Click here to load reader
Upload
syed-khurram-iqbal
View
1.846
Download
0
Embed Size (px)
Citation preview
Building professionalism in project management.TM
A Framework forProject Management
The Project Management Institute
Education Department
Additional materialsA. Seminar Evaluation FormsB. ExercisesC. Resources for Project Management Professional Candidates
A Framework for Project Management Units
1. Introduction and Key Concepts6. Controlling Projects2. Project Life Cycle Models 7. Closing Projects3. Initiating Projects 8. Organizational Impacts4. Planning Projects 9. Overview of Knowledge Areas5. Executing Projects 10. Role of the Project Manager
UNIT 1:INTRODUCTION
AND KEY CONCEPTS
Unit 1: Introduction and Key Concepts
Upon completion, you will be able to …• Define key PM concepts• List the reasons why PM is needed• Explain the difference between projects and
operations• Identify trends in the PM environment• List project success and failure factors• Identify potential benefits of PM
Key PM Concepts from the PMBOK® Guide
This figure is a conceptual view of these re lationships. The overlaps shown are not proportional.
ApplicationArea Knowledge
and Practice
GeneralM anagem entKnowledge
and Practice
The ProjectManagement
Body of Knowledge
Generally A cceptedProject Managem ent
Knowledge and Practice
* Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
Why Do We Need Project Management?*
• Exponential expansion of human knowledge• Global demand for goods and services • Global competition • Above requires the use of teams versus
individuals
Project and Statement of Work (SOW)
• A project is “a temporary endeavor undertaken to create a unique product or service.”
• A SOW is a narrative description of products or services to be supplied under contract.
Project Management
“The application of knowledge, skills, tools and techniques
to project activities in order to meet or exceed stakeholder needs
and expectations from a project.”
PM EnvironmentDiscussion Question
• What are some trends that impact the environment in which projects are managed today?
Accelerating Trends
• Corporate globalization• Massive mergers and reorganizations• Flatter organizations• Short-term results driven
Accelerating Trends (continued)
• Team environment• Contract PM and outsourcing• Primacy of interpersonal skills• Multinational projects• Importance of cultural differences• Dependence on technology
A Balancing ActSchedule requirements cost
Source: William Gendron, presentation at 1998 PMI Global Forum
Business Objective
RiskRisk
The Project
Customer Expectation
A Balanced Project
Time Cost
Scope
Quality
BusinessObjectives
Expectation and Objective Congruency
Client/Customer ExpectationsLow High
Low OK
Customer wantsmore than theorganization
intends to provide.
HighBusiness needs
more from the project than the customer.
OK
Contrast Projects and Operations
Discussion Question
• How are “projects” different from “operations”?
Operations• Semi-permanent
charter, organization, and goals
• Maintains status quo• Standard product or
service• Homogeneous teams• Ongoing
Contrast Projects and Operations
Projects • Create own charter,
organization, and goals• Catalyst for change• Unique product or
service• Heterogeneous teams• Start and end date
Exercise 1-1PM Pitfalls and Pluses
• Looking back on projects with which you were associated, what were the top three factors that caused serious problems?
• That created a perception of success?
Common Pitfalls• Unclear objectives• Lack of senior management support• Lack of effective project integration • Inadequate funding• Change in business priorities• Original assumptions invalid• Ineffective team• Lack of effective communication processes• Other?
Source: NASA study, “Determination of Project Success,” 1974, by David C. Murphy, Bruce N. Baker, and Dalmar Fisher
Factors Affecting Project Success
• Coordination and relations• Adequacy of structure and control• Project uniqueness, importance, and public
exposure• Success criteria salience and consensus• Competitive and budgetary pressure• Initial over-optimism, conceptual difficulty• Internal capabilities buildup
Potential Benefits of PM for the Organization
• Improved control• Improved project support opportunities• Improved performance
Potential Benefits of PM for You
• Recognition of PM as a profession• Future source of company leaders • High visibility of project results • Growth opportunities • Build your reputation and network• Portable skills and experience
Integration Management
Cost Time
Integration
Quality
Summary• Defined key PM concepts• Described why PM is needed• Explained difference between projects
and operations• Identified trends in the PM environment• Discussed project success and failure
factors• Identified potential benefits of PM
UNIT 2:PROJECT LIFE
CYCLE MODELS
Unit 2: Project Life Cycle Models
Upon completion, you will be able to …• List the purpose and types of project life
cycle models• Distinguish between project and product life
cycle• Define the role of phase reviews in PM• Apply a model to a hypothetical and a real
project
Key Concepts • Project phase: “A collection of logically
related project activities usually culminating in the completion of a major deliverable.”
• Project life cycle: “Collectively the project phases are known as the project life cycle.”
• Product life cycle: The natural grouping of ideas, decisions, and actions into product phases, from product conception to operations to product phase-out.
Generic Cost and Staffing Life Cycle
Time
In itia lP hase
F in ishS ta rt
Inte rm ed ia te Phases(one or m ore)
F inalP hase
Cost andStaffing
Level
Project Life CycleExample Phases
Concept and Proposal
Development
Implementation
Termination
Verification
Final PhaseIntermediate PhasesInitial Phase
Pharmaceutical Project Life Cycle Model
Drug Sourcing
Discovery ScreeningPreclin icalDevelopm ent Registration(s) Workup Postsubm ission Activity
Patent Process
ScreeningLeadIdentified
Preclin icalINDWorkup
FileIND
FileNDA Postregistration Activity
Phase IClinicalTests
Phase IIClinical Tests
Phase IIIClinical Tests
APPROVAL
Formulation S tability
Process Development
Metabolism
Toxicology
Ten Plus Years
Construct
Spiral Methodology
Design
IdentifyEvaluate
Test
Evaluation
Evaluation
RiskAnalysis Business
Requirements
SystemRequirements
SubsystemRequirements
UnitRequirements
ConceptualDesign
LogicalDesign
PhysicalDesign
FinalDesign
Proof ofConcept
FirstBuild
SecondBuild
FinalBuild
Deploy Operations andProduction Support
Importance of Phase Reviews
Requirements Review
General Design Review
Detailed Design Review
Unit Test
Proposal Preparation
Requirements Analysis
General Design
Detailed Design
Code and Debug
Phase Initiation ExampleDetailed Design Phase
• Ensure correctness and completeness of previous phase, e.g., general design phase Assess all aspects of requirements, design approach, and deliverables Identify and work off items
• Determine contractor rewards/payment for closing phase
• Conduct a readiness review to begin next phase, e.g., detailed design phase Resource estimates and availability Design maturity Project plan review and update
• Secure stakeholder approval to proceed
Exercise 2-1Project Life Cycle Model
• Divide a current project on which you are working into phases, name them, and write a brief statement of purpose for each phase
Summary• Explained the concept and purpose of
project life cycles• Defined the role of phase reviews in PM• Described life cycle models• Differentiated project life cycle and
product life cycle• Applied a model to hypothetical and real
projects
UNIT 3:INITIATING PROJECTS
Unit 3: Initiating Projects
Upon completion, you will be able to …• List the main functions of each PM process
group• Describe the purpose of the initiation process • Identify its inputs and outputs, tools and techniques• Develop a sample project charter• Give an example of how process groups can apply
to the project as a whole or to a project phase
Process Definition
• “A series of actions people take to bring about a desired result.”
• Types of processes Project management processes Product-oriented processes Business-oriented processes
Initiating Processes
PlanningProcesses
ControllingProcesses Executing
Processes
ClosingProcesses
Commitment toexecuting project
Approach toexecuting project
Monitoring, measuring, andtaking corrective action
Coordinating people and
other resources
Formal productacceptance andend of project
Project Management Process Groups
Process Interactions
• Inputs• Tools and techniques• Outputs• Taxonomy
Process Group Overview
To the Planning Processes(Figure 3 – 5)
In itiating Processes
5 .1In it ia tio n
InitiationScope Initiation
1. Formal authorization that the project exists 2. Recognition the project should continue
into the next phase
Purpose of Initiation Process
1. To commit the organization to a project or phase
2. To set the overall solution direction 3. To define top-level project objectives4. To secure the necessary approvals and
resources5. Validate alignment with strategic objectives 6. To assign a project manager
Process OutputInput
Tools and Techniques
1. Product description2. Strategic plan3. Project selection criteria4. Historical information
“Initiation is the process of formally recognizing that a new project exists or that an existing project should continue into its next phase.”
1. Project charter2. Project manager identified/ assigned3. Constraints4. Assumptions
1. Project selection methods2. Expert judgment
Initiating Core Process—Initiation
Initiation
Inputs• Product description• Strategic plan• Selection criteria• Historical information
Tools• Project selection methods• Expert judgement
Outputs• Project charter• PM assigned• Constraints• Assumptions
Scope Initiation
Inputs• Product description – Documents characteristics of the
product or service and its relationship to a business need
• Strategic plan – Describes the organization’s mission, vision, and goals for the future, which the project supports
• Project selection criteria – Defined in terms of the product and covers the full range of management concerns
• Historical information – Results of previous project decisions and performance
Scope Initiation
Tools & Techniques• Project selection methods (Decision
models)– Benefit-measurement methods – Comparative
approaches; scoring models; benefit-contribution and economic models
– Constrained optimization methods – Mathematical models using linear, dynamic, integer, and multi-objective programming algorithms
• Expert judgment – Experts with specialized knowledge or training assess the inputs to this process
Scope Initiation
Outputs• Project charter • Project manager selected• Constraints – Factors that limit the project
management team’s options regarding scope, staffing, and schedule
• Assumptions – Factors that, for planning purposes, will be considered to be true, real, or certain
Scope Initiation
Project Charter
“A document issued by senior management that
provides the project manager with the authority to apply
organizational resources to project activities.”
Project Charter
• Formally recognizes the existence of a project
• Refers to the business need the project is addressing
• Describes the product to be delivered
• Gives the project manager the authority to apply resources to the project
Scope Initiation
Project Charter Content
• Business need• Project objectives• Project deliverables• Assumptions• Constraints• Key staff• Written authorization
Exercise 3-1Project Charter
• Using the handout, complete the sample project charter
• Assume you are the project manager• As an example, choose an anticipated
major project assignment
Sample Initiating Activities• Negotiate, write, and refine the project charter • Confirm how the project links to the business
need• Identify management responsibilities• Identify geographic locations involved• Test top-level objectives versus strategic
business plans• Make strategic procurement decisions, e.g.,
make, buy, or identify qualified vendors
Key Outputs of Initiation Process
• Project charter• Project manager identified/assigned• Other key positions identified/assigned• Constraints identified• Assumptions identified
UNIT 4:PLANNING PROJECTS
Unit 4: Planning ProjectsUpon completion, you will be able to …• Describe the purposes of the planning processes • Identify the inputs and outputs of core planning
processes• Describe the function and develop sample planning
deliverables such as a scope statement, WBS, and milestone chart
• List the major tools and techniques used in the core planning processes
• Identify the planning facilitating processes and their functions
Planning Process Group
InitiatingProcesses
PlanningProcesses
ControllingProcesses
ExecutingProcesses
ClosingProcesses
Initiating Processes
PlanningProcesses
ControllingProcesses Executing
Processes
ClosingProcesses
Commitment toexecuting project
Approach toexecuting project
Monitoring, measuring, andtaking corrective action
Coordinating people and
other resources
Formal productacceptance andend of project
Project Management Process Groups
Purpose of Planning Processes
To develop a project plan that:• Facilitates later accomplishment*• Ensures project wide integration• Monitors change effectively• Provides decision support information to
stakeholders• Can be updated by iterative planning activities
* Project Management—A Managerial Approach, 1995, by Jack R. Meredith and Samuel J. Mantel Jr.
Scope Planning
A written statement that includes:• Project justification, the major
deliverables, and the project objectives
• Criteria used to determine if the project or phase has been successfully completed
Process OutputInput
Tools and Techniques
1. Product description2. Project charter3. Constraints4. Assumptions
"… the process of developing a written scope statement as the basis for future project decisions including, in particular, the criteria used to determine if the project or phase has been completed successfully.”
1. Scope statement2. Supporting detail3. Scope management plan
1. Product analysis 2. Cost/Benefit analysis3. Alternative identification4. Expert judgment
Core Planning ProcessesScope Planning
Scope Planning
Inputs• Product description• Project charter• Constraints• Assumptions
Tools• Product analysis• Benefit/cost analysis• Alternatives identification• Expert judgment
Outputs• Scope statement• Supporting detail• Scope management
plan
Inputs• Product description – Contains the characteristics of
the product or service in which the project will result
• Project charter – Formally recognizes the existence of a project
• Constraints – Factors that limit the project management team’s options regarding scope, staffing, and schedule
• Assumptions – Factors that, for planning purposes, will be considered to be true, real, or certain
Scope Planning
Tools & Techniques• Product analysis – Techniques to develop a
better understanding of the product (e.g., systems engineering, value engineering, function analysis, quality function deployment)
• Benefit/cost analysis – Estimating the tangible and intangible costs (or outlays) and the benefits (or returns) of various project alternatives
• Alternative identification – Techniques used to generate different approaches to the project
(e.g., brainstorming and lateral thinking)• Expert judgment
Scope Planning
Outputs• Scope statement – Written statement of
project. It contains:– Project objectives – Project justification– Project deliverables
• Supporting detail – Supporting documentation containing identified requirements, plans, assumptions, and constraints
Scope Planning
Project Scope Statement Purpose
• To provide a general description of the sum of the products and services to be provided by the project
• To develop a common understanding of project scope among stakeholders
• May make explicit some exclusions that, based on the audience, would be assumed to be part of the project
Scope Management PlanGuidelines for how scope is to be managed and how scope changes are to be integrated into the project
Scope Planning
• It includes:• An assessment of the stability of the
project scope• A clear description of how scope
changes will be identified and classified
Exercise 4-1Scope Statement
• Using the handout in your manual, develop a project scope statement based on the project charter developed in the initiating process exercise
Tools and Techniques
1. Work breakdown structure templates
2. Decomposition
Process OutputInput
1. Scope statement2. Constraints3. Assumptions4. Other planning outputs5. Historical information
“… subdividing the major project deliverables (as identified in the scope statement) into smaller more manageable components … ”
1. Work breakdown structure
Core Planning ProcessesScope Definition
Scope Definition• Subdividing major project deliverables into
manageable components, in order to improve the accuracy of cost, time, and resources estimates
• Provides a baseline and assigns responsibility
• A scope baseline is the original plan, plus or minus approved changes
Scope Definition
Inputs• Scope statement• Constraints• Assumptions• Other planning inputs• Historical information
Tools• WBS templates• Decomposition
Outputs• Work
breakdown structure
• Scope Statement Update
Scope Definition
Inputs• Scope statement• Constraints• Assumptions• Other planning outputs – Outputs of the
processes in other knowledge areas should be reviewed for possible impact on project scope definition
• Historical information – About previous projects
Scope Definition
Tools & Techniques• WBS templates – Use a WBS from a previous
project or a standard template to develop a WBS for this project
• Decomposition – Subdividing major project deliverables into smaller, more manageable components until deliverables are defined in sufficient detail for supporting future project activities– Identify major elements of the project– For each element, decide if adequate cost and duration
estimates can be developed at this level of detail – Identify constituent elements (e.g., tangible, verifiable
results)– Verify the correctness of the decomposition – is it necessary
and is it sufficient for completion of the item decomposed
Scope Definition
Work Breakdown Structure (WBS)
• “A deliverable oriented grouping of project elements which organizes and defines the total scope of the project.
• Each descending level represents an increasingly detailed definition of a project component.
• Project components may be products or services.”
WBS Definition
Deliverable oriented grouping of project elements that
organizes and defines the total scope of the project
Hardware Services Data
Scope Definition
WBS Purpose• To define:
Solution strategy or general approach Implementation tactics
• To support more accurate estimates of project duration and cost than can be made at the project level
• To provide a basis for estimating project resources: Departmental or subcontractor support Vendors and their products Services Any other identifiable resource
Typical WBS
ProjectPlanning
1.1.1
ProjectControl
1.1.2
ProjectData
1.1.3
ProjectManagement1.1
ProductDesign
1.2.1
SystemsIntegration
1.2.2
Test &Evaluation
1.2.3
SystemsEngineering
1.2
CPUAcquisition
1.3.1
AuxiliaryEquipment
1.3.2
PrinterAcquisition
1.3.3
HardwareAcquisition
1.3
OperatingSystem
1.4.1
Database1.4.2
ApplicationDevelopment1.4.3
SoftwareDevelopment1.4
FacilityPlans
1.5.1
FacilityModification1.5.2
FacilityInstallation
1.5.3
FacilitiesModifications1.5
TrainingPlans
1.6.1
TrainingCourses
1.6.2
TrainingDevelopment1.6
InformationSystem
1.
Scope Definition
Responsibility Assignment Matrix
Scope Definition
WorkWorkBreakdownBreakdown
WorkWorkPackagesPackages
&&PlanningPlanningPackagesPackages
Functional FunctionalOrganizationOrganization
Validate Your WBS• All major elements been identified at top level?• Decomposed into measurable components?• Lower level(s) items necessary? All inclusive?• Would stakeholders agree WBS is satisfactory?• Can elements be scheduled, budgeted, and
assigned to a unit that will accept responsibility?• Too much or too little visibility and control ?• Can status reports be generated at all levels?
Using the WBS to Estimate Cost
• Project manager establishes work requirements by defining the What—“shalls” and “wills” When—sequence Why—dependencies
• Functional managers estimate cost by determining How—equipment and methods Who—type and level of expertise Where—location, department
WBS• Code of accounts – Uniquely identifies each
element of the WBS
• Work packages – A deliverable at the lowest level of the WBS
• WBS dictionary – Includes work-package descriptions
Scope Definition
Outputs• Work breakdown structure• Scope Statement Update
Exercise 4-2Work Breakdown Structure
• Using “Post-it® Notes,” construct a WBS for your project or subproject
• Apply the WBS validation criteria• Discuss any learning or insights with a
classmate, including any learning from applying the WBS test criteria
Activity Definition• Identify the activities that must be
performed to produce the project deliverables
• Define the activities that must be performed to meet the project objectives
Process OutputInput
Tools and Techniques
1. WBS2. Scope statement 3. Historical information4. Constraints5. Assumptions6. Expert Judgment
“Identifying the specific activities that must be performed to produce the various project deliverables.”
1. Activity list2. Supporting detail3. WBS updates
1. Decomposition2. Templates
Core Planning ProcessesActivity Definition
Activity Definition
Inputs• WBS• Scope statement• Historical information• Constraints• Assumptions• Expert Judgment
Tools & Techniques• Decomposition• Templates
Outputs• Activity list• Supporting detail• WBS updates
Inputs• WBS – Primary input to activity definition• Scope statement – Project justification and project
objectives • Historical information – The activities that were actually
required on previous, similar projects• Constraints – Factors that will limit the PM team’s
options• Assumptions – Factors that, for planning purposes, will
be considered to be true, real, or certain• Expert Judgment
Activity Definition
Tools & Techniques• Decomposition – Subdividing project
activities into smaller, more manageable components
• Template – An activity list from a previous project or an activity list for a WBS element from the current project
Activity Definition
Outputs• Activity list – A list of all the activities that
will be performed on the project and a description of each
• Supporting detail – Documentation that contributes to the process, including all identified assumptions and constraints
• WBS updates – Refinements to the existing WBS
Activity Definition
Activity Sequencing
Establishing the activity logic and the dependencies needed to create a realistic and achievable schedule
Process OutputInput
Tools and Techniques
1. Activity list2. Product description3. Mandatory dependencies4. Discretionary dependencies5. External dependencies6. Milestones
“… identifying and documenting interactivity dependencies.”
1. Project network diagrams2. Activity list updates
1. Precedence diagramming method (PDM)
2. Arrow diagramming method (ADM)
3. Conditional diagramming method
4. Network templates
Core Planning ProcessesActivity Sequencing
Activity Sequencing
Inputs• Activity list• Product description• Mandatory dependencies• Discretionary dependencies• External dependencies• Milestones
Tools & Techniques• Precedence diagramming
method (PDM)• Arrow diagramming
method (ADM)• Conditional diagramming
methods• Network templates
Outputs• Project network diagram• Activity list updates
Inputs• Activity list• Product description – Product characteristics
affect activity sequencing• Mandatory dependencies (Hard logic) –
Determined by the qualities of work to be done• Discretionary dependencies (Soft logic) –
Defined by the project management team• External dependencies – Relationships
between project activities and non-project activities
• Milestones
Activity Sequencing
Tools & Techniques• Precedence diagramming method
(PDM) – Nodes represent activities and arrows
show dependencies
Activity Sequencing
Start Finish
A
C D
E
B
Precedence Diagramming Method
Activity Sequencing Process
Activity Sequencing
Finish-to-Start – Activity A must finish before Activity B can start
A B
Start-to-Start – Activity A must start before Activity B can start
A B
Activity Sequencing Process
Activity Sequencing
Finish-to-Finish – Activity A must finish before Activity B can finish
A B
Start-to-Finish – Activity A must start before Activity B can finish
A B
Tools and Techniques (cont.)• Arrow diagramming method (ADM) – Uses
arrows to represent activities and connecting nodes to show dependencies
Activity Sequencing
AB
CD
Start
FinishE
• ADM uses finish-to-start dependencies only and uses dummy activities to show logical relationships
Arrow Diagramming Method
Tools & Techniques (cont.)• Conditional diagramming methods –
Diagramming techniques such as Graphical Evaluation and Review Technique (GERT) and System Dynamics models allow the depiction of non-sequential activities and conditional branches
• Network templates – Can include an entire project or just a portion of it (i.e., subnets and fragnets)
Activity Sequencing
Outputs
• Project network diagram – Schematic display of project’s activities and dependencies
• Activity list updates – Dividing or redefining activities so that the relationships are correctly diagrammed
Activity Sequencing
Activity Duration Estimating
Estimating the number of work periods likely to be needed to complete each activity
• Elapsed time (Delay) – Work periods between the finish of one activity and the start of another activity
Process OutputInput
Tools and Techniques
1. Activity lists2. Constraints3. Assumptions4. Resource requirements5. Resource capabilities6. Historical information7. Identified risks
“… assessing the number of work periods likely to be needed to complete each identified activity.”
1. Activity duration2. Basis of estimates3. Activity list updates
1. Expert judgment2. Analogous estimating3. Quantitatively based durations4. Reserve time (contingency)
Core Planning ProcessesActivity Duration Estimating
Activity Duration Estimating
Inputs• Activity list• Constraints• Assumptions• Resource requirements• Resource capabilities• Historical information• Identified Risks
Tools & Techniques• Expert judgment• Analogous estimating• Quantitatively based durations• Reserve time (contingency)
Outputs• Activity duration estimates• Basis of estimates• Activity list updates
Inputs• Activity list• Constraints• Assumptions• Resource requirements – Duration estimates are
influenced by resource effort and assignments• Resource capabilities – Duration estimates are
influenced by the capability of the people and the material resources assigned to them
• Historical Information– Project files– Commercial duration estimating databases– Project team knowledge
• Identified Risks
Activity Duration Estimating
Tools & Techniques
• Expert judgment – Used with historical information
• Analogous estimates (Top-down estimating) – Uses duration of a previous, similar activity as the basis for the of estimate of a future activity
• Quantitatively based durations• Reserve time (contingency)
Activity Duration Estimating
Outputs• Duration estimates – Quantitative
assessments of the likely number of work periods required to complete an activity
• Basis of estimate – Documentation of the assumptions used for developing the estimates
• Activity list updates
Activity Duration Estimating
Schedule Purpose
• Converts the project plan to an operating plan that is the basic tool for controlling project activitiesBenefits of a realistic schedule?
Benefits of a Realistic Schedule
• Framework for managing critical project activities• Determines planned start and completion dates• Identifies activity and task precedence
relationships• Aids project team in defining critical
communication content • Specifies times when staff must be available• No surprises• Other?
Key Scheduling Definitions
• Network• Network techniques• Path• Node• Arc• Event• Activity
Scheduling TechniquesActivity on Arrow Example
Start A
D
B
E
C
F Fin ish
Work
Activity 2
Set up
Activity 1
Finish
Activity 3
Result 1
Result 2 Result 3
Network Techniques AOA Example
• Activities specified on arrows• Also called arrow diagramming method
(ADM)• Nodes show relationship
Scheduling TechniquesActivity on Node
• Activity on node network format Arrows show precedence relationships Nodes show activities
• 3 types of precedence relationships Activity on node 1—successor but no
predecessor Activity on node 2—predecessor and successor Activity on node 3—predecessor but no
successor
Task BTask A
Precedence RelationshipsFinish to Start
The “from” activity Task A must finish before
the “to” activity Task B can start
Precedence RelationshipsStart to Start
The direction of the arrow defines which task is the predecessor and which is the successor.
Tasks A and B may start at the same time, but the successor (B) cannot start until the predecessor (A) begins.
Task B
Task A
Precedence RelationshipsFinish to Finish
Tasks A and B may end at the same time, but the successor (B) cannot finish until the predecessor (A) finishes
Task B
Task A
Precedence RelationshipsStart to Finish
Task A must start before Task B can finish (seldom used).
Task B
Task A
PDM ExampleDiverging-Converging
ActivitiesDiverging
ActivitiesMultiple predecessors with single successor
Single predecessor with multiple successors
Paint Ceiling
Prep
Paint Trim
Clean-upPaint Walls(2nd coat)
Paint Walls
Converging Activities
Forward Pass Definitions• Early Start Date (ES)
Earliest possible point in time an activity can start, based on the network logic and any schedule constraints
• Duration (DU) Number of work periods, excluding holidays or other nonworking
periods, required to complete the activity; expressed as workdays or workweeks
• Early Finish Date (EF) Earliest possible time the activity can finish
• Forward Pass Starting at the beginning (left) of the network develop early start
and early finish dates for each task, progressing to end (right-most box) of the network
Forward Pass Calculation
EF = ES + DU – 1
DU = 4Paint Walls
DU = 3Paint Ceiling
DU = 2Paint Trim
DU = 2Paint Walls (2nd Coat)
DU = 2Prep
DU = 2Clean-up
1 2
3 4
3 5
3 6 7 8
9 10
DU
TaskFloat
ES
LS
EF
LF
Name Duration ES EF
Prep 2 1 2
Paint Trim 2 3 4
Paint Ceiling 3 3 5
Paint Walls 4 3 6
Paint Walls (2nd Coat) 2 7 8
Clean-up 2 9 10
Task Identification Forward Pass
Backward Pass Definitions• Late Start Date (LS)
Latest point in time that an activity may begin without delaying that activity’s successor
If the activity is on the critical path, the project end date will be affected• Float or Slack
Latest point in time a task may be delayed from its earliest start date without delaying the project finish date
• Late Finish (LF) Latest point in time a task may be completed without delaying that
activity’s successor If the activity is on the critical path, the project end date will be affected
• Backward Pass Calculate late start and late finish dates by starting at project
completion, using finish times and working backwards
Backward Pass Calculation
Name Duration ES EF LS LF Float
Prep 2 1 2 1 2 0
Paint Trim 2 3 4 7 8 4
Paint Ceiling 3 3 5 6 8 3
Paint Walls 4 3 6 3 6 0
Paint Walls (2nd Coat) 2 7 8 7 8 0
Clean-up 2 9 10 9 10 0
Task IdentificationForward and Backward
Passes
Scheduling TechniquesBar/Gantt Chart
Activ ity A
Activ ity B
Activ ity C
Activ ity D
Jun
Tim e
Jul Aug Sep O ct Nov
There are m any other acceptable ways to d isp lay pro ject inform ation on a bar chart.
Schedule Development
Determining the start and finish dates of project activities
• If start and finish dates are not realistic, the project is unlikely to be finished on schedule
Process OutputInput
Tools and Techniques
1. Project network diagram2. Activity duration estimates3. Resource requirements4. Resource pool description5. Calendars6. Constraints7. Assumptions8. Leads and lags9. Risk management plan10. Activity attributes
“… determining startand finish dates forproject activities.”
1. Project schedule2. Supporting detail3. Schedule management plan4. Resource requirements
updates
1. Mathematical analysis2. Duration compression3. Simulation4. Resource leveling
heuristics5. Project management
software6. Coding structure
Core Planning ProcessesSchedule Development
Schedule Development
Inputs• Project network diagram• Activity duration estimates• Resource requirements• Resource-pool description• Calendars• Constraints• Assumptions• Leads and lags• Risk Management Plan• Activity Attributes
Tools & Techniques• Mathematical analysis• Duration compression• Simulation• Resource-leveling heuristics• Project management software• Coding structure
Outputs• Project schedule• Supporting detail• Schedule management plan• Resource-requirement updates
Inputs• Project network diagram• Duration estimates• Resource requirements• Resource pool – Description of the available
resources and the times they are available to work on the project
• Calendars – Identify periods when work is allowed– Project calendars: Affect all resources– Resource calendars: Affect specific resources or
categories of resources
Schedule Development
Inputs
• Constraints– Imposed dates– Key events or milestones
• Assumptions• Leads and lags – Dependencies that
require lead or lag values to accurately define the relationship
• Risk Management Plan• Activity Attributes
Schedule Development
Tools & Techniques• Mathematical analysis – Calculating
theoretical early and late start and finish dates for all activities
– Critical Path Method (CPM) – Calculates a single, deterministic early and late start and finish date for each activity, to be used to determine which activities must be completed on time to avoid impacting the finish date of the project
– Graphical Evaluation and Review Technique (GERT) – Allows for loops in the relationships between activities and for the conditional and probabilistic treatment of relationships
Schedule Development
Tools & Techniques (cont.)
• Mathematical Analysis (cont.)– Program Evaluation and Review Technique
(PERT) – Uses sequential network logic and a weighted-average duration estimate to calculate duration. Uses the probability of an estimate’s accuracy.
Schedule Development
PERT Calculations
• PERT – Program Evaluation and Review Technique
• Expected Time = (Low + 4*Medium + High) / 6
• Standard Deviation = (High – Low) / 6
Schedule Development
PERT Example
Evening CommuteOptimistic time = 15 minutesMost likely time = 30 minutesPessimistic time = 60 minutes
What is the Expected Time?
Schedule Development
Tools & Techniques (cont.)– Duration compression – Looks for ways to shorten
the schedule without changing the project scope
– Simulation
– Resource-leveling heuristics (Resource-based method) – Changing the schedule to accommodate resources
– PM Software – Used to assist schedule development and to display schedule-development outputs
– Coding Structure
Schedule Development
Outputs• Project schedule – Includes planned start and
expected finish dates for each activity
• Supporting detail – Documentation of all identified assumptions and constraints
• Schedule management plan – Defines how changes to the schedule will be managed
• Resource requirement updates – Updates based on the results of resource leveling and on updates to activity lists
Schedule Development
Network Calculation
CalculationsForward Pass – Determine early start and early finish datesBackward Pass – Determine late start and late finish dates and float
0
A
B
C
D E5
5
10
10 5
Start Date 6/1
6/1 6/5
6/6 6/15
6/6 6/10
6/16 6/25 6/26 6/30
Finish Date 6/30
6/26 6/306/16 6/25
6/6 6/15
6/1 6/5
6/11 6/15
5
0 0 0
Schedule Development
• Total float (Slack) – Amount of time an activity can be delayed and the project finish date not be effected
• Free Float – Amount of time an activity can be delayed and the early start of the follow-on activity not be effected
Basic TerminologySchedule Development
Gantt Charts• Bar chart – Displays activity start and end
dates, as well as expected durations
• Milestone chart – Displays scheduled start or completion of major deliverables
• Combination chart – Displays events and activities as a function of time
Schedule Development
Typical Gantt Chart
Time
ActivityTask A
Task B
Task C
Task DJune July Aug Sep Oct Nov
Schedule Development
Key Scheduling Concepts
• Master schedule• Crashing• Hanger• Workaround• Schedule variance
Milestone Chart
Exercise 4-3 Project Milestones
• Identify the major milestones in your project
Resource Planning
Determining physical resources needed (i.e., material, equipment, and people) and number of resources required to perform the project activities
Process OutputInput
Tools and Techniques
1. WBS2. Historical information3. Scope statement4. Resource pool description5. Organizational policies6. Activity Duration Estimates
“… determining whatphysical resources(people, equipment,materials) and whatquantities of each shouldbe used to performproject activities.”
1. Resource requirements
1. Expert judgment2. Alternatives identification3. Project management software
Core Planning ProcessesResource Planning
Resource Planning
Inputs • WBS• Historical information• Scope statement• Resource pool description• Organizational policies• Activity Duration Estimates
Tools & Techniques• Expert judgment• Alternatives identification• Project management software
Outputs• Resource requirements
Inputs• Work breakdown structure (WBS) – Identifies the project
elements that require resources • Historical information – Used to identify the types of
resources that were required for similar work on previous projects
• Scope statement – Contains project justification and the project objectives, which need to be considered
• Resource pool description – Description of resources available, if necessary, to work on a project
• Organizational policies – Of the performing organization, regarding staffing and the rental and purchase of supplies and equipment
• Activity Duration Estimates
Resource Planning
Tools & Techniques• Expert judgment – Expertise, provided
by any group or individual, used to assess the inputs to this process– Other units within organization– Consultants– Professional and technical associations– Industry groups
• Alternatives identification• Project management software
Resource Planning
Outputs
Resource requirements – Description of the types (e.g., skill levels) and numbers of resources required by each element of the WBS
Resource Planning
Cost Estimating
• Difference between cost estimating and pricing:– Cost estimating: Assessing how much it will cost the
organization to provide the product or service– Pricing: Assessing how much the organization will charge for
the product or service
• Cost estimating also includes identifying and considering cost alternatives
Process of developing an approximation (or estimate) for the cost of the resources necessary to complete the project activities
Process OutputInput
Tools and Techniques
1. WBS2. Resource requirements3. Resource rates4. Activity duration estimates5. Estimating Publications6. Historical information7. Chart of accounts8. Risks
“… developing an approximation (estimate of the costs of the resources needed to complete project activities.”
1. Cost estimates2. Supporting detail3. Cost management plan
1. Analogous estimating2. Parametric modeling3. Bottom-up estimating4. Computerized tools5. Other cost estimating methods
Core Planning Processes Cost Estimating
Cost Estimating
Inputs • WBS• Resource requirements• Resource rates• Activity duration estimates• Estimating Publications• Historical information• Chart of accounts• Risks
Tools & Techniques• Analogous estimating• Parametric modeling• Bottom-up estimating• Computerized tools• Other cost estimating methods
Outputs• Cost estimates• Supporting detail• Cost management plan
Inputs• WBS – Used to organize the cost estimates and to ensure that the cost of all
identified work has been estimated• Resource requirements • Resource rates – Unit rates for each resource • Activity duration estimates – Affects cost estimates if project budget
includes an allowance for the cost of financing (i.e., interest)• Historical Information – Information on the cost of resources
– Project files – Records of previous project results that are detailed enough to aid in developing cost estimates
– Commercial cost-estimating databases – Historical information available commercially
– Project team knowledge• Estimating Publications• Chart of accounts – Coding structure used by the organization to report
financial information. Cost estimates must be assigned to the correct accounting category.
• Risks
Cost Estimating
Tools & Techniques• Analogous estimating (Expert judgment) – Used to
estimate total project costs if there is a limited amount of detailed information
• Parametric modeling – Using project characteristics (or parameters) in a mathematical model to predict costs (e.g., price per square foot)
• Bottom-up estimating – Estimating the cost of individual work items and then rolling up the costs to arrive at a project total
• Computerized tools – PM software and spreadsheets• Other Cost Estimating Methods
Cost Estimating
Outputs• Cost estimates – Quantitative assessments of the cost of
resources (e.g., units of currency or staff hours) • Types of estimates
– Order of magnitude (-25% / +75%)– Budget estimate (-10% / +25%)– Definitive estimate (-5% / +10%)
• Supporting detail– Description of estimated scope of work– Documentation of the basis for the estimate– Documentation of any assumptions made– Range of possible results
Cost Estimating
Outputs (cont.)
• Cost management plan– Describes how cost variances will be
managed
– Part of the overall project plan
Cost Estimating
Cost Budgeting
Allocating the value of the overall cost estimate to individual work items, in order to establish a cost baseline to use in measuring project performance
Process OutputInput
Tools and Techniques
1. Cost estimates2. WBS3. Project schedule4. Risk management plan
“… allocating the overall cost estimates to individual work items in order to establish a cost baseline for measuring project performance.”
1. Cost baseline
1. Cost budgeting Tools & Techniques
Core Planning ProcessesCost Budgeting
Cost Budgeting
Inputs • Cost estimates• WBS• Project schedule• Risk management plan
Tools & Techniques• Cost-estimating
tools and techniques
Outputs• Cost baseline
Inputs• Cost estimates • WBS – Identifies the project elements to
which the costs will be allocated• Project schedule – Used to assign costs to
project elements for the time period when costs will be incurred
• Risk Management Plan
Cost Budgeting
Tools & Techniques
• Cost estimating tools and techniques–Analogous estimating–Parametric modeling–Bottom-up estimating–Computerized tools
Cost Budgeting
OutputsCost baseline – Time phased budget that will be used to measure and monitor the cost performance of the project
Cost Budgeting
0
20
40
60
80
100
120
140
Jan Feb Mar Apr May Jun
Reporting Period
BCW
S ($
K)
Project Plan Development
Taking the results of other planning processes and putting them into a
consistent, coherent document
Process OutputInput
Tools and Techniques
1. Other planning outputs2. Historical information3. Organizational policies4. Constraints5. Assumptions
“… taking the results of other planning processes and putting them into a consistent, coherent document.”
1. Project plan2. Supporting detail
1. Project planning methodology
2. Stakeholder’s skills and knowledge
3. Project management information systems
4. Earned value management (EVM)
Core Planning ProcessesProject Plan Development
Project Plan Development
Inputs• Other planning outputs• Historical information• Organizational policies• Constraints• Assumptions
Tools & Techniques• Project planning
methodology• Stakeholder skills
and knowledge• Project management
information system• Earned value management
Outputs• Project plan• Supporting detail
Inputs• Other planning outputs from the other knowledge
areas – They include base documents, as well as the supporting detail
• Historical information – Estimating databases and records of past project performance
• Organizational policies – Any and all of the organization’s formal and informal policies. These include QM process audits, continuous-improvement targets, personnel-hiring and -firing guidelines, employee-performance reviews, and financial controls
• Constraints – Any factors that will limit the project team’s options• Assumptions – Factors that, for planning purposes, will be
considered to be true, real, or certain
Project Plan Development
Tools & Techniques• Project planning methodology – Structured
approach used to guide the development of the project plan
• Stakeholder skills and knowledge – Create an environment in which stakeholders can contribute appropriately
• Project management information system – Consists of the automated and manual tools and techniques used to gather, integrate, and disseminate information and outputs from other PM processes
• Earned Value Management
Project Plan Development
Outputs
• Project plan – The formal, approved document used to manage and control project execution
• Supporting detail– Outputs from other planning processes– Additional information or documentation generated
during development of the project plan– Technical documentation– Documentation of relevant standards
Project Plan Development
Project Plan• Includes:
– Project charter– PM approach or strategy– Scope statement– Work breakdown structure (WBS)– Cost estimates– Schedule– Performance measurement baselines– Major milestones and target dates– Key or required staff– Key risks– Open issues and pending decisions
Project Plan Development
Facilitating Planning Processes
• Quality planning• Communications planning• Organizational planning• Staff acquisition• Procurement planning• Solicitation planning• Risk identification• Qualitative risk analysis• Quantitative risk analysis• Risk response planning
Facilitating Planning Processes
Sample Planning Activities• Subdividing deliverables into manageable
components• Allocating overall cost estimate to individual
work items• Identifying the specific activities people must
perform to produce the project deliverables• Identifying the sequence and duration of
activities• Determining project roles and responsibilities• Other?
Key Outputs of Planning Processes
The Project Plann Schedules n Cost management plann Budgets n Cost baselinen Risk management plan n Scope statementn Quality plan n Work breakdown structuren Staffing plan n Plan updatesn Procurement plan n Resource requirementsn Schedule management plan n Communications plan
UNIT 5:EXECUTING PROJECTS
Unit 5: Executing Projects
Upon completion, you will be able to …• Describe the purposes of the executing
processes • Identify the inputs and outputs of its core
processes• List the major tools and techniques
Initiating Processes
PlanningProcesses
ControllingProcesses Executing
Processes
ClosingProcesses
Commitment toexecuting project
Approach toexecuting project
Monitoring, measuring, andtaking corrective action
Coordinating people and
other resources
Formal productacceptance andend of project
Project Management Process Groups
Purpose
• To coordinate, integrate, and manage all resources
Why?• in order to achieve the project objectives
How?• by carrying out the letter and intent of the project plan
While • responding to change and mitigating risks
Project Plan Execution
Carrying out the project plan by performing activities identified in the
document
Process OutputInput
Tools and Techniques
1. Project plan2. Supporting detail3. Organizational policies4. Preventive action5. Corrective action
“… the primary process for carrying out the project plan.”
1. Work results2. Change requests
1. General management skills2. Product skills and knowledge3. Work authorization system4. Status review meetings5. Project management
information system6. Organizational procedures
Core Execution ProcessProject Plan Execution
Project Plan Execution
Inputs• Project plan• Supporting detail• Organizational
policies• Preventive action• Corrective action
Tools & Techniques• General management skills• Product skills and
knowledge• Work-authorization system• Status review meetings• PM information system• Organizational procedures
Outputs• Work results• Change requests
Inputs
• Project plan• Supporting detail• Organizational policies• Preventive action• Corrective action
– Anything done to bring future performance in line with the project plan
– Output of the various control processes
Project Plan Execution
Tools & Techniques• General management skills – Leadership,
communication, negotiation skills, etc.• Product skills and knowledge – Skills are part of
resource-planning and staff-acquisition processes• Work-authorization system – Formal procedure for
approving project work; source of written authorization to begin work on a specific activity or work package
• Status-review meetings – Regularly scheduled meetings to exchange information about the project
• Project management information system• Organizational procedures – Both formal and informal
procedures that might be useful during project execution
Project Plan Execution
Outputs
• Work results – Outcomes of activities performed in order to accomplish the project; fed into the performance reporting process
• Change request – A request to expand or contract project scope, budget, schedule, or resources
Project Plan Execution
Facilitating Execution Processes
• Quality assurance• Team development• Information distribution• Solicitation• Source selection• Contract administration
Facilitating Execution Processes
Sample Executing Activities• Managing work results and requests for
change• Using tools and techniques in project plan
implementation• Building effective relationships with vendors
and project team members• Choosing from potential sellers• Distributing status information in time for
stakeholders to act• Other?
UNIT 6:CONTROLLING
PROJECTS
Unit 6: Controlling Projects
Upon completion, you will be able to …• Describe the purposes of the controlling
processes • Identify the inputs and outputs of the core
controlling processes• List and define the major tools and
techniques
Initiating Processes
PlanningProcesses
ControllingProcesses Executing
Processes
ClosingProcesses
Commitment toexecuting project
Approach toexecuting project
Monitoring, measuring, andtaking corrective action
Coordinating people and
other resources
Formal productacceptance andend of project
Project Management Process Groups
PurposeTo keep the project on track in order to achieve its objectives as outlined in the project plan by:
• Monitoring and reporting variances • Controlling scope changes• Controlling schedule changes• Controlling costs• Controlling quality• Responding to risks
Overview
Performance Reporting
• This includes status reporting, progress measurement, and forecasting
• Provides information on scope, schedule, cost, and quality, and possibly on risk and procurement
Collecting and disseminating performance information
Process OutputInput
Tools and Techniques
1. Project plan2. Work results3. Other project records
“… collecting and disseminating performance information. This includes status reporting, progress measurements, and forecasting.”
1. Performance reports2. Change requests
1. Performance reviews2. Variance analysis3. Trend analysis4. Earned value analysis5. Information distribution
systems
Core Controlling ProcessesPerformance Reporting
Inputs• Project plan – Contains the various
baselines used to assess project performance
• Work results – Accurate information on project status, such as information about fully, or partially, completed tasks and costs incurred or committed
• Other project records – Any information pertaining to the project context
Performance Reporting
Tools & Techniques• Performance reviews – Meetings held to
assess project status or progress• Variance analysis – Comparing actual project
results to planned or expected results• Trend analysis – Examining project results over
time to determine if performance is improving or deteriorating
• Earned-value analysis – Integrating scope, cost, and schedule measures to assess project performance
• Information-distribution tools and techniques
Performance Reporting
Outputs• Performance report – Organizes and
summarizes the information gathered and presents the results of any analysis. Reports should provide the kinds of information and the level of detail required by various stakeholders and documented in the communications management plan
• Change requests – Requests for changes to some aspect of the project
Performance Reporting
Overall Change Control
Coordinating changes across the entire project
Process OutputInput
Tools and Techniques
Core Controlling ProcessesOverall Change Control
1. Project plan2. Performance reports3. Change requests
1. Change control system2. Configuration management3. Performance measurement4. Additional planning5. Project management
information systems
1. Project plan updates2. Corrective action3. Lessons learned
“Overall change control is concerned with: (a) influencing the factors which
create change to ensure thatchanges are beneficial,
(b) determining that a change has occurred, and
(c) managing the actual changewhen and as they occur.”
Overall Change Control
Inputs• Project plan• Performance
reports• Change requests
Tools & Techniques• Change control system• Configuration management• Performance measurement• Additional planning• PM information system
Outputs• Project plan updates• Corrective action• Lessons learned
Overall Change Control• Concerned with:
– Influencing the factors which create change, in order to ensure that the changes are beneficial
– Determining that a change has occurred– Managing the actual changes
• Requirements:– Reflect all approved changes in the project plan– Reflect changes in the project scope definition. Project
scope changes affect the performance measurement baseline.
– Coordinate changes across all knowledge areas
Inputs
• Project plan – Provides the baseline against which changes will be controlled
• Performance reports – May alert the project team to issues which could cause problems in the future
• Change requests – May occur in many forms: oral or written, direct or indirect, externally- or internally-initiated, legally-mandated or optional
Overall Change Control
Tools & Techniques• Change control system – A collection of formal,
documented procedures that define the steps for changing official project documents
• Configuration management – Provides documented procedures for:– Identifying and documenting the functional and physical
characteristics of an item or a system– Controlling any changes to identified characteristics– Recording and reporting both the change and its status– Auditing the configuration items and systems to verify
conformance to requirements
Overall Change Control
Tools & Techniques (cont.)
• Performance measurements – Help assess whether variances from the plan require corrective action
• Additional planning – Changes may require new or revised plans in other knowledge areas
• Project management information system (PMIS)
Overall Change Control
Outputs
• Project plan updates – Any modifications to the contents of the project plan or to supporting detail
• Corrective action
• Lesson learned – The causes of variances, the reasoning behind the corrective action chosen, and other types of lessons learned should be documented
Overall Change Control
Facilitating Controlling Processes
• Scope Verification• Scope change control• Quality control• Schedule control• Cost control• Risk response control
Facilitating Controlling Processes
Process OutputInput
Tools and Techniques
1. Risk management plan2. Actual risk events3. Additional risk identification
Facilitating Controlling ProcessesRisk Monitoring & Control
1. Workarounds2. Additional risk response
development
1. Corrective action2. Updates to the risk
management plan
“… involves executing the Risk Management Plan in order to respond to risk events over the course of the project.”
Key Cost ConceptEarned Value• A method for measuring project
performance• The budgeted cost of work performed for
an activity or group of activities• Compares the planned amount of work
with the accomplished amount of work to determine if cost and scheduled performance is as planned
Controlling Activities
• Reporting status versus plan and forecasting
• Responding to changes in risk • Completing and settling the contract,
including resolving of any open items• Identifying and reporting schedule slips• Determining whether schedule updates
require plan modifications• Other?
UNIT 7:CLOSING
PROJECTS
Unit 7: Closing Projects
Upon completion, you will be able to … • Describe the purposes of closing
processes • Identify the inputs and outputs of the core
processes• List the major tools and techniques
Initiating Processes
PlanningProcesses
ControllingProcesses Executing
Processes
ClosingProcesses
Commitment toexecuting project
Approach toexecuting project
Monitoring, measuring, andtaking corrective action
Coordinating people and
other resources
Formal productacceptance andend of project
Project Management Process Groups
Purpose
Formalizing acceptance of the project and bringing it to an orderly end by:
• Closing the contract • Achieving administrative closure
Overview
Contract Close Out
• Involves product verification and administrative closeout
Completion and settlement of the contract, including resolution of any open items
Process OutputInput
Tools and Techniques
1. Contract documentation “… involves both product verification (was all work completed correctly and satisfactorily) and administrative close-out (updating of records to reflect final results and archiving of such information for future use.”
1. Contract file2. Formal acceptance and
closure
1. Procurement audits
Core Closing ProcessesContract Close-out
InputsContract documentation – Includes, but not limited to:• Contract• Supporting schedules• Requested and approved contract changes• Seller-developed technical documentation• Seller performance reports• Financial documents (e.g., invoices and payment
records)• Results of any contract-related inspections
Contract Closeout
Tools & Techniques
Procurement audits –Structured reviews of the procurement process, from procurement planning through contract administration, conducted to identify successes and failures (lessons learned)
Contract Closeout
Outputs• Contract file – Set of indexed records,
prepared for inclusion with the final project records
• Formal acceptance and closure – Person or organization responsible for contract administration provides the seller with formal written notice that the contract has been completed. Normally specified in the contract.
Contract Closeout
Administrative Closure
• It includes collecting project reports, ensuring they reflect final specifications and analysis of project success and effectiveness, and archiving such information for future use
• Each phase of the project should be properly closed to ensure that important and useful information is not lost
Gathering, generating, and disseminating information in order to formalize the acceptance of the product by the sponsor, client, or customer
Process OutputInput
Tools and Techniques
1. Performance measurement documentation
2. Documentation of the product of the project
3. Other project records
“… verifying and documenting project results to formalize acceptance of the product by the sponsor, client or customer.”
1. Project archives2. Formal acceptance3. Lessons learned
1. Performance reporting tools and techniques
2. Project Reports3. Project Presentations
Core Closing Process Administrative Closure
Administrative Closure
Inputs• Performance measurement
documentation• Documentation of the
product of the project• Other project records
Tools & Techniques• Performance-reporting
tools and techniques• Project reports• Project Presentations
Outputs• Project archives• Formal acceptance• Lessons learned
Inputs• Performance-measurement documentation –
All documentation produced to record and analyze project performance, including the planning documents which established the framework for performance measurement
• Documentation of the product of the project – Documents produced to describe the product
• Other project records
Administrative Closure
Outputs• Project archives – Complete set of indexed project
records
• Formal acceptance – Documentation that demonstrates that the client or sponsor has accepted the product of the project
• Lessons learned
Administrative Closure
Tools & TechniquesPerformance-reporting tools and techniques
Sample Closing Activities• Ensuring a record of lessons learned is developed,
documented, and made available for future projects• Verifying acceptance of products or services• Collecting all required project records• Determining if final products meet specifications• Assessing the quality, correctness, and completeness
of all formal project acceptance documents• Give performance appraisals and assist in the
planned transfer of personnel to other projects or positions
• Other?
Initiating Processes
PlanningProcesses
ControllingProcesses Executing
Processes
ClosingProcesses
Commitment toexecuting project
Approach toexecuting project
Monitoring, measuring, andtaking corrective action
Coordinating people and
other resources
Formal productacceptance andend of project
Communication Flow
Operations
Start
Exercise 7-1Process Group Allocation
• Allocate the processes and activities to the correct process group
Questions/Opinions on Processes
• Most important processes?• Least important?• Missing?• Other questions?
Units 3–7 Summary• Identified the role of each process group• Identified the inputs and outputs of core
processes• Listed the major tools and techniques used in
core processes of each process group• Described facilitating processes• Recognized and allocated processes and
activities to their correct process group
UNIT 8:ORGANIZATIONAL
IMPACTS
Unit 8: Organizational Impacts
Upon completion, you will be able to …• Describe how different organizational
approaches can impact the process and effectiveness of project management
HR Requirements
• PM position descriptions• Reward system congruence • Career paths• Competency models• Training and development opportunities• Certification
Functional Organization
Functional OrganizationDiscussion Question
• In your opinion, what advantages and potential disadvantage does this type of organizational structure foster?
Functional OrganizationPotential Advantages
• Clear reporting relationships• Highly specialized expertise• Homogeneous group• Drive for technical excellence
Functional OrganizationPotential Issues
• Project boundaries limited to discipline• Barrier to customer influence and satisfaction • Employee development opportunities limited• Project manager dependent on personal influence• Hierarchical decision and communication
processes• Overwork technical issues versus build to standard• Fosters part-time roles
Weak Matrix
Balanced Matrix
Strong Matrix
Projectized Organization
Composite Organization
Projectized OrganizationDiscussion Question
• Based on your experience, what potential advantages and disadvantage does this type of organizational approach foster?
Project-Based OrganizationPotential Advantages
• Strong project manager role• Full-time administrative staff • Clear accountability • Fosters co-location• Improved focus• Cost and performance tracking• Decision-making• Customer relationships• Common processes
Project-Based Organization Potential Issues
• Lessening of employee’s “profession” identity• Reduced focus on technical competence• Leadership by the nontechnically skilled• Focus on administrative work versus technical • Devaluing of functional managers• Process versus deliverable emphasis
Structure Influence on Projects
Exercise 8-1Organizational Impacts
• If you were given authority for a day and tasked to improve project management in your organization, what changes would you make: To the organization structure and delegation of
responsibilities? To your role (no major promotions, please)?
Summary
Reviewed how organizational approaches can impact the effectiveness of project management
Functional organization Matrix organization Project-based organization
UNIT 9:OVERVIEW OF KNOWLEDGE
AREAS
Unit 9: Overview of Knowledge Areas
Upon completion, you will be able to …• Identify and describe the nine knowledge
areas• Identify your current development needs and
strengths in the processes in each knowledge area
Overview of Knowledge Areas
Cost TimeScope
IntegrationHuman ResourcesCommunications
Risk Procurement
Quality
Project Integration Management
“A subset of project management that includes the processes required to ensure that the various elements of the project are properly coordinated.”
• Project plan development• Project plan execution• Overall change control
Proposal Request
Proposal Phase
Requirements Analysis Phase
General Design Phase
Detailed Design Phase
Code and Debug
Overlapped phases can yield cost and schedule benefits but add to the integration challenge
The Integration ChallengeSoftware Product Development Example
Characteristics of Effective Integration
• Overlapped processes • Effective change control and communication
systems• Reduced development time and cost• Early and ongoing involvement of all stakeholders• Early visibility of results• Early problem identification and resolution• Use all relevant expertise at earliest meaningful
time
Project Integration Management
• Project Plan Development• Project Plan Execution• Overall Change Control
Processes required to properly coordinatethe various elements of the project
Project Scope Management“Includes the processes required to ensure that the project includes all of the work required, and only the work required to complete the project successfully.”
• Initiation• Scope planning• Scope definition• Scope verification• Scope change control
Scope Management
• Initiation• Scope Planning• Scope Definition• Scope Verification• Scope Change
Control
Processes used to identify all the work required to successfully complete the project
Key Scope Concepts• Configuration Management
A mechanism to track budget, schedule variances, and deliverable versions
• Specification A precise definition of a physical item, procedure, service, or
result for the purpose of purchase and/or implementation of an item or service
• Sources of Scope Change Variation in government regulations Failure to include a required feature in the design of the product Customers who change their minds about the desired nature of
the deliverable
Key Scope Concepts (continued)
Work Breakdown Structure• A deliverable-oriented grouping of
process elements that organizes and defines the total scope of the project
• Each descending level represents an increasingly detailed definition of a project component
• Project components may be products or services
Project Time Management • Definition
A subset of project management that includes the processes required to ensure timely completion of the project
• Processes Activity definition Activity sequencing Activity duration estimating Schedule development Schedule control
Time Management
• Activity Definition• Activity Sequencing• Activity Duration
Estimating• Schedule Development• Schedule Control
Processes required to ensure the project is completed on time
Purpose of Scheduling Processes
• Illustrates interdependence of project activities, work packages, and work units
• Monitors and controls timing of project work
• Guides the allocation of resources• Drives personnel availability issues and
activities
Remodel Kitchen WBS
ID Task Name Dur1 1 DESIGN 10d
2 1.1 SELECT DESIGNER 3d
3 1.2 CREATE PLANS 5d
4 1.3 SELECT CONTRACTOR 2d
5 2 PURCHASING 6d
6 2.1 PURCHASE APPLIANCES 6d
7 3 CARPENTERS 15d
8 3.1 TEAR OUT 3d
9 3.2 CHANGE WALLS 4d
10 3.3 INSTALL NEW CABINETS 3d
11 3.4 INSTALL SINK 1d
12 3.5 INSTALL DISHWASHER 2d
13 3.6 INSTALL FLOOR 2d
14 3.7 FINISH AND CLEANUP 1d
15 4 ELECTRICAL 3d
16 4.1 WIRING 2d
17 4.2 INSTALL LIGHTS 1d
18 5 MECHANICAL 2d
19 5.1 INSTALL PIPING 2d
20 6 READY FOR DINNER 1d
-3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Kitchen Remodeling Precedence Relationships
Kitchen RemodelingForward Pass - Early Dates
ID Task Name Dur ES Date EF Date1 DESIGN 10d
2 SELECT DESIGNER 3d
3 CREATE PLANS 5d
4 SELECT CONTRACTOR 2d
5 PURCHASING 6d
6 PURCHASE APPLIANCES 6d
7 CARPENTERS 15d
8 TEAR OUT 3d
9 CHANGE WALLS 4d
10 INSTALL NEW CABINETS 3d
11 INSTALL SINK 1d
12 INSTALL DISHWASHER 2d
13 INSTALL FLOOR 2d
14 FINISH AND CLEANUP 1d
15 ELECTRICAL 3d
16 WIRING 2d
17 INSTALL LIGHTS 1d
18 MECHANICAL 2d
19 INSTALL PIPING 2d
20 READY FOR DINNER 1d
S S M T W T F S S M T W T F S S M T W T F S S M T W T FFeb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99
Kitchen RemodelingBackward Pass - Late Dates
ID Task Name Dur LS Date LF Date1 DESIGN 10d
2 SELECT DESIGNER 3d
3 CREATE PLANS 5d
4 SELECT CONTRACTOR 2d
5 PURCHASING 6d
6 PURCHASE APPLIANCES 6d
7 CARPENTERS 15d
8 TEAR OUT 3d
9 CHANGE WALLS 4d
10 INSTALL NEW CABINETS 3d
11 INSTALL SINK 1d
12 INSTALL DISHWASHER 2d
13 INSTALL FLOOR 2d
14 FINISH AND CLEANUP 1d
15 ELECTRICAL 3d
16 WIRING 2d
17 INSTALL LIGHTS 1d
18 MECHANICAL 2d
19 INSTALL PIPING 2d
20 READY FOR DINNER 1d
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S SFeb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99 Mar
Kitchen RemodelingTotal Float
ID Task Name Dur ES Date EF Date LS Date LF Date T Float1 DESIGN 10d
2 SELECT DESIGNER 3d
3 CREATE PLANS 5d
4 SELECT CONTRACTOR 2d
5 PURCHASING 6d
6 PURCHASE APPLIANCES 6d
7 CARPENTERS 15d
8 TEAR OUT 3d
9 CHANGE WALLS 4d
10 INSTALL NEW CABINETS 3d
11 INSTALL SINK 1d
12 INSTALL DISHWASHER 2d
13 INSTALL FLOOR 2d
14 FINISH AND CLEANUP 1d
15 ELECTRICAL 3d
16 WIRING 2d
17 INSTALL LIGHTS 1d
18 MECHANICAL 2d
19 INSTALL PIPING 2d
20 READY FOR DINNER 1d
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S SFeb 28, '99 Mar 7, '99 Mar 14, '99 Mar 21, '99 Ma
Total Float = Late Finish Date – Early Finish Date
Kitchen RemodelingSummary
ID Task Name Dur ES Date EF date LS Date LF Date T Float1 DESIGN 10d 1 10 1 10 0d
2 SELECT DESIGNER 3d 1 3 1 3 0d
3 CREATE PLANS 5d 4 8 4 8 0d
4 SELECT CONTRACTOR 2d 9 10 9 10 0d
5 PURCHASING 6d 9 14 12 17 3d
6 PURCHASE APPLIANCES 6d 9 14 12 17 3d
7 CARPENTERS 15d 11 25 11 25 0d
8 TEAR OUT 3d 11 13 11 13 0d
9 CHANGE WALLS 4d 14 17 14 17 0d
10 INSTALL NEW CABINETS 3d 18 20 18 20 0d
11 INSTALL SINK 1d 21 21 22 22 1d
12 INSTALL DISHWASHER 2d 21 22 21 22 0d
13 INSTALL FLOOR 2d 23 24 23 24 0d
14 FINISH AND CLEANUP 1d 25 25 25 25 0d
15 ELECTRICAL 3d 18 20 20 22 2d
16 WIRING 2d 18 19 20 21 2d
17 INSTALL LIGHTS 1d 20 20 22 22 2d
18 MECHANICAL 2d 18 19 19 20 1d
19 INSTALL PIPING 2d 18 19 19 20 1d
20 READY FOR DINNER 1d 26 26 26 26 0d
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Float
Project Cost Management
“… the processes required to ensure that the project is completed within the approved budget.”
• Resource planning• Cost estimating• Cost budgeting• Cost control
Cost Management
• Resource Planning
• Cost Estimating• Cost Budgeting• Cost Control
Processes required to ensure the project is completed within the approved budget
One Performance Measurement
• Earned Value Budgeted Cost of Work Performed (BCWP)
• Related Terms Budgeted Cost of Work Scheduled (BCWS) Actual Cost of Work Performed (ACWP) Budget at Completion (BAC)
Cumulative Status Display
Variances
• Schedule Variance (SV) = BCWP – BCWS
• Cost Variance (CV) = BCWP – ACWP• Time Variance (TV) = STWP – ATWP
What Is the SV?
What Is the CV?
What Is the Time Variance?
Project Quality Management
“A subset of project management that includes the process required to ensure that the project will satisfy the needs for which it was undertaken.”
• Quality planning• Quality assurance• Quality control
Quality Management
• Quality Planning• Quality
Assurance• Quality Control
Processes required to ensure the project will satisfy customer requirements
Project HR Management
“… the processes required to make the most effective use of the people involved with the project.”
• Organizational planning• Staff acquisition• Team development
Human Resource Management
• Organizational Planning• Staff Acquisition• Team Development
Processes required to make effective use of the people involved with the project
Responsibility ChartA B C D E F
S R A P P
S A P P
S R A I
R S A P
S P I A
...
P
P
P
PERSO NPHASE
Requirem ents
Functional
Design
Developm ent
Testing
P = Participant A = Accountable R = Review required I = Input required S = S ign-off required
Responsibility Chart Characteristics
• Work Package Level• Components
WBS activity Responsible organization Responsible position title or person Type of responsibility
Approving authority Prime implementation accountability Support Notification
Exercise 9-1Responsibility Allocation
• Using the handout in your manual, complete the responsibility matrix for your project
• Discuss with a classmate the effectiveness of the allocation of responsibility and authority depicted
“… the processes concerned with identifying, analyzing, and responding to project risk.”
• Risk identification• Risk quantification• Risk response development• Risk response control
Project Risk Management
Risk Management
• Risk Management Planning• Risk Identification• Qualitative Risk Analysis• Quantitative Risk Analysis• Risk Response Planning• Risk Response Monitoring and
Control
Processes required to effectively identify, analyze,and respond to project risks
Risk Decision Tree
Exercise 9-2Risk Assessment
• Construct a risk assessment tree for a critical decision on your project
• If your original project selection does not lend itself to this exercise, feel free to substitute another project
Project Communications Management
“… the timely and appropriate generation, collection, dissemination, storage, and ultimate disposition of project information.”
• Communications planning• Information distribution• Performance reporting• Administrative closure
Communications Management
• Communications Planning
• Information Distribution• Performance Reporting• Administrative Closure
Processes required to ensure timely and appropriatedevelopment, collection dissemination, storage, and
ultimate disposition of project information
Project Procurement Management
“… includes the processes required to acquire goods and services from outside the performing organization.”
• Procurement planning• Solicitation planning• Solicitation• Source selection• Contract administration• Contract closeout
Procurement Management
• Procurement Planning• Solicitation Planning• Solicitation• Source Selection• Contract
Administration• Contract Close-Out
Processes required to acquire goods and servicesfrom outside the organization
Summary
• Identified and described the nine knowledge areas and the core processes in each
• Allocated typical processes and activities to their appropriate knowledge area
UNIT 10:PROJECT
MANAGER ROLES
Unit 10: Role of the Project Manager
Upon completion, you will be able to …Identify, in your environment, the most
critical project manager:• Roles• Responsibilities• Interpersonal skill requirements• Your knowledge area gaps and strengths
Project Manager Rolesn Decision-maker n Manager n Coach n Sales personn Communication channel n PM expertn Encourager n Facilitatorn Power broker n Behavior modeln Disciplinarian n Other?
Project Manager Responsibilities
• Project plan implementation• Achievement of objectives• Project integration• Communications • Stakeholder relations• Change management system• Priority establishment and maintenance
More Responsibilities• Staff acquisition, retention, and motivation • Selection and use of PM tools and techniques• Compliance with regulations, state and federal
laws, and organization policies and procedures• Resolving team conflicts• Negotiating win/win solutions• Deliver the project on time and within budget• Other?
Skill and Knowledge Requirements
This figure is a conceptual view of these relationships. The overlaps shown are not proportional.
ApplicationArea Knowledge
and Practice
GeneralM anagem entKnowledge
and Practice
The ProjectManagement
Body of Knowledge
Generally A cceptedProject Managem ent
Knowledge and Practice
Competency can be defined as …
• A qualification equal to a position requirement, or
• Capacities one must possess to perform satisfactorily in a position.
Success depends on your …
• Knowledge • Behaviors • Attitude• Organizational environment• Project environment • Fit • Self-knowledge and ability to adjust
One Emerging Operating Style
“We will need scroungers, tinkerers, masters of the extemporaneous,
and those who can make it happen, regardless of the rules,
the odds, or the inevitable second guess.”*
* Project Management Handbook, by David I. Cleland and William R. King
Exercise 10-1Project Manager Interpersonal
Skills
• Use the handout to assess the interpersonal skills required to manage a project successfully in your organization; then assess your skills, and identify skill gaps and strengths
Recognizing a Successful Project Manager
• Meets cost, schedule, technical, and mission objectives
Plus• Attains high levels of satisfaction and
perception of project success from: Client Sponsor Users Team
Example of an Organization Competence Assessment
Tool• CMM™ background• Levels of Software Engineering Maturity
Model Basic Repeatable Defined Managed Optimized
Why Reading Your Environment Is Important
Assessments reveal:• Fit between you, the organization, and the project• Your development needs and strengths • PM strategies most likely to be successful• PM strategies to be avoided• Guide for tools and techniques selection• Guide your performance expectations of self and others
And They:• Influence your own management style
Exercise 10-2 PM Knowledge Needs Assessment
• Complete the exercise in your manual, and then discuss the implications with a classmate
• Identify knowledge gaps, strengths, and possible developmental activities including: Growth assignments Seminars Self-study Degree programs Other?
PM Knowledge Needs Assessment Discussion Question
What did you learn from this exercise about:
• Yourself?• Your project?• Your organization?• Your future?
A Framework for Project Management
Seminar Summary1. Introduction and Key Concepts2. Project Life Cycle Models3. Initiating Projects4. Planning Projects5. Executing Projects6. Controlling Projects7. Closing Projects8. Organizational Impacts9. Overview of Knowledge Areas10. Role of the Project Manager
End
• Please complete the seminar evaluation form before leaving.
• Thank you for your participation!
PROFESSIONAL RESPONSIBILITY
Outline of Lecture• Responsibilities to the Profession• Compliance with Rules
& Policies• Candidate/Certificant Professional Practice• Advancement of the Profession• Responsibilities to Customers
& the Public• Qualifications, Experience & Performance of
Professional Services• Conflict of Interest Situations & Other Prohibited
Professional Conduct
Responsibilities to the Profession
• Compliance with all Organization Rules and Policies
• Candidate/Certificant Professional Practice
• Advancement of the Profession
Compliance with Rules & Policies
• Provide accurate & truthful information directly or indirectly related to all aspects of the PMI Certification Program
• Upon a reasonable & clear factual basis, report possible violations of the PMP Code of Professional Conduct
• Cooperate with PMI concerning ethics violations and the collection of related information
• Disclose to clients, customers, owners or contractors, significant circumstances that could be construed as a conflict of interest or an appearance of impropriety
Candidate/Certificant Professional Practice
• Provide accurate, truthful advertising and representation concerning qualifications, experience and performance of services
• Comply with laws, regulations and ethical standards governing professional practice in the state/province and/or country when providing project management services
Responsibilities to Customers & the Public
• Qualifications, Experience & Professional Services
• Conflict of Interest Situations & Other Prohibited Professional conduct
Qualifications, Experience & Performance of Professional Services
• Provide accurate and truthful representations to the public in advertising, public statements and in the preparation of estimates of costs, services, and expected results
• Maintain & satisfy the scope and objectives of professional services, unless otherwise directed by the customer
• Maintain and respect the confidentiality of sensitive information obtained in the course of professional activities or otherwise where a clear obligation exists
Conflict of Interest Situations & Other Prohibited Professional Conduct
• Ensure that a conflict of interest does not compromise legitimate interest of a client or customer, or influence/interfere with professional judgments
• Refrain from offering or accepting inappropriate payments, gifts or other forms of compensation for personal gain, unless in conformity with applicable laws or customs of the country where project management services are provided