    1 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    A Report

    On

    Project Management of

    E-Commerce Website

    Submitted to Prepared By

    SEMCOM College Jay Ajwani

    Brijesh Agravat

    Nirav Vaghela

    Rahul Dongre

    Piyush Bhimani

    Urvesh Patel

  • 8/13/2019 Project Management Process report for Website Developement

    2/9

    2 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    Introduction

    Today the life is getting fast and purchasing power of consumer has

    increased. In service sector industry quality of service has better impart rather than

    cost factor. Certain sector still is not organized and we therefore intend to create a

    organized service sector in house hold maintenance industry. With use of Web we

    can attract customer and easy access to information and serve also.

    Statement of Work

    The Main Backbone of the Business is Website. The important factor

    considered for the success of business depends on how effectively we execute the

    web development phase and to see that the phase is completed in timely manner

    and satisfies the needs and goals of business.

    Callkarigar.com is launching following services Electrician Plumber Carpenter Pest Control Hardware Engineer R.O water purifier services. Inverter services.

  • 8/13/2019 Project Management Process report for Website Developement

    3/9

    3 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    For accomplishment of primary task of completion of website we have

    divided the project in 10 phases

    Stage 1 Pre-projectStage 2 Proposal

    Stage 3 Agreement

    Stage 4 Concept

    Stage 5 Development

    Stage 6 Content

    Stage 7 Coding and Programming (Build)

    Stage 8 Testing

    Stage 9 Go Livestage 10 Maintenance

    Scope of Project.

    At present all these facilities are not under a single roof and totally

    unorganized. With Delay and irregularity customers are facing more problems.

    This is our main USP which can differentiate us from others.

    By the Use of Website Customer can easily access the information and book the

    service. This website can be used as effective tool for marketing and as the logic ofthe company is get organized work this website can add additional advantage to it.

    Moreover Paperless operations and feedback are also possible from customers.

    Strategic Plan

    As mentioned above we have planned the project of web development in 10

    stages and prior to it proper paperwork with necessary inputs from customer is

    essential.

    Second Strategy is to review at every stage of development and matchingcompletion of work with intended goals of the website.

    Certain phases after initial finalization of work will continue in parallel manner in

    order to avoid time constraint and allot reserve time in case of any problem.

  • 8/13/2019 Project Management Process report for Website Developement

    4/9

    4 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    Project charter

    Person Involved Role

    Jay Ajwani PM

    Brijesh Agravat Client Relations and Inputs

    Nirav Vaghela Content Designer

    Rahul Dongre Programmer

    Samir Patel Tester, Programmer

    Time Schedule

    Activities Deadline

    Primary Information 1stOctober to 15thOctober

    Gathering Necessary Information andFinalizing Concept

    16thOctober to 25thOctober

    Finalizing the Inputs of idea from

    customer

    26thOctober to 31

    StOctober

    Finalizing Web Content with allformalities including domainregistration and hosting

    1st

    November to 15th

    November

    Checklist and review of collectedinformation

    26thNovember to 28thNovember

    Coding the Website 29thNovember to 5 December

    Website Testing and hosting 10 December

    Website Launch 20th December

  • 8/13/2019 Project Management Process report for Website Developement

    5/9

    5 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    Enterprise Environment Factors

    Internal factors

    1. Coordination among team members.2. Completion of work in timely manner3. Acquired Skills4. Difference of Opinion5. Conflicts management

    Organizational Process Assets

    Past Website creation Infrastructure Good Coordination among team members. All belong to same age groups.

    Past website creation

    We already have experience of building a website and this experience is

    useful in this project. However the Criteria and services of this project are different

    but we as a team member have knowledge of all technical aspects which is our

    main strength.

    Infrastructure

    With a better infrastructure and technical eminities we are right on the mark for the

    resources required for the project and allocation of the resources and work is

    assigned and distributed and with clean understanding and communication. Still for

    the safety purpose we follow the method of regular assessment for work done that

    keeps us on the track and avoid time delays. All the computers are updated with

    latest software and hardware required for the project. Our programmers are welltrained regarding the technical aspects of the website.

  • 8/13/2019 Project Management Process report for Website Developement

    6/9

    6 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    Good Coordination among team members.

    We have already worked on such project so we are already aware the technicaldifficulties and problems that can occur and this has helped us to plan the project

    accordingly and time distribution of work done is also done in the similar fashion.

    Similar Age groups of Team members

    We as a team belong to same age groups which increases our understanding and

    we are all aware of responsibilities. Moreover we have equality in work

    distribution so there very less chances of clashes. However under any

    circumstances we always follow the rule of discussion and resolve regarding any

    problems or difference of opinions.

  • 8/13/2019 Project Management Process report for Website Developement

    7/9

    7 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    Work Breakdown Structure of Website

    Phase 1

    Pre-project

    Preparation of brief site

    requirements.

    *Objectives

    *Target Audience

    *Look and Feel

    *Portable Devices

    *Social Media

    *Time Scale

    *Requirements

    *Hosting Requirements

    *Content Management

    Phase 2

    Proposal

    Response to brief

    Technical Specs

    Domain Name

    Sitemap

    Outline Budget

    Hosting Options

    Draft Schedule

    Recommendations

    Phase 3

    Agreement

    From client Feedback

    Finalize

    Recommendations

    Budget

    Sitemap

    Schedule

    Phase 4

    Concept

    From client Feedback

    Design concept

    User Experience

    Site Navigation

    Content Display

    Phase 5

    Development

    Client supplies

    Template Framework

    Modules and

    component.

    Social Media Integration

    Finalize Design approach

    Phase 6

    Content

    Client supplies

    Create Schedule of work

    Regular assessment of

    client.

    Signoff the content

    selected and approved

  • 8/13/2019 Project Management Process report for Website Developement

    8/9

    8 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    Phase 7Build

    Technical Task

    Creating Style sheets

    Section wise

    Programming.

    Dry Run and Initial

    Testing of every code

    with Approval of P.M

    Phase 8

    Testing

    Technical Task

    Browser Compatibility

    Portable Devices

    Resolution

    Testing Functionality

    Hosting Review

    Phase 9

    Go Live

    Technical Task

    Internal Checkup

    E-marketing

    Database Checks

    Phase 10

    Maintenance

    Technical Task

    Site MaintenanceContent Updating

    Tracking Statistics

    users Feedback

    Performance Reviews

  • 8/13/2019 Project Management Process report for Website Developement

    9/9

    9 Project Report on Project Management plan of E-Commerce Website :

    www.Callkarigar.com

    Risk Management Planer

    Risk Plan

    Risk about the Failure of concept Customer Survey and Market ResearchStrategy

    Technical Difficulties Proper check of Software and hardware

    infrastructure.

    Programming Failures Proper Flow charts and best optimizedcode selection by dry run methods

    Availability of Domain Name Alternative Choice prior to finalizationof work

    Content Changes Allot proper time schedule and generate

    dynamic code that can handle suchfrequent changes easily

    Effectiveness of website or Less hits Suggestion for good SEO and Socialmedia marketing methods.