121
316 W. Millbrook Road, Suite 201 Raleigh, North Carolina 27609-4482 Office: 919-872-7866 Fax: 919-872-4486 www.RaymondLLC.com COA# C-4282 License 53143 PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL ROOF REPLACEMENT 1601 Johnson St. High Point, NC 27626 Prepared For GUILFORD COUNTY SCHOOLS 712 North Eugene Street Greensboro, NC 27401 RAYMOND PROJECT NO. RAL1173.001 Prepared By RAYMOND ENGINEERING-GEORGIA, INC. RALEIGH, NORTH CAROLINA June 21, 2021 BID SET ________________________________ Jason Mobraten, RA, RRC, REWC, LEED AP Eric Meehan, PE, RRO 6/21/21

PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

316 W. Millbrook Road, Suite 201

Raleigh, North Carolina 27609-4482

Office: 919-872-7866

Fax: 919-872-4486

www.RaymondLLC.com

COA# C-4282

License 53143

PROJECT MANUAL FOR

JOHNSON ST. ELEMENTARY SCHOOL

ROOF REPLACEMENT

1601 Johnson St.

High Point, NC 27626

Prepared For

GUILFORD COUNTY SCHOOLS

712 North Eugene Street

Greensboro, NC 27401

RAYMOND PROJECT NO. RAL1173.001

Prepared By

RAYMOND ENGINEERING-GEORGIA, INC. RALEIGH, NORTH CAROLINA

June 21, 2021

BID SET

________________________________

Jason Mobraten, RA, RRC, REWC, LEED AP

Eric Meehan, PE, RRO

6/21/21

Page 2: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Table of Contents 00 01 10 1

SECTION 00 01 10

TABLE OF CONTENTS

Division 0 – Procurement and Contracting Requirements

Section 00 00 00 – Cover Page

Section 00 01 10 – Table of Contents

Section 01 01 13 – Advertisement

Section 00 42 00 – Form of Proposal

AIA Document A101-2017 - Exhibit A - Insurance and Bonds

AIA Document A104-2017 - Standard Abbreviated Form of Agreement Between Owner and Contractor

Division 1 – General Requirements

Section 01 11 00 – Summary of Work

Section 01 22 13 – Unit Prices and Allowances

Section 01 23 00 – Alternates

Section 01 32 26 – Progress Reports

Section 01 33 00 – Submittals and Submittal Checklist

Section 01 42 19 – Reference Standards

Section 01 45 00 – Quality Control

Section 01 50 00 – Temporary Facilities and Controls

Section 01 60 00 – Product Requirements

Section 01 66 00 – Storage and Protection

Section 01 74 00 – Cleaning

Section 01 77 00 – Project Closeout Procedures

Section 01 78 36 – Guarantees

Section 01 78 39 – Project Record Documents

Division 2 – Existing Conditions

Section 02 41 13 – Selective Demolition and Preparations

Division 6 – Wood and Plastics

Section 06 10 53 – Miscellaneous Rough Carpentry

Division 7 – Thermal and Moisture Protection

Section 07 22 16 – Roof Board Insulation

Section 07 52 16 – SBS Modified Bituminous Roofing

Section 07 54 19 – Polyvinyl Chloride Roofing

Section 07 60 00 – Flashing and Sheet Metal

Section 07 92 00 – Joint Sealants

Division 8 – Openings

Section 08 62 00 – Plastic Glazed Unit Skylights

Division 15 – Plumbing

Section 15 42 20 – Roof Drains

Drawings

Page 3: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Table of Contents 00 01 10 2

G-001 Cover Page

G-002 General Notes

G-003 UL Penetration Assemblies

A-101 Roof Plan

A-102 Tapered Insulation Plan

A-103 Wind Uplift Pressures

A-501 Typical Details

A-502 Typical Details

Page 4: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Guilford County Schools

ADVERTISEMENT FOR BIDS Johnson St. Global Roof Replacement

1601 Johnson St., High Point, NC 27262

Sealed bids will be received by the Guilford County School Purchasing Department until 2:00 p.m. EST on Tuesday, July 27,

2021 at 501 W. Washington Street, Greensboro, NC 27401, to furnish all materials and labor for the Roof Replacement Project at

Johnson St. Global. Please allow sufficient time for this, as late bids will not be accepted.

Complete electronic plans and specifications for this project can be obtained from Raymond Engineering, Suite 201, 316 W.

Millbrook Road, Raleigh, North Carolina 27609-4482; 919-872-7866, during normal office hours.

A mandatory pre-bid conference will be held for all interested bidders at 11:00 a.m. on July 14, 2021. Please meet at the project

site outside of the main entrance. Please email one day in advance to indicate you will be participating at

[email protected]. Bids will not be accepted from contractors that were not represented at this meeting by an

employee on their payroll staff. Bidders must be properly licensed for the work in accordance with Section 87 of the North

Carolina General Statutes.

E-Verify Requirements: This project requires the awarded vendor to comply with the requirements of E-Verify. (U.S. law requiring

companies to employ only individuals who may legally work in the United States – either U.S. citizens, or foreign citizens who

have the necessary authorization.)

Minority businesses are encouraged to submit bids for this project. The appropriate forms from the section entitled “Participation

by Women and Minority Owned Businesses” must be submitted with each bid to show good faith efforts to obtain Minority and

Women Owned Business Enterprise participation.

The Guilford County Board of Education awards public contracts without regard to race, religion, color, creed, national origin,

sex, age or handicapped condition as defined by North Carolina General Statutes, Section 168A-3. The Board reserves the right

to reject any or all bids presented and to waive any informalities and irregularities.

Guilford County Schools

Shayla Parker

Director of Purchasing

Page 5: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Johnson St. Elementary School Roof Replacement

Form of Proposal Section 00 42 00 1 of 6

F O R M OF P R O P O S A L

Johnson St. Elementary School

Roof Replacement

Bidder:

Date:

The undersigned, as bidder, hereby declares that the only person or persons interested in this proposal as principal or principals is or are named herein and that no other person than herein mentioned has any interest in this proposal or in the contract to be entered into; that this proposal is made without connection with any other person, company or parties making a bid or proposal; and that it is in all respects fair and in good faith without collusion or fraud. The bidder further declares that he has examined the site of the work and the contract documents relative thereto, and has read all special provisions furnished prior to the opening of bids; that he has satisfied himself relative to the work to be performed.

The Bidder proposes and agrees if this proposal is accepted to contract with

Guilford County Schools

in the form of contract specified below, to furnish all necessary materials, equipment, machinery, tools, apparatus, means of transportation and labor necessary to complete the construction of

Johnson St. Elementary School Roof Replacement

in full in complete accordance with the plans, specifications, and contract documents, to the full and entire satisfaction of

Guilford County Schools

with a definite understanding that no money will be allowed for extra work except as set forth in the General Conditions and the contract documents, for the sum of:

Page 6: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Johnson St. Elementary School Roof Replacement

Form of Proposal Section 00 42 00 2 of 6

BASE BID – ROOF A:

TOTAL BASE BID

Dollars ($ )

ALTERNATE BIDS:

Alternate 1: Roof Area B Roof Replacement (Single-ply System):

(Add) Dollars ($)

Alternate 2: Replacement of all dome skylights and associated flashings at Roof Area A:

(Add) Dollars ($)

Alternate 3: Remove and replace existing roof system at Roof Area A with new modified bituminous system in lieu of single-ply system:

(Add) Dollars ($)

Alternate 4: Roof Area B Roof Replacement (Modified Bituminous System) in lieu of Alternate 1:

(Add) Dollars ($)

Page 7: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Johnson St. Elementary School Roof Replacement

Form of Proposal Section 00 42 00 3 of 6

UNIT PRICES Unit Prices quoted and accepted shall apply throughout the life of the contract, except as otherwise specifically noted. Unit prices shall be applied, as appropriate, to compute the total value of changes in the quantity of the work all in accordance with the contract documents. In the event of a discrepancy in the mathematical extensions of unit prices, the extended price shall be corrected per the unit price shown. In the event of a discrepancy in the addition of extended and lump sum prices, the subtotal shall be corrected based on the extended and lump sum prices shown. Should the actual quantities be increased or decreased relative to the estimated quantities included in the Base Bid, the Unit Prices shown in the Base Bid will be used to adjust the contract price in accordance with the contract documents, throughout the life of the contract. The bidder further proposes and agrees hereby to commence work under this contract on a date to be specified in a written order of the designer and shall fully complete all work thereunder within the time specified. Applicable monetary liquidated damages may be applied. No. 1: Replace any deteriorated or damaged wood blocking Unit Price ($) per b.f.

No. 2: Repair any deteriorated or damaged gypsum deck Unit Price ($) per s.f.

No. 3: Patching deteriorated or damaged concrete deck Unit Price ($) per s.f.

No. 4: Replace deteriorated or damaged roof drains Unit Price ($) each

Page 8: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Johnson St. Elementary School Roof Replacement

Form of Proposal Section 00 42 00 4 of 6

PROPOSAL SIGNATURE PAGE The undersigned further agrees that in the case of failure on his part to execute the said contract and the bonds within ten (10) consecutive calendar days after being given written notice of the award of contract, the certified check, cash or bid bond accompanying this bid shall be paid into the funds of the owner's account set aside for the project, as liquidated damages for such failure; otherwise the certified check, cash or bid bond accompanying this proposal shall be returned to the undersigned. Respectfully submitted this __________ day of __________________

(Name of firm or corporation making bid) WITNESS: By: Signature Name:

(Proprietorship or Partnership) Print or type Title (Owner/Partner/Pres./V.Pres) Address

ATTEST:

By: License No.

Title: Federal I.D. No.

(Corp. Sec. or Asst. Sec. only) Email Address:

(CORPORATE SEAL) Addendum received and used in computing bid: Addendum No. 1 Addendum No. 2 Addendum No. 3 Addendum No. 4 Addendum No. 5 Addendum No. 6

Page 9: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Johnson St. Elementary School Roof Replacement

Form of Proposal Section 00 42 00 5 of 6

PVC ROOF SYSTEM MANUFACTURER'S CERTIFICATE

for

JOHNSON ST. ELEMENTARY SCHOOL ROOF REPLACEMENT

TO: Guilford County Schools

The undersigned manufacturer of the specified roof system and related roof system materials has reviewed the plans and technical specifications for this project; and hereby certifies that: (1) their roof system(s) and component materials are suitable for the roofs of this project, (2) their roof membrane and related roof system materials are suitable for use with each

other and that the new roof membrane and new roof system materials specified will be included in the membrane manufacturer’s warranty as specified (see specification section 01 78 36),

(3) the roofing contractor named below is an authorized applicator of their roof system and

related roof system materials, has been trained by the manufacturer in the installation of the roof system specified and, subject to the Owner's award of construction contract, is authorized to install said system,

(4) the roof membrane manufacturer will provide bi-weekly inspection and additional training

(if needed) to the roofing contractor until completion of the roof system.

Contractor:

Name

Address

Manufacturer:

Name

Address

Authorized Signature

Date

Page 10: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Johnson St. Elementary School Roof Replacement

Form of Proposal Section 00 42 00 6 of 6

MODIFIED BITUMINOUS ROOF SYSTEM MANUFACTURER'S CERTIFICATE

for

JOHNSON ST. ELEMENTARY SCHOOL ROOF REPLACEMENT

TO: Guilford County Schools

The undersigned manufacturer of the specified roof system and related roof system materials has reviewed the plans and technical specifications for this project; and hereby certifies that: (1) their roof system(s) and component materials are suitable for the roofs of this project, (2) their roof membrane and related roof system materials are suitable for use with each

other and that the new roof membrane and new roof system materials specified will be included in the membrane manufacturer’s warranty as specified (see specification section 01 78 36),

(3) the roofing contractor named below is an authorized applicator of their roof system and

related roof system materials, has been trained by the manufacturer in the installation of the roof system specified and, subject to the Owner's award of construction contract, is authorized to install said system,

(4) the roof membrane manufacturer will provide bi-weekly inspection and additional training

(if needed) to the roofing contractor until completion of the roof system.

Contractor:

Name

Address

Manufacturer:

Name

Address

Authorized Signature

Date

Page 11: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA®

Document A101TM – 2017

Exhibit A

Insurance and Bonds

AIA Document A101™ – 2017 Exhibit A. Copyright © 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA®

Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document,

or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the

law. This draft was produced by AIA software at 15:45:15 on 01/24/2018 under Order No.5291788124 which expires on 07/12/2018, and is not

for resale.

User Notes: (1698911027)

1

ADDITIONS AND DELETIONS:

The author of this document

has added information

needed for its completion.

The author may also have

revised the text of the

original AIA standard form.

An Additions and Deletions

Report that notes added

information as well as

revisions to the standard

form text is available from

the author and should be

reviewed.

This document has important

legal consequences.

Consultation with an

attorney is encouraged with

respect to its completion

or modification.

This document is intended

to be used in conjunction

with AIA Document A201™–

2017, General Conditions of

the Contract for

Construction. Article 11 of

A201™–2017 contains

additional insurance

provisions.

ELECTRONIC COPYING of any

portion of this AIA® Document

to another electronic file is

prohibited and constitutes a

violation of copyright laws

as set forth in the footer of

this document.

This Insurance and Bonds Exhibit is part of the Agreement, between the Owner and the

Contractor, dated the « » day of « » in the year « »

(In words, indicate day, month and year.)

for the following PROJECT:

(Name and location or address)

« »

«»

THE OWNER: (Name, legal status and address)

« »« »

« »

THE CONTRACTOR: (Name, legal status and address)

« »« »

« »

TABLE OF ARTICLES A.1 GENERAL A.2 OWNER’S INSURANCE A.3 CONTRACTOR’S INSURANCE AND BONDS A.4 SPECIAL TERMS AND CONDITIONS

ARTICLE A.1 GENERAL The Owner and Contractor shall purchase and maintain insurance, and provide bonds, as

set forth in this Exhibit. As used in this Exhibit, the term General Conditions refers to

AIA Document A201™–2017, General Conditions of the Contract for Construction.

ARTICLE A.2 OWNER’S INSURANCE § A.2.1 General Prior to commencement of the Work, the Owner shall secure the insurance, and provide

evidence of the coverage, required under this Article A.2 and, upon the Contractor’s

request, provide a copy of the property insurance policy or policies required by Section

A.2.3. The copy of the policy or policies provided shall contain all applicable conditions,

definitions, exclusions, and endorsements.

§ A.2.2 Liability Insurance The Owner shall be responsible for purchasing and maintaining the Owner’s usual

general liability insurance.

Page 12: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A101™ – 2017 Exhibit A. Copyright © 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA®

Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document,

or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the

law. This draft was produced by AIA software at 15:45:15 on 01/24/2018 under Order No.5291788124 which expires on 07/12/2018, and is not

for resale.

User Notes: (1698911027)

2

§ A.2.3 Required Property Insurance § A.2.3.1 Unless this obligation is placed on the Contractor pursuant to Section A.3.3.2.1, the Owner shall purchase

and maintain, from an insurance company or insurance companies lawfully authorized to issue insurance in the

jurisdiction where the Project is located, property insurance written on a builder's risk “all-risks” completed value or

equivalent policy form and sufficient to cover the total value of the entire Project on a replacement cost basis. The

Owner’s property insurance coverage shall be no less than the amount of the initial Contract Sum, plus the value of

subsequent Modifications and labor performed and materials or equipment supplied by others. The property

insurance shall be maintained until Substantial Completion and thereafter as provided in Section A.2.3.1.3, unless

otherwise provided in the Contract Documents or otherwise agreed in writing by the parties to this Agreement. This

insurance shall include the interests of the Owner, Contractor, Subcontractors, and Sub-subcontractors in the Project

as insureds. This insurance shall include the interests of mortgagees as loss payees.

§ A.2.3.1.3 Unless the parties agree otherwise, upon Substantial Completion, the Owner shall continue the insurance

required by Section A.2.3.1 or, if necessary, replace the insurance policy required under Section A.2.3.1 with

property insurance written for the total value of the Project that shall remain in effect until expiration of the period

for correction of the Work set forth in Section 12.2.2 of the General Conditions.

§ A.2.3.1.4 Deductibles and Self-Insured Retentions. If the insurance required by this Section A.2.3 is subject to

deductibles or self-insured retentions, the Owner shall be responsible for all loss not covered because of such

deductibles or retentions.

§ A.2.3.2 Insurance for Existing Structures If the Work involves remodeling an existing structure or constructing an addition to an existing structure, the Owner

shall purchase and maintain, until the expiration of the period for correction of Work as set forth in Section 12.2.2 of

the General Conditions, “all-risks” property insurance, on a replacement cost basis, protecting the existing structure

against direct physical loss or damage from the causes of loss identified in Section A.2.3.1, notwithstanding the

undertaking of the Work. The Owner shall be responsible for all co-insurance penalties.

§ A.2.4 Within three (3) business days of the date the Owner becomes aware of an impending or actual cancellation

or expiration of any insurance required by this Section A.2, the Owner shall provide notice to the Contractor of such

impending or actual cancellation or expiration. Unless the lapse in coverage arises from an act or omission of the

Contractor: (1) the Contractor, upon receipt of notice from the Owner, shall have the right to stop the Work until the

lapse in coverage has been cured by the procurement of replacement coverage by either the Owner or the

Contractor; (2) the Contract Time and Contract Sum shall be equitably adjusted; and (3) the Owner waives all rights

against the Contractor, Subcontractors, and Sub-subcontractors to the extent any loss to the Owner would have been

covered by the insurance had it not expired or been cancelled. If the Contractor purchases replacement coverage, the

cost of the insurance shall be charged to the Owner by an appropriate Change Order. The furnishing of notice by the

Owner shall not relieve the Owner of any contractual obligation to provide required insurance.

ARTICLE A.3 CONTRACTOR’S INSURANCE AND BONDS § A.3.1 General § A.3.1.1 Certificates of Insurance. The Contractor shall provide certificates of insurance acceptable to the Owner

evidencing compliance with the requirements in this Article A.3 at the following times: (1) prior to commencement

of the Work; (2) upon renewal or replacement of each required policy of insurance; and (3) upon the Owner’s

written request. An additional certificate evidencing continuation of commercial liability coverage, including

coverage for completed operations, shall be submitted with the final Application for Payment and thereafter upon

renewal or replacement of such coverage until the expiration of the periods required by Section A.3.2.1 and Section

A.3.3.1. The certificates will show the Owner as an additional insured on the Contractor’s Commercial General

Liability and excess or umbrella liability policy or policies.

§ A.3.1.2 Deductibles and Self-Insured Retentions. The Contractor shall disclose to the Owner any deductible or self-

insured retentions applicable to any insurance required to be provided by the Contractor.

Page 13: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A101™ – 2017 Exhibit A. Copyright © 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA®

Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document,

or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the

law. This draft was produced by AIA software at 15:45:15 on 01/24/2018 under Order No.5291788124 which expires on 07/12/2018, and is not

for resale.

User Notes: (1698911027)

3

§ A.3.1.3 Additional Insured Obligations. To the fullest extent permitted by law, the Contractor shall cause the

commercial general liability coverage to include (1) the Owner, the Architect, and the Architect’s consultants as

additional insureds for claims caused in whole or in part by the Contractor’s negligent acts or omissions during the

Contractor’s operations; and (2) the Owner as an additional insured for claims caused in whole or in part by the

Contractor’s negligent acts or omissions for which loss occurs during completed operations. The additional insured

coverage shall be primary and non-contributory to any of the Owner’s general liability insurance policies and shall

apply to both ongoing and completed operations. To the extent commercially available, the additional insured

coverage shall be no less than that provided by Insurance Services Office, Inc. (ISO) forms CG 20 10 07 04, CG 20

37 07 04, and, with respect to the Architect and the Architect’s consultants, CG 20 32 07 04.

§ A.3.2 Contractor’s Required Insurance Coverage § A.3.2.1 The Contractor shall purchase and maintain the following types and limits of insurance from an insurance

company or insurance companies lawfully authorized to issue insurance in the jurisdiction where the Project is

located. The Contractor shall maintain the required insurance until the expiration of the period for correction of

Work as set forth in Section 12.2.2 of the General Conditions, unless a different duration is stated below:

(If the Contractor is required to maintain insurance for a duration other than the expiration of the period for

correction of Work, state the duration.)

« »

§ A.3.2.2 Commercial General Liability § A.3.2.2.1 Commercial General Liability insurance for the Project written on an occurrence form with policy limits

of not less than «five million dollars » ($ «5,000,000 » ) each occurrence, «ten million dollars » ($ «10,000,000 »

) general aggregate, and «five million dollars » ($ «5,000,000 » ) aggregate for products-completed operations

hazard, providing coverage for claims including

.1 damages because of bodily injury, sickness or disease, including occupational sickness or disease,

and death of any person;

.2 personal injury and advertising injury;

.3 damages because of physical damage to or destruction of tangible property, including the loss of use

of such property;

.4 bodily injury or property damage arising out of completed operations; and

.5 the Contractor’s indemnity obligations under Section 3.18 of the General Conditions.

§ A.3.2.2.2 The Contractor’s Commercial General Liability policy under this Section A.3.2.2 shall not contain an

exclusion or restriction of coverage for the following:

.1 Claims by one insured against another insured, if the exclusion or restriction is based solely on the

fact that the claimant is an insured, and there would otherwise be coverage for the claim.

.2 Claims for property damage to the Contractor’s Work arising out of the products-completed

operations hazard where the damaged Work or the Work out of which the damage arises was

performed by a Subcontractor.

.3 Claims for bodily injury other than to employees of the insured.

.4 Claims for indemnity under Section 3.18 of the General Conditions arising out of injury to employees

of the insured.

.5 Claims or loss excluded under a prior work endorsement or other similar exclusionary language.

.6 Claims or loss due to physical damage under a prior injury endorsement or similar exclusionary

language.

.7 Claims related to residential, multi-family, or other habitational projects, if the Work is to be

performed on such a project.

.8 Claims related to roofing, if the Work involves roofing.

.9 Claims related to exterior insulation finish systems (EIFS), synthetic stucco or similar exterior

coatings or surfaces, if the Work involves such coatings or surfaces.

.10 Claims related to earth subsidence or movement, where the Work involves such hazards.

.11 Claims related to explosion, collapse and underground hazards, where the Work involves such

hazards.

Page 14: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A101™ – 2017 Exhibit A. Copyright © 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA®

Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document,

or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the

law. This draft was produced by AIA software at 15:45:15 on 01/24/2018 under Order No.5291788124 which expires on 07/12/2018, and is not

for resale.

User Notes: (1698911027)

4

§ A.3.2.3 Automobile Liability covering vehicles owned, and non-owned vehicles used, by the Contractor, with

policy limits of not less than «one million dollars » ($ «1,000,000 » ) per accident, for bodily injury, death of any

person, and property damage arising out of the ownership, maintenance and use of those motor vehicles along with

any other statutorily required automobile coverage.

§ A.3.2.4 The Contractor may achieve the required limits and coverage for Commercial General Liability and

Automobile Liability through a combination of primary and excess or umbrella liability insurance, provided such

primary and excess or umbrella insurance policies result in the same or greater coverage as the coverages required

under Section A.3.2.2 and A.3.2.3, and in no event shall any excess or umbrella liability insurance provide narrower

coverage than the primary policy. The excess policy shall not require the exhaustion of the underlying limits only

through the actual payment by the underlying insurers.

§ A.3.2.5 Workers’ Compensation at statutory limits.

§ A.3.2.6 Employers’ Liability with policy limits not less than «one million dollars » ($ «1,000,000 » ) each

accident, «one million dollars » ($ «1,000,000 » ) each employee, and «five million dollars » ($ « 5,000,000 » )

policy limit.

§ A.3.2.7 Jones Act, and the Longshore & Harbor Workers’ Compensation Act, as required, if the Work involves

hazards arising from work on or near navigable waterways, including vessels and docks

§ A.3.2.8 If the Contractor is required to furnish professional services as part of the Work, the Contractor shall

procure Professional Liability insurance covering performance of the professional services, with policy limits of not

less than «two million dollars » ($ «2,000,000 » ) per claim and «two million dollars » ($ «2,000,000 » ) in the

aggregate.

§ A.3.2.9 If the Work involves the transport, dissemination, use, or release of pollutants, the Contractor shall procure

Pollution Liability insurance, with policy limits of not less than «one million dollars » ($ «1,000,000 » ) per claim

and «two million dollars » ($ «2,000,000 » ) in the aggregate.

§ A.3.2.10 Coverage under Sections A.3.2.8 and A.3.2.9 may be procured through a Combined Professional Liability

and Pollution Liability insurance policy, with combined policy limits of not less than « two million dollars » ($

«2,000,000 » ) per claim and «two million dollars » ($ «2,000,000 » ) in the aggregate.

§ A.3.2.11 Insurance for the use or operation of manned or unmanned aircraft, if the Work requires such activities,

with policy limits of not less than «two million dollars » ($ «2,000,000 » ) per claim and «four million dollars » ($

«4,000,000 » ) in the aggregate.

§ A.3.3 Contractor’s Other Insurance Coverage § A.3.3.1 Insurance selected and described in this Section A.3.3 shall be purchased from an insurance company or

insurance companies lawfully authorized to issue insurance in the jurisdiction where the Project is located. The

Contractor shall maintain the required insurance until the expiration of the period for correction of Work as set forth

in Section 12.2.2 of the General Conditions, unless a different duration is stated below:

(If the Contractor is required to maintain any of the types of insurance selected below for a duration other than the

expiration of the period for correction of Work, state the duration.)

« »

§ A.3.3.2 The Contractor shall purchase and maintain the following types and limits of insurance in accordance with

Section A.3.3.1.

(Select the types of insurance the Contractor is required to purchase and maintain by placing an X in the box(es)

next to the description(s) of selected insurance. Where policy limits are provided, include the policy limit in the

appropriate fill point.)

[ « » ] § A.3.3.2.1 Property insurance of the same type and scope satisfying the requirements identified in

Section A.2.3, which, if selected in this section A.3.3.2.1, relieves the Owner of the responsibility to

Page 15: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A101™ – 2017 Exhibit A. Copyright © 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA®

Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document,

or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the

law. This draft was produced by AIA software at 15:45:15 on 01/24/2018 under Order No.5291788124 which expires on 07/12/2018, and is not

for resale.

User Notes: (1698911027)

5

purchase and maintain such insurance except insurance required by Section A.2.3.1.3 and Section

A.2.3.3. The Contractor shall comply with all obligations of the Owner under Section A.2.3 except to

the extent provided below. The Contractor shall disclose to the Owner the amount of any deductible,

and the Owner shall be responsible for losses within the deductible. Upon request, the Contractor

shall provide the Owner with a copy of the property insurance policy or policies required. The Owner

shall adjust and settle the loss with the insurer and be the trustee of the proceeds of the property

insurance in accordance with Article 11 of the General Conditions unless otherwise set forth below:

(Where the Contractor’s obligation to provide property insurance differs from the Owner’s

obligations as described under Section A.2.3, indicate such differences in the space below.

Additionally, if a party other than the Owner will be responsible for adjusting and settling a loss with

the insurer and acting as the trustee of the proceeds of property insurance in accordance with Article

11 of the General Conditions, indicate the responsible party below.)

« »

[ « » ] § A.3.3.2.2 Railroad Protective Liability Insurance, with policy limits of not less than « » ($ « » ) per

claim and « » ($ « » ) in the aggregate, for Work within fifty (50) feet of railroad property.

[ « » ] § A.3.3.2.3 Asbestos Abatement Liability Insurance, with policy limits of not less than « » ($ « » ) per

claim and « » ($ « » ) in the aggregate, for liability arising from the encapsulation, removal,

handling, storage, transportation, and disposal of asbestos-containing materials.

[ « » ] § A.3.3.2.4 Insurance for physical damage to property while it is in storage and in transit to the

construction site on an “all-risks” completed value form.

[ « » ] § A.3.3.2.5 Property insurance on an “all-risks” completed value form, covering property owned by

the Contractor and used on the Project, including scaffolding and other equipment.

[ « » ] § A.3.3.2.6 Other Insurance

(List below any other insurance coverage to be provided by the Contractor and any applicable

limits.)

Coverage Limits

§ A.3.4 Performance Bond and Payment Bond The Contractor shall provide surety bonds, from a company or companies lawfully authorized to issue surety bonds

in the jurisdiction where the Project is located, as follows:

(Specify type and penal sum of bonds.)

Type Penal Sum ($0.00)

Payment Bond 100% of Contract Sum

Performance Bond 100% of Contract Sum

Payment and Performance Bonds shall be AIA Document A312™, Payment Bond and Performance Bond, or

contain provisions identical to AIA Document A312™, current as of the date of this Agreement.

ARTICLE A.4 SPECIAL TERMS AND CONDITIONS Special terms and conditions that modify this Insurance and Bonds Exhibit, if any, are as follows:

« »

Page 16: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA®

Document A104TM – 2017

Standard Abbreviated Form of Agreement Between Owner and

Contractor

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

1

ADDITIONS AND DELETIONS:

The author of this document

has added information

needed for its completion.

The author may also have

revised the text of the

original AIA standard form.

An Additions and Deletions

Report that notes added

information as well as

revisions to the standard

form text is available from

the author and should be

reviewed.

This document has important

legal consequences.

Consultation with an

attorney is encouraged with

respect to its completion

or modification.

ELECTRONIC COPYING of any

portion of this AIA® Document

to another electronic file is

prohibited and constitutes a

violation of copyright laws

as set forth in the footer of

this document.

AGREEMENT made as of the « » day of « » in the year «»

(In words, indicate day, month and year.)

BETWEEN the Owner:

(Name, legal status, address and other information)

« »

« »

and the Contractor:

(Name, legal status, address and other information)

« »« »

for the following Project:

(Name, location and detailed description)

« »

The Architect:

(Name, legal status, address and other information)

« »« »

« »

« »

« »

The Owner and Contractor agree as follows.

Page 17: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

2

TABLE OF ARTICLES 1 THE WORK OF THIS CONTRACT 2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 3 CONTRACT SUM 4 PAYMENT 5 DISPUTE RESOLUTION 6 ENUMERATION OF CONTRACT DOCUMENTS 7 GENERAL PROVISIONS 8 OWNER 9 CONTRACTOR 10 ARCHITECT 11 SUBCONTRACTORS 12 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS 13 CHANGES IN THE WORK 14 TIME 15 PAYMENTS AND COMPLETION 16 PROTECTION OF PERSONS AND PROPERTY 17 INSURANCE AND BONDS 18 CORRECTION OF WORK 19 MISCELLANEOUS PROVISIONS 20 TERMINATION OF THE CONTRACT 21 CLAIMS AND DISPUTES

ARTICLE 1 THE WORK OF THIS CONTRACT The Contractor shall execute the Work described in the Contract Documents, except as specifically indicated in the

Contract Documents to be the responsibility of others.

ARTICLE 2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 2.1 The date of commencement of the Work shall be:

(Check one of the following boxes.)

Page 18: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

3

[ « » ] The date of this Agreement.

[ «X » ] A date set forth in a notice to proceed issued by the Owner.

[ « » ] Established as follows:

(Insert a date or a means to determine the date of commencement of the Work.)

« »

If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this

Agreement.

§ 2.2 The Contract Time shall be measured from the date of commencement.

§ 2.3 Substantial Completion § 2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall

achieve Substantial Completion of the entire Work:

(Check the appropriate box and complete the necessary information.)

[ « » ] Not later than « » ( « » ) calendar days from the date of commencement of the Work.

[ «X » ] By the following date: « »

§ 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work

are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial

Completion of such portions by the following dates:

Portion of Work Substantial Completion Date « »

§ 2.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 2.3, liquidated damages

shall be assessed as set forth in Section 3.5.

ARTICLE 3 CONTRACT SUM § 3.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the

Contract. The Contract Sum shall be one of the following:

(Check the appropriate box.)

[ « X » ] Stipulated Sum, in accordance with Section 3.2 below

[ « » ] Cost of the Work plus the Contractor’s Fee, in accordance with Section 3.3 below

[ « » ] Cost of the Work plus the Contractor’s Fee with a Guaranteed Maximum Price, in accordance with Section

3.4 below

(Based on the selection above, complete Section 3.2, 3.3 or 3.4 below.)

§ 3.2 The Stipulated Sum shall be « » ($ « » ), subject to additions and deductions as provided in the Contract

Documents.

§ 3.2.1 The Stipulated Sum is based upon the following alternates, if any, which are described in the Contract

Documents and are hereby accepted by the Owner:

(State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the

Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other

alternates showing the amount for each and the date when that amount expires.)

« »

Page 19: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

4

§ 3.2.2 Unit prices, if any:

(Identify the item and state the unit price and the quantity limitations, if any, to which the unit price will be

applicable.)

Item Units and Limitations Price per Unit ($0.00)

§ 3.2.3 Allowances, if any, included in the stipulated sum:

(Identify each allowance.)

Item Price « »

§ 3.3 Cost of the Work Plus Contractor’s Fee

NOT APPLICABLE

§ 3.4 Cost of the Work Plus Contractor’s Fee With a Guaranteed Maximum Price

NOT APPLICABLE

§ 3.4.3 Guaranteed Maximum Price

NOT APPLICABLE

§ 3.5 Liquidated damages:

Ǥ 3.5.1 Should the Contractor fail to achieve substantial completion within the Contract Time, as adjusted,

Contractor shall pay to the Owner ________ and No/100 Dollars ($) for each day beyond the Contract Time, as

may be adjusted for which Substantial Completion has not been achieved.

§ 3.5.2 Contractor and Owner agree to the daily sum of __________and No/100 Dollars ($) as liquidated damages

because of the impracticability and extreme difficulty of fixing and ascertaining the actual damages the Owner

would sustain in the event the Contractor fails to achieve Substantial Completion within the Contract Time, as may

be adjusted.

»

ARTICLE 4 PAYMENT § 4.1 Progress Payments § 4.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for

Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the

Contractor as provided below and elsewhere in the Contract Documents.

§ 4.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of

the month, or as follows:

« »

Page 20: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

5

§ 4.1.3 Provided that an Application for Payment is received by the Architect not later than the «15th » day of a

month, the Owner shall make payment of the certified amount to the Contractor not later than the «15th » day of the

« following » month. If an Application for Payment is received by the Architect after the date fixed above, payment

shall be made by the Owner not later than «thirty » ( « 30 » ) days after the Architect receives the Application for

Payment.

(Federal, state or local laws may require payment within a certain period of time.)

§ 4.1.4 For each progress payment, the Owner may withhold retainage from the payment otherwise due as follows:

(Insert a percentage or amount to be withheld as retainage from each Application for Payment and any terms for

reduction of retainage during the course of the Work. The amount of retainage may be limited by governing law.)

« Owner shall withhold five percent (5%) of the amount of cash certified pay application as retainage.

Once fifty percent (50%) of the Work has been completed, provided the Owner finds that satisfactory progress is

being made and subject to the consent of the Surety, the Owner may authorize payment to the Contractor in full of

any progress payment for work performed beyond the fifty percent (50%) stage of completion. If a reduction in

retainage has been made, the Owner may increase the retainage back to five percent (5%) at any time if the Owner

concludes that the Contractor is not progressing the work in a timely or satisfactory manner. The Owner may also if

agreed by the Contractor release retainage to the Contractor and direct the Contractor to reduce the retainage of a

particular subcontractor. »

§ 4.1.5 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated

below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is

located.

(Insert rate of interest agreed upon, if any.)

« 8 » % «per annum »

§ 4.2 Final Payment § 4.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the

Contractor when

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct

Work as provided in Section 18.2, and to satisfy other requirements, if any, which extend beyond

final payment;

.2 the Contractor has submitted a final accounting for the Cost of the Work, where payment is on the

basis of the Cost of the Work with or without a Guaranteed Maximum Price; and

.3 a final Certificate for Payment has been issued by the Architect in accordance with Section 15.7.1.

§ 4.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the

Architect’s final Certificate for Payment, or as follows:

« »

ARTICLE 5 DISPUTE RESOLUTION § 5.1 Binding Dispute Resolution For any claim subject to, but not resolved by, mediation pursuant to Section 21.5, the method of binding dispute

resolution shall be as follows:

(Check the appropriate box.)

[ « » ] Arbitration pursuant to Section 21.6 of this Agreement

[ « X » ] Litigation in a court of competent jurisdiction

[ « » ] Other (Specify)

« »

Page 21: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

6

If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in

writing to a binding dispute resolution method other than litigation, claims will be resolved in a court of competent

jurisdiction.

ARTICLE 6 ENUMERATION OF CONTRACT DOCUMENTS § 6.1 The Contract Documents are defined in Article 7 and, except for Modifications issued after execution of this

Agreement, are enumerated in the sections below.

§ 6.1.1 The Agreement is this executed AIA Document A104™–2017, Standard Abbreviated Form of Agreement

Between Owner and Contractor.

§ 6.1.2 AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, dated as indicated

below:

(Insert the date of the E203–2013 incorporated into this Agreement.)

« »

§ 6.1.3 The Supplementary and other Conditions of the Contract:

Document Title Date Pages

« See attached table of

contents »

Project Manual

§ 6.1.4 The Specifications:

(Either list the Specifications here or refer to an exhibit attached to this Agreement.)

« »

Section Title Date Pages

«See attached Table of

Contents »

Project Manual

§ 6.1.5 The Drawings:

(Either list the Drawings here or refer to an exhibit attached to this Agreement.)

«See attached List of Drawings, »

Number Title Date « »

§ 6.1.6 The Addenda, if any:

Number Date Pages Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the

bidding or proposal requirements are enumerated in this Article 6.

§ 6.1.7 Additional documents, if any, forming part of the Contract Documents:

.1 Other Exhibits:

(Check all boxes that apply.)

[ « » ] Exhibit A, Determination of the Cost of the Work.

[ « » ] AIA Document E204™–2017, Sustainable Projects Exhibit, dated as indicated below:

(Insert the date of the E204-2017 incorporated into this Agreement.)

« »

Page 22: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

7

[ « » ] The Sustainability Plan:

Title Date Pages « »

[ « » ] Supplementary and other Conditions of the Contract:

Document Title Date Pages

« »

.2 Other documents, if any, listed below:

(List here any additional documents that are intended to form part of the Contract Documents.)

« »

ARTICLE 7 GENERAL PROVISIONS § 7.1 The Contract Documents The Contract Documents are enumerated in Article 6 and consist of this Agreement (including, if applicable,

Supplementary and other Conditions of the Contract), Drawings, Specifications, Addenda issued prior to the

execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of

this Agreement. A Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change

Order, (3) a Construction Change Directive, or (4) a written order for a minor change in the Work issued by the

Architect. The intent of the Contract Documents is to include all items necessary for the proper execution and

completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by

one shall be as binding as if required by all; performance by the Contractor shall be required to the extent consistent

with the Contract Documents and reasonably inferable from them as being necessary to produce the indicated

results.

§ 7.2 The Contract The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated

agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either

written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall

not be construed to create a contractual relationship of any kind between any persons or entities other than the

Owner and the Contractor.

§ 7.3 The Work The term “Work” means the construction and services required by the Contract Documents, whether completed or

partially completed, and includes all other labor, materials, equipment, and services provided or to be provided by

the Contractor to fulfill the Contractor’s obligations. The Work may constitute the whole or a part of the Project.

§ 7.4 Instruments of Service Instruments of Service are representations, in any medium of expression now known or later developed, of the

tangible and intangible creative work performed by the Architect and the Architect’s consultants under their

respective professional services agreements. Instruments of Service may include, without limitation, studies,

surveys, models, sketches, drawings, specifications, and other similar materials.

§ 7.5 Ownership and use of Drawings, Specifications and Other Instruments of Service § 7.5.1 The Architect and the Architect’s consultants shall be deemed the authors and owners of their respective

Instruments of Service, including the Drawings and Specifications, and will retain all common law, statutory and

other reserved rights in their Instruments of Service, including copyrights. The Contractor, Subcontractors, Sub-

subcontractors, and suppliers shall not own or claim a copyright in the Instruments of Service. Submittal or

distribution to meet official regulatory requirements or for other purposes in connection with the Project is not to be

construed as publication in derogation of the Architect’s or Architect’s consultants’ reserved rights.

§ 7.5.2 The Contractor, Subcontractors, Sub-subcontractors and suppliers are authorized to use and reproduce the

Instruments of Service provided to them, subject to the protocols established pursuant to Sections 7.6 and 7.7, solely

and exclusively for execution of the Work. All copies made under this authorization shall bear the copyright notice,

Page 23: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

8

if any, shown on the Instruments of Service. The Contractor, Subcontractors, Sub-subcontractors, and suppliers may

not use the Instruments of Service on other projects or for additions to this Project outside the scope of the Work

without the specific written consent of the Owner, Architect and the Architect’s consultants.

§ 7.6 Digital Data Use and Transmission The parties shall agree upon protocols governing the transmission and use of Instruments of Service or any other

information or documentation in digital form. The parties will use AIA Document E203™–2013, Building

Information Modeling and Digital Data Exhibit, to establish the protocols for the development, use, transmission,

and exchange of digital data.

§ 7.7 Building Information Models Use and Reliance Any use of, or reliance on, all or a portion of a building information model without agreement to protocols

governing the use of, and reliance on, the information contained in the model and without having those protocols set

forth in AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, and the requisite

AIA Document G202™–2013, Project Building Information Modeling Protocol Form, shall be at the using or

relying party’s sole risk and without liability to the other party and its contractors or consultants, the authors of, or

contributors to, the building information model, and each of their agents and employees.

§ 7.8 Severability The invalidity of any provision of the Contract Documents shall not invalidate the Contract or its remaining

provisions. If it is determined that any provision of the Contract Documents violates any law, or is otherwise invalid

or unenforceable, then that provision shall be revised to the extent necessary to make that provision legal and

enforceable. In such case the Contract Documents shall be construed, to the fullest extent permitted by law, to give

effect to the parties' intentions and purposes in executing the Contract.

§ 7.9 Notice § 7.9.1 Except as otherwise provided in Section 7.9.2, where the Contract Documents require one party to notify or

give notice to the other party, such notice shall be provided in writing to the designated representative of the party to

whom the notice is addressed and shall be deemed to have been duly served if delivered in person, by mail, by

courier, or by electronic transmission in accordance with AIA Document E203™–2013, Building Information

Modeling and Digital Data Exhibit, if completed, or as otherwise set forth below:

(If other than in accordance with AIA Document E203–2013, insert requirements for delivering Notice in electronic

format such as name, title and email address of the recipient and whether and how the system will be required to

generate a read receipt for the transmission.)

« »

§ 7.9.2 Notice of Claims shall be provided in writing and shall be deemed to have been duly served only if delivered

to the designated representative of the party to whom the notice is addressed by certified or registered mail, by

courier providing proof of delivery, or by electronic transmission with proof of delivery.

§ 7.10 Relationship of the Parties Where the Contract is based on the Cost of the Work plus the Contractor’s Fee, with or without a Guaranteed

Maximum Price, the Contractor accepts the relationship of trust and confidence established by this Agreement and

covenants with the Owner to cooperate with the Architect and exercise the Contractor’s skill and judgment in

furthering the interests of the Owner; to furnish efficient business administration and supervision; to furnish at all

times an adequate supply of workers and materials; and to perform the Work in an expeditious and economical

manner consistent with the Owner’s interests. The Owner agrees to furnish and approve, in a timely manner,

information required by the Contractor and to make payments to the Contractor in accordance with the requirements

of the Contract Documents.

ARTICLE 8 OWNER § 8.1 Information and Services Required of the Owner § 8.1.1 Prior to commencement of the Work, at the written request by the Contractor, the Owner shall furnish to the

Contractor reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations

under the Contract. The Contractor shall have no obligation to commence the Work until the Owner provides such

Page 24: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

9

evidence. If commencement of the Work is delayed under this Section 8.1.1, the Contract Time shall be extended

appropriately.

§ 8.1.2

The Owner shall furnish surveys describing utilities locations and other information as to the physical characteristics

of, and legal limitations of the Project site. Contractor shall confirm the accuracy of all such information furnished

by Owner before beginning construction and shall notify Architect of any discrepancies discovered. Failure to do so

shall constitute a waiver of any claim for any discrepancies in the materials furnished by Owner. Contractor shall

excavate and dispose of each un-needed on-site utility and shall cap each off-site utility as required by the Work and

as may be included in the Specifications. At Owner’s request, the Contractor shall make available to the Owner the

results of any site investigation, test borings, analyses, studies or other tests conducted by or in possession of the

Contractor or any of its agents. Such materials shall be for Owner’s information only and are not part of the

Contract. The Contractor represents that, prior to commencement of the Work, it will become familiar with the

Project site and will not begin Work until it has received all information it needs concerning the conditions of the

Project site. The Contractor represents that it has inspected the location of the Work. The Contractor shall exercise

special care in executing subsurface Work in proximity of known subsurface utilities, improvements and easements.

§ 8.1.3 The General Contractor will be furnished, free of charge, ten (10) copies of the Drawings and Specifications.

Additional Plans and Specifications requested beyond the above limits will be mailed to the Contractors at the cost

of reproduction, handling and mailing. Owner warrants Architect’s design, plans or specifications only to the extent

that the design plans and specifications were prepared utilizing the ordinary standard of care required of design

professionals in the Davie County area for Projects of this type.

§ 8.1.4 Except for permits and fees that are the responsibility of the Contractor under the Contract Documents,

including those required under Section 9.6.1, the Owner shall secure and pay for other necessary approvals,

easements, assessments, and charges required for the construction, use, or occupancy of permanent structures or for

permanent changes in existing facilities.

§ 8.2 Owner’s Right to Stop the Work If the Contractor fails to correct Work which is not in accordance with the requirements of the Contract Documents,

or fails to carry out the Work in accordance with the Contract Documents, the Owner may issue a written order to

the Contractor to stop the Work, or any portion thereof, until the cause for such order is eliminated; however, the

right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the

benefit of the Contractor or any other person or entity. This right shall be in addition to and not in restriction of

Owner’s rights under Article 20. Such order of stoppage by the Owner shall not constitute grounds for delay, claim

or Contract termination by the Contractor.

§ 8.3 Owner’s Right to Carry Out the Work If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents, and fails

within a ten-day period after receipt of notice from the Owner to commence and continue correction of such default

or neglect or to provide adequate manpower, material or resources, with diligence and promptness, the Owner may,

without prejudice to any other remedies the Owner may have, correct such default or neglect. Owner may perform

such Work in a manner it deems expedient and shall not be required to utilize the least expensive alternative. the

Owner may, pursuant to Section 15.4.3, withhold or nullify a Certificate for Payment in whole or in part, to the

extent reasonably necessary to reimburse the Owner for the reasonable cost of correcting such deficiencies,

including the Owner’s expenses and compensation for the Architect’s additional services made necessary by such

default, neglect, or failure. Notwithstanding any other provision of the Contract, the Owner may withhold payments

then or thereafter due until the cost of correction is determined. If payments then or thereafter due the Contractor

are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner.

If the Contractor disagrees with the actions of the Owner or the Architect, or the amounts claimed as costs to the

Owner, the Contractor may file a Claim pursuant to Article 21.

ARTICLE 9 CONTRACTOR § 9.1 Review of Contract Documents and Field Conditions by Contractor § 9.1.1 Execution of the Contract by the Contractor is a representation (1) that the Contractor has visited the site,

become generally familiar with local conditions under which the Work is to be performed and correlated personal

observations with requirements of the Contract Documents and (2) that the Contractor and each subcontractor has

Page 25: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

10

evaluated and satisfied themselves as to the conditions and limitations under which the Work is to be performed,

including, without limitation, (i) the location, condition, layout, and nature of the Project site and surrounding areas,

(ii) generally prevailing climatic conditions, (iii) anticipated labor supply and costs, (iv) availability and cost of

materials, tools, and equipment, and (v) other similar issues. The Owner assumes no responsibility or liability for

the physical condition or safety of the Project site or any improvements located on the Project site. The Contractor

shall be solely responsible for providing a safe place for the performance of his Work. The Owner shall not be

required to make any adjustment in either the Contract Sum or the Contract Time in connection with any failure by

any Contractor or any Subcontractor to have complied with the requirements of this Section.

.

§ 9.1.2 Because the Contract Documents are complementary, the Contractor shall, before starting each portion of the

Work, carefully study and compare the various Contract Documents relative to that portion of the Work, as well as

the information furnished by the Owner pursuant to Section 8.1.2, shall take field measurements of any existing

conditions related to that portion of the Work and shall observe any conditions at the site affecting it. These

obligations are for the purpose of facilitating coordination and construction by the Contractor and are not for the

purpose of discovering errors, omissions, or inconsistencies in the Contract Documents; however, the Contractor

shall promptly report to the Owner and Architect any errors, inconsistencies, or omissions discovered by or made

known to the Contractor in such form as the Owner or Architect may require. It is recognized that the Contractor’s

review is made in the Contractor’s capacity as a contractor and not as a licensed design professional unless

otherwise specifically provided in the Contract Documents.

§ 9.1.3 The Contractor is not required to ascertain that the Contract Documents are in accordance with applicable

laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Contractor

shall promptly report to the Owner and Architect any nonconformity discovered by or made known to the Contractor

in such form as the Owner or Architect may require.

§ 9.1.4 The Owner makes no representation or warranty as to the exactness of grades, elevations, dimensions or

locations given on any Drawings or the work installed by other contractors. The Contractor shall, therefore,

promptly satisfy itself as to the accuracy of all grades, elevations, dimensions and locations before commencing

Work.

§ 9.1.5 The Contractor shall assume full responsibility for accuracy of measurements obtained at the site and shall

coordinate Work with actual field measurements. The Contractor shall submit field engineering drawings, prepared

and sealed by a licensed surveyor, of proposed installation based on site layout survey and field conditions at the

time of construction and shall note any discrepancies between existing conditions and the Contract Documents or

surveys.

§ 9.1.6 Should the Specifications fail to particularly describe the material or kind of goods to be used in any place, it

shall be the duty of the Contractor to make inquiry of the Architect for what is best suited. Material reasonably

considered to be consistent with a project of this type shall be considered a part of the contract. To the extent that

Contractor believes that the Architect’s decision entitles Contractor to a change order, Contractor shall submit a

change order request as provided elsewhere herein.

§ 9.2 Supervision and Construction Procedures § 9.2.1 The Contractor shall supervise and direct the Work, using the Contractor’s best skill and attention. The

Contractor shall be solely responsible for and have control over construction means, methods, techniques,

sequences, and procedures, and for coordinating all portions of the Work under the Contract, unless the Contract

Documents give other specific instructions concerning these matters. If the Contract Documents give specific

instructions concerning construction means, methods, techniques, sequences or procedures, the Contractor shall

evaluate the jobsite safety thereof and, except as stated below, shall be fully and solely responsible for the jobsite

safety of such means, methods, techniques, sequences or procedures. If the Contractor determines that such means,

methods, techniques, sequences or procedures may not be safe, the Contractor shall give timely written notice to the

Owner and Architect and shall not proceed with that portion of the Work without further written instructions from

the Architect.

Page 26: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

11

§ 9.2.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor’s employees,

Subcontractors and their agents and employees, and other persons or entities performing portions of the Work for or

on behalf of the Contractor or any of its Subcontractors.

§ 9.2.3 The Contractor shall be responsible for inspection of portions of Work already performed to determine that

such portions are in proper condition to receive subsequent Work.

§ 9.2.4 If any of the Work is required to be inspected or approved by any public authority (other than the Owner), the

Contractor shall schedule and coordinate such inspection or approval to be performed. Owner shall not be

responsible for any cost or delay resulting from delays in completing inspections or obtaining approvals from any

public authority (other than the Owner). No inspection performed or failed to be performed by the Owner hereunder

shall be a waiver of any of the Contractor’s obligations hereunder to be construed as an approval or acceptance of

the Work or any part thereof.

§ 9.2.5 The Contractor is required to attend job site progress conferences as called by the General Contractor,

Architect and/or Program Manager (if applicable). The Contractor shall be represented at these job progress

conferences by both home office and project personnel. The representatives attending the meetings shall have

authority to act on behalf of and bind the party they represent. These meetings shall be open to subcontractors,

materials suppliers, and any others who can contribute toward maintaining required job progress. It shall be the

principal purpose of these meetings, or conferences to effect cooperation, and assistance in every practical way

toward the end of maintaining progress of the Project on schedule and to complete the Project within the Contract

Time. The Contractor shall be prepared to assess progress of the Work to recommend remedial measures for

correction of progress as may be appropriate. The General Contractor and/or Architect or their authorized

representative may set the time and place for the conferences, and the General Contractor as Project Coordinator

shall preside as chairman. Contractor shall notify Architect and the Owner in writing within ten (10) days of the

publishing of the meeting minutes of any exception taken thereto, and shall include a detailed statement of the basis

for such exception.

§ 9.3 Labor and Materials § 9.3.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor,

materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other

facilities and services necessary for proper execution and completion of the Work whether temporary or permanent

and whether or not incorporated or to be incorporated in the Work.

§ 9.3.2 The Contractor shall enforce strict discipline and good order among the Contractor’s employees and other

persons carrying out the Work. The Contractor shall not permit employment of unfit persons or persons not skilled

in tasks assigned to them.

§ 9.3.3 The Contractor may make a substitution only with the consent of the Owner, after evaluation by the Architect

and in accordance with a Modification.

§ 9.3.4 The Contractor has the responsibility to ensure that all product suppliers and Subcontractors adhere to the

Contract Documents and that they order products on time, taking into account the current market and delivery

conditions, and that they provide products on time. The Contractor shall keep the Owner, Architect and the Program

Manager informed as to the availability of all specified materials and equipment and shall advise them promptly, in

writing, of all material and equipment that may no longer be obtainable, or the availability of which may be delayed,

for the purposes of the Contract, whether due to conditions of the market or other limiting or governing factors.

§ 9.3.5 The Contractor shall disclose the existence and extent of any financial interests, whether direct or indirect, he

has in Subcontractors and material suppliers which he may propose for this Project.

Page 27: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

12

§ 9.4 Warranty § 9.4.1 The Contractor warrants to the Owner and Architect that materials and equipment furnished under the

Contract will be of good quality and new unless the Contract Documents require or permit otherwise. The

Contractor further warrants that the Work will conform to the requirements of the Contract Documents and will be

free from defects. Work, materials, or equipment not conforming to these requirements, including substitutions not

properly approved and authorized, shall be considered defective.

§ 9.4.2 The Contractor agrees to provide to the Owner following substantial completion but no later than thirty (30)

days after the date of substantial completion, their written warranty in a form satisfactory to the Owner and any and

all manufacturer’s warranties relating to the Work which shall commence as of the date of Substantial Completion

of the entire work and the Contractor further agrees to perform the Work in such manner so as to preserve any and

all such manufacturer’s warranties.

§ 9.4.3 If the Contractor uses any portion of the Work or Owner’s other property prior to the date of Substantial

Completion of the entire Work, such Work shall be restored to new or “like new” condition. Contractor’s warranty

and agreement to correct defective Work shall specifically include Contractor’s obligations under this paragraph.

§ 9.4.4 The warranties and guarantees called for in the specifications shall be for twelve (12) months unless a

longer period is called for in the Contract Drawings or Specifications. Such written warranties or guarantees shall

be signed by the manufacturer or subcontractor, as the case may be, and countersigned by the Contractor. The

Contractor agrees to provide four (4) original copies of all warranties and four (4) Pdf copies of all warranties. All

guarantees shall be addressed to the Owner.

.1 All warranties or guarantees shall commence on the date of Substantial Completion of the entire

work.

.2 The contractor further warrants that for a period of twenty-four (24) months following the date of

substantial completion that the building shall be watertight and leak free at every point and in

every area. The contractor shall, immediately upon notification by the owner of water penetration,

determine the source of water penetration and, at the contractor’s own expense, do any work

necessary to make the building watertight. The contractor shall also, at the contractor’s own

expense, repair or replace any other damaged material to return the building to its original

accepted condition. A written guarantee including the above paragraph and signed by the

contractor shall be submitted to the owner upon substantial completion of the project and before

submission of the Final Certificate of Payment by the contractor.

.3 In the event the manufacturer does not have a suitable written warranty form to fully cover the

guarantee requirements as set forth in the Specifications, the Contractor shall arrange for the

manufacturer to provide a written warranty in such form as shall fully document the guarantee set

forth in the Specifications.

§ 9.4.5 In the event Substantial Completion is achieved in stages, all applicable warranties will begin on the date the

last project portion was Substantially Complete.

§ 9.4.6 If the Contractor, after notice, fails within 48 hours to develop and transmit a proposed Plan of Remedial

Action to the Architect and Owner for correction of warranty items, and/or fails to proceed within three (3) days to

commence corrective measures of warranty items in compliance with the terms of the warranty/guarantee; the

Owner may have the defects corrected and the Contractor and his surety shall be liable for all expense incurred.

§ 9.4.7 The Contractor’s warranty excludes remedy for damage or defect caused by abuse, alterations to the Work

not executed by the Contractor, its subcontractors, or those contractors assigned to or for which the Contractor is

considered the Project Expediter or is otherwise responsible for coordination of the Work, improper or insufficient

maintenance and or operation whereby the Contractor can provide evidence sufficient to the reasonable satisfaction

of the Owner of proper training of Owner’s personnel, or normal wear and tear.

Page 28: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

13

§ 9.5 Taxes The Contractor shall pay sales, consumer, use, and other similar taxes that are legally enacted when bids are

received or negotiations concluded, whether or not yet effective or merely scheduled to go into effect.

§ 9.6 Permits, Fees, Notices, and Compliance with Laws § 9.6.1 Unless otherwise provided in the Contract Documents, the Contractor shall secure and pay for the building

permit as well as other permits, fees, licenses, and inspections by government agencies necessary for proper

execution and completion of the Work that are customarily secured after execution of the Contract and legally

required at the time bids are received or negotiations concluded.

§ 9.6.2 The Contractor shall comply with and give notices required by applicable laws, statutes, ordinances, codes,

rules and regulations, and lawful orders of public authorities applicable to performance of the Work. If the

Contractor performs Work knowing it to be contrary to applicable laws, statutes, ordinances, codes, rules and

regulations, or lawful orders of public authorities, the Contractor shall assume appropriate responsibility for such

Work and shall bear the costs attributable to correction. Contractor shall indemnify and hold the Owner harmless

against any and all fines, penalties, judgments or damages, including reasonable attorneys’ fees, imposed on or

incurred by the Owner as a result of such failure by the Contractor.

§ 9.6.3 Without assuming or performing the Architect’s design responsibility, it shall be the obligation of the

Contractor to review the Contract Documents for any discrepancy between building codes and regulations and to

notify Owners of such discrepancies which the Contractor discovers. If the Contractor observes that portions of the

Contract Documents are at variance with applicable laws, statutes, ordinances, building codes, rules or regulations,

the Contractor promptly shall notify the Owner and Architect in writing, and necessary changes shall be

accomplished by appropriate modification.

§ 9.6.4 Contractor shall notify utility companies of construction to be done near utility lines, including but not

limited to high voltage electric lines, and insure that all appropriate safety precautions are taken.

§ 9.7 Allowances § 9.7.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents. The

Owner shall select materials and equipment under allowances with reasonable promptness.

§ 9.7.2 Unless otherwise provided in the Contract Documents,

.1 allowances shall cover the cost to the Contractor of materials and equipment delivered at the site and

all required taxes, less applicable trade discounts;

.2 Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit and

other expenses contemplated for stated allowance amounts shall be included in the Contract Sum but

not in the allowances; and

.3 whenever costs are more than or less than allowances, the Contract Sum shall be adjusted accordingly

by Change Order. The amount of the Change Order shall reflect (1) the difference between actual

costs and the allowances under Section 3.8.2.1 and (2) changes in Contractor’s costs under Section

3.8.2.2.

§ 9.8 Contractor’s Construction Schedules § 9.8.1 The Contractor, promptly after being awarded the Contract, shall submit for the Owner’s and Architect’s

information a Contractor’s construction schedule for the Work. The schedule shall not exceed time limits current

under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work

and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide

for expeditious and practicable execution of the Work.

§ 9.8.2 The Contractor shall prepare a submittal schedule, promptly after being awarded the Contract and thereafter

as necessary to maintain a current submittal schedule, and shall submit the schedule(s) for the Architect’s approval.

The Architect’s approval shall not unreasonably be delayed or withheld. The submittal schedule shall (1) be

coordinated with the Contractor’s construction schedule, and (2) allow the Architect reasonable time to review

Page 29: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

14

submittals. If the Contractor fails to submit a submittal schedule, the Contractor shall not be entitled to any increase

in Contract Sum or extension of Contract Time resulting from such failure based on the time required for review of

submittals.

§ 9.8.3 The Contractor shall perform the Work in general accordance with the most recent schedule submitted to the

Owner and Architect.

§ 9.8.4 INCLUSION OF WEATHER DAYS IN SCHEDULE The Contractor shall include in the Contractor’s Construction Schedule weather days based upon local Weather data

5 year average Weather days shall be understood to be work days, exclusive of holidays, Sundays and other non-

working days. The Contractor shall use these monthly averages when establishing the construction schedule for this

Project. Claims for weather delays will not be considered until the number of days for the relevant period actually

delayed exceeds the five year average for the period for which a time extension is being requested.

Weather days are to be included to aid the Contractor in its scheduling. Unused weather days are not available for

extending the Contract Time or for decreasing the Project time.

§ 9.9 Submittals § 9.9.1 The Contractor shall review for compliance with the Contract Documents and submit to the Architect Shop

Drawings, Product Data, Samples, and similar submittals required by the Contract Documents in coordination with

the Contractor’s construction schedule and in such sequence as to cause no delay in the Work or in the activities of

the Owner or of separate contractors and to allow the Architect reasonable time for review. By submitting Shop

Drawings, Product Data, Samples, and similar submittals, the Contractor represents to the Owner and Architect that

the Contractor has (1) reviewed and approved them; (2) determined and verified materials, field measurements, and

field construction criteria related thereto, or will do so; and (3) checked and coordinated the information contained

within such submittals with the requirements of the Work and of the Contract Documents. The Work shall be in

accordance with approved submittals.

§ 9.9.2 The Architect will review and approve, or take other appropriate action upon, the Contractor’s Shop

Drawings, Product Data, Samples, and similar submittals. Contractor shall perform no portion of the Work for

which the Contract Document require submittal and review of Shop Drawings, Product Data, Samples and similar

submittals until the respective submittal has been reviewed and approved by the Architect.

§ 9.9.3 Shop Drawings, Product Data, Samples and similar submittals are not Contract Documents.

§ 9.9.4 The Contractor shall not be required to provide professional services that constitute the practice of

architecture or engineering unless such services are specifically required by the Contract Documents or unless the

Contractor needs to provide such services in order to carry out the Contractor's own responsibilities. If professional

design services or certifications by a design professional are specifically required, the Owner and the Architect will

specify the performance and design criteria that such services must satisfy. The Contractor shall cause such services

or certifications to be provided by an appropriately licensed design professional. If no criteria are specified, the

design shall comply with applicable codes and ordinances. Each Party shall be entitled to rely upon the information

provided by the other Party.

§ 9.10 Use of Site § 9.10.1 The Contractor shall confine operations at the site to areas permitted by applicable laws, statutes,

ordinances, codes, rules and regulations, lawful orders of public authorities, and the Contract Documents and shall

not unreasonably encumber the site with materials or equipment.

§ 9.10.2 The Project, as school property, may attract children and unauthorized personnel. Contractor shall take all

necessary precautions to secure the Project and his Work to prevent injury and to discourage the entry onto the

Project of children and unauthorized personnel.

§ 9.10.3 Contractor shall be responsible to avoid fraternization and unnecessary contact with students and school

personnel by the persons and entities on the Project for whom Contractor is responsible. Contractor will maintain

suitable decorum on the site and anyone failing to comply with the requirements of this subparagraph as determined

by Owner shall be subject to immediate dismissal.

Page 30: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

15

§ 9.10.4 Contractor shall not use Owner’s facilities and shall plan and schedule its Work so as not to interrupt or

interfere with school operations or activities.

§ 9.11 Cutting and Patching The Contractor shall be responsible for cutting, fitting, or patching required to complete the Work or to make its

parts fit together properly.

§ 9.12 Cleaning Up The Contractor shall keep the premises and surrounding area free from accumulation of waste materials and rubbish

caused by operations under the Contract. At completion of the Work, the Contractor shall remove waste materials,

rubbish, the Contractor’s tools, construction equipment, machinery, and surplus material from and about the Project.

The Contractor shall maintain streets, parking areas and sidewalks around the Project site free from any materials or

debris resulting from operations under this Contract. The Contractor shall remove all spillage and tracking arising

from the performance of the Work from such areas and any other affected areas, and shall establish a regular

maintenance program of sweeping and hosing to minimize accumulation of dirt and dust upon such areas.

§ 9.13 Access to Work The Contractor shall provide the Owner and Architect with access to the Work in preparation and progress wherever

located.

§ 9.14 Royalties, Patents and Copyrights The Contractor shall pay all royalties and license fees. The Contractor shall defend suits or claims for infringement

of copyrights and patent rights and shall hold the Owner and Architect harmless from loss on account thereof, but

shall not be responsible for defense or loss when a particular design, process, or product of a particular manufacturer

or manufacturers is required by the Contract Documents or where the copyright violations are contained in

Drawings, Specifications or other documents prepared by the Owner or Architect. However, if an infringement of a

copyright or patent is discovered by, or made known to, the Contractor, the Contractor shall be responsible for the

loss unless the information is promptly furnished to the Architect.

§ 9.15 Indemnification § 9.15.1 To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner,

Architect, Architect’s consultants, and agents and employees of any of them from and against claims, damages,

losses and expenses, including but not limited to attorneys’ fees, arising out of or resulting from performance of the

Work, provided that such claim, damage, loss, or expense is attributable to bodily injury, sickness, disease or death,

or to injury to or destruction of tangible property (other than the Work itself), but only to the extent caused by the

negligent acts or omissions of the Contractor, a Subcontractor, anyone directly or indirectly employed by them, or

anyone for whose acts they may be liable. Such obligation shall not be construed to negate, abridge, or reduce other

rights or obligations of indemnity which would otherwise exist as to a party or person described in this Section

9.15.1.

§ 9.15.2 In claims against any person or entity indemnified under this Section 9.15 by an employee of the Contractor,

a Subcontractor, anyone directly or indirectly employed by them, or anyone for whose acts they may be liable, the

indemnification obligation under Section 9.15.1 shall not be limited by a limitation on amount or type of damages,

compensation or benefits payable by or for the Contractor or Subcontractor under workers’ compensation acts,

disability benefit acts or other employee benefit acts.

§ 9.15.3 In the event of accidents involving personal injury or property damage, the Contractor shall immediately

notify the Owner, the Program Manager and the Architect, furnishing as much data as is available. As soon as

practicable, he shall furnish to the Owner, the Program Manager and the Architect a written report indicating the

extent of the damage, the persons involved, the employer of the persons involved and the number of days each

person is hospitalized.

Page 31: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

16

ARTICLE 10 ARCHITECT § 10.1 The Architect will provide administration of the Contract as described in the Contract Documents and will be

an Owner’s representative during construction, until the date the Architect issues the final Certificate for Payment.

The Architect will have authority to act on behalf of the Owner only to the extent provided in the Contract

Documents, unless otherwise modified in writing in accordance with other provisions of the Contract.

§ 10.2 Duties, responsibilities, and limitations of authority of the Architect as set forth in the Contract Documents

shall not be restricted, modified, or extended without written consent of the Owner and Architect. Consent shall not

be unreasonably withheld.

§ 10.3 The Architect will visit the site at intervals appropriate to the stage of the construction, but not less than once

every two weeks. Each engineering discipline shall make periodic visits not less than once every two weeks, during

the course of work applicable to its discipline. During critical work phases, each engineering discipline and

Architect may be required to make more frequent visits. The purpose of the visits is to become generally familiar

with the progress and quality of the portion of the Work completed, and to determine in general, if the Work

observed is being performed in a manner indicating that the Work, when fully completed, will be in accordance with

the Contract Documents. On the basis of the observations, Architect shall use reasonable care to guard the Owner

against defects and deficiencies in the Work of the Contractor. If the Architect observes any work that does not

conform to the Construction Documents, the Architect shall immediately make an oral and written report to Owner

and Program Manager of any such acts or omissions. The engineering disciplines shall prepare and submit a report

on each visit, submitted to the Owner, Program Manager and the Contractor through the Architect within five (5)

days of the visit.

§ 10.4 On the basis of the site visits, the Architect will keep the Owner reasonably informed about the progress and

quality of the portion of the Work completed, and promptly report to the Owner (1) known deviations from the

Contract Documents, (2) known deviations from the most recent construction schedule submitted by the Contractor,

and (3) defects and deficiencies observed in the Work. The Architect shall not have control over, charge of, or

responsibility for the construction means, methods, techniques, sequences (except to the extent phasing is required

in a contract or schedule) or procedures, or for safety precautions and programs in connection with the Work. The

Architect shall be responsible for the Architect’s negligent acts or omissions, including, but not limited to, a

negligent failure to timely determine the Work is not being performed in accordance with the Contract Documents

or a negligent failure to notify the Owner that the construction means, techniques, sequences, or procedures utilized

by the Contractor are not generally accepted in the industry. Notwithstanding the foregoing, the Architect shall not

have control over or charge of, and shall not be responsible for, acts or omissions of the Contractor or of any other

persons or entities performing portions of the Work, provided the Architect has given prompt notice to the Owner in

writing of any deviations from the Contract Documents in the Work or any defects or deficiencies in the Work of the

Contractor of which the Architect has knowledge, or reasonably should have knowledge.

§ 10.5 Based on the Architect’s evaluations of the Work and of the Contractor’s Applications for Payment, the

Architect will review and certify the amounts due the Contractor and will issue Certificates for Payment in such

amounts.

§ 10.6 The Architect has authority to reject Work and shall reject Work that does not conform to the Contract

Documents and to require inspection or testing of the Work.

§ 10.7 The Architect will review and approve or take other appropriate action upon, the Contractor’s submittals such

as Shop Drawings, Product Data, and Samples, but only for the limited purpose of checking for conformance with

information given and the design concept expressed in the Contract Documents.

§ 10.8 The Architect will interpret and decide matters concerning performance under, and requirements of, the

Contract Documents on written request of either the Owner or Contractor. The Architect will make initial decisions

on all claims, disputes, and other matters in question between the Owner and Contractor but will not be liable for

results of any interpretations or decisions rendered in good faith.

§ 10.9 The Architect’s decisions on matters relating to aesthetic effect will be final if consistent with the intent

expressed in the Contract Documents.

Page 32: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

17

ARTICLE 11 SUBCONTRACTORS § 11.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a portion of the

Work at the site.

§ 11.2 Unless otherwise stated in the Contract Documents, the Contractor, as soon as practicable after award of the

Contract, shall notify the Owner and Architect of the Subcontractors or suppliers proposed for each of the principal

portions of the Work. The Contractor shall not contract with any Subcontractor or supplier to whom the Owner or

Architect has made reasonable written objection within ten days after receipt of the Contractor’s list of

Subcontractors and suppliers. If the proposed but rejected Subcontractor was reasonably capable of performing the

Work, the Contract Sum and Contract Time shall be increased or decreased by the difference, if any, occasioned by

such change, and an appropriate Change Order shall be issued before commencement of the substitute

Subcontractor’s Work. The Contractor shall not be required to contract with anyone to whom the Contractor has

made reasonable objection.

§ 11.3 Contracts between the Contractor and Subcontractors shall (1) require each Subcontractor, to the extent of the

Work to be performed by the Subcontractor, to be bound to the Contractor by the terms of the Contract Documents,

and to assume toward the Contractor all the obligations and responsibilities, including the responsibility for safety of

the Subcontractor’s Work, which the Contractor, by the Contract Documents, assumes toward the Owner and

Architect, and (2) allow the Subcontractor the benefit of all rights, remedies and redress against the Contractor that

the Contractor, by these Contract Documents, has against the Owner.

§ 11.4 The Contractor shall not change a Subcontractor, person or entity previously selected without the approval of

the Owner; provided, however, that Contractor shall be entitled to recover any resulting increase in the Contract

Sum resulting from any objection to the substitution.

§ 11.5 CONTINGENT ASSIGNMENT OF SUBCONTRACTS § 11.5.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided

that assignment is effective only after termination of the Contract or Contractor’s performance by the Owner and

only for those subcontract agreements which the Owner accepts by notifying the Subcontractor and Contractor in

writing.

§ 11.5.2 Owner shall not be obligated for any payment or amounts claimed for work performed prior to the effective

date of the Assignment. Upon assignment, if the Work has been suspended for more than 45 days, the

Subcontractor’s compensation shall be equitably adjusted for increases in cost resulting from the suspension.

ARTICLE 12 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS § 12.1 The term “Separate Contractor(s)” shall mean other contractors retained by the Owner under separate

agreements. The Owner reserves the right to perform construction or operations related to the Project with the

Owner’s own forces, and with Separate Contractors retained under Conditions of the Contract substantially similar

to those of this Contract, including those provisions of the Conditions of the Contract related to insurance and

waiver of subrogation.

§ 12.2 The Contractor shall afford the Owner and Separate Contractors reasonable opportunity for introduction and

storage of their materials and equipment and performance of their activities, and shall connect and coordinate the

Contractor’s activities with theirs as required by the Contract Documents.

§ 12.3 The Owner shall be reimbursed by the Contractor for costs incurred by the Owner which are payable to a

Separate Contractor because of delays, improperly timed activities, or defective construction of the Contractor. The

Owner shall be responsible to the Contractor for costs incurred by the Contractor because of delays, improperly

timed activities, damage to the Work, or defective construction of a Separate Contractor.

ARTICLE 13 CHANGES IN THE WORK § 13.1 By appropriate Modification, changes in the Work may be accomplished after execution of the Contract. The

Owner, without invalidating the Contract, may order changes in the Work within the general scope of the Contract

consisting of additions, deletions, or other revisions, with the Contract Sum and Contract Time being adjusted

Page 33: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

18

accordingly. Such changes in the Work shall be authorized by written Change Order signed by the Owner,

Contractor, and Architect, or by written Construction Change Directive signed by the Owner and Architect. Upon

issuance of the Change Order or Construction Change Directive, the Contractor shall proceed promptly with such

changes in the Work, unless otherwise provided in the Change Order or Construction Change Directive.

§ 13.2 Adjustments in the Contract Sum and Contract Time resulting from a change in the Work shall be determined

by mutual agreement of the parties or, in the case of a Construction Change Directive signed only by the Owner and

Architect, by the Contractor’s cost of labor, material, equipment, and reasonable overhead and profit, unless the

parties agree on another method for determining the cost or credit. Pending final determination of the total cost of a

Construction Change Directive, the Contractor may request payment for Work completed pursuant to the

Construction Change Directive. The Architect will make an interim determination of the amount of payment due for

purposes of certifying the Contractor’s monthly Application for Payment. When the Owner and Contractor agree on

adjustments to the Contract Sum and Contract Time arising from a Construction Change Directive, the Architect

will prepare a Change Order. Agreement on any Change Order shall constitute a final settlement of all matters

relating to the change in the Work that is the subject of the Change Order, including, but not limited to, all direct and

indirect costs associated with such change and any and all adjustments to the Contract Sum and the construction

schedule. Subsequent claims for cumulative cost or cumulative impact shall not be allowed.

§ 13.3 The Architect will have authority to order minor changes in the Work not involving adjustment in the

Contract Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents.

Such changes shall be effected by written order and shall be binding on the Owner and Contractor. The Contractor

shall carry out such written orders promptly. If the Contractor believes that the proposed minor change in the Work

will affect the Contract Sum or Contract Time, the Contractor shall notify the Architect and shall not proceed to

implement the change in the Work.

§ 13.4 If concealed or unknown physical conditions are encountered at the site that are (1) subsurface or otherwise

concealed physical conditions that differ materially from those indicated in the Contract Documents or (2) unknown

physical conditions of an unusual nature that differ materially from those conditions ordinarily found to exist and

generally recognized as inherent in construction activities of the character provided for in the Contract Documents,

the Contract Sum and Contract Time shall be equitably adjusted as mutually agreed between the Owner and

Contractor; provided that the Contractor provides notice to the Owner and Architect promptly and before conditions

are disturbed and in no event later than 21 days after first observance of the conditions. The Architect will promptly

investigate such conditions and, if the Architect determines that they differ materially and cause an increase or

decrease in the Contractor’s cost of, or time required for, performance of any part of the Work, will recommend an

equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions

at the site are not materially different from those indicated in the Contract Documents and that no change in the

terms of the Contract is justified, the Architect shall promptly notify the Owner and Contractor in writing, stating the

reasons. If either party disputes the Architect’s determination or recommendation, that party may proceed as

provided in Article 15.

.

ARTICLE 14 TIME § 14.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing this Agreement

the Contractor confirms that the Contract Time is a reasonable period for performing the Work.

§ 14.2 Unless otherwise provided, Contract Time is the period of time, including authorized adjustments, allotted in

the Contract Documents for Substantial Completion of the Work.

§ 14.3 The term “day” as used in the Contract Documents shall mean calendar day unless otherwise specifically

defined.

§ 14.4 The date of Substantial Completion is the date certified by the Architect in accordance with Section 15.6.3.

§ 14.5 If the Contractor is delayed at any time in the commencement or progress of the Work by (1) changes ordered

in the Work; (2) by labor disputes, fire, unusual delay in deliveries, abnormal adverse weather conditions not

reasonably anticipatable, unavoidable casualties, or any causes beyond the Contractor’s control; or (3) by other

causes that the Contractor asserts, and the Architect determines, justify delay, then the Contract Time shall be

Page 34: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

19

extended by Changer Order for such reasonable time as the Owner and Architect may determine, but only if there

was not a concurrent critical path delay in the performance of the Work resulting from any other cause for which the

Contractor is not entitled to an extension in the Contract Time under the Contract Documents. The Contractor

further acknowledges and agrees that adjustments in the Contract Time will be permitted for a delay only to the

extent such delay (i) is not caused by the Contractor, (ii) could not be limited or avoided by the Contractor’s timely

notice to the Owner and Architect of the delay or reasonable likelihood that a delay will occur, and (iii) is of a

duration not less than one (1) day. Contractor shall strictly comply with all notice and time requirements contained

herein. Failure to strictly adhere thereto shall constitute a complete waiver of any claim for an extension of time or

additional compensation for delay.

ARTICLE 15 PAYMENTS AND COMPLETION § 15.1 Schedule of Values § 15.1.1 Where the Contract is based on a Stipulated Sum or the Cost of the Work with a Guaranteed Maximum

Price pursuant to Section 3.2 or 3.4, the Contractor shall submit a schedule of values to the Architect before the first

Application for Payment, allocating the entire Stipulated Sum or Guaranteed Maximum Price to the various portions

of the Work. The schedule of values shall be prepared in the form, and supported by the data to substantiate its

accuracy required by the Architect. This schedule of values shall be used as a basis for reviewing the Contractor’s

Applications for Payment.

§ 15.1.2 The allocation of the Stipulated Sum or Guaranteed Maximum Price under this Section 15.1 shall not

constitute a separate stipulated sum or guaranteed maximum price for each individual line item in the schedule of

values.

§ 15.2 Control Estimate [NOT APPLICABLE]

§ 15.3 Applications for Payment § 15.3.1 At least thirty (30) days before the date established for each progress payment, the Contractor shall submit

to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required

under Section 15.1, for completed portions of the Work. The application shall be notarized, if required; be supported

by all data substantiating the Contractor’s right to payment that the Owner or Architect require; shall reflect

retainage if provided for in the Contract Documents; and include any revised cost control information required by

Section 15.2.4. Such Application for Payment shall be certified as correct by an officer of Contractor and shall be

accompanied by acknowledgments of payment and other documentation from subcontractors’, materialmen and

suppliers as may be required by the Architect or Owner. In addition, such Application for Payment shall contain a

certification by the Contractor that there are no Claims by Contractor for which Owner and Architect have not

received written notice as required in Article 21; that there have been no claims submitted to the Contractor at the

date of such Application for Payment; and that all due and payable bills with respect to the Work have been paid to

date or shall be paid from the proceeds of such Application for Payment. Applications for Payment shall not include

requests for payment for portions of the Work for which the Contractor does not intend to pay a Subcontractor or

supplier, unless such Work has been performed by others whom the Contractor intends to pay and does promptly

pay.

§ 15.3.2 With each Application for Payment where the Contract Sum is based upon the Cost of the Work, or the Cost

of the Work with a Guaranteed Maximum Price, the Contractor shall submit payrolls, petty cash accounts, receipted

invoices or invoices with check vouchers attached, and any other evidence required by the Owner to demonstrate

that cash disbursements already made by the Contractor on account of the Cost of the Work equal or exceed

progress payments already received by the Contractor plus payrolls for the period covered by the present

Application for Payment, less that portion of the progress payments attributable to the Contractor’s Fee.

§ 15.3.3 Payments shall be made on account of materials and equipment delivered and suitably stored at the site for

subsequent incorporation in the Work. If approved in advance by the Owner, payment may similarly be made for

materials and equipment stored, and protected from damage, off the site at a location agreed upon in writing.

§ 15.3.4 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner

no later than the time of payment. The fact that retainage may be withheld shall not affect or limit the Owner’s title

to the Work or material. The Contractor further warrants that upon submittal of an Application for Payment all

Work for which Certificates for Payment have been previously issued and payments received from the Owner shall,

Page 35: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

20

to the best of the Contractor’s knowledge, information and belief, be free and clear of liens, claims, security interests

or other encumbrances adverse to the Owner’s interests. Contractor shall indemnify and hold the Owner harmless

against any liens, claims, security interests or other encumbrances adverse to the Owner’s interests.

§ 15.4 Certificates for Payment § 15.4.1 The Architect will, within seven days after receipt of the Contractor’s Application for Payment, either issue

to the Owner a Certificate for Payment, with a copy to the Contractor, for such amount as the Architect determines

is properly due, or notify the Contractor and Owner of the Architect’s reasons for withholding certification in whole

or in part as provided in Section 15.4.3.

§ 15.4.2 The issuance of a Certificate for Payment will constitute a representation by the Architect to the Owner,

based on the Architect’s evaluations of the Work and the data in the Application for Payment, that, to the best of the

Architect’s knowledge, information, and belief, the Work has progressed to the point indicated, the quality of the

Work is in accordance with the Contract Documents, and the Contractor is entitled to payment in the amount

certified. The foregoing representations are subject to an evaluation of the Work for conformance with the Contract

Documents upon Substantial Completion, to results of subsequent tests and inspections, to correction of minor

deviations from the Contract Documents prior to completion and to specific qualifications expressed by the

Architect. However, the issuance of a Certificate for Payment will not be a representation that the Architect has (1)

made exhaustive or continuous on-site inspections to check the quality or quantity of the Work; (2) reviewed

construction means, methods, techniques, sequences, or procedures; (3) reviewed copies of requisitions received

from Subcontractors and suppliers and other data requested by the Owner to substantiate the Contractor’s right to

payment; or (4) made examination to ascertain how or for what purpose the Contractor has used money previously

paid on account of the Contract Sum.

§ 15.4.3 The Architect may withhold a Certificate for Payment in whole or in part, to the extent reasonably necessary

to protect the Owner, if in the Architect’s or Owner’s opinion the representations to the Owner required by Section

15.4.2 cannot be made. If the Architect is unable to certify payment in the amount of the Application, the Architect

will notify the Contractor and Owner as provided in Section 15.4.1. If the Contractor and the Architect cannot agree

on a revised amount, the Architect will promptly issue a Certificate for Payment for the amount for which the

Architect is able to make such representations to the Owner. The Architect may also withhold a Certificate for

Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for

Payment previously issued, to such extent as may be necessary in the Architect’s opinion to protect the Owner from

loss for which the Contractor is responsible, including loss resulting from acts and omissions described in Section

9.2.2, because of

.1 defective Work not remedied;

.2 third-party claims filed or reasonable evidence indicating probable filing of such claims unless security

acceptable to the Owner is provided by the Contractor;

.3 failure of the Contractor to make payments properly to Subcontractors or suppliers for labor, materials

or equipment;

.4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;

.5 damage to the Owner or a Separate Contractor;

.6 failure of Contractor to achieve the progress required by Contractor’s Construction Schedule;

.7 reasonable evidence that the Work will not be completed within the Contract Time and that the unpaid

balance would not be adequate to cover actual or liquidated damages for the anticipated delay or the

cost of recovery to overcome the delay; or

.8 repeated failure to carry out the Work in accordance with the Contract Documents.

The Owner may withhold payment on any Certificate of Payment on the same grounds the Architect may withhold

or nullify a Certificate of Payment.

§ 15.4.4 When either party disputes the Architect’s decision regarding a Certificate for Payment under Section

15.4.3, in whole or in part, that party may submit a Claim in accordance with Article 21, provided, however, that if

Contractor disputes a determination by the Architect or Owner with regard to a Certificate of Payment, Contractor

nevertheless shall expeditiously continue to prosecute the remainder of the Work.

.

Page 36: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

21

§ 15.4.5 Notwithstanding any other provision of this Contract, the Owner shall not be deemed to be in breach of this

Contract by reason of the withholding of any payment or part of a payment which the Architect has not certified or

which Owner declines to pay on the grounds set forth in Section 15.4.3.

§ 15.5 Progress Payments § 15.5.1 The Contractor shall pay each Subcontractor, no later than seven days after receipt of payment from the

Owner, the amount to which the Subcontractor is entitled, reflecting percentages actually retained from payments to

the Contractor on account of the Subcontractor’s portion of the Work. The Contractor shall, by appropriate

agreement with each Subcontractor, require each Subcontractor to make payments to sub-subcontractors in a similar

manner.

§ 15.5.2 Neither the Owner nor Architect shall have an obligation to pay or see to the payment of money to a

Subcontractor or supplier except as may otherwise be required by law.

§ 15.5.3 A Certificate for Payment, a progress payment, or partial or entire use or occupancy of the Project by the

Owner shall not constitute acceptance of Work not in accordance with the Contract Documents.

§ 15.5.4 Provided the Owner has fulfilled its payment obligations under the Contract Documents, the Contractor shall

defend and indemnify the Owner from all loss, liability, damage or expense, including reasonable attorney’s fees

and litigation expenses, arising out of any lien claim or other claim for payment by any Subcontractor or supplier of

any tier. Upon receipt of notice of a lien claim or other claim for payment, the Owner shall notify the Contractor. If

approved by the applicable court, when required, the Contractor may substitute a surety bond for the property

against which the lien or other claim for payment has been asserted.

§ 15.5.6 If the Owner is entitled to reimbursement or payment from the Contractor under or pursuant to the Contract

Documents, such payment shall be made promptly upon demand by the Owner. Notwithstanding any provisions in

the Contract Documents to the contrary, if the Contractor fails to promptly make any payment due the Owner, if the

Owner incurs any costs and expenses to cure any default of the Contractor or to correct defective Work, or if the

Architect awards a Claim to another Contractor chargeable against Contractor, the Owner shall have an absolute

right to offset such amount against the Contract Sum and may, in the Owner’s sole discretion, elect to (i) deduct

such amount from any payment then or thereafter due the Contractor from the Owner, or (ii) issue a written notice to

the Contractor reducing the Contract Sum.

§ 15.6 Substantial Completion § 15.6.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof

is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the

Work for its intended use.

§ 15.6.2 When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept

separately, is substantially complete, the Contractor shall prepare and submit to the Architect a comprehensive list of

items to be completed or corrected prior to final payment. Failure to include an item on such list does not alter the

responsibility of the Contractor to complete all Work in accordance with the Contract Documents.

§ 15.6.3 Upon receipt of the Contractor’s list, the Architect will make an inspection to determine whether the Work

or designated portion thereof is substantially complete. When the Architect determines and the Owner agrees that

the Work or designated portion thereof is substantially complete, the Architect will issue a Certificate of Substantial

Completion which shall establish the date of Substantial Completion; establish responsibilities of the Owner and

Contractor for security, maintenance, heat, utilities, damage to the Work and insurance; and fix the time within

which the Contractor shall finish all items on the list accompanying the Certificate. Warranties required by the

Contract Documents shall commence on the date of Substantial Completion of the Work or designated portion

thereof unless otherwise provided in the Certificate of Substantial Completion.

§ 15.6.4 The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their written

acceptance of responsibilities assigned to them in the Certificate. Upon such acceptance and consent of surety, if

Page 37: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

22

any, the Owner shall make payment of retainage applying to the Work or designated portion thereof. Such payment

shall be adjusted for Work that is incomplete or not in accordance with the requirements of the Contract Documents.

§ 15.7 Final Completion and Final Payment § 15.7.1 Upon receipt of the Contractor’s notice that the Work is ready for final inspection and acceptance and upon

receipt of a final Application for Payment, the Architect will promptly make such inspection and, when the Architect

finds and the Owner agrees that the Work is acceptable under the Contract Documents and that the Contract is fully

performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s

knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has

been completed in accordance with the Contract Documents and that the entire balance found to be due the

Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will

constitute a further representation that conditions stated in Section 15.7.2 as precedent to the Contractor’s being

entitled to final payment have been fulfilled.

§ 15.7.2 Neither final payment nor any remaining retained percentage shall become due until the Contractor submits

to the Architect and Owner (1) an affidavit that payrolls, bills for materials and equipment, and other indebtedness

connected with the Work have been paid or otherwise satisfied, (2) a certificate evidencing that insurance required

by the Contract Documents to remain in force after final payment is currently in effect and will not be canceled or

allowed to expire until at least thirty (30) days’ prior written notice has been given to the Owner, (3) a written

statement that the Contractor knows of no substantial reason that the insurance will not be renewable to cover the

period required by the Contract Documents, (4) consent of surety, if any, to final payment and (5), if required by the

Owner, other data establishing payment or satisfaction of obligations, such as acknowledgements of payments,

receipts, releases and waivers of liens, claims, security interests or encumbrances arising out of the Contract, to the

extent and in such form as may be designated by the Owner. If a Subcontractor refuses to furnish a release or waiver

required by the Owner, the Contractor may furnish a bond satisfactory to the Owner to indemnify the Owner against

such claim. If such claim remains unsatisfied after payments are made, the Contractor shall refund to the Owner all

money that the Owner may be compelled to pay in discharging such claim, including all costs and reasonable

attorneys’ fees. The Contractor shall furnish such evidence as may be necessary to show that out-of-state

subcontractors or suppliers have fully met the requirements of payment of taxes as established in the law of the State

or local subdivision thereof which may be in effect at the time of final payment..

§ 15.7.3 The making of final payment shall constitute a waiver of claims by the Owner except those arising from

.1 liens, claims, security interests or encumbrances arising out of the Contract and unsettled;

.2 failure of the Work to comply with the requirements of the Contract Documents;

.3 terms of warranties required by the Contract Documents; or

.4 audits performed by the Owner, if permitted by the Contract Documents, after final payment.

§ 15.7.4 Acceptance of final payment by the Contractor, a Subcontractor or supplier shall constitute a waiver of

claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of

the final Application for Payment.

ARTICLE 16 PROTECTION OF PERSONS AND PROPERTY § 16.1 Safety Precautions and Programs The Contractor shall be responsible for initiating, maintaining, and supervising all safety precautions and programs

in connection with the performance of the Contract. The Contractor shall take reasonable precautions for safety of,

and shall provide reasonable protection to prevent damage, injury, or loss to

.1 employees on the Work and other persons who may be affected thereby;

.2 the Work and materials and equipment to be incorporated therein, whether in storage on or off the site,

under care, custody, or control of the Contractor, a Subcontractor, or a Sub-subcontractor; and

.3 other property at the site or adjacent thereto, such as trees, shrubs, lawns, walks, pavements, roadways,

structures and utilities not designated for removal, relocation, or replacement in the course of

construction.

The Contractor shall comply with, and give notices required by, applicable laws, statutes, ordinances, codes, rules

and regulations, and lawful orders of public authorities bearing on safety of persons and property and their

protection from damage, injury, or loss. The Contractor shall promptly remedy damage and loss to property caused

in whole or in part by the Contractor, a Subcontractor, a sub-subcontractor, or anyone directly or indirectly

Page 38: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

23

employed by any of them, or by anyone for whose acts they may be liable and for which the Contractor is

responsible under Sections 16.1.2 and 16.1.3. The Contractor may make a claim for the cost to remedy the damage

or loss to the extent such damage or loss is attributable to acts or omissions of the Owner or Architect or by anyone

for whose acts either of them may be liable, and not attributable to the fault or negligence of the Contractor. The

foregoing obligations of the Contractor are in addition to the Contractor’s obligations under Section 9.15.

§ 16.2 Hazardous Materials and Substances § 16.2.1 The Contractor is responsible for compliance with the requirements of the Contract Documents regarding

hazardous materials or substances. If the Contractor encounters a hazardous material or substance not addressed in

the Contract Documents, and if reasonable precautions will be inadequate to prevent foreseeable bodily injury or

death to persons resulting from a material or substance, including but not limited to asbestos or polychlorinated

biphenyl (PCB), encountered on the site by the Contractor, the Contractor shall, upon recognizing the condition,

immediately stop Work in the affected area and notify the Owner and Architect of the condition. When the material

or substance has been rendered harmless, Work in the affected area shall resume upon written agreement of the

Owner and Contractor. By Change Order, the Contract Time shall be extended appropriately and the Contract Sum

shall be increased in the amount of the Contractor’s reasonable additional costs of shutdown, delay, and start-up.

§ 16.2.2 In the event the Owner believes the Contractor likely will encounter lead paint and / or asbestos on the

Project and included a notice to the Contractor of the likely presence of lead paint and / or asbestos the Bid

Documents, notwithstanding any provision of Section 16.2.1 to the contrary, Contractor acknowledges it shall be

responsible for all testing, abatement, removal, remediation, disposal and clean up of such Hazardous Materials and

to properly protect all people working on or visiting the project. Except as provided herein, the remaining

provisions of Section 16.2 shall remain in full force and effect, including, but not limited to, the Contractor's

obligation to report the presence of any such Hazardous Materials to the Owner prior to any disturbance of such

Hazardous Materials.

ARTICLE 17 INSURANCE AND BONDS § 17.1 Contractor’s Insurance § 17.1.1 The Contractor shall purchase and maintain insurance of the types and limits of liability, containing the

endorsements, and subject to the terms and conditions, as described in this Section 17.1 or elsewhere in the Contract

Documents. The Contractor shall purchase and maintain the insurance required by this Agreement from an insurance

company or insurance companies lawfully authorized to issue insurance in the jurisdiction where the Project is

located. The Contractor shall maintain the required insurance until the expiration of the period for correction of

Work as set forth in Section 18.4, unless a different duration is stated below:

« »

§ 17.1.2 Commercial General Liability insurance for the Project written on an occurrence form with policy limits of

not less than « five million dollars » ($ «5,000,000 » ) each occurrence, «five million dollars » ($ «$5,000,000 » )

general aggregate, and « five million dollars » ($ «5,000,000 » ) aggregate for products-completed operations

hazard, providing coverage for claims including

.1 damages because of bodily injury, sickness or disease, including occupational sickness or disease, and

death of any person;

.2 personal and advertising injury;

.3 damages because of physical damage to or destruction of tangible property, including the loss of use of

such property;

.4 bodily injury or property damage arising out of completed operations; and

.5 the Contractor’s indemnity obligations under Section 9.15.

§ 17.1.3 Automobile Liability covering vehicles owned by the Contractor and non-owned vehicles used by the

Contractor, with policy limits of not less than «one million » ($ «1,000,000 » ) per accident, for bodily injury, death

of any person, and property damage arising out of the ownership, maintenance, and use of those motor vehicles

along with any other statutorily required automobile coverage.

§ 17.1.4 The Contractor may achieve the required limits and coverage for Commercial General Liability and

Automobile Liability through a combination of primary and excess or umbrella liability insurance, provided such

primary and excess or umbrella insurance policies result in the same or greater coverage as those required under

Page 39: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

24

Section 17.1.2 and 17.1.3, and in no event shall any excess or umbrella liability insurance provide narrower

coverage than the primary policy. The excess policy shall not require the exhaustion of the underlying limits only

through the actual payment by the underlying insurers.

§ 17.1.5 Workers’ Compensation at statutory limits.

§ 17.1.6 Employers’ Liability with policy limits not less than « one million dollars » ($ «1,000,000 » ) each accident,

«one million dollars » ($ «1,000,000 » ) each employee, and «five million » ($ «5,000,000 » ) policy limit.

§ 17.1.7 If the Contractor is required to furnish professional services as part of the Work, the Contractor shall procure

Professional Liability insurance covering performance of the professional services, with policy limits of not less

than « two million dollars » ($ «2,000,000 » ) per claim and « two million dollars » ($ «2,000,000 » ) in the

aggregate.

§ 17.1.8 If the Work involves the transport, dissemination, use, or release of pollutants, the Contractor shall procure

Pollution Liability insurance, with policy limits of not less than « one million dollars » ($ « 1,000,000 » ) per claim

and «two million dollars » ($ «2,000,000 » ) in the aggregate.

§ 17.1.9 Coverage under Sections 17.1.7 and 17.1.8 may be procured through a Combined Professional Liability and

Pollution Liability insurance policy, with combined policy limits of not less than «two million dollars » ($

«2,000,000 » ) per claim and «two million dollars » ($ «2,000,000 » ) in the aggregate.

§ 17.1.10 The Contractor shall provide certificates of insurance acceptable to the Owner evidencing compliance with

the requirements in this Section 17.1 at the following times: (1) prior to commencement of the Work; (2) upon

renewal or replacement of each required policy of insurance; and (3) upon the Owner’s written request. An

additional certificate evidencing continuation of liability coverage, including coverage for completed operations,

shall be submitted with the final Application for Payment and thereafter upon renewal or replacement of such

coverage until the expiration of the period required by Section 17.1.1. The certificates will show the Owner as an

additional insured on the Contractor’s Commercial General Liability and excess or umbrella liability policy.

§ 17.1.11 The Contractor shall disclose to the Owner any deductible or self- insured retentions applicable to any

insurance required to be provided by the Contractor.

§ 17.1.12 To the fullest extent permitted by law, the Contractor shall cause the commercial liability coverage

required by this Section 17.1 to include (1) the Owner, the Architect, and the Architect’s Consultants as additional

insureds for claims caused in whole or in part by the Contractor’s negligent acts or omissions during the

Contractor’s operations; and (2) the Owner as an additional insured for claims caused in whole or in part by the

Contractor’s negligent acts or omissions for which loss occurs during completed operations. The additional insured

coverage shall be primary and non-contributory to any of the Owner’s general liability insurance policies and shall

apply to both ongoing and completed operations. To the extent commercially available, the additional insured

coverage shall be no less than that provided by Insurance Services Office, Inc. (ISO) forms CG 20 10 07 04, CG 20

37 07 04, and, with respect to the Architect and the Architect’s Consultants, CG 20 32 07 04.

§ 17.1.13 Within three (3) business days of the date the Contractor becomes aware of an impending or actual

cancellation or expiration of any insurance required by this Section 17.1, the Contractor shall provide notice to the

Owner of such impending or actual cancellation or expiration. Upon receipt of notice from the Contractor, the

Owner shall, unless the lapse in coverage arises from an act or omission of the Owner, have the right to stop the

Work until the lapse in coverage has been cured by the procurement of replacement coverage by the Contractor. The

furnishing of notice by the Contractor shall not relieve the Contractor of any contractual obligation to provide any

required coverage.

§ 17.1.14 Other Insurance Provided by the Contractor (List below any other insurance coverage to be provided by the Contractor and any applicable limits.)

Coverage Limits « »

Page 40: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

25

§ 17.2 Owner’s Insurance § 17.2.1 Owner’s Liability Insurance The Owner shall be responsible for purchasing and maintaining the Owner’s usual liability insurance.

§ 17.2.2 Property Insurance § 17.2.2.1 The Owner shall purchase and maintain, from an insurance company or insurance companies lawfully

authorized to issue insurance in the jurisdiction where the Project is located, property insurance written on a

builder's risk “all-risks” completed value or equivalent policy form and sufficient to cover the total value of the

entire Project on a replacement cost basis. The Owner’s property insurance coverage shall be no less than the

amount of the initial Contract Sum, plus the value of subsequent Modifications and labor performed or materials or

equipment supplied by others. The property insurance shall be maintained until Substantial Completion and

thereafter as provided in Section 17.2.2.2, unless otherwise provided in the Contract Documents or otherwise agreed

in writing by the parties to this Agreement. This insurance shall include the interests of the Owner, Contractor,

Subcontractors, and Sub-subcontractors in the Project as insureds. This insurance shall include the interests of

mortgagees as loss payees.

§ 17.2.2.2 Unless the parties agree otherwise, upon Substantial Completion, the Owner shall continue the insurance

required by Section 17.2.2.1 or, if necessary, replace the insurance policy required under Section 17.2.2.1 with

property insurance written for the total value of the Project that shall remain in effect until expiration of the period

for correction of the Work set forth in Section 18.4.

§ 17.2.2.3 If the insurance required by this Section 17.2.2 is subject to deductibles or self-insured retentions, the

Owner shall be responsible for all loss not covered because of such deductibles or retentions.

§ 17.2.2.4 If the Work involves remodeling an existing structure or constructing an addition to an existing structure,

the Owner shall purchase and maintain, until the expiration of the period for correction of Work as set forth in

Section 18.4, “all-risks” property insurance, on a replacement cost basis, protecting the existing structure against

direct physical loss or damage, notwithstanding the undertaking of the Work. The Owner shall be responsible for all

co-insurance penalties.

§ 17.2.2.5 Prior to commencement of the Work, the Owner shall secure the insurance, and provide evidence of the

coverage, required under this Section 17.2.2 and, upon the Contractor’s request, provide a copy of the property

insurance policy or policies required by this Section 17.2.2. The copy of the policy or policies provided shall contain

all applicable conditions, definitions, exclusions, and endorsements.

§ 17.2.2.6 Within three (3) business days of the date the Owner becomes aware of an impending or actual

cancellation or expiration of any insurance required by this Section 17.2.2, the Owner shall provide notice to the

Contractor of such impending or actual cancellation or expiration. Unless the lapse in coverage arises from an act or

omission of the Contractor: (1) the Contractor, upon receipt of notice from the Owner, shall have the right to stop

the Work until the lapse in coverage has been cured by the procurement of replacement coverage by either the

Owner or the Contractor; (2) the Contract Time and Contract Sum shall be equitably adjusted; and (3) the Owner

waives all rights against the Contractor, Subcontractors, and Sub-subcontractors to the extent any loss to the Owner

would have been covered by the insurance had it not expired or been cancelled. If the Contractor purchases

replacement coverage, the cost of the insurance shall be charged to the Owner by an appropriate Change Order. The

furnishing of notice by the Owner shall not relieve the Owner of any contractual obligation to provide required

insurance.

§ 17.2.2.7 Waiver of Subrogation § 17.2.2.7.1 The Owner and Contractor waive all rights against (1) each other and any of their subcontractors, sub-

subcontractors, agents, and employees, each of the other; (2) the Architect and Architect’s consultants; and (3)

Separate Contractors, if any, and any of their subcontractors, sub-subcontractors, agents, and employees, for

damages caused by fire, or other causes of loss, to the extent those losses are covered by property insurance required

by this Agreement or other property insurance applicable to the Project, except such rights as they have to proceeds

of such insurance. The Owner or Contractor, as appropriate, shall require similar written waivers in favor of the

individuals and entities identified above from the Architect, Architect’s consultants, Separate Contractors,

subcontractors, and sub-subcontractors. The policies of insurance purchased and maintained by each person or entity

agreeing to waive claims pursuant to this Section 17.2.2.7 shall not prohibit this waiver of subrogation. This waiver

Page 41: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

26

of subrogation shall be effective as to a person or entity (1) even though that person or entity would otherwise have a

duty of indemnification, contractual or otherwise, (2) even though that person or entity did not pay the insurance

premium directly or indirectly, or (3) whether or not the person or entity had an insurable interest in the damaged

property.

§ 17.2.2.7.2 If during the Project construction period the Owner insures properties, real or personal or both, at or

adjacent to the site by property insurance under policies separate from those insuring the Project, or if after final

payment property insurance is to be provided on the completed Project through a policy or policies other than those

insuring the Project during the construction period, to the extent permissible by such policies, the Owner waives all

rights in accordance with the terms of Section 17.2.2.7.1 for damages caused by fire or other causes of loss covered

by this separate property insurance.

§ 17.2.2.8 A loss insured under the Owner’s property insurance shall be adjusted by the Owner as fiduciary and made

payable to the Owner as fiduciary for the insureds, as their interests may appear, subject to requirements of any

applicable mortgagee clause. The Owner shall pay the Architect and Contractor their just shares of insurance

proceeds received by the Owner, and by appropriate agreements, written where legally required for validity, the

Architect and Contractor shall make payments to their consultants and Subcontractors in similar manner.

§ 17.2.3 Other Insurance Provided by the Owner (List below any other insurance coverage to be provided by the Owner and any applicable limits.)

Coverage Limits « »

§ 17.3 Performance Bond and Payment Bond § 17.3.1 To the extent required by N.C. Gen. Stat. § 44A-26, the Contractor shall furnish bonds covering faithful

performance of the Contract and payment of obligations arising thereunder as stipulated in the Contract Documents

on the date of execution of the Contract.

§ 17.3.2 Upon the request of any person or entity appearing to be a potential beneficiary of bonds covering payment

of obligations arising under the Contract, the Contractor shall promptly furnish a copy of the bonds or shall

authorize a copy to be furnished.

ARTICLE 18 CORRECTION OF WORK § 18.1 The Contractor shall promptly correct Work rejected by the Architect or failing to conform to the

requirements of the Contract Documents, whether discovered before or after Substantial Completion and whether or

not fabricated, installed, or completed. Costs of correcting such rejected Work, including additional testing and

inspections, the cost of uncovering and replacement, and compensation for the Architect’s services and expenses

made necessary thereby, shall be at the Contractor’s expense.

§ 18.2 In addition to the Contractor’s obligations under Section 9.4, if, within one year after the date of Substantial

Completion of the Work or designated portion thereof or after the date for commencement of warranties established

under Section 15.6.3, or by terms of an applicable special warranty required by the Contract Documents, any of the

Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct

it promptly after receipt of notice from the Owner to do so unless the Owner has previously given the Contractor a

written acceptance of such condition. The Owner shall give such notice promptly after discovery of the condition.

§ 18.3 If the Contractor fails to correct nonconforming Work within a reasonable time, the Owner may correct it in

accordance with Section 8.3.

§ 18.4 The one-year period for correction of Work shall be extended with respect to portions of Work first performed

after Substantial Completion by the period of time between Substantial Completion and the actual completion of that

portion of the Work.

§ 18.5 Nothing contained in this Article 18 shall be construed to establish a period of limitation with respect to other

obligations that the Contractor might have under the Contract Documents. Establishment of the one-year period for

correction of Work as described in Section 18.2 relates only to the specific warranty obligation of the Contractor to

correct the Work, and has no relationship to the time within which the obligation to comply with the Contract

Page 42: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

27

Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish

the Contractor’s liability with respect to the Contractor’s obligations other than specifically to correct the Work.

.

ARTICLE 19 MISCELLANEOUS PROVISIONS § 19.1 Assignment of Contract Neither party to the Contract shall assign the Contract without written consent of the other.

§ 19.2 Governing Law The Contract shall be governed and interpreted in accordance with the laws of the State of North Carolina,

notwithstanding any conflicts of law principles to the contrary that would suggest or require the law of any other

jurisdiction apply. If the parties have selected arbitration as the method of binding dispute resolution, the Federal

Arbitration Act shall govern Section 21.6.

§ 19.3 Tests and Inspections Tests, inspections, and approvals of portions of the Work required by the Contract Documents or by applicable laws,

statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities shall be made at an

appropriate time. Unless otherwise provided, the Contractor shall make arrangements for such tests, inspections, and

approvals with an independent testing laboratory or entity acceptable to the Owner, or with the appropriate public

authority, and shall bear all related costs of tests, inspections, and approvals. The Contractor shall give the Architect

timely notice of when and where tests and inspections are to be made so that the Architect may be present for such

procedures. The Owner shall bear costs of tests, inspections, or approvals that do not become requirements until

after bids are received or negotiations concluded.

§ 19.4 The Owner’s representative:

(Name, address, email address and other information)

«

« »

« »

« »

« »

§ 19.5 The Contractor’s representative:

(Name, address, email address and other information)

« »

« »

« »

« »

« »

§ 19.6 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ prior notice to the

other party.

ARTICLE 20 TERMINATION OF THE CONTRACT § 20.1 Termination by the Contractor If the Architect fails to certify payment as provided in Section 15.4.1 for a period of 30 days through no fault of the

Contractor, any Subcontractors, or the agents or employees of any of them, and has failed to notify the Contractor

of the reason for withholding certification as provided in Section 15.4.3, or if the Owner fails to make payment as

provided in Section 4.1.3 for a period of 30 days and has failed to notify the Contractor of the reason for withholding

payment as provided in Section 15.4.3, the Contractor may give twenty-one (21) days’ written notice to the Owner

and Architect that Contractor is considering terminating the Contract and shall state specifically and in detail all

grounds for termination. If Owner or Architect has not cured the specified grounds for termination set forth in the

written notice within twenty-one (21) days of receipt of such notice, Contractor may, upon giving fifteen (15)

additional days’ written notice, terminate the Contract and recover from the Owner payment for Work executed and

for proven loss with respect to materials, equipment, tools, and construction equipment and machinery, including

Page 43: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

28

reasonable job site overhead, cost and profit earned as of the date of termination. Contractor waives all claims

against the Owner for consequential damages including, but not limited to, damages incurred by the Contractor for

principal office expenses including the compensation of personnel stationed there, for losses of financing, business

and reputation, and for loss of profit except anticipated profit arising directly from the Work.

.

§ 20.2 Termination by the Owner for Cause § 20.2.1 The Owner may terminate the Contract if the Contractor

.1 refuses or fails to supply enough properly skilled workers or proper materials;

.2 fails to make payment to Subcontractors for materials or labor in accordance with the respective

agreements between the Contractor and the Subcontractors;

.3 disregards applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of a

public authority; .4 fails to begin remedial action within any time period set forth in any Notice of Violation issued by

NC DEQ, and/or within forty-eight (48) hours after receipt by the Contractor of written notice from

the Owner;

.5 falls more than fourteen (14) days behind the progress required by the Contractors Construction

Schedule (or fails to achieve any milestone as required therein), and fails promptly to take reasonable

steps, as determined by Owner, to regain the period of delay;

.6 fails to comply with its coordination and/or scheduling obligations; or

.7 otherwise is guilty of substantial breach of a provision of the Contract Documents.

§ 20.2.2 When any of the reasons described in Section 20.2.1 exists, the Owner may, without prejudice to

any other remedy the Owner may have and after giving the Contractor seven days’ notice, terminate

the Contract and:

.1 Take possession of the site and of all plans, files, electronic records or information, materials,

equipment, tools, and construction equipment and machinery thereon owned or leased by or in the

control of the Contractor;

.2 Take assignment of subcontracts pursuant to Section 11.5;

.3 Finish the Work by whatever reasonable method the Owner may deem expedient. Upon request of the

Contractor, the Owner shall furnish to the Contractor reasonable documentation of the costs incurred

by the Owner in finishing the Work; and

.4 Require Contractor to provide to Owner within seven days of notice of termination, a complete

summary and recap of all contracts and agreements with subcontractors, suppliers, materialmen,

consultants, independent contractors and any other entity with which Contractor has contracted in

connection with the Project (collectively the “Contractor’s Subcontractors”). The recap shall set out

the following information for each of the Contractor’s Subcontractors: (i) initial contract amount, (ii)

a list of all approved change orders, (iii) a list of all pending change orders and a description thereof,

(iv) a list of the billings by each of Contractor’s Subcontractors and a list of payments; (v) a list of the

amounts billed on each change order, and a list of payments and such other information and

documentation as the Owner or Architect may, in their discretion, require; (vi) a list of all applicable

offsets or backcharges. The required summary and recap shall be certified as correct by an officer of

Contractor. Along with the recap, Contractor shall deliver all invoices, evidences of payment,

subcontracts, change orders and agreements.

Upon receipt of notification of termination, Contractor shall not remove any of the property described in Section

20.2.2 and will take all necessary action not to interfere with Owner’s rights upon termination. Contractor

acknowledges that his failure to comply with the requirements of Sections 20.2.2 and 20.2.3 will entitle Owner to

equitable relief, including a mandatory injunction to compel Contractor’s performance.

§ 20.2.3 When the Owner terminates the Contract for one of the reasons stated in Section 20.2.1, the Contractor shall

not be entitled to receive further payment until the Work is finished.

§ 20.2.4 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work, including compensation for

the Architect’s services and expenses made necessary thereby, liquidated damages and other damages incurred by

the Owner and not expressly waived, such excess shall be paid to the Contractor. If such costs and damages exceed

the unpaid balance, the Contractor shall pay the difference to the Owner. The amount to be paid to the Contractor or

Page 44: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

29

Owner, as the case may be, shall be certified by the Architect, upon application, and this obligation for payment

shall survive termination of the Contract.

§ 20.3 Termination by the Owner for Convenience § 20.3.1 The Owner may, at any time, terminate the Contract for the Owner’s convenience and without cause.

§ 20.3.2 Upon receipt of written notice from the Owner of such termination for the Owner’s convenience, the

Contractor shall

.1 cease operations as directed by the Owner in the notice;

.2 take actions necessary, or that the Owner may direct, for the protection and preservation of the Work;

and

.3 except for Work directed to be performed prior to the effective date of termination stated in the

notice, terminate all existing subcontracts and purchase orders and enter into no further subcontracts

and purchase orders.

§ 20.3.3 Upon such termination, the Contractor shall recover, as its sole remedy, payment for Work properly

performed in connection with the terminated portion of the Work prior to the effective date of termination, for items

properly and timely fabricated off the Project site, delivered and stored in accordance with the Owner’s instructions,

and for reasonable cost of demobilization. The Contractor hereby waives and forfeits all other claims for payment

and damages, including, without limitation, anticipated profits. The Owner shall be credited for (i) payments

previously made to the Contractor for the terminated portion of the Work, (ii) claims that the Owner or other

Contractors have against the Contractor under the Contract, and (iii) the value of the materials, supplies, equipment,

or other items that are to be disposed of by the Contractor that are part of the Contract Sum.

§ 20.3.5 Contractor will include in each of its subcontracts and purchase order, a provision which allows

termination for convenience on the same terms as set forth above.

§ 20.4 Termination of the contract by Owner will not excuse Contractor or its surety for compliance of the Work

performed prior to the date of termination with the Contract Documents.

§ 20.5 In the event that Owner purports to terminate this Agreement for cause and it is subsequently determined that

no grounds for termination for cause exist, such termination shall be deemed a termination by Owner for

convenience, and the provisions of Article 20.3 shall be applicable.

ARTICLE 21 CLAIMS AND DISPUTES § 21.1 Claims, disputes, and other matters in question arising out of or relating to this Contract, including those

alleging an error or omission by the Architect but excluding those arising under Section 16.2, shall be referred

initially to the Architect for decision. Such matters, except those waived as provided for in Section 21.11 and

Sections 15.7.3 and 15.7.4, shall, after initial decision by the Architect or 30 days after submission of the matter to

the Architect, be subject to mediation as a condition precedent to binding dispute resolution.

§ 21.2 Notice of Claims § 21.2.1 Claims by the Contractor must be initiated by notice to the Architect within 21 days after occurrence of the

event giving rise to such Claim or within 21 days after the Contractor first recognizes, or reasonably should

recognize, the condition giving rise to the Claim, whichever is later.

§ 21.2.2 Time is of the essence with respect to providing notice and filing claims by Contractor. The initial notice of

claim filed in writing shall provide notice of the event giving rise to the claim with sufficient detail to allow

Architect and Owner to investigate such claim. The initial notice of claim filed by Contractor shall also include

Contractor’s best estimate of the additional cost and impact on the schedule. A final claim shall be filed by

Contractor within twenty-one (21) days from completion of the additional work involved in the claim. Such final

claim shall be fully documented with support for all costs claimed and shall include an updated schedule showing

the effect on the time for completion. Failure of Contractor to strictly comply with this procedure shall constitute a

waiver and release of such claim. Any claim shall represent the entire claim for that event, and no additional claims

for impact, delay, or cumulative effect shall be made by the Contractor.

§ 21.2.2 CLAIMS FOR ADDITIONAL TIME

Page 45: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

30

§ 21.2.2.1 If the Contractor wishes to obtain an increase in the Contract Time, a Claim should be submitted in strict

compliance with Section 21.2.2 and the other applicable requirements of Article 21. Contractor’s Claim for delay

must be supported by a critical path analysis which shows to the satisfaction of the Architect and Owner that the

delay involved was to a critical party activity (or activities), was not caused or materially contributed to in whole or

part by Contractor (or anyone for which Contractor is responsible) or any other Prime Contractor, and results in a

delay to Substantial Completion of the Work. Contractor will not be entitled to an extension of time or any damages

for delay where there is concurrent delay for which a Prime Contractor or Contractor (or anyone for which

Contractor is responsible) is responsible in whole or part. Contractor’s claim for additional compensation for delay

shall be limited to reasonable actual, additional direct costs incurred at the job site without mark-up for overhead and

profit. No consequential damages or home-office overhead or expenses shall be recoverable.

§ 21.2.2.2 If abnormal, adverse weather conditions are the basis for a Claim for additional time, such Claim shall be

documented by data substantiating that weather conditions were abnormal for the period of time, could not have

been reasonably anticipated and had an adverse effect on the critical path of construction. Claims for extension of

Contract Time for delays and excessive inclement weather (adverse weather) delay days shall be deemed to be

satisfied by the Owner granting an extension of time only and do not entitle the Contractor to reimbursement for

extended overhead or direct field supervision or other costs.

§ 21.2.3 Claims by either the Owner where the condition giving rise to the Claim is first discovered after expiration

of the period for correction of the Work set forth in Section 18.2, shall be initiated by notice to the Contractor.

§ 21.3 Time Limits on Claims The Owner and Contractor shall commence all claims and causes of action against the other and arising out of or

related to the Contract in accordance with the requirements of the final dispute resolution method selected in this

Agreement whether in contract, tort, breach of warranty, or otherwise, within the period specified by applicable law,

but in any case not more than 10 years after the date of Substantial Completion of the Work. The Owner and

Contractor waive all claims and causes of action not commenced in accordance with this Section 21.3.

§ 21.4 If a claim, dispute or other matter in question relates to or is the subject of a mechanic’s lien, the party

asserting such matter may proceed in accordance with applicable law to comply with the lien notice or filing

deadlines.

§ 21.5 The parties shall endeavor to resolve their disputes by mediation which, unless the parties mutually agree

otherwise, shall be administered by the American Arbitration Association in accordance with their Construction

Industry Mediation Procedures in effect on the date of this Agreement. A request for mediation shall be made in

writing, delivered to the other party to this Agreement, and filed with the person or entity administering the

mediation. The request may be made concurrently with the binding dispute resolution but, in such event, mediation

shall proceed in advance of binding dispute resolution proceedings, which shall be stayed pending mediation for a

period of 60 days from the date of filing, unless stayed for a longer period by agreement of the parties or court order.

If an arbitration is stayed pursuant to this Section, the parties may nonetheless proceed to the selection of the

arbitrator(s) and agree upon a schedule for later proceedings.

§ 21.6 If the parties have selected arbitration as the method for binding dispute resolution in this Agreement, any

claim, subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually

agree otherwise, shall be administered by the American Arbitration Association, in accordance with the

Construction Industry Arbitration Rules in effect on the date of this Agreement. Demand for arbitration shall be

made in writing, delivered to the other party to the Contract, and filed with the person or entity administering the

arbitration. The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in

accordance with applicable law in any court having jurisdiction thereof.

§ 21.7 Subject to the rules of the American Arbitration Association or other applicable arbitration rules, either party,

at its sole discretion, may consolidate an arbitration conducted under this Agreement with any other arbitration to

which it is a party provided that (1) the arbitration agreement governing the other arbitration permits consolidation;

(2) the arbitrations to be consolidated substantially involve common questions of law or fact; and (3) the arbitrations

employ materially similar procedural rules and methods for selecting arbitrator(s).

Page 46: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

AIA Document A104™ – 2017 (formerly A107™ – 2007). Copyright © 1936, 1951, 1958, 1961, 1963, 1966, 1970, 1974, 1978, 1987, 1997, 2007 and

2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and

International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil

and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at

09:53:33 on 08/24/2017 under Order No. 5291788124 which expires on 07/12/2018, and is not for resale.

User Notes: (3B9ADA2D)

31

§ 21.8 Subject to the rules of the American Arbitration Association or other applicable arbitration rules, any party to

an arbitration may include by joinder persons or entities substantially involved in a common question of law or fact

whose presence is required if complete relief is to be accorded in arbitration provided that the party sought to be

joined consents in writing to such joinder. Consent to arbitration involving an additional person or entity shall not

constitute consent to arbitration of a Claim not described in the written Consent.

§ 21.9 The foregoing agreement to arbitrate and other agreements to arbitrate with an additional person or entity duly

consented to by parties to this Agreement, shall be specifically enforceable under applicable law in any court having

jurisdiction thereof.

§ 21.10 Continuing Contract Performance Pending final resolution of a Claim, except as otherwise agreed in writing, the Contractor shall proceed diligently

with performance of the Contract and the Owner shall continue to make payments in accordance with the Contract

Documents.

§ 21.11 Waiver of Claims for Consequential Damages The Contractor waives claims against the Owner for consequential damages arising out of or relating to this

Contract. This waiver includes damages incurred by the Contractor for principal office expenses including the

compensation of personnel stationed there, for losses of financing, business and reputation, and for loss of profit

except anticipated profit arising directly from the Work.

This waiver is applicable, without limitation, to all consequential damages due to termination in accordance with

Article 20.

ARTICLE 22 NON-DISCRIMINATION § 22.1 The non-discrimination clause contained in Section 202 (Federal) Executive Order 11246, as amended by

Executive Order 11375, relative to equal employment opportunity for all persons without regard to race, color,

religion, sex or national origin, and the implementing rules and regulations prescribed by the secretary of Labor, are

incorporated herein.

§ 22.2 The Contractor agrees not to discriminate against any employee or applicant for employment because of

physical or mental handicap in regard to any position for which the employee or applicant is qualified. The

contractor agrees to take affirmative action to employ, advance in employment and otherwise treat qualified

handicapped individuals without discrimination based upon their physical or mental handicap in all employment

This Agreement entered into as of the day and year first written above.

« » « »

OWNER (Signature) CONTRACTOR (Signature)

« »« » « »« »

(Printed name and title) (Printed name and title)

Page 47: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Summary of Work 01 11 00 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 – GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Work Covered by Contract Documents

1.2.1 Work under this Contract consists of furnishing all labor, materials and equipment necessary to perform

the quality roof replacement of the Johnson St. Elementary School Roof, High Point, NC, as specified

herein and as shown on the Drawings. The work will include, but is not necessarily limited to, the

following:

1.2.2 The building will remain occupied during work. The contractor is responsible for taking all precautions

necessary to protect the building, contents, and personnel from damage or injury from his operations, and

from water entry into the building during construction. Refer to specification section 02 41 13 Selective

Demolition and Preparations for inclement weather requirements.

1.2.3 Scope of Work

1.2.3.1 Base Bid – Roof Area A:

(a) Water test all roof drains prior to any work and report any blockages or other

impediments to drainage to Owner and Designer, submit pre-work water test results to

Designer for record.

(b) Remove the existing membranes and insulations, to the existing gypsum roof deck. The

existing assembly is mechanically fastened, the existing fasteners should be cut by hand

to avoid damaging the gypsum deck.

(c) Examine gypsum deck and repair deteriorated areas, if deterioration is found, contact

designer and Owner.

(d) Remove any loose areas of the existing vapor barrier and prepare surface to receive the

new roof as required by the manufacturer.

(e) Remove all existing flashings, metal flashings, and miscellaneous items, and discard.

(f) Review existing roof drains and piping for deterioration, if deterioration is found,

contact designer and Owner.

(g) Furnish and install new red rosin paper separation layer of existing gypsum deck.

(h) Furnish and install new nailed SBS modified fiberglass base sheet.

(i) Furnish and install new adhered flat polyisocyanurate insulation boards (2 layers – R15

minimum) adhered tapered polyisocyanurate insulation boards for 1/8” min slope.

(j) Furnish and install new adhered coverboard.

Page 48: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Summary of Work 01 11 00 2

(k) Furnish and install new PVC single ply roof membrane.

1. Alternate 3: Furnish and install new modified bituminous roof membrane.

(l) Furnish and install new walkway pads.

(m) Furnish and install new membrane flashings and metal flashings.

(n) Furnish and install any miscellaneous items.

(o) Remove and reinstall any rooftop equipment and skylight domes that requires removal

in order to perform new work. The contractor must test all equipment immediately after

reinstallation. Notify the Owner immediately if the equipment does not operate

properly.

(p) Water test all roof drains prior to Final Acceptance and report any blockages or other

impediments to drainage to Owner and Designer. Contractor to provide all work and

testing required to ensure that drains operate equal to or better than pre-work water test

results. Submit final water test results for record.

1.2.3.2 Alternate 1 – Roof Areas B:

(a) Water test all roof drains prior to any work and report any blockages or other

impediments to drainage to Owner and Designer, submit pre-work water test results to

Designer for record.

(b) Remove the existing membranes and insulations, to the existing concrete roof deck.

(c) Examine concrete deck and repair deteriorated areas, if deterioration is found, contact

designer and Owner.

(d) Remove any loose areas of the existing vapor barrier and prepare surface to receive the

new roof as required by the manufacturer.

(e) Remove all existing flashings, metal flashings, and miscellaneous items, and discard.

(f) Review existing roof drains and piping for deterioration, if deterioration is found,

contact designer and Owner.

(g) Furnish and install new adhered flat polyisocyanurate insulation boards (2 layers – R15

minimum) adhered tapered polyisocyanurate insulation boards for 1/8” min slope.

(h) Furnish and install new adhered coverboard.

(i) Furnish and install new PVC single ply roof membrane.

1. Alternate 4: Furnish and install new modified bituminous roof membrane.

(j) Furnish and install new walkway pads.

(k) Furnish and install new membrane flashings and metal flashings.

(l) Furnish and install any miscellaneous items.

Page 49: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Summary of Work 01 11 00 3

(m) Remove and reinstall any rooftop equipment that requires removal in order to perform

new work. The contractor must test all equipment immediately after reinstallation.

Notify the Owner immediately if the equipment does not operate properly.

(n) Water test all roof drains prior to Final Acceptance and report any blockages or other

impediments to drainage to Owner and Designer. Contractor to provide all work and

testing required to ensure that drains operate equal to or better than pre-work water test

results. Submit final water test results for record.

1.2.3.3 Alternate 2: Replacement of all dome skylights and associated flashings at Roof Area A.

1.2.3.4 Existing Roof Systems:

(a) Information in this Section is provided only to establish general description and is

based on observations at test cuts made at selected locations and review of existing

drawings. The Contractor is responsible for visiting the site and satisfying himself as to

the existing conditions, size of roof areas, etc., before submitting his Bid.

(b) Roof Area “A”:

1. EPDM roof membrane

2. Base and tapered board insulation (6” +/-)

3. Gypsum deck

(c) Roof Area “B”:

1. EPDM roof membrane

2. Base and tapered board insulation (6” +/-)

3. Concrete deck

1.2.4 The approximate size of each roof area is as follows:

1.2.4.1 Area “A”: 8,950 square feet

1.2.4.2 Area “B”: 1,600 square feet

1.2.4.3 The approximate sizes are for information purposes only. The Contractor is responsible for

visiting the site and satisfying himself as to the existing conditions, size of roof areas, etc.,

before submitting his Bid.

PART 2 – PRODUCTS

2.1 Not used.

PART 3 – EXECUTION

3.1 Not used.

END OF SECTION

Page 50: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Work Restrictions 01 14 00 1

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Roof Access - access by means of stair towers, lifts, cranes, etc. shall only occur at designated staging areas as

shown on the drawings. Requests made by the contractor for roof access points at locations other than those

designated on the drawings shall be requested in writing of the Owner through the Designer a minimum of seven

(7) working days prior to the desired date of access. The Owner reserves the right to reject all or any requests

made.

1.3 Occupied Building:

1.3.1 Johnson St. Elementary School will remain in full operation during the entire construction period. The

Contractor shall conduct his operations so as to cause no interference with normal operation of the

facility.

1.3.2 Only pre-approved Contractor representatives shall enter the building. Pre-approved representatives must

wear name badges clearly identifying company and name of individual.

1.3.3 The building shall be kept secure at all times.

1.4 Permission to interrupt any drive lanes, loading areas, parking spaces shall be requested in writing of the Owner

through the Designer a minimum of seven (7) days prior to the desired date of interruption.

1.4.1 The Contractor shall exercise all means necessary to maintain temporary facilities and controls in proper

and safe condition throughout the progress of the project.

1.4.2 All required connections to existing utility systems shall be made with minimum disruption. If disruption

of existing service is required, notice shall be given to the Owner and connections shall not be made

without Owner's approval. If necessary, Contractor shall provide for alternate temporary service.

1.4.3 If the required utility is not available from the Owner, the Contractor shall provide for alternate temporary

service for the duration of the project.

1.5 Facility Access - Use of the interior to access the roof is not permitted.

1.6 Skylights – removal of the existing skylights requires coordination with the Owner and written approval. During

removal and after the skylights are removed, the interior below must be blocked off with a contractor

representative rerouting pedestrian traffic until the skylight has been reinstalled.

PART 2 – PRODUCTS – Not Used

PART 3 – EXECUTION – Not Used

END OF SECTION

Page 51: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Unit Prices and Allowances 01 22 13 1

SECTION 01 22 13

UNIT PRICES AND ALLOWANCES

PART 1 - GENERAL

1.1 Work Included: All unit prices and allowances as listed in Form of Proposal.

1.2 Procedures:

1.2.1 Unit prices will be exercised at the option of the Owner.

1.2.2 In the event unit prices are exercised, applicable sections of this Specification shall govern. Other

sections may be modified as required to address the unit price.

1.2.3 Cost associated with any anomalies identified on plans, on the roof, and/or in the Specification shall be

included in the Base Bid.

1.2.4 Cost associated with the repair of decking at removed abandoned penetrations identified on plans and/or

marked on the roof shall be included in the Base Bid.

1.2.5 Bidders shall provide a unit price for the items listed below and on the bid form. Bidder shall include a

cash allowance in the Base Bid for each unit price in the quantity list below and on the bid form. Payment

will be made for unit price work in excess of the cash allowance, which includes all overhead and profit.

In the event it is necessary to replace fewer than quantity associated with the cash allowance, the Owner

will take a credit at the unit price rate. The Design Professional shall be responsible for verifying the

actual quantity and extent of the unit price work.

PART 2 – PRODUCTS – Not Used

PART 3 - EXECUTION

3.1 UNIT PRICE No. (1): Where wood blocking or curbs are damaged or deteriorated, remove existing wood

blocking to a point 6 inches beyond the damage and/or deterioration and repair and/or replace with new wood

blocking to match existing. This unit price shall also reflect any power tools, fasteners, labor, safety harnesses,

interior protections, overhead, and profit associated with accomplishing this work. Refer to Section 02 41 13 of

the Specification.

3.2 UNIT PRICE No. (2): Repair and/or replacement of any damaged gypsum deck. Repairs shall meet the

requirements of the project specifications. This unit price shall also reflect any power tools, fasteners, labor, safety

harnesses, interior protections, overhead, and profit associated with accomplishing this work. Refer to Section 02

41 13 of the Specification.

3.3 UNIT PRICE No. (3): Remove damaged concrete to sound concrete and prepare damaged area per repair

materials manufacturer’s requirements in order to accept new material. Coat all exposed rebar with rust inhibiting

coating and allow to dry before proceeding with the installation of the repair material. Install repair material per

manufacturer’s requirements. This unit price shall also reflect any power tools, fasteners, labor, safety harnesses,

interior protections, overhead, and profit associated with accomplishing this work. Refer to Section 02 41 13 of

the Specification.

Page 52: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Unit Prices and Allowances 01 22 13 2

3.4 UNIT PRICE No. (4): Removal of existing roof drains and installation of new drains and 10’ minimum of drain

piping. Drain sizes shall match those of existing and piping shall match size and material. Install new drains and

piping per manufacturer’s requirements. This unit price shall also reflect any power tools, fasteners, labor, safety

harnesses, interior protections, overhead, and profit associated with accomplishing this work. Refer to Section 02

41 13 of the Specification.

END OF SECTION

Page 53: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Alternates 01 23 00 1

SECTION 01 23 00

ALTERNATES

PART 1 – GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Work Included - All alternates as listed on the Bid Form.

1.3 Procedures

1.3.1 Alternates will be exercised at the option of the Owner.

1.3.2 Modify and coordinate related activities as required to complete the work if, and when, acceptance is

designated by the Owner.

1.3.3 In the event alternates are exercised, applicable sections of this Specification shall govern. Other sections

may be modified as required to address the alternate.

1.3.4 The Owner reserves the right to accept any alternate and to accept any combination of alternates.

PART 2 – PRODUCTS

2.1 See applicable specification sections.

PART 3 – EXECUTION

3.1 Alternate No. 1: Roof Area B Roof Replacement (Single-ply System).

3.2 Alternate No. 2: Replacement of all dome skylights and associated flashings at Roof Area A.’

3.3 Alternate No. 3: Remove and replace existing roof system at Roof Area A with new modified bituminous system

in lieu of single-ply system.

3.4 Alternate No. 4: Roof Area B Roof Replacement (Modified Bituminous System).

END OF SECTION

Page 54: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Progress Reports 01 32 26 1

SECTION 01 32 26

PROGRESS REPORTS

PART 1 - GENERAL

1.1 Summary: Contractor shall keep a daily progress report to provide a continuous record of the progress of this

Work. The format of the report shall be as directed by the Designer.

1.2 Quality Assurance:

1.2.1 Reports shall be filled out on a daily basis by the Contractor's job site representative who shall be in a

supervisory capacity.

1.2.2 Reports shall be completed by the same individual throughout the duration of the Project wherever

possible.

PART 2 - PRODUCTS

2.1 Not Used.

PART 3 - EXECUTION

3.1 Contractor shall complete one form for each work day.

3.2 Forms shall be completed for work days shortened or cancelled due to weather, material shortages, labor

conditions or holidays.

3.3 Forms shall be legible with all pertinent items.

3.4 Submit copies to the Designer upon request.

3.5 Information required in the contractor’s daily report shall include the following:

3.5.1 Date

3.5.2 Company Name

3.5.3 Name of Superintendent/Foreman

3.5.4 Number of Workers

3.5.5 Weather Conditions

3.5.6 Location of Work Performed

3.5.7 Materials Installed

3.5.8 Description of Work Performed

3.5.9 Photographs of Unit Price Work which is in addition to the allowances stated (minimum of 4): Contractor

required to maintain a function digital camera with a minimum resolution of 12 megapixels. Photographs

Page 55: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Progress Reports 01 32 26 2

taken on cell phones shall not be allowed.

3.5.10 Photographs of the day’s sequence of work (minimum of 8): Contractor required to maintain a

functioning digital camera with a minimum resolution of 12 megapixels. Photographs taken on cell

phones shall not be allowed.

3.5.11 Project Issues/Request for Information

3.5.12 Name of Visitors

END OF SECTION

Page 56: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Submittals 01 33 00

SUBMITTAL CHECKLIST

(Submittal Log)

Johnson St. Elementary School Roof Replacement

Review is for general compliance with the contract documents. No responsibility is assumed for

correctness of dimensions or details.

Review Status:

Reviewed: Purchase/fabrication/installation may be undertaken.

Reviewed as Noted: Purchase/fabrication/installation may be undertaken subject to Designer’s comments.

Revise and Resubmit: Purchase/fabrication/installation may not be undertaken, revise per Designer’s comments and

resubmit.

Rejected: Purchase/fabrication/installation may not be undertaken.

ITEM DATE

RECEIVED

REVIEW

STATUS &

DATE

COMMENTS

General

1. Subcontractors

2. Material suppliers

3. Project Schedule

4. Schedule of values

5. CPM Bar Chart Schedule

Section 01 33 00

6. Foreman’s statement

7. Construction Logistics Plan

8. Emergency telephone numbers

Section 01 66 00

9. Site specific safety plan

Section 01 78 36

10. Membrane manufacturers sample

guarantee

11. Metal flashing manufacturer’s

sample guarantee

12. Metal roof coating manufacturer’s

sample guarantee

13. Skylight manufacturer’s sample

guarantee

Section 02 41 13

14. Concrete deck patch

15. Gypsum deck patch

16. Rust inhibiting coating

17. Wood nailers and fasteners

Section 06 10 53

18. Blocking

19. Plywood

Page 57: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Submittals 01 33 00

SUBMITTAL CHECKLIST

(Submittal Log)

Johnson St. Elementary School Roof Replacement

Review is for general compliance with the contract documents. No responsibility is assumed for

correctness of dimensions or details.

Review Status:

Reviewed: Purchase/fabrication/installation may be undertaken.

Reviewed as Noted: Purchase/fabrication/installation may be undertaken subject to Designer’s comments.

Revise and Resubmit: Purchase/fabrication/installation may not be undertaken, revise per Designer’s comments and

resubmit.

Rejected: Purchase/fabrication/installation may not be undertaken.

ITEM DATE

RECEIVED

REVIEW

STATUS &

DATE

COMMENTS

20. Tapered edge strip

21. Screws

22. Nails

23. Anchor bolts

24. Masonry fasteners

Section 07 22 16

25. Tapered insulation roof plan

26. Adhesive insulation roof plan

27. FM Global approved testing data

28. Flat insulation product data

29. Red rosin paper product data

30. Nailed base sheet product data

31. Tapered insulation product data

32. Wood fiber tapered edge strips

33. Cover board

34. Adhesive

35. Fire rated sealant

Section 07 52 16

36. Roof plan

37. Membrane

38. Membrane flashing

39. Flashing cement

40. Granules

41. Adhesives

42. Primer

43. PMMA/PMA liquid flashing

44. Walkway pads

45. Attachment

Page 58: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Submittals 01 33 00

SUBMITTAL CHECKLIST

(Submittal Log)

Johnson St. Elementary School Roof Replacement

Review is for general compliance with the contract documents. No responsibility is assumed for

correctness of dimensions or details.

Review Status:

Reviewed: Purchase/fabrication/installation may be undertaken.

Reviewed as Noted: Purchase/fabrication/installation may be undertaken subject to Designer’s comments.

Revise and Resubmit: Purchase/fabrication/installation may not be undertaken, revise per Designer’s comments and

resubmit.

Rejected: Purchase/fabrication/installation may not be undertaken.

ITEM DATE

RECEIVED

REVIEW

STATUS &

DATE

COMMENTS

Section 07 54 19

46. Roof plan

47. Membrane

48. Membrane flashing

49. PVC coated metal flashing

50. Membrane and metal color charts

51. Adhesive

52. Accessories

53. Termination Bar

54. Water cut off mastic

55. Liquid Applied Flashing

56. Membrane welding machines

57. Barrier Board

58. Walkway Pads

Section 07 60 00

59. Coping metal

60. Counter flashing metal

61. Termination bar

62. Pop rivets

63. Fasteners

64. Sealants

65. Splash blocks

66. Fire rated sealant

Section 07 92 00

67. Joint sealants

68. Backer rod

69. Bond breaker tape

70. Primer

Page 59: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Submittals 01 33 00

SUBMITTAL CHECKLIST

(Submittal Log)

Johnson St. Elementary School Roof Replacement

Review is for general compliance with the contract documents. No responsibility is assumed for

correctness of dimensions or details.

Review Status:

Reviewed: Purchase/fabrication/installation may be undertaken.

Reviewed as Noted: Purchase/fabrication/installation may be undertaken subject to Designer’s comments.

Revise and Resubmit: Purchase/fabrication/installation may not be undertaken, revise per Designer’s comments and

resubmit.

Rejected: Purchase/fabrication/installation may not be undertaken.

ITEM DATE

RECEIVED

REVIEW

STATUS &

DATE

COMMENTS

71. Cleaner

72. Tape

Section 08 62 00

73. Skylight product data

Section 15 42 00

74. Roof drain and drain pipe product

data

Page 60: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Submittals 01 33 00 1

SECTION 01 33 00

SUBMITTALS

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Procedures - Provide in digital format marked to show:

1.2.1 Project name

1.2.2 Contractor

1.2.3 Submittal number (as shown on submittal log and specification section and paragraph).

1.2.4 Contractor’s approval and date.

1.2.5 The specific material to be used:

1.2.5.1 Designate such information as model number, type, trade name, size, weight, color, material

type, manufacturer, etc.

1.2.5.2 Any requests for deviations from the contract shall be clearly identified.

1.2.5.3 Provide MSDS sheets for all submittals.

1.2.6 Address – Send all submittals to [email protected] , at Raymond Engineering-Georgia,

Inc.

1.2.7 Review – After Designer’s review of submittals, revise and resubmit, as required, identifying changes

made since previous submittal.

1.3 Site Specific Safety Plan – Refer to Section 01 66 00.

1.4 Construction Schedules – Submit a construction schedule in a gantt or bar chart schedule showing critical path

activities with dates for review. Update schedule bi-weekly and at each pay request, submit for review upon each

update.

1.5 Foreman's Statement - Submit on or before pre-construction conference.

1.6 Emergency phone number of principals, superintendent, foreman, project manager - Submit to Owner and

Engineer prior to the Pre-Construction Conference.

1.7 Pre-Construction Submittals

1.7.1 Emergency Contact Information - The Contractor will collect and deliver emergency contact information

to the designated Department of Administration Project Manager within 72 hrs of receipt of the executed

contract or at the first preconstruction meeting, whichever comes first. This information will be used in

the event of a project emergency to facilitate rapid communication with responsible project personnel.

Provide the firm’s contact information for each of the following trades and complete contact information

for the three most responsible persons assigned to the Project for each firm.

Page 61: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Submittals 01 33 00 2

1.7.2 Prior to the start of the project, the following items need to be submitted within 7 calendar days after the

receipt of signed Contract. The contractor shall fill out the attached Submittal checklist form, ensuring

that all items listed in this section, referenced for submittal in the specification, and/or items to be used on

this project are properly submitted. Items submitted must conform to the standards and expectations of

that material, detail, and/or procedure expressed in this specification. If not, that item may be rejected for

use by the Engineer.

1.7.3 The Contractor will provide a construction logistics plan for review and approval at the Pre-construction

Conference, the plan will document:

1.7.3.1 Date of proposed implementation (Proposed start date and likely duration.)

1.7.3.2 Map of project work limits and proposed staging/lay-down areas.

1.7.3.3 Plan for safe management of pedestrian & vehicular traffic around construction activity

1.7.3.4 Maintenance of ADA compliant accessible routes and accommodations

1.7.3.5 Safety fencing, barricades, and temporary facilities or services

1.7.3.6 Proposed temporary, MUTCD-compliant directional and informational signage.

1.7.3.7 Review will be conducted by the Owner and adjustments will be executed by the Contractor and

his assigns per the recommendations or requirements of the Owner prior to commencing work

on site

1.7.4 The following literature shall be submitted.

1.7.4.1 Contractor’s Letter of Good Standing with Manufacturer.

1.7.4.2 Manufacturer’s Sample 20 year warranty

1.7.4.3 Contractor’s 2 year warranty (within the specification)

1.7.4.4 Manufacturer’s Application Instructions

1.7.4.5 Contractor’s Foreman’s Statement

1.7.4.6 Contractor’s Construction Schedule

1.7.4.7 Contractor’s Schedule of Values (shall match the bid form)

1.7.4.8 Insulation Manufacturer’s Letter of Approval of Product Use on Project

1.7.4.9 Membrane Manufacturer’s Letter of Approval of Product Use on Project

1.7.5 Submit all materials as outlined in Part 2 of the Specification sections. Group and label material

submittals by Specification Section.

1.7.6 Submit metal flashing color charts.

1.7.7 Provide SDS or MSDS safety data sheets for all submittals.

1.7.8 Submit shop drawings in accordance to Section 01 33 23 and the submittal log or submittal checklist.

1.8 Close-out Submittals - see Specification 01 77 00 Project Closeout Procedures.

PART 2 - PRODUCTS

2.1 Membrane and associated membrane flashings are to be manufactured and labeled by the membrane materials

manufacturer or, if supplied by a different manufacturer, approved for use by membrane manufacturer in

Page 62: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Submittals 01 33 00 3

compliance with warranty requirements.

PART 3 - EXECUTION

3.1 Timing

3.1.1 Make all submittals in accordance with schedules specified herein.

3.1.2 Designer will be allowed a minimum of 10 calendar days following receipt of submittals for review.

3.1.3 Delays caused by tardiness in receipt of submittals shall not be an acceptable basis for extension of the

Contract completion date.

3.2 Review

3.2.1 The notations "No Exceptions Taken" or "Exceptions as Noted" shall authorize the Contractor to proceed

with fabrication, purchase, or both subject to the revisions, if any, required by the Engineer's review

comments.

3.2.2 The Contractor shall make all revisions, as required. If the Contractor considers any revisions to

constitute a change, he shall notify the Engineer under the provisions of the General Conditions.

3.2.3 Only those revisions directed or approved by the Engineer shall be shown on the re-submittal.

3.2.4 After a submittal has been approved by the Engineer, substitution of materials, equipment and/or

procedures shall not be considered unless accompanied by an acceptable explanation for the substitution.

3.3 Foreman's Statement – (to be signed and submitted by the contractor’s staff member who will be on site full time

and have supervisory responsibility to direct the construction, this person shall also be present at the

preconstruction meeting).

STATEMENT

Guilford County Schools

I, ___________________________ an employee of ______________________________________ hereby state that I

(Name) (Contractor)

have my own personal copy of the project specifications and drawings, have thoroughly read them and have visited the

work site.

By______________________________

Date_____________________________

Page 63: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Quality Control 01 45 00 1

SECTION 01 45 00

QUALITY CONTROL

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Quality Control – Contractor: Maintain quality control over products, services, site conditions, and workmanship,

to produce work of specified quality.

1.3 Quality Control – General

1.3.1 Work found in violation of the Specifications, or not in conformance with acceptable roofing

practices/standards, shall be subject to rejection including removal and replacement with new materials at

Contractor's expense.

1.3.2 Failure of Owner or Designer to discover or reject defective work, or work not in accordance with the

Contract, shall not be deemed an acceptance thereof, nor a waiver of Owner's rights to Contractor's

compliance with the Contract or performance of the work, or any part thereof. No partial or final

payment, or partial or entire occupancy, by Owner shall be deemed to be an acceptance with the Contract,

nor shall it be deemed a waiver by Owner or any of Owner's rights pursuant to this Contract or otherwise.

1.3.3 Membrane and base flashings shall be smooth to the substrate, and wrinkles in membrane or base

flashings shall be grounds for rejection.

1.3.4 The accumulation of debris and foam adhesive beneath new membrane is not acceptable and shall be

grounds for rejection.

1.4 Quality Control - Contractor:

1.4.1 Maintain quality control over products, services, site conditions, and workmanship, to produce work of

specified quality.

1.4.2 Promptly after the award, a preconstruction conference will be held at the job site. The contractor shall

be represented, as a minimum, by the superintendent or project manager and foreman who will actually

perform/supervise the work. Meetings with the designer and owner shall also be attended by the

superintendent or project manager and foreman who actually perform/supervise the work. Failure of

representation as stated may result in the rescheduling of the these meetings. Meetings during the project

may be held as often as the designer and owner deem necessary.

1.4.3 The contractor’s project foreman or superintendent who attended the pre-construction meeting shall be on

site at all times that work is being performed.

1.4.4 Subcontractor foremen or supervisor shall be on site at all times that the work is being performed. The

foremen shall be at the actual work site to observe workmanship and to be able to direct the work.

1.5 Quality Control - Owner:

1.5.1 The Owner reserves the right to retain the services of an independent construction monitoring

representative to provide full-time monitoring of the roof replacement. If the Owner engages this service,

the Contractor will be informed. Testing may be performed to determine any deficiencies.

Page 64: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Quality Control 01 45 00 2

1.5.2 The cost of such services as described in paragraph 1.5.1 above, will be borne by the Owner for the

contract time. The cost of any monitoring and testing required after this period of time due to the

installation being incomplete as a result of Contractor-controlled nonperformance will be borne by the

Contractor as stated in time of completion section of the Supplementary General Conditions. Such costs

will be deducted from the monies due to the Contractor at the time of final payment, recognizing any

extensions of time granted by the Owner.

1.5.3 The Owner’s project inspector shall be present during all installation of the roof repair and restoration

system. Any work performed without said presence may be rendered unacceptable unless prior

arrangement is made otherwise with the Owner.

1.5.4 The Contractor shall inform the Owner’s project manager two (2) weeks prior to the start of the roofing

installation and three (3) days prior to the restart of roofing work following a period of work suspension,

except for single days of suspension due to weather.

1.5.5 The Contractor shall be required to notify the Owner’s project manager prior to cancellation of any

operations and subsequent restarts of the project. Any cost resulting from the failure to notify shall be

borne by the Contractor.

1.5.6 Work found to be in violation of the specifications, or not in conformance with acceptable roofing

standards, shall be subject to rejection including removal and replacement with new material at the

Contractor's expense.

1.5.7 The Owner's project inspector shall document quantities of those materials bid on a unit price basis listed

in the Form of Proposal as well as other materials.

1.6 Quality Control - Manufacturer - Selected Membrane Manufacturer shall be required to provide a qualified

technical representative to observe field conditions, including suitability of surfaces and material installation at

start of field work, at two week intervals during the work, and at completion of the work. Manufacturer's

representative shall submit written report(s) to the Contractor and Designer listing observations and

recommendations. Roofing Contractor shall be responsible for ensuring site visits by Membrane Manufacturer's

Representative.

1.7 Inspection of the Work:

1.7.1 It is a condition of this contract that the work shall be subject to inspection during normal working hours

by the designer, designated official representatives of the owner, and those persons required by state law

to test special work for official approval. The contractor shall therefore provide safe access to the work at

all times for such inspections.

1.7.2 All instructions to the contractor will be made only by or through the designer or his designated project

representative. Observations made by official representatives of the owner shall be conveyed to the

designer for review and coordination prior to issuance to the contractor.

1.7.3 Should any work be covered up or concealed prior to inspection and approval by the designer, such work

shall be uncovered or exposed for inspection, if so requested by the designer in writing. Inspection of the

work will be made promptly upon notice from the contractor. All cost involved in uncovering, repairing,

replacing, recovering and restoring to design condition, the work that has been covered or concealed will

be paid by the contractor involved.

1.7.4 If any other portion of the work has been covered which the designer has not specifically requested to

observe prior to being covered, the designer may request to see such work and it shall be uncovered by

the contractor. If such work be found in accordance with the contract documents, the cost of uncovering

Page 65: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Quality Control 01 45 00 3

and replacement shall, by appropriate change order, be charged to the owner. If such work be found not

in accordance with the contract documents, the contractor shall pay such costs unless it be found that this

condition was caused by the owner or a separate contractor, in which event the owner or the separate

contractor shall be responsible for the payment of such costs.

1.7.5 The contractor shall notify the designer in writing that the project is complete and ready for inspection.

The designer shall make an inspection to verify that the project is complete and shall prepare a list

(punchlist) of any incomplete work. The contract shall complete all items shown on the punchlist and

notify the designer the project is complete and ready for final inspection in writing.

1.7.6 Selected manufacturers shall be required to provide qualified personnel to observe field conditions,

including suitability of surfaces and material installation at start of field work and completion of field

work. Manufacturer's representative shall submit written report (s) to the Designer listing observations

and recommendations. Roofing contractor shall be responsible for ensuring site visits by manufacturer's

representative.

1.7.7 Work found to be in violation of specifications or not in accordance with established workmanship

practices and standards will be subject to complete removal and proper replacement with new materials at

Contractor's expense.

1.7.8 Failure of Owner or Designer to discover or reject defective work, or work not in accordance with the

Contract, shall not be deemed an acceptance thereof, nor a waiver of Owner's rights to Contractor's

compliance with the Contract or performance of the work, or any part thereof. No partial or final

payment, or partial or entire occupancy, by Owner shall be deemed to be an acceptance of work or of

material which is not strictly in accordance with the Contract, nor shall it be deemed to be a waiver by

Owner of any of Owner's rights pursuant to this Contract or otherwise.

PART 2 - PRODUCTS

2.1 Not Used.

PART 3 - EXECUTION

3.1 Not Used.

END OF SECTION

Page 66: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Tree and Plant Protection 01 53 12 1

SECTION 01 53 12

TREE AND PLANT PROTECTION

Part 1 - GENERAL

1.1 Related Documents - Drawings and general provisions of the contract, including General Conditions,

Supplementary General Conditions and other Division 1 specification sections apply to work of this section.

1.2 Description:

1.2.1 Landscaping protection during construction.

1.2.2 Removal, replanting, and repairing of damaged plants.

1.2.3 Regrading and seeding of disturbed areas.

1.2.4 Removal, reconstruction, repairing and testing of damaged irrigation systems.

Part 2 - PRODUCTS

2.1 Materials:

2.1.1 Topsoil - Shall be clean and reasonably free of debris such as clay, stones, roots, or other similar

substances. It shall not be excessively acidic or alkaline nor contain toxic substances harmful to

plant growth.

2.1.2 Peat - Shall be low in mineral and wood content and consist of partially decomposed vegetable

matter, mildly acidic.

2.1.3 Pine Bark - For soil mixing shall be aged 3/8" or finer, others shall be nuggets.

2.1.4 Mulch - Double shredded hardwood mulch minimum thickness 2" to maximum thickness 3".

2.1.5 Soil Mixture - Shall be approximately 50% topsoil, and 25% each of soil mixing pine bark and peat.

2.1.6 Grass - Shall be approved by the Owner. Sodding shall be sand grown.

2.1.7 Fence Materials - Shall be woven wire fence with metal posts.

Part 3 - EXECUTION

3.1 Contractor shall contract the services of an underground utilities contractor to locate all underground utilities

prior to staging of materials within the staging area.

3.2 Fence:

3.2.1 Fence and landscape protection shall be conducted in accordance with the International Society of

Arboriculture and the Owner.

3.2.2 Fence location for tree protection shall be at the "drip line" or extreme perimeter of the branches.

Page 67: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Tree and Plant Protection 01 53 12 2

3.2.3 All barriers to inspected and maintained daily.

3.3 Seeding - Shall only be acceptable at locations with low public visibility as approved by the Owner.

3.4 Sodding - Shall be normal procedure for new grassed areas.

3.5 Pruning - All pruning of existing plant materials, including roots and limbs, for construction clearances shall

be done by a trained, licensed, insured arborist and according to standards set forth in the National Arborist

Association publication “Standards for the Pruning for Shade Trees”. All pruning shall be coordinated with

and inspected by Guilford County Schools.

3.6 Any landscaping damaged during construction shall be replaced to match existing and shall be completed by

the Owner, the contractor will be billed for the expense incurred by the Owner. If replacement is not

possible, the contractor will be responsible for reimbursing the Owner for the value of the said damages.

3.7 Any irrigation systems or components damaged during construction shall be replaced, repaired or

reconstructed to match the existing by a licensed irrigation contractor in a manner acceptable to the owner.

Once repairs are completed the irrigation system shall be tested to demonstrate to the Owner the system

functions properly and that repairs are completed.

3.8 Guarantee - Replanted, injured or repaired plants shall be guaranteed for one (1) full growing season.

Irrigation repairs shall be guaranteed for 2 full years.

3.9 Mediation of compaction damage to be competed and maintained by the contractor:

3.9.1 At severe compaction areas within the drip lines, root zone locations or travel lanes, provide fabric,

logging mats and mulch.

3.9.2 At moderate compaction zones (material storage) provide fabric and mulch or mulch only.

3.9.3 At no compaction zones (trailer location), no protection is required.

END OF SECTION

Page 68: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Storage and Protection 01 66 00 1

SECTION 01 66 00

STORAGE AND PROTECTION

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 General Protections

1.2.1 Limit size of work sections to safeguard adjacent materials, structures, etc., and to minimize dust and

noise.

1.2.2 Protect existing facilities from damage during work. Do not overload existing paving, curbs, sidewalks,

etc. with vehicle traffic. Do not overload new or existing construction with demolition debris, equipment,

etc.

1.2.3 Take appropriate steps at each construction site to protect the general public from hazards created by

demolition and construction operations.

1.2.4 Separate demolition or construction site form public access by fences, barricades, or other appropriate

security measures. Accident prevention signs and markers shall comply with N. C. OSHA regulations to

warn of dangers (e.g., overhead electrical wires) and restrictions (e.g., restricted access areas, hard hat

areas). Where necessary, provide protected detour routes for vehicles or pedestrian traffic.

1.2.5 Barricades and signs must be substantial enough to deter bypassing, vandalizing, or theft. Keep signs

neat and legible at all times. Handmade signs are not acceptable.

1.2.6 All barricades, temporary walkways, and protection of work and materials shall accommodate access,

provide adequate warning, and protection to all segments of the population including wheelchair users

and those using walking aids and the hearing and visually impaired.

1.2.7 Contractor will note that building will remain occupied during work. He is responsible for taking all

precautions necessary to protect building, contents, and personnel from damage or injury from his

operations, and from water entry into the building during construction. Dirt and dust must be kept to a

minimum.

1.2.8 Prior to starting work Contractor shall obtain approval of the Owner for locations of work operations at

ground level, such as material storage, hoisting, dumping, etc. Work will be restricted to approved

locations.

1.2.9 Walls, windows, roof edges, etc., adjacent to hoists, and staging areas shall be protected using canvas

tarpaulins. Plastic or felt will not be acceptable.

1.2.10 Plywood, minimum ¾" thick, or other suitable materials shall be used to protect roof areas from damage

that may be caused by concentrated equipment loads and foot traffic.

1.2.11 Roof traffic shall be confined to work areas. Contractor shall be responsible for any leaks and resulting

damage during and after project completion.

1.2.12 Self-supporting ramps shall be used where expansion joints, area dividers, etc. are to be crossed.

1.2.13 Contractor shall protect interior operations from adverse weather or construction operations during the

Page 69: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Storage and Protection 01 66 00 2

project. The contractor shall note that the building will remain occupied and in operation while the

project takes place.

1.2.14 At the end of each work day, the contractor shall apply nightly temporary tie-ins to ensure that the

building is weather tight, and that newly installed materials are free from moisture and debris. Newly

installed materials coming in contact with moisture and debris is grounds for rejection of materials, and

shall constitute the replacement of the materials with like materials at no additional cost to the Owner.

1.2.15 The Contractor will note that the building will remain occupied during work. He is responsible for taking

all precautions necessary to protect building, contents, and personnel from damage or injury from his

operations. The Contractor will be held liable for any damages to the building, building contents, its

occupancy, grounds, landscaping or vehicles (owners, employees or visitors) resulting from work under

the Contract. In the event of damage, Contractor will restore property to a condition equivalent to that at

the time the project started.

1.2.16 The Contractor shall keep existing drainage facilities and associated leaders/downspouts clear of debris

and bitumastic materials during construction. The Contractor will be required to use elastomeric plugs to

protect leaders/downspouts during demolition and re-roofing operations.

1.2.17 Exterior Protections

1.2.17.1 Provide construction trailer, if desired, and material staging at location provided by the Owner at

the pre-bid meeting.

1.2.17.2 Maintain a clean construction area in fencing. Maintain a clean material staging area in fencing.

No spills, splatter, or residue shall remain on tarmac, roads or grounds.

1.2.17.3 Safety - Protection of people & property must be demonstrated at all times. Failure to do so will

result in stoppage of work by the Owner or their designee until unsafe conditions are corrected.

1.2.17.4 Locating Utilities - When digging or trenching on or adjacent to owner property, a 48-hour

notice is required to locate existing underground utilities. The Contractor will accurately

document located utilities on record drawings by means of the Construction Surveyor.

1.2.17.5 Planned Shut-downs – Any utility outage needed by the Contractor to perform or complete work

of the project must be scheduled two weeks (14 calendar days) in advance by written notice

through the owner’s project manager.

1.2.17.6 Construction Traffic & Logistics – All Contractor-provided temporary directional and safety

signage pertaining to the control of vehicular and pedestrian traffic in and around the project

shall comply with MUTCD standards as adopted by the State of North Carolina. These plans

shall also show new ADA routes if existing ADA or sidewalk routes are blocked or detours are

required by the contractor.

1.2.17.7 One week ( 7 day ) advanced notice must be provided to Parking Operations when the

Contractor anticipates closing or blocking owner thoroughfares, driveways, roadways or

sidewalks, etc.

1.2.17.8 Protect the public from Hazardous and Universal Waste (H/U). All Hazardous and Universal

Waste issues shall be presented to the Owner.

1.2.17.9 Contractor is responsible for all parking lots, parking decks, parking equipment, roads, drives

and other vehicle or pedestrian traffic areas (directly or indirectly) related to the project and shall

be restored to their original or better condition as observed at the time of project start. The

Page 70: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Storage and Protection 01 66 00 3

contractor and Owner’s Project Manager shall walk the project at start and final completion and

agree to existing damage and repairs required by the contractor.

1.3 Site Safety Plans

1.3.1 The Contractor shall install and maintain temporary fall protection systems for this type of work in

accordance with the following standards:

1.3.1.1 29 CFR 1910 - OSHA

1.3.1.2 29 CRF 1926 - OHSA

1.3.1.3 ANSI/IWCA I-14.1

1.3.1.4 ANSI/ASSE Z359.0-2007

1.3.1.5 ASME A120.01-2008

1.3.2 The Contractor shall submit a site specific safety plan that shall outline safety precautions that shall be in

place to protect workers, buildings, persons, vehicles, structures, and any other items that may be affected

or otherwise endangered during the work. This shall list techniques, materials, safety personnel, and

precautions that shall be used to achieve a safe working environment. Include sketches, plans, and

diagrams, as necessary, for assessment with the safety plan. This safety plan shall be submitted to the

Owner for approval with the bid. Failure to submit a safety plan shall result in disqualification of the bid

and the bid shall be labeled “non-responsive”. At a minimum, this safety plan shall include:

1.3.2.1 General Safety requirements.

1.3.2.2 Protocol for providing a safe working environment for Contractor Employees, in accordance

with Paragraph 1.1.3 above.

i Temporary fall restraint systems and anchorages,

ii Warning lines and barricades,

iii Safety meetings and minutes.

1.3.2.3 Wind speed working conditions, and protections for temporary roofing in high speed events.

1.3.2.4 Protocol for fire safety,

i Equipment checklist for proper operation,

ii Fire extinguisher locations for every open flame, at staging areas, material storage

areas,

iii Wind requirements for open flames,

iv Monitoring any open flame work for subsequent combustion.

1.3.2.5 Protocol for night/pre-dawn work, including foot-candle lighting, safety monitor per number of

workers, barricades encapsulating work areas, 100% tie-in outside of barricaded work area, etc.

1.3.2.6 Protocol for deviations from submitted safety plan on a temporary, as needed basis.

Page 71: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Storage and Protection 01 66 00 4

Note: This safety plan schedule outlines minimum requirements, and this plan

is subject to expansion and approval by the Owner.

1.3.3 Protect existing facilities from fire as a result of construction operations. Contractor shall provide suitable

and adequate fire extinguishers conveniently located on at staging areas, storage areas and at areas or

equipment where an open flame is being used. Competent operators shall be in attendance at all times

and shall be properly trained or instructed in fire protection.

1.3.3.1 At each location where an open flame is used, Contractor shall provide a watchman with a

suitable fire extinguisher.

1.3.3.2 Hot work permits will be required for the use of torches.

1.4 Material Protection

1.4.1 Products shall be transported by methods which avoid damage. Damaged material shall be subject to

rejection by the Designer.

1.4.2 Store materials off of the ground covered with tarps. Factory-applied wrappings are not acceptable.

1.4.3 Wet materials shall be removed from the project site.

1.5 Storage

1.5.1 Contractor shall be responsible for proper storage of equipment, materials and devices furnished by

himself and/or his subcontractors and suppliers.

1.5.2 To the maximum extent possible, the Contractor shall not store combustible or flammable materials

inside the facility.

1.5.3 All storage areas are subject to approval by the Owner or his authorized representative.

1.6 Security Measures:

1.6.1 The contractor shall keep his materials and equipment secure at all times.

1.6.2 The contractor and their subcontractors shall not smoke on state property.

1.6.3 The Owner will provide only those security measures which are deemed prudent for its own operations.

The Contractor shall provide the necessary security means to protect the work, materials, tools and

construction equipment from vandalism, theft, and fire unless more strict measures are noted elsewhere

within the construction documents. The Contractor is responsible for replacement of his or her materials,

machinery, equipment, tools, and supplies which are the subject of theft or mysterious disappearance.

Clearly mark all tools and equipment with the Contractor’s identification. The Contractor shall clearly

mark all tool boxes.

1.6.4 The Contractors shall provide the Owner with a list of day and night phone numbers to use in case of

emergencies during the course of the project.

1.6.5 Hazard Communication Standards - All Contractors shall comply with the OSHA Hazard

Communication Standard. The written Hazard Communications Program and Material Safety Data

Sheets for each hazardous chemical shall be readily available and centrally located on site.

1.6.6 The contractor must secure all tools and materials stored on site within a locked 6 ft. tall fence (as a

Page 72: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Storage and Protection 01 66 00 5

minimum) at the end of each day. This shall also include the portable toilet. Fence posts shall not

penetrate the ground or parking lot. The fence shall be double locked with a contractor lock and one

supplied by the Owner.

1.6.7 All tools stored on site must be secured in locked steel gang boxes at the end of each day.

1.6.8 All vehicles and motorized equipment shall be locked and secured at the end of each day.

PART 2 - PRODUCTS

2.1 Not Used.

PART 3 - EXECUTION

3.1 Not Used.

END OF SECTION

Page 73: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Cleaning 01 74 00 1

SECTION 01 74 00 CLEANING

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 To maintain the buildings and site in a clean condition throughout the duration of the project. The Contractor shall

comply with all requirements for cleanliness described in other sections of the project documents.

PART 2 - PRODUCTS

2.1 The Contractor shall provide all required manpower, material and equipment to maintain the specified standard of

cleanliness.

2.2 Contractor shall use only those materials and equipment which are compatible with the surface being cleaned as

recommended by the manufacturer or approved by the Designer.

PART 3 - EXECUTION

3.1 Progress Cleaning

3.1.1 Stored items shall be kept in an orderly arrangement allowing maximum access and shall not impede

drainage or traffic.

3.1.2 Scrap, debris, waste material and other items shall not be allowed to accumulate and shall be removed

from the roof on a daily basis in accordance with all federal, state and local regulations.

3.1.3 Contractor shall protect new and existing roofing membrane from dirt and debris during the demolition of

the remainder of the roofing. Areas with new and existing roofing membrane shall be kept clean and free

of debris during the duration of the re-roofing.

3.1.4 Streets, parking lots, walks and grounds connecting to the project area shall be protected from deposits of

mud, sand, stone, litter, or debris in any form, and this protection shall be the responsibility of the

Contractors. All mud collected on vehicle wheels must be cleaned off before leaving the construction

area. Should any mud or debris collect on the streets from the construction project, this shall be removed

immediately before becoming a traffic hazard.

3.1.5 Contractor shall provide storage containers for all items awaiting removal from the site. Storage

containers shall be approved by the Designer and Owner. Use of Owners trash receptacles for debris is

not allowed. Outdoor burning of trash is not allowed.

3.1.6 The Contractor shall conduct daily inspections to ensure that the requirements for cleanliness are met.

3.1.7 Dust, dirt and debris created by project construction shall be properly contained or controlled by the

Contractor.

3.1.8 At locations where the Contractor accesses the site or designated changing areas, the Contractor shall

maintain a clean site. The Contractor shall protect the Owners’ building from damage, staining, soiling,

roofing materials, and roofing debris. This shall also include, at a minimum, the daily cleaning of these

areas. "Clean" shall be interpreted as meaning the level of cleanliness generally attainable by skilled

cleaners using commercially available building maintenance equipment and materials.

Page 74: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Cleaning 01 74 00 2

3.1.9 Work may be stopped or delayed by the Owner should the Contractor fail to take appropriate measures to

clean the site on a daily basis. Extensions to the project completion date for such delays will not be

approved.

3.1.10 Contractor shall visually inspect all exterior surfaces and remove all traces of dirt, waste materials,

smudges, splashed materials, and other foreign matter. The Designer may require that light sandblasting

or other cleaning be performed at no cost to the Owner. If such cleaning is required, the Contractor shall

take all necessary precautions to prevent damage to adjacent materials, property and vegetation.

3.1.11 The contractor shall make every effort to protect the vehicles on site from becoming unclean, from

construction debris and from damage. The contractor is responsible to pay for vehicle cleaning and

repairs necessary due to construction related activity.

3.2 Final Cleaning

3.2.1 Except as specifically provided otherwise, "clean" shall be interpreted as meaning the level of cleanliness

generally attainable by skilled cleaners using commercially available building maintenance equipment

and materials.

3.2.2 All tools, equipment, materials, scrap, debris and waste shall be removed from the project site and a final

progress cleaning conducted in accordance with this Section.

3.2.3 Unless otherwise directed by the Designer, the Contractor shall clean all adjacent areas on the site and

completely remove all resultant debris.

3.2.4 The Contractor shall clean out all gutters and associated downspouts of any debris prior to final

acceptance by the Owner. Such work shall be performed at no additional cost to the Owner.

3.2.5 Restore grass or planted areas by filling ruts, raking, seeding, planting, sodding, and fertilizing. Sweep

paved areas.

3.2.6 Contractor shall visibly inspect all exterior surfaces and remove all traces of dirt, waste materials,

smudges, splashed materials and other foreign matter. The Designer may require that light sandblasting

or other cleaning be performed at no cost to the Owner. If such cleaning is required, the Contractor shall

take all necessary precautions to prevent damage to adjacent materials, property and vegetation.

3.2.7 Prior to final inspection, the surface of the membrane shall be cleaned of all debris, dust, and foreign

material. This may require the use of water, detergents, and other cleaning agents approved by the

roofing system manufacturer. Contractor will be responsible for providing the necessary items to perform

this task. Do not use any abrasive pads that can score the polymer. During the work, the Contractor or

subcontractor shall not be allowed to stage materials on newly installed roofing. The Contractor shall

phase work and stage necessary materials at existing roofing areas. Any damage to new membrane

during construction shall result in repairs to the membrane at no additional cost to the Owner, and large

areas shall result in the removal and replacement of new membrane at no additional cost to the Owner.

END OF SECTION

Page 75: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Project Closeout Procedures 01 77 00 1

SECTION 01 77 00

PROJECT CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 General:

1.1.1 Drawings and general provisions of the contract, including General, Supplemental and Special Conditions

and other Division 1 specification sections apply to work of this section.

1.1.2 Description - To provide a specific format for final acceptance and final inspection.

1.2 Related Requirements Specified Elsewhere

1.2.1 Completion: Waiver of Claims, General Conditions

1.2.2 Cleaning: Section 01 74 00

1.2.3 Project Record Documents: Section 01 78 39

1.2.4 Warranties: Section 01 78 36

1.2.5 Closeout Submittals Required for Trades: Respective Section of Specification

1.2.6 Final Payment: General Conditions & Supplementary General Conditions

1.3 Quality Assurance

1.3.1 All documents submitted to the Designer shall be signed by a person authorized to endorse Contracts on

behalf of the Contractor.

1.3.2 All formats for all documents shall be approved by the designer.

PART 2 - PRODUCTS

2.1 Not Used

PART 3 - EXECUTION

3.1 Punchlist Inspection (pre-final inspection):

3.1.1 The Contractor shall submit written certification to the Owner, through the Designer, when the project or

designated portion of the project is complete.

3.1.2 The Designer will make a punchlist inspection within fourteen (14) days after receipt of certification and

issue a punchlist containing:

3.1.2.1 The Date of Designers punchlist inspection.

3.1.2.2 A list of items to be completed or corrected (punchlist).

3.1.2.3 The time to be allowed for the Contractor to complete or correct listed items shall not exceed the

contract time stated in the Supplementary General Conditions.

Page 76: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Project Closeout Procedures 01 77 00 2

3.1.3 The Contractor shall then complete or correct those items so listed and inform the Designer in writing

upon completion.

3.1.4 Should the Owner and Designer determine that the work is not ready for a Punchlist Inspection, the

Designer shall immediately notify the Contractor in writing stating reasons. The Contractor shall then

complete the work and send a second written notice to the Owner certifying that the project, or designated

portion thereof, is complete. The Designer will re-inspect the work after receipt of additional

replacement certification from the Contractor.

3.2 Final Inspection

3.2.1 The Contractor shall submit written certification to the Owner, through the Designer, that

3.2.1.1 The Contract Documents have been reviewed.

3.2.1.2 Work has been completed in accordance with the Contract Documents.

3.2.1.3 The project has been inspected for compliance with the Contract Documents.

3.2.1.4 The Punchlist is complete.

3.2.1.5 The project is ready for final inspection.

3.2.2 The Owner, Designer, and Contractor will make a final inspection within ten (10) days after receipt of

certification.

3.2.3 Should the Owner and Designer determine that the work is finally complete in accordance with the

requirements of the Contract Documents, the Designer will request that the Contractor submit the

appropriate project closeout documentation.

3.2.4 Should the Owner and Designer determine that the work is not finally complete, the Designer will

immediately notify the Contractor in writing stating reasons. The Contractor shall then take immediate

measures to remedy the stated deficiencies and send an additional written notice to the Owner, through

the Designer certifying that the work is complete. The Owner and Designer will re-inspect the work.

3.3 Re-Inspection Costs

3.3.1 Should the Owner be required to perform additional inspections due to noncompliance of work with the

certifications of the Contractor, the Contractor shall compensate the Owner for such additional services.

Such costs shall be deducted from final payment to the Contractor.

3.4 Closeout Submittals

3.4.1 Project Record Documents: As required by Section 01 78 39

3.4.2 Warranties: As required by Section 01 78 36

3.4.3 Evidence of payment and release of liens: Waiver and Release Upon Payment – Final.

3.4.4 Consent of Surety Company to Final Payment

3.4.5 Contractor's Affidavit of Payment of Debts and Claims: Use form from North Carolina State

Construction Office.

Page 77: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Project Closeout Procedures 01 77 00 3

3.4.6 Contractor’s Affidavit of Release of Liens: Use form from North Carolina State Construction Office.

3.4.7 Cancellation notice for Builders Risk Insurance and date of cancellation.

3.4.8 The Contractor shall be responsible for proper execution of all submittals required by this Section prior to

delivery to the Owner through the Designer.

3.4.9 The Contractor shall submit a final statement of accounting to the Owner through the Designer. The

statement shall reflect all adjustments including, but not limited to:

3.4.9.1 Original Contract sum.

3.4.9.2 Change Orders noting such items as:

i Unit Prices

ii Deductions for Uncorrected Work

iii Deductions for Re-Inspection Payments

iv Other Adjustments

3.4.9.3 Total adjusted Contract sum

3.4.9.4 Previous payments

3.4.9.5 Remaining amount due

3.4.10 The Owner will prepare a final Change Order reflecting approved adjustments not previously noted.

3.5 Final Application for Payment

3.5.1 The Contractor shall submit final application for payment in accordance with the specifications.

3.5.2 The Designer will issue a final certificate in accordance with the specifications.

END OF SECTION

Page 78: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Guarantees 01 78 36 1

SECTION 01 78 36

GUARANTEES

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Upon completion of the work and prior to the final payment, the Contractor shall submit the required contractor’s

guarantee and/or manufacturer’s guarantee, as required by this Section.

1.3 Submit all items required by this Section as part of project record documents, Section 01 78 39.

1.4 Guarantees:

1.4.1 Contractor:

1.4.1.1 Comply with the General Conditions of the Contract concerning guarantees and bonds. The

Contractor shall agree that the work covered under this Contract shall remain free from any

water penetration and physical defects caused by defective workmanship or materials for a

period of five (5) years from the date of final acceptance by Owner. Guarantee shall be executed

on Contractor's company letterhead and signed by an authorized officer of the company.

1.4.1.2 Prior to final payment, Contractor shall submit one original and three copies of the roofing

system manufacturer’s twenty year, No Dollar Limit Guarantee, with flashing endorsement, to

the Owner.

1.4.1.3 The Contractor and the Owner’s representative shall conduct an inspection approximately 30

days prior to the end of the Contractor's guarantee to determine the present physical condition of

the roofing system. The Owner's representative shall then submit a written report as to the

findings of this inspection and the roofing Contractor, at his own expense, shall repair any

defects covered under the scope of this contract.

1.4.2 Roof Membrane Manufacturer:

1.4.2.1 General - Guarantees shall not contain conditions limiting the manufacturer’s obligations due to:

i Receipt of payments from the roofing contractor.

ii The roofing system having been installed in accordance with the manufacturer’s

specifications and procedures.

1.4.2.2 Membrane Manufacturer’s Guarantee:

i The Contractor shall include in the base bid the cost of the manufacturer's 20-year no

dollar limit material and workmanship system guarantee.

ii The system shall include all new components above and including the vapor barrier

such as insulation (board or lightweight insulating concrete), adhesive system,

membrane and flashings, low profile expansion joints and flashings, all liquid applied

membrane and flashings and shall include all portions of the fastening components that

extend through existing insulation and below the top of the roof deck. Guarantee shall

not be limited to only those components manufactured or sold by the membrane

manufacturer.

Page 79: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Guarantees 01 78 36 2

iii The Membrane Manufacturer shall agree that the work covered under this contract shall

remain free from any water penetration and material defects caused by defective

workmanship or materials for a period of twenty (20) years from the date of final

acceptance by the Owner. The Contractor's guarantee shall neither replace nor negate

any agreement furnished by the manufacturer.

1.4.3 Metal Flashing Manufacturer - Prior to final payment, the contractor shall furnish one original and three

copies of the metal flashing manufacturer’s 20-year finish guarantee for factory applied finishes.

1.4.4 Skylight Manufacturer: Provide written Guarantee signed by manufacturer, agreeing to repair or replace

work that exhibits defects in materials or workmanship and guaranteeing weather-tight and leak-free

performance. “Defects” is defined as uncontrolled leakage of water and abnormal aging or deterioration.

1.4.4.1 Guarantee Period: 5 years from date of Final Acceptance.

1.4.4.2 Plastic Guarantee: Provide written Guarantee signed by manufacturer agreeing to repair or

replace work that has or develops defects in the plastic. “Defects” is defined as abnormal aging

or deterioration. Guarantee Period for Impact Glazing: 2 years from date of Substantial

Completion.

1.4.4.3 Finish Guarantee: Provide written guarantee signed by manufacturer agreeing to repair or

replace work with finish defects. “Defects” is defined as peeling, chipping, chalking, fading,

abnormal aging or deterioration, and failure to perform as required. Guarantee Period for

Anodized Finish: 1 year from date of Substantial Completion for film integrity.

1.5 Emergency repairs to defects and leaks shall be performed within 24 hours of receiving notice from Owner. As

soon as weather permits, permanent repairs and restoration of affected areas shall be accomplished in a manner in

conformance with the original Contract requirements. This work shall be done without additional cost to the

Owner, except if it is determined that such leaks and defects were caused by abuse, lightning, hurricane, tornado,

hail storm, or other unusual phenomena.

1.6 Starting dates of all guarantees shall be the date of the final inspection and Owner acceptance which the Owner,

Designer, Contractor and Manufacturer agree that all work has been completed in substantial compliance with the

plans and specifications of the project.

1.7 All guarantees shall be governed by and construed in accordance with the laws of the State of North Carolina. No

guarantee shall require dispute resolution to take place in any court other than those courts having jurisdiction over

the site of the project. All guarantees shall be issued bearing a signature of an officer of the company and shall not

require the signature of the Owner nor Designer.

1.8 Final payment will be made to the Contractor only after three (3) copies of the guarantees and guarantees have

been submitted and the membrane manufacturer acknowledges that all bills are paid. All such documents shall

show the project name and location and the Owner's name.

Page 80: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Guarantees 01 78 36 3

(Print Guarantee Body on Contractor’s Company Letterhead)

GUARANTEE

1. Known all men by these presents, that we, Contractor shall insert company name here (Contractor), having

installed insulation, roofing, flashings, and sheet metal work, and having accomplished certain other work on

Johnson St. Elementary School Roof Replacement, High Point, NC under Contract between Guilford County

Schools and (Contractor) warrant to the Guilford County Schools, with respect to said work that for a period of

two years from date of final acceptance of said work by Guilford County Schools, the roofing including insulation,

roofing membrane, flashings, skylights, and sheet metal work, shall be absolutely watertight and free from all

leaks, provided however that the following are excluded from this Guarantee:

a. Defects or failure resulting from abuse by the Owner.

b. Defects in design involving failure of the structure, load-bearing walls, and/or foundations.

c. Damage caused by fire, tornado, hail, hurricane, acts of God, wars, riots, and/or civil commotion.

2. We agree that should any leaks occur in the roofing, we will promptly remedy said leaks in a manner to restore the

roof to a watertight condition by methods compatible to the system and acceptable under industry standards and/or

general practice.

3. We further agree that for a period of two years from date of final acceptance referred to above, we will make

repairs at no expense to the Owner, to any defects which may develop in the work including, but not limited to,

blisters, wrinkles, ridges, splits, warped insulation, and loose flashings, in a manner compatible to the system and

acceptable under industry standards and general practice.

4. We also agree that the Owner has the right, at any time during the two-year Guarantee period, to make emergency

repairs to protect the contents of the building or the building itself from damage due to leaking. The cost of

emergency repairs made during the five years of the Guarantee period shall be borne by the Contractor and action

by the Owner shall not invalidate the Guarantee.

IN WITNESS WHEREOF, we have caused this instrument to be duly executed, this __day of ________, 2021.

__________________________________ by___________________________________

Contractor President

__________________________

Notary Public

END OF SECTION

Page 81: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Project Record Documents 01 78 39 1

SECTION 01 78 39

PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Description

1.2.1 To maintain an accurate record of the project throughout its duration. Items to be noted include, but are

not necessarily limited to:

1.2.1.1 Contract Documents (Plans, Specifications, Bid Documents, Addenda, and all other documents

related to the Construction Contract).

1.2.1.2 As Built Red Lined Drawings

1.2.1.3 Minutes of prebid, preconstruction, and construction meetings

1.2.1.4 Change Orders

1.2.1.5 Field Orders and Instructions.

1.2.1.6 Construction Schedule.

1.2.1.7 Shop Drawings and Product Samples

1.2.1.8 Progress Reports

1.3 Quality Assurance - The Contractor shall delegate responsibility for maintenance of the record documents to one

person on the Contractor's staff as approved by the Designer. All entries shall be made within 24 hours after

receipt of information.

1.4 Submittals - The Contractor shall submit the final record documents to the Designer for approval prior to

submitting a request for final payment. Submit two copies of "as-built" documents to Designer with letter of

transmittal indicating date, project title, Contractor's name and address, list of documents, and signature of

Contractor.

1.5 Product Handling - the Contractor shall take all necessary precautions to protect the record documents from

deterioration loss and damage until completion of the work and transfer of the recorded data to the final record

documents.

PART 2 – PRODUCTS - Not Used.

PART 3 - EXECUTION

3.1 Maintenance of Record Documents – The Contractor shall maintain the record documents at the project site and

make all documents available to the Designer during all working hours.

3.2 Review and Approval – The Contractor shall submit the completed total set of record documents to the Designer

as described.

END OF SECTION

Page 82: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Selective Demolition and Preparations 02 41 13 1

SECTION 02 41 13

SELECTIVE DEMOLITION AND PREPARATIONS

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Work Included

1.2.1 Selective demolition and preparations for the roof replacement project, as specified herein.

1.2.2 Wood Nailer Replacement (Wood Blocking) - (Unit Price No. 1).

1.2.3 Patching Deteriorated or Damaged Gypsum Deck (Unit Price No. 2).

1.2.4 Patching Deteriorated or Damaged Concrete Deck (Unit Price No. 3).

1.3 Related Work Specified Elsewhere

1.3.1 Temporary Facilities and Controls - Section 01 50 00

1.3.2 Storage and Protection - Section 01 66 00

1.3.3 Miscellaneous Rough Carpentry - Section 06 10 53

1.3.4 Roof Board Insulation – Section 07 22 16

1.3.5 Polyvinyl Chloride Roofing – Section 07 54 19

PART 2 - PRODUCTS

2.1 Gypsum Deck Patch: Basis of Design – USG Securock Brand Gypsum Concrete Patch for use of repairs of

gypsum roof decks with a set time between 30-60 minutes.

2.2 Concrete Deck Patch: Shall be a fast setting cementitious based self-curing trowlable patch material for

smoothing and repairing concrete floors. It shall reach its initial set per ASTM C191 within 15 minutes and its

final set per ASTM C191 within 60 minutes. The material shall reach 4,200 psi minimum compressive strength per

ASTM C109 within 28 days.

2.3 Rust inhibiting coating by:

2.3.1 The Skybryte Company, 3125 Perkins Avenue, Cleveland, Ohio 44114, 216-771-1590 or 703-527-3887,

(basis of design).

2.3.2 Rusty Metal Primer by Rust-oleum.

2.3.3 Armatec 110 by Sika.

2.4 Wood Nailers and Fasteners: Refer to Section 06 10 53.

PART 3 - EXECUTION

Page 83: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Selective Demolition and Preparations 02 41 13 2

3.1 Demolition

3.1.1 Refer to Summary of Work – Section 01 11 00.

3.1.2 Excessive demolition, as determined by the Owner's representative, shall be replaced with equal materials

at the Contractor's expense in accordance with the General Conditions of the Contract. No demolition

shall be performed if the chance of precipitation is 40% or more as reported by the nearest office of the

National Weather Service.

3.1.3 Remove and replace or repair of any deteriorated or damaged existing concrete and gypsum.

3.1.4 Remove all existing flashings and metal flashings, and discard. Remove all membrane flashing at curbs

and penetrations down to the existing substrate.

3.1.5 The Designer and Contractor shall document the actual quantities removed for materials bid on a unit

price basis.

3.1.6 All existing roof mounted equipment shall be lifted or removed so that existing flashings can be totally

removed.

3.1.7 Demolition shall be performed by personnel familiar with the replacement of materials being used.

3.1.8 Demolition adjacent to areas to remain shall be performed in a neat manner with straight lines to facilitate

tie-ins of replacement materials. Contractor shall review tie-in methods with the Designer for approval.

Designer has final approval of such methods.

3.1.9 Excessive demolition, as determined by the Owner's representative, shall be replaced with equal materials

at the Contractor's expense in accordance with the General Conditions of the Contract.

3.1.10 No demolition shall be performed if the chance of precipitation is 40% or more as reported by the nearest

office of the National Weather Service.

3.1.11 During roof drain replacement, contractor shall protect the interior of the school and will be responsible

to replace and/or repair anything that is damaged or broken during as a result of the work.

3.2 Preparations

3.2.1 Prior to the installation of any new roofing, flashings, metal flashings, any other miscellaneous items, the

Contractor shall clean surfaces of all dust, dirt, and other foreign materials.

3.2.2 Inspect the deck carefully. If, in Contractor's opinion, there are concrete deck areas that require repair

and/or replacement, notify the Designer. Do not proceed with any repairs or replacement until directed

by the Designer.

3.2.3 Prior to the installation of any new roofing materials, extend all existing soil pipe vents through the roof

to a minimum height of 8 inches above the finished roof surface. Modifications shall be performed as

follows: Furnish a piece of PVC piping that will fit snugly into the existing soil pipe vent and shall extend

into the pipe a minimum of 12 inches. Provide a second PVC pipe that fits snugly around the smaller

PVC pipe and shall provide a minimum 8" height above the finished roof surface. The smaller pipe

height shall match the outer pipe. Cement the two PVC pipes together with an approved pipe

solvent/glue. Insert the extension into the existing soil pipe vent.

END OF SECTION

Page 84: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Miscellaneous Rough Carpentry 06 10 53 1

SECTION 06 10 53

MISCELLANEOUS ROUGH CARPENTRY

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Work Included - Installation of blocking and/or curbs, as specified herein.

1.3 Related Work

1.3.1 Roof Board Insulation - Section 07 22 16

1.3.2 Polyvinyl Chloride Roofing – Section 07 54 19

1.3.3 Flashing and Sheet Metal - Section 07 60 00

1.4 Submittals - In accordance with Section 01 33 00 of this Specification.

1.5 Environmental Conditions - Material installation shall proceed only when weather conditions are in compliance

with the applicable manufacturer's recommendations for installation and no precipitation is imminent. Materials

installed during adverse weather conditions shall be subject to removal and replacement with new materials at no

additional cost to Owner.

1.6 Guarantee - In accordance with Section 01 78 39 of this Specification.

PART 2 - PRODUCTS

2.1 Non-structural wood blocking: Nominal 1" x 6" and 2" x 6", unless otherwise noted, pine, shop pressure-treated

for above ground contact. Do not use oil-based preservatives.

2.2 CD-X Exterior Grade Plywood. Nominal 1" thick, five-ply minimum.

2.3 Wood Fiber Tapered Edge Strips: ASTM C208, Type II, Grade 1 (Built-Up Roofs), C209. Approved for use by

approved roofing system manufacturer.

2.4 Screws: #12 stainless steel self-tapping wood screws that shall be able to resist any galvanic action that may be

able to develop between the nail and the pressure treatment. The use of a lesser quality screw will not be

approved. Screws shall be of sufficient length to penetrate a minimum of 1-1/2 inches into the substrate.

2.5 Nails: For securing new lumber to new lumber or new plywood/OSB to new lumber, stainless steel ring shank

nails to penetrate a minimum of 1-1/2 inches into the substrate but not smaller than 8d nails. Use 16d nails where

material being secured is 1½ to 2 inches thick.

2.6 Anchor Bolts: Stainless Steel ½” diameter, length to embed in concrete a minimum of 8”, with appropriately-sized

nuts and washers.

Page 85: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Miscellaneous Rough Carpentry 06 10 53 2

2.7 Masonry Fastener (stainless steel):

2.7.1 Tapcon ¼” x minimum 1-1/4” in the substrate, as manufactured by Buildex.

2.7.2 Tapper ¼” x minimum 1-1/4” in the substrate, as manufactured by Powers Fasteners.

2.7.3 Zamac Hammer-Screw, minimum 1-1/4 inch into substrate, as manufactured by Powers Fasteners.

2.7.4 Approved equal prior to bid.

PART 3 - EXECUTION

3.1 Wood Blocking Installation

3.1.1 Furnish and install new wood blocking at all roof mounted equipment as required to provide a minimum

flashing height of 8 inches above roof level. Blocking shall be installed under integral equipment curbs

as required to maintain full cant face above roof level and secured to the deck with appropriate fasteners

through the deck at spacings not to exceed 12 inches on-center, staggered pattern.

3.1.2 Furnish and install wood blocking where indicated in the drawings. Secure the first layer to the substrate

with appropriate fasteners at spacings not to exceed 12 inches on center, staggered pattern. Secure

succeeding layers to the preceding with appropriate nails at spacings not to exceed 12 inches on center,

staggered pattern.

3.1.3 Furnish and install new pressure-treated tapered wood blocking at all parapets, as required, to insure

positive shedding of water off of the coping. Finished slope of wood blocking to have a minimum slope

of 1 inch across the width of the parapet. Secure wood to the existing with appropriate nails at spacings

not to exceed 12 inches on center, staggered pattern. Contractor shall submit a shop drawing of details to

the Designer for approval prior to the start of work.

3.1.4 Furnish and install new pressure-treated tapered wood blocking at roof-to-roof expansion joint curb, as

required, to maintain a minimum height of 8 inches above the roof surface. Refer to the Drawings.

Wood blocking shall be secured through the top with screw type fasteners at spacings not to exceed 12

inches on-center. Screws shall penetrate the top of the existing curb a minimum of 1-1/2 inches. The

entire length of the screw shall not exceed 4 inches. It may be necessary to drill into the new blocking in

order to maintain adequate penetration into the existing curb. Secure plywood to wood blocking with

screw type fasteners at spacings not to exceed 12 inches on-center, staggered pattern. Insure that the top

of the wood is tapered so that water does not pond on top of the cover, when installed.

3.1.5 Furnish and install new pressure-treated wood blocking at roof-to-wall expansion joint curbs, as required,

to maintain a minimum height of 8 inches above the roof surface. Refer to the Drawings. Wood blocking

shall be secured through the top with screw type fasteners at spacings not to exceed 12 inches on-center.

Screws shall penetrate the top of the existing curb a minimum of 1-1/2 inches. The entire length of the

screw shall not exceed 4 inches. It may be necessary to drill into the new blocking in order to maintain

adequate penetration into the existing curb.

3.1.6 At those locations where the fan unit is either too large or too small relative to the existing curb, remove

the existing curb and discard. Furnish and install a new wood or pre-fabricated curb that matches the size

of the fan cover that sits on top of the curb. If a pre-fabricated curb is used, secure the flange to the deck

using appropriate fasteners at spacings not to exceed 12 inches on center. If a wood curb is fabricated,

furnish and install the first layer of nominal 2" x 6" wood blocking and secure to the deck with

appropriate fasteners at spacings not to exceed 12 inches on center. Add additional layers of wood

blocking until the top of the blocking matches the thickness of the roof insulation. Secure each

succeeding layer to the preceding with appropriate fasteners at spacings not to exceed 12 inches on

center, staggered pattern. The vertical leg of the curb shall have a minimum height of 8 inches above

the finished roof surface. Furnish and install a wood cant with a nominal 4 inch face, securing the top

and bottom to the curb and blocking with appropriate nails at spacings not to exceed 6 inches on center.

Page 86: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Miscellaneous Rough Carpentry 06 10 53 3

3.1.6.1 Contractor shall submit a shop drawing to the Designer of the proposed curb for review and

approval prior to the start of this work.

3.1.6.2 The size of the curb shall also take into account the additional space required to install base

flashings prior to the installation of the curb.

3.1.6.3 Extending and/or modifying ductwork as part of this work shall be included in the Base Bid.

3.1.7 At all existing pitch pan locations, furnish and install new curbs in accordance with Paragraph 3.1.6

above.

END OF SECTION

Page 87: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Roof Board Insulation 07 22 16 1

SECTION 07 22 16

ROOF BOARD INSULATION

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Work Included - Installation of new base sheet and roof insulation, as specified herein.

1.3 Related Work

1.3.1 Miscellaneous Rough Carpentry - Section 06 10 53

1.3.2 Polyvinyl Chloride Roofing – Section 07 54 19

1.3.3 Flashing and Sheet Metal - Section 07 60 00

1.4 Submittals

1.4.1 Refer to Section 01 33 00 of this Specification.

1.4.2 Provide a roof plan showing the insulation, tapered, and adhesive layout for each roof area. Also, note

the progression of the reroofing and the locations for discharge of tear off materials to show that the new

membrane and adjacent existing roofs will not be subjected to construction traffic.

1.4.3 Provide shop drawings showing the method of securement.

i Fully Adhered System: Provide a copy of the membrane manufacturer’s FM Global

approved testing showing compliance with the specified uplift requirements.

ii Tests shall be performed by the membrane manufacturer or their representative prior to

construction to verify adequate pullout resistance and to confirm the adequacy of the

adhesive that has been proposed.

1.5 Environmental Conditions - Materials installation shall proceed only when weather conditions are in compliance

with the applicable manufacturer's recommendations for installation and no precipitation is imminent. Materials

installed during adverse weather conditions shall be subject to removal and replacement with new materials at no

additional cost to Owner.

1.6 Guarantee - Refer to Section 01 78 36 of this Specification.

PART 2 - PRODUCTS

2.1 Base Sheet: 48 mil (min) thick SBS modified fiberglass base sheet as approved by the membrane manufacturer for

attachment to meet wind uplift and roof assembly warranty.

2.2 Polyisocyanurate Roof Insulation: Flat and tapered, as specified, ASTM C1289, Type II, Class I. Board size of

tapered insulation shall not exceed 4’ x 4’. The Long-Term Thermal Resistance shall be a minimum of 5.6 per

inch. Insulation compressive strength shall be minimum 20 psi. Insulation density shall be 2 pcf minimum.

Thermal insulating factor as specified; however, thicknesses of each layer of insulation shall not exceed 2 inches.

Flat insulation shall have a minimum total R-Value of 22.8.

2.3 Wood Fiber Tapered Edge Strips: ASTM C208, Type II, Grade 1, C209. Approved for use by approved roofing

Page 88: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Roof Board Insulation 07 22 16 2

system manufacturer.

2.4 Cover Board: Gypsum Board, Nominal 1/2” thick, ASTM C 1177, 0 Flame Spread and 0 Smoke Developed when

tested in accordance with ASTM E 84, nominal 900 psi minimum compressive strength, Class A, non-

combustible, 4' x 8' board size.

2.5 Insulation Fastening - Low-Rise Adhesive: double or single-component low-rise polyurethane adhesive as

approved by the roofing system manufacturer and meeting the requirements of FM 1-90 or Florida Building Code

approval R-53. Contractor shall verify through pull tests that the selected adhesive and bead spacing meet the

membrane manufacturer’s requirements.

2.6 Fire Rated Sealant: Sealant to be as recommended by the following manufacturer’s to provide a one hour rated

closure and shall meet ASTM E119 or UL 263. Use proper sealant joint design as required by the sealant joint

manufacturer. The following manufacturers are approved for use on this project:

2.6.1 Hilti Corporation.

2.6.2 Pecora Corporation.

2.6.3 Tremco.

2.6.4 DAP.

PART 3 - EXECUTION

3.1 Coordination and Inspection

3.1.1 The substrate shall be clean, smooth, dry, and free of debris and all foreign matter prior to receiving

insulation and cover board. Application of new materials shall constitute approval of the substrate by the

Contractor.

3.1.2 All penetrations shall be sealed to meet a UL rating of 1 hr. See the UL Fire Ratings included after this

section (each of which is copyrighted 2015 by UL LLC). For any conditions which are different than

these consult the designer for the appropriate detail.

3.2 Base Sheet at Gypsum Deck:

3.2.1 Prepare and install per manufacturers requirements.

3.2.2 Make gypsum deck dry and clean and prepared per assembly manufacturers requirements.

3.2.3 Unroll base sheet and allow it to relax.

3.2.4 Mechanically fasten to the deck with approved fasteners and plates at a rate according to the

manufacturers requirements for fastening rates and patterns.

3.2.5 Overlap side laps 3” and end laps 6”, minimum.

3.3 Installation – Concrete Deck:

3.3.1 Make base sheet or concrete deck dry and clean and prepared per adhesive manufacturer.

3.3.2 Polyisocyanurate - Apply one layer of 1.5 inch thick polyisocyanurate roof insulation to the existing

concrete deck using low-rise foam adhesive.

3.3.2.1 Apply insulation with end joints staggered approximately one-half the length of the units.

Page 89: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Roof Board Insulation 07 22 16 3

3.3.2.2 Fit insulation units snugly to each other and to all vertical surfaces.

3.3.2.3 Secure each board to the substrate:

i Using low-rise adhesive beads as required by the Membrane Manufacturer to meet the

requirements of Factory Mutual 1-90 or Florida Building Code approval R-53

(105mdp).

3.3.3 Polyisocyanurate - Apply one layer of 1.5 inch thick polyisocyanurate insulation over the insulation

described in the preceding paragraph.

3.3.3.1 Install insulation in accordance with paragraphs 3.2.2.1 through 3.2.2.3.

3.3.3.2 Offset insulation joints from the preceding layer a minimum of six (6) inches.

3.3.4 Install polyisocyanurate tapered insulation system with polyisocyanurate fill units over the flat

polyisocyanurate roof insulation, and increase the thickness toward the high points. Refer to the

Drawings. Contractor shall submit a shop drawing to the Designer for review and approval showing the

tapered insulation layout.

3.3.4.1 Apply insulation with end joints staggered approximately one-half the length of the units.

3.3.4.2 Stagger insulation joints from the preceding layer a minimum of six (6) inches.

3.3.4.3 Fit insulation units snugly to each other and to all vertical surfaces.

3.3.4.4 Loose lay the insulation over the substrate.

3.3.4.5 Utilize tapered wood fiber edge strips that transition from 0” to 1/2” as the first layer of tapered

insulation to provide a smooth transition. Set wood fiber on top of the polyisocyanurate

insulation in one continuous band of low-rise foam adhesive.

3.3.5 Sumps - At drains, apply ½” per foot tapered polyisocyanurate insulation and polyisocyanurate fill units

that extend 2 feet from the center of the drain bowl. Fill units shall not exceed 1 inch in thickness. The

thin edge of the tapered insulation shall be located adjacent to the drain bowl. Secure each board to the

substrate using low-rise adhesive beads at spacings not to exceed 4 inches on center in accordance with

manufacturer’s written instructions. The insulation thickness adjacent to the drain shall be nominal 1/2

inch. Increase the thickness of the tapered insulation until it matches the thickness of the base layer of

polyisocyanurate insulation. Ensure insulation contact with adhesive by weighting units. Remove and

replace damaged units with new insulation or repair to provide a smooth surface and uniform insulation

thickness. Remove any foam at joints prior to installing cover board. Utilize tapered wood fiber edge

strips that transition from 0” to 1/2” as the first layer of tapered insulation to provide a smooth transition.

Set wood fiber in two continuous bands of low-rise foam adhesive. Refer to the Drawings.

3.3.6 Cricket/Valley Polyisocyanurate - Install tapered insulation to move water from walls, form

valleys/crickets, as shown on roof plans, and upslope from any roof mounted unit larger than 24 inches on

the upslope side, on top of the flat insulation using factory-tapered polyisocyanurate insulation units and

polyisocyanurate insulation fill units. Refer to the Drawings.

3.3.6.1 Start cricket construction by striking chalk lines for outer edges of tapered units. Install the first

row along the chalk lines, mitering and fitting at the points where lines break.

3.3.6.2 Complete the cricket assembly using tapered polyisocyanurate and polyisocyanurate fill units.

Secure the tapered insulation in accordance with paragraph 3.3.1.3.

3.3.6.3 Crickets shall provide a minimum finished slope of 1/4 inch per foot, unless otherwise noted.

3.3.6.4 Remove and replace damaged units with new insulation or repair to provide a smooth surface

and uniform insulation thickness.

3.3.6.5 Utilize tapered wood fiber edge strips that transition from 0” to 1/2” as the first layer of tapered

insulation to provide a smooth transition. Set wood fiber on top of the polyisocyanurate

insulation in one continuous band of low-rise foam adhesive.

Page 90: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Roof Board Insulation 07 22 16 4

3.3.7 Cover Board - Furnish and install one layer of nominal 1/2 inch thick cover board over all

polyisocyanurate insulation and secure to the polyisocyanurate insulation using low-rise foam adhesive.

3.3.7.1 Remove any foam at joints prior to installing cover board.

3.3.7.2 Apply insulation with end joints staggered approximately one-half the length of the units.

3.3.7.3 Stagger insulation joints from the preceding layer a minimum of six (6) inches.

3.3.7.4 Fit insulation units snugly to each other and to all vertical surfaces.

3.3.7.5 Secure the insulation in accordance with paragraph 3.3.1.3. Contractor shall submit insulation

attachment patterns to the Designer for approval prior to the start of insulation installation

activities.

3.3.7.6 Remove and replace damaged units with new insulation or repair to provide a smooth surface

and uniform insulation thickness.

END OF SECTION

Page 91: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 1

SECTION 07 52 16 SBS MODIFIED BITUMINOUS ROOFING (ALTERNATES 3 & 4)

PART 1 – GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract,

Supplementary General Conditions, and other Division 1 specification sections apply to work of this

section.

1.2 General: Provide wind tested and warranted roof system.

1.3 Work Included - Installation of SBS modified bitumen membrane, as specified herein.

1.4 Related Work

1.4.1 Selective Demolitions and Preparations – Section 02 41 13.

1.4.2 Roof Board Insulation - Section 07 22 16

1.4.3 Flashing and Sheet Metal – Section 07 60 00

1.5 Submittals

1.5.1 Submittals shall be in accordance with Section 01 33 00 of this Specifications.

1.5.2 Provide a roof plan showing the membrane for each roof. Also, note the progression of the

reroofing and the locations for discharge of tear off materials to show that the new membrane and

adjacent existing roofs will not be subjected to construction traffic.

1.5.3 Provide a copy of testing showing compliance with the requirements of FM 4474, UL 580 or UL

1897

1.5.4 Shop Drawings: Provide job-specific shop drawings for all terminations and flashings.

1.5.5 Technical Data Sheets: Provide for Roofing membrane, Liquid Flashing, Vapor Barrier /

Temporary Roof; Roofing adhesives and all related thereto accessory components.

1.5.6 Safety Data sheets: Technical Data Sheets: Provide for Roofing membrane, Liquid Flashing,

Vapor Barrier / Temporary Roof; Roofing adhesives and all related thereto accessory components.

1.6 Quality Assurance: Installation of modified bitumen roofing shall comply with the provisions of Section

1507.11.2 of the North Carolina State Building Code.

1.7 Fire Safety: Comply with NRCA/CERTA Roofing Torch Safety Program and 2018 NC Fire Prevention

Code.

1.7.1 Contractor shall coordinate with Owner to schedule Hot Work during a time in which the owner

will shut down fans to prevent odors from entering the buildings.

1.7.2 Charcoal filters shall be utilized at HVAC air intakes to prevent odors caused by Hot Work from

entering the building.

1.7.3 All Hot Work shall conform to the following specifications. All workers shall be trained in the

proper use of torching equipment and fire extinguishers.

Page 92: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 2

1.7.4 Hot Work Permits may be required by the Owner for the use of torches prior to the beginning of

any work. Personnel designated by the Owner will oversee and issue permits and monitor rooftop

fire prevention measures.

1.7.5 A minimum of three (3) fully charged 20 lb. fire extinguishers shall be on the roofs at all times.

1.7.6 All combustible materials (primers, solvents, etc.) must be removed from hot work areas prior to

any torching operation. Cover all wood or other flammable materials with a protective sheet of

nailed base ply prior to any torching of roof membrane.

1.7.7 Torches in operation may not be left unattended at any time.

1.7.8 Contractor shall provide a handheld infrared thermometer at all times to check for “hot spots”

during application and will check all areas after the required fire watches.

1.7.9 Contractor to provide a minimum one-hour fire watch on all days that a torch is utilized. At least

one worker will remain on the roof during lunch breaks and after completion of work to monitor

fire safety.

1.7.10 At existing walls or curbs, gypsum boards can be utilized to provide temporary protection and

avoid flame contact with the underlying substrate. “Heat and flop” methods for the flashing

membrane installation are recommended.

1.7.11 In no circumstances shall flames contact wood or other combustible components in the structure.

The installation of a nailed base sheet or use of self-adhering underlayment is required.

1.7.12 Propane tanks shall be secured in an upright position to pneumatic-tired dollies at all times while

on the roof. At the end of each working day, the tanks shall be lowered to the ground and secured.

1.8 Environmental Conditions - Material installation shall proceed only when weather conditions are in

compliance with the applicable manufacturer's recommendations for installation and no precipitation is

imminent. Materials installed during adverse weather conditions shall be subject to removal and

replacement with new materials at no additional cost to Owner.

1.9 Guarnatee - In accordance with Section 01 78 36 of this Specification.

PART 2 – PRODUCTS

1.1 Approved SBS Modified Bituminous Membrane Manufacturers are manufacturers by which the Contractor

may solely furnish materials to perform the work. Materials furnished by the roofing system Manufacturer

are subject to the standards listed below. Any deviations from standards listed below shall only be

considered if the approved system manufacturer does not produce a material to that stated standard, and

must be submitted in writing by the approved roofing system manufacturer. Any substitutions shall not

alter the Warranty periods as described in this specification.

2.1 Membrane manufacturer shall be one of the following:

2.1.1 Soprema, 310 Quadral Drive, Wadsworth, OH 44281, (800)-356-3521:

2.1.2 Siplast, Suite 1600, Xerox Centre, 222 Las Collinas Blvd., Irving, TX 75039, (800)-922-8800:

2.1.3 Derbigum Americas, Inc., 4800 Blue Parkway, Kansas City, MO 64130, (800)-727-9872:

2.2 Membrane requirements:

Page 93: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 3

2.2.1 Provide SBS modified bitumen roof membrane compliant to ASTM D6163 or ASTM D6164,

Type 1.

Ply Sheet: Grade S, Thickness minimum 87mil

Cap Sheet: Grade G, Thickness minimum 160mil

Flashing membrane (Base Flashing): As recommended by the roofing manufacturer.

2.3 Flashing Cement – Asbestos-free SBS polymer modified trowel grade asphaltic cement as provided by the

Membrane Manufacturer.

2.4 Granules – shall be provided by the membrane manufacturer.

2.5 Adhesives: Provide Manufacturer`s Low-Odor or No-Odor standard adhesives.

2.6 Primer – Shall be asphaltic primer conforming to requirements of ASTM D-41 as provided by the

membrane manufacturer.

2.7 PMMA/PMA Liquid Flashings: Two-component, with catalyst, cold fluid-applied reinforced low-odor

polymethyl-methacrylate (PMMA) or polymethacrylate (PMA) flashing/vertical grade waterproofing

membrane. Membrane installation shall consist of PMMA/PMA resin; polyester fleece reinforcement;

PMMA/PMA resin application for a finished dry film membrane thickness of .105-inch nominal per ply;

conforming to ASTM C 836. Provide products manufactured and supplied or approved for use to be

included in the roofing system warranty. Provide primer as required by Liquid Flashing manufacturer and

compatible with the roofing system.

2.8 Walkway Pads: As manufactured by approved roofing system manufacturer. Nominal 30" wide x 50' long.

Black color (modified bitumen roofing). Approved for use by approved roofing system manufacturer.

2.9 Attachment:

2.9.1 Membrane adhesive: As recommended by the roofing manufacturer.

2.9.2 Roofing Nails: 304 or 316 SS masonry fasteners.

2.9.3 Termination Bar: ¼” wide, lip bar. Materials: Stainless Steel

PART 3 - EXECUTION

3.1 All roofing and waterproofing components shall be installed in accordance with: respective manufacturer`s

printed instructions; the contract documents and applicable codes.

3.2 Both Torch application and Cold Adhesive application is acceptable for the roof membrane. For the Vapor

barrier/Temporary roof, coordinate the application technique with Manufacturer`s recommendations and

substrate conditions.

3.3 Inspection

3.3.1 The substrate shall be clean, smooth, dry, free of debris and all foreign matter prior to installation

of the roof membrane. Application of new materials shall constitute approval of the substrate by

the Roofing Contractor.

3.3.2 The Contractor shall disconnect, extend, and/or reconnect all pipes, conduits, wires, frames, curbs,

Page 94: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 4

etc. as necessary to provide 8” flashing height from the finished roof surface at all flashings,

unless otherwise noted. The Contractor shall coordinate all disconnections, service interruptions,

and reconnections with the Owner prior to all disconnections.

3.3.3 Insulation joints with gaps greater than ¼" shall be filled with roof insulation in order to provide a

smooth surface.

3.3.4 The Contractor shall maintain a fire watch with an operational fire extinguisher on the roof for a

minimum of one hour after the completion of all torch operations, unless the roofing system

manufacturer has a more stringent requirement. At the end of one hour, the fire watch shall

inspect all areas where torch work was performed to insure ignition has not occurred.

3.3.5 The contractor shall not apply torch flame directly to plywood sheathing or wood blocking. At

locations where membrane is to be turned up wood blocking/sheathing, the contractor shall place

membrane in appropriate location and then fold the membrane back onto itself. The underside

shall be heated, and the membrane then “flopped” into place.

3.4 Inspection:

3.4.1 Verify insulation is smooth, clean, rigid, and free from debris, projections, holes, etc. which may

adversely affect the membrane application.

3.4.2 Plug drains during roofing activities. Remove plugs at end of each work day.

3.4.3 Verify the suitability of the insulation system prior to installing the membrane system.

3.5 Manufacturer Inspections – Contractor shall schedule the Membrane Manufacturer’s Technical

Representative to be perform the following inspections:

3.5.1 Be present during the first day of Vapor Barrier installation. Manufacturer`s technical

representative shall approve the substrate prior to installation of the Vapor Barrier. Plan and

organize the work so that the roofing manufacturer inspects the deck in an area with wet roof

assembly, as indicated on the drawings. In addition to submitting written report, notify the

designer about the result of the inspection via a phone call immediately after its completion.

3.5.2 Inspect the roofing installation during the first 100 SQ

3.5.3 Inspect installed base ply on first day of cap ply installation.

3.5.4 Inspect at two week intervals during the membrane and flashing installation.

3.5.5 Inspect at substantial completion and generate punch list of items to be completed or repaired.

3.5.6 Inspect at final completion and ensure that all punch list items have been satisfactory addressed.

3.6 Vapor barrier installation

Verify the moisture content in the substrate and the suitability for torch application. Conform strictly with

Manufacturer`s printed instructions. Remove all loose asphaltic residue and obtain Roofing manufacturer’s

approval prior to proceeding with installation.

3.7 Base Membrane Installation (Torch)

3.7.1 Conform to the printed manufacturer`s installation instructions.

Page 95: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 5

3.7.2 Check insulation carefully for damage and application defects and make appropriate repairs and

corrections prior to application of roof surfacing.

3.7.3 Roll out membrane and allow to “relax” in accordance with roofing system manufacturer’s written

instructions.

3.7.4 Beginning at the low point of the roof area, one ply of base membrane shall be applied shingle

fashion, uniformly adhered to the insulation and to each other without voids.

3.7.5 Heat the underside of the membrane to a molten state and unroll the membrane onto the cover

board.

3.7.6 Side laps and end laps shall be a minimum of 2 inches and 6 inches, respectively, unless the

manufacturer has more stringent requirements.

3.7.7 Utilize a steel roller to press the side and end laps of the membrane to ensure proper adhesion and

bleed-out.

3.7.8 Whenever possible, the entire roll shall be applied in a continuous manner. If rolls are allowed to

set while partially rolled out, the roll shall be rolled back sufficiently to expose the area where the

roll had stopped so that the underside the membrane can be heated at this area.

3.7.9 All roofing membrane shall be cut off neatly along top edge of all cants and at the exterior edge of

gutter wood blocking.

3.7.10 Furnish and install granule-surfaced modified bitumen cap sheet in accordance with Paragraph 3.3

of this Section.

3.8 Cap Sheet Application (Torch)

3.8.1 Conform to the manufacturer`s printed installation instructions.

3.8.2 Check roof surface carefully for damage and application defects and make appropriate repairs and

corrections prior to application of roof surfacing.

3.8.3 Install roof surfacing after base membrane has been applied, including stripping plies for

flashings. However, roof surfacing shall be applied prior to base flashings surfacing membrane.

3.8.4 Roll out cap sheet and allow to “relax” in accordance with roofing system manufacturer’s written

instructions.

3.8.5 Beginning at the saddle and cricket valleys created with tapered insulation at drains, torch apply

one ply of granule surfaced SBS modified bitumen cap sheet without voids. Install cap sheet at

valley so that water will run across the laps.

3.8.6 After the valleys, beginning at the lowest point of the roof, torch apply one ply of granule surfaced

SBS modified bitumen cap sheet without voids. Apply the membrane in shingle fashion.

3.8.7 Heat the underside of the membrane to a molten state and unroll the membrane onto the smooth

membrane.

3.8.8 Lap sides and ends in accordance with the roofing system manufacturer written requirements.

However, side laps shall be lapped a minimum of two (2) inches and end laps a minimum of six

(6) inches.

Page 96: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 6

3.8.9 At all end laps, heat and embed the granules on the underlying sheet for a distance to match the

end lap.

3.8.10 Utilize a steel roller to press the side and end laps of the membrane to ensure proper adhesion and

bleed-out.

3.8.11 Embed white roofing granules, which match the cap sheet surface, in all asphalt overruns.

Finished surfaces must be reasonably uniform without asphalt streaks or spots.

3.8.12 Extend the cap sheet to the top of cant strips.

3.8.13 Whenever possible, the entire roll shall be applied in a continuous manner.

3.8.14 Finished roof surfaces must have a uniform appearance throughout.

3.8.15 Completed roof covering must comply with the requirements of Underwriter's Laboratories, Inc.

for a Class A roof covering.

3.8.16 All roofing membrane shall be cut off neatly along top edge of all cants and at the exterior edge of

gutter wood blocking.

3.8.17 Install base flashings in accordance with Paragraph 3.4 below.

3.9 Base Flashing Installation (Torch)

3.9.1 Conform to the manufacturer`s printed installation instructions.

3.9.2 Prior to application of base flashings to metal, concrete, or masonry surface, apply appropriate

primer and allow to thoroughly dry.

3.9.3 At a minimum, smooth flashing membrane shall be applied after the roofing base membrane.

3.9.4 Base flashing granule-surfaced membrane shall be applied after granule-surfaced cap sheet has

been applied.

3.9.5 Install bituminous flashings at all curbs, walls and vertical surfaces where other types of flashings

are not specified or shown on Drawings.

3.9.6 At inside and outside corners of the parapet, curbs, and/or walls above roof level, furnish and

install a sacrifice smooth membrane in the corner. This sacrifice membrane shall extend onto

either side of the corner a minimum of 4 inches. Fully adhered the sacrifice membrane in

accordance with the membrane manufacturer written instruction.

3.9.7 Torch apply a strip of smooth base membrane, without voids, extending at least six (6) inches onto

the roof, up the face of the cant and at least six (6) inches up the vertical surface. However, base

flashing should extend up the vertical surface to the point of counter flashing installation. Lap the

ends at least three (3) inches, unless manufacturer has more stringent requirements. Flashings

shall not extend up the wall higher than 8 inches above the surface of the roof.

3.9.8 Certain SBS modified bitumen materials are not compatible with black plastic roofing/flashing

cement. Follow the manufacturer's written instructions regarding the use of such cements in close

proximity to flashing material.

3.9.9 Torch apply a strip of granules-surfaced membrane, without voids, extending at least six (6) inches

Page 97: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 7

onto the roof, up the face of the cant and at least six (6) inches up the vertical surface. However,

base flashing should extend up the vertical surface to the point of counter flashing installation.

Offset laps from the previous layer a minimum of six (6) inches. Lap the ends at least three (3)

inches, unless manufacturer has more stringent requirements. Flashings shall not extend up the

wall higher than 8 inches above the surface of the roof.

3.9.10 At walls/parapets with flashing heights exceeding eight (8) inches or as shown on detail drawings,

apply a strip of SBS modified bitumen wall flashing extending at least three (3) inches over the

top of the base flashing top edge and up to the wood blocking. Lap the ends at least three (3)

inches. Offset laps from base flashings a minimum of 12 inches. Heat the underside of the

membrane in accordance with the roofing system manufacturer’s written instructions. Fasten the

top of the wall flashing and apply cement, fiber glass mat, cement, and aluminum coating at the

laps in accordance with this section.

3.9.11 At inside and outside corners, extend the base flashing from 1st side of the corner to 4 inches onto

the 2nd side of the corner. The base flashing from the 2nd side of the corner shall extend onto the

base flashing at the 1st side of the corner a minimum of 4 inches. Notch extensions at cants and

where membrane extends onto roofing. Fully adhere base flashing in accordance with membrane

manufacturer recommendations and this section of the specification. This process shall be

accomplished for all base flashings layers and flashing extension.

3.9.12 Fasten the bituminous flashings top edge with flashing nails or appropriate fasteners on a line

approximately one (1) inch below the top edge and spaced not over four (4) inches apart. Where it

is not possible to secure the top of the bituminous flashings with flashing nails, furnish and install

nominal ¼” x 1" aluminum termination bar fastened to the substrate with appropriate fasteners at

spacings not to exceed six (6) inches on center. In the event that multiple termination bar sections

are used, leave a ¼ inch gap between sections.

3.9.13 Cover the top edges and fasteners with a nominal 1/8 inch thick trowelling of cement. At vertical

laps and corners, apply a trowelling of nominal 1/8 inch thick cement, embed a fiber glass mat,

and then cover with another 1/8 inch thick trowelling of cement. Apply cement on either side of

the vertical lap a minimum of three (3) inches.

3.9.14 Apply a uniform coating of a fibrated aluminum roof coating over all bituminous flashings and

laps using not less than 1-½" to 2 gallons per 100 square feet.

3.10 Bituminous Adhesive Application:

3.10.1 Pour the bituminous adhesive over the substrate and spread adhesive to an even and uniform

thickness using notched squeegees in accordance with manufacturer written instructions. The

adhesive shall be applied to the substrate so that the constant rate of coverage is one and one half

to two (1-1/2 – 2) gallons per square, unless manufacturer has more stringent requirements. Care

shall be taken not to apply adhesive over an area that is to be later cleaned and spliced to another

membrane sheet.

3.10.2 No adhesive is to be applied to the back side of the membrane.

3.10.3 While the adhesive is still wet, carefully roll the membrane into the adhesive, being sure to lap

membrane in accordance with the roofing system manufacturer’s written instruction and as

specified herein.

3.10.4 The formation of film on top of the adhesive shall not be allowed to occur, and the adhesive shall

not be applied if the application temperature is below 40°F or expected to be below 40°F during

drying time.

Page 98: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 8

3.10.5 Using a water-filled, foam covered lawn roller, firmly press the membrane to ensure full contact

with the adhesive layer by frequent rolling in two directions.

3.10.6 Membrane shall be smooth to the substrate, and wrinkles in the membrane shall be grounds for

rejection.

3.10.7 Bituminous adhesive shall not be used on vertical surfaces.

3.11 Cold-Process Smooth Bituminous Roof Membrane Installation:

3.11.1 Check substrate carefully for damage and application defects and make appropriate repairs and

corrections prior to application of roof surfacing.

3.11.2 Roll out membrane and allow to “relax” in accordance with roofing system manufacturer’s written

instructions.

3.11.3 Beginning at the low point of the roof area, 1 ply of smooth polyester base membrane shall be

applied shingle fashion, uniformly cemented with bituminous adhesive to the substrate and to each

other without voids.

3.11.4 Lap sides and ends in accordance with the approved Assembly and the roofing system

manufacturer written requirements. However, side laps shall be lapped a minimum of two (2)

inches and end laps a minimum of six (6) inches.

3.11.5 Whenever possible, the entire roll shall be applied in a continuous manner. If rolls can set while

partially rolled out, the roll shall be rolled back sufficiently to expose the area where the roll had

stopped so that asphalt may be applied to this area.

3.11.6 All roofing membrane shall be cut off neatly along top edge of all cants. Extend the membrane to

the exterior edge of eave wood blocking.

3.11.7 At internal roof drains, membrane shall be extended across the drain. Membrane shall be cut

across the drain body opening and trimmed flush with the inside face of the drain body. Seal the

membrane to the drain bowl using a three-coursing of roofing cement and mesh.

3.11.8 Drain lead flashings, clamping rings, and stripping shall be installed prior to the end of each

workday. Refer to Section 07 60 00 of this specification.

3.11.9 Furnish and install granulated bituminous membrane as specified herein.

3.12 Cold-Process Granulated Roof Membrane (Capsheet) Application:

3.12.1 Check roof surface carefully for damage and application defects and make appropriate repairs and

corrections prior to application of roof surfacing.

3.12.2 Install roof surfacing after base membrane has been applied, including stripping plies for

flashings. However, roof surfacing shall be applied prior to base flashings surfacing membrane.

3.12.3 Beginning at the saddle and cricket valleys created with tapered insulation at drains, apply one ply

of specified granulated bituminous membrane. Install cap sheet at valley so that water will run

across the laps.

3.12.4 After the valleys, beginning at the lowest point of the roof, apply one ply of granulated bituminous

membrane. Apply the membrane in shingle fashion.

Page 99: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 9

3.12.5 At hips, furnish and install an additional full width cap sheet over the hip extending 18 inches on

either side of the valley/hip.

3.12.6 Uniformly cement all granulated bituminous membrane with bituminous adhesive to the base

membrane and to each other.

3.12.7 Lap sides and ends in accordance with the approved Assembly and the roofing system

manufacturer written requirements. However, side laps shall be lapped a minimum of two (2)

inches and end laps a minimum of six (6) inches.

3.12.8 Embed white roofing granules, which match the cap sheet surface, in all asphalt overruns.

Finished surfaces must have a uniform appearance throughout without asphalt streaks or spots.

3.12.9 Whenever possible, the entire roll shall be applied in a continuous manner. If rolls are allowed to

set while partially rolled out, the roll shall be rolled back sufficiently to expose the area where the

roll had stopped so that asphalt may be applied to this area.

3.12.10 All roofing membrane shall be cut off neatly along top edge of all cants and at the exterior edge of

eave wood blocking.

3.12.11 At roof drains, the contractor shall apply a nominal 36” x 36” target patch where the drain bowl

lies in the center of the target patch. The target patch shall be cut across the drain body opening

and trimmed flush with the inside face of the drain body. The contractor shall adhere the target

patch to the base membrane by torch application.

3.12.12 At internal roof drains, cap sheet shall be extended onto the target patch a minimum of 6 inches at

all locations. The granules of the target patch shall be heated and embedded into the underlying

membrane asphalt prior to cap sheet application. Priming the granules is not acceptable.

3.12.13 At internal roof drains, furnish and install new fully reinforced PMMA/PMA flashing that shall

extend into the drain bowl a minimum of 4-inches and onto the roofing a minimum of 18-inches.

Apply the flashing in accordance with the flashing manufacturer’s written instructions.

3.12.14 Install base flashings as specified herein.

3.13 Base Flashing Installation:

3.13.1 Prior to application of base flashings to metal, concrete, or masonry surface, apply appropriate

primer and allow to thoroughly dry.

3.13.2 At a minimum, smooth bituminous flashing membrane shall be applied after the smooth

bituminous roof membrane.

3.13.3 Granulate bituminous flashing membrane shall be applied after granulated bituminous roofing

membrane has been applied.

3.13.4 Install bituminous flashings at all curbs, walls and vertical surfaces where other types of flashings

are not specified or shown on Drawings.

3.13.5 At inside and outside corners of the parapet, curbs, and/or walls above roof level, furnish and

install a sacrifice sheet in the corner. This sacrifice membrane shall extend onto either side of the

corner a minimum of 4 inches. Fully adhered the sacrifice membrane in accordance with the

membrane manufacturer written instruction.

Page 100: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 10

3.13.6 Apply a strip of smooth bituminous flashing membrane in flashing cement, without voids,

extending at least four (4) inches onto the roof, up the face of the cant, and at least eight (8) inches

above the top of the roof surface. However, base flashing should extend up the vertical surface to

the point of counterflashing installation. Lap the ends at least three (3) inches, unless manufacturer

has more stringent requirements. Flashings shall not extend up the wall higher than 8 inches

above the surface of the roof unless otherwise shown on drawings.

3.13.7 Apply a strip of granulated bituminous flashing membrane in flashing cement, without voids,

extending at least six (6) inches onto the roof, up the face of the cant, and at least eight (8) inches

above the top of the roof surface. However, base flashing should extend up the vertical surface to

the point of counterflashing installation. Offset laps from the previous layer a minimum of six (6)

inches. Lap the ends at least three (3) inches, unless manufacturer has more stringent

requirements. Flashings shall not extend up the wall higher than 8 inches above the surface of the

roof unless otherwise shown on drawings.

3.13.8 At walls/parapets with flashing heights exceeding eight (8) inches or as shown on detail drawings,

apply a strip of granulated bituminous flashing membrane in flashing cement extending at least

three (3) inches over the top of the base flashing top edge and up to the point of counterflashing.

Lap the ends at least three (3) inches. Offset laps from base flashings a minimum of 12 inches.

3.13.9 At inside and outside corners, extend the base flashing from 1st side of the corner to 4 inches onto

the 2nd side of the corner. The base flashing from the 2nd side of the corner shall extend onto the

base flashing at the 1st side of the corner a minimum of 4 inches. Notch extensions at cants and

where membrane extends onto roofing. Fully adhere base flashing in accordance with membrane

manufacturer recommendations and this section of the specification. This process shall be

accomplished for all base flashings layers and flashing extension.

3.13.10 Fasten the bituminous flashings top edge with flashing nails or appropriate fasteners on a line

approximately one (1) inch below the top edge and spaced not over four (4) inches apart. Where it

is not possible to secure the top of the bituminous flashings with flashing nails, furnish and install

specified termination bar fastened to the substrate with appropriate fasteners at spacings not to

exceed six (6) inches on center. If multiple termination bar sections are used, leave a ¼ inch gap

between sections.

3.13.11 Cover the top edges and fasteners with a nominal 1/8-inch-thick troweling of cement. At vertical

laps and corners, apply a troweling of nominal 1/8-inch-thick cement, embed a fiber glass mat, and

then cover with another 1/8-inch-thick troweling of cement. Apply cement on either side of the

vertical lap a minimum of three (3) inches.

3.13.12 Allow flashing cement to fully cure prior to applying coatings. Apply a uniform coating of a

fibrated aluminum roof coating over all bituminous flashings and laps using not less than 1-½" to

2 gallons per 100 square feet.

3.14 Heat Welding

3.14.1 Hot air weld all membrane seams a minimum of 2-inches using either a machine or hand-held hot

air welder approved by the roofing system manufacturer. A copy of the operating instructions

shall be provided to the Designer prior to the start of the project.

3.14.2 Utilize a roller to press the side and end laps of the membrane to ensure proper adhesion and

bleed-out.

Page 101: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 11

3.14.3 Monitor the temperature of the hot air welder to minimize the amount of smoke that should

develop and to ensure that the material from the bottom of the sheet begins to soften and flow

from the seam. Hand held welders shall insure that membrane welding is immediately followed

by a hand roller to press the heated membrane surfaces together with slow, even movements.

3.14.4 All seams shall be manually probed using a blunt rounded instrument daily. Any fishmouths or

other seam defects where the seam is not fully adhered shall be repaired in accordance with the

roofing system manufacturer’s instructions.

3.14.5 After seams have set for approximately 8 hours, the Contractor shall make a minimum of 3, 4" x

12" test cuts across the seam for every day of welding. Test cuts shall be repaired by the

Contractor daily and shall be done at no additional cost to the Owner. An archive of test shall be

available for Designer inspection.

3.14.6 Seams shall be tested in accordance with the roofing system manufacturer’s instructions and

evaluated for seam integrity. Seams that fail this test shall be subject to additional test cuts, as

directed by the Designer and/or roofing system manufacturer, in order to further quantify the

extend of the deficient condition. Repairs to deficient seams and/or test cut locations shall be

performed by the Contractor at no additional cost to the Owner.

3.15 Polyurethane-Bituminous Liquid Flashing

3.15.1 Install liquid flashings at location shown on drawings.

3.15.2 Perform adhesive test of all surfaces to received liquid membrane prior to application. Abrade

metal and/or roofing membrane surfaces to receive liquid flashing as required by the flashing

manufacturer.

3.15.3 Fill gaps between surfaces with backing and silicone sealant.

3.15.4 Mask target area a minimum of 8” onto the field with tape or other material and onto the vertical

substrate as shown on drawings. Prime all areas requiring the liquid flashing as required by the

flashing manufacturer.

3.15.5 Apply the liquid flashing base coat a minimum of 8” into the field of the roof and onto the vertical

substrate as shown on drawings. Cut reinforcement as to have a maximum of 2” of basecoat

exposed on both the field and vertical side of the sheet and completely embed the scrim sheet into

the liquid flashing base coat. Apply the liquid flashing finish coat a maximum of 2” beyond the

scrim outline.

3.15.6 Apply loose granules to the wet finish coat to match new field membrane. Immediately remove

the masking tape.

3.16 PMMA/PMA Liquid Flashing Installation:

3.16.1 Install liquid flashings at location shown on drawings.

3.16.2 Perform adhesive test of all surfaces to received liquid flashing prior to application. Abrade metal

and/or roofing membrane surfaces to receive liquid flashing as required by the flashing

manufacturer.

3.16.3 Fill gaps between surfaces with backing and silicone sealant.

3.16.4 Mask target area a minimum of 8” onto the field with tape or other material and onto the vertical

Page 102: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

SBS Modified Bituminous Membrane Roofing 07 52 16 12

substrate as shown on drawings. Prime all areas requiring the liquid flashing as required by the

flashing manufacturer.

3.16.5 Apply the liquid flashing base coat a minimum of 8” into the field of the roof and onto the vertical

substrate as shown on drawings. Cut reinforcement as to have a maximum of 1/8” of basecoat

exposed on both the field and vertical side of the sheet and completely embed the scrim sheet into

the liquid flashing base coat. Apply the liquid flashing finish coat a maximum of 1/8” beyond the

scrim outline.

3.16.6 Immediately remove the masking tape.

3.17 Walkway Pad

3.17.1 Check roof surface carefully for damage and application defects and make appropriate repairs and

corrections prior to application of walkway pads.

3.17.2 Roll out walkway pads and allow to “relax” in accordance with roofing system manufacturer’s

written instructions.

3.17.3 Refer to drawings for layout.

END OF SECTION

Page 103: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Polyvinyl Chloride Roofing 07 54 19 1

SECTION 07 54 19

POLYVINYL CHLORIDE ROOFING

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General and Supplementary Conditions, and

other Division 1 specification sections apply to work of this section.

1.2 Work Included:

1.2.1 Installation of a PVC roof membrane, as specified herein.

1.3 Related Work

1.3.1 Selective Demolitions and Preparations – Section 02 41 13.

1.3.2 Roof Board Insulation - Section 07 22 16.

1.3.3 Flashing and Sheet Metal – Section 07 60 00.

1.4 Submittals

1.4.1 In accordance with Section 01 33 00 of this Specification.

1.4.2 Provide a roof plan showing the membrane sheet layout for each roof. Also, note the progression

of the reroofing and the locations for discharge of tear off materials to show that the new

membrane and adjacent existing roofs will not be subjected to construction traffic.

1.5 Environmental Conditions

1.5.1 Material installation shall proceed only when weather conditions are in compliance with the

applicable manufacturer's recommendations for installation and no precipitation is imminent.

Materials installed during adverse weather conditions shall be subject to removal and replacement

with new materials at no additional cost to Owner.

1.6 Warranty

1.6.1 In accordance with Section 01 78 36 of this Specification.

PART 2 - PRODUCTS

2.1 Approved PVC Membrane Manufacturers are manufacturers by which the Contractor may solely furnish

materials to perform the work. PVC Membrane Manufacturer must, at a minimum, produce or

warrant/guarantee materials as specified in Sections 07 22 16 and 07 26 00 of this specification. Materials

furnished by the roofing system manufacturer are subject to the standards listed below. Any deviations

from standards listed below shall only be considered if the approved system manufacturer does not produce

a material to that stated standard, and must be submitted in writing by the approved roofing system

manufacturer. Any substitutions shall not alter the Warranty periods as described in this specification

Page 104: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Polyvinyl Chloride Roofing 07 54 19 2

2.2 Membrane manufacturer shall be one of the following:

2.2.1 Sika Sarnafil

2.2.2 Carlisle,

2.2.3 Fibertite Roofing Products by Seaman Corporation,

2.2.4 Soprema.

2.3 PVC Roofing Materials

2.3.1 Polyvinyl Chloride Roofing Membrane: Polyester reinforced fleece-back membrane meeting

ASTM D4434 or ASTM D 6754. Thickness shall be as required for specific no dollar limit

warranty but shall not be less than 36 mils.

2.3.2 Membrane shall be membrane manufacturer’s premium grade.

2.3.3 PVC Unsupported Flashing: Minimum 55 mil thickness as provided by the approved roofing

system manufacturer.

2.3.4 PVC Universal Pipe Boot Flashings: As manufactured by the approved roofing system

manufacturer. Pre-fabricated flashing boot shall include a draw band for securing the top of the

flashing boot to the pipe

2.3.5 PVC Inside and Outside Corners: As manufactured by the approved roofing system manufacturer.

For use at inside and outside corners of curbs, parapets, and other similar junctures. The use of

field-fabricated corner pieces is not acceptable.

2.3.6 PVC Membrane Cleaner: As manufactured by the approved roofing system manufacturer. For use

in removing foreign debris from the membrane prior to welding.

2.3.7 PVC Membrane Adhesive: As manufactured by the approved roofing system manufacturer. For

use to adhere PVC membrane to the substrate.

2.3.8 PVC Coated Clad Metal: As manufactured by the approved roofing system manufacturer,

minimum 24 ga. galvanized steel.

2.3.9 Termination Bar: As manufactured or approved by the approved roofing system manufacturer.

2.3.10 Polyurethane Caulk: As manufactured and/or approved by the roofing system manufacturer. To

be applied at those locations identified by the manufacturer.

2.3.11 Water Cut Off Mastic: Butyl sealant as manufactured and/or approved by the roofing system

manufacturer.

2.3.12 Liquid Applied Flashing: Shall be supplied by the membrane manufacturer.

2.3.13 PMMA: Shall be supplied by the membrane manufacturer and shall be compatible with the

membrane.

2.3.14 Membrane Welding Machines: As approved by the roofing system manufacturer. Contractor shall

Page 105: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Polyvinyl Chloride Roofing 07 54 19 3

provide written documentation that operators have received the roofing system manufacturer’s

required training to operate equipment. Welders shall be maintained in good working order and

shall be operated and maintained in accordance with the welding machine manufacturer’s written

instructions.

2.3.15 Roofing Nails: See specification section 06 10 53 Miscellaneous Rough Carpentry.

2.3.16 Barrier board (Parapets and curbs): Shall be high density, water resistant, and moisture resistant

treated board with inorganic fibrous glass mat facer on both sides. All pieces shall have a

maximum size of 4’x8’. Shall be ½” thick, a nominal weight of 1,100 lbs. per 1000 s.f., and shall

be UL Classified (UL 790 Class A and UL 1256).

2.3.17 Curb barrier – Shall be one of the following:

2.3.17.1 Sheet metal: Shall be 26 gage galvanized sheet metal properly cleaned of oils, etc. as

required by the membrane manufacturer and fastened to the substrate with fasteners at

12” o.c. staggered.

2.3.17.2 Fleece: Shall be 9oz/yd2 polyester fleece as required by the membrane manufacturer and

adhered to the substrate with adhesive as required by the membrane manufacturer.

2.3.18 Fire Resistance: System components shall be tested, manufactured and installed to result in a

roofing system that is UL Class A rated.

PART 3 - PROCEDURES

3.1 Inspection

3.1.1 One ply of modified asphalt membrane shall be installed prior to beginning application of PVC

membrane.

3.1.2 The substrate shall be clean, smooth, dry, free of debris and all foreign matter prior to installation

of the roof membrane, and in a condition to receive the manufacturer’s product in accordance with

manufacturer’s instructions. Application of new materials shall constitute approval of the

substrate by the Roofing Contractor.

3.1.3 The accumulation of debris beneath or above new membrane is not acceptable and shall be

grounds for rejection.

3.1.4 Verify proper installation of all roof penetrations, projections, and nailers including but not

necessarily limited to dimensions, heights, and locations of curbs, prior to installation of new roof

material.

3.2 Barrier Board Installation: Install barrier board as required by the membrane manufacturer. Secure parapet

barrier board with fasteners appropriate for the substrate (do not use nails) at a rate of 1 row every 16”

maximum and spacing of 12” o.c.

3.3 All adhered flashings that exceed 30 inches in height shall receive additional securement per

manufacturer’s warranty requirements and as shown on the drawings.

Page 106: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Polyvinyl Chloride Roofing 07 54 19 4

3.4 Roof Membrane Installation

3.4.1 Roll out membrane and allow the membrane to “relax” in accordance with manufacturer written

instructions. Back roll the membrane prior to application.

3.4.2 Roll or brush a smooth, even coat of adhesive over the substrate, ensuring 100% coverage of the

substrate with no voids, skips, globs, puddles or similar irregularities.

3.4.3 Allow the adhesive to become sticky but still wet to the touch. Do not allow a film to develop on

the adhesive or allow the adhesive to dry out.

3.4.4 Roll/maneuver the membrane onto the glued substrate, avoiding any wrinkles or air pockets.

3.4.5 Broom the adhered portion of the membrane to ensure full contact and complete the bonding

process by firmly pressing the bonded membrane into place with a weighted, foam-covered, lawn

roller.

3.4.6 Repeat the process for the remaining unbonded portion of the membrane, lapping subsequent,

adjacent rolls of membrane a minimum of 3”; aligning the top leading edge of membrane to the

top finished edge of the bottom section of membrane, ensuring proper shingling of the membrane

to shed water along the laps.

3.4.7 No adhesive shall be applied to the lap seam areas of the membrane. Contaminated areas will

inhibit proper welding of the seams requiring a membrane patch.

3.4.8 Water based adhesives can be directly affected by moisture. Water based adhesives should not to

be installed over/on substrates that are moist or wet or on systems or substrates that have residual

moisture.

3.4.9 At roof edges, extend membrane over the wood blocking and down past the exterior outside face

of the blocking a minimum of 1 inch.

3.4.10 Turn membrane up vertical surfaces and using the roofing system manufacturer’s fasteners and

termination bar in accordance with the roofing system manufacturer’s approved written

instructions. Apply water cut-off mastic behind the membrane prior to fastening, and apply sealant

at the top of the membrane after securing. Fasteners shall penetrate the substrate at spacings and

depths approved by the roofing system manufacturer, however, depth shall be a minimum of 1

inch and spacings shall be exceed 8 inches on center.

3.4.11 At drains, extend the membrane over the drain. Cut an opening in the membrane at the center of

the drain bowl so that the membrane extends past the edge of the drain bowl a minimum of 1 inch.

Apply water block between the membrane and the drain bowl prior to applying the drain clamping

ring. If a field membrane seam lies within 18 inches of the center of the drain bowl, furnish and

install a new minimum 36 inch by 36 inch target patch. Fully adhere the target patch to the field

membrane using the membrane manufacturer bonding adhesive. Fully weld target patch splices to

the field membrane a minimum of 2 inches on all sides. Weld in accordance with this section of

the specification. Refer to the Drawings.

3.4.12 Hot air weld all membrane seams using either a machine or hand-held hot air welder approved by

the roofing system manufacturer. A copy of the operating instructions shall be provided to the

Engineer prior to the start of the project.

Page 107: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Polyvinyl Chloride Roofing 07 54 19 5

3.4.13 Monitor the temperature of the hot air welder so as to minimize the amount of smoke that should

develop and to ensure that the material from the bottom of the sheet begins to soften and flow

from the seam. Hand held welders shall ensure that membrane welding is immediately followed

by a hand roller to press the heated membrane surfaces together with slow, even movements.

3.4.14 All seams shall be manually probed using a blunt rounded instrument daily. Any fishmouths or

other seam defects where the seam is not fully adhered shall be repaired in accordance with the

roofing system manufacturer’s instructions.

3.4.15 After seams have set for approximately 8 hours, the Contractor shall make a minimum of 3, 4" x

12" test cuts across the seam for every day of welding. Test cuts shall be repaired by the

Contractor daily and shall be done at no additional cost to the Owner. In lieu of test cuts, the

contractor may perform pull test. Pull test shall be performed with two 4” x 12” pieces of

membrane that shall be welded together 1-1/2 inch for the machine welder and 2 inches for hand

welders. The membrane shall be pulled apart across the seam. Test shall be dated, and one test

shall be performed every time a welding device is turned on. An archive of tests shall be available

for Engineer inspection.

3.4.16 Seams shall be tested in accordance with the roofing system manufacturer’s instructions and

evaluated for seam integrity. Seams that fail this test shall be subject to additional test cuts, as

directed by the Engineer and/or roofing system manufacturer, in order to further quantify the

extend of the deficient condition. Repairs to deficient seams and/or test cut locations shall be

performed by the Contractor at no additional cost to the Owner.

3.4.17 Furnish and install the roofing system manufacturer’s patches at all required locations such as

intersection field seams. Apply the manufacturer’s approved seam caulk, as required, at locations

specified by the roofing system manufacturer.

3.4.18 Install membrane manufacturer’s walkway pads to 4 sides of roof hatch, mechanical units and

skylights.

3.5 Where membrane terminates on metal, the metal shall be PVC clad metal and the membrane shall be hot air

welded to the metal.

3.6 Base Flashings Installation

3.6.1 Apply the roofing system manufacturer’s approved flashing adhesive to the inside face of vertical

surfaces, such as parapets, curbs, wall and/or wood blocking, at the rate specified by the roofing

system manufacturer for the substrate using the manufacturer’s approved applicator. At locations

where membrane flashing will be applied directly to smooth residual asphaltic materials, the

Contractor shall secure curb barrier material with fasteners (for sheet metal) or adhesive (for

fleece).

3.6.2 Roll out the membrane to be used for base flashings and allow to relax in accordance with the

roofing system manufacturer’s written instructions.

3.6.3 Cut flashing pieces so as to extend onto the roof a minimum of 8 inches and up the vertical surface

a minimum of 8 inches.

3.6.4 Apply the roofing system manufacturer’s approved flashing adhesive to the back of the base

flashing material and substrate at the rate specified by the roofing system manufacturer for the

substrate. At side laps and the edge of the base flashing extending onto the roof, do not apply

Page 108: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Polyvinyl Chloride Roofing 07 54 19 6

adhesive at these locations so as to allow hot-air welding. Allow adhesive to dry sufficiently so as

to produce strings when touched with a dry, clean finger.

3.6.5 Roll the base flashing material onto the previously coated substrate without voids using a hand

roller to insure positive contact of the substrate and base flashing material. Overlap all adjacent

flashing sheets a minimum of 3 inches. Base flashing shall be smooth to the substrate, and

wrinkles in base flashing shall be grounds for rejection.

3.6.6 Hot air weld all side laps and the edge of the base flashings that extend onto the roof in accordance

with hot-air welding instructions listed in this section and/or the instructions provided with the

welding machine. Fully weld all laps, even those extending beneath flashings and units.

3.6.7 All seams shall be probed daily using a blunt, rounded instrument. All defects shall be corrected

in accordance with the roofing system manufacturer’s written instructions.

3.6.8 Seal the edges of the base flashings where the reinforcing fabric is cut with the roofing system

manufacturer’s approved seam sealant, as required by the membrane manufacturer. Such work

shall be done on a daily basis.

3.6.9 At those locations where the top of the base flashings will not be secured with counter flashings,

or as shown on drawings, furnish and install a nominal 1" x ¼” flat bar or the roofing system

manufacturer’s termination bar along the top edge of the base flashings. Secure with appropriate

fasteners at spacings not to exceed 8 inches on center. Apply a bead of the roofing system

manufacturer’s water cut-off mastic behind the top edge of the base flashing. Apply a bead of the

roofing system manufacturer’s approved caulk along the top edge of the base flashings.

3.6.10 In the event that base flashings terminate at a corner and edges would be exposed, furnish and

install new 4 inch wide PVC-coated metal closures with an exterior edge caulking cove. The

closure shall be set in water cut-off mastic and fastened to the substrate using appropriate fasteners

at spacings not to exceed 12 inches on center. Completely hot air weld the base flashings to the

PVC-coated metal. Apply a non-shrinking sealant, such as NP-1 or approved equal, to the

caulking cove at the exterior edge of the closure. Completely remove all residual asphalt from the

substrate prior to installing any sealant or caulking.

3.6.11 At inside and outside corners of curbs, Contractor shall use the roofing system manufacturer’s pre-

fabricated corner pieces. The use of field-fabricated pieces is not acceptable. Pre-fabricated

pieces shall be installed in accordance with the roofing system manufacturer’s written instructions.

3.6.12 Use the roofing system manufacturer’s termination bar at base flashing edges at changes in base

flashing height. Fastener spacings not to exceed 12 inches on center. Set flashing in water cut-off

mastic, set the bar over the edge of the base flashing, and apply caulk at the top of the flashing.

3.6.13 At a minimum, extend base flashings up and over the top horizontal surface of curbs and inside

the curb a minimum of 1 inch, unless otherwise stated in specification or shown on drawings.

END OF SECTION

Page 109: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Flashing and Sheet Metal 07 60 00 1

SECTION 07 60 00

FLASHING AND SHEET METAL

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract, Supplementary

General Conditions, and other Division 1 specification sections apply to work of this section.

1.2 Work Included - Includes the fabrication and installation of sheet metal and related accessories associated with

roofing membranes, providing physical protection to membrane, base flashings and membrane terminations, as

specified herein.

1.3 Related Work

1.3.1 Miscellaneous Rough Carpentry - Section 06 10 53

1.3.2 Polyvinyl Chloride Roofing – Section 07 54 19

1.3.3 Joint Sealants – Section 07 92 00

1.4 Submittals - In accordance with Section 01 33 00 of this Specification

1.5 Environmental Conditions - Material installation shall proceed only when weather conditions are in compliance

with the applicable manufacturer's recommendations for installation and no precipitation is imminent. Materials

installed during adverse weather conditions shall be subject to removal and replacement with new materials at no

additional cost to Owner.

1.6 Guarantee - In accordance with Section 01 78 36 of this Specification.

PART 2 - PRODUCTS

2.1 Copings:

2.1.1 Galvalume: ASTM A-792, minimum 24 ga. thickness, unless otherwise noted.

2.1.2 Kynar 500-based finish: Shall be factory-applied, oven-finish. Finish and primer shall be applied in

strict accordance with the formulator's specifications and shall meet the performance criteria of AAMA

605.2-90 and ASTM A-653 G-90. Finish coat thickness shall be a minimum of 1.0 mil. Primer coat

thickness shall be a minimum of 0.3 mil. Color to match the existing color to be selected by owner.

2.2 Through-Wall Flashing, Counter Flashing:

2.2.1 Stainless Steel: 24 gauge (0.025 inches) Type 316 (16% chromium, 10% nickel, and 2% molybdenum)

ASTM A240, mill finished.

2.2.2 Solder: ASTM B 32, Grade Sn60, with an acid flux of type recommended by stainless-steel sheet

manufacturer.

2.2.3 Cleats: Continuous, same metal as flashing.

Page 110: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Flashing and Sheet Metal 07 60 00 2

2.3 Termination Bar: ¼” x 1” aluminum.

2.4 Pop rivets: 1/8" diameter stainless steel pop rivets color to match adjoining metal.

2.5 Fasteners: Same metal as flashing/sheet metal, or other non-corrosive metal as recommended by sheet

manufacturer.

2.6 Sealant: See Specification Section 07 92 00 Joint Sealants.

2.7 New splash blocks shall be concrete and provided at each downspout.

2.8 Fire Rated Sealant - Sealant to be as recommended by the following manufacturer’s to provide a one hour rated

closure and shall meet ASTM E119 or UL 263. Use proper sealant joint design as required by the sealant joint

manufacturer. The following manufacturers are approved for use on this project:

2.8.1 Hilti Corporation

2.8.2 Pecora Corporation

2.8.3 Tremco

2.8.4 DAP

2.9 MINIMUM ACCEPTABLE METAL WEIGHT:

Coping: 24 ga. galvalume steel (kynar coated)

Cleat: 22 ga. galvalume steel (mill finish)

Counter Flashing: 24 ga. galvalume steel (kynar coated)

Reglet Flashing: 24 ga. galvanized steel (kynar coated)

Overflow Scupper: 24 ga. stainless steel (membrane-coated)

Overflow Scupper Exterior Flange: 24 ga. galvanized steel (kynar coated)

Drip Edge Flashing: 24 ga. galvanized steel (membrane-coated)

PART 3 - EXECUTION

3.1 General Installation Requirements

3.1.1 Inspect all surfaces to which metal is to be applied. Do not install metal unless surfaces are even, sound,

clean, dry and free from defects which might affect the application.

3.1.2 Follow recommendations of the Sheet Metal and Air Conditioning Contractors National Association

Architectural Sheet Metal Manual (7th Edition) for fabricating in-shop and on-site, and for installation,

unless otherwise specified herein.

3.1.3 Follow published instructions of the product manufacturer for installation of extruded or proprietary

metal products, unless otherwise specified herein.

3.1.4 Use nails, screws, bolts, cleats or other fasteners of the same material or of material chemically

compatible with the contacted metal.

3.1.5 Do not place dissimilar metals in direct contact or in positions where water sheds across both metals.

3.1.6 Install metal to be water and weather tight with lines, arises and angles sharp and true and with paint

Page 111: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Flashing and Sheet Metal 07 60 00 3

surfaces free of waves and buckles.

3.1.7 Install shop-formed metal flashings in 10 foot lengths maximum with a minimum number of pieces in

each straight run.

3.1.8 Shop form all metal shapes, which are to be formed of prefinished metal, with protective plastic film in

place. Do not remove plastic film until just prior to (or, if possible, after) installation.

3.1.9 At all corners, shop form corner pieces of fascia and drip edge flashing from a single section of metal

with minimum 36 inch legs on either side of the corner.

3.1.10 Apply a continuous bead of caulk between any lapped metal sections, with the exception of counter

flashing lapped joints. The application of caulk after metal components have been lapped is unacceptable

and will be grounds for rejection.

3.2 Installation

3.2.1 Material:

3.2.1.1 Coping caps shall be prefinished roll-formed 24 gauge galvalume steel with “Kynar 500” resin

fluoropolymer. Color shall be selected by Owner from manufacturer’s standard color selections.

3.2.1.2 Counter flashings, through-wall flashings, shall be mill finished, 24 gauge stainless steel.

3.2.2 Provide flashing in 10 foot long sections shop formed.

3.2.3 Anchors shall be provided at 6” o.c. unless otherwise noted or in accordance with the manufacturer’s

requirements if more stringent.

3.2.4 Notch and lap sections a minimum of 3 inches.

3.2.5 At places where the counterflashing is being installed behind a frame or existing sheet metal flashing,

slide counterflashing behind frame/existing flashing a minimum of one inch. Furnish and install stainless

steel bonded neoprene washers with screws to secure counter flashing to curbs at spacings not to exceed

12 inches on-center.

3.2.6 At places where counter flashing will be surface-mounted, form a sealant cove at the top of the counter

flashing. Secure the counter flashing to the substrate using continuous 1” x ¼” aluminum flat bar and

appropriate fasteners at spacings not to exceed 12 inches on-center. Fill the cove with sealant.

3.2.7 Notch and lap joints and inside corners. Notch and seam outside corners. Do not rivet or otherwise

secure joints and corner. To the extent possible, form corners from a single piece that extends 5 feet on

either side of the corner.

END OF SECTION

Page 112: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Joint Sealants 07 92 00 1

SECTION 07 92 00

JOINT SEALANTS

PART 1 - GENERAL

1.1 Drawings and general provisions of the contract, including General Conditions of the Contract,

Supplementary General Conditions, and other Division 1 specification sections apply to work of this

section.

1.2 Related work specified elsewhere - Selective Demolition and Preparations- Section 02 41 13

1.3 Submittals

1.3.1 Submit copies of manufacturer's literature for the following:

1.3.1.1 Product Data consisting of sealant manufacturer’s product information for components,

materials, accessories, and equipment necessary to perform the work.

1.3.1.2 Applicable detail and shop drawings for the work.

1.3.1.3 Samples for initial selection purposes in form of manufacturer’s color charts or chips

showing full range of colors and textures.

1.3.1.4 Installer certificates signed by sealant system manufacturer and written certification

certifying that the installer complies with requirements included under the “Quality

Assurance” section of the Specification.

1.3.1.5 Operation and Maintenance Data as required by the warranty.

1.3.1.6 Manufacturer’s Certificates: Certify products meet or exceed specified requirements.

1.3.2 Refer to Section 01 33 00 of Specification.

1.4 Environmental Conditions

1.4.1 Material installation shall proceed only when weather conditions are in compliance with

manufacturer's recommendations for installation and no precipitation is imminent. Materials

installed during adverse weather conditions shall be subject to rejection including removal and

replacement.

1.4.2 Use manufacturer’s standard test method to determine whether priming and other specific joint

preparation techniques are required to obtain rapid, optimum adhesion of joint sealants to joint

substrates.

1.5 Quality Assurance

1.5.1 Contractor: Joint Sealant applicator must be approved, authorized, or licensed in writing by the

approved sealant product manufacturer and have a minimum of five years’ experience as an

approved, authorized, or licensed applicator with that manufacturer and be approved at a level

capable of providing the specified warranty. The applicator must supply the names, locations and

client contact information of five projects of similar size and scope that the applicator has

constructed using the manufacturer's sealant products submitted for this project within the

previous three years.

1.5.2 Contractor shall perform destructive adhesion test in accordance with the latest edition of ASTM

C1521. Test shall be documented with photographs. Test results and photographs shall be

composed into a report that shall be issued to the Owner and Designer within 24 hours of the test.

Adhesion test shall be performed by a North Carolina licensed third party firm with a minimum of

5 years experience in material testing. A minimum of 2 tests shall be performed (1 in a joint

Page 113: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Joint Sealants 07 92 00 2

between EIFS and EIFS and 1 in a joint between brick and EIFS). Each test shall be performed on

a minimum of 6 linear inches of sealant. Any repairs to sealant as a result of failure under this

paragraph shall be performed by the Contractor at no additional cost to the Owner.

1.5.2.1 Make a transverse cut in the new sealant across the entire width of the sealant.

1.5.2.2 Make parallel cuts down the length of the joint starting at the transverse cut on either side

of the sealant for a distance of 3 inches.

1.5.2.3 Pull the top of the cut sealant out tight to a 90 degree angle to the wall.

1.5.2.4 Make a mark that is 1 inch away from the wall down the length of the pulled out section.

1.5.2.5 Pull the sealant at this angle until the mark made at 1 inch is at 4 inches and no adhesive

or cohesive failure has occurred.

1.5.2.6 This represents a 300% elongation and a successful test.

1.5.2.7 Document and record results.

1.5.2.8 All pull tests under this paragraph shall be repaired by the Contractor at no additional

cost to the Owner.

1.5.3 Manufacturer: Manufacturer shall have a minimum of 10 years of continuous, concurrent

experience providing specified materials including the current year.

1.6 Warranty - Refer to Section 01 78 36 of this specification.

PART 2 - PRODUCTS

2.1 Materials, General

2.1.1 Compatibility: Provide joint sealants, backings, and other related materials that are compatible

with one another and with joint substrates under conditions of service and application, as

demonstrated by joint-sealant manufacturer, based on testing and field experience.

2.1.2 Colors of Exposed Joint Sealants: To match existing wall finish as selected by Owner.

2.2 Joint Sealants

2.2.1 Silicone, non-sagging, non-staining, low modulus sealant; ASTM C 920, Type S or M, Grade NS,

Class 100/50, for Use NT, M, A, and O:

2.2.1.1 For use in joining stone, metal, and/or composite plastic at joints.

2.2.1.2 Products: Subject to compliance with requirements. All listed manufacturers and

products are provided as examples of the salient characteristics to be found in the

submitted product. Any additional manufacturers not listed must meet the requirements

set forth in this specification and be approved prior to bid in accordance with Section 01

60 00. Products that may be incorporated into the Work include, but are not limited to

the following:

i Dow Corning Corporation; 790 Silicone Building Sealant

ii Sika Corporation; SikaSil 15LM

iii Tremco; Dymonic 100

2.3 Joint Sealant Backing

2.3.1 General: Provide sealant backings of material that are nonstaining; are compatible with joint

substrates, sealants, primers, and other joint fillers; and are approved for applications indicated by

Page 114: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Joint Sealants 07 92 00 3

sealant manufacturer based on field experience and laboratory testing.

2.3.2 Cylindrical Sealant Backings: ASTM C 1330, type C (closed-cell material with a surface skin)

and of size and density to control sealant depth and otherwise contribute to producing optimum

sealant performance. Approximately 1.25 – 1.33 times larger than the openings, unless

manufacturer has more stringent requirements.

2.3.3 Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant

manufacturer for preventing sealant from adhering to rigid, inflexible joint-filler materials or joint

surfaces at back of joint. Provide self-adhesive tape where applicable.

2.4 Miscellaneous Materials

2.4.1 Primer: Material recommended by joint-sealant manufacturer where required for adhesion of

sealant to joint substrates.

2.4.2 Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and

sealant backing materials, free of oily residues or other substances capable of staining or harming

joint substrates and adjacent nonporous surfaces in any way, and formulated to promote optimum

adhesion of sealants to joint substrates.

2.4.3 Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces

adjacent to joints.

PART 3 - EXECUTION

3.1 Examination

3.1.1 Sealant and backer rod installation shall be performed by a qualified and experienced installer

having at least 5 years of experience in this type of work.

3.1.2 Contractor shall make every effort to match the new sealant with the existing wall panels.

3.2 Preparation

3.2.1 Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply

with joint-sealant manufacturer’s written instructions and the following requirements:

3.2.1.1 Remove all foreign material from joint substrates that could interfere with adhesion of

joint sealant, including dust, paints (except for permanent, protective coatings tested and

approved for sealant adhesion and compatibility by sealant manufacturer), old joint

sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.

3.2.1.2 Clean porous joint substrate surfaces by brushing, grinding, mechanical abrading, or a

combination of these methods to produce a clean, sound substrate capable of developing

optimum bond with joint sealants. Remove loose particles remaining after cleaning

operations above by vacuuming or blowing out joints with oil-free compressed air.

Ensure surface roughness inside joints is as necessary for sealant application in

accordance with joint sealant manufacturer written instructions.

3.2.1.3 Clean nonporous joint substrate surfaces with chemical cleaners or other means that do

not stain, harm substrates, or leave residues capable of interfering with adhesion of joint

sealants.

Page 115: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Joint Sealants 07 92 00 4

3.2.1.4 Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer.

Apply primer to comply with joint-sealant manufacturer’s written instructions. Confine

primer to areas of joint-sealant bond; do not allow spillage or migration onto adjoining

surfaces.

3.2.1.5 Masking Tape: Use masking tape where required to prevent contact of sealant or primer

with adjoining surfaces that otherwise would be permanently stained or damaged by such

contact or by cleaning methods required to remove sealant smears. Remove tape

immediately after tooling without disturbing joint seal.

3.3 Installation of Joint Sealants

3.3.1 General: Comply with joint-sealant manufacturer’s written installation instructions for products

and applications indicated, unless more stringent requirements apply.

3.3.2 Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint

sealants as applicable to materials, applications, and conditions indicated.

3.3.3 Install sealant backings of kind indicated to support sealants during application and at position

required to produce cross-sectional shapes and depths of installed sealants relative to joint widths

that allow optimum sealant movement capability:

3.3.3.1 Do not leave gaps between ends of sealant backings.

3.3.3.2 Do not stretch, twist, puncture, or tear sealant backings.

3.3.3.3 Remove absorbent sealant backings that have become wet before sealant application and

replace them with dry materials.

3.3.3.4 Set depth of backing in accordance with manufacturer written instructions for optimal

joint depth.

3.3.4 Install sealants using proven techniques that comply with the following and at the same time

backings are installed:

3.3.4.1 Place sealants so they directly contact and fully wet joint substrates.

3.3.4.2 Completely fill recesses in each joint configuration.

3.3.4.3 Produce uniform, cross-sectional shapes and depths relative to joint widths that allow

optimum sealant adhesion and movement capability.

3.4 Cleaning - Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods

and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which

joints occur.

3.5 Protection - Protect joint sealants during and after curing period from contact with contaminating

substances and from damage resulting from construction operations or other causes so sealants are without

deterioration or damage at time of Substantial Completion. If, despite such protection, damage or

deterioration occurs, cut out and remove damaged or deteriorated joint sealants immediately so installations

with repaired areas are indistinguishable from original work.

END OF SECTION

Page 116: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Plastic Glazed Unit Skylights 08 62 00 1

SECTION 08 62 00

PLASTIC GLAZED UNIT SKYLIGHTS

PART 1 - GENERAL

1.1 Work Included: Removal and Installation of new curb mounted skylights.

1.2 Related Work

1.2.1 Rough Carpentry – Section 06 10 53

1.2.2 Polyvinyl Chloride Roofing – Section 07 54 9

1.2.3 Flashing and Sheet Metal - Section 07 60 00

1.3 Submittals - Refer to Section 01 33 00 of this Specification.

1.4 Guarantee - In accordance with Section 01 78 36 of this Specification.

1.5 Environmental Conditions - Materials installation shall proceed only when weather conditions are in compliance

with the applicable manufacturer's recommendations for installation and no precipitation is imminent. Materials

installed during adverse weather conditions shall be subject to removal and replacement with new materials at no

additional cost to Owner.

1.6 Installation Requirements – removal of the existing skylights requires coordination with the Owner and written

approval. During removal and after the skylights are removed, the interior below must be blocked off with a

contractor representative rerouting pedestrian traffic until the skylight has been reinstalled.

1.7 Performance Requirements

1.7.1 General: Provide unit skylights capable of withstanding loads indicated without failure. Failure includes

the following:

1.7.1.1 Thermal stresses transferred to the building structure.

1.7.1.2 Framing members transferring stresses, including those caused by thermal and structural

movement, to glazing.

1.7.1.3 Noise or vibration created by thermal and structural movement and wind.

1.7.1.4 Weakening of fasteners, attachments, and other components.

1.7.2 Structural Loads: Provide unit skylights that meet the requirements of American Architectural

Manufacturer’s Association (AAMA) publication “Voluntary Uniform Load Structural Standard for

Plastic Domed Skylights” (AAMA 1606-82) which requires glazing thickness adequate to withstand a

positive and negative test pressure of 60 PSF.

1.8 Quality Assurance - Fire-Test-Response Characteristics: Provide Thermoformed domes fabricated from sheets

identical to those tested for the following fire-test-response characteristics, per ASTM test method indicated

below, by UL or other testing and inspecting agencies acceptable to authorities having jurisdiction. Identify plastic

sheets with appropriate markings of applicable testing and inspecting organization.

1.8.1 Self-Ignition Temperature: 651 deg F (343 deg C) or greater when tested per ASTM D 1929 on plastic

sheets in the thickness intended for use.

1.8.2 Smoke density of 75 or less when tested per ASTM D 2843 on plastic sheets in the thickness intended for

Page 117: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Plastic Glazed Unit Skylights 08 62 00 2

use.

1.8.3 Relative- Burning Characteristics: As follows, when tested per ASTM D 635. Acrylic: Burning rate of 2.5

inches (64 mm) per minute or less when tested on plastic glazing indicated below with a nominal

thickness of 0.060 inch (1.5 mm) or the thickness intended for use.

PART 2 - PRODUCTS

2.1 Fixed Skylight Units

2.1.1 General: Factory-assembled, curb-mounted unit consisting of impact plastic glazing, gasketing, inner

frame designed to mount on separate curb, and self-contained flashing.

2.1.2 Manufacturers: Must have been in the skylight business for not less than a period of 15 years. Shall be of

the systems as listed below, or approved equal:

2.1.2.1 EcoSky Model E3CA Plastic Glazed Unit Skylights by Wasco Products, Inc., Wells, ME (800-

388-0293).

2.1.3 Condensation Control: Fabricate skylight units with integral internal gutters and weeps to collect and

dispose of condensation.

2.1.4 Thermal Break: Fabricate skylight units with thermal barrier separating interior metal framing from

materials exposed to outside temperature.

2.1.5 Field Measurements: Verify dimensions of existing skylight curbs by field measurements before

fabrication and indicate measurements on Shop Drawings. Coordinate fabrication schedule with

construction progress to avoid delaying the work.

2.1.6 Outer Glazing: Impact Glazing, Thermoformed outer dome or pyramid with 25% rise. Infrared blocking.

2.1.6.1 Smoke Density: ASTM D 2843 < 75.

2.1.6.2 Combustibility Classification: ASTM D-635, CC2 - less than 2.5”/minute.

2.1.6.3 Self-Ignition Temperature: ASTM D-1929 > 650 degrees Fahrenheit.

2.1.7 Inner Glazing: 10mm lumira aerogel filled polycarbonate.

2.1.7.1 Smoke Density: ASTM D 2843 - 35.

2.1.7.2 Combustibility Classification: ASTM D-635, CC1 - less than 1”/minute.

2.1.7.3 Self-Ignition Temperature: ASTM D-1929 > 1110 degrees Fahrenheit.

2.1.8 Performance Requirements:

2.1.8.1 SHGC: 0.34

2.1.8.2 U: 0.25

2.1.8.3 VT: 43%

2.1.8.4 Glare-Free, Full Spectrum diffused light.

Page 118: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Plastic Glazed Unit Skylights 08 62 00 3

2.1.8.5 Air Infiltration: 0.10 cfm/ft square at 1.57 psf per ASTM E283

2.1.8.6 Water Penetration: 12psf per ASTM E547 and ASTM E331

2.1.9 Fasteners: Same metal as metals being fastened, or non-magnetic stainless steel or other non-corrosive

metal as recommended by manufacturer.

2.2 Fasteners: Same metal as metals being fastened, or non-magnetic stainless steel or other non-corrosive metal as

recommended by manufacturer

2.3 Fall Protection Safety - Uniform design load capacity to meet or exceed 40 PSF snow load and 40 PSF wind uplift.

No dome breakage or total disengagement of glazing from the frame shall occur upon impact of minimum 775 ft.

lbs. Units shall be designed to comply with the intent of OSHA fall protection regulations.

2.4 Aluminum Finishes

2.4.1 General: Comply with NAAMM “Metal Finishes Manual” recommendations for application and

designations of finishes.

2.4.2 Finish designations prefixed by AA conform to the system for designations of aluminum finishes

established by the Aluminum Association.

2.4.3 Mill Finish: Manufacturer’s standard mill finish.

PART 3 - EXECUTION

3.1 Removal

3.1.1 Remove all existing skylights and associated flashings, and discard.

3.1.2 Remove or correct any obstruction which might interfere with the proper application of new materials.

3.2 Examination - Examine substrates and conditions, with installer present, for compliance with requirements for

installation tolerances and other conditions affecting skylight performance. Proceed with installation only after

unsatisfactory conditions have been corrected.

3.3 Preparation

3.3.1 Prior to the start of fabrication, verify all field dimensions to ensure that new skylight frames will fit on

the existing curbs after roof flashings have been installed. Frames that pinch and/or damage new roofing

materials shall result in the replacement of skylight materials with new materials at no additional cost to

the owner.

3.3.2 Metal Protection: As follows:

3.3.2.1 Where aluminum will contact dissimilar metals, protect against galvanic action by painting

contact surfaces with primer or by applying sealant or tape recommended by manufacturer for

this purpose.

3.3.2.2 Where aluminum will contact concrete or masonry, protect against corrosion by painting contact

surfaces with bituminous paint.

3.3.2.3 Where aluminum will contact pressure-treated wood, separate dissimilar materials by methods

recommended by manufacturer.

Page 119: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Plastic Glazed Unit Skylights 08 62 00 4

3.3.3 Fabrication

3.3.3.1 Framing Components: As follows:

i Factory fit and assemble components.

ii Fabricate components that, when assembled, will have accurately fitted joints with

ends coped or mitered to produce hairline joints free of burrs and distortion.

iii Fabricate components to drain water passing joints and to drain condensation and

moisture occurring or migrating within skylight system to the exterior.

iv Fabricate components to accommodate expansion, contraction, and field adjustment,

and to provide for minimum clearance and shimming at skylight perimeter.

v Fabricate components to ensure that glazing is thermally and physically isolated from

framing members.

vi Form shapes with sharp profiles, strait and free of defects or deformations, before

finishing.

vii Fit and secure joints by heliarc welding.

3.4 Installation

3.4.1 General: Comply with manufacturer’s written instructions for protecting, handling, and installing skylight

components.

3.4.2 Coordinate with installation of substrates to receive skylight units.

3.4.3 Coordinate with installation of roof insulation, roofing, and flashing as required to assure that each

element of the work performs properly and that combined elements are waterproof and weather tight.

Anchor units securely to supporting structural substrates, adequate to withstand lateral and thermal

stresses as well as inward and outward loading pressures.

3.4.4 Counter Flashing: Where counter flashing is required as component of the skylight, install to provide an

adequate waterproof overlap with roofing or roof flashing (as counter flashing). Seal with thick bead of

mastic sealant, except where overlap is indicated to be left open for ventilation.

3.5 Cleaning and Protection

3.5.1 Clean exposed metal and plastic surfaces according to manufacturer’s instructions. Touch up damaged

metal coatings.

3.5.2 Clean plastic skylight units, inside and out, not more than 5 days prior to date of substantial completion.

END OF SECTION

Page 120: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Roof Drains 15 42 20 1

SECTION 15 42 20

ROOF DRAINS (UNIT PRICE #4)

PART 1 - GENERAL

1.1 Work Included:

1.1.1 Removal of existing roof drains and installation of new drains and 10’ minimum of drain piping. Drain

sizes shall match those of existing and piping shall match size and material (Unit Price #4).

1.2 Related Work

1.2.1 Roof Board Insulation – Section 07 22 16

1.2.2 Polyvinyl Chloride Roofing – Section 07 54 9

1.3 Submittals – Provide product data sheets for all materials and shop drawings with detailed drawings of drains,

fittings, and joints.

1.4 Environmental Conditions - Materials installation shall proceed only when weather conditions are in compliance

with the applicable manufacturer's recommendations for installation and no precipitation is imminent. Materials

installed during adverse weather conditions shall be subject to removal and replacement with new materials at no

additional cost to Owner.

PART 2 - PRODUCTS

2.1 Acceptable Manufacturers: Tech Specialties Company, Zurn, Josam and Smith.

2.2 Roof Drains - Shall be coating cast iron roof drain, having large cast iron locking dome, nonpuncturing clamp ring

with integral gravel stop, large sump with wide roof flange, bottom outlet no-hub connection, under deck clam

suitable for gypsum, sump receiver, and hardware packages included or equal. Provide adjustable extension

sleeves to accommodate specified insulation thickness. Drains shall also include new cast iron drain domes.

2.3 Drainage Pipe and Fittings:

2.3.1 PVC – Shall be solvent weld joint, schedule 40 PVC conforming to ASTM D-2665 include necessary

fittings. All PVC piping shall be Fire Wrapped.

2.3.2 Cast Iron – Shall be hubless cast iron pipe and fittings manufactured from gray cast iron and shall

conform to ASTM A888 and CISPI Standard 301 and shall be marked by the Cast Iron Soil Pipe Institute

and be listed by NSF International. Hubless couplings shall conform to CISPI Standard 310 and gaskets

shall conform to ASTM C564. All pipe and fittings shall be produced by a single manufacturer.

2.3.3 Insulation: Shall be 1-1/2” thick heavy density pre-formed fiberglass, single-seam pipe insulation with

self-sealing lap, conforming to ASTM C-547, Class 2, similar or equal to Certainteed 5000 degree, Snap

on pipe insulation.

2.3.4 Fire Wrap – Shall be aluminum foil fiberglass reinforced blanket encapsulating insulation, which is

specifically designed to provide a single layer, flexible enclosure around combustible items located

within a return air plenum. Its shall be ½” thick (min.), 8pcf, scrim encapsulated. It shall meet ASTM E-

136 for non-combustibility, ASTME-84/UL 723 Surface Burning Characteristics. Flame spread rating of

0 (unfaced blanket) and less than 25 (encapsulated). Smoke Developed Rating of 0 (unfaced blanket) and

Page 121: PROJECT MANUAL FOR JOHNSON ST. ELEMENTARY SCHOOL …

Raymond Johnson St. Elementary School

Roof Replacement

Project No. RAL1173.001

Roof Drains 15 42 20 2

less than 50 (encapsulated). Its core material shall be made from calcia, magnesia and silica chemistry.

Design Basis is FyreWrap by Unifrax I LLC.

2.3.5 Drain Flashing: Shall be 30-inch square, 4 pounds per square foot sheet lead.

2.3.6 Primer: Shall be asphaltic primer conforming to requirements of ASTM D-41.

2.3.7 Flashing/Roof Cement: Shall be Perflash by Performance Roof Systems, Inc.

2.3.8 Fire Rated Sealant – Sealant to be as recommended by the following manufacturers to provide a 1 hour

rated closure and shall meet AST E119 or UL 263. Use proper sealant joint design as required by the

sealant manufacturer. Suitable manufacturers are:

2.3.8.1 Hilti Corporation

2.3.8.2 Pecora Corporation

2.3.8.3 Tremco

2.3.8.4 DAP

2.3.9 Stainless Steel: Cold rolled, annealed, pickles, type 316L, with 2B finish conforming to ASTM A-240.

2.3.10 Fasteners – see Rough Carpentry Specification Section.

PART 3 - EXECUTION

3.1 Removal – All roof drains are to be removed and replaced. See Selective Demolition Specifications.

3.2 Installation:

3.2.1 Shorten or lengthen existing drain leaders as required to allow installation of a minimum of 10’ new drain

leader piping.

3.2.2 Remove and replace existing drain components with new drain components. Modify piping, as necessary.

3.2.3 Contractor shall install drain bowls and accessories.

3.2.4 Install new drains in accordance with membrane manufacturer’s recommendations and detail drawings in

the specifications.

3.2.5 Lead flashing sheets shall be set on finished roof membrane in a solid 1/8” thick bed of flashing cement

and top surface primed.

3.2.6 Strip in primed lead flashing sheets with an additional piece of membrane per detail drawings.

3.2.7 Bolt clamping ring in place on top of membrane stripping piece and lead flashing.

3.2.8 Drain bowls and riser pipe shall be insulated using pre-formed fiberglass insulation.

3.2.9 Piping shall be sealed with fire rated sealant at any location it penetrates a fire rated ceiling.

END OF SECTION