Project Management November 22, 2013

Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Embed Size (px)

Citation preview

Page 1: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Project Management

November 22, 2013

Page 2: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Engineering Economics

Macroeconomics

OperationsResearch

Linear programmingPERT/CPM

Queueing Theory

Accounting

Page 3: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Project Management Tools:

Work breakdown structure: what there is to do

Gantt Chart: times to do things

Critical Path Method: dependencies; time/cost trade-offs

Page 4: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Work breakdown structure: what there is to do

E.g., “Prepare beans on toast”

Page 5: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Prepare Beans on Toast

Prepare Beans Prepare Toast Combine

Open Can

Place Beans in saucepan

Place Saucepan on stove

Light stove

Stir beans till warm

Slice bread

Place bread in toaster

Depress toaster button

Remove toast from toaster

Butter the toast

Page 6: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

WBS activities should be mutually exclusive andcollectively exhaustive

The WBS allows us to calculate total project costand personnel requirements

It can include time estimates for each activity, butit doesn’t, by itself, allow us to calculate projectduration.

Page 7: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Task Start

End 9:00

9:02

9:04

9:06

9:08

9:10 9:12

1 Open can 9:00 9:01

2 Fill saucepan

9:01 9:03

3 Saucepan on stove

9:03 9:04

4 Light stove

9:04 9:05

5 Stir 9:05 9:10

6 Cut bread

9:00 9:01

7 Bread in toaster

9:01 9:06

8 Butter toast

9:06 9:07

9 Beans onto toast

9:10 9:11

A Gantt Chart for Beans on Toast

Page 8: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Task Start

End 9:00

9:02

9:04

9:06

9:08

9:10 9:12

1 Open can 9:00 9:01

2 Fill saucepan

9:01 9:03

3 Saucepan on stove

9:03 9:04

4 Light stove

9:04 9:05

5 Stir 9:05 9:10

6 Cut bread

9:00 9:01

7 Bread in toaster

9:01 9:06

8 Butter toast

9:06 9:07

9 Beans onto toast

9:10 9:11

Dependencies shown, but not self-evident

Page 9: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

CPM: Two conventions

Start

Can Open

Bread cut

Beans on Toast Ready

Beans Ready

Toast Ready

Open Can

Slice bread

Toast Bread

Heat Beans

Beans onto toast

Dummy

AOA

AON Start

Open Can

Slice bread

Heat Beans

Toast bread

Beans onto toast

End

Page 10: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T:ES: EF:LS: LF:

Slice breadT:ES: EF:LS: LF:

Heat BeansT:ES: EF:LS: LF:

Toast breadT:ES: EF:LS: LF:

Beans onto toastT:ES: EF:LS: LF:

End

Add notation: “T” = time, “ES” = Earliest Start, “EF” = Earliest Finish“LS” = Latest Start, “LF” = Latest Finish

Page 11: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T: 1:00ES: EF:LS: LF:

Slice breadT:1:00ES: EF:LS: LF:

Heat BeansT: 5:00ES: EF:LS: LF:

Toast breadT:3:00ES: EF:LS: LF:

Beans onto toastT: 1:00ES: EF:LS: LF:

End

Fill in the times.

Page 12: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T: 1:00ES:0 EF:1LS: LF:

Slice breadT:1:00ES: 0 EF:1LS: LF:

Heat BeansT: 5:00ES: EF:LS: LF:

Toast breadT:3:00ES: EF:LS: LF:

Beans onto toastT: 1:00ES: EF:LS: LF:

End

ES for the first activity is zero, EF is ES + T

Page 13: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T: 1:00ES:0 EF:1LS: LF:

Slice breadT:1:00ES: 0 EF:1LS: LF:

Heat BeansT: 5:00ES:1 EF:6LS: LF:

Toast breadT:3:00ES:1 EF:4LS: LF:

Beans onto toastT: 1:00ES:6 EF:7LS: LF:

End

For subsequent activities, ES is max(EF of all upstream activities), EF is ES + T

Page 14: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T: 1:00ES:0 EF:1LS: LF:

Slice breadT:1:00ES: 0 EF:1LS: LF:

Heat BeansT: 5:00ES:1 EF:6LS: LF:

Toast breadT:3:00ES:1 EF:4LS: LF:

Beans onto toastT: 1:00ES:6 EF:7LS: LF:

End

For subsequent activities, ES is max(EF of all upstream activities), EF is ES + T

Page 15: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T: 1:00ES:0 EF:1LS: LF:

Slice breadT:1:00ES: 0 EF:1LS: LF:

Heat BeansT: 5:00ES:1 EF:6LS: LF:

Toast breadT:3:00ES:1 EF:4LS: LF:

Beans onto toastT: 1:00ES:6 EF:7LS: LF:7

End

The earliest finish of the final activity is also the latest acceptable finish for thefinal activity, assuming we don’t want the project completion to be delayed.

Page 16: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T: 1:00ES:0 EF:1LS:0 LF:1

Slice breadT:1:00ES: 0 EF:1LS: 2 LF: 3

Heat BeansT: 5:00ES:1 EF:6LS:1 LF:6

Toast breadT:3:00ES:1 EF:4LS:3 LF: 6

Beans onto toastT: 1:00ES:6 EF:7LS:6 LF:7

End

Then we do a second, backwards, pass through the network, where for each node,LF is min(LS of all downstream nodes) and LS is LF - T

Page 17: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T: 1:00ES:0 EF:1LS:0 LF:1

Slice breadT:1:00ES: 0 EF:1LS: 2 LF: 3

Heat BeansT: 5:00ES:1 EF:6LS:1 LF:6

Toast breadT:3:00ES:1 EF:4LS:3 LF: 6

Beans onto toastT: 1:00ES:6 EF:7LS:6 LF:7

End

The difference between EF and LF for a node is the slack for that activity

Slack = 2 Slack = 2

Page 18: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Finding the critical path

Start

Open Can T: 1:00ES:0 EF:1LS:0 LF:1

Slice breadT:1:00ES: 0 EF:1LS: 2 LF: 3

Heat BeansT: 5:00ES:1 EF:6LS:1 LF:6

Toast breadT:3:00ES:1 EF:4LS:3 LF: 6

Beans onto toastT: 1:00ES:6 EF:7LS:6 LF:7

End

Activities with no slack are on the critical path

Slack = 2 Slack = 2

Page 19: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Crashing a Project

Crashing an activity means spending more money in order to get it done faster

(Important note: This doesn’t always work – seeBrooks, “The Mythical Man-Month”)

It’s obviously a waste of money to crash any activity that has slack.

Page 20: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Crashing a Project

1. Assume linearity:

Crash cost – normal cost

Crash cost/ unit time =

Normal Time –Crash Time

2. Find minimum crash cost/unit time on the critical path

3. Reduce time as much as possible

4. Repeat

Page 21: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

You own a start-up software company. You and your colleagues are planning the launch of a new computer.

“Before we can start designing the Mark II, we need to complete three steps: there’s the market research, which will take about six weeks, there’s about five weeks of technical research needed to identify the best chip set, and meanwhile we’re going to have to raise capital to pay for all of this – we should allow four weeks for that. The good news is that all those activities can go on independently. When they’re all complete, we’ve reached Milestone 1 and we can start working on the hardware and software.” “That’s a dependency – we can’t write the software till we’ve got a machine to run it on.” “There’s a way round that: we can emulate the Mark II on a Mark I machine. It won’t run as fast, but we can use it for debugging. So we can develop the pre-prototype hardware, which should take about twelve weeks, and write software on an emulated machine at the same time – we should be able to get that done in ten weeks. Once both those things are done, we’re at Milestone 2.”

“Once the pre-prototype hardware is done, we can adapt the software to run on it. That will take another twelve weeks. Meanwhile our hardware engineers can build the prototype Mark II. That’s going to be the longest step in the whole process – we’ll allow twenty-four weeks for that. And once those two steps are complete, we’re at Milestone 3.”

Page 22: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

“Once we’re past Milestone 3, there’s a lot of things we can get started on. We can start designing the production version of the Mark II, and at the same time design the production tooling. Both those steps should take about sixteen weeks. We’ll also be in a position to release guidelines to applications developers, inside and outside the company. We can expect the first applications to be ready within twenty weeks, ideally just as the Mark II is put on the market.” “Milestone 3 is also the point at which we can start adapting the software to the prototype machine. Let’s allow eighteen weeks for that. ” “So when the production tooling and the production version of the Mark II are complete, and assuming the software for the prototype machine is ready by that time, we’ve at Milestone 4. Then all we’ve got to do is design the hardware packaging – call that a six-week job – adapt the software to the production version of the machine – allow twelve weeks for that – once the software is complete, we package that too, which shouldn’t take more than four weeks – and, as long as the applications developers are on schedule, we can put the machine on the market.”

Represent the project as a Gantt chart, and calculate the earliest possible finish date.

Page 23: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting
Page 24: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

2.Represent the project using both an AOA and an AON network diagram. Note that it may be useful to use `dummy arcs’ to represent the dependencies between some activities  3.Using the AON diagram developed in 2, perform a critical path analysis and complete a table showing the slack for each activity.

Page 25: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

First, the Activity-on-Arc representation. The arcs are labelled according to the table below. We use dummy arcs, indicated by grey lines, to indicate that one activity cannot begin before others are completed. The milestones correspond to the nodes labelled `M’.

Page 26: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting
Page 27: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

We next construct the AON network. This time we’ll use square nodes, and provide them with labels ready for a CPM analysis.

Page 28: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

We can now begin the CPM analysis. We start going through the diagram, filling in the earliest start times. We define the earliest we can start as time 0, so this goes into the first row of boxes. Then we add the duration times to get the earliest each activity can finish. When we get to the second row of boxes, we apply the rule that the earliest an activity can start is the latest that any of the activities it depends upon can finish. All of the boxes in the second row depend on all of the boxes in the first row, so the earliest any of them can start is 6 weeks into the project.

Page 29: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

We carry on in this way till we get to the bottom of the diagram, where we find that the earliest we can finish the project is in 76 weeks, the same answer as we got from the Gantt diagram. Then we start working our way back up the diagram, this time using the rule that the latest any activity can finish is the latest that any of the activities that depend on it can start. This gives us the `LF’ entry, and the `LS’ entry is the value of the LF entry minus the activity duration. When we’re done, the diagram should look like this, where we’ve marked the critical activities in yellow and the critical path in red:

Page 30: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting
Page 31: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

4.You discover that a rival company is planning to put out a product that will compete with the Mark II. Every week that you can shorten your time to market is worth $1 000 000 in increased sales. You know that each of the relevant activities can be shortened by a certain percentage, with per-week costs as follows:

What is your most profitable strategy?

Page 32: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Production Tooling: 16 weeksES: 42 EF: 58LS: 54 LF: 70

EndEF: 76LF: 76

Package Software: 4 weeksES: 72 EF: 76LS: 72 LF: 76

Production Software: 12 weeksES:60 EF:72LS: 60 LF:72

Package Hardware: 6 weeksES: 58 EF:64LS: 70 LF: 76

Production Hardware: 16 weeksES:42 EF: 58LS: 44 LF: 60

Step 1: Crash Software Packaging 2 weeks

Prototype Software: 18 weeksES:42 EF:60LS: 42 LF: 30

Develop apps: 20 weeksES:42 EF:62LS: 56 LF: 76

Page 33: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Production Tooling: 16 weeksES: 42 EF: 58LS: 54 LF: 70

EndEF: 74LF: 74

Package Software: 2 weeksES: 72 EF: 74LS: 72 LF: 74

Production Software: 12 weeksES:60 EF:72LS: 60 LF:72

Package Hardware: 6 weeksES: 58 EF:64LS: 68 LF: 74

Production Hardware: 16 weeksES:42 EF: 58LS: 44 LF: 60

Prototype Software: 18 weeksES:42 EF:60LS: 42 LF: 60

Develop apps: 20 weeksES:42 EF: 62LS: 54 LF: 74

Critical Path has not changed, but it’s shorter

Page 34: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Market Research: 6 weeksES: 0 EF:6LS: 0 LF: 6

Start

Technical Research: 5 weeksES:0 EF:5LS: 1 LF: 6

Raise Capital: 4 weeksES:0 EF:4LS: 2 LF: 6

Pre-prototype Hardware: 12 weeksES:6 EF:18LS: 6 LF: 18

Software on emulated machine: 10 weeksES:6 EF:16LS: 20 LF: 30

Step 2: crash market research 1 week

Page 35: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting

Market Research: 6 weeksES: 0 EF:5LS: 0 LF: 5

Start

Technical Research: 5 weeksES:0 EF:5LS: 0 LF: 5

Raise Capital: 4 weeksES:0 EF:4LS: 1 LF: 5

Pre-prototype Hardware: 12 weeksES:5 EF:17LS: 5 LF: 17

Software on emulated machine: 10 weeksES:5 EF:16LS: 19 LF: 29

Critical Path has changed

Page 36: Project Management November 22, 2013. Engineering Economics Macroeconomics Operations Research Linear programming PERT/CPM Queueing Theory Accounting