided on this project will be provided with replacement parts and technical support for ten years from date of installation.

1. Shop Drawings. Drawings shall be a minimum of 8.5 inches

by 11 inches in size, except as specified otherwise.

2. Manufacturer's Data. Submittals for each manufactured item shall be manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves, and catalog cuts.

3. Cataloged Products. Materials and equipment shall be

cataloged products of manufacturers regularly engaged in production of such materials or equipment and shall be manufacturer's latest design that complies with the specification requirements. Materials and equipment shall duplicate items that have been in satisfactory commercial or industrial use at least 2 years prior to bid opening. Where two or more items of the same class of equipment are required, these items shall be products of a single manufacturer.

4. Submittal Organization. The submittal shall be organized

in the same order as the specification sections. The cut sheets shall be marked with equipment number which is shown on the drawings or name for something general such as piping. The submittal sheets shall document the piece of equipment meets the performance requirements of the contract documents. Note: Unmarked submittals will be rejected without review.

5. Samples. The samples shall be such as to illustrate the

functional and aesthetic characteristics of the product.

6. Equipment Application. The contractor shall note on the submittal or in writing of any equipment provided which may not operate satisfactory when installed as indicated on the plans.

1.9 NAMEPLATES: A. Each major item of equipment shall have the manufacturer's

name, address, serial and model numbers, and date of manufacture, on a plate securely attached to the item.

1.10 VERIFICATION OF DIMENSIONS: A. The contractor shall visit the premises to thoroughly

familiarize himself with all details of the work and working conditions and verify all dimensions in the field, and shall

Page 59: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-4

advise the Contracting Officer of any discrepancy before performing any work. The contractor shall be specifically responsible for the coordination and proper relation of his work to other structures and to the work of all other trades.

1.11 DRAWINGS: A. Because of the scale of the drawings, it is not possible to

indicate all offsets, fittings and accessories that is required. The contractor shall carefully investigate the structural and finish conditions affecting his work and he shall furnish fittings, offsets, transitions, unions, etc., as may be required to meet such conditions at no additional cost to the Government.

1.12 CUTTING AND REPAIRING: A. The work shall be carefully laid out in advance and no

excessive cutting of construction will be permitted. Damage to building, piping, wiring, or equipment as a result of cutting for installation shall be repaired by mechanics skilled in the trade involved at no additional expense to the Government.

1.13 SAFETY REQUIREMENTS: A. Belts, pulleys, chains, gears, couplings, projecting

setscrews, keys, and other rotating parts located so that any person can come in close proximity thereto shall be fully enclosed or properly guarded. High-temperature equipment and piping so located as to endanger personnel or create a fire hazard shall be properly guarded or covered with insulation of a type as specified herein. Items such as catwalks, ladders, and guardrails shall be provided where required for safe operation and maintenance of equipment.

1.14 MANUFACTURER'S RECOMMENDATIONS: A. Where installation procedures or any part thereof are required

to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations shall be furnished to the Contracting Officer prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.

1.15 PAINTING: A. At the completion of all work, all equipment on this project

shall be checked for damage, and any factory finished paint that has been damaged shall be repaired to match the adjacent

Page 60: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-5

areas. Any metal item that has been provided which has not been painted or otherwise protected shall be painted with primer and final coatings as recommended by the paint manufacturer for the particular application. The buildings will require custom matching because they have different shades of same basic color.

1.16 FINAL CLEANUP: A. At the completion of all work, all equipment on the project

shall be checked and thoroughly cleaned, including coils, plenums, under equipment, and any and all other areas around or in equipment. The final clean up shall include removing all debris from above the drop ceiling.

1.17 OPERATING AND MAINTENANCE INSTRUCTIONS: A. Bound instructions. Three complete sets of instructions

containing the manufacturer's operating and maintenance instructions for each piece of equipment shall be furnished to the Contracting Officer before the contract is completed. Each set shall be permanently bound and shall have a hard cover. The following identification shall be inscribed on the covers: The words "Operating and Maintenance Instructions", the name and location of the building, the name of the contractor and the contract number. Flysheet shall be placed before instructions covering each subject. The instruction sheet shall be approximately 8-1/2 by 11 inches, with large sheets of drawings folded in. The instructions shall include, but shall not be limited to, the following:

1. Approved wiring and control diagrams, with data to

explain the detailed operation and control of each component.

2. A control sequence describing startup, operation and

shutdown.

3. Operating and maintenance instructions for each piece of equipment, including lubrication instructions.

4. Manufacturer's bulletins, cuts and descriptive data.

5. Parts lists and recommended spare parts.

B. Framed Instructions. Approved wiring and control diagrams

showing the complete layout of the entire system, including equipment, piping, valves and control sequence, framed under glass or in approved laminated plastic, shall be posted, where directed. In addition, condensed operating instructions explaining preventive maintenance procedures, methods of checking the system for normal safe operation, and procedures

Page 61: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-6

for safely starting and stopping the system shall be prepared in typed form framed as specified above for the wiring and control diagrams and posted beside the diagram. Proposed diagrams, instructions, and other sheets shall be submitted prior to posting. The framed instructions shall be posted before acceptance-testing of the system.

1.18 DELIVERY AND STORAGE: A. Equipment and materials shall be carefully handled, properly

stored, and adequately protected to prevent damage before and during installation, in accordance with the manufacturer's recommendations and as approved by the Contracting Officer. Damaged or defective items shall be replaced. Equipment will not be delivered to the job site unless it can be stored inside the building or in an enclosed area such as a trailer.

1.19 LOCKOUT OF ENERGY SOURCES: A. Provide appropriate lockout devices for energy isolating

valves and for machines or other equipment to prevent unexpected start-up or release of stored electrical, mechanical, hydraulic, pneumatic, thermal, chemical, or other energy in accordance with 29 CFR 1910.147. Lockout devices for valves shall provide a means of attachment to which, or through which, a lock can be affixed or shall have a locking mechanism built into it so that the valve cannot be moved from the lockout position until the lock is removed. Electrical isolation of machines or other equipment shall be in accordance with requirements of Division 16 "Electrical."

1.20 CONTRACTOR PREPARED AS-BUILT DRAWINGS

A. General: The Government will furnish the Contractor on CD ROM one electronic set of solicitation drawing files and any amendments for use in preparation of as-built drawings by the Contractor. Copies of the drawings will be the responsibility of the Contractor. The as-built drawings shall be a record of the construction as installed and completed by the Contractor. They shall include all deviations, modifications, or changes from the contract drawings, however minor, that were incorporated in the work, all additional work not appearing on the contract drawings, and all changes which are made after final inspection of the contract work. In the event the Contractor accomplishes additional work which changes the as-built condition of the facility after submission of the as-built drawings, the Contractor shall furnish revised and/or additional drawings

Page 62: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-7

as required to depict as-built conditions. The requirements for these additional drawings will be the same as for the as-built drawings included in the original submittal.

B. Red line as-built drawings: The Contractor shall have on his

staff, personnel to mark up a set of paper copy construction drawings to show the as-built conditions. These as-built marked copies shall be kept current and available on the job site at all times. All changes from the contract plans which are made in the work or additional information which might be uncovered in the course of construction shall be accurately and neatly recorded, as the events occur, by means of details and notes. The Contractor shall call attention to entries by redlining areas affected. The red line as-built will be jointly inspected for accuracy and completeness by the Contracting Officer's representative and a responsible representative of the Contractor prior to submittal of each request for payment. The Contracting Officer's approval of the current status of the as-built drawings shall be a prerequisite to the Contracting Officer's approval of request for progress payment and request for final payment under the contract. The drawings shall show the following information, but not be limited thereto: (1) The location and description of any utility lines or

other installations of any kind or description known to exist within the construction area. The location includes dimensions to permanent features.

(2) The location and dimensions of any changes within the

building or structures. (3) Correct grade or alignment of roads, structures or

utilities if any changes were made from contract plans. (4) Changes in details of design or additional information

obtained from working drawings specified to be prepared and/or furnished by the Contractor including but not limited to fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment foundations, etc.(

(5) All changes or modifications which result from the

final inspection.

Page 63: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-8

(6) Options: Where contract drawings or specifications

allow options, only the option selected for construction shall be shown on the as-built drawings.

(7) Extensions of Design: Shop Drawings such as structural

fabrication and erection drawings and fire alarm systems that will require extensive redrafting effort in order to create a electronic set will not be required to be incorporated into the electronic set. They will be included as an Appendix to the paper copy set.

C. Submittal of as-built drawings for review and approval: The Contractor shall participate in monthly review meetings with the Contracting Officer's Representative to show the progress made the preceding month and make all required changes. At time of final construction inspection, the Contractor shall submit one copy of the red lined as-built drawings to the Contracting Officer's Representative for review and approval. The as-built drawings shall be certified as to their correctness by the signature of an authorized representative of the Contractor. Upon Government approval of the Contractor's redlined copy of the as-built drawings, the Contractor shall prepare and provide two electronic sets of as-built drawings by incorporating the red line marked up notations on the construction drawings into the electronic set of solicitation drawings and amendments. In addition to the electronic sets of as-built drawings which shall be submitted on a CD-ROM, the Contractor shall also submit a full size set of as-built drawings on mylar. Submittals are to be to the Contracting Officer's Representative not later than ten (10) calendar days after project completion date.

D. Final Drawing Format.

(1) The solicitation drawing files and any amendments

thereto will be furnished to the Contractor in electronic format. The solicitation drawing files have been prepared in MicroStation and/or AutoCAD format. The drawing file indicates the format which the drawing was developed. The As Built drawings shall reflect all changes made during construction as indicated by the red line marked up

Page 64: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-9

notations on the construction drawings. Revisions/redrafting shall match the font styles,sizes, and formats; line weights/thicknesses and styles/types; and all other drafting elements used on the solicitation drawing/amendments. All elements must be incorporated into each as-built drawing file; the use of reference files shall not be permitted. In addition, the Contractor will include the building number issued by Eglin AFB in the title block of the Final As-Built Drawings.

(2) As-built drawings will be submitted in a version of

AutoCAD that is coordinated with 96 CEG drafting section at the time of submission. The as-built DWG files shall have no reference files attached as all shall be bound into the file to make one AutoCAD DWG file, which also shall be purged and created with standard AutoCAD pen table. Scaled drawings should provide a bar scale and shall be in feet not meters. Contractor shall provide 1 hard copy of as-built drawings on Mylar on an Arch D sheet size and 2 CD’s in AutoCAD and PDF. Final As-Built drawings will include the assigned building number in the title block.

a. AutoCAD drawings shall have correct geometry:

1. Segmented lines and arcs are to be made continuous and free of self overlapping sections, thus decreasing files size and increasing efficiency within the AutoCAD platform.

2. All AutoCAD data shall be free of topological errors such as slivers, undershoots, overshoots dangles, overlaps, intersections, etc.

3. Area features such as building footprints, parking lots, roadways, and airfield pavements shall be true polyline polygons. Adjacent polygons will not have gaps or overlaps.

b. AutoCAD drawings shall be checked for correct spatial projection to one of the following: 1. North American Datum 1983 Florida State Plane North FIPS 0903 Feet (AutoCAD Code FL83-NF) 2. Universal Transverse Mercator 1984, Zone 16 North (AutoCAD Code UTM84-16N)

Page 65: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-10

c. Any Building Information Models (BIM) developed for a project will be supplied in a Model Archive as part of the final as-built submittal consisting of two sets of files: 1. The first set shall be a collection of individual Models as received from the Model Element Author(s). 2. The second set of files will consist of the aggregate of those individual Models in a format suitable for archiving and viewing. The aggregate model will also be submitted in a DWG file format.

(3) All revisions made to the solicitation drawings and/or

amendment drawings to reflect changes made during construction shall be flagged in a numbered triangle and shall have the revision block completed as follows. The entry in the description column of the revision block shall read "AS-BUILT". The date of the revision and one approving initial from a responsible person within the Contractor's Firm shall also be included in the revision block. Above the drawing title block the drawing will be labeled in bold letters "AS-BUILT".The Contractor shall also furnish a revised index of drawings to match the actual design drawings. The drawing title blocks shall be in a uniform format to match the requirements as specified in the Design Manual.

(4) The two electronic sets of as-built drawing files shall

be submitted in AutoCAD format and two electronic sets of as built drawings shall be submitted in pdf.

(5) The hard copy reproducible set of as-built drawings

shall be submitted unbound on mylar. The drawings shall be full size.

E. Payment: No separate payment will be made for the as-built drawings required under this contract, and all costs in connection there-with will be considered a subsidiary obligation of the Contract. 1.21 TRAINING/START UP A. The contractor shall meet on the site after the job is

complete and review the systems operation with the building manager and maintenance personnel. During the review the

Page 66: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15010-11

contractor shall verify that all system settings and timetables are satisfactory with the building manager.

END OF SECTION

Page 67: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15325 - 1

SECTION 15325 WET PIPE SPRINKLER SYSTEM PART 1 GENERAL 1.1 SECTION INCLUDES

A. Wet-pipe sprinkler system.

B. System design, installation, and certification.

C. Fire department connections. 1.2 RELATED SECTIONS

A. Section 15010 - "Mechanical General Requirements". 1.3 REFERENCES

A. NFPA 13 - Installation of Sprinkler Systems.

B. FM - Factory Mutual Approval Guide.

C. UL - Fire Resistance Directory.

D. UFC 3-600-01 – (Sep 2006 with Change 1 dated 14 July 2009) Fire Protection for Engineering Facilities

1.4 SYSTEM DESCRIPTION

A. System to provide coverage for area of building as shown.

B. Provide system according to UFC 3-600-01. C. Provide system according to NFPA 13.

D. Interface system with building fire alarm system.

E. Provide fire department connections where indicated.

F. Contractor to conduct water flow test before submittal

of shop drawings. 1.5 SUBMITTALS FOR REVIEW

A. Section 15010 - Mechanical General Requirements.

B. Qualifications of Installer: Prior to installation submit the following for 3 jobs; name of jobs, short description of jobs, locations, and current person with phone number at the job site which would be knowledgeable of the system. Two of the three jobs must

Page 68: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15325 - 2

have been in for a minimum of 4 years.

C. Product Data: Provide data on sprinklers, valves, and specialties, including manufacturers catalog information. Submit performance ratings, rough-in details, weights, support requirements, and piping connections. The product data shall be marked for easy cross reference to drawings.

D. Shop Drawings:

1. Submit working plans as required in Chapter 6 of NFPA 13. The plans shall have manufacturer's part numbers on the drawings so they can be referenced to the product data submitted.

2. Submit hydraulic calculations, which will be the summary sheet and detailed pipe input.

E. Submit plans and hydraulic calculations to authority

having jurisdiction for approval. Submit proof of approval to Architect/Engineer.

1.6 SUBMITTALS AT PROJECT CLOSEOUT

A. Section 01340 for record drawings, operation and maintenance data, procedures for submittals.

B. Project Record Documents: Record actual locations of

sprinklers and deviations of piping from drawings. Indicate drain and test locations. The record drawings shall be not smaller than 24" x 30" reproducible drawings on Mylar film.

C. Manufacturer's Certificate: Certify that system has

been tested and meets or exceeds code requirements.

D. Operation and Maintenance Data: Include components of system, servicing requirements, record drawings, inspection data, replacement part numbers and availability, and location and numbers of service depot.

E. Warranty: Submit manufacturer warranty and ensure forms

have been completed in Owner's name and registered with manufacturer.

1.7 QUALITY ASSURANCE

A. Perform Work in accordance with NFPA 13. In the NFPA publications referred to herein, the advisory provisions shall be considered to be mandatory, as though the work "shall" have been substituted for "should" wherever it appears; reference to the "authority having jurisdiction" shall be interpreted to mean the Contracting Officer.

Page 69: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15325 - 3

B. Manufacturer Qualifications: Company specializing in manufacturing the Products specified in this section with minimum three years documented experience.

C. Installer Qualifications: Company specializing in

performing the work of this section with minimum five years documented experience.

D. Design system under direct supervision of a Professional

Engineer experienced in design of this Work and licensed in the State of Florida and meets the requirements of designer qualifications listed in UFC 3-600-01. The Contractor shall submit documentation to the Contracting Officer.

1.8 REGULATORY REQUIREMENTS

A. Conform to UL and FM.

B. Perform Work in accordance with NFPA 13 and UFC 3-600-01.

C. Equipment and Components: Bear UL, FM label or marking.

D. Products Requiring Electrical Connection: Listed and

classified by Underwriters Laboratories Inc., as suitable for the purpose specified and indicated.

1.9 DELIVERY, STORAGE, AND PROTECTION

A. Store products in shipping containers and maintain in place until installation. Provide temporary inlet and outlet caps. Maintain caps in place until installation.

1.10 EXTRA MATERIALS

A. Provide extra sprinklers under provisions of NFPA 13.

B. Provide suitable wrenches for each sprinkler type.

C. Provide metal storage cabinet at the riser. PART 2 PRODUCTS 2.1 SPRINKLERS

A. Suspended Ceiling: 1. Type: Standard pendant type with matching clamp on

escutcheon plate. 2. Finish: Chrome plated. 3. Escutcheon Plate Finish: Chrome plated. 4. Fusible Link: Glass bulb type temperature rated for

specific area hazard.

Page 70: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15325 - 4

B. Exposed Area Type: 1. Type: Standard upright type with guard. 2. Finish: Chrome plated. 3. Fusible Link: Glass bulb type temperature rated for

specific area hazard.

C. Sidewall Type: 1. Type: Standard horizontal sidewall type with

matching clamp on escutcheon plate. 2. Finish: Chrome plated. 3. Escutcheon Plate Finish: Chrome plated. 4. Fusible Link: Glass bulb type temperature rated for

specific area hazard.

D. Guards: Finish to match sprinkler finish. 2.2 PIPING SPECIALTIES

A. Water Flow Switch: Vane type switches for mounting horizontal or vertical, with two contacts; rated 10 amps at 125 volt AC.

B. Gauges: Shall be 3-1/2" dial type and shall conform to ANSI B40.1.

C. Monitoring: Valves shall have supervisory contact unit

to interface with alarm system.

D. Sprinkler Pipe and Fittings: NFPA 13, except steel piping shall be Schedule 40. Fittings into which sprinkler heads, sprinkler head riser nipples, or drop nipples are threaded shall be welded, threaded, or grooved-end type. Use of plain-end fittings with mechanical couplings (which utilize steel gripping devices to bite into the pipe when pressure is applied) will not be permitted. Rubber gasket grooved-end pipe and fittings with mechanical couplings shall be permitted in pipe sizes 1.25 inches and larger; fittings shall be UL listed or FM approved for use in sprinkler systems.

E. Identification Signs: Attach properly lettered approved

metal signs conforming to NFPA 13 to each valve and alarm device. The lettering on nameplates shall be engraved.

F. Inspector's Test Connection: Provide test connections

about 6 feet above the floor for sprinkler system of portion of sprinkler system equipped with an alarm device and locate at the hydraulically most remote part of system. Provide test connection piping to a location where the discharge will be readily visible and where water may be discharged without damage. The test connection shall have a sight glass at the valve

Page 71: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15325 - 5

location.

G. Pipe Sleeves: Provide where piping passes through walls, floors, roofs, and partitions. Secure sleeves in proper position and location. Provide sleeves of sufficient length to pass through entire thickness of walls, floors, roofs, and partitions. Provide not less than 0.25-inch space between exterior of piping or pipe insulation and interior of sleeve. Firmly pack space with insulation and calk at both ends of the sleeve with plastic waterproof cement which will dry to a firm but pliable mass, or provide a segmented elastomeric seal. 1. Sleeves in Masonry and Concrete Walls, Floors, and

Roofs: Provide ASTM A 53 or ASTM A 120, Schedule 40 or Standard Weight, zinc-coated steel pipe sleeves. Extend sleeves in floor slabs 3 inches above the finished floor.

2. Sleeves in Partitions and Other Than Masonry and Concrete Walls, Floors, and Roofs: Provide zinc-coated steel sheet having a nominal weight of not less than 0.9 pounds per square foot.

PART 3 EXECUTION 3.1 INSTALLATION

A. Install in accordance with NFPA 13.

B. Install equipment in accordance with manufacturer’s instructions.

C. Install buried shut-off valves in valve box. Provide

post indicator.

D. Locate fire department connection with sufficient clearance from walls, obstructions, or adjacent Siamese connectors to allow full swing of fire department wrench handle. The connections shall be no lower than 36 inches and no higher than 48 inches above finish grade.

E. Locate outside alarm on building wall.

F. Place pipe runs to minimize obstruction to other work.

G. Place piping in concealed spaces above finished

ceilings.

H. Center sprinklers in one direction only in ceiling tile with location in other direction variable, dependent upon spacing and coordination with ceiling elements.

I. Apply masking tape or paper cover to ensure concealed

sprinklers, cover plates, and sprinkler escutcheons do not receive field paint finish. Remove after painting.

Page 72: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15325 - 6

J. Disinfection: Disinfect the new water piping affected

by Contractor's operations in accordance with AWWA C601. Fill the piping systems with solution containing minimum of 50 parts per million of available chlorine and allow solution to stand for minimum of 24 hours. Flush the solution from the systems with clean water until maximum residual chlorine content is not greater than 0.2 parts per million.

K. Field Testing and Flushing:

1. Preliminary Tests: Hydrostatically test system at 200 psig for a period of 2 hours. Flush piping in accordance with NFPA 13. Piping above suspended ceiling shall be tested, inspected, and approved before installation of ceilings. Test the alarms and other devices. Test the water flow alarms by flowing water through the inspector's test connection. When test have been completed and corrections made, submit a signed and dated certificate, similar to that specified in NFPA 13, with a request for a formal inspection and tests.

2. Formal Inspection and Tests: The authority having jurisdiction and Architect/Engineer will witness formal tests and approve system before they are accepted. Submit the request for formal inspection at least 15 days prior to the date the inspection is to take place. An experienced technician regularly employed by the sprinkler installer shall be present during the inspection. At this inspection, repeat any or all of the required tests as directed. Correct defects in the work provided by the Contractor, and make additional tests until it has been demonstrated that the systems comply with all contract requirements. Furnish appliances, equipment, electricity, instruments, connecting devices, and personnel for the tests. The Contractor will furnish water for the tests.

L. The exterior discharge locations from inspector test and

main drains shall be provided with concrete splash blocks.

3.2 INTERFACE WITH OTHER PRODUCTS

A. The required devices shall be provided, installed and connected as required to interface with the fire alarm system by this Contractor. The Contractor shall reprogram existing fire alarm system as needed for including the new systems installed in the buildings. This includes updating graphics and any other annunciators showing fire alarm conditions.

END OF SECTION

Page 73: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-1

SECTION 15329 Rev 1

GASEOUS CLEAN-AGENT FIRE SUPPRESSION SYSTEM PART 1 - GENERAL 1.1 SCOPE

This specification outlines the requirements for a "Total Flood" Clean Agent Fire Suppression System with automatic detection and control. The work described in this specification includes all engineering, labor, materials, equipment and service necessary, and required, to complete and test the suppression system.

1.2 APPLICABLE STANDARDS AND PUBLICATIONS

A. The design, equipment, installation, testing and maintenance of the Clean Agent Suppression System shall be in accordance with the applicable requirements set forth in 1he latest edition of the following codes and standards

1. NFPA No. 2001 - Clean Agent Fire Extinguishing Systems 2. NFPA No. 70 - National Electrical Code 3. NFPA No. 72 - Standard for Protective Signaling 4. Factory Mutual Approval Guide 6. UL Listings 7. UFC 3-600-01 – (Sep 2006 with Change 1 dated 14 July 2009)

Fire Protection for Engineering Facilities 8. Requirements of the Authority Having Jurisdiction (AHJ)

B. The standards listed, as well as all other applicable codes.

Environmental standards and good engineering practices shall be used as -minimum" design standards.

1.3 REQUIREMENTS

The Suppression System installation shall be made in accordance with the drawings, specifications and applicable standards. Should a conflict occur between the drawings and specifications, the specifications shall prevail. The gaseous systems installed

Page 74: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-2

in all buildings shall meet the requirements of UFC 3-600-01. Section 4-11 of UFC 3-600-01 has specific requirements for gaseous clean-agent fire suppression systems. Building 374 has a Notifier 3030 Fire Alarm System installed after 2007. The system shall be upgraded to include the monitoring of the gaseous system.

1.4 QUALITY ASSURANCE

A. Manufacturer

1. The manufacturer of the suppression system hardware and detection components shall be ISO 9000 registered.

2. The name of the manufacturer shall appear on all major

components. 3. All devices, Components and equipment shall be the

products of the same manufacturer. 4. All devices, components and equipment shall be new,

standard products of the manufacturer's latest design and suitable to perform the functions intended.

5. All devices and equipment shall be U.L listed and/or FM

approved. 6 Locks for all cabinets shall be keyed alike.

B. Installer

1. The installing contractor shall be trained by the

supplier to design, install, test and maintain fire suppression systems. .

2. The design of the system must meet the requirements of

UFC 3-600-01, 4-1.2. 3. The installing contractor shall be an experienced firm

regularly engaged In the Installation of automatic Clean Agent, or similar, fire suppression systems in strict accordance with all applicable codes and standards.

4. The installing contractor must have a minimum of five

(5) years experience in the design, installation and testing of Clean Agent, or similar, and fire suppression systems. A list of systems of a similar nature and scope

Page 75: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-3

shall be provided on request. 5. The installing contractor shall show evidence that his

company carries a minimum $2,000,000.00 liability and completed operations Insurance policy. These limits shall supersede limits required in the general conditions of the specifications.

6. The installing contractor shall maintain, or have access

to a resupply of agent. The Installing contractor shall provide proof of his ability to recharge the largest Clean Agent system within 24 hours after a discharge. Include the amount of bulk agent storage available.

7. The installing contractor shall be an authorized

stocking distributor of the Clean Agent system equipment so that immediate replacement parts are available from inventor

8. The installing contractor shall show proof of emergency

service available on a twenty-four-hour-, seven-day-a-week basis.

1.5 SUBMITTALS

A. The installing contractor shall submit the following design information and drawings for approval prior to starting work on this project:

1. Field Installation layout drawings having a scale of not

less than 1/8" = 1'- 0" detailing the location of all agent storage tanks, nozzles, pipe runs Including pipe sizes and lengths, control panel(s), detectors, manual pull stations, abort stations, audible and visual alarms, etc.

2. Auxiliary details and information such as maintenance

panels, door holders, special sealing requirements and equipment shutdown.

3. Separate layouts, 'or drawings, shall be provided for

each level, (i.e. room, under floor. and above ceiling) and for mechanical and electrical work.

4. A separate layout or drawing shall show isometric

details of gent storage containers mounting details proposed pipe runs and sizes, all symbol legend.

Page 76: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-4

5. Electrical layout drawings shall show the location of

all devices and Include point-to-point conduit runs and a description of the method(s) used for detector mounting.

6. Provide an internal control panel wiring diagram which

shall include power supply requirements and field wiring termination points.

7. Separate drawing providing symbol legend to identify all

symbols used. 8. Complete hydraulic flow calculations, from a UL listed

computer program, shall be provided for all engineered Clean Agent systems. Calculation sheet(s) must include the manufacturers name and UL listing number for verification. The individual sections of pipe and each fitting to be used, as shown on the isometrics, must be identified and included in the calculation. Total agent discharge time must be shown and detailed by zone.

9. Provide calculations for the battery stand-by power

supply taking into consideration the power requirements of all alarms, initiating devices and auxiliary components under full load conditions.

10. A complete sequence of operation shall be submitted

detailing all alarm devices, shutdown functions, remote signaling, damper operation, time delay and agent discharge for each zone or system.

B. Submit drawings, calculations and system component data

sheets for approval to the Contracting Officer. 1.6 SYSTEM DESCRIPTION AND OPERATION

A. The system shall be a Total FLOOD Suppression System using NOVEK 1230.

B. The system shall provide a NOVEC 1230 minimum design

concentration of 4.2% by volume for Class A hazards and a 5.85% by volume for Class B hazards, in all areas and/or protected spaces, at the minimum anticipated temperature within the protected area. System design shall not exceed 10% for normally occupied spaces, adjusted for maximum space temperature anticipated with provisions for room

Page 77: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-5

evacuation before agent release. C. The system shall be complete in all ways. It shall include

a mechanical and electrical installation, all detection and control equipment, agent storage containers, clean agent, discharge nozzles, pipe and fittings, manual release and abort stations, audible and visual alarm devices, auxiliary devices and controls, shutdowns, alarm interface, caution advisory signs, functional checkout and testing, training and an other operations necessary for a functional, UL listed Clean Agent suppression system. In Building 374 the existing Notifier 3030 shall be expanded for the gaseous system.

D. Provide two (2) inspections during the first year of

service: Inspections shall be made at 6-month intervals commencing when the system is first placed into normal service.

E. The Contractor shall be responsible for checking the

sealing of the protected spaces for agent loss and/or leakage during the 10-minute "hold" period. The Contractor shall notify the Contracting Officer if the room does not meet the test.

F. The system(s) shall be actuated by a combination of

Ionization and photoelectric detectors installed for maximum area coverage of 250 sq. ft. If the airflow is one air change per minute, photoelectric detectors only shall be installed for maximum area coverage of 125 sq. ft.

G. Detectors shall be Cross-Zoned detection requiring two

detectors to be in alarm before release. H. Automatic operation of each protected area shall be as

follows:

1. Actuation of one (1) detector, within the system, shall:

a. Illuminate the "ALARM" lamp on the control panel face. b. Energize an alarm bell and/or an optional visual

indicator. c. Transfer auxiliary contacts which can perform

auxiliary system functions such as: I} Operate door holder/closures on access doors, II) Transmit a

Page 78: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-6

signal to a fire alarm system, III) Shutdown HVAC equipment.

d. Light an Individual lamp on an annunciator.

2. Actuation of a 2nd detector, within the system, shall:

a. Illuminate the "PRE-DISCHARGE" lamp on the control

panel face. b. Energize a pre-discharge horn or horn/strobe device. c. Shut down the HVAC system and/or close dampers. d. Start time-delay sequence (not to exceed 60 seconds). e. System abort sequence is enabled at this time. f. Light an individual lamp on an annunciator

3. After completion of the time-delay sequence, the Clean

Agent system shall discharge and the following shall occur:

a. Illuminate a "SYSTEM FIRED" lamp on the control panel

face. b. Shutdown of all power to high-voltage equipment c. Energize a visual indicator(s) outside the hazard in

which the discharge occurred. d. Energize a "System Fired" audible device.

4. The system shall be capable of being actuated by manual

discharge devices located at each hazard exit. Operation of a manual device shall duplicate the sequence description above except that the time delay and abort functions shall be bypassed. The manual discharge station shall be of the electrical actuation type and shall be supervised at the main control panel.

PART 2 - PRODUCTS 2.1 GENERAL REQUIREMENTS

A. The Clean Agent System materials and equipment shall be

Page 79: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-7

standard products of the supplier's latest design and suitable to perform functions Intended. When one or more pieces of equipment must perform, the same function(s), they shall be duplicates produced by one manufacturer.

B. All devices and equipment shall be UL Listed and/or FM

approved. C. Chemical agent shall be environmentally sustainable with

an Ozone Depletion potential (ODP) no greater than one and a Global Warming Potential (GWP) no greater than one.

2.2 NOVEC 1230® FIRE FIGHTING FLUID®

A. Each system shall have its own supply of clean agent. B. The system design can be modular. Central storage or a

combination of both design criteria. C. Systems shall be designed in accordance with the

manufacturer's guidelines. D. Each supply shall be located within the hazard area, or as

near as possible to reduce the amount of pipe and fittings required to install the system.

E. The clean agent shall be stored in Clean-Agent Storage

Containers. Containers shall be super-pressurized with dry nitrogen to an operating pressure of 360 psi @ 70 of. Containers shall be of high-strength low alloy steel construction and conform to NFPA 2001.

F. Containers shall be actuated by a resettable electric

actuator with mechanical override located at each agent container or connected bank of cylinders. Non- resettable or explosive devices shall not be permitted.

G. Each container shall have a pressure gauge and low pressure

switch to provide visual and electrical supervision of the container pressure. The low-pressure switch shall be wired to the control panel to provide an audible and visual "Trouble" alarms in the event the container pressure drops below 247 psi. The pressure gauge shall be color coded to provide an easy, visual indication of container pressure.

H. Each container shall have a pressure relief provision that

automatically operates before the internal pressure

Page 80: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-8

exceeds 750 psi. I. Engineered discharge nozzles shall be provided within the

manufacturer's guidelines to distribute the NOVEC 1230 ® Fire Fighting Fluid ® agent throughout the protected spaces. The nozzles shall be design to provide proper agent quantity and distribution.

1. Nozzles shall be available in 3/8 in. through 2 in. Pipe

sizes. Each size shall be available in 180° and 360° distribution patterns.

2. Ceiling plates can be used with the nozzles to conceal

pipe entry holes through ceiling tiles.

J. Distribu1ion piping, and fittings, shall be installed In accordance with the manufacturer's requirements. NFPA 2001 and approved piping standards and guidelines. All distribution piping shall be installed by qualified individuals using accepted practices and quality procedures. All piping shall be adequately supported and anchored at all directional changes and nozzle locations.

1. All piping shall be reamed, blown clear and swabbed with

suitable solvents to remove burrs, mill varnish and cutting oils before assembly.

2. All pipe threads shall be sealed with Teflon tape pipe

sealant applied to the male thread only. 2.3 CONTROL PANEL

A. The control panel shall be an automatic releasing panel. B. The control system and its components shall be UL listed

and FM approved for use as a local fire alarm system with releasing device service.

C. The control system shall perform all functions necessary

to operate the system detection. Actuation and auxiliary functions.

D. The control system shall include battery standby power to

support 24 hours in standby and 5 minutes in alarm. E. The control system shall be microprocessor based utilizing

a distributed processing concept A single microprocessor

Page 81: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-9

failure shall not impact operation of additional modules on the system.

F. The control system shall be capable of supporting Cross

Zoned Detection. G. The control system shall supply integrated 2.0 amp power

supply circuitry. H. Each control system shall four (4) initiating circuits.

1. Each circuit shall be capable of Class A (Style D) or Class B (Style A) operation.

2. Each circuit shall be capable of operating up to fifteen

(15) approved detectors for thirty (30) detectors per system.

3. Each circuit shall be capable of monitoring contact

devices configured for manual release, manual alarm system abort, trouble input or auxiliary (non-fire) input.

I. Each control shall contain release circuits for activation

of an extinguishing/suppression system(s).

1. Each circuit shall be capable of Class B (Style Y) operation.

2. Each circuit shall be rated for 1.5amp @ 24 VDC.

J. Each control system shall contain two (2) indicating

appliance circuits for annunciation.

1. Each circuit shall be capable of Class A (Style B) or Class B (Style Y) operation.

2. Each circuit shall be rated for: 1.5 amps @ 24 VDC.

K. Each control system shall provide an auxiliary power supply

rated for 2 amps @ 24 VDC.

L. Each control system shall provide two (2) SPST relays: one for common alarm and one for common trouble. Four (4) additional programmable relays can be added to each control system by adding a Relay Module.

Page 82: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-10

2.4 DETECTORS

A. The detectors shall be spaced and Installed in accordance with the manufacturer's specifications and the guidelines of NFPA 72.

B. The Ionization detector shall be the one supplied by the

system equipment supplier. C. The Photoelectric detector shall be the one supplied by the

system equipment supplier. 2.5 MANUAL RELEASE (Electric)

A. The electric manual release switch shall be a dual action device which provides a means of manually discharging the Suppression System when used in conjunction with the control system

B. The Manual Release switch or Manual Pull station shall be

a dual action device requiring two distinct operations to initiate a system actuation.

C. Manual actuation shall bypass the time delay and abort

functions shall cause the system to discharge and shall cause all release and shutdown devices to operate in the same manner as if the system had operated automatically.

D. Manual Release switch shall be located at each exit from

the protected hazard. 2.6 ABORT STATION

A. The Abort Station shall be the "Dead Man" type and shall be located next to each manual switch.

B. The Abort Station shall be supervised and shall indicate

a trouble condition at the control panel, if depressed and no alarm condition exist.

C. "Locking" or "Keyed" abort stations shall not be permitted.

2.7 AUDIBLE and VISUAL ALARMS

A. Alarm audible and visual signal devices shall operate from the control pane

Page 83: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-11

B. The Alarm Bell, Visual Alarm and Horn Strobe devices shall be provided from the same manufacturer as the control panel

C. A Strobe device shall be placed outside, and above, each

exit door from the protected space. Provide an advisory sign at each light location

2.8 CAUTION and ADVISORY SIGNS

A. Signs shall be provided to comply with NFPA 2001 and the recommendations of the equipment provider

1. Entrance sign (1) required at each entrance to a

protected space. 2. Manual discharge sign: (1) required at each manual

discharge station. 3. Flashing light sign: (1) required at each flashing light

over each exit from a protected space. 2.9 SYSTEM and CONTROL WIRING

A. All system wiring shall be furnished and installed by the contractor.

B. All wiring shall be installed in electrical metallic tubing

(EMT), or conduit, and must be installed and kept separate from all other building wiring.

C. All system components shall be securely supported

independent of the wiring. Runs of conduit and wiring shall be straight. Neatly arranged, properly supported, and installed parallel and perpendicular to walls and partitions.

D. The sizes of the conductors shall be those specified by the

manufacturer. Color- coded wire shall be used. All wires shall be tagged at all junction points and shall be free from shorts, earth connections, and crosses between conductors. Final terminations between the control panes and the system field wiring shall be made under the direct supervision of a factory-trained representative.

E. All wiring shall be installed by qualified individuals, in

a neat and workmanlike manner, to conform to the National Electrical Code, Article 725 and Article 760, except as

Page 84: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-12

otherwise permitted for limited energy circuits, as described in NFPA 72. Wiring installation shall meet all local, state, province and/or country codes.

F. The complete system electrical installation and all

auxiliary components shall be connected to earth ground in accordance with the National Electrical Code.

G. The shielded rooms require fiber optic “wiring” going

through any shielded wall. Provide all interface devices required for this type installation.

PART 3 - EXECUTION 3.1 EVACUATION FAN AND TUBING

A. The fan shall be a fan that shall provide 400 cfm at 2 inches of static pressure. The fan shall be provided with hose connections to both the supply and discharge to attach a 12 inch diameter flexible duct. The fan shall be provided with a 100 foot cord. The fan shall plug into a 120 outlet. The fan shall pull a maximum of 18 amps full load. The flexible duct shall be provided in 50 foot section and be 12 inches in diameter. The duct shall be provided with quick connectors for connection without tools. The fan and all the hose shall be provided in storage containers, which will be labeled “Emergency Evacuation Equipment.”

3.2 SYSTEM INSPECTION and CHECKOUT

A. After the system installation has been completed, the entire system shall be checked out, inspected and functionally tested by qualified, trained personnel, in accordance with the manufacturer's recommended procedures and NFPA standards.

B. All containers and distribution piping shall be checked for

proper mounting and installation. C. All electrical wiring shall be tested for proper connection,

continuity and resistance to earth. D. The complete system shall be functionally tested, in the

presence of the Contracting Officer or his representative, and all functions, including system and equipment interlocks, must be operational at least five (5) days prior to the final acceptance tests.

Page 85: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-13

1. Each detector shall be tested in accordance with the

manufacturer's recommended procedures and test values recorded.

2. All system and equipment interlocks, such as door

release devices, audible and visual devices, equipment shutdowns, local and remote alarms, etc. shall function as required and designed.

3. Each control panel circuit shall be tested for trouble

by inducing a trouble condition into the system. 3.3 TRAINING REQUIREMENTS

A. Prior to final acceptance, the Installing contractor shall provide operational training to each shift of the owner’s personnel. Each training session shall include control panel operation, manual and abort functions, trouble procedures, supervisory procedures, auxiliary functions and emergency procedures. The Contractor shall also provide two training sessions for the first responders for each facility.

3.4 OPERATION and MAINTENANCE

A. Prior to final acceptance, the installing contractor shall provide complete operation and maintenance instruction manuals and four (4) copies for each system, to the owner. All aspects of system operation and maintenance shall be detailed, including piping isometrics, wiring diagrams of all circuits, a written description of the system design, sequence of operation and drawling(s) illustrating control logic and equipment used in the system. Checklists and procedures for emergency situations, troubleshooting techniques, maintenance operations and procedures shall be included in the manual.

3.5 CONTRACTOR PREPARED AS-BUILT DRAWINGS

A. General: The Government will furnish the Contractor on CD ROM one electronic set of solicitation drawing files and any amendments for use in preparation of as-built drawings by the Contractor. Copies of the drawings will be the responsibility of the Contractor. The as-built drawings shall be a record of the construction as installed and completed by the Contractor. They shall include all deviations,

Page 86: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-14

modifications, or changes from the contract drawings, however minor, that were incorporated in the work, all additional work not appearing on the contract drawings, and all changes which are made after final inspection of the contract work. In the event the Contractor accomplishes additional work which changes the as-built condition of the facility after submission of the as-built drawings, the Contractor shall furnish revised and/or additional drawings as required to depict as-built conditions. The requirements for these additional drawings will be the same as for the as-built drawings included in the original submittal.

B. Red line as-built drawings: The Contractor shall have on his

staff, personnel to mark up a set of paper copy construction drawings to show the as-built conditions. These as-built marked copies shall be kept current and available on the job site at all times. All changes from the contract plans which are made in the work or additional information which might be uncovered in the course of construction shall be accurately and neatly recorded, as the events occur, by means of details and notes. The Contractor shall call attention to entries by redlining areas affected. The red line as-built will be jointly inspected for accuracy and completeness by the Contracting Officer's representative and a responsible representative of the Contractor prior to submittal of each request for payment. The Contracting Officer's approval of the current status of the as-built drawings shall be a prerequisite to the Contracting Officer's approval of request for progress payment and request for final payment under the contract. The drawings shall show the following information, but not be limited thereto: (1) The location and description of any utility lines or other

installations of any kind or description known to exist within the construction area. The location includes dimensions to permanent features.

(2) The location and dimensions of any changes within the

building or structures. (3) Correct grade or alignment of roads, structures or

utilities if any changes were made from contract plans. (4) Changes in details of design or additional information

obtained from working drawings specified to be prepared and/or furnished by the Contractor including but not limited to fabrication, erection, installation plans and

Page 87: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-15

placing details, pipe sizes, insulation material, dimensions of equipment foundations, etc.(

(5) All changes or modifications which result from the final

inspection.

(6) Options: Where contract drawings or specifications allow options, only the option selected for construction shall be shown on the as-built drawings.

(7) Extensions of Design: Shop Drawings such as structural

fabrication and erection drawings and fire alarm systems that will require extensive redrafting effort in order to create a electronic set will not be required to be incorporated into the electronic set. They will be included as an Appendix to the paper copy set.

C. Submittal of as-built drawings for review and approval: The Contractor shall participate in monthly review meetings with the Contracting Officer's Representative to show the progress made the preceding month and make all required changes. At time of final construction inspection, the Contractor shall submit one copy of the red lined as-built drawings to the Contracting Officer's Representative for review and approval. The as-built drawings shall be certified as to their correctness by the signature of an authorized representative of the Contractor. Upon Government approval of the Contractor's redlined copy of the as-built drawings, the Contractor shall prepare and provide two electronic sets of as-built drawings by incorporating the red line marked up notations on the construction drawings into the electronic set of solicitation drawings and amendments. In addition to the electronic sets of as-built drawings which shall be submitted on a CD-ROM, the Contractor shall also submit a full size set of as-built drawings on mylar. Submittals are to be to the Contracting Officer's Representative not later than ten (10) calendar days after project completion date.

D. Final Drawing Format. (1) The solicitation drawing files and any amendments thereto

will be furnished to the Contractor in electronic format. The solicitation drawing files have been prepared in MicroStation and/or AutoCAD format. The drawing file indicates the format which the drawing was developed. The As Built drawings shall reflect all changes made during construction as indicated by the red line marked up notations on the construction drawings.

Page 88: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-16

Revisions/redrafting shall match the font styles, sizes, and formats; line weights/thicknesses and styles/types; and all other drafting elements used on the solicitation drawing/amendments. All elements must be incorporated into each as-built drawing file; the use of reference files shall not be permitted. In addition, the Contractor will include the building number issued by Eglin AFB in the title block of the Final As-Built Drawings.

(2) As-built drawings will be submitted in a version of AutoCAD

that is coordinated with 96 CEG drafting section at the time of submission. The as-built DWG files shall have no reference files attached as all shall be bound into the file to make one AutoCAD DWG file, which also shall be purged and created with standard AutoCAD pen table. Scaled drawings should provide a bar scale and shall be in feet not meters. Contractor shall provide 1 hard copy of as-built drawings on Mylar on an Arch D sheet size and 2 CD’s in AutoCAD and PDF. Final As-Built drawings will include the assigned building number in the title block.

a. AutoCAD drawings shall have correct geometry:

1. Segmented lines and arcs are to be made continuous and free of self overlapping sections, thus decreasing files size and increasing efficiency within the AutoCAD platform.

2. All AutoCAD data shall be free of topological errors such as slivers, undershoots, overshoots dangles, overlaps, intersections, etc.

3. Area features such as building footprints, parking lots, roadways, and airfield pavements shall be true polyline polygons. Adjacent polygons will not have gaps or overlaps.

b. AutoCAD drawings shall be checked for correct spatial projection to one of the following: 1. North American Datum 1983 Florida State Plane North FIPS 0903 Feet (AutoCAD Code FL83-NF) 2. Universal Transverse Mercator 1984, Zone 16 North (AutoCAD Code UTM84-16N) c. Any Building Information Models (BIM) developed for a

project will be supplied in a Model Archive as part of the final as-built submittal consisting of two sets of

files:

Page 89: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-17

1. The first set shall be a collection of individual Models as received from the Model Element Author(s). 2. The second set of files will consist of the aggregate of those individual Models in a format suitable for archiving and viewing. The aggregate model will also be submitted in a DWG file format.

(3) All revisions made to the solicitation drawings and/or

amendment drawings to reflect changes made during construction shall be flagged in a numbered triangle and shall have the revision block completed as follows. The entry in the description column of the revision block shall read "AS-BUILT". The date of the revision and one approving initial from a responsible person within the Contractor's Firm shall also be included in the revision block. Above the drawing title block the drawing will be labeled in bold letters "AS-BUILT". The Contractor shall also furnish a revised index of drawings to match the actual design drawings. The drawing title blocks shall be in a uniform format to match the requirements as specified in the Design Manual.

(4) The two electronic sets of as-built drawing files shall

be submitted in AutoCAD format and two electronic sets of as built drawings shall be submitted in pdf.

(5) The hard copy reproducible set of as-built drawings shall be

submitted unbound on mylar. The drawings shall be full size.

E. Payment: No separate payment will be made for the as-built drawings required under this contract, and all costs in connection there-with will be considered a subsidiary obligation of the Contract. 3.6 ACCEPTANCE TEST

A. At the time "AS-Built" drawings and maintenance/operations manuals are submitted, the installing contractor shall submit a "Test Plan" describing procedures to be used to test the control system(s). The Test Plan shall include a Step-by-step description of all tests to be performed and shall indicate the type and location of test apparatus to be employed. The tests shall demonstrate that the operational and installation requirements of this specification have been met. All tests shall be conducted In the presence of the owner and shall not be conducted until the Test Plan has been approved.

Page 90: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-18

B. The tests shall demonstrate that the entire control system

functions as designed and intended. All circuits shall be tested: automatic actuation, solenoid and manual actuation, HVAC and power shutdowns, audible and visual alarm devices and manual override of abort functions. Supervision of all panel circuits including AC power and battery power supplies shall be tested and qualified.

C. A room pressurization test shall be conduc1ed, in each

protected space, to determine the presence of openings which would affect the agent concentration levels. The test(s) shall be conducted using the door fan system, or equivalent, with integrated computer program. All testing shall be In accordance with NFPA 2001.

D. If room pressurization testing indicates that openings

exist which would result in leaks and/or loss of the extinguishing agent, the installing contractor shall be responsible for coordinating the proper sealing of the protected space(s). The Owner shall be responsible for adequately sealing all protected space(s) against agent loss or leakage. The Installing contractor shall inspect all work to ascertain that the protected space(s) have been adequately and property sealed. THE SUPPRESSION SYSTEM INSTALLING CONTRACTOR SHALL BE RESPONSIBLE FOR THE SUCCESS OF THE ROOM PRESSURIZATION TESTS. If the first room pressurization test is not successful, in accordance with these specifications, the installing contractor shall provide direction on the cause of the test failure. The installing contractor shall conduct additional room pressurization tests, at no additional cost to the owner, until a successful test is obtained. Copies of successful test results shall be submitted to the owner for record. Upon acceptance by the Government, the completed system(s) shall be placed into service.

3.7 SYSTEM INSPECTIONS

A. The installing contractor shall provide two (2) inspections of each system, installed under this contract, during the one-year warranty period. The first inspection shall be at the six- month Interval, and the second inspection at the 12-month interval, after system acceptance. Inspections shall be conducted in accordance with the manufacturer's guidelines and the recommendations of NFPA 2001.

Page 91: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

15329-19

B. Documents certifying satisfactory system(s) operation

shall be submitted to the owner upon completion of each inspection.

3.8 WARRANTY

A. All system components furnished and Installed under this contract shall be warranted against defects in design, materials and workmanship for the full warranty period which is standard with the manufacturer, but in no case less than one (1) year from the date of system acceptance.

-- End of Section --

Page 92: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16050 - 1

SECTION 16050

BASIC ELECTRICAL MATERIALS AND METHODS PART 1 GENERAL 1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. Where approval by Underwriter’s Laboratories, Inc., is indicated, the contractor is given the option of submitting a certified test report from any nationally recognized testing agency adequately equipped and competent to perform the required services.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI C2 - National Electrical Safety Code

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

ASTM D 709 - Laminated Thermosetting Material

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS, INC. (IEEE)

IEEE 100 - Dictionary of Electrical and Electronics Terms

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA ICS 6 - Industrial Control and Systems Enclosures

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 - National Electrical Code DoD UNIFIED FACILITIES CODE (UFC) UFC 3-520-01 – Interior Electrical Systems

1.2 RELATED REQUIREMENTS

This section applies to all sections of Division 16, "Electrical," of this project specification unless specified otherwise in the individual sections.

1.3 DEFINITIONS

a. Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, shall be as defined in IEEE 100.

b. The technical sections referred to herein are those specification

sections that describe products, installation procedures, and equipment operations and that refer to this section for detailed description of submittal types.

c. The technical paragraphs referred to herein are those paragraphs

in PART 2 - PRODUCTS and PART 3 - EXECUTION of the technical sections that describe products, systems, installation procedures, equipment, and test methods.

Page 93: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16050 - 2

1.4 SUBMITTALS

Submittals required in the sections which refer to this section shall conform to the requirements of section entitled "Shop Drawings, Product Data, and Samples" and to the following additional requirements. Submittals shall include the manufacturer's name, trade name, place of manufacture, catalog model or number, nameplate data, size, layout dimensions, capacity, project specification and technical paragraph reference. Submittals shall also include applicable federal, military, industry, and technical society publication references, and years of satisfactory service, and other information necessary to establish contract compliance of each item to be provided. Photographs of existing installations are unacceptable and will be returned without approval.

1.4.1 Manufacturer's Catalog Data

Submittals for each manufactured item shall be current manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves, and catalog cuts. Handwritten and typed modifications and other notations not part of the manufacturer's preprinted data will result in the rejection of the submittal. Should manufacturer's data require supplemental information for clarification, the supplemental information shall be submitted as specified for certificates of compliance.

1.4.2 Drawings

Submit drawings a minimum of 14 inches by 20 inches in size. Include wiring diagrams and installation details of equipment indicating proposed location, layout and arrangement, control panels, accessories, piping, ductwork, and other items that must be shown to ensure a coordinated installation. Wiring diagrams shall identify circuit terminals and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment. Drawings shall indicate adequate clearance for operation, maintenance, and replacement of operating equipment devices.

1.4.3 Instructions

Where installation procedures or part of the installation procedures are required to be in accordance with manufacturer's instructions, submit printed copies of those instructions prior to installation. Installation of the item shall not proceed until manufacturer's instructions are received. Failure to submit manufacturer's instructions shall be cause for rejection of the equipment or material.

1.4.4 Certificates

Submit manufacturer's certifications as required for products, materials, finishes, and equipment as specified in the technical sections. Certificates from material suppliers are not acceptable. Preprinted certifications and copies of previously submitted documents will not be acceptable. The manufacturer's certifications shall name the appropriate products, equipment, or materials and the publication specified as controlling the quality of that item. Certification shall not contain statements to imply that the item does not meet requirements specified, such as "as good as"; "achieve the same end use and results as materials formulated in accordance with the referenced publications"; or "equal or exceed the service and performance of the specified material." Certifications shall simply state that the item conforms to

Page 94: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16050 - 3

the requirements specified. Certificates shall be printed on the manufacturer's letterhead and shall be signed by the manufacturer's official authorized to sign certificates of compliance.

1.4.4.1 Reference Standard Compliance

Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American National Standards Institute (ANSI), American Society for Testing and Materials (ASTM), National Electrical Manufacturers Association (NEMA), Underwriters Laboratories Inc. (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance.

1.4.4.2 Independent Testing Organization Certificate

In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. The certificate shall state that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.

1.4.5 Operation and Maintenance Manuals

Comply with the requirements of the technical sections. 1.4.5.1 Operating Instructions

Submit text of posted operating instructions for each system and principal item of equipment as specified in the technical sections.

1.5 QUALITY ASSURANCE 1.5.1 Material and Equipment Qualifications

Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products, which are of equal material, design and workmanship. Products shall have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period shall include applications of equipment and materials under similar circumstances and of similar size. The product shall have been on sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period. Where two or more items of the same class of equipment are required, these items shall be products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in the technical section.

1.5.2 Regulatory Requirements

Equipment, materials, installation, and workmanship shall be in accordance with the mandatory and advisory provisions of NFPA 70.

1.5.3 Alternative Qualifications

Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.

Page 95: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16050 - 4

1.5.4 Service Support

The equipment items shall be supported by service organizations, which are reasonably convenient to the equipment installation in order to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.

1.5.5 Manufacturer's Nameplate

Each item of equipment shall have a nameplate bearing the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable.

1.5.6 Modification of References

In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "shall" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer.

1.6 NAMEPLATES

ASTM D 709. Provide laminated plastic nameplates for each equipment enclosure, as specified in the technical sections or as indicated on the drawings. Each nameplate inscription shall identify the function and, when applicable, the position. Nameplates shall be melamine plastic, 0.125 inch thick, white with black center core. Surface shall be matte finish. Corners shall be square. Accurately align lettering and engrave into the core. Minimum size of nameplates shall be one by 2.5 inches. Lettering shall be a minimum of 0.25 inch high normal block style.

1.7 ELECTRICAL REQUIREMENTS

Electrical installations shall conform to ANSI C2, NFPA 70, and requirements specified herein.

1.8 INSTRUCTION TO GOVERNMENT PERSONNEL

Where specified in the technical sections, furnish the services of competent instructors to give full instruction to designated Government personnel in the adjustment, operation, and maintenance of the specified systems and equipment, including pertinent safety requirements as required. Instructors shall be thoroughly familiar with all parts of the installation and shall be trained in operating theory as well as practical operation and maintenance work. Instruction shall be given during the first regular work week after the equipment or system has been accepted and turned over to the Government for regular operation. When significant changes or modifications in the equipment or system are made under the terms of the contract, provide additional instructions to acquaint the operating personnel with the changes or modifications.

PART 2 PRODUCTS

Drawings indicate visually a general location of items. Contractor shall verify and coordinate with the Government on all actual and final locations of cabling, communications, conduits, displays, fixtures, indicators, lights, outlets, receptacles, sensors, switches, thermostats

Page 96: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16050 - 5

and other electrical items prior to any installation. PART 3 EXECUTION 3.1 PAINTING OF EQUIPMENT 3.1.1 Factory Applied

Electrical equipment shall have factory-applied painting systems which shall, as a minimum, meet the requirements of NEMA ICS 6 corrosion-resistance test and the additional requirements specified in the technical sections.

3.2 NAMEPLATE MOUNTING

Provide number, location, and letter designation of nameplates as indicated. Fasten nameplates to the device with a minimum of two sheet-metal screws or two rivets.

END OF SECTION

Page 97: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 1

SECTION 16402

INTERIOR DISTRIBUTION SYSTEM PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI C80.5 Aluminum Rigid Conduit (ARC)

ASTM INTERNATIONAL (ASTM)

ASTM B 1 Hard-Drawn Copper Wire

ASTM B 8 Concentric-Lay-Stranded Copper Conductors,

Hard, Medium-Hard, or Soft ASTM D 709 Laminated Thermosetting Materials

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE C2 National Electrical Safety Code

IEEE Std 100 The Authoritave Dictionary of IEEE Standards

Terms IEEE Std 81 Guide for Measuring Earth Resistivity, Ground

Impedance, and Earth Surface Potentials of a Ground System (Part 1) Normal Measurements

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA 250 Enclosures for Electrical Equipment (1000

Volts Maximum) NEMA C80.1 Rigid Steel Conduit - Zinc Coated (GRC)

NEMA C80.3 Electrical Metallic Tubing - Zinc Coated

(EMT) NEMA TC 2 Electrical Polyvinyl Chloride (PVC) Tubing

and Conduit NEMA TC 3 Polyvinyl Chloride PVC Fittings for Use with

Rigid PVC Conduit and Tubing

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) NFPA 70 National Electrical Code

NFPA 70E Electrical Safety in the Workplace

Page 98: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 2

DoD UNIFIED FACILITIES CODE (UFC)

UFC 3-520-01 Interior Electrical Systems

UNDERWRITERS LABORATORIES (UL) UL 1 Flexible Metal Conduit

UL 1063 Machine-Tools Wires and Cables

UL 360 Liquid-Tight Flexible Steel Conduits

UL 44 Thermoset-Insulated Wires and Cables

UL 486A-486B Wire Connectors

UL 486C Splicing Wire Connectors

UL 50 Enclosures for Electrical Equipment

UL 510 Polyvinyl Chloride, Polyethylene, and Rubber

Insulating Tape UL 514A Metallic Outlet Boxes

UL 514B Conduit, Tubing and Cable Fittings

UL 6 Rigid Metal Conduit

UL 651 Schedule 40 and 80 Rigid PVC Conduit

UL 6A Electrical Rigid Metal Conduit - Aluminum,

Bronze, and Stainless Steel UL 797 Electrical Metallic Tubing -- Steel

UL 83 Thermoplastic-Insulated Wires and Cables

1.2 DEFINITIONS Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, shall be as defined in IEEE Std 100.

1.3 SUBMITTALS The following shall be submitted in accordance with Section 01340 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES:

SD-03 Product Data

Conduit

Wiring

Page 99: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 3

SD-06 Test Reports

600-volt wiring test

1.4 QUALITY ASSURANCE 1.4.1 Regulatory Requirements In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "shall" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer. Equipment, materials, installation, and workmanship shall be in accordance with the mandatory and advisory provisions of NFPA 70 unless more stringent requirements are specified or indicated.

1.4.2 Standard Products Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship. Products shall have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period shall include applications of equipment and materials under similar circumstances and of similar size. The product shall have been on sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period. Where two or more items of the same class of equipment are required, these items shall be products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.

1.4.2.1 Alternative Qualifications Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.

1.4.2.2 Material and Equipment Manufacturing Date Products manufactured more than 3 years prior to date of delivery to site shall not be used, unless specified otherwise.

1.5 WARRANTY The equipment items shall be supported by service organizations which are reasonably convenient to the equipment installation in order to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.

PART 2 PRODUCTS 2.1 MATERIALS AND EQUIPMENT

Page 100: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 4

Materials, equipment, and devices shall, as a minimum, meet requirements of UL, where UL standards are established for those items, and requirements of NFPA 70 and UFC 3-520-01.

2.2 CONDUIT AND FITTINGS Shall conform to the following:

2.2.1 Rigid Metallic Conduit 2.2.1.1 Rigid, Threaded Zinc-Coated Steel Conduit NEMA C80.1, UL 6.

2.2.1.2 Rigid Aluminum Conduit ANSI C80.5, UL 6A.

2.2.2 Electrical, Zinc-Coated Steel Metallic Tubing (EMT) UL 797, NEMA C80.3.

2.2.3 Flexible Metal Conduit UL 1.

2.2.3.1 Liquid-Tight Flexible Metal Conduit, Steel UL 360.

2.2.4 Fittings for Metal Conduit, EMT, and Flexible Metal Conduit UL 514B. Ferrous fittings shall be cadmium- or zinc-coated in accordance with UL 514B.

2.2.4.1 Fittings for Rigid Metal Conduit and IMC Threaded-type. Split couplings unacceptable.

2.2.4.2 Fittings for EMT Steel compression type. Set screw type unacceptable.

2.2.5 Fittings for Rigid Nonmetallic Conduit NEMA TC 3 for PVC, and UL 514B.

2.3 OUTLET BOXES AND COVERS UL 514A, cadmium- or zinc-coated, if ferrous metal. UL 514C, if nonmetallic.

2.4 CABINETS, JUNCTION BOXES, AND PULL BOXES Volume greater than 100 cubic inches, UL 50, hot-dip, zinc-coated, if sheet steel.

Page 101: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 5

2.5 WIRES AND CABLES Wires and cables shall meet applicable requirements of NFPA 70 and UL for type of insulation, jacket, and conductor specified or indicated. Wires and cables manufactured more than 12 months prior to date of delivery to site shall not be used.

2.5.1 Conductors Conductors No. 8 AWG and larger diameter shall be stranded. Conductors No. 10 AWG and smaller diameter shall be solid, except that conductors for remote control, alarm, and signal circuits, classes 1, 2, and 3, shall be stranded unless specifically indicated otherwise. Conductor sizes and ampacities shown are based on copper, unless indicated otherwise. All conductors shall be copper.

2.5.1.1 Minimum Conductor Sizes Minimum size for branch circuits shall be No. 12 AWG; for Class 1 remote-control and signal circuits, No. 14 AWG; for Class 2 low-energy, remote-control and signal circuits, No. 16 AWG; and for Class 3 low-energy, remote-control, alarm and signal circuits, No. 22 AWG.

2.5.2 Insulation Unless specified or indicated otherwise or required by NFPA 70, wiring shall be 600-volt, Type THW conforming to UL 83, except that grounding wire may be type THW conforming to UL 83; remote-control and signal circuits shall be Type THW, conforming to UL 83. Where lighting fixtures require 90-degree Centigrade (C) conductors, provide only conductors with 90-degree C insulation or better.

2.5.4 Bonding Conductors ASTM B 1, solid bare copper wire for sizes No. 8 AWG and smaller diameter; ASTM B 8, Class B, stranded bare copper wire for sizes No. 6 AWG and larger diameter.

2.6 SPLICES AND TERMINATION COMPONENTS UL 486A-486B for wire connectors and UL 510 for insulating tapes. Connectors for No. 10 AWG and smaller diameter wires shall be insulated, pressure-type in accordance with UL 486A-486B or UL 486C (twist-on splicing connector). Provide solderless terminal lugs on stranded conductors.

2.7 MANUFACTURER'S NAMEPLATE Each item of equipment shall have a nameplate bearing the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable.

2.8 FIELD FABRICATED NAMEPLATES ASTM D 709. Provide laminated plastic nameplates for each equipment enclosure, relay, switch, and device; as specified or as indicated on the drawings. Each nameplate inscription shall identify the function and, when

Page 102: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 6

applicable, the position. Nameplates shall be melamine plastic, 0.125 inch thick, white with black center core. Surface shall be matte finish. Corners shall be square. Accurately align lettering and engrave into the core. Minimum size of nameplates shall be one by 2.5 inches. Lettering shall be a minimum of 0.25 inch high normal block style.

2.9 FIRESTOPPING MATERIALS Provide firestopping around electrical penetrations.

2.10 FACTORY APPLIED FINISH Electrical equipment shall have factory-applied painting systems which shall, as a minimum, meet the requirements of NEMA 250 corrosion-resistance test and the additional requirements as specified herein. Interior and exterior steel surfaces of equipment enclosures shall be thoroughly cleaned and then receive a rust-inhibitive phosphatizing or equivalent treatment prior to painting. Exterior surfaces shall be free from holes, seams, dents, weld marks, loose scale or other imperfections. Interior surfaces shall receive not less than one coat of corrosion-resisting paint in accordance with the manufacturer's standard practice. Exterior surfaces shall be primed, filled where necessary, and given not less than two coats baked enamel with semigloss finish. Equipment located indoors shall be ANSI Light Gray. Provide manufacturer's coatings for touch-up work and as specified in paragraph FIELD APPLIED PAINTING.

PART 3 EXECUTION 3.1 INSTALLATION Electrical installations, including weatherproof and hazardous locations and ducts, plenums and other air-handling spaces, shall conform to requirements of NFPA 70 and IEEE C2 and to requirements specified herein.

3.1.1.1 Labels Wherever work results in service entrance disconnect devices in more than one enclosure, as permitted by NFPA 70, each enclosure, new and existing, shall be labeled as one of several enclosures containing service entrance disconnect devices. Label, at minimum, shall indicate number of service disconnect devices housed by enclosure and shall indicate total number of enclosures that contain service disconnect devices. Provide laminated plastic labels conforming to paragraph FIELD FABRICATED NAMEPLATES. Use lettering of at least 0.25 inch in height, and engrave on black-on-white matte finish. Service entrance disconnect devices in more than one enclosure, shall be provided only as permitted by NFPA 70.

3.1.2 Wiring Methods Provide insulated conductors installed in rigid steel conduit, IMC, rigid nonmetallic conduit, or EMT, except where specifically indicated or specified otherwise or required by NFPA 70 to be installed otherwise. Grounding conductor shall be separate from electrical system neutral conductor. Provide insulated green equipment grounding conductor for circuit(s) installed in conduit and raceways. Minimum conduit size shall be 1/2 inch in diameter for low voltage lighting and power circuits. Vertical distribution in multiple story buildings shall be made with metal conduit in

Page 103: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 7

fire-rated shafts. Metal conduit shall extend through shafts for minimum distance of 6 inches. Conduit which penetrates fire-rated walls, fire-rated partitions, or fire-rated floors shall be firestopped.

3.1.2.1 Conductors All electrical wiring shall be installed in conduits.

3.1.3 Conduit Installation All electrical conduits shall be located inside wall cavities. Keep conduit minimum 6 inches away from parallel runs of flues and steam or hot water pipes. Install conduit parallel with or at right angles to ceilings, walls, and structural members where located above accessible ceilings and where conduit will be visible after completion of project.

3.1.3.1 Restrictions Applicable to Aluminum Conduit

a. Do not install underground or encase in concrete or masonry.

b. Do not use brass or bronze fittings.

c. Do not use when the enclosed conductors must be shielded from the effects of High-altitude Electromagnetic Pulse (HEMP).

3.1.3.2 Restrictions Applicable to EMT

a. Do not install underground.

b. Do not encase in concrete, mortar, grout, or other cementitious materials.

c. Do not use in areas subject to severe physical damage including but

not limited to equipment rooms where moving or replacing equipment could physically damage the EMT.

d. Do not use in hazardous areas.

e. Do not use outdoors.

f. Do not use in fire pump rooms.

g. Do not use when the enclosed conductors must be shielded from the

effects of High-altitude Electromagnetic Pulse (HEMP).

h. All electrical conduits shall be located inside wall cavities. 3.1.3.3 Restrictions Applicable to Nonmetallic Conduit

a. PVC Schedule 40 and PVC Schedule 80

(1) Do not use in areas where subject to severe physical damage, including but not limited to, mechanical equipment rooms, electrical equipment rooms, hospitals, power plants, missile magazines, and other such areas.

(2) Do not use in hazardous (classified) areas.

Page 104: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 8

(3) Do not use in fire pump rooms.

(4) Do not use in penetrating fire-rated walls or partitions, or fire-rated floors.

(5) Do not use above grade, except where allowed in this section for rising through floor slab or indicated otherwise.

(6) Do not use when the enclosed conductors must be shielded from the effects of High-altitude Electromagnetic Pulse (HEMP).

3.1.3.4 Conduit Support Support conduit by pipe straps, wall brackets, hangers, or ceiling trapeze. Fasten by wood screws to wood; by toggle bolts on hollow masonry units; by concrete inserts or expansion bolts on concrete or brick; and by machine screws, welded threaded studs, or spring-tension clamps on steel work. Threaded C-clamps may be used on rigid steel conduit only. Do not weld conduits or pipe straps to steel structures. Load applied to fasteners shall not exceed one-fourth proof test load. Fasteners attached to concrete ceiling shall be vibration resistant and shock-resistant. Holes cut to depth of more than 1 1/2 inches in reinforced concrete beams or to depth of more than 3/4 inch in concrete joints shall not cut main reinforcing bars. Fill unused holes. In partitions of light steel construction, use sheet metal screws. In suspended-ceiling construction, run conduit above ceiling. Do not support conduit by ceiling support system. Conduit and box systems shall be supported independently of both (a) tie wires supporting ceiling grid system, and (b) ceiling grid system into which ceiling panels are placed. Supporting means shall not be shared between electrical raceways and mechanical piping or ducts. Installation shall be coordinated with above-ceiling mechanical systems to assure maximum accessibility to all systems. Where conduit crosses building expansion joints, provide suitable expansion fitting that maintains conduit electrical continuity by bonding jumpers or other means. For conduits greater than 2 1/2 inches inside diameter, provide supports to resist forces of 0.5 times the equipment weight in any direction and 1.5 times the equipment weight in the downward direction.

3.1.3.5 Directional Changes in Conduit Runs Make changes in direction of runs with symmetrical bends or cast-metal fittings. Make field-made bends and offsets with hickey or conduit-bending machine. Do not install crushed or deformed conduits. Avoid trapped conduits. Prevent plaster, dirt, or trash from lodging in conduits, boxes, fittings, and equipment during construction. Free clogged conduits of obstructions.

3.1.3.6 Locknuts and Bushings Fasten conduits to sheet metal boxes and cabinets with two locknuts where required by NFPA 70, where insulated bushings are used, and where bushings cannot be brought into firm contact with the box; otherwise, use at least minimum single locknut and bushing. Locknuts shall have sharp edges for digging into wall of metal enclosures. Install bushings on ends of conduits, and provide insulating type where required by NFPA 70.

Page 105: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 9

3.1.3.7 Flexible Connections Provide flexible steel conduit between 3 and 6 feet in length for equipment subject to vibration, noise transmission, or movement; and for motors. Install flexible conduit to allow 20 percent slack. Minimum flexible steel conduit size shall be 1/2 inch diameter. Provide liquidtight flexible conduit in wet and damp locations for equipment subject to vibration, noise transmission, movement or motors. Provide separate ground conductor across flexible connections.

3.1.4 Boxes, Outlets, and Supports Provide boxes in wiring and raceway systems wherever required for pulling of wires, making connections, and mounting of devices or fixtures. Boxes for metallic raceways shall be cast-metal, hub-type when located in wet locations, when surface mounted on outside of exterior surfaces, and when specifically indicated. Boxes in other locations shall be sheet steel, except that aluminum boxes may be used with aluminum conduit. Each box shall have volume required by NFPA 70 for number of conductors enclosed in box. Provide gaskets for cast-metal boxes installed in wet locations and boxes installed flush with outside of exterior surfaces. Fasten boxes and supports with wood screws on wood, with bolts and expansion shields on concrete or brick, with toggle bolts on hollow masonry units, and with machine screws or welded studs on steel. When penetrating reinforced concrete members avoid cutting reinforcing steel.

3.1.4.1 Boxes Boxes for use with raceway systems shall be minimum 1 1/2 inches deep, except where shallower boxes required by structural conditions are approved. Boxes shall be minimum 4 inches square, except that 4 by 2 inch boxes may be used where only one raceway enters outlet.

3.1.4.2 Pull Boxes Construct of at least minimum size required by NFPA 70 of code-gauge aluminum or galvanized sheet steel, and compatible with nonmetallic raceway systems, except where cast-metal boxes are required in locations specified herein. Provide boxes with screw-fastened covers. Where several feeders pass through common pull box, tag feeders to indicate clearly electrical characteristics, circuit number, and panel designation.

3.1.5 Mounting Heights Mount panelboards, enclosed circuit breakers, motor controller and disconnecting switches so height of operating handle at its highest position is maximum 78 inches above floor.

3.1.6 Conductor Identification Provide conductor identification within each enclosure where tap, splice, or termination is made. For conductors No. 6 AWG and smaller diameter, color coding shall be by factory-applied, color-impregnated insulation. For conductors No. 4 AWG and larger diameter, color coding shall be by plastic-coated, self-sticking markers; colored nylon cable ties and plates; or heat shrink-type sleeves. Identify control circuit terminations in accordance with manufacturer's recommendations.

Page 106: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 10

3.1.6.1 Marking Strips White or other light-colored plastic marking strips, fastened by screws to each terminal block, shall be provided for wire designations. The wire numbers shall be made with permanent ink. The marking strips shall be reversible to permit marking both sides, or two marking strips shall be furnished with each block. Marking strips shall accommodate the two sets of wire numbers. Each device to which a connection is made shall be assigned a device designation in accordance with NEMA ICS 1 and each device terminal to which a connection is made shall be marked with a distinct terminal marking corresponding to the wire designation used on the Contractor's schematic and connection diagrams. The wire (terminal point) designations used on the Contractor's wiring diagrams and printed on terminal block marking strips may be according to the Contractor's standard practice; however, additional wire and cable designations for identification of remote (external) circuits shall be provided for the Government's wire designations. Prints of the marking strips drawings submitted for approval will be so marked and returned to the Contractor for addition of the designations to the terminal strips and tracings, along with any rearrangement of points required.

3.1.7 Splices Make splices in accessible locations. Make splices in conductors No. 10 AWG and smaller diameter with insulated, pressure-type connector. Make splices in conductors No. 8 AWG and larger diameter with solderless connector, and cover with insulation material equivalent to conductor insulation.

3.1.8 Electrical Penetrations Seal openings around electrical penetrations through fire resistance-rated walls, partitions, floors, or ceilings.

3.1.9 Grounding and Bonding Provide In accordance with NFPA 70. Ground exposed non-current-carrying metallic parts of electrical equipment, metallic raceway systems, grounding conductor in metallic and nonmetallic raceways, and neutral conductor of wiring systems. Make ground connection to driven ground rods on exterior of building. In addition to the requirements specified herein.

3.1.10 Workmanship Lay out work in advance. Exercise care where cutting, channeling, chasing, or drilling of floors, walls, partitions, ceilings, or other surfaces is necessary for proper installation, support, or anchorage of conduit, raceways, or other electrical work. Repair damage to buildings, piping, and equipment using skilled craftsmen of trades involved.

3.2 FIELD FABRICATED NAMEPLATE MOUNTING Provide number, location, and letter designation of nameplates as indicated. Fasten nameplates to the device with a minimum of two sheet-metal screws or two rivets.

3.3 FIELD APPLIED PAINTING

Page 107: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

16402 - 11

Paint electrical equipment as required to match finish of adjacent surfaces or to meet the indicated or specified safety criteria.

3.4 FIELD QUALITY CONTROL Furnish test equipment and personnel and submit written copies of test results. Give Contracting Officer 5 working days notice prior to each test.

3.4.1 Devices Subject to Manual Operation Each device subject to manual operation shall be operated at least five times, demonstrating satisfactory operation each time.

3.4.2 600-Volt Wiring Test Test wiring rated 600 volt and less to verify that no short circuits or accidental grounds exist. Perform insulation resistance tests on wiring No. 6 AWG and larger diameter using instrument which applies voltage of approximately 500 volts to provide direct reading of resistance. Minimum resistance shall be 250,000 ohms.

END OF SECTION

Page 108: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

AF Form 66, OCT 89 PREVIOUS EDITION WILL BE USED 01340-2

PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

SCHEDULE OF MATERIAL SUBMITTALS FTFA 94-1196 Addition to Bldg 3105, Duke Field

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATORNUMBER OF COPIES REQUIRED

LIN

E N

UM

BE

R

ITEM OR DESCRIPTION OF ITEMCONTRACT REFERENCE, TYPE OF

SUBMITTAL

RE

QU

IRE

D S

UB

MIS

SIO

ND

ATE

DA

TE R

EC

EIV

ED

IN

CO

NTR

AC

TIN

G

DA

TE T

O C

IVIL

E

NG

INE

ER

ING

RE

TUR

N S

US

PE

NS

E

DA

TE

SU

BM

ITTA

L N

UM

BE

RS

DATE CONTRACTOR NOTIFIED

CO

NTR

AC

TOR

R

ES

UB

MIT

TAL

FIN

AL

AP

PR

OV

AL

REMARKS

APPROVEDDIS-

APPROVED

1SCHEDULINGSEC 01011 PAR 1.9 5

2CONFORMANCE SEC 01011 PAR 1.11 5

3MATERIALS/EQUIPMENT SEC 01011 PAR 1.13 5 5 5

4RECOMMENDATIONS SEC 01011 PAR 1.18 5

5RECORD DOCUMENTS SEC 01011 PAR 1.22 5 5 5

6HAZARDOUS MATERIALS SEC 01500 PAR 1.3 5

7PRODUCT SOURCES & INFOSEC 01540 PAR 1.3 5 5

8DEWATERING METHOD SEC 02222 PAR 1.5 5

9MATERIALS/EQUIPMENT SEC 02222 PAR 1.5 5

10SHEETING/DESIGN SEC 02222 PAR 1.5 5

11VALVES/PIPING/FITTINGS SEC 02602 PAR 1.4 5

12DEPARTURE FROM ORIGINALSEC 15010 PAR 1.3 5

SD

-04

SA

MP

LES

SD-0

9 M

FR'S

FIE

LD R

EPO

RTS

SD-1

0 O

PER

ATIO

N &

MAI

NT.

DAT

A

SD-1

1 C

LOSE

OU

T SU

BMIT

TALS

SD

-08

MFR

'S IN

STR

UC

TIO

NS

SD

-01

PR

EC

ON

STR

UC

TIO

N S

UB

.

SD

-05

DE

SIG

N D

ATA

SD

-06

TES

T R

EP

OR

TS

SD

-07

CE

RTI

CIA

TES

SD

-02

SH

OP

DR

AW

ING

S

SD

-03

PR

OD

UC

T D

ATA

Page 109: PROJECT NO. FTFA 94-1196 SPECIFICATION NO. 09AN DRAWING NO. 09AN FINAL … · 2016-08-26 · project no. ftfa 94-1196 specification no. 09an . drawing no. 09an . final submittal

AF Form 66, OCT 89 PREVIOUS EDITION WILL BE USED 01340-3

PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

SCHEDULE OF MATERIAL SUBMITTALS FTFA 94-1196 Addition to Bldg 3105, Duke Field

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATORNUMBER OF COPIES REQUIRED

LIN

E N

UM

BE

R

ITEM OR DESCRIPTION OF ITEMCONTRACT REFERENCE, TYPE OF

SUBMITTAL

RE

QU

IRE

D S

UB

MIS

SIO

ND

ATE

DA

TE R

EC

EIV

ED

IN

CO

NTR

AC

TIN

G

DA

TE T

O C

IVIL

E

NG

INE

ER

ING

RE

TUR

N S

US

PE

NS

E

DA

TE

SU

BM

ITTA

L N

UM

BE

RS

DATE CONTRACTOR NOTIFIED

CO

NTR

AC

TOR

R

ES

UB

MIT

TAL

FIN

AL

AP

PR

OV

AL

REMARKS

APPROVEDDIS-

APPROVEDSD

-04

SA

MP

LES

SD-0

9 M

FR'S

FIE

LD R

EPO

RTS

SD-1

0 O

PER

ATIO

N &

MAI

NT.

DAT

A

SD-1

1 C

LOSE

OU

T SU

BMIT

TALS

SD

-08

MFR

'S IN

STR

UC

TIO

NS

SD

-01

PR

EC

ON

STR

UC

TIO

N S

UB

.

SD

-05

DE

SIG

N D

ATA

SD

-06

TES

T R

EP

OR

TS

SD

-07

CE

RTI

CIA

TES

SD

-02

SH

OP

DR

AW

ING

S

SD

-03

PR

OD

UC

T D

ATA

13MATERIALS/EQUIPMENTSEC 15010 PAR 1.8 5 5 5 5 5

14OPERATION & MAINTENANCESEC 15010 PAR 1.17 5

15PROJECT RECORDSEC 15010 PAR 1.20 5 5 5 5

16WET PIPE SPRINKLER SEC 15325 PAR 1.5 5 5 5 5 5 5 5 5

17FIRE SUPPRESSION SYS SEC 15329 PAR 1.5 5 5 5 5 5 5 5 5

18INTERIOR DIST SYS SEC 16402 PAR 1.3 5

5