MBB3173 Project Management Developing the project schedule (PART 1) Topic To Be Covered Scheduling procedure Timing estimates Manual timing calculations Float: Optional Start and Finish Times Tabulating the schedule Setting up the calendar schedule Constructing the bar chart time schedule MBB3173 Project Management

Project Management - · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Embed Size (px)

Citation preview

Page 1: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

MBB3173

Project ManagementDeveloping the project schedule (PART 1)

Topic To Be Covered• Scheduling procedure• Timing estimates• Manual timing calculations• Float: Optional Start and Finish Times• Tabulating the schedule• Setting up the calendar schedule• Constructing the bar chart time schedule

MBB3173 Project Management

Page 2: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

PERT AND CPM NETWORKS

MEM 612 Project Management

Page 3: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

History

• Late 1950s• Program Evaluation and Review Technique (PERT)

• U.S. Navy, Booz-Allen Hamilton, and Lockeheed Aircraft

• Probabilistic activity durations

• Critical Path Method (CPM)• Dupont De Nemours Inc.

• Deterministic activity durations

Page 4: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

The Language of PERT/CPM

• Activity• task or set of tasks

• use resources

• Event• state resulting from completion of one or more activities

• consume no resources or time

• predecessor activities must be completed

Page 5: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

The Language of PERT/CPM continued

• Milestones• events that mark significant progress

• Network• diagram of nodes and arcs

• used to illustrate technological relationships

• Path• series of connected activities between two events

Page 6: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

The Language of PERT/CPM concluded

• Critical Path• set of activities on a path that if delayed will delay

completion of project

• Critical Time• time required to complete all activities on the critical

path

Page 7: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Building the Network

• AOA Network

• AON Network

Page 8: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Table 5-1 A Sample Set of Project Activities and Precedences

Task Predecessor

a --

b --

c a

d b

e b

f c, d

g e

Page 9: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-1 Stage 1 of a Sample AON Network

Task Predecessor

a --

b --

c a

d b

e b

f c, d

g e

Page 10: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-2 Stage 2 of a Sample AON Network

Task Predecessor

a --

b --

c a

d b

e b

f c, d

g e

Page 11: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-3 A Completed Sample AON Network

Task Predecessor

a --

b --

c a

d b

e b

f c, d

g e

Page 12: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-4 Stage 1 of a Sample AOA Network

Task Predecessor

a --

b --

c a

d b

e b

f c, d

g e

Page 13: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-5 Stage 2 of a Sample AOA Network

Task Predecessor

a --

b --

c a

d b

e b

f c, d

g e

Page 14: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-6a A Completed Sample AOA Network

Task Predecessor

a --

b --

c a

d b

e b

f c, d

g e

Page 15: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-6b A Completed Sample AOA Network Showing the Use of a Dummy Task

Page 16: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Table 5-2 A Sample Problem for Finding the Critical Path and Critical Time

Activity Predecessor Duration

a -- 5 days

b -- 4

c a 3

d a 4

e a 6

f b, c 4

g d 5

h d, e 6

i f 6

j g, h 4

Page 17: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-7 Stage 1 of a Sample Network

Activity Predecessor Duration

a -- 5 days

b -- 4

c a 3

d a 4

e a 6

f b, c 4

g d 5

h d, e 6

i f 6

j g, h 4

Page 18: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-8 A Complete Network

Activity Predecessor Duration

a -- 5 days

b -- 4

c a 3

d a 4

e a 6

f b, c 4

g d 5

h d, e 6

i f 6

j g, h 4

Page 19: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-9 Information Contents in an AON Node

Page 20: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-10 The Critical Path and Time for Sample Project

Activity Predecessor Duration

a -- 5 days

b -- 4

c a 3

d a 4

e a 6

f b, c 4

g d 5

h d, e 6

i f 6

j g, h 4

Page 21: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Calculating Activity Slack

• Slack or Float

LST - EST = LFT - EFT = Slack

Page 22: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-11 An MSP Version of PERT/CPM Network

Activity Predecessor Duration

a -- 5 days

b -- 4

c a 3

d a 4

e a 6

f b, c 4

g d 5

h d, e 6

i f 6

j g, h 4

Page 23: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-12 A Modified Version of MSP Network

Activity Predecessor Duration

a -- 5 days

b -- 4

c a 3

d a 4

e a 6

f b, c 4

g d 5

h d, e 6

i f 6

j g, h 4

Page 24: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

PROJECT UNCERTAINTY AND RISK MANAGEMENT

MEM 612 Project Management

Page 25: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Calculating Probabilistic Activity Times

• Three Time Estimates• pessimistic (a)

• most likely (m)

• optimistic (b)

Page 26: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-13 The Statistical Distribution of all Possible Times for an Activity

• Three Time Estimates• pessimistic (a)

• most likely (m)

• optimistic (b)

Page 27: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Activity Expected Time and Variance

2

2

E

6

)(Var

6

)(

6

)4(T

ab

ab

bma

• Three Time Estimates• pessimistic (a)

• most likely (m)

• optimistic (b)

Page 28: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

95 Percent Level

• Task will be a or lower 5 percent of the time

• Task will be b or greater 5 percent of the time

3.3

)( ab

• Three Time Estimates• pessimistic (a)

• most likely (m)

• optimistic (b)

Page 29: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

90 Percent Level

• Task will be a or lower 10 percent of the time

• Task will be b or greater 10 percent of the time

6.2

)( ab

• Three Time Estimates• pessimistic (a)

• most likely (m)

• optimistic (b)

Page 30: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

95 Percent Level (Alternative Interpretation)• Task will be between a and b 95 percent of the time

92.3

)( ab

• Three Time Estimates• pessimistic (a)

• most likely (m)

• optimistic (b)

Page 31: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

90 Percent Level (Alternative Interpretation)• Task will be between a and b 90 percent of the time

29.3

)( ab

• Three Time Estimates• pessimistic (a)

• most likely (m)

• optimistic (b)

Page 32: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-14 An AON Network

Page 33: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-15 An MSP Version of a Sample Problem Network

Page 34: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-16 A Pert/CPM Network for the Day Care Project

Page 35: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-17 An MSP Calendar for the Day Care Project, 4/16/00 to 5/27/00

Page 36: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

The Probability of Completing the Project on Time

2

)(

DZ

=NORMDIST(D,,,TRUE)

Page 37: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h

Page 38: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Selecting Risk and Finding D

2

ZD

NORMINV(probability,,,TRUE)

Page 39: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

SIMULATION

MEM 612 Project Management

Page 40: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Traditional Statistics Versus Simulation• Similarities

• must enumerate alternate paths

• Differences• simulation does not require assumption of path

independence

Page 41: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

THE GANNT CHART

MEM 612 Project Management

Page 42: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-23 A Gantt Chart of a Sample Project

Page 43: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT

Page 44: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements

Page 45: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-26 A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline

Page 46: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

EXTENSIONS TO PERT/CPM

MEM 612 Project Management

Page 47: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Precedence Diagramming

• Finish-to-start linkage

• Start-to-start linkage

• Finish-to-finish linkage

• Start-to-finish linkage

Page 48: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Figure 5-27 Precedence Diagramming Conventions

Page 49: Project Management -  · PDF file•Task will be between a and b 95 percent of the time ... •Similarities ... PERT/CPM MEM 612 Project Management

Other Methods

• Graphical Evaluation and Review Technique (GERT)• combines flowgraphs, probabilistic networks, and

decision trees

• allows loops back to earlier events and probabilistic branching